SlideShare a Scribd company logo
1 of 34
Download to read offline
Substation Commissioning
Substation Commissioning
• What is substation
commissioning?
– Proving the proper
operation of a newly
• Installed
• Replaced
• Modified
• Repaired
piece of equipment
before it is placed into
service
Substation Commissioning
• New/replaced/repaired
circuit breakers
• New/replaced/repaired
transformers
Substation Commissioning
• Green field substation
Substation Commissioning
• Control Devices
Substation Commissioning
• New relays or modified
relay settings
Substation Commissioning
• All commissioning tasks
require a good plan. In
order to prove proper
operation, the
technician must
understand proper
operation.
Substation Commissioning
• Safety
– Always mitigate safety
concerns
– LOTO
– Clearance, Hold, Tag out
– May require help from
other departments
– When in doubt, stop
Substation Commissioning
• Levels of commissioning
– Simple
– Moderate
– Difficult
Substation Commissioning
• Creating a game plan
– Simple Checklist
• Cooling system
contactor replacement
– Fans/Pumps working
properly?
– All stages?
– SCADA alarms?
– Simple component
replacement should be
checked for proper
operation
Substation Commissioning
• Moderate to difficult commissioning
– Intense familiarity with all aspects of the task at
hand isn’t always necessary. Sometimes there are
other groups involved in the commissioning
process. General familiarity with other work
groups responsibilities is highly encouraged.
– Thorough knowledge and expertise in the
responsibilities of the relay technician is required.
Substation Commissioning
• Comprehensive
checklist needed for
more complicated
commissioning tasks
SUBSTATION COMMISSIONING
CHECKLIST
TRANSFORMER INFORMATION
MANUFACTURER:
SERIEL NUMBER:
MVA:
NUMBER OF WINDINGS:
SELF NUMBER:
WINDING H VOLTAGE:
WINDING X VOLTAGE:
WINDING Y VOLTAGE:
WINDING Z VOLTAGE:
LTC ? : Y N
LTC SENSING VOLTAGE LEVEL:
LTC SENSING VOLTAGE SOURCE:
COOLING SYSTEM:
COOLING SYSTEM VOLTAGE LEVEL:
COOLING SYSTEM VOLTAGE SOURCE:
COOLING SYSTEM CONFIGURATION: OA FA OAFA FOFA
NUMBER OF PRESURE RELIEF DEVICES:
STYLE OF SUDDEN PRESSURE DEVICE: RAPID RISE FAULT PRESSURE BUCHOLTZ NA
N2 SYSTEM: Y N
TYPE OF N2 REGULATION: SINGLE STAGE MULTISTAGED
MANUFACTURER RECOMMENDED N2 PRESSURE:
Substation Commissioning
• Large component replacement
– Transformers and Circuit Breakers
• Acceptance tests can be performed without prints and
relay settings
– CT saturation, ratio, polarity, and insulation testing
– VT ratio, polarity, insulation testing
– Power Factor testing
– Transformer turns ratio testing
Acceptance testing really only proves that the equipment was
built to specifications at the factory, it survived the travel and
installation, and is the baseline for future performance
comparison.
Substation Commissioning
• Testing that requires
prints and settings is
really the crux of the
commissioning process.
• These tests include:
– DC Circuit checks
– AC Circuit checks
– Relay testing
– Trip Checks
– Communication
processor programming
– Point to Point testing
Substation Commissioning
• DC Checks
– DC circuit checks can be accomplished in a few
different ways, but all must be documented to
stay on track.
– A good place to start is comparing the schematics
to the wiring diagrams. Mistakes can be identified
and possibly rectified during construction, or upon
arrival of equipment to the job site.
– Good time to review mistakes with engineering
Substation Commissioning
• DC Checks
– Circuits can be “pre‐
tested” with continuity
before DCV is applied
– (+) DCV can be applied
without (‐) DCV and
checks can be made
– DCV can be applied
without “pre‐testing”
and the location of the
smoke can be noted
Substation Commissioning
• DC Checks
– Note the voltage rating
of the power supply and
the I/O of the relay
before powering up
– Note proper DCV
polarity. Most devices
are not polarity
sensitive, but some are
and will not work
properly unless
connected properly
Substation Commissioning
• DC Checks
– Yellow lining prints is a
good way to keep track
of what has checked
good
– Test switches, start with
all open, then mark and
close when checked
good
– Leave checked test
switches closed
Substation Commissioning
• AC Voltage Checks
– Goal of AC voltage circuit
checks is to prove proper
phasing and polarity
throughout the circuit
– Existing phasing can be
identified with
equipment that has
been in service
– Secondary wires checked
with continuity as long
as all conductors are
isolated
– “Live” Bus or Line
voltage can be used
– Phase between new and
old secondary wires
– Metering screen on
microprocessor relay
Substation Commissioning
• AC Current Checks
– Very important to be
tested properly
– Primary loading with
prediction current flow
sheet
– Proves CT ratio, CT
circuit polarity, and CT
circuit continuity in one
test
Substation Commissioning
• AC Current Checks
– Secondary injection also
viable test.
• Only way to test
transformer CT circuits
• Extreme care must be
taken to get polarity
correct
• Documented same as
Primary load test
• Predicted results
Substation Commissioning
• Relay Testing
– Testing the relay is managed in different ways, but
the goal is to prove the relay settings, relay logic,
and relay functions are all working to “as set”
settings
– Element testing can be accomplished via manual
or automatic testing
– Strive to test relay logic with real dynamic testing
Substation Commissioning
• Dynamic Logic Testing
– Don’t just pulse/jumper contacts, create relay
reaction by injecting values into the relay
– Use logic diagrams and yellow line them as they
are tested is a great way to understand the relay
logic
– Better yet, draw your own logic diagrams and test
them
Substation Commissioning
Substation Commissioning
• Dynamic Logic Testing
– Make breaker reclose or
not reclose
– Block close by injecting
false sync values
– Block transfer tripping
with c/o switch
– Roll LOR with Breaker
Failure or DTT RX
Substation Commissioning
• Trip Checks
– Vital to proving proper
operation of all devices
– Electrical and
mechanical
Substation Commissioning
• Circuit Breakers
– Trip from all known
tripping sources
– Trip from mechanical
devices such as low gas
– Test each trip coil
individually
– Trip breaker failure back
up devices
– Trip to/from remote
sources if using Transfer
Trip
Substation Commissioning
• Transformers
– Trip from all known
tripping sources
– Trip from mechanical
devices such as low oil
and sudden pressure
– Trip from cooling related
issues
– Trip breaker failure back
up schemes
– Trip and lock out
Substation Commissioning
• Communication
Processor Programming
• Meter testing
• TOP‐006 testing
• Communication circuit
testing
• End to end testing
• Pre check alarm circuits
Substation Commissioning
• Point to Point
– Complete final check of
proper operation of all
new devices in the
substation
– Control points
– Analog points
– Alarm points
– Verified to remote
control center
Substation Commissioning
• Energization Day
– Expectations
• Could be a long day
• Problems may arise
• Plan to mitigate problems
• Personal safety
• Non field personnel in
substation
• Confident
• All protective devices in
service
Substation Commissioning
• Post Energization
– Setting files
– Red/Green prints
– Complete all
documentation
– “Honey do” list
– Best commissioning jobs
are the substations you
never hear from
Substation Commissioning
• Conclusions
– A well thought out plan will guarantee the best
chance for a successful commissioning job
regardless of size of scope
– Strive for a plan that will “double check” yourself
– Ask for help when it’s needed
– Have confidence in your approach
Thank You

