SlideShare a Scribd company logo
1 of 3
Download to read offline
NEWSLETTER PRIORY CONTRACT LAW LTD Issue 2
Construction
Law
Update
QUARTER 2
2015
IN THIS ISSUE
COMMERCIAL MANAGEMENT
The Start. When should a Commercial
Manager be appointed? To put it bluntly as
soon as possible. They should be involved in
the tender or at least have an understanding
of what has been tendered, the intended
margin for the project, how it has been
tendered and the risks being assumed by the
parties. They need to understand the form of
contract that the project is being procured
under and the terms and conditions
contained therein. They should be allowed to
discuss and negotiate some of those terms
and conditions, what damages apply, any
agreements made before contract
commencement and the limitations of entire
agreement clauses. On Utilities contracts an
understanding of the law appertaining to
Public Procurement, both EU Directives and
the UK Public Procurement Regulations
would be invaluable.
Managing. Once the contract commences
then the Commercial Manager should be able
to manage the contract. This means that
when the contract requires a condition
precedent to commence an action that this is
complied with, a good example is the FIDIC
time bar clause (20.1) and notification or the
NEC III clause 60.3 where it states, “If the
Contractor does not notify a compensation
event within eight weeks of becoming aware
of the event, he is not entitled to a change in
the Prices, the Completion Date or a Key
Date unless the Project Manager should have
notified the event to the Contractor but did
not”.
They should map out the key notification dates
and application submission dates, but most
importantly, they should do exactly what the
contract says. Too many times the parties set off
in commercial bliss where the submission of
notifications and applications are not as per the
contract, the parties fall out later down the road
and end up in dispute.
A good example of this was where a contractor
failed to submit notification as per FIDIC clause
20.1, the employer just accepted this and the
parties continued on their merry way. Near
completion the Employer declared that a large
amount of outstanding money was not due
because of a breach of clause 20.1 and therefore
they were not entitled to recover entitlement
under clause 20.5.
The contractor argued that the Early Warnings
submitted constituted notification, more by luck
than judgement the early warning was followed
by a letter which gave very sparse details on the
events and circumstances giving rise to the claim,
this was successfully argued as the required
notification.
Commercial Contracts – Acuity
After predominantly handling disputes that arise due to
the failure of one or more of the parties to follow the
terms and condition laid down in the contract, from
inception to completion, we have decided to review the
basics.
Case Law Reports
A number of disputes about payment have
ended up in the Technology and Construction
Court in recent months, as such this newsletter
concentrates on those cases.
COMMERCIAL AND CASES LAW UPDATE.
By Colin Tomlinson
CONSTRUCTION LAW UPDATE | Issue 2 2
Once the procedures are in place, the
Commercial Manager is then reliant on the
surveyors to report the figures on how the project
is doing, their responsibility is reporting of the
figures, not for the management of the project,
or should not be. The construction works lies
outside the duties of the Commercial Manager,
there is some direct input with procurement and
subcontractor payment with the surveyor
checking that the application from the
subcontractor are correct and that the work
invoiced for has been completed but the direct
responsibility for the Project margin lies with the
project manager.
How the work is reported lies with Project Control
and it is now not unusual to see the Earned Value
Analysis method being used, this gives accurate
reporting of the work complete and the project
expenditure and any cost variance that has
occurred.
The finishing role of the Commercial Manager is
the final account and any dispute that may have
occurred. If the commercial manager has
managed the commercial aspects of the project
correctly then the approval of the submitted final
account should be completed with relative ease.
As is usually the case this is not so, and disputes
