SlideShare a Scribd company logo
1 of 79
© 2017 UOP LLC. A Honeywell Company All rights reserved.
Introduction
Separex™ Membrane System
 PV Gas Ca Mau GPP Project
• Membrane Separation Principles and Overview
• Pre-treatment Equipment and Operations
• Membrane pre-commisioning activities and element loading
• Startup/Shutdown
• Normal Operations and Troubleshooting
Course Learning Objectives
1
Regions of Use for CO2 Removal Technologies
1000
100
10
1.0
0.1
Scavengers
MolSiv ™
PSA
Selexol™
Amine Guard™ FS
Membrane
Benfield™
PartialPressureAcidGasinFeed,psia
Partial Pressure Acid Gas in Product, psia
0.001 0.01 0.1 1.0 10 100
1000
100
10
1.0
0.1
2
Block Flow Diagram
3
Do’s
 Bulk CO2 removal
 Variety of CO2 feeds
 Offshore, remote, difficult
locations. modular
 Medium to high pressure
(> 600 psig)
 CO2 is a product
(re-injection, fuel gas)
Don'ts
 Try to get CO2 to ppm
levels (like feed gas for
LNG production)
 H2S to ppm levels
 Low feed gas pressure
Separex Membrane – Do’s and Don'ts
4
Membrane Principles
• Membranes separate components by a solution and diffusion
mechanism
- More soluble components permeate quicker
• Not a filtration process
• Separation is not perfect
5
Relative Permeation Rates
H2S, CO2, O2
H2O, H2, He
Fastest  Most Soluble
 Least Soluble
CO, CH4, N2, C2+
Slowest
CO, CH4, N2, C2+
H2S, CO2, O2
M
e
m
b
r
a
n
e
6
Selectivity of CO2 Membranes
UOP 4375C-06
UOP Confidential
Fast
Slow
HighPressure
LowPressure
H2O, H2S
CO2
(+ small amount of hydrocarbons)
Hydrocarbons
7
Driving Force
M
e
m
b
r
a
n
e
PCO2
High Pressure
(Feed)
Low Pressure
(Permeate)
Pressure Differential Across The Membrane
PCO2
8
Membrane Elements – Spiral Wound
9
Spiral Wound Membrane Element
8” Dia x 40” Long
40 lbs (18 kg)
10
Element Permeate Tube
11
Spiral Wound Membrane Tube
Residual
FeedPermeate
Inlet Seal
(U-Cup)
Membrane
Elements
Membrane
Housing
Permeate Tube
Clamp
Permeate
Standoff Tube
Taper-Lok
Enclosure
Taper-Lok
Enclosure
12
© 2017 UOP LLC. A Honeywell Company All rights reserved.
Design Basis
Separex™ Membrane System
 PV Gas Ca Mau GPP Project
PV Gas Membrane Pretreatment
 Performs well on light clean feed gas
 6-Month / 1-year maintenance cycle
 No dew point control downstream of cryo unit
Residue Gas
Cooler A-3001Feed
Membrane
X-4092
Filter
Coalescer F-4091
14
PV Gas Separex and Pretreatment Skid
15
Process Flow Scheme Diagram
16
Design Basis
• Sales Gas Specification:
- Maximum CO2 content: 8.0 mol%
- Minimum Gross Heating Value: 37.0 MJ/m3
• After separating the NGLs from the feed gas,
- Residue gas CO2 concentration > the specification of 8.0 mol%.
- Gross heating value lower than the required minimum of 37 MJ/m3.
• A small amount of CO2 will be removed in the membrane unit to
adjust the residue gas so that it is within the specifications.
• The low pressure, CO2 rich permeate will be used for fuel in the
HMO heaters and in the dehydration unit regeneration gas heater.
17
© 2017 UOP LLC. A Honeywell Company All rights reserved.
Membrane Pre-Commissioning Activities & Loading
Separex™ Membrane System
 PV Gas Ca Mau GPP Project
Pre-Commissioning
Understand:
• Pre-commissioning Activities
• Personal Protective Equipment and Safety
Considerations
• Pre-commissioning of Pretreatment
• Pre-commissioning of Membrane
• Leak Testing
19
Pre-Commissioning Main Activities
• P&ID Verification – Field verify including “as-built” mark-up
• Equipment Verification – Installed per design
• Line Cleaning – Confirm piping and headers been cleaned
• Load vessels – Filter cartridges and adsorbent
• Membrane Tubes – Clean membrane tubes and load elements
20
Pre-Commissioning Main Activities
• Instrumentation – Field verify instrumentation have been properly
reinstalled
• DCS/Instrumentation – Complete checks of field loops and DCS
interface
• SDV and BDV – Set and confirm limit switch operation
• Control Valves – Set and confirm valve movement
• Logic Check – Confirm functionality & verify proper
responses/actions
• ESD /DCS – Perform ‘dry tests’ to confirm C&E and field verify for
proper actions
• Line up PRVs – Confirm isolation valves in proper positions
including car seals or locks installed
• Leak Test – Audit flange tightness records. In controlled manner
test to operating pressure to confirm no loose connections
21
Filter Coalescer
outlet
inlet
Tubesheet
Standpipes
(adaptors)
Pre-separator
Liquidlevel control
Seprasol™Plus cartridges
22
Filter Coalescer Drawing
23
Main Pre-commissioning Activities
• Inspect F-4091 vessel
• Clean as needed
• Install filter coalescer cartridges
• Membrane Activities
- Remove permeate headers and Taper-Lok flanges
- Clean tubes
- Load membrane elements
- Reinstall Taper-Lok flanges and headers
- Leak test
- Nitrogen blanket
24
Remove Taper-Lok Flanges
• Erect scaffolding at residual end
of membrane skid if needed
• Prepare work area for removal
of Taper-Lok flanges
• Confirm each pair of Taper-Lok
flanges clearly marked to aid
reinstallation
Residual end Taper-Lok flange
Feed end Taper-Lok flange
25
Taper Lok Ring and Permeate Tube
Taper-Lok
metal seal
rings
Taper-Lok flange
with permeate
standoff tube
Poor practice – 2” flange resting on grating
26
Tube Cleaning
• Tube cleaning critical step prior to membrane loading
• Required to remove:
- Dirt
- Debris
- Scale
- Rust
- Corrosion inhibitor applied during fabrication
 Cleaning will take more time
• Prevents contamination of membrane elements, leading to
poor performance
• Not complicated
27
Tube Cleaning
• Pull rags/cleaning pig back and forth through tubes
• Use solvent like mineral spirit or paint thinner
• Continue until clean
• Let any excess solvent weather off before loading membranes
Tube cleaning is important but not complicated
28
Tube Cleaning
• Rags, foam, etc.
• Pull back and forth through tube with rope
29
Tube Before & After Cleaning
Before Cleaning After Cleaning
30
Before You Begin Loading
• Develop a loading plan
• Know which tubes will be opened
• Know what you will do with removed elements (if applicable)
• Know which elements will be added or replaced
• Have log prepared to record element serial numbers and location
inside the tube
• Develop staging plan (clamps, pins, vacuum grease etc.) and
equipment
• Ensure no rain or humidity > 80% expected. If not possible:
- Plan for shelter
- Plan for humidity control
UOP will advise on membrane loading activities at site
31
Loading Precautions
• Do not drop membrane elements
• Do not expose membrane elements to water or excessive
moisture/humidity
• Do not expose membrane elements or tubes to excessive
particulates (sand, etc.)
• Do not allow element to rest on edges or points
• If element is dropped or damage suspected, inform the UOP
technical advisor
• Open membrane packaging immediately prior to installation
(staging consideration)
• Keep tubes covered that are not being worked on
32
Loading Precautions (continued)
• Do not apply excessive force when snapping in clamp
• Do not twist or turn elements once they are connected
• Do not allow elements to hang on element connections – proper
support required until the newly connected element is adequately
inserted into the tube
• Do not allow Taper-Lok flanges to hang on element connections –
use support rods
Always avoid excessive load onto elements by providing proper support
(tray & support rods)!!
33
Element Loading
• Evenly apply grease to U-cup seal of next element
• Install o-ring onto centering ring
• Apply vacuum grease to o-ring
• Stick greased o-ring/centering ring onto flange of first
element
• Place next element permeate tube against o-ring/centering
ring on the first. Install clamp and pin
• Push the element string into tube leaving ~ 6” (15cm) outside
• Repeat until the proper number of elements have been
installed
34
Loading Procedure (cont.)
• Install Taper-Lok metal seal ring
- Seal ring can be reused if not damaged
• Place greased o-ring/centering ring against permeate flange.
Push Taper-Lok flange until its ‘stand-off’ tube flange is
against the o-ring/centering ring
• Connect element and stand-off tube with clamp and lock pin
• Push Taper-Lok flange onto the tube flange and hot bolt
• Remove support rods
• Tighten bolts, using star pattern, to proper torque
35
Element Loading
36
Element & Taper-Lok Stand-off Tube Connection
Membrane connected to Taper Lok
flange with permeate tube
Do not forget the
metal seal ring!
37
Loading Procedure – Final Steps
• Repeat procedure at next membrane tube until all tubes are
loaded
• Purge skid with nitrogen and maintain nitrogen blanket
38
Nitrogen Purge
• Nitrogen Purge and blanket all installed membrane
elements when not in use
• Always purge after exposing element to air
• Always purge prior to opening the system for maintenance
- Remove hydrocarbons
- Purge to meet safety requirements (LEL – lower explosion
limits, etc.)
• Nitrogen is an asphyxiant – oxygen-deficient atmosphere
may result
• Never allow the permeate pressure to exceed the feed or
residual pressures
39
• Pre-treatment & Membrane
skid/modules must be leak tested
to operating pressure prior to
introducing feed gas to the system
• This procedure must be followed
prior to the initial startup, after
turnaround or after opening up
significant components for
maintenance purposes
• If the unit is not to be started
immediately, leave a nitrogen
blanket until start-up
• Do not exceed 5 bar/minute
depressurization rate
• Always depressurize downstream
of filters (forward flow direction) to
avoid damage to cartridges
Leak Test
40
Leak Test Depressurization Procedure –
Membrane Section
• If using process gas:
- Must depressurize permeate and residual gas sides together always
keeping permeate pressure 3-5 bar lower
- Never depressurize via permeate side only
- Never allow permeate pressure to exceed feed or residual gas
pressure
41
Very important to always keep permeate pressure lower. Process gas
must be depressurized from both sides to avoid liquids condensation
and subsequent damage to membrane elements
Residue Gas Compressor (Not in UOPR Scope)
• Compresses residue gas to pipeline pressure
• Two centrifugal compressors running in parallel
- Not intended to be ran at the same time
• Online Condition Monitoring
- Continuous Vibration Monitoring
- Temperatures
 Gas (suction/discharge)
 Lube Oil
- Oil Sampling
• Preventative Maintenance
- Filter Changes (per dP monitoring or periodically based on
IOM)
 Lube Oil
 Seal gas
- Oil Conditioning (based on oil analysis)
- Check manual for all recommended PM tasks
42
© 2017 UOP LLC. A Honeywell Company All rights reserved.
