Fulham Reach Block G Risk Review
Presentation
Presented by: Mark Platten – Senior Project Manager &
David Dicker – Group Health, Safety & Environment Manager
SEE Group Companies
Presentation Overview
Contents
• Company Overview
• Typical Systems
• Our approach
• Safe Systems of Work
• Nominated Persons
• Safe Isolation
• Permit to Work
• Pressure Testing
• Live Working
• Hot Works
• COSHH
• House Keeping
• Site Inspections
• Working at Height
• Accreditations
Company Overview
• 1981 - Founded as South Eastern Electrical Ltd.
• 2010 - Company rebranded as SEE.
• 2011 – SES formed.
• 2011 - Introduction of ‘In house’ Mechanical Division.
• 2012 – SEE acquire PBM Construction.
• 2012 – SER established – Renewable and Sustainable energy.
• 2014 – SEE Rail Division
Typical Apartments Services
Typical Apartment Lighting Layout
Typical Apartment Small Power
Layout
Typical Apartments Air Services
Typical Floor LTHW System
Typical Floor Domestic Water System
Typical Floor MAOV System
Our Approach
• Dedicated on site Mechanical & Electrical Project Managers
• Focused on Safety
• Daily / Task Specific Safe Start Briefings for all operatives
• Robust Safe Working Rules Mechanical & Electrical
• Self delivery through our network of engineers
• Management against agreed KPI’s
• Regular reporting
• Pro-active approach to Health and Safety, Environment & Quality
Our Approach
Safe Start Team Briefing Form
Safe Start Team Briefing Form
Safe Systems of Work
• SEE Electrical Safe Working Rules.
• SEE Mechanical Safe Working Rules.
Nominated Persons
• EACH OPERATING SITE IS TO PRODUCE A LIST OF NOMINATED PERSONS
• NOMINATED PERSONS WILL HAVE RECEIVED INSTRUCTION AND HAVE
BEING ASSESSED TO BE COMPETENT
• Every contract requires a nominated person to be Authorised in writing by
his Department Director.
• As ANP they will receive:
• Letter detailing duties, duration, site*
• Copy SEE Plc. Safe Working Rules
*The letter gives Authorisation for the named site only.
Safe Isolation
• Check isolator disconnects all supplies
• Check alternative sources of supply (where applicable)
• Isolator to be locked off and key held by ANP (Key Safe)
• Where there is no facility to lock off fuses or links may be removed and
held by ANP (Key Safe)
• Warning notices must be displayed (Cation Notice)
• PROVE ALL CONDUCTORS DEAD with appropriate test instrument BEFORE touching.
• Danger Notice to be displayed on all LIVE Equipment.
SAFE SYSTEMS OF WORK
Two Safe Systems of Work to be used for both
mechanical and electrical works:-
1. TAGOUT SYSTEM
LOW RISK WORK
2. PERMIT SYSTEM
HIGH RISK WORK
can also be used for low risk work
TAGOUT & PERMIT SYSTEM
SSW S.06/1 – Tagout Procedures
TB/01/906 - Safety Padlock Policy.
Note :- Safety locks are coloured Red and
have a single unique key and are
used solely for isolation purposes.
TAGOUT PROCEDURES
• Tagout is to be used for local isolation and
short duration work only.
• The Competent Person (CP) personally holds
the isolation keys.
+
PERMIT SYSTEM
• The work is under the control of the required Authorised
Person (AP), electrical, confined spaces etc.
• The works are carried out in accordance with the relevant
Safety Rules.
• The AP carries out the high risk Risk Assessment
• And issues the Safety Documentation
• Safety Lock(s) (red) or Caution Tape + Caution Sign(s) are
used.
• Isolation keys are locked in a Key Safe (or other secure
place). Under control of the ANP
EQUIPMENT THAT MUST BE USED WITH THE PERMIT
SYSTEM
PERMIT SYSTEM
+ +
Safety Rules Specific Risk Assessment Safety Lock
+ + +
Caution sign Safety Key Box Permit to Work
HIGH RISK ACTIVITIES ARE CLASSIFIED AS:-
• Live Working (Pressure Systems, Electrical, Gas).
• Confined Spaces.
• Other Hazardous Areas.
• High Voltage (at or greater than 1000V).
• Low Voltage Main Intake Switches, Switchboards and Equipment
having two or more sources of supply, plus cables and other
equipment on the supply side of the Main Intake Switch.
• Pressure Systems.
• Gas Systems above a nominal 21 mbar.
• LPG Systems above a nominal 37 mbar.
Locking Off
Example: Locking Circuit Breakers
