SlideShare a Scribd company logo
1 of 30
Managed by
PHYSICAL WORKS PROJECT MONITORING
ORIENTATION
2
PROJECT MONITORING
- In Construction Supervision, project
monitoring is the procedures/methods
wherein it involves work projection and
accomplishment within the period of time
specified in the contract agreement.
3
CONCEPT:
Construction
Supervision
QUALITY
ASSURANCE
PROCEDURES
/ METHODS
MONITORING
REPORTING
PROJECT MONITORING
4
EMPHASIS ON MONITORING:
PROJECT MONITORING
MONITORING
PROJECTION /
PLAN
ACCOMPLISHMENT
SLIPPAGE /
VARIANCE
TIME
REPORTING
5
PROJECT MONITORING
• Project performance?
• Completed structures/works?
• Progress accomplishment?
• Physical
• Billable
VALIDATE/MONITOR BY:
6
• Project performance
- Compliance with
- the Technical Specifications
- the approved Methodology
- the required documentation/reporting
- Works ahead of schedule/plan
- Quality Assurance (workmanship)
PROJECT MONITORING
7
• Completed structures/works?
- Reporting from the contractors needs to be
validated and/or inspected by the CS Team
- A straight line diagram can be used as tool for
monitoring and validating reported completed
as well as on-going site works
PROJECT MONITORING
8
• Progress accomplishment?
• Physical
- This is the work of items completed at site subject
for validation, testing and quality assurance
• Billable
- This is the work of items completed at site that are
already validated, passed testing and quality
assurance
PROJECT MONITORING
9
• Progress accomplishment?
• Physical
- This is the work of items completed at site subject
for validation, testing and quality assurance
• Billable
- This is the work of items completed at site that are
already validated, passed testing and quality
assurance
PROJECT MONITORING
10
STRAIGHT LINE DIAGRAM – CAD FILES
11
STRAIGHT LINE DIAGRAM – EXCEL FILES
Clearing and Grubbing
Pipe Culvert and Drain Excavation
Subgrade Preparation (existing Pavement)
Aggregate Subbase Course
Stone Masonry (Slope Protection) Sta. 4+940-5+000
Stone Masonry (Headwall and Line Ditch)
Sta. 4+946-5+104
Existing Concrete Road
Guardrails Sta. 4+250-4+265
Sta. 4+250-4+280
Sta. 4+450-4+465 Sta. 4+820-4+850
Legend: Proposed Plan
Ongoing
Completed
Completed culvert
5+330
END
5+300
Provide lined ditch cover
4+900
5+000
5+100
5+200
4+200
4+300
4+400
4+500
4+800
Sta. 4+300-4+580
Sta. 4+680-4+720
Sta. 4+640-4+893
4+000
4+100
4+600
4+700
STA.4+000 - STA. 5+330
Sta5+024 existing 1-610mmØ x 6 m RCPC
Remove and replaced1-910mm Ø x 8 m
provide straight headwalls B/S
Sta 4+400 InstallRCPC1-910
mm Ø x 8 m cross drain &
provide straight headwallB/S
Sta. 4+569.60existing 1
610mmØ x 6m RCPC Cleanand
Maintain, ProvideStraight
Sta. 4+760 InstallRCPC 1 910mmØ
x 8m CRoss drain &provide
straightheadwall B/S
Sta. 4+760 InstallRCPC 1 910mmØ
x 8m CRoss drain &provide
straightheadwall B/S
As of September 26, 2014
Clearing and Grubbing
Pipe Culvert and Drain Excavation
Subgrade Preparation (existing Pavement)
Aggregate Subbase Course
Stone Masonry (Slope Protection)
Stone Masonry (Headwall and Line Ditch)
Existing PCCP/Asphalt
Guardrails
Sta. 1+223-1+323
1+800
STRAIGHT LINE DIAGRAM FOR PW-BHL-13-005
0+100
0+200
0+300
0+400
0+500
0+600
0+700
0+900
0+800
0+000
STA. 0+000- STA. 2+000
START
1+900
2+000
1+400
1+500
1+600
1+000
1+100
1+200
1+300
1+700
Sta. 0+674 existing 1 410mmØ
x 7m RCPC Clean andMaintain,
Provide StraightHeadwallB/S
Sta. 0+282 existing 1-410mmØ
x 6 RCPC Clean and Maintain,
Provide StraightHeadwallB/S
Sta. 0+494 existing 1-610mmØ
x m RCPC Clean andMaintain,
Provide StraightHeadwallB/S
Sta. 0+826.70existing 1 410mmØ
x 6m RCPC Clean andMaintain,
Provide StraightHeadwallB/S
Sta. 1+223 existing 1 410mmØ x
6m RCPC Clean andMaintain,
Provide StraightHeadwallB/S
Sta. 1+800 existing 1 910mmØ x
8m RCPC ProvideStraight
HeadwallB/S
12
STRAIGHT LINE DIAGRAM – EXCEL FILES
MAINTENANCE OF AKLAN PROVINCIAL GRAVEL ROAD
NUMAMCIA-JOYAO-JOYAO-ALIPUTOS-IBAO-LEZO ROAD
NUMANCIA-BADIO-ALBASAN-NAVITAS SUR
NUMANCIA-DUNGON-BAYBAY ROAD
LAGUINBANUA-BOBOG-ALBASAN ROAD
LAGUINBANUA EAST-BULWANG-CAMANCE SUR ROAD
BRIDGE
4+743.51
BRIDGE
3+378.89
1+900
2+000
0+400
0+500
0+600
0+700
3+800
3+900
4+000
4+100
4+200
4+300
3+300
Existing Gravel
2+000
2+100
2+200
2+300
2+400
2+500
2+600
2+700
Existing PCCP
0+900
vegetation Control
Manual Patching for Unpaved Road Surface
Materials to resurface unpaved road by means ofmechanical equip.
Machine Grading for Unpaved Road section including side ditch drains by means ofmechaical equipment
Manual Line Ditch Cleaning (lined and Unlined)
Machine Grading for Unpaved Road section including side ditch drains by means ofmechaical equipment
Manual Line Ditch Cleaning (lined and Unlined)
vegetation Control
AS-STAKED PLAN
vegetation Control
AS-STAKED PLAN
Manual Patching for Unpaved Road Surface
Materials to resurface unpaved road by means ofmechanical equip.
vegetation Control
AS-STAKED PLAN
Manual Patching for Unpaved Road Surface
Materials to resurface unpaved road by means ofmechanical equip.
Machine Grading for Unpaved Road section including side ditch drains by means ofmechaical equipment
Manual Line Ditch Cleaning (lined and Unlined)
Manual Patching for Unpaved Road Surface
Materials to resurface unpaved road by means ofmechanical equip.
Machine Grading for Unpaved Road section including side ditch drains by means ofmechaical equipment
Manual Line Ditch Cleaning (lined and Unlined)
Manual Patching for Unpaved Road Surface
Materials to resurface unpaved road by means ofmechanical equip.
Machine Grading for Unpaved Road section including side ditch drains by means ofmechaical equipment
Manual Line Ditch Cleaning (lined and Unlined)
