INTERNATIONAL SEMINAR ON 
MASS RAPID TRANSIT SYSTEM(MRTS) 
4th‐5th November 2014 
REVIEW AND ASSESSMENT OF CHALLENGES 
DURING CONSTRUCTION OF CHENNAI 
METRO
CONTENT 
y PROJECT DETAILS 
y PROJECT DESCRIPTION 
y GEOLOGICAL AND GEOTECHNICAL OVERVIEW 
y TUNNELLING PERFORMANCE (TBM ADVANCE/EXCAVATION) 
y TUNNELING THROUGH STATION 
y TUNNEL – STATION INTERFACE 
y CROSS PASSAGE SOIL TREATMENT
DESIGN AND CONSTRUCTION OF UNDERGROUND 
AND ASSOCIATED TUNNELS FOR UAA‐01 & UAA‐05 
OF CHENNAI METRO 
CLIENT :CHENNAI METRO RAIL LTD 
GENERAL CONSULTANT :EMBYE 
CONTRACTOR :TRANSTONNELSTORY‐AFCONS JV 
DESIGNER :PARSONS BRINCKERHOFF 
SOURCE OF FUND :FUNDED BY JICA 
Total Twin Tunnel Length : 17.5 KM
UAA 01 
UAA ‐‐ 05 
‐ Afcons Project
SITE LAYOUT OF THE PROJECT 
UAA 01 
UAA 05
EPBM –– Main Body 
20# shove rams
Transportation of TBM From Port to Site
View of EOT at Washermanpet
Tail Skin Lowering for TBM 718 at Shenoy Nagar Station
Front & middle Shields ready for lowering into Shaft
TBM Assembly
Trial of Muck Tilting Divice
VIEW OF 1ST TUNNEL ‐ SHENOY NAGAR STATION
View of Twin Tunnel
Casting shed & View of Commissioned Moulds
Segment casting at casting Yard
View of Segment stacking
Cutter Head / Cutting Tools
Sample TBM Data Record 
Types of reports/records 
•TBM Steering & alignment 
•TBM Excavation volume control 
•Tunnel grouting records 
•Ring survey & orientation record 
•Ring build record (steps, cracks, 
damage etc) 
•TBM Operational Data record
Typical Soil Profile ‐ Packages 05
Typical Mixed Soil Profile ‐ Packages 01 
Ground Level : +2.855 
Roof Top level : -0.420 
Concourse Level : -6.420 
Base Slab Level : -14.135 
D-Wall Tip level : -24.600
Mixed Ground
Typical Rock Soil Profile ‐ Packages 01
Soil Profile‐Mannadi Station 
Project UAA 01
Soil Profile‐ Chennai Central Station 
Project UAA 01
Core Details
Surface Constraints 
Saint Andrew’s Church 
SHIFTING OF MONUMENT AT RIPPON 
BUILDING AREA
High Court Mannadi
Surface Constraint 
Chennai Central
Surface Constraint Chennai Central 
SHC Shaft
Surface Constraint ‐Egmore
Surface Constraint - Railway tracks on the stretch High Court – 
Chennai Central and geological Profile
Surface Constrain - Railway tracks on the stretch 
Chennai Central ‐ Mayday Park Tunnel
View of Locomotive ‐ Mayday Park 
Tunnelling beneath Coovam River 
Under Coovam River
100% 
TYPICAL GEOLOGICAL PROFILE VARIATION 
60% 
80% 
Percent 
age 
Expected 
W1 W2 W3 W4 
20% 
40% 
0% 
4842.0133 
4847 
4862.9 
4880 
4891 
4903 
4910.4 
4915 
4923 
4934 
4940 
4951 
4956 