arise about an assortment of items on very minor
particulars. This is where a good Commercial
Manager will have kept meticulous records and
correspondence detailing any variations, notices
or warnings. One important note to consider is
that when you start the project, do so as if it will
go to Adjudication, keep your correspondence
polite, correct and detailed, do not as in so many
cases be pedantic, rude or insult the employer’s
representative, you can imagine the inference the
Adjudicator will infer from the commercial
representative of a company telling the
employers representative exactly what they think
of them.
CASE LAW
Caledonian Modular Ltd v Mar City
Developments Ltd [2015] EWHC 1855
(TCC).
In Caledonian Modular v Mar City Developments
Mr Justice Coulson declined to enforce an
Adjudicator's decision where the employer had
failed to serve the requisite payment notices but
where the contractor's application for payment
was found to be invalid. In this case the
contractor had submitted 15 applications, one at
the end of each month, during the project. Upon
submission of the 15th application a payless
notice was issued by the employer, as a
consequence very little was paid in response to it.
In the interim, the parties commenced final
account negotiations. Approximately a week
after the valid payless notice was served, the
contractor submitted further payment
substantiation and requested that the payless
notice be revised. When the employer queried
the status of the submitted documents, the
contractor confirmed they were "an update of the
account" the employer did not issue a further
payless notice. Consequently the contractor
initiated an adjudication asserting that the
documents constituted a 16th application for
payment which was due in full as no payless
notice had been served.
The Adjudicator decided for the contractor, on
the basis that the further documents were an
"early" 16th application, as a consequence the
employer had to pay GBP 1.5 million to the
contractor. The employer refused to pay and
the case came before Mr Justice Coulson for
enforcement, he had "no hesitation" in
rejecting the claim. He noted that the
Adjudicator had not considered the merits of
the contractor's claim, and that one of the
"baleful effects" of the amendments to the
HGCRA had been to increase the number of
claims from contractors relying on an
automatic right to payment where the
employer had failed to serve notices on time.
Mr Justice Coulson commented that if
contractors wished to benefit from the
provisions they needed to submit applications
with "proper clarity".
This decision provides some comfort to
employers that contractors will not be able to
engineer what Mr Justice Coulson described as
a "wholly undeserved windfall" in this way, and
also reminds contractors of the importance of
submitting payment applications in a clear and
straightforward fashion.
Henia Investments Inc v Beck Interiors
Ltd [2015] EWHC 2433 (TCC).
The commercial administration of a
Construction Contract can be quite difficult, the
contractual procedures are not always
straightforward, mistakes occur and, when
relationships break down, and parties often use
errors by the other side to get an "easy win".
Background
Henia Investments Inc ("Henia") appointed
Beck Interiors Ltd ("Beck") to carry out
construction and fitting out works under the
JCT Standard Building Contract without
Quantities 2011.
The payment process under the contract was:
Not later than seven days before the due
date, Beck could issue an Interim Application
setting out the sum it considered would
become due on the due date
The due date was the 29th of each month
FAST FACTS
Adjudicators Fees
For general information the
following are the last five
Adjudicators rates by nominating
body, primary profession and
hourly fee that PCL have managed
in 2015:
Tecbar Barrister - £230 hr
CIC Barrister - £275 hr
RICS QS - £210 hr
CIC Civil Eng. - £200 hr
CIC Solicitor - £250 hr
CONSTRUCTION LAW UPDATE | Issue 2 3
Interim Certificates were issued by the
Contract Administrator not later than five
days after the due date. These set out the
sum the Contract Administrator considered
was due on the due date
The final date for payment was 28 days from
the due date. Henia had to pay the sum set
out in the Interim Certificate before this date.
If there was no a valid Interim Certificate,
