SlideShare a Scribd company logo
1 of 16
ESTIMATION
(ARCH 683)
- LIPIKA PANDEY
6TH SEM, B.ARCH
CONTENTS
o Introduction
o Need for an Estimate
o Procedure of Estimation
o Data required to prepare an Estimate
o Types Of Estimate
o Methods to Calculate Estimate
o Example
o Estimation for a Small Room
INTRODUCTION
Estimation is the technique of calculating or computing the various quantities and expected
expenditure to be incurred on a particular work or project.
NEED FOR AN ESTIMATE –
o To know about the estimate cost of the project.
o To calculate the tax of the building.
o To fix the rent of the building.
o To know the cost of the various materials involved in construction.
o To arrange the labours for the project.
o To take approvals for the government projects.
o To have loan from bank.
o To understand the time required for project completion.
INTRODUCTION
PROCEDURE OF ESTIMATION –
o Preparing detailed estimate.
o Calculating the rate of each unit of work.
o Preparing abstract of estimate.
DATA REQUIRED TO PREPARE AN ESTIMATE–
o Drawings and detailed contents.
o Materials specifications and rates.
o Labour requirements.
o Accessibility to plot.
o Transportation cost.
o Purpose of building.
o Site location.
TYPES OF ESTIMATE
TYPES OF ESTIMATE–
o Abstract or Approximate or Preliminary Estimate – It is the estimate prepared using
any rough method to get an approximate cost of the project.
o Rough cost estimate based on Plinth Area – It is the estimate prepared on the basis
of plinth area of the various buildings proposed to be constructed.
o Rough cost estimate based on Cubic Content – It is the estimate prepared on the
basis of cubic content (plinth area x height of building) of the various buildings
proposed to be constructed.
o Detailed Estimate – It is the estimate which provide the item wise quantities of work,
item wise unit rate, and item wise expenditure in the project.
TYPES OF ESTIMATE
TYPES OF ESTIMATE–
o Annual Repair Estimate – It is prepared by the concerned department for getting
allocation of funds made in the annual budgets.
o Special Repair Estimate – It is prepared when the work cannot be carried out of the
annual repair funds due to certain reasons resulting in genuine increase in the cost.
o Revised Estimate – It is prepared when, the sanctioned estimate exceeds 5% either
due to the rate being found insufficient or due to some other reasons.
o Supplementary Estimate – This is fresh detailed estimate in addition to the original
sanctioned estimate prepared when additional works are deemed necessary during
progress of work to supplement the original works.
o Complete Estimate – It includes, additional cost of construction, land, surveys, legal
assistance, registration documents, taxes, services, plans, etc.
METHODS TO CALCULATE ESTIMATE
METHODS TO CALCULATE ESTIMATE–
o Centre Line Method – In this method total centre line length of walls in a building is
calculated and then multiplied by the breadth and the depth of the respective items
get the total quantity. Centre line method is applicable to the square building with
symmetrical offsets. It is more accurate and fast method as compared to other
methods.
o Crossing Method – It is designed for calculating materials needed for masonry walls.
In this method, the lengths and breadths of walls at plinth level (the base on which a
column is raised) are included. The internal dimension of the room and the thickness
of the walls are also important to calculate the quantities. Symmetrical offsets should
be counted as they play a major role in the calculation of quantity of materials.
METHODS TO CALCULATE ESTIMATE
METHODS TO CALCULATE ESTIMATE–
o Out to Out, and In to In Method – This method follows P
.W.D system for computing
materials and this seems to be the most accurate method among all.
o Bay Method – It is applicable in garages, factory, and railway platform where identical
structures are visible. Bay in a construction term means a compartment of a building.
The cost of one room is calculated first and it is multiplied by the number of bays.
o Service Unit Method – The term service unit method is designed for building with
identical rooms. This method is applicable in the construction of college, hospital,
cinemas, prison, and more. When it is a construction of a hospital, the service unit will
be a bed. Likewise, for cinema/stadium, it is seats.
EXAMPLE
ESTIMATION FOR A SMALL FULLY FURNISHED ROOM–
o Room Size – 10’ x 10’
o Foundation/ Footing Cost – Let Foundation size is 4’×4′ and 4’ depth, so volume of
soil excavation for 4 footing = 4× 4’×4’×4′ = 256 cubic feet. Converting into cubic
meter 256/35.32 =7.25m³. Soil excavation rate is around Rs. 800 per m³ for hard soil