4967 
4977 
4992 
100% 
Chainage 
60% 
80% 
entage 
Actual Profile 
0% 
20% 
40% 
3 
7 
9 
0 
1 
3 
4 
5 
3 
4 
0 
1 
6 
7 
7 
2 
Perce 
4842.0133 
4847 
4862.9 
4880 
4891 
4903 
4910.4 
4915 
4923 
4934 
4940 
4951 
4956 
4967 
4977 
4992 
Chainage W1‐Fresh Rock 
W2‐Slightly weathered Rock 
W3‐M Weathered Rock 
W4‐ Highly Weathered Rock
Geological Variation Results: 
Cutter Consumption & Frequency of Intervention
TBM retrieval in wet condition
CHENNAI CENTRAL 
(Overlapping of Two Corridor)
Retrieval Shaft at SCC ‐ Mayday Park Tunnel
Obstacles during Tunnel Operation 
Ground Level 
CL 
Red 
Zone 
Ora 
Zon 
Gr 
Zone 
L 
TUNNEL 
A 
ange 
ne 
reen Zone 
Green Z 
Orange 
Zone 
TUNNEL 
B 
1.0 mt 1.0 mt 
Bore well influence 1mt from Extrados of Tunnel 
Segment
Obstacles during Tunnel Operation 
UAA 01 
NO. OF EXISTING WELLS IN DIFFERENT ZONES: UAA01 
Project 
RED ZONE 
(11.355 m. 
f T l 
ORANGE ZONE 
(5.15 m. from RED 
GREEN ZONE 
( 4.5 m. from 
TOTAL R + O + 
G 
from Tunnel 
CL) 
5. 5 R 
ZONE) 
ORANGE ZONE) 
Package 01 304 98 90 492 
Package 05 
61 24 60 145 
Total 365 122 150 637
BUILDING CONDITION SURVEY 
BUILDING CONDITION SURVEY
TUNNELLING PERFORMANCE 
The TBMS are normally operated on a 24 hr basis, working 2 
shifts per day. 
The following main results have been achieved: 
¾ Average Daily Production:.12 ..Rings =16.8 m 
¾¾ Best Day(09/02/2013): 39rings=54.6 m 
¾ Best week(04/02/2013 to 09/02/2013): 139 rings=182 m 
¾ Best Month ( Oct 2013): 525 rings= 735 m 
¾We have achieved 39 Rings Boring in a day first time in 
the World 
Considering that all the 5 TBMs have been operated in a very sensitive urban 
environment, almost always in closed mode, these results can be regarded as very 
positive and above the usual standard.
Heave pressure verification 
3 50 
4.00 
4.50 
5.00 
2.00 
2.50 
3.00 
3.50 
ressures (bar) 
0.50 
1.00 
1.50 
Pr 
Cohesive material 
0.00 
0+220 
0+260 
0+300 
0+340 
0+380 
0+420 
0+460 
0+500 
0+540 
0+580 
0+620 
0+660 
0+700 
0+740 
0+780 
0+820 
0+860 
0+900 
0+940 
0+980 
1+020 
1+060 
1+100 
1+140 
1+180 
1+220 
1+260 
1+300 
1+340 
1+380 
1+420 
1+460 
1+500 
1+540 
1+580 
CHAINAGE 
Heave pressure (by Jancsez th.) Recommended Max. Pressure
Recommended EPB pressure and 
Grout Injection Pressure 
3.00 
2.00 
2.50 
ar) 
Pressures (b 
1 00 
1.50 
0.50 
1.00 
0.00 
1+580 
1+620 
1+660 
1+700 
1+740 
1+780 
1+820 
1+860 
1+900 
1+940 
1+980 
2+020 
2+060 
2+100 
2+140 
2+180 
2+220 
2+260 
2+300 
2+340 
2+380 
2+420 
2+460 
2+500 
CHAINAGE 