then Henia instead had to pay the sum set
out in the Interim Application
If Henia wanted to pay less than the sum in
the Interim Certificate / Interim Application, it
had to issue a Pay Less Notice. This had to be
issued not later than three days before the
final date for payment.
Mr Justice Akenhead noted that the parties
had failed to follow the specific terms of the
contract in regards to payment, again a
commercial necessity to ensuring the parties
do not end up in this situation.
The dispute centred on payment numbers 18
and 19. And the facts are:
Beck issued Interim Application 18 on 28
April 2015 (six days late) and applied for a
net sum of £2,943,098.95 for the period to 30
April 2015
The Contract Administrator issued Interim
Certificate 18 on 6 May 2015 (one day late). It
showed a net sum payable to Beck of
£226,248.95
Beck did not issue an Interim Application 19
The Contract Administrator issued Interim
Certificate 19 on 4 June 2015 at 00:03 hours
(three minutes late). This showed a net sum
payable to Beck of £18,893.53
Henia issued a Pay Less Notice on 17 June
2015 (which was in time). This was based on
Interim Certificate 19 and deductions of
liquidated damages of £373,751.05. It stated
that £0 was due in relation to Interim
Payment 19.
The questions put before Mr. Justice
Akenhead were:
1. Was Beck's Interim Application 18 valid?
and
2. Was Henia's Pay Less Notice valid?
The Judgment
The Interim Application
The Contract allowed Beck to submit an
Interim Application setting out the sum it
considered would become due on each due
date (which was the 29th of each month).
However, Beck's Interim Application 18
indicated the works applied for were "Valued
to 30/04/15".
On this basis, Mr Justice Akenhead held that
Beck's Interim Application was invalid. The
Contract only allowed an application based
on a valuation of the works on either 29 April
or 29 May and as a consequence the
application submitted on the 30 April was not
valid.
Mr Justice Akenhead did not comment on the
timing of Beck's Interim Application which
was six days late, However, the Courts have
clearly shown lately that they will interpret
such provisions resolutely, most recently in
Caledonian Modular Ltd v Mar City
Developments Ltd [2015] EWHC 1855 (TCC)
and Leeds City Council v Waco UK Ltd [2015]
EWHC 1400 (TCC).
The Courts will show exception where there
has been a course of previous dealing
showing that the parties have varied the
provisions, for example by allowing
applications which are three-four days late.
The Pay Less Notice
Mr Justice Akenhead’s decision on Interim
Application 18 meant the dispute over
Henia's Pay Less Notice was no longer
pertinent. The entire contractual mechanism
had broken down, as there was no valid
Interim Application or Interim Certificates no
interim payment was due. Nevertheless, Mr
Justice Akenhead did go on to consider the
parties' arguments in relation to the Pay Less
Notice.
If Interim Application 18 had been valid,
Henia would have been required to pay the
sum in that application (as there were no
valid Interim Certificates), subject to the
effect of Henia's Pay Less Notice.
Beck argued that a Pay Less Notice allowed
Henia to pay less than the sum in the Interim
Certificate only on the basis of cross claims –
setoff. Therefore Beck was entitled to the
difference between the sum in its Interim
Application 18 (£2,943,098.95) and the
liquidated damages claimed by Henia
(£373,751.05).
Henia contended that, as well as including
any cross claims, it was also entitled to put
forward its own valuation of the works in its
Pay Less Notice. In this case, Henia's
valuation was based on the late Interim
Certificate 19 (which valued the work at
£18,893.53). Its claim for liquidated damages
far exceeded this and therefore no sums were
due to Beck.
Mr Justice Akenhead agreed with Henia. He
held that the contract required Henia to serve
a Pay Less Notice if it intended to "pay less
than the sums stated as due". There was
nothing in the wording to suggest this was
limited to cross-claims.
Henia could therefore, as part of a Pay Less
Notice, put forward its own valuation of the
works.
For More Information
Contact:
Enquiries
enquiries@priorycontractlaw.com
0044 8452 60 61 05
or
ctomlinson@priorycontractlaw.com
+44 07539 036 470
http://www.priorycontractlaw.com/