and Rs. 300 per m³ for soft soil. We take soil excavation rate Rs. 400/m³ for this
calculation. Total cost of soil excavation for foundation = 7.25 × 400 = Rs. 2900.
o Brick work quantity and Cost calculation – Assume that the room 10’×10′ have 9″
brick wall on four side height up to 10’ and parapet wall for partition wall will be of
inch. Outer dimension of room is 11.5’×11.5′ and inner dimension of room excluding
brick wall is 10’×10′.
Area of one brick wall =10’×10′ =100 sq foot
Area of 4 brick wall =4 ×100 = 400 sq foot.
EXAMPLE
ESTIMATION FOR A SMALL FULLY FURNISHED ROOM–
Door size = 4’×7′ = 28 sq ft.
Window size = 3’×4’= 12 sq ft.
Door and window size should be deducted from total area of brick wall.
Net area of brick wall= 400 - (28+12)= 360 sq ft
Volume of 9 inch thick brick wall = 360×9/12 = 270 cubic feet, converting into
cubic meter we have 270/35.32=7.65 cubic meter.
Consider parapet brick wall 3.5 feet height 4.5 inch thick, and outer dimension of
room is 11.5’×11.5′ = 132.25 sq ft, total area of parapet brick wall on all four side =
11.5 × 3.5 ×4 =161 sq ft.
Volume of parapet wall =( 4.5/12)×161=60 cubic ft, converting into cubic meter,
60/35.32 = 1.70 cubic meter.
Total brickwork = 4 brick wall + parapet wall = 7.65+ 1.70 = 9.35 cubic meter.
We know, for 1 cubic meter of brickwork we require 500 bricks, 1.26 bags of
cement and 9.28 cubic feet sand quantity.
EXAMPLE
ESTIMATION FOR A SMALL FULLY FURNISHED ROOM–
o Brick work quantity and Cost calculation – Number of brick in 9.35 cubic meter =
500×9.35= 4675 no's, suppose first class brick rate is around Rs. 8000 per thousand,
brick cost = 8000× (4675/1000) = Rs. 37400.
o Cement quantity and their Cost – Quantity of cement required for 9.35 cubic meter
brickwork is 1.26 × 9.35 = around 12 bags cement. Suppose market rate of cement is
around rupees 400 per bag so cement cost = 12×400= Rs. 4800.
o Sand quantity and their Cost – Quantity of sand required for 9.35 cubic meter brick
work is 9.28 × 9.35 = 87 cubic ft. Market rate of sand is around Rs, 40 per CFT then
sand cost= 87 ×40 = Rs. 3480. So total brickwork cost = brick cost + cement cost +
sand cost = 37400 + 4800 + 3480 = Rs. 45680.
EXAMPLE
ESTIMATION FOR A SMALL FULLY FURNISHED ROOM–
o Concrete quantity and Cost calculation for Footing, Column, Plinth Beam, Wall Beam and
RCC Slab – Footing is 4 feet depth and column size is 9 inch into 12 inch and height of
column is 10 feet up to slab and 3.5 feet above slab. There is four column. So column
length is = 4’+10’+3.5’= 17.5′. Total volume of concrete quantity for 4 column = 4 ×
(9″×12″)×17.5′ = 4 × 13.125 =52.5 cubic feet.
Plinth beam size 9″×12″ for all around for length 11.5×4 = 46 feet. Total volume of
concrete quantity for plinth beam = (9″×12″)× 46 = 34.5 cubic feet.
Wall beam size 9″×9″ for all around for length 11.5×4 = 46 feet. Total volume of
concrete quantity for wall beam = (9″×9″)× 46′ = 25.9 cubic feet.
RCC slab 5 inch thick for 11.5’×11.5′, concrete volume is 11.5’×11.5’×5/12′ = 55 cft.
Total Weight volume of rcc concrete = concrete quantity for column + concrete
quantity for RCC plinth beam + concrete quantity for RCC wall + concrete
RCC slab = 52.5 +34.5+25.9+55 = 170 cft.
EXAMPLE
ESTIMATION FOR A SMALL FULLY FURNISHED ROOM–
Converting 170cft into cubic metre,170/35.32 = 4.8 m³. Ready mix concrete
available in market is around rupees 4000 per m³ for M20 grade of concrete, so
material cost of concrete = 4000×4.8 = Rs. 19200.
o Reinforcement Cost and Quantity Calculation – Suppose reinforcement required is 1% of
concrete volume for RCC work like footing column beam and RCC slab. Steel quantity =
(1/100)×4.8 m³ = 0.048 m³. Weight of steel = 0.048 m³ × 7850kg/ m³ = 376.8kg, market
rate of Steel is around 60 rupees per kg then total cost of Steel = 60×376.8 = Rs. 22600.
EXAMPLE
ESTIMATION FOR A SMALL FULLY FURNISHED ROOM–
o Labor Cost for Construction – Labor cost for construction of house around 180
rupees per square foot without plastering and PCC or tile flooring.
So total outer area of one room is 11.5’×11.5 = 132.25 square foot, total labor
cost = 180×132.25 = Rs. 23805.
o Therefore, Total Cost of Construction for a Small Room without PCC Plastering and
Floor Tiling = Soil excavation cost + Brick work cost + Concreting cost +
Reinforcement cost + Labor cost.
= 2900 + 45680 + 19200 + 22600 + 23805 = Rs. 114200 (approx.)
EXAMPLE
ESTIMATION FOR A SMALL FULLY FURNISHED ROOM–
o Now consider finishing cost is about 60% of total construction cost of one room,
finishing should be required plastering, PCC flooring, tile flooring, putty painting,
electrical fitting, lumbering, water and sanitization.
Therefore, 60% of construction cost of one room = (70/100)×114200= Rs. 68520.
Hence, the Total Cost =114200+68520 = Rs. 182700.
Thank You!