MCB’ & MCCB’s
Use of proprietary locking off devices
Example:
Multiple Isolations / Rotary Isolators
Signage
Safe Isolation & Permit to Work Flow Chart
Sequence for proving Dead
• Prove Voltage Indicator on a known source or with a proving
unit.
• Test all conductors which are to be worked on including the
Neutral.
• Retest the Voltage Indicator after testing each conductor.
Voltage Indicator & Proving Unit
Sequence for proving Dead
• ISOLATE AT ALL SOURCES OF SUPPLY
• LOCK OFF AND FIT SIGNS
• PROVE DEAD
• ISSUE PERMIT AT POINT OF WORK
Work Permit Demarcation
Permit to Work
SEE
Electrical Permit to Work
Page 1
Authorisation.
Permit to Work
SEE
Electrical Permit to Work
Page 2
Receipt & Declaration
Permit to Work
SEE
Electrical Permit to Work
Page 3
Cancellation & Clearance
Energisation Procedure
Request for Energisation of Equipment
SEE
Request for Initial
Energisation of
Equipment or Systems
Request for Isolation of Equipment
SEE
Request for Isolation of
Equipment or Systems
Pressure Testing
Pneumatic & Hydraulic Testing of services pipework
SAFE METHOD OF WORK
• Inform the Site Manager or their representative of the works to be carried out
• Check that the work area is clear for the work to commence.
• Brief the work team of the works to be carried out and sign the briefing sheet
attached.
• Cordon off the work area to prevent unauthorised access.
• ENSURE WARNING SIGNAGE IS POSTED THROUGHOUT THE TEST AREA
Pressure Testing
Pneumatic Testing (Air Test)
• Check that the work area is clear for the work to commence. A site-specific / task specific risk assessment must be carried out prior to
the work commencing using form FM/H&S/RISK/02. Where indicated on the risk assessment a separate manual handling risk
assessment may be required. If so use form FM/HSE/RISK/03
• Put into place any ‘control or additional control measures’ indicated on the risk assessment.
• Place Pressure testing warning signs in the location to warn others of the testing in progress and to set up Exclusion zones and time
when tests can be carried out will be agreed on site with St. George and implemented. This will be a dynamic process and under
constant review
• Connect test manifold to the steel and plastic pipework. NOTE: Ensure the test manifold components are rated above the test pressure
• Check all isolation valves where fitted are in the open position.
• Install a secondary vent valve as a backup and plug the valve. NOTE: Ensure it is rated above the test pressure
• Fill the system
• Bring the system up to 0.5 bar pressure and close the valve
• Check for air leaks and observe the pressure gauge for 15 Minute’s
• Bring the system up to the test pressure & disconnect the compressor.
• After 1 hour (or as required by the specification) check for pressure drop and if satisfactory obtain signoff from the client using
appropriate QA forms.
• A controlled evacuation of the air using the valve will discharge the pressure Eye & Hearing protection must be worn.
• If the system lets buy then the engineer will test with a leak detector spray (soapy water) on joints to establish the leak, then retested
as above.
• All valves to be left in the open position
• Clear the area and leave in a safe condition.
Pressure Testing
Hydraulic Testing (Water Test)
• Check that the work area is clear for the work to commence. A site-specific / task specific risk assessment must be carried out prior to the work
commencing using form FM/H&S/RISK/02. Where indicated on the risk assessment a separate manual handling risk assessment may be required. If
so use form FM/HSE/RISK/03
• Put into place any ‘control or additional control measures’ indicated on the risk assessment.
• Place Pressure testing warning signs in the location to warn others of the testing in progress and to Set up Exclusion zones and time when tests can
be carried out will be agreed on site with St George and implemented. This will be a dynamic process and under constant review
• Connect test manifold to the steel pipework.
• Check all isolation valves where fitted are in the open position.