More Related Content

What's hot

CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...Werksmans Attorneys
 
Construction Contract Issues in Nebraska
Construction Contract Issues in NebraskaConstruction Contract Issues in Nebraska
Construction Contract Issues in NebraskaWoods & Aitken LLP
 
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyFIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyKhalil Hasan
 
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...Divyanshu Dayal
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2ahmong4
 
Internal Controls at Construction Site
Internal Controls at Construction SiteInternal Controls at Construction Site
Internal Controls at Construction Sitesandesh mundra
 
Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...
Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...
Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...Bodman PLC
 
Time Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsTime Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsEversheds Sutherland
 
List Of Documents For Home Loan Processing
List Of Documents For Home Loan ProcessingList Of Documents For Home Loan Processing
List Of Documents For Home Loan ProcessingI & Finance
 
Supreme Court Judgement - L&T / K Raheja (VAT on Builders)
Supreme Court Judgement - L&T / K Raheja (VAT on Builders)Supreme Court Judgement - L&T / K Raheja (VAT on Builders)
Supreme Court Judgement - L&T / K Raheja (VAT on Builders)sandesh mundra
 
How To Protect Your Construction Business and Legal Interests
How To Protect Your Construction Business and Legal InterestsHow To Protect Your Construction Business and Legal Interests
How To Protect Your Construction Business and Legal InterestsPalecek & Palecek, PLLC
 
Webinar Slides: Is Your Company Ready for the New Revenue Recognition Standards?
Webinar Slides: Is Your Company Ready for the New Revenue Recognition Standards?Webinar Slides: Is Your Company Ready for the New Revenue Recognition Standards?
Webinar Slides: Is Your Company Ready for the New Revenue Recognition Standards?MHM (Mayer Hoffman McCann P.C.)
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011Tahir B Mirza
 
Case Laws on Construction and Works contract
Case Laws on Construction and Works contractCase Laws on Construction and Works contract
Case Laws on Construction and Works contractsandesh mundra
 

What's hot (19)

UKA conference 2021 - 19 August 2021
UKA conference 2021 - 19 August 2021UKA conference 2021 - 19 August 2021
UKA conference 2021 - 19 August 2021
 
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...
CONSTRUCTION AND ENGINEERING LAW: THE INTERPRETATION AND APPLICATION OF DEMAN...
 
Construction Contract Issues in Nebraska
Construction Contract Issues in NebraskaConstruction Contract Issues in Nebraska
Construction Contract Issues in Nebraska
 
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case StudyFIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
FIDIC Lecture - Joint operation of multiple Fidic Forms - A Case Study
 
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
 
Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
CIArb Promotional Talk
CIArb Promotional TalkCIArb Promotional Talk
CIArb Promotional Talk
 
Internal Controls at Construction Site
Internal Controls at Construction SiteInternal Controls at Construction Site
Internal Controls at Construction Site
 
Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...
Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...
Managing the Construction Lien Process: A Primer on the Lien Act and Recurrin...
 
Time Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsTime Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contracts
 
UK Adjudicators March 2018 newsletter
UK Adjudicators March 2018 newsletterUK Adjudicators March 2018 newsletter
UK Adjudicators March 2018 newsletter
 
List Of Documents For Home Loan Processing
List Of Documents For Home Loan ProcessingList Of Documents For Home Loan Processing
List Of Documents For Home Loan Processing
 
UK Adjudicators Newsletter August 2021
UK Adjudicators Newsletter August 2021UK Adjudicators Newsletter August 2021
UK Adjudicators Newsletter August 2021
 
Supreme Court Judgement - L&T / K Raheja (VAT on Builders)
Supreme Court Judgement - L&T / K Raheja (VAT on Builders)Supreme Court Judgement - L&T / K Raheja (VAT on Builders)
Supreme Court Judgement - L&T / K Raheja (VAT on Builders)
 
How To Protect Your Construction Business and Legal Interests
How To Protect Your Construction Business and Legal InterestsHow To Protect Your Construction Business and Legal Interests
How To Protect Your Construction Business and Legal Interests
 
Webinar Slides: Is Your Company Ready for the New Revenue Recognition Standards?
Webinar Slides: Is Your Company Ready for the New Revenue Recognition Standards?Webinar Slides: Is Your Company Ready for the New Revenue Recognition Standards?
Webinar Slides: Is Your Company Ready for the New Revenue Recognition Standards?
 