More Related Content

What's hot

Rate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation EngineeringRate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation EngineeringShanmugasundaram N
 
ABC Analysis and FIFO and LIFO of Stanley Furniture (Hypothetical)
ABC Analysis and FIFO and LIFO of Stanley Furniture (Hypothetical) ABC Analysis and FIFO and LIFO of Stanley Furniture (Hypothetical)
ABC Analysis and FIFO and LIFO of Stanley Furniture (Hypothetical) Divyae Sherry
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works ALI HYDER GADHI
 
5#rate analysis problems
5#rate analysis   problems5#rate analysis   problems
5#rate analysis problemsLIJI A
 
Rate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate AnalyisisRate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate AnalyisisJaptyesh Singh
 
Project analysis and advanced data calculation and conditional formatting
Project analysis and advanced data calculation and conditional formattingProject analysis and advanced data calculation and conditional formatting
Project analysis and advanced data calculation and conditional formattingChachrist Srisuwanrat
 
Cement industry of Rajasthan by Divyank Sharma
Cement industry of Rajasthan by Divyank SharmaCement industry of Rajasthan by Divyank Sharma
Cement industry of Rajasthan by Divyank SharmaNibir Pawan
 
Inventory mgmt. in scm
Inventory mgmt. in scmInventory mgmt. in scm
Inventory mgmt. in scmAashi Agarwal
 
Rate Analysis Site Meeting
Rate Analysis   Site MeetingRate Analysis   Site Meeting
Rate Analysis Site MeetingSanjay Patnaik
 
Chapter 5 location - 2nd
Chapter 5 location - 2ndChapter 5 location - 2nd
Chapter 5 location - 2ndShadina Shah
 
SMM7 Cost Summary Report
SMM7 Cost Summary ReportSMM7 Cost Summary Report
SMM7 Cost Summary ReportNatalie Reid
 
Break even-point
Break even-point Break even-point
Break even-point Aditi Gadia
 

What's hot (19)

rate analysis
rate analysisrate analysis
rate analysis
 
Rate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation EngineeringRate analysis and costing - Estimation, Costing and Valuation Engineering
Rate analysis and costing - Estimation, Costing and Valuation Engineering
 
