SlideShare a Scribd company logo
1 of 26
Download to read offline
15-Mar-13
CE 370: Prof. Abdelhamid Charifi 1
CE 370
REINFORCED CONCRETE-I
Prof. A. Charif
Bond and Development Length
Bond
• RC design assumes perfect bond between concrete and steel
• There must be no slippage between steel bars and surrounding
concrete
• Bond stress results from variation of axial force in bars, caused
by moment variation
• Bond stress is affected by development of tensile cracks.
• At a point where a tensile crack crosses a reinforcing bar, all
the tensile force is carried by the reinforcement.
• At a short distance from the crack, tension is resisted by both
the reinforcement and uncracked concrete.
• Bond stress is zero at the crack, but may be large a short
distance away.
2
15-Mar-13
CE 370: Prof. Abdelhamid Charifi 2
Bond
• Note: If there is no bonding between the two
materials and if the bars are not anchored at
their ends, they will pull out of the concrete.
As a result, the concrete beam will act as an
unreinforced member and will be subject to
sudden collapse as soon as the concrete
cracks.
3
Mechanism of bond transfer
• Bond between concrete and steel bars is due to chemical
adhesion, friction and bearing of reinforcement ribs on the
concrete
• Adhesion and friction are lost when the bar is loaded in tension as
a result of diameter reduction due to Poisson’s ratio effect
• Adhesion and friction are neglected
• Bond is transferred mainly by bearing of the deformed bars
• Plain bars have a poor bond transfer and are no longer used
• Steel bars subjected to axial compression develop a better bond
because of Poisson’s ratio effect
4
15-Mar-13
CE 370: Prof. Abdelhamid Charifi 3
Mechanism of bond transfer
Bar Bearing
5
6
Mechanism of bond transfer
15-Mar-13
CE 370: Prof. Abdelhamid Charifi 4
Types of Bond Failures
7
 Forces in concrete have longitudinal and radial
components
 Wedging action of ribs against concrete produces
tension in a cylindrical section around the bars
(similar to a concrete pipe filled with water)
 Wedging action causes cracks (splits) to occur
around the reinforcement
 Bond failure occurs by splitting of concrete parallel
to the bar
 Splitting failure surface depends on cover and bar
spacing values
8
Typical splitting failure surfaces
15-Mar-13
CE 370: Prof. Abdelhamid Charifi 5
9
Bond stress
Bond stress results from
variation of axial force in
bars, caused by moment
variation
jdd
V
jdd
dx
M
V
jd
dxd
jd
M
TTT
b
b
b













armLever
12
Development length
 Development length is the minimum embedment length of a bar
in concrete necessary to develop the yield stress in the bar, plus
some additional distance to insure toughness
 If the distance from a point where the bar stress is equal to yield
stress fy to the end of the bar (zero stress) is less than the
development length, then the bar will pull out of the concrete
10
u
by
d
dbu
y
b
yb
df
l
ld
f
d
fATT



4
4
0
2
2



15-Mar-13
CE 370: Prof. Abdelhamid Charifi 6
Tension development length
 As bond in tension bars is less than bond in compressed
bars, the development length expressions are different.
 Many factors affect the development length:
 Bar size
 Bar location
 Type of concrete (normal or lightweight)
 Bar coating (if any)
 Concrete cover and bar spacing
 Transverse reinforcement effect (confinement)
 ACI , SBC and all codes give simplified expressions
based on experimental data
11
12
Tension development length
• Bar diameter effect: Bond strength is better with larger bars
• Bar location effect: Bars with more than 300 mm of fresh
concrete cast below them will experience some gravity
migration of mortar resulting in reduction of bond strength
• Bar coating effect: Epoxy-coated bars (to protect them against
corrosion) have a reduced bond
• Concrete type effect: Lightweight concrete has a lower bond
strength than normal concrete
• Transverse steel effect: Stirrups and ties improve the bond
strength
• Cover and bar spacing effect: Bond strength is reduced with
smaller values of cover and bar spacing.
15-Mar-13
CE 370: Prof. Abdelhamid Charifi 7
13
SBC / ACI Tension development length ld
General Equation
5.2with
10
9
'







 

b
tr
b
b
trc
y
d
d
Kc
d
d
Kcf
f
l (1)

mml
K
c
d
l
d
tr
b
d
300
factorsteelTransverse
effectspacingbarandCover
factordiameterBar
factorconcretetLightweigh
factorcoatingEpoxy
factorlocationlocationBar
mmindiameterBar
mminlengthtDevelopmen