Recommended pressure Min.pressure Max.pressure Grout injection system
Earth Pressure Monitoring 
3 
2.5 
2 
1.5 
1 
Pressure (bar) 
0.5 
0 
0 200 400 600 800 1000 1200 1400 1600 1800 2000 
Earth P 
Mannadi Station Ring No. 
D'W ll C tti 
High Court 
D'Wall Cutting Station Area 
3.5 
3 
2.5 
ure (bar) 
2 
1.5 
1 
0.5 
Earth Pressu 
0 
0 200 400 600 800 1000 1200 1400 1600 1800 2000 
Ring No.
Typical Machining Parameters 
monitoring 
30000 
25000 
20000 
orce 
Thrust Force(kN) 
3.5 
3 
2.5 
2 
M 
Cutting wheel Rotation (rpm) 
15000 
10000 
5000 
0 
0 500 1000 1500 2000 
Thrust Fo 
1.5 
1 
0.5 
0 
0 500 1000 1500 2000 
RPM 
Ring No. 
Ring No. 
Torque(MN.m) Advance Speed (mm/Min) 
4 
3.5 
3 
2.5 
2 
que 
60 
50 
40 
30 
eed()mm/Min. 
1.5 
1 
0.5 
0 
Torq 
20 
10 
0 
0 500 1000 1500 2000 
Advance Spe 
0 500 1000 1500 2000 
Ring No. 
Ring No.
Operation steps in Mechanized Tunneling 
¾Making Launching Shaft 
¾¾Assembly of TBM ¾ i i Sh f 
¾Initial Drive 
¾Muck Out 
Receiving Shaft 
¾Tunnel Break through 
¾Dissemble TBM 
¾Boring 
¾Assembly of Lining 
¾Grouting 
¾Segment Lining 
¾Close of Launching shaft 
upon Completion 
¾Retrieval of TBM to Groundt 
¾Close of receiving shaft 
p p 
Segment yard 
™Casting of Segment
Type of TBM 
EPBM‐Mixed Ground Type EPB‐Soft Ground Type 
UAA 01 
Washermanpet to Chennai 
Central 
M f t H k ht 
UAA 05 
Shenoy Nagar to 
Thirumangalam 
Manufacture‐Herrenknecht Manufacture‐ 
Herrenknecht 
UAA 01 
May day Park to Chennai 
EPB‐Rock/Mixed Face 
Central 
Manufacture‐Robbins
TBM Confinement
Breaking Out Through Confinement
Interface Tunnel ‐ Station 
Mining Through D Th h 
UAA 01 Drag Through 
Mining Through Station Trag Through 
Break In Break Out Break In Break Out 
Break In 
Break Out 
UAA 05 
Mining Through h h 
reak 
hrough 
Drag Through Drag Through 
Br 
Th 
Break In 
Break Out Break In Break Out Break In
TBM 717 Break In – Anna Nagar TBM Break In Shenoy Nagar Station 
Tower 
In‐
View of 1st Tunnel & TBM 718 ‐ Shenoy Nagar Station
Mining Through Station 
Plan 
Elevation
TBM Drag through
TBM Break through 
717
718 
711 
710 711 717 710
Tunnel Boring Machine Specification 
TBM’s 
Cost of each TBM & backup equipment 33.5Cr 
TBM total weight 290 T 
Excavation diameter 6.6 m 
Overall length 9.7 m 
Electrical power 940 kW 
Left & right rotation speed Max 4.57 rpm 
Ram advance speed Max. 80 mm/min 
Ram jacks 32 # 
Total advance thrust force 42000 KN 
Earth pressure sensors 6 #
Cross Passage Soil 
Treatment
Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)

