Engagement Background
 Customer: A leading bank in the Caribbean
 The Bank is using FLEXCUBE Core Banking System with IBM P6, DB Oracle 10g for their Banking Business
Operations.
 The Bank planned to migrate the Hardware, DB and the CBS software from the existing one to the newer
supportive version with the “AS IS” functionality.
 IBM P6 to IBM P8
 Oracle DB 10g to 12g
 CBS FCv7.1 to FCv12.3
 There were 14 interface applications along with CBS that needed consideration during the Migration.
 The Bank team needed the Test Process and Test suite build & Execution support for the CBS and
interfaces.
 The Bank wished to review the Test suite and participate in the Test execution under the guidance of the
Oaksys SMEs for User Acceptance Testing of FLEXCUBE CBS and interfaces.
 Timeline: Aug 2019 to May 2020.
 Engagement Type: Off-Shore delivery.
 Status: Completed.
Copyright © 2020 Oak Systems Private Limited. All Rights Reserved
2
Test Team & Size
Bank CORE
Team - 6
Bank
Extended
Team - 4
Test Process Manager
Oaksys
Test Manager
Bank Team
Test Lead
Oaksys - 6
SME’s
Impln Team - 4 SME’s
Bank Team - 4
Oaksys Project
Manager for the
Project
Copyright © 2020 Oak Systems Private Limited. All Rights Reserved
3
Test Plan Support – Areas & Activities
Services extended to the Customer for the implementation of the FLEXCUBE UBS
(Universal Banking System) core banking application upgrade that will cover the
following aspects of the Project:
 Test Planning including documentation
 Test Preparation
 Remote support to the Client’s team for test execution
Activities involved in the above process are:
 Preparation of Test Plan documents
 Writing of test scenarios/cases for the above mentioned modules
 Writing of test scenarios for the above mentioned interfaces/migration
 Remote Test Execution support to the Client during test execution
 Defect logging and tracking during test preparation
 Review and support of defects during the Client’s Team test execution
Copyright © 2020 Oak Systems Private Limited. All Rights Reserved
4
Test Plan Support - Scope
Scope is to provide UAT Test Support (functional) with the following..
Modules
✓ Core – HO, Branch, Currencies,
SMS and related options
✓ CIF
✓ CASA ✓ Overdraft – CASA
✓ Term Deposits ✓ Consumer Lending
✓ Teller ✓ Funds Transfer
✓ Money Market ✓ ICCF (Interest & CD)
✓ Tax (VAT) – Converted to IC ✓ General Ledger
✓ Standing Instructions ✓ ELCM
✓ Security Maintenance System ✓ Bank specific customizations
✓ Utility Payment
Interfaces
✓ Integration Gateway/Custom
Suite User Perpetual – 13
Interfaces
✓ ATM Interface/ Account
Perpetual
Copyright © 2020 Oak Systems Private Limited. All Rights Reserved
5
Test Plan Support – Deliverables
Planned
Deliverables
Test
Strategy /
Approach
Master
Test Plan
Detailed
Test Plan
Test
scenarios
(HLTC)
Test cases
(DLTC)
Progress
Reports
Copyright © 2020 Oak Systems Private Limited. All Rights Reserved
6
Quality Commitment
On the Test preparation, Oaksys will ensure that the Client’s
business functionality coverage error record is limited to less than 5%.
This does not apply to scope changes and corrections post the Client’s
review.
Test Deliverables by Oaksys
Description of Tasks Status
Test Strategy ✓ Delivered
Test Approach ✓ Delivered
Master Test Plan ✓ Delivered
Gathering Business Requirements ✓ Delivered
Documentation of Business Requirements ✓ Delivered
Review of Business Requirements with Business Heads/SME’s ✓ Delivered
Test Scenarios/High Level Test Cases (HLTC) ✓ Delivered
Test Cases/Detailed Level Test Cases (DLTC) ✓ Delivered
Progress Reports for preparation ✓ Delivered
Peer review of all the deliverables as per Process Plan ✓ Delivered
Process Related Tasks
Understanding the Bank PM & Test Process ✓ Delivered
Preparation of Estimates based on the Business depth ✓ Delivered
Resource planning and allocation for the tasks ✓ Delivered
Test Management and Project Management for delivery ✓ Delivered
Internal Process review as per Oaksys Audit needs ✓ Delivered
Support rendered to the Bank team for UAT Execution ✓ Delivered
Copyright © 2020 Oak Systems Private Limited. All Rights Reserved
7
Tasks delivered differently
 This engagement was fully delivered at Offshore.
 The tasks were completed by frequent discussions, documentation and
structured review.