ABC Analysis and FIFO and LIFO of Stanley Furniture (Hypothetical)
ABC Analysis and FIFO and LIFO of Stanley Furniture (Hypothetical) ABC Analysis and FIFO and LIFO of Stanley Furniture (Hypothetical)
ABC Analysis and FIFO and LIFO of Stanley Furniture (Hypothetical)
 
Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works  Rates Analysis For Calculating Material and Labour for building works
Rates Analysis For Calculating Material and Labour for building works
 
5#rate analysis problems
5#rate analysis   problems5#rate analysis   problems
5#rate analysis problems
 
Nasir Documents
Nasir DocumentsNasir Documents
Nasir Documents
 
Rate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate AnalyisisRate analysis road work in Estimation & Rate Analyisis
Rate analysis road work in Estimation & Rate Analyisis
 
Project analysis and advanced data calculation and conditional formatting
Project analysis and advanced data calculation and conditional formattingProject analysis and advanced data calculation and conditional formatting
Project analysis and advanced data calculation and conditional formatting
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
 
Cement industry of Rajasthan by Divyank Sharma
Cement industry of Rajasthan by Divyank SharmaCement industry of Rajasthan by Divyank Sharma
Cement industry of Rajasthan by Divyank Sharma
 
Odev 13
Odev 13Odev 13
Odev 13
 
Inventory mgmt. in scm
Inventory mgmt. in scmInventory mgmt. in scm
Inventory mgmt. in scm
 
Odev 13
Odev 13Odev 13
Odev 13
 
Rate Analysis Site Meeting
Rate Analysis   Site MeetingRate Analysis   Site Meeting
Rate Analysis Site Meeting
 
Ppt 3
Ppt 3Ppt 3
Ppt 3
 
Chapter 5 location - 2nd
Chapter 5 location - 2ndChapter 5 location - 2nd
Chapter 5 location - 2nd
 
Presentation1
Presentation1Presentation1
Presentation1
 
SMM7 Cost Summary Report
SMM7 Cost Summary ReportSMM7 Cost Summary Report
SMM7 Cost Summary Report
 
Break even-point
Break even-point Break even-point
Break even-point
 

Similar to Estimating Construction Costs

fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...Deepak37004
 
Estimation And Costing Of A Building
Estimation And Costing Of A Building Estimation And Costing Of A Building
Estimation And Costing Of A Building shahidibn hussain
 
Project 3 - Costing
Project 3 - CostingProject 3 - Costing
Project 3 - CostingKai Yun Pang
 
Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6Padmasinh Patil
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).pptNaumanIjaz12
 
Quantity notes pdf
Quantity notes pdfQuantity notes pdf
Quantity notes pdfSaqib Imran
 
Estimation Costing and Valuation Unit 1
Estimation Costing and Valuation Unit 1Estimation Costing and Valuation Unit 1
Estimation Costing and Valuation Unit 1Padmasinh Patil
 
2 Presentation on Estimation and its Methods.pptx
2 Presentation on Estimation and its Methods.pptx2 Presentation on Estimation and its Methods.pptx
2 Presentation on Estimation and its Methods.pptxRaniVishwakarma15
 
Quantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsQuantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsmeghajain275
 
Presentation [AP14015]
Presentation [AP14015]Presentation [AP14015]
Presentation [AP14015]Rahul Dasgupta
 
chapter1-210122051628.pdf
chapter1-210122051628.pdfchapter1-210122051628.pdf
chapter1-210122051628.pdfDeepak37004
 
estimation,costingandvaluation.pdf
estimation,costingandvaluation.pdfestimation,costingandvaluation.pdf
estimation,costingandvaluation.pdfIctsol
 

Similar to Estimating Construction Costs (20)

Cost estimation
Cost estimationCost estimation
Cost estimation
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
fuw5fomwrucbh1ojdlxe-signature-b01f2df686b9c053f2f9f35a62a4a1f12d0e812f6cbea3...
 