MPaff
l
f
l
cc
d
c
d
4.69
3
25
:ofequationsallIn
ofin termsexpressed
lengthtDevelopmen
''
'

14





























0.1:22
8.0:20
:factorsizeBar
1.3:concretetLightweigh
1.0:concreteNormal
:factorconcretetLightweigh
1.2:coatingepoxyofcasesOther
1.5:6thanlessspacingclearor3thanlesscoverwithcoatingEpoxy
1.0:entreinforcemUncoated
:factorcoatingEpoxy
1.0:casesOther
bond)weakeningmigrationmortarwithsteeltopof(case
1.3:(splice)bardevelopedbelowcastconcretefreshofmm300thanMore
:factorlocationlocationBar













mmd
mmd
dd
b
b
bb
SBC / ACI Tension development length
15-Mar-13
CE 370: Prof. Abdelhamid Charifi 8
15
SBC / ACI Tension development length
presentissteeletransversifevenzerotoequaltakenbemay
planesplittingalongdevelopedbeing(wires)barsofNumber
withinsteeletransversofspacingcenter-to-centerMaximum
barsdevelopedalongplanesplittingpotentialthecrosseshichw
spacingwithinsteeletransversallofareasection-crossTotal
10
factoreffectentreinforcemTransverse
tr
d
tr
yttr
trtr
K
n
ls
sA
sn
fA
KK




c = Minimum of :
(a) Smallest distance measured from concrete surface to
center of bar
(b) One half of center-to-center bar spacing
16
SBC / ACI Tension development length
In addition to the previous general equation (1), SBC and
ACI propose other conservative simplified equations for
tensile development length.
15-Mar-13
CE 370: Prof. Abdelhamid Charifi 9
17
Bar diam 20 mm or less
and deformed bars (a)
Bar diam 22 mm
or more (b)
Case 1: Clear spacing of bar
not less than db, cover not less
than db, stirrups or ties
throughout ld not less than
minimum or
Case 2: Clear spacing of bar
not less than 2db and cover
not less than db
Other cases
(S1a)b
c
y
d
f
f








'
25
12 
(S2a)b
c
y
d
f
f








'
25
18 
(S2b)b
c
y
d
f
f








'
10
9 
(S1b)b
c
y
d
f
f








'
5
3 
SBC / ACI Tension development length ld given
by simplified equations, not less than 300 mm
18
SBC / ACI Tension development length























1.3:concretetLightweigh
1.0:concreteNormal
:factorconcretetLightweigh
1.2:coatingepoxyofcasesOther
1.5:6thanlessspacingclearor3thanlesscoverandcoatingEpoxy
1.0:entreinforcemUncoated
:factorcoatingEpoxy
1.0:casesOther
1.3:bardevelopedbelowcastconcretefreshofmm300thanMore
:factorlocationlocationBar
mmindiameterBar
mminbarsdeformedoflengthtDevelopmen










bb
b
d
dd
d
l
15-Mar-13
CE 370: Prof. Abdelhamid Charifi 10
19
SBC / ACI Compression development length
(2)








 by
c
by
dc df
f
df
l 043.0,
24.0
Max:unitsmmandNewtonIn
'
Development length for bundled bars
• For bundled bars, the development length shall be that of an
individual bar increased by :
 20 % for three-bar bundle
 33 % for four-bar bundle
• The value of bar diameter d0 to consider in equations shall be
that of a hypothetical bar having the same area as the bundle.
)4or3(
44
0
22
0
 nndd
d
n
d
b
b
20
Development length for wire fabric
Deformed welded wire fabric
The development length is that
of deformed bars, times a wire
fabric factor.
The minimum value is 200 mm spacingWire
0.1,
5
,
240
Max
,.,









 


w
w
b
y
y
bardwireweldd
s
s
d
f
f
ll

 (3)
Plain welded wire fabric
For plain welded wire fabric,
the development length
shall be determined by :
factorconcretetLightweigh
areasectioncrossWire
spacingWire
3.3
',






w
w
c
y
w
w
wireplaind
A
s
f
f
s
A
l (4)
15-Mar-13
CE 370: Prof. Abdelhamid Charifi 11
Hooked Anchorages
 When sufficient space is not available to provide straight
development lengths, hooks are used.
 Hooks must satisfy geometric conditions
 Hooks are not effective in compression
 Standard Hooks: As defined in SBC 304:
21
Development Length for Standard Hooks
22
The development length ldh is measured from the critical
section of the bar to the outside end or edge of the hooks.
15-Mar-13
CE 370: Prof. Abdelhamid Charifi 12
Development length for a hook
23
The development length needed for a hook is given by:
casesspecialsomeinexcept1.0
1.0toequalareandcasesotherallFor
concreteaggregatetlightweighfor1.3toequaltaken
barscoated-eopxyfor1.2astaken
.8ormm150thanlessbenotshallequationabovefromobtained
24.0
'