 Oaksys SME’s had deep knowledge of Domain & Product.
 Oaksys internal process delivery mechanism deeply helped.
 Oaksys team had past experience in Offshore delivery.
 Bank SME’s knowledge on localization crafted the Business requirements.
 Oaksys team were flexible to work with the Bank Business hours.
 Difference in time zone helped deliver in quick intervals.
 Cultural differences were overcome quickly to ensure timely delivery.
 Quality of deliverables adhered to the Bank SOW stipulations.
Copyright © 2020 Oak Systems Private Limited. All Rights Reserved
8
Timelines and Project Gains
↑ Scope corrections due to customizations – Handled in execution runs,
saving time
↑ Test scope – Delivered above the agreed scope
↑ Test deliverables – Delivered beyond scope (Numbers & Quality).
→ Test Project Risks – Mitigated & controlled using back-up plans for each
Module.
→ Test Quality – Zero deviation on all parameters.
→ Test suite for Interfaces – Zero deviation, covered all 14 interfaces.
↓ Test Project value – No cost overrun – delivered more.
↓ Test Man-days – Extended work beyond agreed numbers to cover
customization.
↓ Test Resources – Extended team support for build with no additional cost to
Bank.
Copyright © 2020 Oak Systems Private Limited. All Rights Reserved
9
Value Adds and Additional Support
$ Test cases prepared for the Parameter validation as well, although the scope
was limited to functional product testing.
$ Although this was a contract with agreed number of deliverables, additional
test cases prepared beyond the numbers were not charged to the Bank as a
good will.
$ Remote delivery will be a challenge unless the understanding and expertise to
convert the requirements exists. This was provided right through the project.
$ Test Process and internal Oaksys Quality checks ensured minimal slippage.
$ During the execution support timeline, Oaksys SME’s Prepared the Business
requirement document for future set of Modules – No additional cost.
Copyright © 2020 Oak Systems Private Limited. All Rights Reserved
10
Thank you!
Oak Systems Pvt. Ltd.
#27, NGEF Lane, Off 100 Feet Road,
Indira Nagar, Bangalore – 560 038, INDIA
Tel : +91-80-4126 7681
Email: contact@oaksys.net
URL: www.oaksys.net
We add value through engagement
Copyright © 2020 Oak Systems Private Limited. All Rights Reserved
11

Banking Case study: UAT Support for CBS Migration

  • 1.
    Banking Case Study– UAT Support for CBS Migration Oak Systems Pvt. Ltd. Copyright © 2020 Oak Systems Private Limited. All Rights Reserved 1
  • 2.
    Engagement Background  Customer:A leading bank in the Caribbean  The Bank is using FLEXCUBE Core Banking System with IBM P6, DB Oracle 10g for their Banking Business Operations.  The Bank planned to migrate the Hardware, DB and the CBS software from the existing one to the newer supportive version with the “AS IS” functionality.  IBM P6 to IBM P8  Oracle DB 10g to 12g  CBS FCv7.1 to FCv12.3  There were 14 interface applications along with CBS that needed consideration during the Migration.  The Bank team needed the Test Process and Test suite build & Execution support for the CBS and interfaces.  The Bank wished to review the Test suite and participate in the Test execution under the guidance of the Oaksys SMEs for User Acceptance Testing of FLEXCUBE CBS and interfaces.  Timeline: Aug 2019 to May 2020.  Engagement Type: Off-Shore delivery.  Status: Completed. Copyright © 2020 Oak Systems Private Limited. All Rights Reserved 2
  • 3.
    Test Team &Size Bank CORE Team - 6 Bank Extended Team - 4 Test Process Manager Oaksys Test Manager Bank Team Test Lead Oaksys - 6 SME’s Impln Team - 4 SME’s Bank Team - 4 Oaksys Project Manager for the Project Copyright © 2020 Oak Systems Private Limited. All Rights Reserved 3
  • 4.
    Test Plan Support– Areas & Activities Services extended to the Customer for the implementation of the FLEXCUBE UBS (Universal Banking System) core banking application upgrade that will cover the following aspects of the Project:  Test Planning including documentation  Test Preparation  Remote support to the Client’s team for test execution Activities involved in the above process are:  Preparation of Test Plan documents  Writing of test scenarios/cases for the above mentioned modules  Writing of test scenarios for the above mentioned interfaces/migration  Remote Test Execution support to the Client during test execution  Defect logging and tracking during test preparation  Review and support of defects during the Client’s Team test execution Copyright © 2020 Oak Systems Private Limited. All Rights Reserved 4
  • 5.