ECV All Chapters
ECV All ChaptersECV All Chapters
ECV All Chapters
 
Estimation And Costing Of A Building
Estimation And Costing Of A Building Estimation And Costing Of A Building
Estimation And Costing Of A Building
 
Project 3 - Costing
Project 3 - CostingProject 3 - Costing
Project 3 - Costing
 
Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6Estimation Costing and Valuation Unit 1 to Unit 6
Estimation Costing and Valuation Unit 1 to Unit 6
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).ppt
 
4.2 square foot estimating
4.2 square foot estimating4.2 square foot estimating
4.2 square foot estimating
 
Quantity notes pdf
Quantity notes pdfQuantity notes pdf
Quantity notes pdf
 
Rate analysis vansheika
Rate analysis   vansheikaRate analysis   vansheika
Rate analysis vansheika
 
Estimation Costing and Valuation Unit 1
Estimation Costing and Valuation Unit 1Estimation Costing and Valuation Unit 1
Estimation Costing and Valuation Unit 1
 
Re appr unit 11
Re   appr unit 11Re   appr unit 11
Re appr unit 11
 
deva batch FINAL PPT.pptx
deva batch FINAL PPT.pptxdeva batch FINAL PPT.pptx
deva batch FINAL PPT.pptx
 
Preliminary estimate
Preliminary estimatePreliminary estimate
Preliminary estimate
 
2 Presentation on Estimation and its Methods.pptx
2 Presentation on Estimation and its Methods.pptx2 Presentation on Estimation and its Methods.pptx
2 Presentation on Estimation and its Methods.pptx
 
Quantity Survey and Estimation basic terms
Quantity Survey and Estimation basic termsQuantity Survey and Estimation basic terms
Quantity Survey and Estimation basic terms
 
Presentation [AP14015]
Presentation [AP14015]Presentation [AP14015]
Presentation [AP14015]
 
chapter1-210122051628.pdf
chapter1-210122051628.pdfchapter1-210122051628.pdf
chapter1-210122051628.pdf
 
estimation,costingandvaluation.pdf
estimation,costingandvaluation.pdfestimation,costingandvaluation.pdf
estimation,costingandvaluation.pdf
 

More from LipikaPandey

Motel design - Case Study
Motel design - Case StudyMotel design - Case Study
Motel design - Case StudyLipikaPandey
 
Post modern architecture
Post modern architecturePost modern architecture
Post modern architectureLipikaPandey
 
Architect's and their works
Architect's and their worksArchitect's and their works
Architect's and their worksLipikaPandey
 
Data collection for primary school
Data collection for primary schoolData collection for primary school
Data collection for primary schoolLipikaPandey
 
Case study on libraries
Case study on librariesCase study on libraries
Case study on librariesLipikaPandey
 
Composite house - Lipika Pandey- 3rd sem
Composite house - Lipika Pandey- 3rd semComposite house - Lipika Pandey- 3rd sem
Composite house - Lipika Pandey- 3rd semLipikaPandey
 
Methods of construction .
Methods of construction  .Methods of construction  .
Methods of construction .LipikaPandey
 
Site analysis for primary school
Site analysis for primary schoolSite analysis for primary school
Site analysis for primary schoolLipikaPandey
 
Data collection - Climate Analysis - Tropical Wet and Dry Climate - Architect...
Data collection - Climate Analysis - Tropical Wet and Dry Climate - Architect...Data collection - Climate Analysis - Tropical Wet and Dry Climate - Architect...
Data collection - Climate Analysis - Tropical Wet and Dry Climate - Architect...LipikaPandey
 
Hindu temples - ARCH 203
Hindu temples - ARCH 203Hindu temples - ARCH 203
Hindu temples - ARCH 203LipikaPandey
 
Architectural design III - Case study on Architect's House
Architectural design III - Case study on Architect's HouseArchitectural design III - Case study on Architect's House
Architectural design III - Case study on Architect's HouseLipikaPandey
 
Computer education presentation - ARCH 383
Computer education presentation - ARCH 383Computer education presentation - ARCH 383
Computer education presentation - ARCH 383LipikaPandey
 
Computer education presentation - ARCH 383
Computer education presentation - ARCH 383Computer education presentation - ARCH 383
Computer education presentation - ARCH 383LipikaPandey
 
Computer education presentation - ARCH 383
Computer education presentation - ARCH 383Computer education presentation - ARCH 383
Computer education presentation - ARCH 383LipikaPandey
 
