Preparation of Digital Route Sheet of Regional Over-Head & Sub-Station Network.
This project was aimed to provide computer aided Geographical placed Over-Head-Mains,Sub-Staions,PMTs & RMUs for Planning,Development and Maintenance purpose.I was directly reporting to GM Mr Riffat Ali
2- Preparation of Digital Route Sheet Of Regional Under-Ground-Cable Network
This Project was aimed to draw computer aided Under-Ground Network for Planning,Development and maintenance purpose. I was directly reporting to GM Mr Riffat Ali.
1. WHY DIGITAL ROUTE SHEET AND
NETWORK ON DIGITAL MAP
•CABLE ROUTE SHEET IS ESSENTIAL PART
OF HT NETWORK AND IT IS REQUIRED TO
KEEP RECORD OF UNDERGROUND ASSETS
OF KESC
MAIN CABLE
LINK CABLE
LT CABLES
2. WHY DIGITAL ROUTE SHEET AND
NETWORK ON DIGITAL MAP
•WITHOUT ROUTE SHEET, FAULTS ON
UNDERGROUND CABLES CAN’T BE LOCATED.
3. WHYIDEA OF DIGITAL ROUTE SHEET AND
NETWORK ON DIGITAL MAP CONCEIVED
In R-4 route sheet were outdated. 70 % route sheets of Main
cables were not available. 30% were outdated
100% link cable route sheet were not available.
Without route sheet fault rectifications are delayed as only
experienced persons can locate cable routes.
4. Digital Route Sheet with HT Network is a
PLANING TOOL
Being the Map on True Scale it is used as a Planning Tool for
addition and alteration in HT Network and for laying of new
feeders. Required material may be conceived from Map
scale. Different route for laying underground cable or over
head may be analyzed for least material required.
5. •TASK WAS ASSIGNED TO ENGR. PERVAIZ IQBAL
TO COMPLETE “DIGITAL ROUTE SHEET” IN JUNE
2010.
•FIRST PHASE WAS STARTED ON 10TH
AUGUST
2010.
PROJECT OF DIGITAL ROUTE
SHEETS
6. 1ST
PHASE: COMPLETION OF 256 MC ROUTE SHEET DT
20-02-2011.
2ND
PHASE: POSTING OF PMTS/SUBSTATIONS DT 30TH
SEPT 2011.
3RD
PHASE: COMPLETION OF 100% LINK CABLE DT 30TH
NOV 2011.
1ST
PHASE INAUGURATION BY DR. NAVEED AHMED
DEO-II 0N 23-02-11.
PROJECT OF DIGITAL ROUTE
SHEETS
7. PROJECT TEAM
Project Leader:
Muhammad Pervaiz Iqbal
Team Members:
Abid Jamshed Siddiqi Ameer Ahmed
Jamshed Raza Syed Azam Ali
Qazi Ahmed Saleem Muhammad Anis (Late)
Tuseef Ahmed Khan Rafey
Hassan Yar Khan M. Rafique
Afaq Ahmed Tahir
Khalid Rafeh Shams
Muhammad Azeem Mukhtar
Abdul Rasheed Manzoor
9. •PROPOSALS OF FEEDER FROM HOSPITAL GRID STATION
WERE PLANNED THROUGH DIGITAL RS AND SAVING 2KM HT
CABLE ACHIEVED.
•HT CABLE LENGTH OF EXISTING CABLE LINK CABLE HAS
REDUCED.
•LENGTH OF EXISTING FEEDER AND LINK CABLES
CALCULATED ON DRS.
•BETTER FAULT RECTIFICATION PLANNING.
Utilization
10. FOR REGION WE NEED FOLLOWINGS
• 1 X LAPTOP COMPUTERS
• 1 X AE / AM AWARE OF AUTO CAD
• LICENSED AUTOCAD SOFTWARE
Requirements TO LAUNCH
DIGITAL NETWORK IN OTHER
REGIONS