    Test Plan Support- Scope Scope is to provide UAT Test Support (functional) with the following.. Modules ✓ Core – HO, Branch, Currencies, SMS and related options ✓ CIF ✓ CASA ✓ Overdraft – CASA ✓ Term Deposits ✓ Consumer Lending ✓ Teller ✓ Funds Transfer ✓ Money Market ✓ ICCF (Interest & CD) ✓ Tax (VAT) – Converted to IC ✓ General Ledger ✓ Standing Instructions ✓ ELCM ✓ Security Maintenance System ✓ Bank specific customizations ✓ Utility Payment Interfaces ✓ Integration Gateway/Custom Suite User Perpetual – 13 Interfaces ✓ ATM Interface/ Account Perpetual Copyright © 2020 Oak Systems Private Limited. All Rights Reserved 5
  • 6.
    Test Plan Support– Deliverables Planned Deliverables Test Strategy / Approach Master Test Plan Detailed Test Plan Test scenarios (HLTC) Test cases (DLTC) Progress Reports Copyright © 2020 Oak Systems Private Limited. All Rights Reserved 6 Quality Commitment On the Test preparation, Oaksys will ensure that the Client’s business functionality coverage error record is limited to less than 5%. This does not apply to scope changes and corrections post the Client’s review.
  • 7.
    Test Deliverables byOaksys Description of Tasks Status Test Strategy ✓ Delivered Test Approach ✓ Delivered Master Test Plan ✓ Delivered Gathering Business Requirements ✓ Delivered Documentation of Business Requirements ✓ Delivered Review of Business Requirements with Business Heads/SME’s ✓ Delivered Test Scenarios/High Level Test Cases (HLTC) ✓ Delivered Test Cases/Detailed Level Test Cases (DLTC) ✓ Delivered Progress Reports for preparation ✓ Delivered Peer review of all the deliverables as per Process Plan ✓ Delivered Process Related Tasks Understanding the Bank PM & Test Process ✓ Delivered Preparation of Estimates based on the Business depth ✓ Delivered Resource planning and allocation for the tasks ✓ Delivered Test Management and Project Management for delivery ✓ Delivered Internal Process review as per Oaksys Audit needs ✓ Delivered Support rendered to the Bank team for UAT Execution ✓ Delivered Copyright © 2020 Oak Systems Private Limited. All Rights Reserved 7
  • 8.
    Tasks delivered differently This engagement was fully delivered at Offshore.  The tasks were completed by frequent discussions, documentation and structured review.  Oaksys SME’s had deep knowledge of Domain & Product.  Oaksys internal process delivery mechanism deeply helped.  Oaksys team had past experience in Offshore delivery.  Bank SME’s knowledge on localization crafted the Business requirements.  Oaksys team were flexible to work with the Bank Business hours.  Difference in time zone helped deliver in quick intervals.  Cultural differences were overcome quickly to ensure timely delivery.  Quality of deliverables adhered to the Bank SOW stipulations. Copyright © 2020 Oak Systems Private Limited. All Rights Reserved 8
  • 9.
    Timelines and ProjectGains ↑ Scope corrections due to customizations – Handled in execution runs, saving time ↑ Test scope – Delivered above the agreed scope ↑ Test deliverables – Delivered beyond scope (Numbers & Quality). → Test Project Risks – Mitigated & controlled using back-up plans for each Module. → Test Quality – Zero deviation on all parameters. → Test suite for Interfaces – Zero deviation, covered all 14 interfaces. ↓ Test Project value – No cost overrun – delivered more. ↓ Test Man-days – Extended work beyond agreed numbers to cover customization. ↓ Test Resources – Extended team support for build with no additional cost to Bank. Copyright © 2020 Oak Systems Private Limited. All Rights Reserved 9
  • 10.
    Value Adds andAdditional Support $ Test cases prepared for the Parameter validation as well, although the scope was limited to functional product testing. $ Although this was a contract with agreed number of deliverables, additional test cases prepared beyond the numbers were not charged to the Bank as a good will. $ Remote delivery will be a challenge unless the understanding and expertise to convert the requirements exists. This was provided right through the project. $ Test Process and internal Oaksys Quality checks ensured minimal slippage. $ During the execution support timeline, Oaksys SME’s Prepared the Business requirement document for future set of Modules – No additional cost. Copyright © 2020 Oak Systems Private Limited. All Rights Reserved 10
  • 11.
    Thank you! Oak SystemsPvt. Ltd. #27, NGEF Lane, Off 100 Feet Road, Indira Nagar, Bangalore – 560 038, INDIA Tel : +91-80-4126 7681 Email: contact@oaksys.net URL: www.oaksys.net We add value through engagement Copyright © 2020 Oak Systems Private Limited. All Rights Reserved 11