Climatology Arch 302
Climatology Arch 302Climatology Arch 302
Climatology Arch 302LipikaPandey
 

More from LipikaPandey (16)

Motel design - Case Study
Motel design - Case StudyMotel design - Case Study
Motel design - Case Study
 
Post modern architecture
Post modern architecturePost modern architecture
Post modern architecture
 
Noise barriers
Noise barriersNoise barriers
Noise barriers
 
Architect's and their works
Architect's and their worksArchitect's and their works
Architect's and their works
 
Data collection for primary school
Data collection for primary schoolData collection for primary school
Data collection for primary school
 
Case study on libraries
Case study on librariesCase study on libraries
Case study on libraries
 
Composite house - Lipika Pandey- 3rd sem
Composite house - Lipika Pandey- 3rd semComposite house - Lipika Pandey- 3rd sem
Composite house - Lipika Pandey- 3rd sem
 
Methods of construction .
Methods of construction  .Methods of construction  .
Methods of construction .
 
Site analysis for primary school
Site analysis for primary schoolSite analysis for primary school
Site analysis for primary school
 
Data collection - Climate Analysis - Tropical Wet and Dry Climate - Architect...
Data collection - Climate Analysis - Tropical Wet and Dry Climate - Architect...Data collection - Climate Analysis - Tropical Wet and Dry Climate - Architect...
Data collection - Climate Analysis - Tropical Wet and Dry Climate - Architect...
 
Hindu temples - ARCH 203
Hindu temples - ARCH 203Hindu temples - ARCH 203
Hindu temples - ARCH 203
 
Architectural design III - Case study on Architect's House
Architectural design III - Case study on Architect's HouseArchitectural design III - Case study on Architect's House
Architectural design III - Case study on Architect's House
 
Computer education presentation - ARCH 383
Computer education presentation - ARCH 383Computer education presentation - ARCH 383
Computer education presentation - ARCH 383
 
Computer education presentation - ARCH 383
Computer education presentation - ARCH 383Computer education presentation - ARCH 383
Computer education presentation - ARCH 383
 
Computer education presentation - ARCH 383
Computer education presentation - ARCH 383Computer education presentation - ARCH 383
Computer education presentation - ARCH 383
 
Climatology Arch 302
Climatology Arch 302Climatology Arch 302
Climatology Arch 302
 

Recently uploaded

Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxsocialsciencegdgrohi
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxUnboundStockton
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaVirag Sontakke
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 

Recently uploaded (20)

Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docx
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of India
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 

