SlideShare a Scribd company logo
1 of 11
PIPING HYDROTEST
Mohammed Mukarram Jah
Mechanical Engineer,
mukarram169@rediffmail.com
+91 9701 99 3862,
overview
• Pipe Inspection and Testing
• Pressure Tests
• What is hydrotest
• Why hydrotest is Required
• Where hydrotest is Required
• Requirements of Hydrotest
Pipe Inspection and Testing
• Once the piping system is installed, it must be inspected for
defects and tested before it is placed into operation/Service.
• The tests are of two type
A. Destructive Tests and
B. Non Destructive Tests
Destructive Test: It is a test conducted for checking the quality of
System/Material by impacting the properties of the material.
Non Destructive Test: It is a test conducted for checking the
quality of System/Material without impacting the properties of
the material.
• Pressure Test is a Non Destructive Test and is of different
types depending on requirements.
• Pressure Test is a test conducted to piping or equipment by
subjecting it to an internal pressure using liquid or gas to
ensure strength or tightness of the system at the test
pressure. Pressure Test may be
• Hydrostatic Test
• Pneumatic Test
• Leak test
• Revalidation Test
• Service Test
• Strength Test
• System Test
• Tightness Test
Pressure Tests
What is Hydrotest
• Hydrotest : A pressure test conducted using water or other
approved liquid as the test medium. Test Pressure Varies from one
code to another depending on the pipeline service and pipeline
location. For Instance
1. ASME 31.4 for “Pipeline Transportation Systems for Liquid
Hydrocarbons and Other Liquids” requires test pressure 1.25 times
the maximum operating pressure.
2. ASME 31.8 for “Gas Transmission and Distribution Piping Systems”
requires test pressure ranging from 1.25 -1.4 times the maximum
operating pressure depending on location of pipeline in populated
areas.
3. ASME31.9 for “Building Services Piping” requires test pressures 1.5
times the Design Pressure
4. In Aramco Test pressure is determined to produce 90% Specified
Minimum Yield Strength for a minimum of 2hrs, based on nominal
wall thickness as per the following formula.
P= 2t x (0.9SMYS)/D
5. Test Pressure for Utility piping system shall be as per SAES-S-070/
UPC
Why Hydrotest
• To ensure the integrity of Piping
• To ensure the strength of the pipe joints
• To ensures safe and reliable performance during the operational life
Hydrotest Prerequisite
• Test Package shall be prepared with Engineering and Technical
Perspective.
• Good planning is essential for completion of hydrotest in minimum
possible time.
• Calibrated Relief Valve, Gauges, Pressure and Temperature recorders,
Pump etc. shall be available.
• Location, draining, Venting shall be considered.
• Water- quantity, quality & temperature
• Torque tightening
Bolt Tightening
• Carry out Bolt tightening of all flange Joints as per the required
torque mentioned in SAEP-351/Pipe Manufacturer
• Use proper Tightening Tool to meet the requirement of Torque
and follow the tightening sequence as per approved procedure
for bolts / studs
1
2
3
4 5
6 7
8
TIGHTENING SEQUENCE (with torque tightening Tool)
8
4
• Ensure that minimum two pressure gauges are available in the
test system.
• The pressure gauges shall have a range such that the test
pressure is within 30 to 80% of the full range . Validity of
calibration shall be verified on the calibration sticker pasted on
the pressure indicators
• Ensure that the valves (top) are open for air removal prior to
water filling.
• Start filling water after confirmation of all requirements (
water chemistry report etc.)
• Let the water flow out of the top Valves so that the air is
removed
• Start the pump for pressurizing the water inside the pipe. (Set
the output pressure of pump such that it should not exceed
hydro test pressure for safer operation)
• Increase the pressure as per the requirement given the
approved procedure
• All safety Precautions shall be taken during pressurizing and
no one shall remain near pipe
• Hold the test pressure for 4hrs. for exposed joints and 24hrs.
for buried joints. The test pressure shall not get dropped
during the holding time.
• Check for any leakage in joints.
• If no leakage is observed, depressurizing can be started
Depressurizing :
• Reduce pressure slowly by opening valve at drain point such
that pressure drops to zero.
• While draining the pipe, the top Air vent valve shall be kept
open before opening any valve at low point. This is for
eliminating the possible collapse of pipe due to vacuum
created within the test pipe.
Hydrotest Package
Hydrotest Package shall be as per applicable SATIP. Below are
general contents.
1. Test Package Flow chart
2. Pressure Test Information Sheet
3. Approved Test Procedure
4. Safety Instruction Sheet
5. Hydrotest Diagram showing Test Limits, P&ID, Isometric
Drawings
6. Pre-Test Punch list
7. Flushing Report
8. Test Equipment verification checklist
9. Pressure gauge, Relief valve, Temperature and Pressure
Recorder calibration certificates
10. Manifold Approval
11. Water chemistry Report
12. Filling & Pressurization checklist
13. Visual inspection at test pressure
14. Depressurization & Disposal checklist
15. Welding summary sheets, Weld map, Test Reports such
as RT,PT,MT etc.
16. Bolted flange joints Assembly checklist
17. Torque wrench certificate
18. Valves Test Report
19. Preservation of Valves(Inline Tested)
20. Layup of piping system
21. Final Punch listing checklist