More Related Content

What's hot

DMRC REPORT ON UNDERGROUND CONSTRUCTION
DMRC REPORT ON UNDERGROUND CONSTRUCTIONDMRC REPORT ON UNDERGROUND CONSTRUCTION
DMRC REPORT ON UNDERGROUND CONSTRUCTION
Md Shadab
 

What's hot (20)

DMRC REPORT ON UNDERGROUND CONSTRUCTION
DMRC REPORT ON UNDERGROUND CONSTRUCTIONDMRC REPORT ON UNDERGROUND CONSTRUCTION
DMRC REPORT ON UNDERGROUND CONSTRUCTION
 
NATM ppt sumit
NATM ppt sumitNATM ppt sumit
NATM ppt sumit
 
Depots presentation
Depots presentationDepots presentation
Depots presentation
 
Metro rail segments
Metro rail segmentsMetro rail segments
Metro rail segments
 
Metro Work
Metro WorkMetro Work
Metro Work
 
conceptual desig of Chenab bridge
conceptual desig of Chenab bridge conceptual desig of Chenab bridge
conceptual desig of Chenab bridge
 
Metro ppt-180628112005
Metro ppt-180628112005Metro ppt-180628112005
Metro ppt-180628112005
 
Railway engineering
Railway engineeringRailway engineering
Railway engineering
 
Metro Underground civil structures and track structures AR.pdf
Metro Underground civil structures and track structures AR.pdfMetro Underground civil structures and track structures AR.pdf
Metro Underground civil structures and track structures AR.pdf
 
Components of railway track
Components of railway trackComponents of railway track
Components of railway track
 
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTIONINDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
 
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRCDELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
 
62617938 launching-girder
62617938 launching-girder62617938 launching-girder
62617938 launching-girder
 
Metro Construction
Metro ConstructionMetro Construction
Metro Construction
 
Metro system routing studies.pptx
Metro system routing studies.pptxMetro system routing studies.pptx
Metro system routing studies.pptx
 
Pier & bridge guide
Pier & bridge guidePier & bridge guide
Pier & bridge guide
 
Bandra worli sealink pdf
Bandra worli sealink pdfBandra worli sealink pdf
Bandra worli sealink pdf
 
Rapid transit system
Rapid transit systemRapid transit system
Rapid transit system
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 
Chennai metro rail
Chennai metro railChennai metro rail
Chennai metro rail
 

Viewers also liked

Chennai metro rail
Chennai metro railChennai metro rail
Chennai metro rail
karthik1923
 
Taipei MRT Signage Study
Taipei MRT Signage StudyTaipei MRT Signage Study
Taipei MRT Signage Study
kelake
 
L&T Inplant training at chennai metro report
L&T Inplant training at chennai metro reportL&T Inplant training at chennai metro report
L&T Inplant training at chennai metro report
hemanth kumar
 
Beyond Buses - Creating a better Public Transport System through Marketing, C...
Beyond Buses - Creating a better Public Transport System through Marketing, C...Beyond Buses - Creating a better Public Transport System through Marketing, C...
Beyond Buses - Creating a better Public Transport System through Marketing, C...
WRI Ross Center for Sustainable Cities
 

Viewers also liked (20)

Metro Rail in India ppt
Metro Rail in India pptMetro Rail in India ppt
Metro Rail in India ppt
 
Chennai metro rail
Chennai metro railChennai metro rail
Chennai metro rail
 
Metro rail seminor
Metro rail seminor Metro rail seminor
Metro rail seminor
 
Cmrl ppt
Cmrl pptCmrl ppt
Cmrl ppt
 
.Chennai metro rail-2
.Chennai metro rail-2.Chennai metro rail-2
.Chennai metro rail-2
 
Metro train prototype
Metro train prototypeMetro train prototype
Metro train prototype
 
Formulation of detailed project report(final)
Formulation of detailed project report(final)Formulation of detailed project report(final)
Formulation of detailed project report(final)
 
Mumbai metro project Phase I
Mumbai metro project Phase IMumbai metro project Phase I
Mumbai metro project Phase I
 
Modern Methods of Construction
Modern Methods of ConstructionModern Methods of Construction
Modern Methods of Construction
 
Narasimhan 7537
Narasimhan 7537Narasimhan 7537
Narasimhan 7537
 
Metro stations all over world
Metro stations all over worldMetro stations all over world
Metro stations all over world
 
The MRT In Taipei
The MRT In TaipeiThe MRT In Taipei
The MRT In Taipei
 
Taipei MRT Signage Study
Taipei MRT Signage StudyTaipei MRT Signage Study
Taipei MRT Signage Study
 
Mass Rapid Transit (Bangkok, Thailand)
Mass Rapid Transit (Bangkok, Thailand)Mass Rapid Transit (Bangkok, Thailand)
Mass Rapid Transit (Bangkok, Thailand)
 
L&T Inplant training at chennai metro report
L&T Inplant training at chennai metro reportL&T Inplant training at chennai metro report
L&T Inplant training at chennai metro report
 
Beyond Buses - Creating a better Public Transport System through Marketing, C...
Beyond Buses - Creating a better Public Transport System through Marketing, C...Beyond Buses - Creating a better Public Transport System through Marketing, C...
Beyond Buses - Creating a better Public Transport System through Marketing, C...
 
