SlideShare a Scribd company logo
1 of 7
Download to read offline
Building Economy ARE 431
Dr. Mohammad A. Hassanain 1
1
Square Foot Estimate - Approach
The method of developing a square foot estimate is similar to
that used for a conceptual estimate except more information
is required and costs are tabulated per square foot, not by
service unit.
The estimate is still used primarily by the owner for
budgeting purposes and still conducted during the
conceptual stage of the project.
Cost data can be taken from outside data sources or can be
developed by the designer, owner, or construction company.
Adjustments are made the same as in the rough order of
magnitude (ROM) estimate.
These estimates take slightly longer than a ROM estimate
and should provide an accuracy in the plus or minus 15%
range.
2
Square Foot Estimate - Data
Companies that have information for ROM estimates should
also have the data needed for square foot estimates.
If information is not available in-house, Means has two
square foot data books, each published utilizing different
source material.
The first source:
The Assemblies Cost Data Book. (Figure 5-7)
Bases its costs on actual completed projects as
reported by owners, designers, and contractors.
This is the same source of information used in the
conceptual estimate, only broken down on a
square foot basis. It uses the same ÂĽ, median, and
Âľ quality distinction and it is based on 11,500
projects.
Building Economy ARE 431
Dr. Mohammad A. Hassanain 2
3
Square Foot Estimate - Data
Advantages of the Assemblies Cost Data Book:
1. The reported costs are derived from actual projects that have
been built around the country.
2. The costs have been localized to the national average.
3. These are true costs reflecting actual contractor costs
including overhead and profit.
Disadvantage of the Assemblies Cost Data Book:
Specific project conditions are not known, thereby making it
difficult to know exactly what the square foot cost includes.
4
Square Foot Estimate - Data
The second source
The Square Foot Data Book. (Figures 5-8, 5-9)
Based on stereotypical models that have been
created for different project types.
This allows Means to determine the quantities of
materials and labor required to build each project at
the sizes tabulated.
With the quantities held constant, each year the unit
prices are adjusted to reflect current costs for labor
and materials.
Building Economy ARE 431
Dr. Mohammad A. Hassanain 3
5
Square Foot Estimate - Data
Advantages of the Square Foot Data book:
1. The modeled data is more specific.
2. It identifies the costs associated with different combinations
of structural and exterior closures.
3. It allows specific pricing for common project additives such as
basements, and adjustment for story height and building
perimeter.
4. The perimeter adjustment factor allows the estimator to
properly account for the added cost associated with
unusually shaped buildings.
5. This data book also provides a detailed breakout of the
model for the project. The detail breakout allows the
estimator to make small adjustments for items in the model
by deleting or adding line items as necessary.
6
Square Foot Estimate - Data
Using the Reported Square Foot Data:
What is the cost of a 15,000 sq. ft. library? Assume
median quality and 1995 data.
Using Figure 5-7
Total cost = size in sq. ft. x cost per sq. ft.
Total cost = 15,000 sq. ft. x $87.7/sq. ft.
Total cost = $1,315,500
Building Economy ARE 431
Dr. Mohammad A. Hassanain 4
7
Square Foot Estimate - Data
Using the Modeled Square Foot Data
What is the estimated cost of a 15,000 sq. ft.
library? Assume face brick with concrete block
back-up and a reinforced concrete frame, using
1995 data.
Using Figure 5-8
Total cost = size in sq. ft. x cost per sq. ft.
8
Square Foot Estimate - Data
Using the Modeled Square Foot Data
Determining the cost per sq. ft of the library, the
table shows the following estimates for given sizes:
13,000 sq. ft. = $89.00
16,000 sq. ft. = $87.00
For a 15,000 sq. ft. building, interpolate to a cost of
87.67 per sq. ft.
Total cost = 15,000 sq. ft. x $87.67 = $1,315,050
Both approaches have provided us with a square foot price
that at this point is unadjusted and therefore is good for the
national average city in the data year.
Building Economy ARE 431
Dr. Mohammad A. Hassanain 5
9
Square Foot Estimate - Adjustments
Reported Square Foot Prices
To make adjustments to the reported square foot
prices, the same method is used as in a ROM
estimate.
Example:
To design and build a median quality, 15,000 sq. ft.
library in Orlando, Florida, with construction to
begin in June 1995.
Previously the cost for a median quality library at
1995 prices was determined to be $1,315,500.
10
Square Foot Estimate - Adjustments
Reported Square Foot Prices
To make adjustment for size (see Figure 5-3).
Size factor = 15,000/12,000 = 1.25
Cost modifier = 0.98
Library adjusted for size = $1,315,500 x 0.98 = $1,289,190
To adjust for location:
Orlando index = 88.6
Estimated cost/100 = Adjusted cost for city/City index
Orlando cost = ($1,289, 190 x 88.6)/100 = $1,142,222
Building Economy ARE 431
Dr. Mohammad A. Hassanain 6
11
Square Foot Estimate - Adjustments
Reported Square Foot Prices
To adjust for time:
Assume a June 1995 construction start and a projected
increase of 2.5% per year, thus add 1.25% to the above
(early 1995) price.
Total project cost = $1,142,222 + ($1,142,222 x 0.0125)
Total project cost = $1,142,222 + $14,278
Total project cost = $1,156,500
12
Square Foot Estimate - Adjustments
Reported Square Foot Prices
Design fee adjustment (See Figure 5-10)
A further adjustment would add in the design fee. That reference
table shows that a library is in the same category as an apartment
building. Therefore, read 7.3%, as this building’s cost is close to
$1,000,000.
Total project cost = $1,156,500 + ($1,156,500 x 0.073)
Total project cost = $1,156,500 + $84,424
Total project cost = $1,240,924
This represent a median quality 15,000 sq. ft. library in
Orlando. Construction would begin in mid 1995, and the
cost includes a 7.3% fee for design services.
Building Economy ARE 431
Dr. Mohammad A. Hassanain 7
13
Square Foot Estimate - Adjustments
Modeled Square Foot Prices
Adjustment is somewhat different from the Reported Square
Foot approach, because data from Means’ Modeled Square
Foot references does not include some common features that
would be in a typical library.
These typical add-on features that have to be added in
include:
Study carrels.
Emergency lights.
Furnishings (bookshelves, reading tables).
Site work is not included but the architect’s fee is.
14
Square Foot Estimate - Adjustments
Modeled Square Foot Prices
The price determined previously, building with face brick
with concrete block backup with a reinforced concrete
frame, using 1995 data, was $1,315,050. Accounting for
these project additives (See Figure 5-8).
(5) emergency lights @ 610 each = $3,050
(20) Study carrels @700 each = $14,000
(1) flagpole = $3,125
Bookshelves