• Install a secondary vent valve as a backup and plug the valve.
• Fill the system with water ensuring all air is vented out before testing
• NOTE: When using water for pressure testing ensure that the system is properly vented before pressurisation.
• Testing should always start by applying a low pressure (below safe operating limits) to verify initial integrity of the system.
• Bring the system up to 2 bar pressure and close the valve
• Check for water leaks and observe the pressure gauge for 15 Minute’s
• Raise the test pressure in stages (holding the pressure for a period of time) to reduce the potential energy release resulting from failure of the
assembly and associated components under test.
• Bring the system up to the test pressure & disconnect the hydraulic pump.
• After 1 hour (or as required by the specification) check for pressure drop and if satisfactory obtain signoff from the client using appropriate QA forms.
• A controlled evacuation of the water using the valve will discharge the pressure to a suitable drain Eye protection must be worn.
• If the system lets buy then the engineer will look for leaks on joints to establish the leak, then retested as above.
• All valves to be left in the open position or the system left filled with water as required.
• Clear the area and leave in a safe condition.
Pressure Testing
LIVE WORKING
EXCEPTIONAL CIRCUMSTANCES
THE FOLLOWING SAFEGUARDS ARE REQUIRED
Risk Assessment by Authorised Nominated Person
Authorised by Senior Project Manager & Group SHEQ Manager
• Training
• Information
• Tools
• Barriers/Screens
• Test probes
• Accompaniment
• Product Testing Area
• Effective Control
Hot Works
• Hot Works Permit Required for;
• VRV pipework brazing.
• Gas pipework welding.
• Fire Extinguisher issued.
• 1hr. Fire Watch period after hot works
suspended.
• Close out of Hot Works Permit.
Hot Works Mitigation
• Cold cut wheels to be used on site.
• LTHW Pipework will be Crimped Copper.
• BCW Pipework will be Crimped Copper &
Plastic.
Hot Works
COSHH
Typical COSHH Assessment
House Keeping
• All access routes to be kept clear at all times,
free from trailing leads, materials, tools etc.
• All work areas to be tidied as the task is done.
• All work areas to be cleared of waste materials
& tools and left in a clean and tidy condition.
• Trailing leads to be clipped up to avoid trip
hazards. (SKY HOOK).
Site Inspection
Working at Height
We operate a simple hierarchy for managing & selecting
equipment for work at height.
a) avoid work at height where they can;
b) use work equipment or other measures to prevent falls where
they cannot avoid working at height; and
c) Where they cannot eliminate the risk of a fall, use work
equipment or other measures to minimise the distance and
consequences of a fall should one occur.
Working at Height
Line Managers as ‘Duty holders’ are required to ensure:
a) all work at height is properly planned and organised;
b) all work at height takes account of weather conditions that
could endanger health and safety;
c) those involved in work at height are trained and competent;
d) the place where work at height is done is safe;
e) equipment for work at height is appropriately inspected;
f) the risks from fragile surfaces are properly controlled; and
g) the risks from falling objects are properly controlled.
Working at Height
Access Equipment
Podium Steps Stair Access Tower Insulated Step Ladder
For Short Duration
Light Duties Only
Work at Height
Podium
Steps
Inspection Record
WARNING
Unlawful removal or interference with
this sign could make you liable to
PROSECUTION AND FINES
Authorised Person:
Date Signed
All podium steps, access
equipment must be inspected at
the time of erection, by a
competent person & signed off for
safe use.
An inspection by a competent
person must be carried out on a
weekly basis and the “Scaff Tag”
signed and dated.
The equipment must be visually
inspected and the “Scaff Tag”
checked for the last inspection
date to ensure it is in date before
each use.
Health and Safety
Behavioural
Safe Systems
Training
Intervention
Benchmark
FOCUSED ON SAFETY
Accreditations