Tp metro
Tp metroTp metro
Tp metro
 
Metro train prototype
Metro train prototypeMetro train prototype
Metro train prototype
 
Metro ppt - copy
Metro ppt - copyMetro ppt - copy
Metro ppt - copy
 
Automatic Metro
Automatic MetroAutomatic Metro
Automatic Metro
 

Similar to Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)

ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
Egyptian Engineers Association
 
2.1 port of miami tunnel cei
2.1 port of miami tunnel cei2.1 port of miami tunnel cei
2.1 port of miami tunnel cei
ascemiami-dade
 
Site visit presentation: Kwun Tong line extension
Site visit presentation: Kwun Tong line extensionSite visit presentation: Kwun Tong line extension
Site visit presentation: Kwun Tong line extension
Association for Project Management
 
Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)
John Latilla
 

Similar to Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar) (20)

Dragline Planning
Dragline PlanningDragline Planning
Dragline Planning
 
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxPPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
 
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
 
Project 4 Presentation
Project 4 PresentationProject 4 Presentation
Project 4 Presentation
 
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
 
Report work on retaining wall
Report work on retaining wallReport work on retaining wall
Report work on retaining wall
 
Nbc cso apwa expo july 8 t12
Nbc cso apwa expo july 8 t12Nbc cso apwa expo july 8 t12
Nbc cso apwa expo july 8 t12
 
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
 
NATM Tunneling ppt
NATM Tunneling pptNATM Tunneling ppt
NATM Tunneling ppt
 
2.1 port of miami tunnel cei
2.1 port of miami tunnel cei2.1 port of miami tunnel cei
2.1 port of miami tunnel cei
 
Construction Presentations 2019
Construction Presentations 2019Construction Presentations 2019
Construction Presentations 2019
 
Site visit presentation: Kwun Tong line extension
Site visit presentation: Kwun Tong line extensionSite visit presentation: Kwun Tong line extension
Site visit presentation: Kwun Tong line extension
 
Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessity
 
Project Monitoring
Project MonitoringProject Monitoring
Project Monitoring
 
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.
 
(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...
(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...
(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...
 

Recently uploaded

Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
jaanualu31
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
Kamal Acharya
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
mphochane1998
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 

Recently uploaded (20)

Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech Civil
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills KuwaitKuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
Kuwait City MTP kit ((+919101817206)) Buy Abortion Pills Kuwait
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptx
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Thermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - VThermal Engineering-R & A / C - unit - V
Thermal Engineering-R & A / C - unit - V
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 

Technical Paper on Chennai Metro Project (Mr Klaus Muenz and Nandan Kumar)