Estimating Construction Costs

  • 1. ESTIMATION (ARCH 683) - LIPIKA PANDEY 6TH SEM, B.ARCH
  • 2. CONTENTS o Introduction o Need for an Estimate o Procedure of Estimation o Data required to prepare an Estimate o Types Of Estimate o Methods to Calculate Estimate o Example o Estimation for a Small Room
  • 3. INTRODUCTION Estimation is the technique of calculating or computing the various quantities and expected expenditure to be incurred on a particular work or project. NEED FOR AN ESTIMATE – o To know about the estimate cost of the project. o To calculate the tax of the building. o To fix the rent of the building. o To know the cost of the various materials involved in construction. o To arrange the labours for the project. o To take approvals for the government projects. o To have loan from bank. o To understand the time required for project completion.
  • 4. INTRODUCTION PROCEDURE OF ESTIMATION – o Preparing detailed estimate. o Calculating the rate of each unit of work. o Preparing abstract of estimate. DATA REQUIRED TO PREPARE AN ESTIMATE– o Drawings and detailed contents. o Materials specifications and rates. o Labour requirements. o Accessibility to plot. o Transportation cost. o Purpose of building. o Site location.
  • 5. TYPES OF ESTIMATE TYPES OF ESTIMATE– o Abstract or Approximate or Preliminary Estimate – It is the estimate prepared using any rough method to get an approximate cost of the project. o Rough cost estimate based on Plinth Area – It is the estimate prepared on the basis of plinth area of the various buildings proposed to be constructed. o Rough cost estimate based on Cubic Content – It is the estimate prepared on the basis of cubic content (plinth area x height of building) of the various buildings proposed to be constructed. o Detailed Estimate – It is the estimate which provide the item wise quantities of work, item wise unit rate, and item wise expenditure in the project.
  • 6. TYPES OF ESTIMATE TYPES OF ESTIMATE– o Annual Repair Estimate – It is prepared by the concerned department for getting allocation of funds made in the annual budgets. o Special Repair Estimate – It is prepared when the work cannot be carried out of the annual repair funds due to certain reasons resulting in genuine increase in the cost. o Revised Estimate – It is prepared when, the sanctioned estimate exceeds 5% either due to the rate being found insufficient or due to some other reasons. o Supplementary Estimate – This is fresh detailed estimate in addition to the original sanctioned estimate prepared when additional works are deemed necessary during progress of work to supplement the original works. o Complete Estimate – It includes, additional cost of construction, land, surveys, legal assistance, registration documents, taxes, services, plans, etc.
  • 7. METHODS TO CALCULATE ESTIMATE METHODS TO CALCULATE ESTIMATE– o Centre Line Method – In this method total centre line length of walls in a building is calculated and then multiplied by the breadth and the depth of the respective items get the total quantity. Centre line method is applicable to the square building with symmetrical offsets. It is more accurate and fast method as compared to other methods. o Crossing Method – It is designed for calculating materials needed for masonry walls. In this method, the lengths and breadths of walls at plinth level (the base on which a column is raised) are included. The internal dimension of the room and the thickness of the walls are also important to calculate the quantities. Symmetrical offsets should be counted as they play a major role in the calculation of quantity of materials.
  • 8. METHODS TO CALCULATE ESTIMATE METHODS TO CALCULATE ESTIMATE– o Out to Out, and In to In Method – This method follows P .W.D system for computing materials and this seems to be the most accurate method among all. o Bay Method – It is applicable in garages, factory, and railway platform where identical structures are visible. Bay in a construction term means a compartment of a building. The cost of one room is calculated first and it is multiplied by the number of bays. o Service Unit Method – The term service unit method is designed for building with identical rooms. This method is applicable in the construction of college, hospital, cinemas, prison, and more. When it is a construction of a hospital, the service unit will be a bed. Likewise, for cinema/stadium, it is seats.