Machine Grading for Unpaved Road section including side ditch drains by means ofmechaical equipment
Manual Line Ditch Cleaning (lined and Unlined)
vegetation Control
AS-STAKED PLAN
vegetation Control
AS-STAKED PLAN
Manual Patching for Unpaved Road Surface
Materials to resurface unpaved road by means ofmechanical equip.
0+400
0+500
2+300
START
2+100
2+200
0+000
0+100
AS-STAKED PLAN
Manual Patching for Unpaved Road Surface
Materials to resurface unpaved road by means ofmechanical equip.
Machine Grading for Unpaved Road section including side ditch drains by means ofmechaical equipment
vegetation Control
Manual Line Ditch Cleaning (lined and Unlined)
AS-STAKED PLAN
1+500
1+600
1+700
1+800
vegetation Control
AS-STAKED PLAN
Manual Patching for Unpaved Road Surface
Materials to resurface unpaved road by means ofmechanical equip.
Machine Grading for Unpaved Road section including side ditch drains by means ofmechaical equipment
1+000
1+100
1+200
1+300
1+400
0+700
START
0+800
2+400
2+500
2+600
2+700
0+200
0+300
2+363.29
0+900
0+000
0+100
0+200
0+300
0+400
0+500
2+800
2+900
3+000
3+100
3+200
3+300
0+600
2+100
2+200
2+300
2+400
0+800
0+900
1+000
1+100
1+500
1+600
1+700
1+800
1+900
2+000
1+200
1+300
1+400
3+400
3+500
3+600
3+700
2+900
3+000
3+100
3+200
3+300
0+100
0+200
0+300
0+400
START
4+400
4+500
4+500
4+700
0+000
0+900
1+000
4+700
0+000
0+100
0+200
0+300
0+400
START
1+300
1+400
1+500
1+600
0+500
0+600
0+700
0+800
2+300
2+400
2+500
2+600
2+700
2+800
1+700
1+800
1+900
2+000
2+100
2+200
Manual Line Ditch Cleaning (lined and Unlined)
4+000
4+000
4+100
4+200
4+300
4+400
4+500
4+600
3+400
3+500
3+600
3+700
3+800
3+900
2+800
2+900
3+000
3+100
3+200
3+300
1+100
1+200
STRAIGHT LINE DIAGRAM
1+800
1+700
1+600
1+500
1+400
1+300
0+700
0+800
0+900
1+000
1+100
2+000
1+200
1+900
0+000
START
0+100
0+200
0+300
0+400
0+500
0+600
Sta. 0+664 clean and maintain
existing 3-line1.20m Ø RCPC
Sta2+547 clean and maintain
existing 1-line1.50m Ø RCBC
Sta 3+743.93clean and maintain
existing 1-line0.60m Ø RCBC
Sta. 0+0333cleanandmaintain
existing 1-line2.5m Ø RCBCSta. 1+750 clean and maintain
existing 2-line0.60m Ø RCPC
Sta. 4+062 clean and maintain
existing 1-line3.0m Ø RCPC
Sta. 0+567 clean and maintain
existing 3-barrel3.0m wideRCBC
Sta. 0+977 clean and maintain
existing 1-line0.90m Ø RCPC
Sta 2+363.29clean and maintain
existing 1-line0.45m Ø RCPC
Sta. 0+209.00clean andmaintain Sta. 0+604.00clean andmaintain
Sta. 316 cleanand maintain
existing RCPC
Sta. 521 cleanand maintain
existing RCPC
Sta. 1+276 clean and maintain
existing RCPC
Sta. 2+279 clean and maintain
existing RCPC
NUMANCIA-BADIO-ALBASAN-NAVITAS SUR
NUMANCIA-DUNGON-BAYBAY ROAD
LAGUINBANUA-BOBOG-ALBASAN ROAD
LAGUINBANUA EAST-BULWANG-CAMANCE SUR ROAD
MABILO-BRIONES ROAD
Legend: Proposed Plan
Ongoing
Completed
Completed culvert
1+266.15
1+100
1+200
0+400
0+500
0+600
0+700
0+700
0+800
0+900
1+000
0+300
BRIDGE
1+760.84
0+000
0+100
0+200
4+743.51
BRIDGE
3+378.89
1+900
2+000
0+400
0+500
0+600
0+700
3+800
3+900
4+000
4+100
4+200
4+300
3+300
Machine Grading for Unpaved Road section including side ditch drains by means of mechaical equipment
Manual Line Ditch Cleaning (lined and Unlined)
vegetation Control
0+9000+500
vegetation Control
AS-STAKED PLAN
Manual Patching for Unpaved Road Surface
Materials to resurface unpaved road by means of mechanical equip.
vegetation Control
AS-STAKED PLAN
Manual Patching for Unpaved Road Surface
Materials to resurface unpaved road by means of mechanical equip.
Machine Grading for Unpaved Road section including side ditch drains by means of mechaical equipment
Manual Line Ditch Cleaning (lined and Unlined)
Manual Patching for Unpaved Road Surface
Materials to resurface unpaved road by means of mechanical equip.
Machine Grading for Unpaved Road section including side ditch drains by means of mechaical equipment
Manual Line Ditch Cleaning (lined and Unlined)
Machine Grading for Unpaved Road section including side ditch drains by means of mechaical equipment
Manual Line Ditch Cleaning (lined and Unlined)
vegetation Control
AS-STAKED PLAN
vegetation Control
AS-STAKED PLAN
Manual Patching for Unpaved Road Surface
Materials to resurface unpaved road by means of mechanical equip.
vegetation Control
AS-STAKED PLAN
Manual Patching for Unpaved Road Surface
Materials to resurface unpaved road by means of mechanical equip.
Machine Grading for Unpaved Road section including side ditch drains by means of mechaical equipment
Manual Line Ditch Cleaning (lined and Unlined)
Manual Patching for Unpaved Road Surface
Materials to resurface unpaved road by means of mechanical equip.
Machine Grading for Unpaved Road section including side ditch drains by means of mechaical equipment
Manual Line Ditch Cleaning (lined and Unlined)
Machine Grading for Unpaved Road section including side ditch drains by means of mechaical equipment
Manual Line Ditch Cleaning (lined and Unlined)
vegetation Control
AS-STAKED PLAN
vegetation Control
AS-STAKED PLAN
Manual Patching for Unpaved Road Surface
Materials to resurface unpaved road by means of mechanical equip.
0+600
START
1+300
1+400
1+500
1+600
1+700
0+700
0+800
0+900
1+000
1+100
1+200
0+400
0+500
2+300
START
2+100
2+200
0+000
0+100
1+500
1+600
1+700
1+800
AS-STAKED PLAN
Manual Patching for Unpaved Road Surface
Materials to resurface unpaved road by means of mechanical equip.
Machine Grading for Unpaved Road section including side ditch drains by means of mechaical equipment
1+000
1+100
1+200
1+300
1+400
0+700
START
0+800
2+400
2+500
2+600
2+700
0+200
0+300
2+363.29
0+900
0+000
0+100
0+200
0+300
0+400
0+500
2+800
2+900
3+000
3+100
3+200
3+300
0+600
2+100
2+200
2+300
2+400
0+800
0+900