  • 1. INTERNATIONAL SEMINAR ON MASS RAPID TRANSIT SYSTEM(MRTS) 4th‐5th November 2014 REVIEW AND ASSESSMENT OF CHALLENGES DURING CONSTRUCTION OF CHENNAI METRO
  • 2. CONTENT y PROJECT DETAILS y PROJECT DESCRIPTION y GEOLOGICAL AND GEOTECHNICAL OVERVIEW y TUNNELLING PERFORMANCE (TBM ADVANCE/EXCAVATION) y TUNNELING THROUGH STATION y TUNNEL – STATION INTERFACE y CROSS PASSAGE SOIL TREATMENT
  • 3. DESIGN AND CONSTRUCTION OF UNDERGROUND AND ASSOCIATED TUNNELS FOR UAA‐01 & UAA‐05 OF CHENNAI METRO CLIENT :CHENNAI METRO RAIL LTD GENERAL CONSULTANT :EMBYE CONTRACTOR :TRANSTONNELSTORY‐AFCONS JV DESIGNER :PARSONS BRINCKERHOFF SOURCE OF FUND :FUNDED BY JICA Total Twin Tunnel Length : 17.5 KM
  • 4. UAA 01 UAA ‐‐ 05 ‐ Afcons Project
  • 5. SITE LAYOUT OF THE PROJECT UAA 01 UAA 05
  • 6. EPBM –– Main Body 20# shove rams
  • 7. Transportation of TBM From Port to Site
  • 8. View of EOT at Washermanpet
  • 9. Tail Skin Lowering for TBM 718 at Shenoy Nagar Station
  • 10. Front & middle Shields ready for lowering into Shaft
  • 12. Trial of Muck Tilting Divice
  • 13. VIEW OF 1ST TUNNEL ‐ SHENOY NAGAR STATION
  • 14. View of Twin Tunnel
  • 15. Casting shed & View of Commissioned Moulds
  • 16. Segment casting at casting Yard
  • 17. View of Segment stacking
  • 18. Cutter Head / Cutting Tools
  • 19. Sample TBM Data Record Types of reports/records •TBM Steering & alignment •TBM Excavation volume control •Tunnel grouting records •Ring survey & orientation record •Ring build record (steps, cracks, damage etc) •TBM Operational Data record
  • 20. Typical Soil Profile ‐ Packages 05
  • 21. Typical Mixed Soil Profile ‐ Packages 01 Ground Level : +2.855 Roof Top level : -0.420 Concourse Level : -6.420 Base Slab Level : -14.135 D-Wall Tip level : -24.600
  • 23. Typical Rock Soil Profile ‐ Packages 01
  • 25. Soil Profile‐ Chennai Central Station Project UAA 01
  • 27. Surface Constraints Saint Andrew’s Church SHIFTING OF MONUMENT AT RIPPON BUILDING AREA
  • 30. Surface Constraint Chennai Central SHC Shaft
  • 32. Surface Constraint - Railway tracks on the stretch High Court – Chennai Central and geological Profile
  • 33.
  • 34. Surface Constrain - Railway tracks on the stretch Chennai Central ‐ Mayday Park Tunnel
  • 35. View of Locomotive ‐ Mayday Park Tunnelling beneath Coovam River Under Coovam River
  • 36. 100% TYPICAL GEOLOGICAL PROFILE VARIATION 60% 80% Percent age Expected W1 W2 W3 W4 20% 40% 0% 4842.0133 4847 4862.9 4880 4891 4903 4910.4 4915 4923 4934 4940 4951 4956 4967 4977 4992 100% Chainage 60% 80% entage Actual Profile 0% 20% 40% 3 7 9 0 1 3 4 5 3 4 0 1 6 7 7 2 Perce 4842.0133 4847 4862.9 4880 4891 4903 4910.4 4915 4923 4934 4940 4951 4956 4967 4977 4992 Chainage W1‐Fresh Rock W2‐Slightly weathered Rock W3‐M Weathered Rock W4‐ Highly Weathered Rock
  • 37. Geological Variation Results: Cutter Consumption & Frequency of Intervention
  • 38. TBM retrieval in wet condition
  • 39. CHENNAI CENTRAL (Overlapping of Two Corridor)
  • 40. Retrieval Shaft at SCC ‐ Mayday Park Tunnel
  • 41. Obstacles during Tunnel Operation Ground Level CL Red Zone Ora Zon Gr Zone L TUNNEL A ange ne reen Zone Green Z Orange Zone TUNNEL B 1.0 mt 1.0 mt Bore well influence 1mt from Extrados of Tunnel Segment
  • 42. Obstacles during Tunnel Operation UAA 01 NO. OF EXISTING WELLS IN DIFFERENT ZONES: UAA01 Project RED ZONE (11.355 m. f T l ORANGE ZONE (5.15 m. from RED GREEN ZONE ( 4.5 m. from TOTAL R + O + G from Tunnel CL) 5. 5 R ZONE) ORANGE ZONE) Package 01 304 98 90 492 Package 05 61 24 60 145 Total 365 122 150 637
  • 43. BUILDING CONDITION SURVEY BUILDING CONDITION SURVEY