Factor
dl
Factord
f
f
l
bdh
b
c
y
dh




(5)
Development length for a hook
24
0.1:taketoveconservatiisIt
0.1:casesotherallIn
8.0
3spacingwith(stirrups)lar tiesperpendicu
withenclosedbars,36andHook180
8.0
3spacingwith(stirrups)tiesparallelwithin
enclosedor(stirrups)lar tiesperpendicu
withenclosedbars,36andHook90
7.0
hookbeyondcoverHook with90
mm60coverside,36
:
24.0
0
0
0
'


































Factor
Factor
d
mmd
d
mmd
mmd
Factor
Factord
f
f
l
b
b
b
b
b
b
c
y
dh (5)

15-Mar-13
CE 370: Prof. Abdelhamid Charifi 13
25
Development length for a hook
26
Development length for a hook
Correction factor values
Hook
Type
Hooked
bar db
Side
cover
Tail
cover
Stirrups
or ties
Factor
value
1800 Any Not required 0.7
900 Not required 0.7
900 Any Any Perpendicular 0.8
900 Any Any Parallel 0.8
900 or
1800
Any Any Perpendicular 0.8
60
50
36
bds 3
6036
36
36
36
bds 3
bds 3
For all other cases : Factor = 1.0
15-Mar-13
CE 370: Prof. Abdelhamid Charifi 14
27
Problem-1: Anchorage of a Straight Bar
A 400 x 450 mm cantilever beam frames into a 400 mm thick wall.
The three 25-mm top bars are assumed to be yielding at 420 MPa.
point A (face of the wall). Compute the minimum embedment of the
bars inside the wall. 20 MPa lightweight concrete is used.
28
Problem-1: Anchorage of a Straight Bar
Construction joints are located as shown. The beam has closed 10-mm
stirrups with 300 MPa yield stress and 180 mm spacing.
Cover is 40 mm. The three 25-mm bars (in tension) are inside 14-mm
bars of grade 420 at 300 mm in each face of the wall
15-Mar-13
CE 370: Prof. Abdelhamid Charifi 15
29
Solution-1a: General Equation
mm22ismm)(25diameterbarbecause1.0
usedisconcretehlightweigtbecause1.3
coatedepoxynotarebarsbecause1.0
barstopthebelowcastconcretefreshof
mm300thanmorebewilltherebecause3.1
10
9
'









 






(1)b
b
trc
y
d d
d
Kcf
f
l
c = Minimum of :
(a) Smallest distance measured from concrete surface to
center of bar
(b) One half of center-to-center bar spacing
No stirrups in wall but 14-mm bars play role of transverse steel
30
c = Minimum of :
(a) Smallest distance measured from concrete surface to
center of bar in wall = 40 + 14 + 25/2 = 66.5 mm
(b) One half of center-to-center bar spacing
Solution-1a: General Equation
mmc
mm
5.66
75.66
2
5.662400
5.0






 

36.14
330010
4208.307
3:anchoredbeingbarsofNumber
300:withinsteeletransversofspacingMaximum
face)eachatmm300atbarmm14vertical(onesplitting
ofplanecrossingsteeletransversallofareasection-crossTotal
8.307
4
14
2420
10
2
2







tr
d
tr
tryt
yttr
tr
Knn
mmsls
-
A
mmAMPaf
sn
fA
K

15-Mar-13
CE 370: Prof. Abdelhamid Charifi 16
31
resultthechangenotwill,0Taking:Note
walltheintom1.5barsExtend
4.142825
5.2
3.10.10.13.1
20
420
10
9
5.25.22.3
25
36.145.66
10
9
'
















 

tr
d
b
tr
b
tr
b
b
trc
y
d
K
mml
d
Kc
d
Kc
d
d
Kcf
f
l (1)