More Related Content

What's hot

Electrical Safety for the Non-Electrical Skilled Worker by EFCOG
Electrical Safety for the Non-Electrical Skilled Worker by EFCOGElectrical Safety for the Non-Electrical Skilled Worker by EFCOG
Electrical Safety for the Non-Electrical Skilled Worker by EFCOGAtlantic Training, LLC.
 
Electrical Safety in Construction by South Carolina State Association
Electrical Safety in Construction by South Carolina State AssociationElectrical Safety in Construction by South Carolina State Association
Electrical Safety in Construction by South Carolina State AssociationAtlantic Training, LLC.
 
Arc Flash as it Relates to AC Drives
Arc Flash as it Relates to AC DrivesArc Flash as it Relates to AC Drives
Arc Flash as it Relates to AC DrivesFlow-Tech, Inc.
 
2015 Arc Flash Conference MV Switchgear Standards
2015 Arc Flash Conference MV Switchgear Standards2015 Arc Flash Conference MV Switchgear Standards
2015 Arc Flash Conference MV Switchgear StandardsBryan Johnson
 
High Voltage Design and Installations Master Class
High Voltage Design and Installations Master ClassHigh Voltage Design and Installations Master Class
High Voltage Design and Installations Master ClassLiving Online
 
Pd Maintenance
Pd MaintenancePd Maintenance
Pd Maintenancedwessin
 
A Review Comprehension: Guideline for Testing of HV, EHV and UHV Substation E...
A Review Comprehension: Guideline for Testing of HV, EHV and UHV Substation E...A Review Comprehension: Guideline for Testing of HV, EHV and UHV Substation E...
A Review Comprehension: Guideline for Testing of HV, EHV and UHV Substation E...IRJET Journal
 
MM Electrical Safety Policy-Procedure draft 2
MM Electrical Safety Policy-Procedure draft 2MM Electrical Safety Policy-Procedure draft 2
MM Electrical Safety Policy-Procedure draft 2Benjamin Canaday
 
Permit to work training
Permit to work trainingPermit to work training
Permit to work trainingKarnav Rana
 
Practical HV and LV Switching Operations and Safety Rules
Practical HV and LV Switching Operations and Safety RulesPractical HV and LV Switching Operations and Safety Rules
Practical HV and LV Switching Operations and Safety RulesLiving Online
 
Benefits of using iec 61439 standard in electrical busbar systems
Benefits of using iec 61439 standard in electrical busbar systemsBenefits of using iec 61439 standard in electrical busbar systems
Benefits of using iec 61439 standard in electrical busbar systemsMessung Electrical Engineering
 
Arc Flash Safety by Murray State University
Arc Flash Safety by Murray State UniversityArc Flash Safety by Murray State University
Arc Flash Safety by Murray State UniversityAtlantic Training, LLC.
 
Arc Flash Calculations What Does It All Mean
Arc Flash Calculations What Does It All MeanArc Flash Calculations What Does It All Mean
Arc Flash Calculations What Does It All MeanB Bhargav Reddy
 
Practical Electrical Wiring Standards - National Rules for Electrical Install...
Practical Electrical Wiring Standards - National Rules for Electrical Install...Practical Electrical Wiring Standards - National Rules for Electrical Install...
Practical Electrical Wiring Standards - National Rules for Electrical Install...Living Online
 

What's hot (19)

Electrical Safety for the Non-Electrical Skilled Worker by EFCOG
Electrical Safety for the Non-Electrical Skilled Worker by EFCOGElectrical Safety for the Non-Electrical Skilled Worker by EFCOG
Electrical Safety for the Non-Electrical Skilled Worker by EFCOG
 
Electrical Safety in Construction by South Carolina State Association
Electrical Safety in Construction by South Carolina State AssociationElectrical Safety in Construction by South Carolina State Association
Electrical Safety in Construction by South Carolina State Association
 
Arc Flash as it Relates to AC Drives
Arc Flash as it Relates to AC DrivesArc Flash as it Relates to AC Drives
Arc Flash as it Relates to AC Drives
 
shock_arc_flash
shock_arc_flashshock_arc_flash
shock_arc_flash
 
2015 Arc Flash Conference MV Switchgear Standards
2015 Arc Flash Conference MV Switchgear Standards2015 Arc Flash Conference MV Switchgear Standards
2015 Arc Flash Conference MV Switchgear Standards
 
High Voltage Design and Installations Master Class
High Voltage Design and Installations Master ClassHigh Voltage Design and Installations Master Class
High Voltage Design and Installations Master Class
 
Pd Maintenance
Pd MaintenancePd Maintenance
Pd Maintenance
 
A Review Comprehension: Guideline for Testing of HV, EHV and UHV Substation E...
A Review Comprehension: Guideline for Testing of HV, EHV and UHV Substation E...A Review Comprehension: Guideline for Testing of HV, EHV and UHV Substation E...
A Review Comprehension: Guideline for Testing of HV, EHV and UHV Substation E...
 