More Related Content

What's hot

Building Economics
Building Economics Building Economics
Building Economics JIT KUMAR GUPTA
 
Specification writting civil construction
Specification writting civil constructionSpecification writting civil construction
Specification writting civil constructiondiasawada12345
 
PPT on Construction Costing
PPT on Construction CostingPPT on Construction Costing
PPT on Construction CostingManish Kandpal
 
Cost management in Buildings
Cost management in BuildingsCost management in Buildings
Cost management in BuildingsJIT KUMAR GUPTA
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methodsgayu pandian
 
working drawings for beginners
working drawings for beginners working drawings for beginners
working drawings for beginners Dr.Ebtehal G
 
Components of a building
Components of a buildingComponents of a building
Components of a buildingKartikeya Pandey
 
5th Qatar BIM User Day, Understanding stakeholder roles in BIM
5th Qatar BIM User Day, Understanding stakeholder roles in BIM5th Qatar BIM User Day, Understanding stakeholder roles in BIM
5th Qatar BIM User Day, Understanding stakeholder roles in BIMBIM User Day
 
Costing for-civil-engineering-project
Costing for-civil-engineering-projectCosting for-civil-engineering-project
Costing for-civil-engineering-projecthlksd
 
BIM Presentation
BIM PresentationBIM Presentation
BIM PresentationOmer Syed
 
contract procedure
contract procedurecontract procedure
contract procedurehasyimah ismail
 
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJCOST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJTapesh Ajmera
 
Construction process
Construction processConstruction process
Construction processMazen Al-Qadi
 
measurement wall to floor ratio 2013
measurement wall to floor ratio  2013measurement wall to floor ratio  2013
measurement wall to floor ratio 2013Daniel Ross
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costingGanesh Murugan
 