Session-02 17-09-2011
Session-02 17-09-2011Session-02 17-09-2011
Session-02 17-09-2011
 
Fidic
FidicFidic
Fidic
 
Case Laws on Construction and Works contract
Case Laws on Construction and Works contractCase Laws on Construction and Works contract
Case Laws on Construction and Works contract
 

Similar to Construction Law Updates

Slides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claimsSlides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claimsRobert MacDonald
 
Article 41 payment and pay less notices february 2017 rm03
Article 41 payment and pay less notices february 2017 rm03Article 41 payment and pay less notices february 2017 rm03
Article 41 payment and pay less notices february 2017 rm03Nick Cheetham
 
Techno Engineering & Associates
Techno Engineering & AssociatesTechno Engineering & Associates
Techno Engineering & AssociatesCerasela Angelescu
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation Lin Hui
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006Melvin Lim
 
Clause 16 suspension
Clause 16 suspensionClause 16 suspension
Clause 16 suspensionbreyerhanna
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Yee Len Wan
 
It Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction ContractsIt Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction ContractsFrancis Ho
 
M32089 Construction Contracts And Dispute Resolution.docx
M32089 Construction Contracts And Dispute Resolution.docxM32089 Construction Contracts And Dispute Resolution.docx
M32089 Construction Contracts And Dispute Resolution.docxstirlingvwriters
 
Dispute Resolution-Mechanism.pptx
Dispute Resolution-Mechanism.pptxDispute Resolution-Mechanism.pptx
Dispute Resolution-Mechanism.pptxPujanNeupane6
 
Tender & Tender Notice
Tender & Tender NoticeTender & Tender Notice
Tender & Tender NoticeSakshi Kirar
 
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....Pierrette Khoury BComm/B Laws, GDLP
 
CL Seminar
CL SeminarCL Seminar
CL Seminarkohwenqi
 
UK Adjudicators Newsletter November 2021
UK Adjudicators  Newsletter November 2021UK Adjudicators  Newsletter November 2021
UK Adjudicators Newsletter November 2021SeanGibbs12
 

Similar to Construction Law Updates (20)

Pp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyangPp2 chapter 1 cheeyong & yih shyang
Pp2 chapter 1 cheeyong & yih shyang
 
Slides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claimsSlides from the niceties of notices and their importance for construction claims
Slides from the niceties of notices and their importance for construction claims
 
Article 41 payment and pay less notices february 2017 rm03
Article 41 payment and pay less notices february 2017 rm03Article 41 payment and pay less notices february 2017 rm03
Article 41 payment and pay less notices february 2017 rm03
 
Techno Engineering & Associates
Techno Engineering & AssociatesTechno Engineering & Associates
Techno Engineering & Associates
 
PP2 - Seminar Presentation
PP2 - Seminar Presentation PP2 - Seminar Presentation
PP2 - Seminar Presentation
 
A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006A Case Study based on FIDIC and PAM Form 2006
A Case Study based on FIDIC and PAM Form 2006
 
UK Adjudicators April 2019 newsletter
UK Adjudicators April 2019 newsletterUK Adjudicators April 2019 newsletter
UK Adjudicators April 2019 newsletter
 
Clause 16 suspension
Clause 16 suspensionClause 16 suspension
Clause 16 suspension
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)
 
It Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction ContractsIt Pays to Be Right: Payment in Construction Contracts
It Pays to Be Right: Payment in Construction Contracts
 
January 2018 newsletter
January 2018 newsletterJanuary 2018 newsletter
January 2018 newsletter
 
