This document summarizes quality control and site execution activities on a construction project. It includes 3 sections:
1. Quality control testing results like cube tests showing the concrete met the required compressive strength. Lab tests were performed for mix design, slump, and compressive strength.
2. Details of site execution activities for different construction elements like pile foundations, coupling beams, slabs, and formwork installation. Labour productivity rates for different crews are provided.
3. Material consumption data is summarized showing wastage rates for curing compound and grout were higher than expected, suggesting issues with workmanship. Suggestions are provided to address these issues through better work planning and resource coordination.
4. 4
Quality Department
1. Quality assurance and quality control
2. Concrete mix design
3. Lab test
4. Cube test results
5. RMC plant
5. 5
Quality Assurance And Quality Control
1. For quality assurance we have checklist, Quality plan in our QMS,
QMS works as a tool for our quality assurance.
2. For quality control we do conduct lab test and various materials gets tested there
at frequent intervals of time.
24. 24
MATERIAL CONSUMPTION RECONCILATION REPORT
CURING COMPOUND
SURFACE AREA COVERAGE FOR CURING
COMPOND(THEORETICAL)(SQM/LT)
7
SURFACE AREA COVERAGE FOR CURING
COMPOND(PRACTICAL)(SQM/LT)
12
WASTAGE(%) -71.4
26. 26
SUGGESTIONS
1. Need to look upon curing compound application
(70% less application as compared to data given by manufacturer)
Poor workmanship issue.
2. Some kind of app (spread sheet or Google forms ) for better use of resources like crane,
(in which like everyone needed to use it has to quote date and time,
for which it is required, and in app showing is it available or not, & hence plan accordingly)