Start-Up/Shutdown
Separex™ Membrane System
 PV Gas Ca Mau GPP Project
• Main Steps for Start-Up:
- PRETREATMENT START-UP
 Pressurization
 Warm-Up
- INITIAL MEMBRANE BANK START-UP
 Assure Initial Membrane Bank is Ready
 Pressurize Membrane Bank
 Warm-Up Membrane Bank
 Permeate Pressure Reduction
- START-UP ADDITIONAL MEMBRANE BANK
 Pressurize Membrane Bank
 Warming-Up Membrane Bank
 Permeate Pressure Reduction
Start-Up Steps – Overview
44
1. All blinds are in positions shown per P&ID’s.
2. All pressure relief devices are online, tested and installed. Any isolation valves
must be locked open or car sealed open (CSO).
3. The utilities, sewers, and flare header are purged and in service.
4. All instruments (sensors, controllers, etc.) are calibrated and commissioned
5. All drains and vent valves to atmosphere are closed, plugged, or blinded.
6. The proper quantity and quality of nitrogen is available.
7. All equipment and associated piping is air-freed by purge with nitrogen.
8. All nitrogen isolation valves closed and bleed valves open.
9. All manual vent valves to the relief header are closed.
10. All process valves for on-line sample points are lined up for service.
11. All process root valves for Pressure and Pressure Differential instruments
(indicators, switches, and transmitters) are lined up for service.
12. Feed Gas and Residual Gas Shut down valves (SDVs) are closed.
13. All blowdown valve (BDVs) are closed.
14. Verify that all membrane bank isolation and startup valves are closed.
GENERAL PRE-STARTUP CHECKLIST
45
Step Location Description Chk
1 CCR Verify Plant Emergency Shutdowns have been RESET
2 CCR Confirm adequate feed gas pressure (~54 bar(g)) and flow (2.04 lean/.95
rich mmscmd to membranes) is available for start-up at upstream unit.
3 CCR Close and confirm closed the following automated valves:
 Shutdown Valves: 4090, 4094 and 4095
 Permeate Pressure control valve
 Close membrane bypass valve
4 Field Confirm all manual valves per checklist (to be determined) are closed prior
to start-up.
5 Field
Field
Position one operator at the 2” Pressurization by-pass valve L1D1 1600.
He/she will have to slowly open the valve in order to pressurize this
section.
Another operator should be positioned at PI 4091 to supervise
pressurization of the pre-treatment section.
6 Field Slowly open 2” Pressurization by-pass valve L1D1 1600.
Pressurization rate should be no higher than 3.5 bar/minute.
CAUTION: To prevent damage to filter coalescer and other downstream
equipment, the pressurization rate must not exceed 3.5 bar/minute.
7
CCR
Field
When the pre-treatment section pressure reaches approximately operating
pressure, pressurization is complete.
Therefore:
Open 10” Pre-treatment section isolation valve SDV4090.
And then,
Close 2” Pressurization by-pass valve L1D1 1600 once SDV4090 is fully
opened.
8 Field Drain any liquids in feed gas at Filter Coalescer manual drain valves.
CAUTION: Membrane elements can suffer permanent damage from
contact with liquids.
9
Field
Field
CCR
After pressurization is complete, the next step is to adjust the inlet gas
temperature to meet the target.
Therefore,
Open 2” Pre-treatment warm-up isolation valve G1D1 1212.
And then,
Slowly Open 2” Pre-treatment warm-up valve and L1D1 1617. Adjust it to
achieve a desired feed flow of: 30% of the design flowrate.
Request flow rate confirmation from CCR at upstream unit flow meter.
10 CCR When the pre-treatment section temperature reaches target temperature
per heat and weight balance at TI 4003B the temperature adjustment step
is complete.
Pre-treatment Section Start-up
46
Step Location Description
1
CCR
CCR
Field
Field
Field
In order to start-up the Membrane section, Confirm it is depressurized – Check the following pressure instruments
indication:
 PI-4411B – Bank 1 Permeate Line
 PI-4411A – Bank 1 Residue Line
 PT-4094 –Permeate Line
 PT-4095 –Residue Line
If Membrane section is not fully depressurized, open 2” Permeate start-up valve B1D1 2433 and 2” Permeate
start-up isolation valve L1D1 2612.
Allow to depressurize for a few minutes. After confirmation, close B1D1 2433 and L1D1 2612.
CAUTION:
Membranes kept under a nitrogen blanket will have equal residual and permeate pressures. If depressuring
manually always open the permeate startup valve FIRST. Inadvertent opening of the residual startup valve can
cause a reverse pressurization where the permeate pressure will become higher than the residual. This can cause
permanent damage to the membranes. Check valves at the end of each membrane element string are intended to
avoid damage, but they should not be relied upon.
When Membrane Section prsure is fully depressurized, start-up may proceed.
2 Field Confirm all manual valves per Appendix A are closed prior to start-up.
3
Field
Field
Field
Field
Field
Prior to start, Open the following valves:
- 6” Bank 1 feed isolation valve B1D1 2409.
- 2” Bank 1 permeate isolation valve L1D1 2612.
- 2” Bank 1 residue isolation valve L1D1 2611.
After that,
Slowly open 2” Membrane 1 feed by-pass valve L1D1 2604 and maintain a pressurization rate of 3.5 bar/minute to
pressurize Membrane 1.
Operator to monitor the pressurization rate at PI 4411B (Membrane 1 permeate line) and PT-4411A (Membrane 1
residue line).
4 CCR
Field
Field
CCR
When permeate pressure PI4411B is ~ 5 bar(g), crack OPEN - 2” Permeate start-up valve B1D1 2433.
Adjust the 2” Permeate start-up valve B1D1 2433 to ALWAYS maintain permeate pressure lower than residual by
5 bar†.
Operator to monitor residue pressure at PI 4411A.
Operator to monitor permeate pressure at PI 4411B.
† - CAUTION: Allowing permeate pressure to approach or exceed residue pressure can damage the membranes.
Always maintain permeate pressure 5 bar lower than residual throughout the procedure. An operator should be
stationed at the 2” Permeate start-up valve B1D1 2433 at all times.
An excessive rate of pressurization or depressurization higher than 3.5 bar/minute can also damage the
membranes. These events can occur if the residue start-up valve is opened too quickly.
The above two warnings apply throughout the remainder of the procedure.
MEMBRANE BANK STARTUP
47
Step Location Description
5 CCR
Field
Field
CCR
When residue pressure PI 4411A is approximately 13-15 bar(g), crack-open 2” Residue
start-up valve B1D1 2432 to establish some flow through the membranes.
Adjust 2” Permeate start-up valve B1D1 2433 to maintain a pressure difference
between residue and permeate pressures (PI 4411A – PI 4411B) of ~ 5 bar.
6 CCR
Field
Field
Keep the pressurization rate at 3.5 bar/minute. Bank 1 is fully pressurized when feed
pressure minus residue pressure is less than 3 bar (PI 4411A – PI 4411B < 3 bar).
Then:
Open 6” Bank 1 feed valve B1D1 2408.
After that,
Close 2” Bank 1 feed by-pass valve L1D1 2604 once B1D1 2408 is fully opened.
7 Field
Field
Further open 2” Residue start-up valve B1D1 2432 while maintaining permeate 5 bar
lower until target gas flow is achieved:
At Pre-treatment Section, gradually close the 2” Pre-treatment warm-up valve L1D1
1617 to allow the required flow through the Membrane Section and out the residual
startup line.
8
CCR
CCR
Monitor temperature difference between:
TI-4003A (Membrane Feed)
and
TI-4411 (Bank 1 Residual Gas).
When temperature difference (TI-4403A – TI-4411) is within 10ºC, then Membrane 1 is
warmed-up.
9 CCR
CCR
CCR
Contact Control Room prior to line-up the residue gas to downstream unit. Slowly open
B1D1 2422 and B1D1 2423.
After confirmation,
Slowly open 2” pressurization valve on residue header L1D1 2613. Monitor pressure till
both sides of the valve has equalized.
Open Shutdown valve SDV4095.
MEMBRANE BANK STARTUP
48
MEMBRANE BANK STARTUP
Step Location Description
10 Field
Field
Slowly close 2” Residue start-up valve L1D1 2611 ensuring feed gas flow is not reduced.
After that, close 2” Residue startup isolation valve B1D1 2432 once L1D1 2611 is fully
closed.
11 Field
Field
At Pre-treatment Section, completely close the 2” Pre-treatment warm-up valve L1D1
1617
Then, close the 2” Pre-treatment warm-up isolation valve G1D1 1212.
12 Field After lining-up the residue to downstream unit, it is time to reduce the permeate pressure.
Open B1D1 2424 and B1D1 2425.
Therefore, further open 2” Permeate start-up valve B1D1 2433 to reduce pressure at a
rate of 3.5 bar/minute. Continue to open the valve until the target permeate pressure is
observed at PI 4411B.
Warning – If for any reason the Membrane feed flow rate falls below minimum flow rate
while permeate pressure is being reduced, then stop depressurization and increase
permeate pressure.
13 Field
Field
Open 8” Permeate valve SDV 4094. Keep PCV 4094A and PCV 4094B closed. Slowly
start to open the PCV with small increments.
IN CONJUNCTION
Slowly close 2” Permeate start-up valve B1D1 2433 while maintaining the desired
permeate pressure on PI 4411B. Then, close 2” Permeate start-up isolation valve L1D1
2612 once B1D1 2433 is fully closed.
14 CCR After the unit is started-up, switch TIC-4003B Setpoint to the required feed membrane
temperature.
49
MEMBRANE BANK SHUTDOWN
Step Location Description
1 Field
CCR
Field
Prior to shut down of the Separex™ Membrane Skid,
station an operator at:
2” Permeate vent valve B1D1 2433 and 2” L1D1 2612
Also,
Station an operator at 6” D-4411 Bank feed valve
B1D1 2408 if D-4411 Bank is to be taken off-line.
2
Field
If one membrane skid is to be closed, adjust FCV
4092 accordingly to divert some flow from membranes
to the bypass line. Reduce the total feed to no more
than can be handled by the numbers of sections to be
used.
Close the valves below:
6” B1D1 2408 (Feed)
6” B1D1 2423 (Residue)
Open:
2” B1D1 2612 permeate vent valve
Partially open:
2” B1D1 2433 permeate vent valve
Close:
6” B1D1 2425 (Permeate)
Open:
2” L1D1 2611 residue vent valve but keep closed 2”
B1D1 2432.
50
MEMBRANE BANK SHUTDOWN
Step Location Description
3
Field
CCR
Field
Crack Open:
2” residue vent valve to reduce residual pressure at 3.5 to 5 bar(g) per
minute.
Operator to monitor residue PI 4411A if Bank 1 is to be taken off.
Do not open the residual vent valve so far that the residual pressure
drops to near the permeate pressure. The residual pressure must always
be at least 7 bar(g) higher than the permeate pressure until the end of
depressurization.
CAUTION: An excessive rate of depressurization higher than 3.5 to 5
bar/minute can also damage the membranes. These events can occur if
the residue start-up valve is opened too quickly.
4 CCR
Field
CCR
Field
Field
Field
Field
When the residue PI 4411A reaches a pressure of ~7 bar(g)