Ac 17
Ac 17Ac 17
Ac 17
 
M32089 Construction Contracts And Dispute Resolution.docx
M32089 Construction Contracts And Dispute Resolution.docxM32089 Construction Contracts And Dispute Resolution.docx
M32089 Construction Contracts And Dispute Resolution.docx
 
Dispute Resolution-Mechanism.pptx
Dispute Resolution-Mechanism.pptxDispute Resolution-Mechanism.pptx
Dispute Resolution-Mechanism.pptx
 
Tender & Tender Notice
Tender & Tender NoticeTender & Tender Notice
Tender & Tender Notice
 
April 2018 newsletter
April 2018 newsletterApril 2018 newsletter
April 2018 newsletter
 
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
 
CL Seminar
CL SeminarCL Seminar
CL Seminar
 
UK Adjudicators Newsletter November 2021
UK Adjudicators  Newsletter November 2021UK Adjudicators  Newsletter November 2021
UK Adjudicators Newsletter November 2021
 
UK Adjudicators November 2020 Newsletter
UK Adjudicators November 2020 NewsletterUK Adjudicators November 2020 Newsletter
UK Adjudicators November 2020 Newsletter
 

Recently uploaded

Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 

Recently uploaded (20)

Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 

Construction Law Updates

  • 1. NEWSLETTER PRIORY CONTRACT LAW LTD Issue 2 Construction Law Update QUARTER 2 2015 IN THIS ISSUE COMMERCIAL MANAGEMENT The Start. When should a Commercial Manager be appointed? To put it bluntly as soon as possible. They should be involved in the tender or at least have an understanding of what has been tendered, the intended margin for the project, how it has been tendered and the risks being assumed by the parties. They need to understand the form of contract that the project is being procured under and the terms and conditions contained therein. They should be allowed to discuss and negotiate some of those terms and conditions, what damages apply, any agreements made before contract commencement and the limitations of entire agreement clauses. On Utilities contracts an understanding of the law appertaining to Public Procurement, both EU Directives and the UK Public Procurement Regulations would be invaluable. Managing. Once the contract commences then the Commercial Manager should be able to manage the contract. This means that when the contract requires a condition precedent to commence an action that this is complied with, a good example is the FIDIC time bar clause (20.1) and notification or the NEC III clause 60.3 where it states, “If the Contractor does not notify a compensation event within eight weeks of becoming aware of the event, he is not entitled to a change in the Prices, the Completion Date or a Key Date unless the Project Manager should have notified the event to the Contractor but did not”. They should map out the key notification dates and application submission dates, but most importantly, they should do exactly what the contract says. Too many times the parties set off in commercial bliss where the submission of notifications and applications are not as per the contract, the parties fall out later down the road and end up in dispute. A good example of this was where a contractor failed to submit notification as per FIDIC clause 20.1, the employer just accepted this and the parties continued on their merry way. Near completion the Employer declared that a large amount of outstanding money was not due because of a breach of clause 20.1 and therefore they were not entitled to recover entitlement under clause 20.5. The contractor argued that the Early Warnings submitted constituted notification, more by luck than judgement the early warning was followed by a letter which gave very sparse details on the events and circumstances giving rise to the claim, this was successfully argued as the required notification. Commercial Contracts – Acuity After predominantly handling disputes that arise due to the failure of one or more of the parties to follow the terms and condition laid down in the contract, from inception to completion, we have decided to review the basics. Case Law Reports A number of disputes about payment have ended up in the Technology and Construction Court in recent months, as such this newsletter concentrates on those cases. COMMERCIAL AND CASES LAW UPDATE. By Colin Tomlinson