Exterior and interior Finishes- Building Construction
Exterior and interior Finishes- Building ConstructionExterior and interior Finishes- Building Construction
Exterior and interior Finishes- Building ConstructionTaha Padrawala
 

What's hot (20)

Estimating & Costing - I
Estimating & Costing - IEstimating & Costing - I
Estimating & Costing - I
 
Building Economics
Building Economics Building Economics
Building Economics
 
Specification writting civil construction
Specification writting civil constructionSpecification writting civil construction
Specification writting civil construction
 
PPT on Construction Costing
PPT on Construction CostingPPT on Construction Costing
PPT on Construction Costing
 
Cost management in Buildings
Cost management in BuildingsCost management in Buildings
Cost management in Buildings
 
estimation,its types and methods
estimation,its types and methodsestimation,its types and methods
estimation,its types and methods
 
Types of estimates
Types of estimatesTypes of estimates
Types of estimates
 
working drawings for beginners
working drawings for beginners working drawings for beginners
working drawings for beginners
 
Quantity take off
Quantity take offQuantity take off
Quantity take off
 
Refurbishment
RefurbishmentRefurbishment
Refurbishment
 
Components of a building
Components of a buildingComponents of a building
Components of a building
 
5th Qatar BIM User Day, Understanding stakeholder roles in BIM
5th Qatar BIM User Day, Understanding stakeholder roles in BIM5th Qatar BIM User Day, Understanding stakeholder roles in BIM
5th Qatar BIM User Day, Understanding stakeholder roles in BIM
 
Costing for-civil-engineering-project
Costing for-civil-engineering-projectCosting for-civil-engineering-project
Costing for-civil-engineering-project
 
BIM Presentation
BIM PresentationBIM Presentation
BIM Presentation
 
contract procedure
contract procedurecontract procedure
contract procedure
 
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJCOST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
 
Construction process
Construction processConstruction process
Construction process
 
measurement wall to floor ratio 2013
measurement wall to floor ratio  2013measurement wall to floor ratio  2013
measurement wall to floor ratio 2013
 
Estimation and costing
Estimation and costingEstimation and costing
Estimation and costing
 
Exterior and interior Finishes- Building Construction
Exterior and interior Finishes- Building ConstructionExterior and interior Finishes- Building Construction
Exterior and interior Finishes- Building Construction
 

Similar to 4.2 square foot estimating

4.1 conceptual estimates
4.1 conceptual estimates4.1 conceptual estimates
4.1 conceptual estimatesAli Juma Albahrani
 
06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdfJunaidMughal34
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimationDhavalMithaiwala
 
5 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp015 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp01hlksd
 
Residential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel TemplateResidential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel TemplateSHAZEBALIKHAN1
 
Eca workshop
Eca workshopEca workshop
Eca workshopshensin1015
 
ECA Workshop - Brief
ECA Workshop - BriefECA Workshop - Brief
ECA Workshop - BriefKai Yun Pang
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).pptNaumanIjaz12
 
cost estimation model per unit model and segmenting model.pdf
cost estimation model per unit model and segmenting model.pdfcost estimation model per unit model and segmenting model.pdf
cost estimation model per unit model and segmenting model.pdfArnabChakraborty499766
 
Cost Indices for Industrial Application
Cost Indices for Industrial ApplicationCost Indices for Industrial Application
Cost Indices for Industrial ApplicationK. Shahzad Baig
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgetingIzah Asmadi
 
L06 cost management
L06 cost managementL06 cost management
L06 cost managementAsa Chan
 
Estimation and Costing
Estimation and CostingEstimation and Costing
Estimation and CostingSakshi Kirar
 
3 estimate considerations
3 estimate considerations3 estimate considerations
3 estimate considerationsAli Juma Albahrani
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimatinghatim ahmed
 
Lec.2 binifits of estamations...Types of Estimation
Lec.2  binifits of estamations...Types of EstimationLec.2  binifits of estamations...Types of Estimation
Lec.2 binifits of estamations...Types of EstimationMuthanna Abbu
 
Types of estimate
Types of estimateTypes of estimate
Types of estimateArpit Sethia
 