Open further 2” permeate vent valve B1D1 2433 and allow the residue to
depressurize through it.
When the residue pressure PI 4411A drops to below 1 bar (g) seen at
pressure PI 4411B, Close:
2” Residue vent start-up valve L1D1 2611.
2” Residue start-up isolation vent valve B1D1 2432
2” Permeate start up vent isolation valve L1D1 2612
2” Permeate start-up vent isolation valve B1D1 2433
5 After depressurization is complete, purge and add nitrogen blanket if the
membrane section is to be offline for more than an hour.
51
© 2017 UOP LLC. A Honeywell Company All rights reserved.
Normal Operations and Troubleshooting
Separex™ Membrane System
 PV Gas Ca Mau GPP Project
Membrane Mechanical Damage
• Reverse Pressure Differential
- Occurs when Permeate Pressure > Feed or Residual Pressure
- Membrane cracks at adhesive lines
- Most likely to occur on shutdown or purging
- Indicated by increased H/C losses to permeate
- Be aware of system conditions at all times
53
Membrane Mechanical Damage (continued)
• High Flow per Operating Area (# tubes online)
- On startup or at changes in system capacity
- During system upsets
- Also may be caused by flow surge
- Elements can ‘telescope’ and damaged
- Indicated by increased Hydrocarbon losses to permeate
54
Membrane Mechanical Damage (continued)
• Rapid Depressurization
- Occurs when banks or skid depressurizing valves opened too
quickly
- Depressurization is a manual operation
- When depressurizing individual bank, use ~15 minute criteria
for depressurizing.
- Crack open valve initially and then open more as pressure
decreases (< 5bar/minute)
55
Membrane Contaminant Damage
• Liquids
- Chemical injection such as methanol
- Upstream unit malfunction
- Filter Coalescer malfunction
- Poor commissioning
- Feed temperature control failure
• Particulate Damage
- Occurs when particle filter malfunctions
- Usually due to operator inattention
- Particles of corrosion products or activated carbon fines clog the
membrane elements
- May result in high HC losses
56
Hydrocarbon Dew Point
• Condensation within the
membrane will damage it’s
elements
• Residual stream temperature
must always be 5C above the
calculated dew point (dew point
margin) to guard against
condensation
• Factors affecting dew point
- Permeate pressure
- Number of membrane
sections
- Membrane feed temperature
• There is no major concern due
to cryo unit residue gas dew
point being low
57
T
J-T effect
HC Dewpoint
HC DEWPOINT
MARGIN
Membrane Mechanical Damage
58
System Optimization
• Goals
- Target Export Gas CO2 specifications
- Maximize sales gas production
- Minimize hydrocarbon losses
- Maximize membrane life
• Why optimize?
- Too low residue gas CO2 = more hydrocarbon losses
 Higher CO2 removal = higher CO2 and methane slippage
- Too high membrane feed gas temperature = more hydrocarbon losses
- Too high permeate pressure = more hydrocarbon losses
- Too high residue gas CO2 = off-spec HHV
59
Membrane Optimization
• Methods
- Operating Condition Adjustments
 Feed flow
 Lowest feed temperature
 Feed pressure (to a more limited extent)
 Lowest permeate pressure
- Membrane Area Adjustment
• Lean Case
- The Normal LEAN case requires all 4 banks in
operation, while the Normal RICH case requires only
one bank in operation
- Load 10 elements per tube (5 on each side)
60
Operations Adjustment
Control Variables
• A: Number Banks Online (Membrane Area)
• T: Feed Temperature (A-3001 outlet)
• P1: Feed Pressure (discharge of compressor, indirect
control)
• P2: Permeate Pressure
• F: Feed Flow (to an extent, indirect control)
• F1: Bypass
P1
F FEED
RESIDUAL GAS
T P2A
PERMEATE
F1
61
Membrane Operating Variables
Process Variable
Effect on Residual Composition
(with fixed membrane area)
Increased Feed Flowrate Higher CO2 content
Decreased Feed Flowrate Lower CO2 content
Increased Membrane Feed Temperature Lower CO2 content
Decreased Membrane Feed Temperature Higher CO2 content
Increased Feed Pressure Lower CO2 content
Decreased Feed Pressure Higher CO2 content
Increased Permeate Pressure Higher CO2 content
Decreased Permeate Pressure Lower CO2 content
Increased Feed CO2 Content Higher CO2 content
Decreased Feed CO2 Content Lower CO2 content
62
Membrane Operating Conditions
FEED FLOW
• An Increase in Feed Gas Flow results in:
- Increase of CO2 Content of Residual/Sales Gas
- Can cause mechanical damage to membrane if above design or
too little area for the feed rate
• A Decrease in Feed Gas Flow results in:
- Reduction of CO2 Content in Residual/Sales Gas
- Higher hydrocarbon losses
- Can potentially cause hydrocarbon condensation and membrane
damage if flow or operating temperature is too low
 Not expected to be a major issue here since dew point of gas is
already low to the membrane unit
63
Membrane Operating Conditions (continued)
TEMPERATURE
• An Increase in Operating Temperature results in:
- Reduction of CO2 Content of Residual/Sales Gas
- Increase of permeate flow (higher hydrocarbon losses)
• A Decrease in Operating Temperature results in:
- Increase in CO2 Content of Residual/Sales Gas
- Reduction of permeate flow (lower hydrocarbon losses)
- Can cause hydrocarbon condensation and membrane damage if operating
temperature is too low
64
FEED PRESSURE
• An Increase in Operating Pressure results in:
- Reduction of CO2 Content of Residual/Sales Gas
- Increase of permeate flow (higher hydrocarbon losses)
• A Decrease in Operating Pressure results in:
- Increase in CO2 Content of Residual/Sales Gas
- Reduction of permeate flow (lower hydrocarbon losses)
Membrane Operating Conditions (continued)
65
PERMEATE PRESSURE
• An Increase in Permeate Pressure results in:
- Increase in CO2 Content of Residual/Sales Gas
- Reduction of permeate flow
• A Decrease in Permeate Pressure results in:
- Reduction of CO2 Content of Residual/Sales Gas
- Increase of permeate flow
- Typically improves selectivity – decreases hydrocarbon concentration
in permeate
Membrane Operating Conditions (continued)
66
Membrane Operating Conditions (continued)
MEMBRANE AREA
• An Increase in Membrane Area results in:
- Reduction of CO2 Content of Residual/Sales Gas
- Increase of permeate flow (higher hydrocarbon losses)
• A Decrease in Primary Membrane Area results in:
- Increase of CO2 Content of Residual/Sales Gas
- Reduction of permeate flow (lower hydrocarbon losses)
67
Can only be increased in increments.
Do not operate below minimum or above maximum flow for the # of
membrane tubes online
Optimization Flow Chart
Plant Operation
Stable
CO2 in
Sales Gas at
at 8%?
Plant is
operating in
Specification
Sales CO2
Concentration?
Do one of the
following:
2) Increase
Permeate
backpressure
3) Increase feed
gas flow
Shut down a
membrane bank
Do one of the
following:
3) Decrease feed
gas flow
Below 8% Above 8%
Yes
2) Increase
feed gas
temperature
1) Decrease
feed gas
temperature
Can 1 bank be
Taken off-line?
No
Yes Yes
No
Can 1 bank be
Be put on-line?
Start up a
membrane bank
No
In order of preference In order of preference
1) Decrease
permeate
pressure
68
Filter Coalescer
69
Filter Coalescer
Primary Symptom Local Causes Remedy
Liquid carryover Filter Coalescer cartridge rupture
High delta P (then low dP)
Feed surge
Pressure surge
Filter Coalescer cartridge plugged
High delta P
High solids ingress
Bypass the whole
unit for filter
cartridge
replacement if
possible, replace
cartridges
High level in Filter Coalescer due to:
Excessive liquids load
Plugged LCV
Level instrument malfunction
Troubleshoot
upstream unit
Isolate & clean
LCV
Repair instrument
malfunction
Follow specific recommendations from coalescer vendor
Membrane Unit
Membrane Unit
Symptom Local Causes Remedy
Low feed temperature to
membranes
Residue Gas Cooler or
upstream issues
Troubleshoot Residue Gas
Cooler or upstream issues
High feed temperature
to Membranes
Residue Gas Cooler or
upstream issues
Troubleshoot Residue Gas
Cooler or upstream issues
High CO2 content in
residual gas
Permeate pressure set too
high
Lower permeate pressure
set point
Increased feed gas flow rate
or CO2 composition
Lower permeate pressure.
Raise Membrane Feed
Temperature
Start additional membrane
bank/section/skid
Damaged membranes due to
condensation, or aging; or
feed gas flow or composition
too high for design.
Add, and/or replace
elements in tubes
Reduce feed gas flow or
CO2 level
70
Membrane Unit
Membranes Unit
Symptom Local Causes Remedy
Low CO2 content in
residual gas/ poor
hydrocarbon recovery
Permeate pressure set too
low
Raise permeate pressure
control set point,
investigate downstream
compression
Decrease in feed flow rate
or composition (low CO2)
1. Raise permeate
pressure
2. Lower Membrane
Feed Temperature
3. Remove membranes
sections
Feed flow rate and/or
composition too low,
outside of design range
1. Increase feed gas flow
2. Remove membrane
sections or elements
per tube
Feed pressure too high 1. Decrease feed gas
pressure
2. Remove membrane
sections
71
Membrane Unit
Membranes Unit
Symptom Local Causes Remedy
Decrease in permeate CO2
concentration, increase in
hydrocarbon concentration
Elements are damaged and
leaking
Find tube with leaking
element by performing
thermal scan.
Replace elements at
cold tubes
72
Damaged Element – Visual Inspections
73
New Membrane element
Thermal Scanning
• Quickly identify tubes with potential damaged elements based
on permeate tube temperatures
• Use thermal IR gun or similar
• Aim directly onto the permeate pipe exiting each membrane
tube
- Do not scan on pipe insulation
• Scan similar position for all permeate pipes
- Suggestion: complete at night – minimize impact of sunlight
• Can also be completed on the residual gas exit nozzles
• Record:
- Temperature
- Skid/tube number/permeate or residual
- Populate data into the excel sheet
74
Thermal Scanning
• Tubes should have similar permeate temperatures
• Tubes with severely leaking/damaged elements should show
colder permeate temperature
- More flow from high pressure to low pressure Joule Thompson
effect
• Statistics/data graphs can help identify which tubes may have
leaking elements
75
Good Thermal Scan Data
• All permeate tubes: similar temperature
- Not a lot of scatter in the data: data points all between 47-48C
76
40
41
42
43
44
45
46
47
48
49
1 3 5 7 9 11 13 15
PermeateTemperature,DegC.
Tube
Suspected Tube with Leak- Thermal Scan Data
• One tube temperature significantly different than the others
77
38.0
38.5
39.0
39.5
40.0
40.5
41.0
41.5
42.0
42.5
43.0
43.5
1 3 5 7 9 11 13 15
PermeateTemperature,DegC.
Tube
Tube with potential leaking/damaged element
78
UOP 7116-78