1+000
1+100
1+500
1+600
1+700
1+800
1+900
2+000
1+200
1+300
1+400
3+400
3+500
3+600
3+700
2+900
3+000
3+100
3+200
3+300
0+100
0+200
0+300
0+400
START
4+400
4+500
4+500
4+700
0+000
0+900
1+000
4+700
0+000
0+100
0+200
0+300
0+400
START
1+300
1+400
1+500
1+600
0+500
0+600
0+700
0+800
2+300
2+400
2+500
2+600
2+700
2+800
1+700
1+800
1+900
2+000
2+100
2+200
Manual Line Ditch Cleaning (lined and Unlined)
4+000
4+100
4+200
4+300
4+400
4+500
4+600
1+100
1+200
Sta. 0+0333cleanandmaintain
existing 1-line2.5m Ø RCBCSta. 1+750 clean and maintain
existing 2-line0.60m Ø RCPC
Sta. 4+062 clean and maintain
existing 1-line3.0m Ø RCPC
Sta. 0+567 clean and maintain
existing 3-barrel3.0m wideRCBC
Sta. 0+977 clean and maintain
existing 1-line0.90m Ø RCPC
Sta 2+363.29clean and maintain
existing 1-line0.45m Ø RCPC
Sta. 0+589.00clean andmaintain
existing 1-line0.60m Ø RCPC
Sta. 1+121.00clean andmaintain
existing 3 barrel3.00 m wide
Sta. 0+209.00clean andmaintain
existing 1-line1.20m Ø RCPC
Sta. 0+400.00clean andmaintain
existing 1 barrel2.00 m wide
Sta. 0+604.00clean andmaintain
existing 1 line .45mØ RCPC
Sta. 0+725.00clean andmaintain
existing 1 line.60m Ø RCPC
Sta. 0+925.00clean andmaintain
existing 1 line .60mØ RCPC
Sta. 316 cleanand maintain
existing RCPC
Sta. 521 cleanand maintain
existing RCPC
Sta. 1+276 clean and maintain
existing RCPC
Sta. 2+279 clean and maintain
existing RCPC
13
ESTIMATED DETAILED SCHEDULE PROJECTS
Estimated Detailed Schedule of Batch 1 Physical Works Projects
M ay Jun Jul A ug Sep Oct N o v D ec Jan F eb M ar A pr M ay Jun Jul A ug Sep Oct N o v D ec Jan F eb M ar A pr M ay Jun Jul A ug Sep Oct N o v D ec
PW-AKL-13-01 Malinao – Madalag Road RMI
Rebidding on-
going
14,430,325.97 13.65
F. Guerrea
Construction
222 13 - Sep 23-Apr 22-Apr
PW-AKL-13-02 Aklan Provincial Roads Package 1 MBC On-going 6,392,473.63 17.56
Pastrana Builders &
Supplies
365 1- Aug 31-Jul
PW-AKL-13-03
Cluster 2: Makato-Cayangwan-Libang Road,
Makato-Tugas-Hagachac Road, Makato-
Cajilo Road
MBC
For issuance of
NOA
5,241,151.38 9.23 365 27-Nov 27-Nov
PW-AKL-13-04 Cabangila-Angas-Palay-Camaci-Napti RMI
For issuance of
NTP
21,671,656.25 7.04 222 6-N o v 16-Jun 15-Jun
PW-AKL-13-05
Makato-calangcang-Agcawilan-San Ramon-
Banay-banay Road
RMI
Bid Submission /
Opening 12-11
8,903,374.26 8.28 277 11-D ec 14-Sep 13-Sep
Aklan
Length
(km)
Sub-Contractor
Duration
(Days)
2014 2015 2016
Province Project Code Provincial Road Sections Project Type Status Cost (Php)
2.33%
66.94%
C o lo r
Extension of Time
Defects liability period after RMI
Legend
Procurement activities completed/forthcoming
Contract implementation period
Maintenance period in 'RMI & Maintenance'
14
PROGRESS ACCOMPLISHMENT
AKLAN
PROJECT SUMMARY AS OF October 24, 2014
Amount
Php
RMI Maint. Total Days %
PW-AKL-13-002Numancia Joyao-Joyao Aliputos-
Ibao Lezo, Numancia-Badio-Albasan-
Navitas, Numancia-Dongon-Baybay-
Laguimbanua-Bubog-Albasan-
Laguimbanua East Bulwang Camanci
Sur; mabilo Briones Road
Pastrana
Builders
&
Supplies
Maintena
nce
17.74 km 1-Aug-14 31-Jul-15 365 365 6,259,807.76 100.00 44.53 48.43 3.90 44.53 48.43 3.90 85 23.29%
Slippage
(%)
Plan (%)
Project Code: Province/Road Sections
Contract
or
Contract
Type
Contract
Length
Contract Duration
Weight
(%)
Remarks
Start End
Calendar Days
Individual Accomplishment Overall Accomplishment
Plan (%)
Actual
(%)
Actual
(%)
Slippage
(%)
RMI only
Time elapsed
• Description of the table:
- The green tab is the project profile
- The yellow tab is the computation
15
PROJECT MONITORING
• Other Monitoring/Reporting Tools
- Weather Monitoring
- Rainfall Data Monitoring
16
PROJECT MONITORING
• Importance of weather/rainfall data
monitoring:
- During the unfavorable weather condition at site, this tools are
for requesting work suspensions and extension of time (EOT), if
necessary.
- A justification for the slippages incurred in the work
implementations
- An attachment of weekly and monthly progress reports
17
PROJECT MONITORING
• Weather Monitoring
18
PROJECT MONITORING
• Rainfall Data Monitoring
Gauge Station/location:
HOUR 1:00 2:00 3:00 4:00 5:00 6:00 7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00 24:00
DATE
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
MONTHLY RAINFALL READING
for the month of _____________, 2014
19
PROJECT MONITORING
• Rainfall Data Monitoring
A rain gauge is provided for the monitoring, however
for validation, may use the Philippine Real-Time
Environment Data Acquisition and Interpretation for
Climate-Related Tragedy Prevention and Mitigation
(PREDICT) and take note this:
- Rainfall reading is based on the Philippine Real-Time
Environment Data Acquisition and Interpretation for
Climate-Related Tragedy Prevention and Mitigation
(PREDICT) at ________________________ in
cooperation of three (3) government agencies: ASTI,
PAG-ASA and DOST.
20
PROJECT MONITORING
• PREDICT
LINK: http://fmon.asti.dost.gov.ph/weather/predict/
21
PROJECT MONITORING
• PREDICT
22
PROJECT MONITORING
• PREDICT
23
PROJECT MONITORING
• PREDICT
24
PROJECT MONITORING
• PREDICT
25
PROJECT MONITORING
• PREDICT
26
Maraming Salamat Po
27
28
• Straight Line Diagram (SLD) – preparation is
not only of the contractor but as well as the
CS Team to validate if the Contractor’s report
is realistic/factual.
PROJECT MONITORING SYSTEM
29
PROJECT MONITORING SYSTEM
• Progress accomplishment
- Physical is the accomplishment of items of
works done at site
- Billed is the accomplishment of items of works
already paid
30
STRAIGHT LINE DIAGRAM EXERCISE
• Exercises
- Formatting in excel format (user’s friendly
method)
- Data inputting based on the detailed quantity
calculations in the billing