Similar to 4.2 square foot estimating (20)

4.1 conceptual estimates
4.1 conceptual estimates4.1 conceptual estimates
4.1 conceptual estimates
 
type of cost Estimation
type of cost Estimationtype of cost Estimation
type of cost Estimation
 
Lec05.pptx
Lec05.pptxLec05.pptx
Lec05.pptx
 
06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf06 -Estimates, QS_CE, Mar 2021.pdf
06 -Estimates, QS_CE, Mar 2021.pdf
 
Introduction to estimation
Introduction to estimationIntroduction to estimation
Introduction to estimation
 
5 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp015 costestimation-110716160453-phpapp01
5 costestimation-110716160453-phpapp01
 
Residential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel TemplateResidential Building Preliminary Cost Estimate- Excel Template
Residential Building Preliminary Cost Estimate- Excel Template
 
Eca workshop
Eca workshopEca workshop
Eca workshop
 
ECA Workshop - Brief
ECA Workshop - BriefECA Workshop - Brief
ECA Workshop - Brief
 
Estimation (power Point).ppt
Estimation (power Point).pptEstimation (power Point).ppt
Estimation (power Point).ppt
 
cost estimation model per unit model and segmenting model.pdf
cost estimation model per unit model and segmenting model.pdfcost estimation model per unit model and segmenting model.pdf
cost estimation model per unit model and segmenting model.pdf
 
B0342014027
B0342014027B0342014027
B0342014027
 
Cost Indices for Industrial Application
Cost Indices for Industrial ApplicationCost Indices for Industrial Application
Cost Indices for Industrial Application
 
Project Management C8 -cost_estimation_and_budgeting
Project Management C8  -cost_estimation_and_budgetingProject Management C8  -cost_estimation_and_budgeting
Project Management C8 -cost_estimation_and_budgeting
 
L06 cost management
L06 cost managementL06 cost management
L06 cost management
 
Estimation and Costing
Estimation and CostingEstimation and Costing
Estimation and Costing
 
3 estimate considerations
3 estimate considerations3 estimate considerations
3 estimate considerations
 
Project cost stimating
Project cost stimatingProject cost stimating
Project cost stimating
 
Lec.2 binifits of estamations...Types of Estimation
Lec.2  binifits of estamations...Types of EstimationLec.2  binifits of estamations...Types of Estimation
Lec.2 binifits of estamations...Types of Estimation
 
Types of estimate
Types of estimateTypes of estimate
Types of estimate
 

More from Ali Juma Albahrani

10 depreciation and depletion
10 depreciation and depletion10 depreciation and depletion
10 depreciation and depletionAli Juma Albahrani
 
9 benefit to cost ratio method
9 benefit to cost ratio method9 benefit to cost ratio method
9 benefit to cost ratio methodAli Juma Albahrani
 
8.the rate of return method
8.the rate of return method8.the rate of return method
8.the rate of return methodAli Juma Albahrani
 
7.2 equivalent uniform annual cost method
7.2 equivalent uniform annual cost method7.2 equivalent uniform annual cost method
7.2 equivalent uniform annual cost methodAli Juma Albahrani
 
7.1 present worth method
7.1 present worth method7.1 present worth method
7.1 present worth methodAli Juma Albahrani
 
6.3 use of interest tables
6.3 use of interest tables6.3 use of interest tables
6.3 use of interest tablesAli Juma Albahrani
 
6.2 cash flow - time diagrams
6.2 cash flow - time diagrams6.2 cash flow - time diagrams
6.2 cash flow - time diagramsAli Juma Albahrani
 
6.1 simple versus compound interest
6.1 simple versus compound interest6.1 simple versus compound interest
6.1 simple versus compound interestAli Juma Albahrani
 
4.0 pre-construction estimates
4.0 pre-construction estimates4.0 pre-construction estimates
4.0 pre-construction estimatesAli Juma Albahrani
 
1 introduction to cost estimating
1 introduction to cost estimating1 introduction to cost estimating
1 introduction to cost estimatingAli Juma Albahrani
 

More from Ali Juma Albahrani (17)

10 depreciation and depletion
10 depreciation and depletion10 depreciation and depletion
10 depreciation and depletion
 