More Related Content

What's hot

35 Insp, Ndt, Stat Reqmts Fope
35 Insp, Ndt, Stat Reqmts Fope35 Insp, Ndt, Stat Reqmts Fope
35 Insp, Ndt, Stat Reqmts Fope
jubin
 

What's hot (20)

pipefitting pressure-test
pipefitting pressure-testpipefitting pressure-test
pipefitting pressure-test
 
Flange management presentation
Flange management presentationFlange management presentation
Flange management presentation
 
495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx495265750-Hydro-Test-Procedure.docx
495265750-Hydro-Test-Procedure.docx
 
Hydrostatic pressure testing of PE pipelines (handbook) as per EN805
Hydrostatic pressure testing of PE pipelines (handbook) as per EN805Hydrostatic pressure testing of PE pipelines (handbook) as per EN805
Hydrostatic pressure testing of PE pipelines (handbook) as per EN805
 
7) hydro test 3
7) hydro test 37) hydro test 3
7) hydro test 3
 
Piping Components Handbook (Piping Training Material) for Oil & Gas Engineer
Piping Components Handbook (Piping Training Material) for Oil & Gas EngineerPiping Components Handbook (Piping Training Material) for Oil & Gas Engineer
Piping Components Handbook (Piping Training Material) for Oil & Gas Engineer
 
what is process piping
what is process pipingwhat is process piping
what is process piping
 
Qc piping guide
Qc piping guideQc piping guide
Qc piping guide
 
Offshore qc welding inspection versi 1
Offshore qc welding inspection versi 1Offshore qc welding inspection versi 1
Offshore qc welding inspection versi 1
 
B31.3 process piping course 02 metallic pipe & fitting selection
B31.3 process piping course   02 metallic pipe & fitting selectionB31.3 process piping course   02 metallic pipe & fitting selection
B31.3 process piping course 02 metallic pipe & fitting selection
 
presentation
presentationpresentation
presentation
 
Precommisioning and commissioning updated
Precommisioning and commissioning updatedPrecommisioning and commissioning updated
Precommisioning and commissioning updated
 
Piping presentation part ii 2
Piping presentation part ii 2Piping presentation part ii 2
Piping presentation part ii 2
 
How to Qualify a Welding Procedure
How to Qualify a Welding ProcedureHow to Qualify a Welding Procedure
How to Qualify a Welding Procedure
 
Fundamental of Pipe / Pipeline used in Process Piping.
Fundamental of Pipe / Pipeline used in Process Piping.Fundamental of Pipe / Pipeline used in Process Piping.
Fundamental of Pipe / Pipeline used in Process Piping.
 
Pressure Relief valve sizing and design
Pressure Relief valve sizing and designPressure Relief valve sizing and design
Pressure Relief valve sizing and design
 
Piping handbook
Piping handbookPiping handbook
Piping handbook
 
35 Insp, Ndt, Stat Reqmts Fope
35 Insp, Ndt, Stat Reqmts Fope35 Insp, Ndt, Stat Reqmts Fope
35 Insp, Ndt, Stat Reqmts Fope
 
Cswip welding inspection notes and questions
Cswip welding inspection notes and questionsCswip welding inspection notes and questions
Cswip welding inspection notes and questions
 
Asme sec viii div 2
Asme sec viii div 2Asme sec viii div 2
Asme sec viii div 2
 

Similar to Piping hydrotest

Fulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewFulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For review
Mark Platten
 
Commissioning Supervisor New
Commissioning Supervisor NewCommissioning Supervisor New
Commissioning Supervisor New
Joseph Jaiwin Das
 
Internship Report
Internship ReportInternship Report
Internship Report
Malik Ehsan
 
control valve functional testing - Swetha
control valve functional testing - Swethacontrol valve functional testing - Swetha
control valve functional testing - Swetha
Swetha Sundaram
 