Permit to work
Permit to workPermit to work
Permit to work
 
Electrical Safety Training by ISRI
Electrical Safety Training by ISRIElectrical Safety Training by ISRI
Electrical Safety Training by ISRI
 
MM Electrical Safety Policy-Procedure draft 2
MM Electrical Safety Policy-Procedure draft 2MM Electrical Safety Policy-Procedure draft 2
MM Electrical Safety Policy-Procedure draft 2
 
Permit to work training
Permit to work trainingPermit to work training
Permit to work training
 
Practical HV and LV Switching Operations and Safety Rules
Practical HV and LV Switching Operations and Safety RulesPractical HV and LV Switching Operations and Safety Rules
Practical HV and LV Switching Operations and Safety Rules
 
SIL in de praktjk (functional Safety)
SIL in de praktjk (functional Safety)SIL in de praktjk (functional Safety)
SIL in de praktjk (functional Safety)
 
Benefits of using iec 61439 standard in electrical busbar systems
Benefits of using iec 61439 standard in electrical busbar systemsBenefits of using iec 61439 standard in electrical busbar systems
Benefits of using iec 61439 standard in electrical busbar systems
 
Arc Flash Safety by Murray State University
Arc Flash Safety by Murray State UniversityArc Flash Safety by Murray State University
Arc Flash Safety by Murray State University
 
Abraham CV 03.06.2015
Abraham CV 03.06.2015Abraham CV 03.06.2015
Abraham CV 03.06.2015
 
Arc Flash Calculations What Does It All Mean
Arc Flash Calculations What Does It All MeanArc Flash Calculations What Does It All Mean
Arc Flash Calculations What Does It All Mean
 
Practical Electrical Wiring Standards - National Rules for Electrical Install...
Practical Electrical Wiring Standards - National Rules for Electrical Install...Practical Electrical Wiring Standards - National Rules for Electrical Install...
Practical Electrical Wiring Standards - National Rules for Electrical Install...
 

Similar to Fulham Reach Block G Risk Review Presentation For review

WSM Yard-High-Pressure Safety-22.12.19
WSM Yard-High-Pressure Safety-22.12.19WSM Yard-High-Pressure Safety-22.12.19
WSM Yard-High-Pressure Safety-22.12.19SARWAR SALAM
 
R1_Project - QC Safety System
R1_Project - QC Safety SystemR1_Project - QC Safety System
R1_Project - QC Safety SystemBhupendra Meher
 
Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)SAJJAD KHUDHUR ABBAS
 
Are you at Risk? The Role of Lockout/Tagout in Pneumatic Safety
Are you at Risk? The Role of Lockout/Tagout in Pneumatic SafetyAre you at Risk? The Role of Lockout/Tagout in Pneumatic Safety
Are you at Risk? The Role of Lockout/Tagout in Pneumatic SafetyDesign World
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updatedPersonal Secret
 
Boiler recommissioning procedure after capital overhaul
Boiler recommissioning procedure after capital overhaul Boiler recommissioning procedure after capital overhaul
Boiler recommissioning procedure after capital overhaul Manohar Tatwawadi
 
SubstationCommissioning.pdf
SubstationCommissioning.pdfSubstationCommissioning.pdf
SubstationCommissioning.pdfAnithaSyam
 
Operation and maintanance
Operation and maintananceOperation and maintanance
Operation and maintananceAnasMirza10
 
Safe Isolation Procedure
Safe Isolation ProcedureSafe Isolation Procedure
Safe Isolation Proceduretotalpeople
 
Installation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersInstallation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersLiving Online
 

Similar to Fulham Reach Block G Risk Review Presentation For review (20)

WSM Yard-High-Pressure Safety-22.12.19
WSM Yard-High-Pressure Safety-22.12.19WSM Yard-High-Pressure Safety-22.12.19
WSM Yard-High-Pressure Safety-22.12.19
 
Piping hydrotest
Piping hydrotestPiping hydrotest
Piping hydrotest
 
R1_Project - QC Safety System
R1_Project - QC Safety SystemR1_Project - QC Safety System
R1_Project - QC Safety System
 
SD.pptx
SD.pptxSD.pptx
SD.pptx
 
Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION
 
Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)
 
Are you at Risk? The Role of Lockout/Tagout in Pneumatic Safety
Are you at Risk? The Role of Lockout/Tagout in Pneumatic SafetyAre you at Risk? The Role of Lockout/Tagout in Pneumatic Safety
Are you at Risk? The Role of Lockout/Tagout in Pneumatic Safety
 