More Related Content

Similar to PW project monitoring orientation

Planning track maintenance.ppt
Planning track maintenance.pptPlanning track maintenance.ppt
Planning track maintenance.pptAfendiAriff
 
Dragline Planning
Dragline PlanningDragline Planning
Dragline PlanningVR M
 
Proposed Methodology Shore Approach
Proposed Methodology  Shore ApproachProposed Methodology  Shore Approach
Proposed Methodology Shore ApproachMohd Zaini Baharum
 
Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.Hitesh Khanna
 
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, Rajasthan
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, RajasthanHDPE Pipes By Perfect Prime Piping & Agritech Private Limited, Rajasthan
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, RajasthanIndiaMART InterMESH Limited
 
Water pipe Lines Progress Planned Vs actual.pptx
Water pipe Lines  Progress Planned Vs actual.pptxWater pipe Lines  Progress Planned Vs actual.pptx
Water pipe Lines Progress Planned Vs actual.pptxDILIP KUMAR M.Tech (ACT)
 
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...Association for Project Management
 
Tabnak Drilling Management
Tabnak Drilling ManagementTabnak Drilling Management
Tabnak Drilling ManagementMojrian Web
 
Qa qc mech enggs or sr.qc inspector welding.piping.pipeline
Qa qc mech enggs or sr.qc inspector welding.piping.pipelineQa qc mech enggs or sr.qc inspector welding.piping.pipeline
Qa qc mech enggs or sr.qc inspector welding.piping.pipelineJOBY Joby.Stephan
 
CE Confr Presentation 08 Oct 2022.pptx
CE Confr Presentation 08 Oct 2022.pptxCE Confr Presentation 08 Oct 2022.pptx
CE Confr Presentation 08 Oct 2022.pptxSaketChandra4
 
. Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro....
.   Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro.....   Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro....
. Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro....IndraNathMishra2
 

Similar to PW project monitoring orientation (20)

Planning track maintenance.ppt
Planning track maintenance.pptPlanning track maintenance.ppt
Planning track maintenance.ppt
 
A SATTAR DC&WI CV-II
A SATTAR DC&WI CV-IIA SATTAR DC&WI CV-II
A SATTAR DC&WI CV-II
 
Dragline Planning
Dragline PlanningDragline Planning
Dragline Planning
 
Proposed Methodology Shore Approach
Proposed Methodology  Shore ApproachProposed Methodology  Shore Approach
Proposed Methodology Shore Approach
 
A SATTAR DC&WI CV-II
A SATTAR DC&WI CV-IIA SATTAR DC&WI CV-II
A SATTAR DC&WI CV-II
 
Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.
 