  • 2. CONSTRUCTION LAW UPDATE | Issue 2 2 Once the procedures are in place, the Commercial Manager is then reliant on the surveyors to report the figures on how the project is doing, their responsibility is reporting of the figures, not for the management of the project, or should not be. The construction works lies outside the duties of the Commercial Manager, there is some direct input with procurement and subcontractor payment with the surveyor checking that the application from the subcontractor are correct and that the work invoiced for has been completed but the direct responsibility for the Project margin lies with the project manager. How the work is reported lies with Project Control and it is now not unusual to see the Earned Value Analysis method being used, this gives accurate reporting of the work complete and the project expenditure and any cost variance that has occurred. The finishing role of the Commercial Manager is the final account and any dispute that may have occurred. If the commercial manager has managed the commercial aspects of the project correctly then the approval of the submitted final account should be completed with relative ease. As is usually the case this is not so, and disputes arise about an assortment of items on very minor particulars. This is where a good Commercial Manager will have kept meticulous records and correspondence detailing any variations, notices or warnings. One important note to consider is that when you start the project, do so as if it will go to Adjudication, keep your correspondence polite, correct and detailed, do not as in so many cases be pedantic, rude or insult the employer’s representative, you can imagine the inference the Adjudicator will infer from the commercial representative of a company telling the employers representative exactly what they think of them. CASE LAW Caledonian Modular Ltd v Mar City Developments Ltd [2015] EWHC 1855 (TCC). In Caledonian Modular v Mar City Developments Mr Justice Coulson declined to enforce an Adjudicator's decision where the employer had failed to serve the requisite payment notices but where the contractor's application for payment was found to be invalid. In this case the contractor had submitted 15 applications, one at the end of each month, during the project. Upon submission of the 15th application a payless notice was issued by the employer, as a consequence very little was paid in response to it. In the interim, the parties commenced final account negotiations. Approximately a week after the valid payless notice was served, the contractor submitted further payment substantiation and requested that the payless notice be revised. When the employer queried the status of the submitted documents, the contractor confirmed they were "an update of the account" the employer did not issue a further payless notice. Consequently the contractor initiated an adjudication asserting that the documents constituted a 16th application for payment which was due in full as no payless notice had been served. The Adjudicator decided for the contractor, on the basis that the further documents were an "early" 16th application, as a consequence the employer had to pay GBP 1.5 million to the contractor. The employer refused to pay and the case came before Mr Justice Coulson for enforcement, he had "no hesitation" in rejecting the claim. He noted that the Adjudicator had not considered the merits of the contractor's claim, and that one of the "baleful effects" of the amendments to the HGCRA had been to increase the number of claims from contractors relying on an automatic right to payment where the employer had failed to serve notices on time. Mr Justice Coulson commented that if contractors wished to benefit from the provisions they needed to submit applications with "proper clarity". This decision provides some comfort to employers that contractors will not be able to engineer what Mr Justice Coulson described as a "wholly undeserved windfall" in this way, and also reminds contractors of the importance of submitting payment applications in a clear and straightforward fashion. Henia Investments Inc v Beck Interiors Ltd [2015] EWHC 2433 (TCC). The commercial administration of a Construction Contract can be quite difficult, the contractual procedures are not always straightforward, mistakes occur and, when relationships break down, and parties often use errors by the other side to get an "easy win". Background Henia Investments Inc ("Henia") appointed Beck Interiors Ltd ("Beck") to carry out construction and fitting out works under the JCT Standard Building Contract without Quantities 2011. The payment process under the contract was: Not later than seven days before the due date, Beck could issue an Interim Application setting out the sum it considered would become due on the due date The due date was the 29th of each month FAST FACTS Adjudicators Fees For general information the following are the last five Adjudicators rates by nominating body, primary profession and hourly fee that PCL have managed in 2015: Tecbar Barrister - £230 hr CIC Barrister - £275 hr RICS QS - £210 hr CIC Civil Eng. - £200 hr CIC Solicitor - £250 hr