Technician Training: Safety basics
Technician Training: Safety basicsTechnician Training: Safety basics
Technician Training: Safety basics
 
MET 214 Module 6
MET 214 Module 6MET 214 Module 6
MET 214 Module 6
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updated
 
Boiler recommissioning procedure after capital overhaul
Boiler recommissioning procedure after capital overhaul Boiler recommissioning procedure after capital overhaul
Boiler recommissioning procedure after capital overhaul
 
SubstationCommissioning.pdf
SubstationCommissioning.pdfSubstationCommissioning.pdf
SubstationCommissioning.pdf
 
Lockout/Tagout
Lockout/TagoutLockout/Tagout
Lockout/Tagout
 
E JIMOH
E JIMOHE JIMOH
E JIMOH
 
E JIMOH
E JIMOHE JIMOH
E JIMOH
 
Operation and maintanance
Operation and maintananceOperation and maintanance
Operation and maintanance
 
Safe Isolation Procedure
Safe Isolation ProcedureSafe Isolation Procedure
Safe Isolation Procedure
 
Elearningtemplateppt
ElearningtemplatepptElearningtemplateppt
Elearningtemplateppt
 
Installation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersInstallation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of Transformers
 
11. membrane unit
11. membrane unit11. membrane unit
11. membrane unit
 

Fulham Reach Block G Risk Review Presentation For review

  • 1. Fulham Reach Block G Risk Review Presentation Presented by: Mark Platten – Senior Project Manager & David Dicker – Group Health, Safety & Environment Manager
  • 3. Presentation Overview Contents • Company Overview • Typical Systems • Our approach • Safe Systems of Work • Nominated Persons • Safe Isolation • Permit to Work • Pressure Testing • Live Working • Hot Works • COSHH • House Keeping • Site Inspections • Working at Height • Accreditations
  • 4. Company Overview • 1981 - Founded as South Eastern Electrical Ltd. • 2010 - Company rebranded as SEE. • 2011 – SES formed. • 2011 - Introduction of ‘In house’ Mechanical Division. • 2012 – SEE acquire PBM Construction. • 2012 – SER established – Renewable and Sustainable energy. • 2014 – SEE Rail Division
  • 5.
  • 6. Typical Apartments Services Typical Apartment Lighting Layout Typical Apartment Small Power Layout
  • 9. Typical Floor Domestic Water System
  • 11. Our Approach • Dedicated on site Mechanical & Electrical Project Managers • Focused on Safety • Daily / Task Specific Safe Start Briefings for all operatives • Robust Safe Working Rules Mechanical & Electrical • Self delivery through our network of engineers • Management against agreed KPI’s • Regular reporting • Pro-active approach to Health and Safety, Environment & Quality
  • 13. Safe Start Team Briefing Form
  • 14. Safe Start Team Briefing Form
  • 15. Safe Systems of Work • SEE Electrical Safe Working Rules. • SEE Mechanical Safe Working Rules.
  • 16. Nominated Persons • EACH OPERATING SITE IS TO PRODUCE A LIST OF NOMINATED PERSONS • NOMINATED PERSONS WILL HAVE RECEIVED INSTRUCTION AND HAVE BEING ASSESSED TO BE COMPETENT • Every contract requires a nominated person to be Authorised in writing by his Department Director. • As ANP they will receive: • Letter detailing duties, duration, site* • Copy SEE Plc. Safe Working Rules *The letter gives Authorisation for the named site only.
  • 17. Safe Isolation • Check isolator disconnects all supplies • Check alternative sources of supply (where applicable) • Isolator to be locked off and key held by ANP (Key Safe) • Where there is no facility to lock off fuses or links may be removed and held by ANP (Key Safe) • Warning notices must be displayed (Cation Notice) • PROVE ALL CONDUCTORS DEAD with appropriate test instrument BEFORE touching. • Danger Notice to be displayed on all LIVE Equipment.
  • 18. SAFE SYSTEMS OF WORK Two Safe Systems of Work to be used for both mechanical and electrical works:- 1. TAGOUT SYSTEM LOW RISK WORK 2. PERMIT SYSTEM HIGH RISK WORK can also be used for low risk work
  • 19. TAGOUT & PERMIT SYSTEM SSW S.06/1 – Tagout Procedures TB/01/906 - Safety Padlock Policy. Note :- Safety locks are coloured Red and have a single unique key and are used solely for isolation purposes.
  • 20. TAGOUT PROCEDURES • Tagout is to be used for local isolation and short duration work only. • The Competent Person (CP) personally holds the isolation keys. +
  • 21. PERMIT SYSTEM • The work is under the control of the required Authorised Person (AP), electrical, confined spaces etc. • The works are carried out in accordance with the relevant Safety Rules. • The AP carries out the high risk Risk Assessment • And issues the Safety Documentation • Safety Lock(s) (red) or Caution Tape + Caution Sign(s) are used. • Isolation keys are locked in a Key Safe (or other secure place). Under control of the ANP