Metro Project
Metro ProjectMetro Project
Metro Project
 
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, Rajasthan
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, RajasthanHDPE Pipes By Perfect Prime Piping & Agritech Private Limited, Rajasthan
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, Rajasthan
 
Water pipe Lines Progress Planned Vs actual.pptx
Water pipe Lines  Progress Planned Vs actual.pptxWater pipe Lines  Progress Planned Vs actual.pptx
Water pipe Lines Progress Planned Vs actual.pptx
 
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
Keeping Wastewater Flowing while managing major capital works for NI Water, 9...
 
Tabnak Drilling Management
Tabnak Drilling ManagementTabnak Drilling Management
Tabnak Drilling Management
 
Rehab Solutions for Today's Infrastructure
Rehab Solutions for Today's InfrastructureRehab Solutions for Today's Infrastructure
Rehab Solutions for Today's Infrastructure
 
Capitulo 02 grupo 01
Capitulo 02 grupo 01Capitulo 02 grupo 01
Capitulo 02 grupo 01
 
Training PPT
Training PPTTraining PPT
Training PPT
 
Qa qc mech enggs or sr.qc inspector welding.piping.pipeline
Qa qc mech enggs or sr.qc inspector welding.piping.pipelineQa qc mech enggs or sr.qc inspector welding.piping.pipeline
Qa qc mech enggs or sr.qc inspector welding.piping.pipeline
 
CE Confr Presentation 08 Oct 2022.pptx
CE Confr Presentation 08 Oct 2022.pptxCE Confr Presentation 08 Oct 2022.pptx
CE Confr Presentation 08 Oct 2022.pptx
 
. Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro....
.   Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro.....   Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro....
. Narmada Canal ExPresentation for Extradose Bridge for Gandhi Nagar Metro....
 
Constant Springs Webinar - January
Constant Springs Webinar - JanuaryConstant Springs Webinar - January
Constant Springs Webinar - January
 
Submarine outfalls & intakes ppt
Submarine outfalls & intakes pptSubmarine outfalls & intakes ppt
Submarine outfalls & intakes ppt
 
SISCO - Presentation SABIC
SISCO - Presentation SABICSISCO - Presentation SABIC
SISCO - Presentation SABIC
 