Solution-1a: General Equation
32
Solution-1b: Simplified Equations
(S1b)equationsimplifiedusethuswe
,25withand(2)caseisThis
barscover toclear2spacingbarClear
4.40.110
2
253-52.52-400
spacingbarClear
mm52.55.2140barsthecover tosideClear







mmd
dd
dmm
b
bb
b
equationgeneralrepect towith
veconservatieryequation vSimplified:Note
walltheintom2.5barsExtend
7.238025
205
3.10.13.14203
5
3
'






 









 mmld
f
f
l db
c
y
d (S1b)

15-Mar-13
CE 370: Prof. Abdelhamid Charifi 17
33
Problem-2: Development of a Bar in a Cantilever
Previous example with same data. The beam has closed 10-mm
stirrups with 300 MPa yield stress and 180 mm spacing.
Check whether there is sufficient distance in the span for the
development of the three 25-mm bars.
If not what is the maximum bar diameter that can be used ?
34
Solution 2
The maximum yield stress in the bars is at point A (face of the wall).
The bars must extend a distance ld into the wall support and a
distance ld into the span. The span is 1.5 m long.
The development length for 25-mm bars has been determined in
example 1. The only difference is in the transverse reinforcement.
We use the simplified equations.
Clear bar spacing determined in example 1 is 91.5 mm = 3.66 db
Stirrup spacing (180 mm) is less than maximum spacing value
d/2 = 385/2 = 192.5 mm
For 180 mm spacing, the minimum stirrup area is:
min,
2
2
2
'
min,
0.157
4
10
2:areastirrupActual
0.80
300
180400
3
1
,
16
20
Max
3
1
,
16
Max
vv
y
wc
v
AmmA
mm
f
sbf
A






















15-Mar-13
CE 370: Prof. Abdelhamid Charifi 18
35
Solution 2
Since the clear bar spacing is at least equal to db
and stirrup area exceeds minimum value, this in fact corresponds to
case 1, and 25-mm bars, equation (S1b) is to be used. We find the
same solution as in solution 2 of example1:
mmld
f
f
l db
c
y
d 7.238025
205
3.10.13.14203
5
3
'





 









 (S1b)

The maximum distance for bar extension is equal to the span length
minus the cover : 1500 – 40 = 1460 mm
This distance is insufficient for the straight development length of
2381 mm. Thus 25-mm bars cannot be used.
We must use smaller diameter bars.
Three 25-mm bars (1472 mm2) can be replaced by six 18-mm bars
(1526 mm2).
36
Solution 2
Three 25-mm bars replaced by six 18-mm bars (1526 mm2).
(S1a)equationsimplifiedusethuswe
)20(,18withand(1)caseisThis
value,minimumexceedsareastirrupand,spacingbarClear
16.28.38
5
816-942-400
spacingbarClear
mm94940wallin thebarsthecover tosideClear







mmmmd
d
dmm
b
b
b
mml
ld
f
f
l
d
db
c
y
d
1.1371
18
2025
3.10.13.142012
25
12
'






 









 (S1a)

The available distance (1460 mm) is sufficient for this development
length. 18-mm bars can thus be used for this cantilever beam.
15-Mar-13
CE 370: Prof. Abdelhamid Charifi 19
37
Problem-3: Hooked Bar Anchorage into a Column
The end of 400 x 600 mm beam frames into a 650 x 650 mm column.
The column has four 36-mm bars. The top reinforcement of the beam
consists of four 25-mm bars. 20 MPa normal concrete and 420 MPa
steel are used. Design the anchorage of the four 25-mm bars.
38
Problem-3: Hooked Bar Anchorage into a Column
15-Mar-13
CE 370: Prof. Abdelhamid Charifi 20
39
Solution 3
As the column reinforcement provides considerable confinement,
we will use general equation (1) for a straight development length :
mm22ismm)(25diameterbarbecause1.0
usedisconcretenormalbecause1.0
coatedepoxynotarebarsbecause1.0
barstopthebelowcastconcretefreshof
mm300thanmorebewilltherebecause3.1
10
9
'









 






(1)b
b
trc
y
d d
d
Kcf
f
l
40
c = Minimum of :
(a) Smallest distance measured from concrete surface to
center of bar = 125 + 40 + 10 + 25/2 = 187.5 mm
(b) One half of center-to-center bar spacing
mmc
mm
83.45
83.45
3
)5.121040(2400
5.0






 