  • 22. EQUIPMENT THAT MUST BE USED WITH THE PERMIT SYSTEM PERMIT SYSTEM + + Safety Rules Specific Risk Assessment Safety Lock + + + Caution sign Safety Key Box Permit to Work
  • 23. HIGH RISK ACTIVITIES ARE CLASSIFIED AS:- • Live Working (Pressure Systems, Electrical, Gas). • Confined Spaces. • Other Hazardous Areas. • High Voltage (at or greater than 1000V). • Low Voltage Main Intake Switches, Switchboards and Equipment having two or more sources of supply, plus cables and other equipment on the supply side of the Main Intake Switch. • Pressure Systems. • Gas Systems above a nominal 21 mbar. • LPG Systems above a nominal 37 mbar.
  • 24. Locking Off Example: Locking Circuit Breakers MCB’ & MCCB’s Use of proprietary locking off devices Example: Multiple Isolations / Rotary Isolators
  • 26. Safe Isolation & Permit to Work Flow Chart
  • 27. Sequence for proving Dead • Prove Voltage Indicator on a known source or with a proving unit. • Test all conductors which are to be worked on including the Neutral. • Retest the Voltage Indicator after testing each conductor. Voltage Indicator & Proving Unit
  • 28. Sequence for proving Dead • ISOLATE AT ALL SOURCES OF SUPPLY • LOCK OFF AND FIT SIGNS • PROVE DEAD • ISSUE PERMIT AT POINT OF WORK
  • 30. Permit to Work SEE Electrical Permit to Work Page 1 Authorisation.
  • 31. Permit to Work SEE Electrical Permit to Work Page 2 Receipt & Declaration
  • 32. Permit to Work SEE Electrical Permit to Work Page 3 Cancellation & Clearance
  • 34. Request for Energisation of Equipment SEE Request for Initial Energisation of Equipment or Systems
  • 35. Request for Isolation of Equipment SEE Request for Isolation of Equipment or Systems
  • 36. Pressure Testing Pneumatic & Hydraulic Testing of services pipework SAFE METHOD OF WORK • Inform the Site Manager or their representative of the works to be carried out • Check that the work area is clear for the work to commence. • Brief the work team of the works to be carried out and sign the briefing sheet attached. • Cordon off the work area to prevent unauthorised access. • ENSURE WARNING SIGNAGE IS POSTED THROUGHOUT THE TEST AREA
  • 37. Pressure Testing Pneumatic Testing (Air Test) • Check that the work area is clear for the work to commence. A site-specific / task specific risk assessment must be carried out prior to the work commencing using form FM/H&S/RISK/02. Where indicated on the risk assessment a separate manual handling risk assessment may be required. If so use form FM/HSE/RISK/03 • Put into place any ‘control or additional control measures’ indicated on the risk assessment. • Place Pressure testing warning signs in the location to warn others of the testing in progress and to set up Exclusion zones and time when tests can be carried out will be agreed on site with St. George and implemented. This will be a dynamic process and under constant review • Connect test manifold to the steel and plastic pipework. NOTE: Ensure the test manifold components are rated above the test pressure • Check all isolation valves where fitted are in the open position. • Install a secondary vent valve as a backup and plug the valve. NOTE: Ensure it is rated above the test pressure • Fill the system • Bring the system up to 0.5 bar pressure and close the valve • Check for air leaks and observe the pressure gauge for 15 Minute’s • Bring the system up to the test pressure & disconnect the compressor. • After 1 hour (or as required by the specification) check for pressure drop and if satisfactory obtain signoff from the client using appropriate QA forms. • A controlled evacuation of the air using the valve will discharge the pressure Eye & Hearing protection must be worn. • If the system lets buy then the engineer will test with a leak detector spray (soapy water) on joints to establish the leak, then retested as above. • All valves to be left in the open position • Clear the area and leave in a safe condition.