  • 44. TUNNELLING PERFORMANCE The TBMS are normally operated on a 24 hr basis, working 2 shifts per day. The following main results have been achieved: ¾ Average Daily Production:.12 ..Rings =16.8 m ¾¾ Best Day(09/02/2013): 39rings=54.6 m ¾ Best week(04/02/2013 to 09/02/2013): 139 rings=182 m ¾ Best Month ( Oct 2013): 525 rings= 735 m ¾We have achieved 39 Rings Boring in a day first time in the World Considering that all the 5 TBMs have been operated in a very sensitive urban environment, almost always in closed mode, these results can be regarded as very positive and above the usual standard.
  • 45. Heave pressure verification 3 50 4.00 4.50 5.00 2.00 2.50 3.00 3.50 ressures (bar) 0.50 1.00 1.50 Pr Cohesive material 0.00 0+220 0+260 0+300 0+340 0+380 0+420 0+460 0+500 0+540 0+580 0+620 0+660 0+700 0+740 0+780 0+820 0+860 0+900 0+940 0+980 1+020 1+060 1+100 1+140 1+180 1+220 1+260 1+300 1+340 1+380 1+420 1+460 1+500 1+540 1+580 CHAINAGE Heave pressure (by Jancsez th.) Recommended Max. Pressure
  • 46. Recommended EPB pressure and Grout Injection Pressure 3.00 2.00 2.50 ar) Pressures (b 1 00 1.50 0.50 1.00 0.00 1+580 1+620 1+660 1+700 1+740 1+780 1+820 1+860 1+900 1+940 1+980 2+020 2+060 2+100 2+140 2+180 2+220 2+260 2+300 2+340 2+380 2+420 2+460 2+500 CHAINAGE Recommended pressure Min.pressure Max.pressure Grout injection system
  • 47. Earth Pressure Monitoring 3 2.5 2 1.5 1 Pressure (bar) 0.5 0 0 200 400 600 800 1000 1200 1400 1600 1800 2000 Earth P Mannadi Station Ring No. D'W ll C tti High Court D'Wall Cutting Station Area 3.5 3 2.5 ure (bar) 2 1.5 1 0.5 Earth Pressu 0 0 200 400 600 800 1000 1200 1400 1600 1800 2000 Ring No.
  • 48. Typical Machining Parameters monitoring 30000 25000 20000 orce Thrust Force(kN) 3.5 3 2.5 2 M Cutting wheel Rotation (rpm) 15000 10000 5000 0 0 500 1000 1500 2000 Thrust Fo 1.5 1 0.5 0 0 500 1000 1500 2000 RPM Ring No. Ring No. Torque(MN.m) Advance Speed (mm/Min) 4 3.5 3 2.5 2 que 60 50 40 30 eed()mm/Min. 1.5 1 0.5 0 Torq 20 10 0 0 500 1000 1500 2000 Advance Spe 0 500 1000 1500 2000 Ring No. Ring No.
  • 49. Operation steps in Mechanized Tunneling ¾Making Launching Shaft ¾¾Assembly of TBM ¾ i i Sh f ¾Initial Drive ¾Muck Out Receiving Shaft ¾Tunnel Break through ¾Dissemble TBM ¾Boring ¾Assembly of Lining ¾Grouting ¾Segment Lining ¾Close of Launching shaft upon Completion ¾Retrieval of TBM to Groundt ¾Close of receiving shaft p p Segment yard ™Casting of Segment
  • 50. Type of TBM EPBM‐Mixed Ground Type EPB‐Soft Ground Type UAA 01 Washermanpet to Chennai Central M f t H k ht UAA 05 Shenoy Nagar to Thirumangalam Manufacture‐Herrenknecht Manufacture‐ Herrenknecht UAA 01 May day Park to Chennai EPB‐Rock/Mixed Face Central Manufacture‐Robbins
  • 52. Breaking Out Through Confinement
  • 53. Interface Tunnel ‐ Station Mining Through D Th h UAA 01 Drag Through Mining Through Station Trag Through Break In Break Out Break In Break Out Break In Break Out UAA 05 Mining Through h h reak hrough Drag Through Drag Through Br Th Break In Break Out Break In Break Out Break In
  • 54. TBM 717 Break In – Anna Nagar TBM Break In Shenoy Nagar Station Tower In‐
  • 55. View of 1st Tunnel & TBM 718 ‐ Shenoy Nagar Station
  • 56. Mining Through Station Plan Elevation
  • 59. 718 711 710 711 717 710
  • 60. Tunnel Boring Machine Specification TBM’s Cost of each TBM & backup equipment 33.5Cr TBM total weight 290 T Excavation diameter 6.6 m Overall length 9.7 m Electrical power 940 kW Left & right rotation speed Max 4.57 rpm Ram advance speed Max. 80 mm/min Ram jacks 32 # Total advance thrust force 42000 KN Earth pressure sensors 6 #
  • 61. Cross Passage Soil Treatment