  • 9. EXAMPLE ESTIMATION FOR A SMALL FULLY FURNISHED ROOM– o Room Size – 10’ x 10’ o Foundation/ Footing Cost – Let Foundation size is 4’×4′ and 4’ depth, so volume of soil excavation for 4 footing = 4× 4’×4’×4′ = 256 cubic feet. Converting into cubic meter 256/35.32 =7.25m³. Soil excavation rate is around Rs. 800 per m³ for hard soil and Rs. 300 per m³ for soft soil. We take soil excavation rate Rs. 400/m³ for this calculation. Total cost of soil excavation for foundation = 7.25 × 400 = Rs. 2900. o Brick work quantity and Cost calculation – Assume that the room 10’×10′ have 9″ brick wall on four side height up to 10’ and parapet wall for partition wall will be of inch. Outer dimension of room is 11.5’×11.5′ and inner dimension of room excluding brick wall is 10’×10′. Area of one brick wall =10’×10′ =100 sq foot Area of 4 brick wall =4 ×100 = 400 sq foot.
  • 10. EXAMPLE ESTIMATION FOR A SMALL FULLY FURNISHED ROOM– Door size = 4’×7′ = 28 sq ft. Window size = 3’×4’= 12 sq ft. Door and window size should be deducted from total area of brick wall. Net area of brick wall= 400 - (28+12)= 360 sq ft Volume of 9 inch thick brick wall = 360×9/12 = 270 cubic feet, converting into cubic meter we have 270/35.32=7.65 cubic meter. Consider parapet brick wall 3.5 feet height 4.5 inch thick, and outer dimension of room is 11.5’×11.5′ = 132.25 sq ft, total area of parapet brick wall on all four side = 11.5 × 3.5 ×4 =161 sq ft. Volume of parapet wall =( 4.5/12)×161=60 cubic ft, converting into cubic meter, 60/35.32 = 1.70 cubic meter. Total brickwork = 4 brick wall + parapet wall = 7.65+ 1.70 = 9.35 cubic meter. We know, for 1 cubic meter of brickwork we require 500 bricks, 1.26 bags of cement and 9.28 cubic feet sand quantity.
  • 11. EXAMPLE ESTIMATION FOR A SMALL FULLY FURNISHED ROOM– o Brick work quantity and Cost calculation – Number of brick in 9.35 cubic meter = 500×9.35= 4675 no's, suppose first class brick rate is around Rs. 8000 per thousand, brick cost = 8000× (4675/1000) = Rs. 37400. o Cement quantity and their Cost – Quantity of cement required for 9.35 cubic meter brickwork is 1.26 × 9.35 = around 12 bags cement. Suppose market rate of cement is around rupees 400 per bag so cement cost = 12×400= Rs. 4800. o Sand quantity and their Cost – Quantity of sand required for 9.35 cubic meter brick work is 9.28 × 9.35 = 87 cubic ft. Market rate of sand is around Rs, 40 per CFT then sand cost= 87 ×40 = Rs. 3480. So total brickwork cost = brick cost + cement cost + sand cost = 37400 + 4800 + 3480 = Rs. 45680.
  • 12. EXAMPLE ESTIMATION FOR A SMALL FULLY FURNISHED ROOM– o Concrete quantity and Cost calculation for Footing, Column, Plinth Beam, Wall Beam and RCC Slab – Footing is 4 feet depth and column size is 9 inch into 12 inch and height of column is 10 feet up to slab and 3.5 feet above slab. There is four column. So column length is = 4’+10’+3.5’= 17.5′. Total volume of concrete quantity for 4 column = 4 × (9″×12″)×17.5′ = 4 × 13.125 =52.5 cubic feet. Plinth beam size 9″×12″ for all around for length 11.5×4 = 46 feet. Total volume of concrete quantity for plinth beam = (9″×12″)× 46 = 34.5 cubic feet. Wall beam size 9″×9″ for all around for length 11.5×4 = 46 feet. Total volume of concrete quantity for wall beam = (9″×9″)× 46′ = 25.9 cubic feet. RCC slab 5 inch thick for 11.5’×11.5′, concrete volume is 11.5’×11.5’×5/12′ = 55 cft. Total Weight volume of rcc concrete = concrete quantity for column + concrete quantity for RCC plinth beam + concrete quantity for RCC wall + concrete RCC slab = 52.5 +34.5+25.9+55 = 170 cft.
  • 13. EXAMPLE ESTIMATION FOR A SMALL FULLY FURNISHED ROOM– Converting 170cft into cubic metre,170/35.32 = 4.8 m³. Ready mix concrete available in market is around rupees 4000 per m³ for M20 grade of concrete, so material cost of concrete = 4000×4.8 = Rs. 19200. o Reinforcement Cost and Quantity Calculation – Suppose reinforcement required is 1% of concrete volume for RCC work like footing column beam and RCC slab. Steel quantity = (1/100)×4.8 m³ = 0.048 m³. Weight of steel = 0.048 m³ × 7850kg/ m³ = 376.8kg, market rate of Steel is around 60 rupees per kg then total cost of Steel = 60×376.8 = Rs. 22600.
  • 14. EXAMPLE ESTIMATION FOR A SMALL FULLY FURNISHED ROOM– o Labor Cost for Construction – Labor cost for construction of house around 180 rupees per square foot without plastering and PCC or tile flooring. So total outer area of one room is 11.5’×11.5 = 132.25 square foot, total labor cost = 180×132.25 = Rs. 23805. o Therefore, Total Cost of Construction for a Small Room without PCC Plastering and Floor Tiling = Soil excavation cost + Brick work cost + Concreting cost + Reinforcement cost + Labor cost. = 2900 + 45680 + 19200 + 22600 + 23805 = Rs. 114200 (approx.)
  • 15. EXAMPLE ESTIMATION FOR A SMALL FULLY FURNISHED ROOM– o Now consider finishing cost is about 60% of total construction cost of one room, finishing should be required plastering, PCC flooring, tile flooring, putty painting, electrical fitting, lumbering, water and sanitization. Therefore, 60% of construction cost of one room = (70/100)×114200= Rs. 68520. Hence, the Total Cost =114200+68520 = Rs. 182700.