9 benefit to cost ratio method
9 benefit to cost ratio method9 benefit to cost ratio method
9 benefit to cost ratio method
 
8.the rate of return method
8.the rate of return method8.the rate of return method
8.the rate of return method
 
7.2 equivalent uniform annual cost method
7.2 equivalent uniform annual cost method7.2 equivalent uniform annual cost method
7.2 equivalent uniform annual cost method
 
7.1 present worth method
7.1 present worth method7.1 present worth method
7.1 present worth method
 
7.0 life cycle costing
7.0 life cycle costing7.0 life cycle costing
7.0 life cycle costing
 
6.4 multiple factors
6.4 multiple factors6.4 multiple factors
6.4 multiple factors
 
6.3 use of interest tables
6.3 use of interest tables6.3 use of interest tables
6.3 use of interest tables
 
6.2 cash flow - time diagrams
6.2 cash flow - time diagrams6.2 cash flow - time diagrams
6.2 cash flow - time diagrams
 
6.1 simple versus compound interest
6.1 simple versus compound interest6.1 simple versus compound interest
6.1 simple versus compound interest
 
5.3 estimate setup
5.3 estimate setup5.3 estimate setup
5.3 estimate setup
 
5.2 unit pricing
5.2 unit pricing5.2 unit pricing
5.2 unit pricing
 
5.1 quantity take-off
5.1 quantity take-off5.1 quantity take-off
5.1 quantity take-off
 
5.0 detailed estimating
5.0 detailed estimating5.0 detailed estimating
5.0 detailed estimating
 
4.0 pre-construction estimates
4.0 pre-construction estimates4.0 pre-construction estimates
4.0 pre-construction estimates
 
2 types of estimates
2 types of estimates2 types of estimates
2 types of estimates
 
1 introduction to cost estimating
1 introduction to cost estimating1 introduction to cost estimating
1 introduction to cost estimating
 

Recently uploaded

Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 

Recently uploaded (20)

Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 

4.2 square foot estimating

  • 1. Building Economy ARE 431 Dr. Mohammad A. Hassanain 1 1 Square Foot Estimate - Approach The method of developing a square foot estimate is similar to that used for a conceptual estimate except more information is required and costs are tabulated per square foot, not by service unit. The estimate is still used primarily by the owner for budgeting purposes and still conducted during the conceptual stage of the project. Cost data can be taken from outside data sources or can be developed by the designer, owner, or construction company. Adjustments are made the same as in the rough order of magnitude (ROM) estimate. These estimates take slightly longer than a ROM estimate and should provide an accuracy in the plus or minus 15% range. 2 Square Foot Estimate - Data Companies that have information for ROM estimates should also have the data needed for square foot estimates. If information is not available in-house, Means has two square foot data books, each published utilizing different source material. The first source: The Assemblies Cost Data Book. (Figure 5-7) Bases its costs on actual completed projects as reported by owners, designers, and contractors. This is the same source of information used in the conceptual estimate, only broken down on a square foot basis. It uses the same ÂĽ, median, and Âľ quality distinction and it is based on 11,500 projects.
  • 2. Building Economy ARE 431 Dr. Mohammad A. Hassanain 2 3 Square Foot Estimate - Data Advantages of the Assemblies Cost Data Book: 1. The reported costs are derived from actual projects that have been built around the country. 2. The costs have been localized to the national average. 3. These are true costs reflecting actual contractor costs including overhead and profit. Disadvantage of the Assemblies Cost Data Book: Specific project conditions are not known, thereby making it difficult to know exactly what the square foot cost includes. 4 Square Foot Estimate - Data The second source The Square Foot Data Book. (Figures 5-8, 5-9) Based on stereotypical models that have been created for different project types. This allows Means to determine the quantities of materials and labor required to build each project at the sizes tabulated. With the quantities held constant, each year the unit prices are adjusted to reflect current costs for labor and materials.
  • 3. Building Economy ARE 431 Dr. Mohammad A. Hassanain 3 5 Square Foot Estimate - Data Advantages of the Square Foot Data book: 1. The modeled data is more specific. 2. It identifies the costs associated with different combinations of structural and exterior closures. 3. It allows specific pricing for common project additives such as basements, and adjustment for story height and building perimeter. 4. The perimeter adjustment factor allows the estimator to properly account for the added cost associated with unusually shaped buildings. 5. This data book also provides a detailed breakout of the model for the project. The detail breakout allows the estimator to make small adjustments for items in the model by deleting or adding line items as necessary. 6 Square Foot Estimate - Data Using the Reported Square Foot Data: What is the cost of a 15,000 sq. ft. library? Assume median quality and 1995 data. Using Figure 5-7 Total cost = size in sq. ft. x cost per sq. ft. Total cost = 15,000 sq. ft. x $87.7/sq. ft. Total cost = $1,315,500
  • 4. Building Economy ARE 431 Dr. Mohammad A. Hassanain 4 7 Square Foot Estimate - Data Using the Modeled Square Foot Data What is the estimated cost of a 15,000 sq. ft. library? Assume face brick with concrete block back-up and a reinforced concrete frame, using 1995 data. Using Figure 5-8 Total cost = size in sq. ft. x cost per sq. ft. 8 Square Foot Estimate - Data Using the Modeled Square Foot Data Determining the cost per sq. ft of the library, the table shows the following estimates for given sizes: 13,000 sq. ft. = $89.00 16,000 sq. ft. = $87.00 For a 15,000 sq. ft. building, interpolate to a cost of 87.67 per sq. ft. Total cost = 15,000 sq. ft. x $87.67 = $1,315,050 Both approaches have provided us with a square foot price that at this point is unadjusted and therefore is good for the national average city in the data year.
  • 5. Building Economy ARE 431 Dr. Mohammad A. Hassanain 5 9 Square Foot Estimate - Adjustments Reported Square Foot Prices To make adjustments to the reported square foot prices, the same method is used as in a ROM estimate. Example: To design and build a median quality, 15,000 sq. ft. library in Orlando, Florida, with construction to begin in June 1995. Previously the cost for a median quality library at 1995 prices was determined to be $1,315,500. 10 Square Foot Estimate - Adjustments Reported Square Foot Prices To make adjustment for size (see Figure 5-3). Size factor = 15,000/12,000 = 1.25 Cost modifier = 0.98 Library adjusted for size = $1,315,500 x 0.98 = $1,289,190 To adjust for location: Orlando index = 88.6 Estimated cost/100 = Adjusted cost for city/City index Orlando cost = ($1,289, 190 x 88.6)/100 = $1,142,222
  • 6. Building Economy ARE 431 Dr. Mohammad A. Hassanain 6 11 Square Foot Estimate - Adjustments Reported Square Foot Prices To adjust for time: Assume a June 1995 construction start and a projected increase of 2.5% per year, thus add 1.25% to the above (early 1995) price. Total project cost = $1,142,222 + ($1,142,222 x 0.0125) Total project cost = $1,142,222 + $14,278 Total project cost = $1,156,500 12 Square Foot Estimate - Adjustments Reported Square Foot Prices Design fee adjustment (See Figure 5-10) A further adjustment would add in the design fee. That reference table shows that a library is in the same category as an apartment building. Therefore, read 7.3%, as this building’s cost is close to $1,000,000. Total project cost = $1,156,500 + ($1,156,500 x 0.073) Total project cost = $1,156,500 + $84,424 Total project cost = $1,240,924 This represent a median quality 15,000 sq. ft. library in Orlando. Construction would begin in mid 1995, and the cost includes a 7.3% fee for design services.
  • 7. Building Economy ARE 431 Dr. Mohammad A. Hassanain 7 13 Square Foot Estimate - Adjustments Modeled Square Foot Prices Adjustment is somewhat different from the Reported Square Foot approach, because data from Means’ Modeled Square Foot references does not include some common features that would be in a typical library. These typical add-on features that have to be added in include: Study carrels. Emergency lights. Furnishings (bookshelves, reading tables). Site work is not included but the architect’s fee is. 14 Square Foot Estimate - Adjustments Modeled Square Foot Prices The price determined previously, building with face brick with concrete block backup with a reinforced concrete frame, using 1995 data, was $1,315,050. Accounting for these project additives (See Figure 5-8). (5) emergency lights @ 610 each = $3,050 (20) Study carrels @700 each = $14,000 (1) flagpole = $3,125 Bookshelves