Pre commissioning steam turbines load trial
Pre commissioning steam turbines load trialPre commissioning steam turbines load trial
Pre commissioning steam turbines load trial
Nagesh H
 

Similar to Piping hydrotest (20)

Fulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewFulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For review
 
WSM Yard-High-Pressure Safety-22.12.19
WSM Yard-High-Pressure Safety-22.12.19WSM Yard-High-Pressure Safety-22.12.19
WSM Yard-High-Pressure Safety-22.12.19
 
NONG YAO PROJECT SUBSEA VALVE Rev 0
NONG YAO PROJECT SUBSEA VALVE Rev 0NONG YAO PROJECT SUBSEA VALVE Rev 0
NONG YAO PROJECT SUBSEA VALVE Rev 0
 
Commissioning Supervisor New
Commissioning Supervisor NewCommissioning Supervisor New
Commissioning Supervisor New
 
Internship Report
Internship ReportInternship Report
Internship Report
 
Boiler recommissioning procedure after capital overhaul
Boiler recommissioning procedure after capital overhaul Boiler recommissioning procedure after capital overhaul
Boiler recommissioning procedure after capital overhaul
 
Gas Lift Optimization and Troubleshooting
Gas Lift Optimization and Troubleshooting Gas Lift Optimization and Troubleshooting
Gas Lift Optimization and Troubleshooting
 
The humble check_valve
The humble check_valveThe humble check_valve
The humble check_valve
 
Aerosols
AerosolsAerosols
Aerosols
 
control valve functional testing - Swetha
control valve functional testing - Swethacontrol valve functional testing - Swetha
control valve functional testing - Swetha
 
Validation utility system
Validation utility systemValidation utility system
Validation utility system
 
Edited j6.doc
Edited j6.docEdited j6.doc
Edited j6.doc
 
Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)
 
Basics Of Pricess Plant Piping System Design .pdf
Basics Of Pricess Plant Piping System Design .pdfBasics Of Pricess Plant Piping System Design .pdf
Basics Of Pricess Plant Piping System Design .pdf
 
Fluke and Transcat Present: 4 Common Pressure Calibration Pain Points Webinar
Fluke and Transcat Present: 4 Common Pressure Calibration Pain Points Webinar Fluke and Transcat Present: 4 Common Pressure Calibration Pain Points Webinar
Fluke and Transcat Present: 4 Common Pressure Calibration Pain Points Webinar
 
Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION
 
Tightness testing of gravity pipelines
Tightness testing of gravity pipelinesTightness testing of gravity pipelines
Tightness testing of gravity pipelines
 
Ekit (B) Sdn Bhd
Ekit (B) Sdn BhdEkit (B) Sdn Bhd
Ekit (B) Sdn Bhd
 
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratoryدليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
دليل تجارب الاسفلت المختبرية - Asphalt Experiments Guide Laboratory
 
Pre commissioning steam turbines load trial
Pre commissioning steam turbines load trialPre commissioning steam turbines load trial
Pre commissioning steam turbines load trial
 

Recently uploaded

Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
hublikarsn
 
Query optimization and processing for advanced database systems
Query optimization and processing for advanced database systemsQuery optimization and processing for advanced database systems
Query optimization and processing for advanced database systems
meharikiros2
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
Kamal Acharya
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
mphochane1998
 

Recently uploaded (20)

Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
 
Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)Introduction to Artificial Intelligence ( AI)
Introduction to Artificial Intelligence ( AI)
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
 
Query optimization and processing for advanced database systems
Query optimization and processing for advanced database systemsQuery optimization and processing for advanced database systems
Query optimization and processing for advanced database systems
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth Reinforcement
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .ppt
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257Memory Interfacing of 8086 with DMA 8257
Memory Interfacing of 8086 with DMA 8257
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 