More Related Content

What's hot

Amine Gas Treating Unit - Best Practices - Troubleshooting Guide
Amine Gas Treating Unit  - Best Practices - Troubleshooting Guide Amine Gas Treating Unit  - Best Practices - Troubleshooting Guide
Amine Gas Treating Unit - Best Practices - Troubleshooting Guide Gerard B. Hawkins
 
Gas Plant Separator Design
Gas Plant Separator DesignGas Plant Separator Design
Gas Plant Separator Designiyaselex
 
Trays in distillation column
Trays in distillation columnTrays in distillation column
Trays in distillation columnShaukat Ali
 
Troughed Belt Conveyor & Flat Belt Conveyor
Troughed Belt Conveyor & Flat Belt ConveyorTroughed Belt Conveyor & Flat Belt Conveyor
Troughed Belt Conveyor & Flat Belt ConveyorMAKAUT
 
6. phase separatation
6. phase separatation6. phase separatation
6. phase separatationElsayed Amer
 
Overview of subsea production systems
Overview of subsea production systemsOverview of subsea production systems
Overview of subsea production systemsGiuseppe Moricca
 
Dr. Aborig Lecture- Chapter 3 natural gas processing
Dr. Aborig Lecture- Chapter 3 natural gas processingDr. Aborig Lecture- Chapter 3 natural gas processing
Dr. Aborig Lecture- Chapter 3 natural gas processingamaborig
 
Belt conveyor and its type
Belt conveyor and its typeBelt conveyor and its type
Belt conveyor and its typebenitesh
 
Introduction To Pressure Surge In Liquid Systems
Introduction To Pressure Surge In Liquid SystemsIntroduction To Pressure Surge In Liquid Systems
Introduction To Pressure Surge In Liquid SystemsGerard B. Hawkins
 
Design of Gas and Oil Separator 2023.pdf
Design of Gas and Oil Separator 2023.pdfDesign of Gas and Oil Separator 2023.pdf
Design of Gas and Oil Separator 2023.pdfAl AYAn University
 
Filter bag sdl presentation v3
Filter bag sdl presentation v3Filter bag sdl presentation v3
Filter bag sdl presentation v3UNIDO SA
 
Well abandonment process procedures
Well abandonment process proceduresWell abandonment process procedures
Well abandonment process proceduresDrilling Manual
 
SNUBBING UNIT Presentasi.pptx
SNUBBING UNIT Presentasi.pptxSNUBBING UNIT Presentasi.pptx
SNUBBING UNIT Presentasi.pptxGorillasNgobam
 

What's hot (20)

Amine Gas Treating Unit - Best Practices - Troubleshooting Guide
Amine Gas Treating Unit  - Best Practices - Troubleshooting Guide Amine Gas Treating Unit  - Best Practices - Troubleshooting Guide
Amine Gas Treating Unit - Best Practices - Troubleshooting Guide
 
Gas Plant Separator Design
Gas Plant Separator DesignGas Plant Separator Design
Gas Plant Separator Design
 
Dust collection system
Dust collection  systemDust collection  system
Dust collection system
 
Dust collector filter bag specification
Dust collector filter bag specificationDust collector filter bag specification
Dust collector filter bag specification
 
Trays in distillation column
Trays in distillation columnTrays in distillation column
Trays in distillation column
 
Belt conveyor foundtions 3
Belt conveyor foundtions 3 Belt conveyor foundtions 3
Belt conveyor foundtions 3
 
Troughed Belt Conveyor & Flat Belt Conveyor
Troughed Belt Conveyor & Flat Belt ConveyorTroughed Belt Conveyor & Flat Belt Conveyor
Troughed Belt Conveyor & Flat Belt Conveyor
 
6. phase separatation
6. phase separatation6. phase separatation
6. phase separatation
 
Oil and gas separators
Oil and gas separatorsOil and gas separators
Oil and gas separators
 
Overview of subsea production systems
Overview of subsea production systemsOverview of subsea production systems
Overview of subsea production systems
 
Dr. Aborig Lecture- Chapter 3 natural gas processing
Dr. Aborig Lecture- Chapter 3 natural gas processingDr. Aborig Lecture- Chapter 3 natural gas processing
Dr. Aborig Lecture- Chapter 3 natural gas processing
 
Belt conveyor and its type
Belt conveyor and its typeBelt conveyor and its type
Belt conveyor and its type
 
Distillation Basics(Done).ppt
Distillation Basics(Done).pptDistillation Basics(Done).ppt
Distillation Basics(Done).ppt
 
Belt conveyor
Belt conveyorBelt conveyor
Belt conveyor
 
Introduction To Pressure Surge In Liquid Systems
Introduction To Pressure Surge In Liquid SystemsIntroduction To Pressure Surge In Liquid Systems
Introduction To Pressure Surge In Liquid Systems
 
Design of Gas and Oil Separator 2023.pdf
Design of Gas and Oil Separator 2023.pdfDesign of Gas and Oil Separator 2023.pdf
Design of Gas and Oil Separator 2023.pdf
 
Filter bag sdl presentation v3
Filter bag sdl presentation v3Filter bag sdl presentation v3
Filter bag sdl presentation v3
 
Well abandonment process procedures
Well abandonment process proceduresWell abandonment process procedures
Well abandonment process procedures
 
SNUBBING UNIT Presentasi.pptx
SNUBBING UNIT Presentasi.pptxSNUBBING UNIT Presentasi.pptx
SNUBBING UNIT Presentasi.pptx
 
Understanding the Nutsche Filtration and Drying Process
Understanding the Nutsche Filtration and Drying ProcessUnderstanding the Nutsche Filtration and Drying Process
Understanding the Nutsche Filtration and Drying Process
 

Similar to 11. membrane unit

Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)SAJJAD KHUDHUR ABBAS
 
compressor Operation pdf.pdf
compressor Operation pdf.pdfcompressor Operation pdf.pdf
compressor Operation pdf.pdfyusuf699644
 
Compressor operation.pdf
Compressor operation.pdfCompressor operation.pdf
Compressor operation.pdfMBouderbala
 
Fulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewFulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewMark Platten
 
WSM Yard-High-Pressure Safety-22.12.19
WSM Yard-High-Pressure Safety-22.12.19WSM Yard-High-Pressure Safety-22.12.19
WSM Yard-High-Pressure Safety-22.12.19SARWAR SALAM
 
Fuel gas system of gas production
Fuel gas system of gas productionFuel gas system of gas production
Fuel gas system of gas productionPhyoe Maung Maung
 
Relief Systems.pdf
Relief Systems.pdfRelief Systems.pdf
Relief Systems.pdfKAhmedRehman
 
Oxygen MANUFACTRE STORAGE PREPERATION AND CLINICAL ASPECT
Oxygen  MANUFACTRE STORAGE PREPERATION AND CLINICAL ASPECTOxygen  MANUFACTRE STORAGE PREPERATION AND CLINICAL ASPECT
Oxygen MANUFACTRE STORAGE PREPERATION AND CLINICAL ASPECTDr.RMLIMS lucknow
 
Wellhead and christmas tree components, functions and more
Wellhead and christmas tree components, functions and moreWellhead and christmas tree components, functions and more
Wellhead and christmas tree components, functions and moreMohamed Abdelshafy Abozeima
 
wellheads-170105153648 (1).pdf
wellheads-170105153648 (1).pdfwellheads-170105153648 (1).pdf
wellheads-170105153648 (1).pdfAZLANAiyub
 
Condensate Return Solutions.ppt
Condensate Return Solutions.pptCondensate Return Solutions.ppt
Condensate Return Solutions.pptssuser8006c7
 