PW project monitoring orientation

  • 1. Managed by PHYSICAL WORKS PROJECT MONITORING ORIENTATION
  • 2. 2 PROJECT MONITORING - In Construction Supervision, project monitoring is the procedures/methods wherein it involves work projection and accomplishment within the period of time specified in the contract agreement.
  • 4. 4 EMPHASIS ON MONITORING: PROJECT MONITORING MONITORING PROJECTION / PLAN ACCOMPLISHMENT SLIPPAGE / VARIANCE TIME REPORTING
  • 5. 5 PROJECT MONITORING • Project performance? • Completed structures/works? • Progress accomplishment? • Physical • Billable VALIDATE/MONITOR BY:
  • 6. 6 • Project performance - Compliance with - the Technical Specifications - the approved Methodology - the required documentation/reporting - Works ahead of schedule/plan - Quality Assurance (workmanship) PROJECT MONITORING
  • 7. 7 • Completed structures/works? - Reporting from the contractors needs to be validated and/or inspected by the CS Team - A straight line diagram can be used as tool for monitoring and validating reported completed as well as on-going site works PROJECT MONITORING
  • 8. 8 • Progress accomplishment? • Physical - This is the work of items completed at site subject for validation, testing and quality assurance • Billable - This is the work of items completed at site that are already validated, passed testing and quality assurance PROJECT MONITORING
  • 9. 9 • Progress accomplishment? • Physical - This is the work of items completed at site subject for validation, testing and quality assurance • Billable - This is the work of items completed at site that are already validated, passed testing and quality assurance PROJECT MONITORING
  • 10. 10 STRAIGHT LINE DIAGRAM – CAD FILES
  • 11. 11 STRAIGHT LINE DIAGRAM – EXCEL FILES Clearing and Grubbing Pipe Culvert and Drain Excavation Subgrade Preparation (existing Pavement) Aggregate Subbase Course Stone Masonry (Slope Protection) Sta. 4+940-5+000 Stone Masonry (Headwall and Line Ditch) Sta. 4+946-5+104 Existing Concrete Road Guardrails Sta. 4+250-4+265 Sta. 4+250-4+280 Sta. 4+450-4+465 Sta. 4+820-4+850 Legend: Proposed Plan Ongoing Completed Completed culvert 5+330 END 5+300 Provide lined ditch cover 4+900 5+000 5+100 5+200 4+200 4+300 4+400 4+500 4+800 Sta. 4+300-4+580 Sta. 4+680-4+720 Sta. 4+640-4+893 4+000 4+100 4+600 4+700 STA.4+000 - STA. 5+330 Sta5+024 existing 1-610mmØ x 6 m RCPC Remove and replaced1-910mm Ø x 8 m provide straight headwalls B/S Sta 4+400 InstallRCPC1-910 mm Ø x 8 m cross drain & provide straight headwallB/S Sta. 4+569.60existing 1 610mmØ x 6m RCPC Cleanand Maintain, ProvideStraight Sta. 4+760 InstallRCPC 1 910mmØ x 8m CRoss drain &provide straightheadwall B/S Sta. 4+760 InstallRCPC 1 910mmØ x 8m CRoss drain &provide straightheadwall B/S As of September 26, 2014 Clearing and Grubbing Pipe Culvert and Drain Excavation Subgrade Preparation (existing Pavement) Aggregate Subbase Course Stone Masonry (Slope Protection) Stone Masonry (Headwall and Line Ditch) Existing PCCP/Asphalt Guardrails Sta. 1+223-1+323 1+800 STRAIGHT LINE DIAGRAM FOR PW-BHL-13-005 0+100 0+200 0+300 0+400 0+500 0+600 0+700 0+900 0+800 0+000 STA. 0+000- STA. 2+000 START 1+900 2+000 1+400 1+500 1+600 1+000 1+100 1+200 1+300 1+700 Sta. 0+674 existing 1 410mmØ x 7m RCPC Clean andMaintain, Provide StraightHeadwallB/S Sta. 0+282 existing 1-410mmØ x 6 RCPC Clean and Maintain, Provide StraightHeadwallB/S Sta. 0+494 existing 1-610mmØ x m RCPC Clean andMaintain, Provide StraightHeadwallB/S Sta. 0+826.70existing 1 410mmØ x 6m RCPC Clean andMaintain, Provide StraightHeadwallB/S Sta. 1+223 existing 1 410mmØ x 6m RCPC Clean andMaintain, Provide StraightHeadwallB/S Sta. 1+800 existing 1 910mmØ x 8m RCPC ProvideStraight HeadwallB/S
  • 12. 12 STRAIGHT LINE DIAGRAM – EXCEL FILES MAINTENANCE OF AKLAN PROVINCIAL GRAVEL ROAD NUMAMCIA-JOYAO-JOYAO-ALIPUTOS-IBAO-LEZO ROAD NUMANCIA-BADIO-ALBASAN-NAVITAS SUR NUMANCIA-DUNGON-BAYBAY ROAD LAGUINBANUA-BOBOG-ALBASAN ROAD LAGUINBANUA EAST-BULWANG-CAMANCE SUR ROAD BRIDGE 4+743.51 BRIDGE 3+378.89 1+900 2+000 0+400 0+500 0+600 0+700 3+800 3+900 4+000 4+100 4+200 4+300 3+300 Existing Gravel 2+000 2+100 2+200 2+300 2+400 2+500 2+600 2+700 Existing PCCP 0+900 vegetation Control Manual Patching for Unpaved Road Surface Materials to resurface unpaved road by means ofmechanical equip. Machine Grading for Unpaved Road section including side ditch drains by means ofmechaical equipment Manual Line Ditch Cleaning (lined and Unlined) Machine Grading for Unpaved Road section including side ditch drains by means ofmechaical equipment Manual Line Ditch Cleaning (lined and Unlined) vegetation Control AS-STAKED PLAN vegetation Control AS-STAKED PLAN Manual Patching for Unpaved Road Surface Materials to resurface unpaved road by means ofmechanical equip. vegetation Control AS-STAKED PLAN Manual Patching for Unpaved Road Surface Materials to resurface unpaved road by means ofmechanical equip. Machine Grading for Unpaved Road section including side ditch drains by means ofmechaical equipment Manual Line Ditch Cleaning (lined and Unlined) Manual Patching for Unpaved Road Surface Materials to resurface unpaved road by means ofmechanical equip. Machine Grading for Unpaved Road section including side ditch drains by means ofmechaical equipment Manual Line Ditch Cleaning (lined and Unlined) Manual Patching for Unpaved Road Surface Materials to resurface unpaved road by means ofmechanical equip. Machine Grading for Unpaved Road section including side ditch drains by means ofmechaical equipment Manual Line Ditch Cleaning (lined and Unlined) Machine Grading for Unpaved Road section including side ditch drains by means ofmechaical equipment Manual Line Ditch Cleaning (lined and Unlined) vegetation Control AS-STAKED PLAN vegetation Control AS-STAKED PLAN Manual Patching for Unpaved Road Surface Materials to resurface unpaved road by means ofmechanical equip. 