More Related Content

Similar to SubstationCommissioning.pdf

Electrical General Awareness1.pptx
Electrical General Awareness1.pptxElectrical General Awareness1.pptx
Electrical General Awareness1.pptxAbdoAbdo345332
 
Chandan_Electrical Engineer
Chandan_Electrical EngineerChandan_Electrical Engineer
Chandan_Electrical EngineerChandan Nag
 
Fulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewFulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewMark Platten
 
Installation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersInstallation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersLiving Online
 
NESTOR-UPDATED-CV-1 ALEGA
NESTOR-UPDATED-CV-1 ALEGANESTOR-UPDATED-CV-1 ALEGA
NESTOR-UPDATED-CV-1 ALEGAnestor alega
 
A year with Larsen & Toubro
A year with  Larsen & ToubroA year with  Larsen & Toubro
A year with Larsen & ToubroJAIPRAKASH PATIL
 
filip_damian cv poza.docx NEW IUNIE
filip_damian cv poza.docx NEW IUNIEfilip_damian cv poza.docx NEW IUNIE
filip_damian cv poza.docx NEW IUNIEdamian Filip
 
REPORT -VALLUR THERMAL POWER PLANT
REPORT -VALLUR THERMAL POWER PLANTREPORT -VALLUR THERMAL POWER PLANT
REPORT -VALLUR THERMAL POWER PLANTRAJPRASAD RS
 

Similar to SubstationCommissioning.pdf (20)

Electrical General Awareness1.pptx
Electrical General Awareness1.pptxElectrical General Awareness1.pptx
Electrical General Awareness1.pptx
 
Chandan_Electrical Engineer
Chandan_Electrical EngineerChandan_Electrical Engineer
Chandan_Electrical Engineer
 
Fulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewFulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For review
 
Fundamentals of Field Testing Meters
Fundamentals of Field Testing MetersFundamentals of Field Testing Meters
Fundamentals of Field Testing Meters
 