910 System Overview
910 System Overview910 System Overview
910 System OverviewDaveSheasby
 
Final Design Presentation (1) (1)
Final Design Presentation (1) (1)Final Design Presentation (1) (1)
Final Design Presentation (1) (1)Craig Medlin
 
Basics Of Pricess Plant Piping System Design .pdf
Basics Of Pricess Plant Piping System Design .pdfBasics Of Pricess Plant Piping System Design .pdf
Basics Of Pricess Plant Piping System Design .pdfVenkataSivaNagaSai
 

Similar to 11. membrane unit (20)

Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION
 
Episode 34 : Project Execution Part (5)
Episode 34 :  Project Execution Part (5)Episode 34 :  Project Execution Part (5)
Episode 34 : Project Execution Part (5)
 
compressor Operation pdf.pdf
compressor Operation pdf.pdfcompressor Operation pdf.pdf
compressor Operation pdf.pdf
 
Compressor operation.pdf
Compressor operation.pdfCompressor operation.pdf
Compressor operation.pdf
 
Fulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewFulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For review
 
WSM Yard-High-Pressure Safety-22.12.19
WSM Yard-High-Pressure Safety-22.12.19WSM Yard-High-Pressure Safety-22.12.19
WSM Yard-High-Pressure Safety-22.12.19
 
Lessons learned solving pilot valve instability issues on LNG storage tanks
Lessons learned solving pilot valve instability issues on LNG storage tanksLessons learned solving pilot valve instability issues on LNG storage tanks
Lessons learned solving pilot valve instability issues on LNG storage tanks
 
Fuel gas system of gas production
Fuel gas system of gas productionFuel gas system of gas production
Fuel gas system of gas production
 
Packers GFK
Packers GFKPackers GFK
Packers GFK
 
Relief Systems.pdf
Relief Systems.pdfRelief Systems.pdf
Relief Systems.pdf
 
Relief systems
Relief systemsRelief systems
Relief systems
 
Oxygen MANUFACTRE STORAGE PREPERATION AND CLINICAL ASPECT
Oxygen  MANUFACTRE STORAGE PREPERATION AND CLINICAL ASPECTOxygen  MANUFACTRE STORAGE PREPERATION AND CLINICAL ASPECT
Oxygen MANUFACTRE STORAGE PREPERATION AND CLINICAL ASPECT
 
Piping hydrotest
Piping hydrotestPiping hydrotest
Piping hydrotest
 
Wellhead and christmas tree components, functions and more
Wellhead and christmas tree components, functions and moreWellhead and christmas tree components, functions and more
Wellhead and christmas tree components, functions and more
 
wellheads-170105153648 (1).pdf
wellheads-170105153648 (1).pdfwellheads-170105153648 (1).pdf
wellheads-170105153648 (1).pdf
 
Condensate Return Solutions.ppt
Condensate Return Solutions.pptCondensate Return Solutions.ppt
Condensate Return Solutions.ppt
 
910 System Overview
910 System Overview910 System Overview
910 System Overview
 
Final Design Presentation (1) (1)
Final Design Presentation (1) (1)Final Design Presentation (1) (1)
Final Design Presentation (1) (1)
 
Basics Of Pricess Plant Piping System Design .pdf
Basics Of Pricess Plant Piping System Design .pdfBasics Of Pricess Plant Piping System Design .pdf
Basics Of Pricess Plant Piping System Design .pdf
 
Manual filtro pentair
Manual filtro pentair Manual filtro pentair
Manual filtro pentair
 

Recently uploaded

Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)simmis5
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdfKamal Acharya
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Bookingdharasingh5698
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxfenichawla
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGSIVASHANKAR N
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 

Recently uploaded (20)

Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Online banking management system project.pdf
Online banking management system project.pdfOnline banking management system project.pdf
Online banking management system project.pdf
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptxBSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
BSides Seattle 2024 - Stopping Ethan Hunt From Taking Your Data.pptx
 
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTINGMANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
MANUFACTURING PROCESS-II UNIT-1 THEORY OF METAL CUTTING
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 