0+400 0+500 2+300 START 2+100 2+200 0+000 0+100 AS-STAKED PLAN Manual Patching for Unpaved Road Surface Materials to resurface unpaved road by means ofmechanical equip. Machine Grading for Unpaved Road section including side ditch drains by means ofmechaical equipment vegetation Control Manual Line Ditch Cleaning (lined and Unlined) AS-STAKED PLAN 1+500 1+600 1+700 1+800 vegetation Control AS-STAKED PLAN Manual Patching for Unpaved Road Surface Materials to resurface unpaved road by means ofmechanical equip. Machine Grading for Unpaved Road section including side ditch drains by means ofmechaical equipment 1+000 1+100 1+200 1+300 1+400 0+700 START 0+800 2+400 2+500 2+600 2+700 0+200 0+300 2+363.29 0+900 0+000 0+100 0+200 0+300 0+400 0+500 2+800 2+900 3+000 3+100 3+200 3+300 0+600 2+100 2+200 2+300 2+400 0+800 0+900 1+000 1+100 1+500 1+600 1+700 1+800 1+900 2+000 1+200 1+300 1+400 3+400 3+500 3+600 3+700 2+900 3+000 3+100 3+200 3+300 0+100 0+200 0+300 0+400 START 4+400 4+500 4+500 4+700 0+000 0+900 1+000 4+700 0+000 0+100 0+200 0+300 0+400 START 1+300 1+400 1+500 1+600 0+500 0+600 0+700 0+800 2+300 2+400 2+500 2+600 2+700 2+800 1+700 1+800 1+900 2+000 2+100 2+200 Manual Line Ditch Cleaning (lined and Unlined) 4+000 4+000 4+100 4+200 4+300 4+400 4+500 4+600 3+400 3+500 3+600 3+700 3+800 3+900 2+800 2+900 3+000 3+100 3+200 3+300 1+100 1+200 STRAIGHT LINE DIAGRAM 1+800 1+700 1+600 1+500 1+400 1+300 0+700 0+800 0+900 1+000 1+100 2+000 1+200 1+900 0+000 START 0+100 0+200 0+300 0+400 0+500 0+600 Sta. 0+664 clean and maintain existing 3-line1.20m Ø RCPC Sta2+547 clean and maintain existing 1-line1.50m Ø RCBC Sta 3+743.93clean and maintain existing 1-line0.60m Ø RCBC Sta. 0+0333cleanandmaintain existing 1-line2.5m Ø RCBCSta. 1+750 clean and maintain existing 2-line0.60m Ø RCPC Sta. 4+062 clean and maintain existing 1-line3.0m Ø RCPC Sta. 0+567 clean and maintain existing 3-barrel3.0m wideRCBC Sta. 0+977 clean and maintain existing 1-line0.90m Ø RCPC Sta 2+363.29clean and maintain existing 1-line0.45m Ø RCPC Sta. 0+209.00clean andmaintain Sta. 0+604.00clean andmaintain Sta. 316 cleanand maintain existing RCPC Sta. 521 cleanand maintain existing RCPC Sta. 1+276 clean and maintain existing RCPC Sta. 2+279 clean and maintain existing RCPC NUMANCIA-BADIO-ALBASAN-NAVITAS SUR NUMANCIA-DUNGON-BAYBAY ROAD LAGUINBANUA-BOBOG-ALBASAN ROAD LAGUINBANUA EAST-BULWANG-CAMANCE SUR ROAD MABILO-BRIONES ROAD Legend: Proposed Plan Ongoing Completed Completed culvert 1+266.15 1+100 1+200 0+400 0+500 0+600 0+700 0+700 0+800 0+900 1+000 0+300 BRIDGE 1+760.84 0+000 0+100 0+200 4+743.51 BRIDGE 3+378.89 1+900 2+000 0+400 0+500 0+600 0+700 3+800 3+900 4+000 4+100 4+200 4+300 3+300 Machine Grading for Unpaved Road section including side ditch drains by means of mechaical equipment Manual Line Ditch Cleaning (lined and Unlined) vegetation Control 0+9000+500 vegetation Control AS-STAKED PLAN Manual Patching for Unpaved Road Surface Materials to resurface unpaved road by means of mechanical equip. vegetation Control AS-STAKED PLAN Manual Patching for Unpaved Road Surface Materials to resurface unpaved road by means of mechanical equip. Machine Grading for Unpaved Road section including side ditch drains by means of mechaical equipment Manual Line Ditch Cleaning (lined and Unlined) Manual Patching for Unpaved Road Surface Materials to resurface unpaved road by means of mechanical equip. Machine Grading for Unpaved Road section including side ditch drains by means of mechaical equipment Manual Line Ditch Cleaning (lined and Unlined) Machine Grading for Unpaved Road section including side ditch drains by means of mechaical equipment Manual Line Ditch Cleaning (lined and Unlined) vegetation Control AS-STAKED PLAN vegetation Control AS-STAKED PLAN Manual Patching for Unpaved Road Surface Materials to resurface unpaved road by means of mechanical equip. vegetation Control AS-STAKED PLAN Manual Patching for Unpaved Road Surface Materials to resurface unpaved road by means of mechanical equip. Machine Grading for Unpaved Road section including side ditch drains by means of mechaical equipment Manual Line Ditch Cleaning (lined and Unlined) Manual Patching for Unpaved Road Surface Materials to resurface unpaved road by means of mechanical equip. Machine Grading for Unpaved Road section including side ditch drains by means of mechaical equipment Manual Line Ditch Cleaning (lined and Unlined) Machine Grading for Unpaved Road section including side ditch drains by means of mechaical equipment Manual Line Ditch Cleaning (lined and Unlined) vegetation Control AS-STAKED PLAN vegetation Control AS-STAKED PLAN Manual Patching for Unpaved Road Surface Materials to resurface unpaved road by means of mechanical equip. 0+600 START 1+300 1+400 1+500 1+600 1+700 0+700 0+800 0+900 1+000 1+100 1+200 0+400 0+500 2+300 START 2+100 2+200 0+000 0+100 1+500 1+600 1+700 1+800 AS-STAKED PLAN Manual Patching for Unpaved Road Surface Materials to resurface unpaved road by means of mechanical equip. Machine Grading for Unpaved Road section including side ditch drains by means of mechaical equipment 1+000 1+100 1+200 1+300 1+400 0+700 START 0+800 2+400 2+500 2+600 2+700 0+200 0+300 2+363.29 0+900 0+000 0+100 0+200 0+300 0+400 0+500 2+800 2+900 3+000 3+100 3+200 3+300 0+600 2+100 2+200 2+300 2+400 0+800 0+900 1+000 1+100 1+500 1+600 1+700 1+800 1+900 2+000 1+200 1+300 1+400 3+400 3+500 3+600 3+700 2+900 3+000 3+100 3+200 3+300 0+100 0+200 0+300 0+400 START 4+400 4+500 4+500 4+700 0+000 0+900 1+000 4+700 0+000 0+100 0+200 0+300 0+400 START 1+300 1+400 1+500 1+600 0+500 0+600 0+700 0+800 2+300 2+400 2+500 2+600 2+700 2+800 1+700 1+800 1+900 2+000 2+100 2+200 Manual Line Ditch Cleaning (lined and Unlined) 4+000 4+100 4+200 4+300 4+400 4+500 4+600 1+100 1+200 Sta. 0+0333cleanandmaintain existing 1-line2.5m Ø RCBCSta. 1+750 clean and maintain existing 2-line0.60m Ø RCPC Sta. 4+062 clean and maintain existing 1-line3.0m Ø RCPC Sta. 0+567 clean and maintain existing 3-barrel3.0m wideRCBC Sta. 0+977 clean and maintain existing 1-line0.90m Ø RCPC Sta 2+363.29clean and maintain existing 1-line0.45m Ø RCPC Sta. 0+589.00clean andmaintain existing 1-line0.60m Ø RCPC Sta. 1+121.00clean andmaintain existing 3 barrel3.00 m wide Sta. 0+209.00clean andmaintain existing 1-line1.20m Ø RCPC Sta. 0+400.00clean andmaintain existing 1 barrel2.00 m wide Sta. 0+604.00clean andmaintain existing 1 line .45mØ RCPC Sta. 0+725.00clean andmaintain existing 1 line.60m Ø RCPC Sta. 0+925.00clean andmaintain existing 1 line .60mØ RCPC Sta. 316 cleanand maintain existing RCPC Sta. 521 cleanand maintain existing RCPC Sta. 1+276 clean and maintain existing RCPC Sta. 2+279 clean and maintain existing RCPC