  • 3. CONSTRUCTION LAW UPDATE | Issue 2 3 Interim Certificates were issued by the Contract Administrator not later than five days after the due date. These set out the sum the Contract Administrator considered was due on the due date The final date for payment was 28 days from the due date. Henia had to pay the sum set out in the Interim Certificate before this date. If there was no a valid Interim Certificate, then Henia instead had to pay the sum set out in the Interim Application If Henia wanted to pay less than the sum in the Interim Certificate / Interim Application, it had to issue a Pay Less Notice. This had to be issued not later than three days before the final date for payment. Mr Justice Akenhead noted that the parties had failed to follow the specific terms of the contract in regards to payment, again a commercial necessity to ensuring the parties do not end up in this situation. The dispute centred on payment numbers 18 and 19. And the facts are: Beck issued Interim Application 18 on 28 April 2015 (six days late) and applied for a net sum of £2,943,098.95 for the period to 30 April 2015 The Contract Administrator issued Interim Certificate 18 on 6 May 2015 (one day late). It showed a net sum payable to Beck of £226,248.95 Beck did not issue an Interim Application 19 The Contract Administrator issued Interim Certificate 19 on 4 June 2015 at 00:03 hours (three minutes late). This showed a net sum payable to Beck of £18,893.53 Henia issued a Pay Less Notice on 17 June 2015 (which was in time). This was based on Interim Certificate 19 and deductions of liquidated damages of £373,751.05. It stated that £0 was due in relation to Interim Payment 19. The questions put before Mr. Justice Akenhead were: 1. Was Beck's Interim Application 18 valid? and 2. Was Henia's Pay Less Notice valid? The Judgment The Interim Application The Contract allowed Beck to submit an Interim Application setting out the sum it considered would become due on each due date (which was the 29th of each month). However, Beck's Interim Application 18 indicated the works applied for were "Valued to 30/04/15". On this basis, Mr Justice Akenhead held that Beck's Interim Application was invalid. The Contract only allowed an application based on a valuation of the works on either 29 April or 29 May and as a consequence the application submitted on the 30 April was not valid. Mr Justice Akenhead did not comment on the timing of Beck's Interim Application which was six days late, However, the Courts have clearly shown lately that they will interpret such provisions resolutely, most recently in Caledonian Modular Ltd v Mar City Developments Ltd [2015] EWHC 1855 (TCC) and Leeds City Council v Waco UK Ltd [2015] EWHC 1400 (TCC). The Courts will show exception where there has been a course of previous dealing showing that the parties have varied the provisions, for example by allowing applications which are three-four days late. The Pay Less Notice Mr Justice Akenhead’s decision on Interim Application 18 meant the dispute over Henia's Pay Less Notice was no longer pertinent. The entire contractual mechanism had broken down, as there was no valid Interim Application or Interim Certificates no interim payment was due. Nevertheless, Mr Justice Akenhead did go on to consider the parties' arguments in relation to the Pay Less Notice. If Interim Application 18 had been valid, Henia would have been required to pay the sum in that application (as there were no valid Interim Certificates), subject to the effect of Henia's Pay Less Notice. Beck argued that a Pay Less Notice allowed Henia to pay less than the sum in the Interim Certificate only on the basis of cross claims – setoff. Therefore Beck was entitled to the difference between the sum in its Interim Application 18 (£2,943,098.95) and the liquidated damages claimed by Henia (£373,751.05). Henia contended that, as well as including any cross claims, it was also entitled to put forward its own valuation of the works in its Pay Less Notice. In this case, Henia's valuation was based on the late Interim Certificate 19 (which valued the work at £18,893.53). Its claim for liquidated damages far exceeded this and therefore no sums were due to Beck. Mr Justice Akenhead agreed with Henia. He held that the contract required Henia to serve a Pay Less Notice if it intended to "pay less than the sums stated as due". There was nothing in the wording to suggest this was limited to cross-claims. Henia could therefore, as part of a Pay Less Notice, put forward its own valuation of the works. For More Information Contact: Enquiries enquiries@priorycontractlaw.com 0044 8452 60 61 05 or ctomlinson@priorycontractlaw.com +44 07539 036 470 http://www.priorycontractlaw.com/