BR-High-Power-Test-Lab-Brochure
BR-High-Power-Test-Lab-BrochureBR-High-Power-Test-Lab-Brochure
BR-High-Power-Test-Lab-Brochure
 
Installation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of TransformersInstallation, Testing and Troubleshooting of Transformers
Installation, Testing and Troubleshooting of Transformers
 
Brian Norton
Brian NortonBrian Norton
Brian Norton
 
New cv jithesh
New cv jitheshNew cv jithesh
New cv jithesh
 
updated_ashishmalhotra
updated_ashishmalhotraupdated_ashishmalhotra
updated_ashishmalhotra
 
ComRent Capabilities Overview v10 Solar
ComRent Capabilities Overview v10 SolarComRent Capabilities Overview v10 Solar
ComRent Capabilities Overview v10 Solar
 
Engr kashif cv
Engr kashif cvEngr kashif cv
Engr kashif cv
 
asif sup new (4)
asif sup new (4)asif sup new (4)
asif sup new (4)
 
NESTOR-UPDATED-CV-1 ALEGA
NESTOR-UPDATED-CV-1 ALEGANESTOR-UPDATED-CV-1 ALEGA
NESTOR-UPDATED-CV-1 ALEGA
 
cv of pjnehru
cv of pjnehrucv of pjnehru
cv of pjnehru
 
Irfan - Elec Engr
Irfan - Elec EngrIrfan - Elec Engr
Irfan - Elec Engr
 
A year with Larsen & Toubro
A year with  Larsen & ToubroA year with  Larsen & Toubro
A year with Larsen & Toubro
 
filip_damian cv poza.docx NEW IUNIE
filip_damian cv poza.docx NEW IUNIEfilip_damian cv poza.docx NEW IUNIE
filip_damian cv poza.docx NEW IUNIE
 
Fusing Metering Voltages for High Capacity Circuits
Fusing Metering Voltages for High Capacity CircuitsFusing Metering Voltages for High Capacity Circuits
Fusing Metering Voltages for High Capacity Circuits
 
REPORT -VALLUR THERMAL POWER PLANT
REPORT -VALLUR THERMAL POWER PLANTREPORT -VALLUR THERMAL POWER PLANT
REPORT -VALLUR THERMAL POWER PLANT
 
Field Verification: Test Equipment and Best Practices
Field Verification: Test Equipment and Best PracticesField Verification: Test Equipment and Best Practices
Field Verification: Test Equipment and Best Practices
 

Recently uploaded

Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 

Recently uploaded (20)

Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 

SubstationCommissioning.pdf

  • 2. Substation Commissioning • What is substation commissioning? – Proving the proper operation of a newly • Installed • Replaced • Modified • Repaired piece of equipment before it is placed into service
  • 3. Substation Commissioning • New/replaced/repaired circuit breakers • New/replaced/repaired transformers
  • 6. Substation Commissioning • New relays or modified relay settings
  • 7. Substation Commissioning • All commissioning tasks require a good plan. In order to prove proper operation, the technician must understand proper operation.
  • 8. Substation Commissioning • Safety – Always mitigate safety concerns – LOTO – Clearance, Hold, Tag out – May require help from other departments – When in doubt, stop
  • 9. Substation Commissioning • Levels of commissioning – Simple – Moderate – Difficult
  • 10. Substation Commissioning • Creating a game plan – Simple Checklist • Cooling system contactor replacement – Fans/Pumps working properly? – All stages? – SCADA alarms? – Simple component replacement should be checked for proper operation
  • 11. Substation Commissioning • Moderate to difficult commissioning – Intense familiarity with all aspects of the task at hand isn’t always necessary. Sometimes there are other groups involved in the commissioning process. General familiarity with other work groups responsibilities is highly encouraged. – Thorough knowledge and expertise in the responsibilities of the relay technician is required.
  • 12. Substation Commissioning • Comprehensive checklist needed for more complicated commissioning tasks SUBSTATION COMMISSIONING CHECKLIST TRANSFORMER INFORMATION MANUFACTURER: SERIEL NUMBER: MVA: NUMBER OF WINDINGS: SELF NUMBER: WINDING H VOLTAGE: WINDING X VOLTAGE: WINDING Y VOLTAGE: WINDING Z VOLTAGE: LTC ? : Y N LTC SENSING VOLTAGE LEVEL: LTC SENSING VOLTAGE SOURCE: COOLING SYSTEM: COOLING SYSTEM VOLTAGE LEVEL: COOLING SYSTEM VOLTAGE SOURCE: COOLING SYSTEM CONFIGURATION: OA FA OAFA FOFA NUMBER OF PRESURE RELIEF DEVICES: STYLE OF SUDDEN PRESSURE DEVICE: RAPID RISE FAULT PRESSURE BUCHOLTZ NA N2 SYSTEM: Y N TYPE OF N2 REGULATION: SINGLE STAGE MULTISTAGED MANUFACTURER RECOMMENDED N2 PRESSURE:
  • 13. Substation Commissioning • Large component replacement – Transformers and Circuit Breakers • Acceptance tests can be performed without prints and relay settings – CT saturation, ratio, polarity, and insulation testing – VT ratio, polarity, insulation testing – Power Factor testing – Transformer turns ratio testing Acceptance testing really only proves that the equipment was built to specifications at the factory, it survived the travel and installation, and is the baseline for future performance comparison.
  • 14. Substation Commissioning • Testing that requires prints and settings is really the crux of the commissioning process. • These tests include: – DC Circuit checks – AC Circuit checks – Relay testing – Trip Checks – Communication processor programming – Point to Point testing
  • 15. Substation Commissioning • DC Checks – DC circuit checks can be accomplished in a few different ways, but all must be documented to stay on track. – A good place to start is comparing the schematics to the wiring diagrams. Mistakes can be identified and possibly rectified during construction, or upon arrival of equipment to the job site. – Good time to review mistakes with engineering
  • 16. Substation Commissioning • DC Checks – Circuits can be “pre‐ tested” with continuity before DCV is applied – (+) DCV can be applied without (‐) DCV and checks can be made – DCV can be applied without “pre‐testing” and the location of the smoke can be noted
  • 17. Substation Commissioning • DC Checks – Note the voltage rating of the power supply and the I/O of the relay before powering up – Note proper DCV polarity. Most devices are not polarity sensitive, but some are and will not work properly unless connected properly
  • 18. Substation Commissioning • DC Checks – Yellow lining prints is a good way to keep track of what has checked good – Test switches, start with all open, then mark and close when checked good – Leave checked test switches closed
  • 19. Substation Commissioning • AC Voltage Checks – Goal of AC voltage circuit checks is to prove proper phasing and polarity throughout the circuit – Existing phasing can be identified with equipment that has been in service – Secondary wires checked with continuity as long as all conductors are isolated – “Live” Bus or Line voltage can be used – Phase between new and old secondary wires – Metering screen on microprocessor relay
  • 20. Substation Commissioning • AC Current Checks – Very important to be tested properly – Primary loading with prediction current flow sheet – Proves CT ratio, CT circuit polarity, and CT circuit continuity in one test
  • 21. Substation Commissioning • AC Current Checks – Secondary injection also viable test. • Only way to test transformer CT circuits • Extreme care must be taken to get polarity correct • Documented same as Primary load test • Predicted results
  • 22. Substation Commissioning • Relay Testing – Testing the relay is managed in different ways, but the goal is to prove the relay settings, relay logic, and relay functions are all working to “as set” settings – Element testing can be accomplished via manual or automatic testing – Strive to test relay logic with real dynamic testing
  • 23. Substation Commissioning • Dynamic Logic Testing – Don’t just pulse/jumper contacts, create relay reaction by injecting values into the relay – Use logic diagrams and yellow line them as they are tested is a great way to understand the relay logic – Better yet, draw your own logic diagrams and test them
  • 25. Substation Commissioning • Dynamic Logic Testing – Make breaker reclose or not reclose – Block close by injecting false sync values – Block transfer tripping with c/o switch – Roll LOR with Breaker Failure or DTT RX
  • 26. Substation Commissioning • Trip Checks – Vital to proving proper operation of all devices – Electrical and mechanical
  • 27. Substation Commissioning • Circuit Breakers – Trip from all known tripping sources – Trip from mechanical devices such as low gas – Test each trip coil individually – Trip breaker failure back up devices – Trip to/from remote sources if using Transfer Trip
  • 28. Substation Commissioning • Transformers – Trip from all known tripping sources – Trip from mechanical devices such as low oil and sudden pressure – Trip from cooling related issues – Trip breaker failure back up schemes – Trip and lock out
  • 29. Substation Commissioning • Communication Processor Programming • Meter testing • TOP‐006 testing • Communication circuit testing • End to end testing • Pre check alarm circuits
  • 30. Substation Commissioning • Point to Point – Complete final check of proper operation of all new devices in the substation – Control points – Analog points – Alarm points – Verified to remote control center
  • 31. Substation Commissioning • Energization Day – Expectations • Could be a long day • Problems may arise • Plan to mitigate problems • Personal safety • Non field personnel in substation • Confident • All protective devices in service
  • 32. Substation Commissioning • Post Energization – Setting files – Red/Green prints – Complete all documentation – “Honey do” list – Best commissioning jobs are the substations you never hear from
  • 33. Substation Commissioning • Conclusions – A well thought out plan will guarantee the best chance for a successful commissioning job regardless of size of scope – Strive for a plan that will “double check” yourself – Ask for help when it’s needed – Have confidence in your approach