Piping hydrotest

  • 1. PIPING HYDROTEST Mohammed Mukarram Jah Mechanical Engineer, mukarram169@rediffmail.com +91 9701 99 3862,
  • 2. overview • Pipe Inspection and Testing • Pressure Tests • What is hydrotest • Why hydrotest is Required • Where hydrotest is Required • Requirements of Hydrotest
  • 3. Pipe Inspection and Testing • Once the piping system is installed, it must be inspected for defects and tested before it is placed into operation/Service. • The tests are of two type A. Destructive Tests and B. Non Destructive Tests Destructive Test: It is a test conducted for checking the quality of System/Material by impacting the properties of the material. Non Destructive Test: It is a test conducted for checking the quality of System/Material without impacting the properties of the material. • Pressure Test is a Non Destructive Test and is of different types depending on requirements.
  • 4. • Pressure Test is a test conducted to piping or equipment by subjecting it to an internal pressure using liquid or gas to ensure strength or tightness of the system at the test pressure. Pressure Test may be • Hydrostatic Test • Pneumatic Test • Leak test • Revalidation Test • Service Test • Strength Test • System Test • Tightness Test Pressure Tests
  • 5. What is Hydrotest • Hydrotest : A pressure test conducted using water or other approved liquid as the test medium. Test Pressure Varies from one code to another depending on the pipeline service and pipeline location. For Instance 1. ASME 31.4 for “Pipeline Transportation Systems for Liquid Hydrocarbons and Other Liquids” requires test pressure 1.25 times the maximum operating pressure. 2. ASME 31.8 for “Gas Transmission and Distribution Piping Systems” requires test pressure ranging from 1.25 -1.4 times the maximum operating pressure depending on location of pipeline in populated areas. 3. ASME31.9 for “Building Services Piping” requires test pressures 1.5 times the Design Pressure 4. In Aramco Test pressure is determined to produce 90% Specified Minimum Yield Strength for a minimum of 2hrs, based on nominal wall thickness as per the following formula. P= 2t x (0.9SMYS)/D 5. Test Pressure for Utility piping system shall be as per SAES-S-070/ UPC
  • 6. Why Hydrotest • To ensure the integrity of Piping • To ensure the strength of the pipe joints • To ensures safe and reliable performance during the operational life Hydrotest Prerequisite • Test Package shall be prepared with Engineering and Technical Perspective. • Good planning is essential for completion of hydrotest in minimum possible time. • Calibrated Relief Valve, Gauges, Pressure and Temperature recorders, Pump etc. shall be available. • Location, draining, Venting shall be considered. • Water- quantity, quality & temperature • Torque tightening
  • 7. Bolt Tightening • Carry out Bolt tightening of all flange Joints as per the required torque mentioned in SAEP-351/Pipe Manufacturer • Use proper Tightening Tool to meet the requirement of Torque and follow the tightening sequence as per approved procedure for bolts / studs 1 2 3 4 5 6 7 8 TIGHTENING SEQUENCE (with torque tightening Tool) 8 4
  • 8. • Ensure that minimum two pressure gauges are available in the test system. • The pressure gauges shall have a range such that the test pressure is within 30 to 80% of the full range . Validity of calibration shall be verified on the calibration sticker pasted on the pressure indicators • Ensure that the valves (top) are open for air removal prior to water filling. • Start filling water after confirmation of all requirements ( water chemistry report etc.) • Let the water flow out of the top Valves so that the air is removed • Start the pump for pressurizing the water inside the pipe. (Set the output pressure of pump such that it should not exceed hydro test pressure for safer operation)
  • 9. • Increase the pressure as per the requirement given the approved procedure • All safety Precautions shall be taken during pressurizing and no one shall remain near pipe • Hold the test pressure for 4hrs. for exposed joints and 24hrs. for buried joints. The test pressure shall not get dropped during the holding time. • Check for any leakage in joints. • If no leakage is observed, depressurizing can be started Depressurizing : • Reduce pressure slowly by opening valve at drain point such that pressure drops to zero. • While draining the pipe, the top Air vent valve shall be kept open before opening any valve at low point. This is for eliminating the possible collapse of pipe due to vacuum created within the test pipe.
  • 10. Hydrotest Package Hydrotest Package shall be as per applicable SATIP. Below are general contents. 1. Test Package Flow chart 2. Pressure Test Information Sheet 3. Approved Test Procedure 4. Safety Instruction Sheet 5. Hydrotest Diagram showing Test Limits, P&ID, Isometric Drawings 6. Pre-Test Punch list 7. Flushing Report 8. Test Equipment verification checklist 9. Pressure gauge, Relief valve, Temperature and Pressure Recorder calibration certificates
  • 11. 10. Manifold Approval 11. Water chemistry Report 12. Filling & Pressurization checklist 13. Visual inspection at test pressure 14. Depressurization & Disposal checklist 15. Welding summary sheets, Weld map, Test Reports such as RT,PT,MT etc. 16. Bolted flange joints Assembly checklist 17. Torque wrench certificate 18. Valves Test Report 19. Preservation of Valves(Inline Tested) 20. Layup of piping system 21. Final Punch listing checklist