11. membrane unit

  • 1. © 2017 UOP LLC. A Honeywell Company All rights reserved. Introduction Separex™ Membrane System  PV Gas Ca Mau GPP Project
  • 2. • Membrane Separation Principles and Overview • Pre-treatment Equipment and Operations • Membrane pre-commisioning activities and element loading • Startup/Shutdown • Normal Operations and Troubleshooting Course Learning Objectives 1
  • 3. Regions of Use for CO2 Removal Technologies 1000 100 10 1.0 0.1 Scavengers MolSiv ™ PSA Selexol™ Amine Guard™ FS Membrane Benfield™ PartialPressureAcidGasinFeed,psia Partial Pressure Acid Gas in Product, psia 0.001 0.01 0.1 1.0 10 100 1000 100 10 1.0 0.1 2
  • 5. Do’s  Bulk CO2 removal  Variety of CO2 feeds  Offshore, remote, difficult locations. modular  Medium to high pressure (> 600 psig)  CO2 is a product (re-injection, fuel gas) Don'ts  Try to get CO2 to ppm levels (like feed gas for LNG production)  H2S to ppm levels  Low feed gas pressure Separex Membrane – Do’s and Don'ts 4
  • 6. Membrane Principles • Membranes separate components by a solution and diffusion mechanism - More soluble components permeate quicker • Not a filtration process • Separation is not perfect 5
  • 7. Relative Permeation Rates H2S, CO2, O2 H2O, H2, He Fastest  Most Soluble  Least Soluble CO, CH4, N2, C2+ Slowest CO, CH4, N2, C2+ H2S, CO2, O2 M e m b r a n e 6
  • 8. Selectivity of CO2 Membranes UOP 4375C-06 UOP Confidential Fast Slow HighPressure LowPressure H2O, H2S CO2 (+ small amount of hydrocarbons) Hydrocarbons 7
  • 9. Driving Force M e m b r a n e PCO2 High Pressure (Feed) Low Pressure (Permeate) Pressure Differential Across The Membrane PCO2 8
  • 10. Membrane Elements – Spiral Wound 9
  • 11. Spiral Wound Membrane Element 8” Dia x 40” Long 40 lbs (18 kg) 10
  • 13. Spiral Wound Membrane Tube Residual FeedPermeate Inlet Seal (U-Cup) Membrane Elements Membrane Housing Permeate Tube Clamp Permeate Standoff Tube Taper-Lok Enclosure Taper-Lok Enclosure 12
  • 14. © 2017 UOP LLC. A Honeywell Company All rights reserved. Design Basis Separex™ Membrane System  PV Gas Ca Mau GPP Project
  • 15. PV Gas Membrane Pretreatment  Performs well on light clean feed gas  6-Month / 1-year maintenance cycle  No dew point control downstream of cryo unit Residue Gas Cooler A-3001Feed Membrane X-4092 Filter Coalescer F-4091 14
  • 16. PV Gas Separex and Pretreatment Skid 15
  • 17. Process Flow Scheme Diagram 16
  • 18. Design Basis • Sales Gas Specification: - Maximum CO2 content: 8.0 mol% - Minimum Gross Heating Value: 37.0 MJ/m3 • After separating the NGLs from the feed gas, - Residue gas CO2 concentration > the specification of 8.0 mol%. - Gross heating value lower than the required minimum of 37 MJ/m3. • A small amount of CO2 will be removed in the membrane unit to adjust the residue gas so that it is within the specifications. • The low pressure, CO2 rich permeate will be used for fuel in the HMO heaters and in the dehydration unit regeneration gas heater. 17
  • 19. © 2017 UOP LLC. A Honeywell Company All rights reserved. Membrane Pre-Commissioning Activities & Loading Separex™ Membrane System  PV Gas Ca Mau GPP Project
  • 20. Pre-Commissioning Understand: • Pre-commissioning Activities • Personal Protective Equipment and Safety Considerations • Pre-commissioning of Pretreatment • Pre-commissioning of Membrane • Leak Testing 19
  • 21. Pre-Commissioning Main Activities • P&ID Verification – Field verify including “as-built” mark-up • Equipment Verification – Installed per design • Line Cleaning – Confirm piping and headers been cleaned • Load vessels – Filter cartridges and adsorbent • Membrane Tubes – Clean membrane tubes and load elements 20
  • 22. Pre-Commissioning Main Activities • Instrumentation – Field verify instrumentation have been properly reinstalled • DCS/Instrumentation – Complete checks of field loops and DCS interface • SDV and BDV – Set and confirm limit switch operation • Control Valves – Set and confirm valve movement • Logic Check – Confirm functionality & verify proper responses/actions • ESD /DCS – Perform ‘dry tests’ to confirm C&E and field verify for proper actions • Line up PRVs – Confirm isolation valves in proper positions including car seals or locks installed • Leak Test – Audit flange tightness records. In controlled manner test to operating pressure to confirm no loose connections 21
  • 25. Main Pre-commissioning Activities • Inspect F-4091 vessel • Clean as needed • Install filter coalescer cartridges • Membrane Activities - Remove permeate headers and Taper-Lok flanges - Clean tubes - Load membrane elements - Reinstall Taper-Lok flanges and headers - Leak test - Nitrogen blanket 24
  • 26. Remove Taper-Lok Flanges • Erect scaffolding at residual end of membrane skid if needed • Prepare work area for removal of Taper-Lok flanges • Confirm each pair of Taper-Lok flanges clearly marked to aid reinstallation Residual end Taper-Lok flange Feed end Taper-Lok flange 25
  • 27. Taper Lok Ring and Permeate Tube Taper-Lok metal seal rings Taper-Lok flange with permeate standoff tube Poor practice – 2” flange resting on grating 26
  • 28. Tube Cleaning • Tube cleaning critical step prior to membrane loading • Required to remove: - Dirt - Debris - Scale - Rust - Corrosion inhibitor applied during fabrication  Cleaning will take more time • Prevents contamination of membrane elements, leading to poor performance • Not complicated 27
  • 29. Tube Cleaning • Pull rags/cleaning pig back and forth through tubes • Use solvent like mineral spirit or paint thinner • Continue until clean • Let any excess solvent weather off before loading membranes Tube cleaning is important but not complicated 28
  • 30. Tube Cleaning • Rags, foam, etc. • Pull back and forth through tube with rope 29
  • 31. Tube Before & After Cleaning Before Cleaning After Cleaning 30
  • 32. Before You Begin Loading • Develop a loading plan • Know which tubes will be opened • Know what you will do with removed elements (if applicable) • Know which elements will be added or replaced • Have log prepared to record element serial numbers and location inside the tube • Develop staging plan (clamps, pins, vacuum grease etc.) and equipment • Ensure no rain or humidity > 80% expected. If not possible: - Plan for shelter - Plan for humidity control UOP will advise on membrane loading activities at site 31
  • 33. Loading Precautions • Do not drop membrane elements • Do not expose membrane elements to water or excessive moisture/humidity • Do not expose membrane elements or tubes to excessive particulates (sand, etc.) • Do not allow element to rest on edges or points • If element is dropped or damage suspected, inform the UOP technical advisor • Open membrane packaging immediately prior to installation (staging consideration) • Keep tubes covered that are not being worked on 32
  • 34. Loading Precautions (continued) • Do not apply excessive force when snapping in clamp • Do not twist or turn elements once they are connected • Do not allow elements to hang on element connections – proper support required until the newly connected element is adequately inserted into the tube • Do not allow Taper-Lok flanges to hang on element connections – use support rods Always avoid excessive load onto elements by providing proper support (tray & support rods)!! 33
  • 35. Element Loading • Evenly apply grease to U-cup seal of next element • Install o-ring onto centering ring • Apply vacuum grease to o-ring • Stick greased o-ring/centering ring onto flange of first element • Place next element permeate tube against o-ring/centering ring on the first. Install clamp and pin • Push the element string into tube leaving ~ 6” (15cm) outside • Repeat until the proper number of elements have been installed 34
  • 36. Loading Procedure (cont.) • Install Taper-Lok metal seal ring - Seal ring can be reused if not damaged • Place greased o-ring/centering ring against permeate flange. Push Taper-Lok flange until its ‘stand-off’ tube flange is against the o-ring/centering ring • Connect element and stand-off tube with clamp and lock pin • Push Taper-Lok flange onto the tube flange and hot bolt • Remove support rods • Tighten bolts, using star pattern, to proper torque 35
  • 38. Element & Taper-Lok Stand-off Tube Connection Membrane connected to Taper Lok flange with permeate tube Do not forget the metal seal ring! 37
  • 39. Loading Procedure – Final Steps • Repeat procedure at next membrane tube until all tubes are loaded • Purge skid with nitrogen and maintain nitrogen blanket 38
  • 40. Nitrogen Purge • Nitrogen Purge and blanket all installed membrane elements when not in use • Always purge after exposing element to air • Always purge prior to opening the system for maintenance - Remove hydrocarbons - Purge to meet safety requirements (LEL – lower explosion limits, etc.) • Nitrogen is an asphyxiant – oxygen-deficient atmosphere may result • Never allow the permeate pressure to exceed the feed or residual pressures 39
  • 41. • Pre-treatment & Membrane skid/modules must be leak tested to operating pressure prior to introducing feed gas to the system • This procedure must be followed prior to the initial startup, after turnaround or after opening up significant components for maintenance purposes • If the unit is not to be started immediately, leave a nitrogen blanket until start-up • Do not exceed 5 bar/minute depressurization rate • Always depressurize downstream of filters (forward flow direction) to avoid damage to cartridges Leak Test 40
  • 42. Leak Test Depressurization Procedure – Membrane Section • If using process gas: - Must depressurize permeate and residual gas sides together always keeping permeate pressure 3-5 bar lower - Never depressurize via permeate side only - Never allow permeate pressure to exceed feed or residual gas pressure 41 Very important to always keep permeate pressure lower. Process gas must be depressurized from both sides to avoid liquids condensation and subsequent damage to membrane elements
  • 43. Residue Gas Compressor (Not in UOPR Scope) • Compresses residue gas to pipeline pressure • Two centrifugal compressors running in parallel - Not intended to be ran at the same time • Online Condition Monitoring - Continuous Vibration Monitoring - Temperatures  Gas (suction/discharge)  Lube Oil - Oil Sampling • Preventative Maintenance - Filter Changes (per dP monitoring or periodically based on IOM)  Lube Oil  Seal gas - Oil Conditioning (based on oil analysis) - Check manual for all recommended PM tasks 42
  • 44. © 2017 UOP LLC. A Honeywell Company All rights reserved. Start-Up/Shutdown Separex™ Membrane System  PV Gas Ca Mau GPP Project
  • 45. • Main Steps for Start-Up: - PRETREATMENT START-UP  Pressurization  Warm-Up - INITIAL MEMBRANE BANK START-UP  Assure Initial Membrane Bank is Ready  Pressurize Membrane Bank  Warm-Up Membrane Bank  Permeate Pressure Reduction - START-UP ADDITIONAL MEMBRANE BANK  Pressurize Membrane Bank  Warming-Up Membrane Bank  Permeate Pressure Reduction Start-Up Steps – Overview 44
  • 46. 1. All blinds are in positions shown per P&ID’s. 2. All pressure relief devices are online, tested and installed. Any isolation valves must be locked open or car sealed open (CSO). 3. The utilities, sewers, and flare header are purged and in service. 4. All instruments (sensors, controllers, etc.) are calibrated and commissioned 5. All drains and vent valves to atmosphere are closed, plugged, or blinded. 6. The proper quantity and quality of nitrogen is available. 7. All equipment and associated piping is air-freed by purge with nitrogen. 8. All nitrogen isolation valves closed and bleed valves open. 9. All manual vent valves to the relief header are closed. 10. All process valves for on-line sample points are lined up for service. 11. All process root valves for Pressure and Pressure Differential instruments (indicators, switches, and transmitters) are lined up for service. 12. Feed Gas and Residual Gas Shut down valves (SDVs) are closed. 13. All blowdown valve (BDVs) are closed. 14. Verify that all membrane bank isolation and startup valves are closed. GENERAL PRE-STARTUP CHECKLIST 45
  • 47. Step Location Description Chk 1 CCR Verify Plant Emergency Shutdowns have been RESET 2 CCR Confirm adequate feed gas pressure (~54 bar(g)) and flow (2.04 lean/.95 rich mmscmd to membranes) is available for start-up at upstream unit. 3 CCR Close and confirm closed the following automated valves:  Shutdown Valves: 4090, 4094 and 4095  Permeate Pressure control valve  Close membrane bypass valve 4 Field Confirm all manual valves per checklist (to be determined) are closed prior to start-up. 5 Field Field Position one operator at the 2” Pressurization by-pass valve L1D1 1600. He/she will have to slowly open the valve in order to pressurize this section. Another operator should be positioned at PI 4091 to supervise pressurization of the pre-treatment section. 6 Field Slowly open 2” Pressurization by-pass valve L1D1 1600. Pressurization rate should be no higher than 3.5 bar/minute. CAUTION: To prevent damage to filter coalescer and other downstream equipment, the pressurization rate must not exceed 3.5 bar/minute. 7 CCR Field When the pre-treatment section pressure reaches approximately operating pressure, pressurization is complete. Therefore: Open 10” Pre-treatment section isolation valve SDV4090. And then, Close 2” Pressurization by-pass valve L1D1 1600 once SDV4090 is fully opened. 8 Field Drain any liquids in feed gas at Filter Coalescer manual drain valves. CAUTION: Membrane elements can suffer permanent damage from contact with liquids. 9 Field Field CCR After pressurization is complete, the next step is to adjust the inlet gas temperature to meet the target. Therefore, Open 2” Pre-treatment warm-up isolation valve G1D1 1212. And then, Slowly Open 2” Pre-treatment warm-up valve and L1D1 1617. Adjust it to achieve a desired feed flow of: 30% of the design flowrate. Request flow rate confirmation from CCR at upstream unit flow meter. 10 CCR When the pre-treatment section temperature reaches target temperature per heat and weight balance at TI 4003B the temperature adjustment step is complete. Pre-treatment Section Start-up 46
  • 48. Step Location Description 1 CCR CCR Field Field Field In order to start-up the Membrane section, Confirm it is depressurized – Check the following pressure instruments indication:  PI-4411B – Bank 1 Permeate Line  PI-4411A – Bank 1 Residue Line  PT-4094 –Permeate Line  PT-4095 –Residue Line If Membrane section is not fully depressurized, open 2” Permeate start-up valve B1D1 2433 and 2” Permeate start-up isolation valve L1D1 2612. Allow to depressurize for a few minutes. After confirmation, close B1D1 2433 and L1D1 2612. CAUTION: Membranes kept under a nitrogen blanket will have equal residual and permeate pressures. If depressuring manually always open the permeate startup valve FIRST. Inadvertent opening of the residual startup valve can cause a reverse pressurization where the permeate pressure will become higher than the residual. This can cause permanent damage to the membranes. Check valves at the end of each membrane element string are intended to avoid damage, but they should not be relied upon. When Membrane Section prsure is fully depressurized, start-up may proceed. 2 Field Confirm all manual valves per Appendix A are closed prior to start-up. 3 Field Field Field Field Field Prior to start, Open the following valves: - 6” Bank 1 feed isolation valve B1D1 2409. - 2” Bank 1 permeate isolation valve L1D1 2612. - 2” Bank 1 residue isolation valve L1D1 2611. After that, Slowly open 2” Membrane 1 feed by-pass valve L1D1 2604 and maintain a pressurization rate of 3.5 bar/minute to pressurize Membrane 1. Operator to monitor the pressurization rate at PI 4411B (Membrane 1 permeate line) and PT-4411A (Membrane 1 residue line). 4 CCR Field Field CCR When permeate pressure PI4411B is ~ 5 bar(g), crack OPEN - 2” Permeate start-up valve B1D1 2433. Adjust the 2” Permeate start-up valve B1D1 2433 to ALWAYS maintain permeate pressure lower than residual by 5 bar†. Operator to monitor residue pressure at PI 4411A. Operator to monitor permeate pressure at PI 4411B. † - CAUTION: Allowing permeate pressure to approach or exceed residue pressure can damage the membranes. Always maintain permeate pressure 5 bar lower than residual throughout the procedure. An operator should be stationed at the 2” Permeate start-up valve B1D1 2433 at all times. An excessive rate of pressurization or depressurization higher than 3.5 bar/minute can also damage the membranes. These events can occur if the residue start-up valve is opened too quickly. The above two warnings apply throughout the remainder of the procedure. MEMBRANE BANK STARTUP 47