  • 38. Pressure Testing Hydraulic Testing (Water Test) • Check that the work area is clear for the work to commence. A site-specific / task specific risk assessment must be carried out prior to the work commencing using form FM/H&S/RISK/02. Where indicated on the risk assessment a separate manual handling risk assessment may be required. If so use form FM/HSE/RISK/03 • Put into place any ‘control or additional control measures’ indicated on the risk assessment. • Place Pressure testing warning signs in the location to warn others of the testing in progress and to Set up Exclusion zones and time when tests can be carried out will be agreed on site with St George and implemented. This will be a dynamic process and under constant review • Connect test manifold to the steel pipework. • Check all isolation valves where fitted are in the open position. • Install a secondary vent valve as a backup and plug the valve. • Fill the system with water ensuring all air is vented out before testing • NOTE: When using water for pressure testing ensure that the system is properly vented before pressurisation. • Testing should always start by applying a low pressure (below safe operating limits) to verify initial integrity of the system. • Bring the system up to 2 bar pressure and close the valve • Check for water leaks and observe the pressure gauge for 15 Minute’s • Raise the test pressure in stages (holding the pressure for a period of time) to reduce the potential energy release resulting from failure of the assembly and associated components under test. • Bring the system up to the test pressure & disconnect the hydraulic pump. • After 1 hour (or as required by the specification) check for pressure drop and if satisfactory obtain signoff from the client using appropriate QA forms. • A controlled evacuation of the water using the valve will discharge the pressure to a suitable drain Eye protection must be worn. • If the system lets buy then the engineer will look for leaks on joints to establish the leak, then retested as above. • All valves to be left in the open position or the system left filled with water as required. • Clear the area and leave in a safe condition.
  • 40. LIVE WORKING EXCEPTIONAL CIRCUMSTANCES THE FOLLOWING SAFEGUARDS ARE REQUIRED Risk Assessment by Authorised Nominated Person Authorised by Senior Project Manager & Group SHEQ Manager • Training • Information • Tools • Barriers/Screens • Test probes • Accompaniment • Product Testing Area • Effective Control
  • 41. Hot Works • Hot Works Permit Required for; • VRV pipework brazing. • Gas pipework welding. • Fire Extinguisher issued. • 1hr. Fire Watch period after hot works suspended. • Close out of Hot Works Permit.
  • 42. Hot Works Mitigation • Cold cut wheels to be used on site. • LTHW Pipework will be Crimped Copper. • BCW Pipework will be Crimped Copper & Plastic.
  • 45. House Keeping • All access routes to be kept clear at all times, free from trailing leads, materials, tools etc. • All work areas to be tidied as the task is done. • All work areas to be cleared of waste materials & tools and left in a clean and tidy condition. • Trailing leads to be clipped up to avoid trip hazards. (SKY HOOK).
  • 47. Working at Height We operate a simple hierarchy for managing & selecting equipment for work at height. a) avoid work at height where they can; b) use work equipment or other measures to prevent falls where they cannot avoid working at height; and c) Where they cannot eliminate the risk of a fall, use work equipment or other measures to minimise the distance and consequences of a fall should one occur.
  • 48. Working at Height Line Managers as ‘Duty holders’ are required to ensure: a) all work at height is properly planned and organised; b) all work at height takes account of weather conditions that could endanger health and safety; c) those involved in work at height are trained and competent; d) the place where work at height is done is safe; e) equipment for work at height is appropriately inspected; f) the risks from fragile surfaces are properly controlled; and g) the risks from falling objects are properly controlled.
  • 50. Access Equipment Podium Steps Stair Access Tower Insulated Step Ladder For Short Duration Light Duties Only
  • 51. Work at Height Podium Steps Inspection Record WARNING Unlawful removal or interference with this sign could make you liable to PROSECUTION AND FINES Authorised Person: Date Signed All podium steps, access equipment must be inspected at the time of erection, by a competent person & signed off for safe use. An inspection by a competent person must be carried out on a weekly basis and the “Scaff Tag” signed and dated. The equipment must be visually inspected and the “Scaff Tag” checked for the last inspection date to ensure it is in date before each use.
  • 52. Health and Safety Behavioural Safe Systems Training Intervention Benchmark FOCUSED ON SAFETY