  • 13. 13 ESTIMATED DETAILED SCHEDULE PROJECTS Estimated Detailed Schedule of Batch 1 Physical Works Projects M ay Jun Jul A ug Sep Oct N o v D ec Jan F eb M ar A pr M ay Jun Jul A ug Sep Oct N o v D ec Jan F eb M ar A pr M ay Jun Jul A ug Sep Oct N o v D ec PW-AKL-13-01 Malinao – Madalag Road RMI Rebidding on- going 14,430,325.97 13.65 F. Guerrea Construction 222 13 - Sep 23-Apr 22-Apr PW-AKL-13-02 Aklan Provincial Roads Package 1 MBC On-going 6,392,473.63 17.56 Pastrana Builders & Supplies 365 1- Aug 31-Jul PW-AKL-13-03 Cluster 2: Makato-Cayangwan-Libang Road, Makato-Tugas-Hagachac Road, Makato- Cajilo Road MBC For issuance of NOA 5,241,151.38 9.23 365 27-Nov 27-Nov PW-AKL-13-04 Cabangila-Angas-Palay-Camaci-Napti RMI For issuance of NTP 21,671,656.25 7.04 222 6-N o v 16-Jun 15-Jun PW-AKL-13-05 Makato-calangcang-Agcawilan-San Ramon- Banay-banay Road RMI Bid Submission / Opening 12-11 8,903,374.26 8.28 277 11-D ec 14-Sep 13-Sep Aklan Length (km) Sub-Contractor Duration (Days) 2014 2015 2016 Province Project Code Provincial Road Sections Project Type Status Cost (Php) 2.33% 66.94% C o lo r Extension of Time Defects liability period after RMI Legend Procurement activities completed/forthcoming Contract implementation period Maintenance period in 'RMI & Maintenance'
  • 14. 14 PROGRESS ACCOMPLISHMENT AKLAN PROJECT SUMMARY AS OF October 24, 2014 Amount Php RMI Maint. Total Days % PW-AKL-13-002Numancia Joyao-Joyao Aliputos- Ibao Lezo, Numancia-Badio-Albasan- Navitas, Numancia-Dongon-Baybay- Laguimbanua-Bubog-Albasan- Laguimbanua East Bulwang Camanci Sur; mabilo Briones Road Pastrana Builders & Supplies Maintena nce 17.74 km 1-Aug-14 31-Jul-15 365 365 6,259,807.76 100.00 44.53 48.43 3.90 44.53 48.43 3.90 85 23.29% Slippage (%) Plan (%) Project Code: Province/Road Sections Contract or Contract Type Contract Length Contract Duration Weight (%) Remarks Start End Calendar Days Individual Accomplishment Overall Accomplishment Plan (%) Actual (%) Actual (%) Slippage (%) RMI only Time elapsed • Description of the table: - The green tab is the project profile - The yellow tab is the computation
  • 15. 15 PROJECT MONITORING • Other Monitoring/Reporting Tools - Weather Monitoring - Rainfall Data Monitoring
  • 16. 16 PROJECT MONITORING • Importance of weather/rainfall data monitoring: - During the unfavorable weather condition at site, this tools are for requesting work suspensions and extension of time (EOT), if necessary. - A justification for the slippages incurred in the work implementations - An attachment of weekly and monthly progress reports
  • 18. 18 PROJECT MONITORING • Rainfall Data Monitoring Gauge Station/location: HOUR 1:00 2:00 3:00 4:00 5:00 6:00 7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00 24:00 DATE 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 MONTHLY RAINFALL READING for the month of _____________, 2014
  • 19. 19 PROJECT MONITORING • Rainfall Data Monitoring A rain gauge is provided for the monitoring, however for validation, may use the Philippine Real-Time Environment Data Acquisition and Interpretation for Climate-Related Tragedy Prevention and Mitigation (PREDICT) and take note this: - Rainfall reading is based on the Philippine Real-Time Environment Data Acquisition and Interpretation for Climate-Related Tragedy Prevention and Mitigation (PREDICT) at ________________________ in cooperation of three (3) government agencies: ASTI, PAG-ASA and DOST.
  • 20. 20 PROJECT MONITORING • PREDICT LINK: http://fmon.asti.dost.gov.ph/weather/predict/
  • 27. 27
  • 28. 28 • Straight Line Diagram (SLD) – preparation is not only of the contractor but as well as the CS Team to validate if the Contractor’s report is realistic/factual. PROJECT MONITORING SYSTEM
  • 29. 29 PROJECT MONITORING SYSTEM • Progress accomplishment - Physical is the accomplishment of items of works done at site - Billed is the accomplishment of items of works already paid
  • 30. 30 STRAIGHT LINE DIAGRAM EXERCISE • Exercises - Formatting in excel format (user’s friendly method) - Data inputting based on the detailed quantity calculations in the billing

Editor's Notes

  1. What is the relation of monitoring to reporting? It varies with each other. Monitor then report, report is based in the monitoring=factual reporting What are the benefits/importance of monitoring for reporting? Can produce factual reporting Can prevent enormous problem, because of updating can figure out problems and solutions Can achieve targets schedule
  2. Under contract management guidelines 4.2 Document Control, Page 8
  3. (PREDICT is a nationwide system that is meant to complement the existing observation capability of PAGASA. It consists of a network of automated weather stations that gather and transmit observation data to a central server through the cellular network. Each observation station is a rugged device equipped with sensor for the various required parameter such as temperature, pressure, humidity, wind directions, wind speed and rainfall. It is also equipped with a GSM/GPRS modem to transmit data to the central server.)
  4. Under contract management guidelines 4.2 Document Control, Page 8
  5. This will be hyperlink to blank Microsoft excel with a hardcopy of the SLD cad files for exercises.