  • 49. Step Location Description 5 CCR Field Field CCR When residue pressure PI 4411A is approximately 13-15 bar(g), crack-open 2” Residue start-up valve B1D1 2432 to establish some flow through the membranes. Adjust 2” Permeate start-up valve B1D1 2433 to maintain a pressure difference between residue and permeate pressures (PI 4411A – PI 4411B) of ~ 5 bar. 6 CCR Field Field Keep the pressurization rate at 3.5 bar/minute. Bank 1 is fully pressurized when feed pressure minus residue pressure is less than 3 bar (PI 4411A – PI 4411B < 3 bar). Then: Open 6” Bank 1 feed valve B1D1 2408. After that, Close 2” Bank 1 feed by-pass valve L1D1 2604 once B1D1 2408 is fully opened. 7 Field Field Further open 2” Residue start-up valve B1D1 2432 while maintaining permeate 5 bar lower until target gas flow is achieved: At Pre-treatment Section, gradually close the 2” Pre-treatment warm-up valve L1D1 1617 to allow the required flow through the Membrane Section and out the residual startup line. 8 CCR CCR Monitor temperature difference between: TI-4003A (Membrane Feed) and TI-4411 (Bank 1 Residual Gas). When temperature difference (TI-4403A – TI-4411) is within 10ºC, then Membrane 1 is warmed-up. 9 CCR CCR CCR Contact Control Room prior to line-up the residue gas to downstream unit. Slowly open B1D1 2422 and B1D1 2423. After confirmation, Slowly open 2” pressurization valve on residue header L1D1 2613. Monitor pressure till both sides of the valve has equalized. Open Shutdown valve SDV4095. MEMBRANE BANK STARTUP 48
  • 50. MEMBRANE BANK STARTUP Step Location Description 10 Field Field Slowly close 2” Residue start-up valve L1D1 2611 ensuring feed gas flow is not reduced. After that, close 2” Residue startup isolation valve B1D1 2432 once L1D1 2611 is fully closed. 11 Field Field At Pre-treatment Section, completely close the 2” Pre-treatment warm-up valve L1D1 1617 Then, close the 2” Pre-treatment warm-up isolation valve G1D1 1212. 12 Field After lining-up the residue to downstream unit, it is time to reduce the permeate pressure. Open B1D1 2424 and B1D1 2425. Therefore, further open 2” Permeate start-up valve B1D1 2433 to reduce pressure at a rate of 3.5 bar/minute. Continue to open the valve until the target permeate pressure is observed at PI 4411B. Warning – If for any reason the Membrane feed flow rate falls below minimum flow rate while permeate pressure is being reduced, then stop depressurization and increase permeate pressure. 13 Field Field Open 8” Permeate valve SDV 4094. Keep PCV 4094A and PCV 4094B closed. Slowly start to open the PCV with small increments. IN CONJUNCTION Slowly close 2” Permeate start-up valve B1D1 2433 while maintaining the desired permeate pressure on PI 4411B. Then, close 2” Permeate start-up isolation valve L1D1 2612 once B1D1 2433 is fully closed. 14 CCR After the unit is started-up, switch TIC-4003B Setpoint to the required feed membrane temperature. 49
  • 51. MEMBRANE BANK SHUTDOWN Step Location Description 1 Field CCR Field Prior to shut down of the Separex™ Membrane Skid, station an operator at: 2” Permeate vent valve B1D1 2433 and 2” L1D1 2612 Also, Station an operator at 6” D-4411 Bank feed valve B1D1 2408 if D-4411 Bank is to be taken off-line. 2 Field If one membrane skid is to be closed, adjust FCV 4092 accordingly to divert some flow from membranes to the bypass line. Reduce the total feed to no more than can be handled by the numbers of sections to be used. Close the valves below: 6” B1D1 2408 (Feed) 6” B1D1 2423 (Residue) Open: 2” B1D1 2612 permeate vent valve Partially open: 2” B1D1 2433 permeate vent valve Close: 6” B1D1 2425 (Permeate) Open: 2” L1D1 2611 residue vent valve but keep closed 2” B1D1 2432. 50
  • 52. MEMBRANE BANK SHUTDOWN Step Location Description 3 Field CCR Field Crack Open: 2” residue vent valve to reduce residual pressure at 3.5 to 5 bar(g) per minute. Operator to monitor residue PI 4411A if Bank 1 is to be taken off. Do not open the residual vent valve so far that the residual pressure drops to near the permeate pressure. The residual pressure must always be at least 7 bar(g) higher than the permeate pressure until the end of depressurization. CAUTION: An excessive rate of depressurization higher than 3.5 to 5 bar/minute can also damage the membranes. These events can occur if the residue start-up valve is opened too quickly. 4 CCR Field CCR Field Field Field Field When the residue PI 4411A reaches a pressure of ~7 bar(g) Open further 2” permeate vent valve B1D1 2433 and allow the residue to depressurize through it. When the residue pressure PI 4411A drops to below 1 bar (g) seen at pressure PI 4411B, Close: 2” Residue vent start-up valve L1D1 2611. 2” Residue start-up isolation vent valve B1D1 2432 2” Permeate start up vent isolation valve L1D1 2612 2” Permeate start-up vent isolation valve B1D1 2433 5 After depressurization is complete, purge and add nitrogen blanket if the membrane section is to be offline for more than an hour. 51
  • 53. © 2017 UOP LLC. A Honeywell Company All rights reserved. Normal Operations and Troubleshooting Separex™ Membrane System  PV Gas Ca Mau GPP Project
  • 54. Membrane Mechanical Damage • Reverse Pressure Differential - Occurs when Permeate Pressure > Feed or Residual Pressure - Membrane cracks at adhesive lines - Most likely to occur on shutdown or purging - Indicated by increased H/C losses to permeate - Be aware of system conditions at all times 53
  • 55. Membrane Mechanical Damage (continued) • High Flow per Operating Area (# tubes online) - On startup or at changes in system capacity - During system upsets - Also may be caused by flow surge - Elements can ‘telescope’ and damaged - Indicated by increased Hydrocarbon losses to permeate 54
  • 56. Membrane Mechanical Damage (continued) • Rapid Depressurization - Occurs when banks or skid depressurizing valves opened too quickly - Depressurization is a manual operation - When depressurizing individual bank, use ~15 minute criteria for depressurizing. - Crack open valve initially and then open more as pressure decreases (< 5bar/minute) 55
  • 57. Membrane Contaminant Damage • Liquids - Chemical injection such as methanol - Upstream unit malfunction - Filter Coalescer malfunction - Poor commissioning - Feed temperature control failure • Particulate Damage - Occurs when particle filter malfunctions - Usually due to operator inattention - Particles of corrosion products or activated carbon fines clog the membrane elements - May result in high HC losses 56
  • 58. Hydrocarbon Dew Point • Condensation within the membrane will damage it’s elements • Residual stream temperature must always be 5C above the calculated dew point (dew point margin) to guard against condensation • Factors affecting dew point - Permeate pressure - Number of membrane sections - Membrane feed temperature • There is no major concern due to cryo unit residue gas dew point being low 57 T J-T effect HC Dewpoint HC DEWPOINT MARGIN
  • 60. System Optimization • Goals - Target Export Gas CO2 specifications - Maximize sales gas production - Minimize hydrocarbon losses - Maximize membrane life • Why optimize? - Too low residue gas CO2 = more hydrocarbon losses  Higher CO2 removal = higher CO2 and methane slippage - Too high membrane feed gas temperature = more hydrocarbon losses - Too high permeate pressure = more hydrocarbon losses - Too high residue gas CO2 = off-spec HHV 59
  • 61. Membrane Optimization • Methods - Operating Condition Adjustments  Feed flow  Lowest feed temperature  Feed pressure (to a more limited extent)  Lowest permeate pressure - Membrane Area Adjustment • Lean Case - The Normal LEAN case requires all 4 banks in operation, while the Normal RICH case requires only one bank in operation - Load 10 elements per tube (5 on each side) 60
  • 62. Operations Adjustment Control Variables • A: Number Banks Online (Membrane Area) • T: Feed Temperature (A-3001 outlet) • P1: Feed Pressure (discharge of compressor, indirect control) • P2: Permeate Pressure • F: Feed Flow (to an extent, indirect control) • F1: Bypass P1 F FEED RESIDUAL GAS T P2A PERMEATE F1 61
  • 63. Membrane Operating Variables Process Variable Effect on Residual Composition (with fixed membrane area) Increased Feed Flowrate Higher CO2 content Decreased Feed Flowrate Lower CO2 content Increased Membrane Feed Temperature Lower CO2 content Decreased Membrane Feed Temperature Higher CO2 content Increased Feed Pressure Lower CO2 content Decreased Feed Pressure Higher CO2 content Increased Permeate Pressure Higher CO2 content Decreased Permeate Pressure Lower CO2 content Increased Feed CO2 Content Higher CO2 content Decreased Feed CO2 Content Lower CO2 content 62
  • 64. Membrane Operating Conditions FEED FLOW • An Increase in Feed Gas Flow results in: - Increase of CO2 Content of Residual/Sales Gas - Can cause mechanical damage to membrane if above design or too little area for the feed rate • A Decrease in Feed Gas Flow results in: - Reduction of CO2 Content in Residual/Sales Gas - Higher hydrocarbon losses - Can potentially cause hydrocarbon condensation and membrane damage if flow or operating temperature is too low  Not expected to be a major issue here since dew point of gas is already low to the membrane unit 63
  • 65. Membrane Operating Conditions (continued) TEMPERATURE • An Increase in Operating Temperature results in: - Reduction of CO2 Content of Residual/Sales Gas - Increase of permeate flow (higher hydrocarbon losses) • A Decrease in Operating Temperature results in: - Increase in CO2 Content of Residual/Sales Gas - Reduction of permeate flow (lower hydrocarbon losses) - Can cause hydrocarbon condensation and membrane damage if operating temperature is too low 64
  • 66. FEED PRESSURE • An Increase in Operating Pressure results in: - Reduction of CO2 Content of Residual/Sales Gas - Increase of permeate flow (higher hydrocarbon losses) • A Decrease in Operating Pressure results in: - Increase in CO2 Content of Residual/Sales Gas - Reduction of permeate flow (lower hydrocarbon losses) Membrane Operating Conditions (continued) 65
  • 67. PERMEATE PRESSURE • An Increase in Permeate Pressure results in: - Increase in CO2 Content of Residual/Sales Gas - Reduction of permeate flow • A Decrease in Permeate Pressure results in: - Reduction of CO2 Content of Residual/Sales Gas - Increase of permeate flow - Typically improves selectivity – decreases hydrocarbon concentration in permeate Membrane Operating Conditions (continued) 66
  • 68. Membrane Operating Conditions (continued) MEMBRANE AREA • An Increase in Membrane Area results in: - Reduction of CO2 Content of Residual/Sales Gas - Increase of permeate flow (higher hydrocarbon losses) • A Decrease in Primary Membrane Area results in: - Increase of CO2 Content of Residual/Sales Gas - Reduction of permeate flow (lower hydrocarbon losses) 67 Can only be increased in increments. Do not operate below minimum or above maximum flow for the # of membrane tubes online
  • 69. Optimization Flow Chart Plant Operation Stable CO2 in Sales Gas at at 8%? Plant is operating in Specification Sales CO2 Concentration? Do one of the following: 2) Increase Permeate backpressure 3) Increase feed gas flow Shut down a membrane bank Do one of the following: 3) Decrease feed gas flow Below 8% Above 8% Yes 2) Increase feed gas temperature 1) Decrease feed gas temperature Can 1 bank be Taken off-line? No Yes Yes No Can 1 bank be Be put on-line? Start up a membrane bank No In order of preference In order of preference 1) Decrease permeate pressure 68
  • 70. Filter Coalescer 69 Filter Coalescer Primary Symptom Local Causes Remedy Liquid carryover Filter Coalescer cartridge rupture High delta P (then low dP) Feed surge Pressure surge Filter Coalescer cartridge plugged High delta P High solids ingress Bypass the whole unit for filter cartridge replacement if possible, replace cartridges High level in Filter Coalescer due to: Excessive liquids load Plugged LCV Level instrument malfunction Troubleshoot upstream unit Isolate & clean LCV Repair instrument malfunction Follow specific recommendations from coalescer vendor
  • 71. Membrane Unit Membrane Unit Symptom Local Causes Remedy Low feed temperature to membranes Residue Gas Cooler or upstream issues Troubleshoot Residue Gas Cooler or upstream issues High feed temperature to Membranes Residue Gas Cooler or upstream issues Troubleshoot Residue Gas Cooler or upstream issues High CO2 content in residual gas Permeate pressure set too high Lower permeate pressure set point Increased feed gas flow rate or CO2 composition Lower permeate pressure. Raise Membrane Feed Temperature Start additional membrane bank/section/skid Damaged membranes due to condensation, or aging; or feed gas flow or composition too high for design. Add, and/or replace elements in tubes Reduce feed gas flow or CO2 level 70
  • 72. Membrane Unit Membranes Unit Symptom Local Causes Remedy Low CO2 content in residual gas/ poor hydrocarbon recovery Permeate pressure set too low Raise permeate pressure control set point, investigate downstream compression Decrease in feed flow rate or composition (low CO2) 1. Raise permeate pressure 2. Lower Membrane Feed Temperature 3. Remove membranes sections Feed flow rate and/or composition too low, outside of design range 1. Increase feed gas flow 2. Remove membrane sections or elements per tube Feed pressure too high 1. Decrease feed gas pressure 2. Remove membrane sections 71
  • 73. Membrane Unit Membranes Unit Symptom Local Causes Remedy Decrease in permeate CO2 concentration, increase in hydrocarbon concentration Elements are damaged and leaking Find tube with leaking element by performing thermal scan. Replace elements at cold tubes 72
  • 74. Damaged Element – Visual Inspections 73 New Membrane element
  • 75. Thermal Scanning • Quickly identify tubes with potential damaged elements based on permeate tube temperatures • Use thermal IR gun or similar • Aim directly onto the permeate pipe exiting each membrane tube - Do not scan on pipe insulation • Scan similar position for all permeate pipes - Suggestion: complete at night – minimize impact of sunlight • Can also be completed on the residual gas exit nozzles • Record: - Temperature - Skid/tube number/permeate or residual - Populate data into the excel sheet 74
  • 76. Thermal Scanning • Tubes should have similar permeate temperatures • Tubes with severely leaking/damaged elements should show colder permeate temperature - More flow from high pressure to low pressure Joule Thompson effect • Statistics/data graphs can help identify which tubes may have leaking elements 75
  • 77. Good Thermal Scan Data • All permeate tubes: similar temperature - Not a lot of scatter in the data: data points all between 47-48C 76 40 41 42 43 44 45 46 47 48 49 1 3 5 7 9 11 13 15 PermeateTemperature,DegC. Tube
  • 78. Suspected Tube with Leak- Thermal Scan Data • One tube temperature significantly different than the others 77 38.0 38.5 39.0 39.5 40.0 40.5 41.0 41.5 42.0 42.5 43.0 43.5 1 3 5 7 9 11 13 15 PermeateTemperature,DegC. Tube Tube with potential leaking/damaged element