6.41
451410
4207.2035
4:anchoredbeingbarsofNumber
514)2/361040(2650:steeletransversofSpacing
bars)mm36vertical(twosplitting
ofplanecrossingsteeletransversallofareasection-crossTotal
7.2035
4
36
2420
10
2
2







tr
tr
tryt
yttr
tr
Knn
mmss
-
A
mmAMPaf
sn
fA
K

Solution 3
15-Mar-13
CE 370: Prof. Abdelhamid Charifi 21
41
Solution 3
mml
d
Kc
d
Kc
d
d
Kcf
f
l
d
b
tr
b
tr
b
b
trc
y
d
8.109825
5.2
0.10.10.13.1
20
420
10
9
5.25.25.3
25
6.4183.45
10
9
'














 
 (1)

This development length exceeds the column width.
It is thus necessary to use hooks to anchor the bars.
42
mm563.5oflengthtdevelopmenhookfor thesufficientisdistanceThis
mm60050650coverTail-650hookforavailableDistance
5.563OK
144)8,150(Max5.56325
20
4200.10.124.0
0.1factorcorrectionunitconsiderWe
bars)forcoating-epoxynoandconcrete(Normal1.0
.8ormm150thanlessbenotshallequationabovefromobtained
24.0
'








mml
mmdmml
Factor
dl
Factord
f
f
l
dh
bdh
bdh
b
c
y
dh


(5)
Solution 3
The development length for a hook is given by equation (5):
15-Mar-13
CE 370: Prof. Abdelhamid Charifi 22
43
Solution 3
heightmm600joint withcolumn-beamin thefitwilldistanceThis
40016
312
2
12hookofheightVertical
5.563
mmd
dddd
D
d
mml
b
bbbbb
dh



Bar Cutoff
• RC flexural design is usually performed at the
maximum moment point.
• At other points, the required reinforcement is smaller
and the number of bars may be reduced by stopping
some of them (bar cutoff)
• A bar can be stopped when it is no longer required. It
must however be extended at a sufficient distance.
• The bar must be extended by a distance equal to the
development length plus an extra distance (due to shear
effect) equal to Max(d , 12db) where d is the steel depth
and db is the bar diameter
44
15-Mar-13
CE 370: Prof. Abdelhamid Charifi 23
Capacity and demand diagrams (offer > demand) with bar cutoff for
simply supported beam– BMD on tension side in RC
For real structures, bar cutoff must be performed using the
envelope of moment diagram using all load combinations
Bar Cutoff
46
Bar Cutoff
15-Mar-13
CE 370: Prof. Abdelhamid Charifi 24
Bar Splices
• Reinforcing bars must frequently be spliced because of:
– Limited bar lengths available (bar length usually limited to
12 m and exceptionally to 18 m)
– Requirement at construction joints
– Changes from larger bars to smaller bars
• There are three splice types:
 Lapped splices
 Mechanical splices
 Welded splices
47
Lap Splices
• Lap splices are achieved by overlapping the bars over a certain
length, thereby enabling the transfer of axial force from the
terminating bar to the connecting bar through the mechanism of
anchorage (development) bond with the surrounding concrete.
• Lap splices are usually not permitted for very large diameter bars
(Ф > 36 mm), for which welded splices are recommended (except
at footing-column joints).
48
15-Mar-13
CE 370: Prof. Abdelhamid Charifi 25
49
Tension Lap Splice
Tension Lap Splice
• Center-to-center distance between lapped bars not greater than
minimum of (one fifth of lap splice , 150 mm)
• There are two classes of tension lap splices:
 Class A splice : 1.0 ld
 Class B splice : 1.3 ld
• The required lap class is selected as shown :
50
Amount of steel spliced
Stress ratio
fs / fy
50 % or less
spliced
More than 50 %
spliced
0.5 or less Class A Class B
More than 0.5 Class B Class B
15-Mar-13
CE 370: Prof. Abdelhamid Charifi 26
Welded Splices and
Mechanical Connections
• Welded splices and mechanical connections are
particularly suitable for large diameter bars.
• This reduces consumption of reinforcing steel.
51
52
Compression Lap Splice
Compression lap splices will be described
in the Column Chapter

More Related Content

What's hot

Design and Detailing of RC Deep beams as per IS 456-2000
Design and Detailing of RC Deep beams as per IS 456-2000Design and Detailing of RC Deep beams as per IS 456-2000
Design and Detailing of RC Deep beams as per IS 456-2000VVIETCIVIL
 