Editor's Notes

  1. 2
  2. Separex membranes are ideal for bulk removal of CO2 as shown at upper right area in this chart. Membranes can handle high CO2 feed gas while producing medium to low CO2 product gas. They are not ideal for very low CO2 product gas.
  3. 4
  4. Membranes are not filters where small molecules are separated from larger ones. Instead, separation of components is by a solution-diffusion mechanism. Highly soluble components such as CO2 solubilize into the membrane and then diffuse to the low pressure side. Separation is not perfect as hydrocarbons have some small amount of solubility.
  5. 6
  6. From the high pressure side, 'fast' molecules solubilize and diffuse through the membrane to be collected at the low pressure side. In natural gas applications these molecules are typically water, hydrogen sulfide, carbon dioxide, and a small amount of HCs. HCs are 'slow' or less soluble and remain at the high pressure side to be drawn off as residual gas.  
  7. 8
  8. 9
  9. This is a photograph of our 8” diameter spiral wound membrane element. It is 40” long and weighs 40 lbs.
  10. 12
  11. This is a standard pretreatment unit block flow diagram. The Filter Coalsecer removes liquids and aerosols from the feed gas. The membrane preheater raises the feed gas temperature to maintain a vapor phase throughout the membrane tube. The non-regenerative carbon guard bed removes trace level of contaminants. The Particle Filter removes any dust from the carbon guard bed. This type of P/T works well with relatively clean gas. The consumables are typically replaced every six months. There is no dew pointing of the membrane feed gas.
  12. Mechanical causes include: MemGuard bed support leakage leading to adsorbent migration. Leaking or passing MemGuard switching valves leading to poor regeneration. Leaking membrane unit isolation valves causing offline units to pressure up w/ feed gas. Poor quality welds at Filter Coalescer or Particle Filter tubesheet. Tubesheet leakage at Gas/gas exchanger leading to liquids to membranes. Membrane feed gas strainer leakage or rupture. Other causes include: Actual feed gas composition or contaminant level different from design basis. Improper membrane element loading. This include using HC grease instead of vacuum grease.
  13. One of the crucial tasks during pre-commissioning is the cleaning of the Membrane Element Tubes. Rust, debris, welding slag, and any other material or substance such as corrosion inhibitor coatings, oil and water will affect membrane performance. While it is necessary to perform a thorough cleaning, it is not complicated.
  14. One of the crucial tasks during pre-commissioning is the cleaning of the Membrane Element Tubes. Rust, debris, welding slag, and any other material or substance such as corrosion inhibitor coatings, oil and water will affect membrane performance. While it is necessary to perform a thorough cleaning, it is not complicated.
  15. One of the crucial tasks during pre-commissioning is the cleaning of the Membrane Element Tubes. Rust, debris, welding slag, and any other material or substance such as corrosion inhibitor coatings, oil and water will affect membrane performance. While it is necessary to perform a thorough cleaning, it is not complicated.
  16. 22
  17. One of the crucial tasks during pre-commissioning is the cleaning of the Membrane Element Tubes. Rust, debris, welding slag, and any other material or substance such as corrosion inhibitor coatings, oil and water will affect membrane performance. While it is necessary to perform a thorough cleaning, it is not complicated.
  18. One of the crucial tasks during pre-commissioning is the cleaning of the Membrane Element Tubes. Rust, debris, welding slag, and any other material or substance such as corrosion inhibitor coatings, oil and water will affect membrane performance. While it is necessary to perform a thorough cleaning, it is not complicated.
  19. Example of Taper Lok flanges with permeate tube and Taper Lok iron seal rings. Note that it is important to remove and store properly the Taper lok iron seal rings. Avoid scratch or any type of damage to it otherwise, the seal won’t perform as expected and maybe a leak could appear.
  20. One of the crucial tasks during pre-commissioning is the cleaning of the Membrane Element Tubes. Rust, debris, welding slag, and any other material or substance such as corrosion inhibitor coatings, oil and water will affect membrane performance. While it is necessary to perform a thorough cleaning, it is not complicated.
  21. To clean the tubes, Use rags/cleaning pig tied to ropes at both ends. Rags should be damp but not dripping in order to prevent excess solvent from entering pipe work and not evaporating completely. Pull the rags back and forth inside the membrane tube and inspect it for cleanliness. Repeat until the membrane tube is completely clean.
  22. These pictures show examples of rags used to clean the tubes. The rags should have a ball shape and using the pillow cases and tie wraps with approximately the same diameter as the membrane tube ID. Cover the tie wraps with duct tape. The ball should fit tightly inside the pressure tube.
  23. Internal surface should be shiny, with no remaining rust inhibitor or solid particulates present. You can see on the left side a tube before the cleaning and on the right side a tube after the cleaning.
  24. 31
  25. 32
  26. 33
  27. 34
  28. 35
  29. Example of Elements connected to Taper Lok flange via permeate tube. You can see the iron seal attached to the flange, also the membrane connected to taper lok flange with permeate tube.
  30. 38
  31. 39
  32. 40
  33. 41
  34. It’s important to have enough filters on hand to deal with an upset that may cause the seal gas filters to clog prematurely (this happens most often during startup) IOM: Installation and Operating Manual
  35. 27
  36. 28
  37. 29
  38. 29
  39. 59
  40. 61
  41. 62
  42. 69
  43. 70
  44. 71
  45. 72