BIAXIAL COLUMN DESIGN
BIAXIAL COLUMN DESIGNBIAXIAL COLUMN DESIGN
BIAXIAL COLUMN DESIGNshawon_sb
 
Module 1 Behaviour of RC beams in Shear and Torsion
Module 1   Behaviour of RC beams in Shear and TorsionModule 1   Behaviour of RC beams in Shear and Torsion
Module 1 Behaviour of RC beams in Shear and TorsionVVIETCIVIL
 
Static Indeterminacy and Kinematic Indeterminacy
Static Indeterminacy and Kinematic IndeterminacyStatic Indeterminacy and Kinematic Indeterminacy
Static Indeterminacy and Kinematic IndeterminacyDarshil Vekaria
 
Design of combined footing ppt
Design of combined footing pptDesign of combined footing ppt
Design of combined footing pptBharti Shinde
 
Stiffness method of structural analysis
Stiffness method of structural analysisStiffness method of structural analysis
Stiffness method of structural analysisKaran Patel
 
Structural analysis 1
Structural analysis   1Structural analysis   1
Structural analysis 1R VIJAYAKUMAR
 
Unit 3 flexibility-anujajape
Unit 3 flexibility-anujajapeUnit 3 flexibility-anujajape
Unit 3 flexibility-anujajapeanujajape
 
Analysis & design of T-Beam bridge
Analysis & design of T-Beam bridgeAnalysis & design of T-Beam bridge
Analysis & design of T-Beam bridgeElamathy Murugan
 

What's hot (20)

7 losses in prestress
7 losses in prestress7 losses in prestress
7 losses in prestress
 
Design of beams
Design of beamsDesign of beams
Design of beams
 
Beam design
Beam designBeam design
Beam design
 
Design and Detailing of RC Deep beams as per IS 456-2000
Design and Detailing of RC Deep beams as per IS 456-2000Design and Detailing of RC Deep beams as per IS 456-2000
Design and Detailing of RC Deep beams as per IS 456-2000
 
Prestressed Concrete Design
Prestressed Concrete DesignPrestressed Concrete Design
Prestressed Concrete Design
 
Design of steel structural elements
Design of steel structural elementsDesign of steel structural elements
Design of steel structural elements
 
BIAXIAL COLUMN DESIGN
BIAXIAL COLUMN DESIGNBIAXIAL COLUMN DESIGN
BIAXIAL COLUMN DESIGN
 
Module 1 Behaviour of RC beams in Shear and Torsion
Module 1   Behaviour of RC beams in Shear and TorsionModule 1   Behaviour of RC beams in Shear and Torsion
Module 1 Behaviour of RC beams in Shear and Torsion
 
Design of footing as per IS 456-2000
Design of footing as per IS 456-2000Design of footing as per IS 456-2000
Design of footing as per IS 456-2000
 
Static Indeterminacy and Kinematic Indeterminacy
Static Indeterminacy and Kinematic IndeterminacyStatic Indeterminacy and Kinematic Indeterminacy
Static Indeterminacy and Kinematic Indeterminacy
 
Design of combined footing ppt
Design of combined footing pptDesign of combined footing ppt
Design of combined footing ppt
 
Stiffness method of structural analysis
Stiffness method of structural analysisStiffness method of structural analysis
Stiffness method of structural analysis
 
Classification of bridges
Classification of bridgesClassification of bridges
Classification of bridges
 
Structural analysis 1
Structural analysis   1Structural analysis   1
Structural analysis 1
 
Design of floor slab
Design of floor slabDesign of floor slab
Design of floor slab
 
Reinforced column design
Reinforced column design Reinforced column design
Reinforced column design
 
Unit 3 flexibility-anujajape
Unit 3 flexibility-anujajapeUnit 3 flexibility-anujajape
Unit 3 flexibility-anujajape
 
Design of steel beams
Design of steel beamsDesign of steel beams
Design of steel beams
 
Bs8110 design notes
Bs8110 design notesBs8110 design notes
Bs8110 design notes
 
Analysis & design of T-Beam bridge
Analysis & design of T-Beam bridgeAnalysis & design of T-Beam bridge
Analysis & design of T-Beam bridge
 

Similar to Lec10 Bond and Development Length (Reinforced Concrete Design I & Prof. Abdelhamid Charif)

Lec03 Flexural Behavior of RC Beams (Reinforced Concrete Design I & Prof. Abd...
Lec03 Flexural Behavior of RC Beams (Reinforced Concrete Design I & Prof. Abd...Lec03 Flexural Behavior of RC Beams (Reinforced Concrete Design I & Prof. Abd...
Lec03 Flexural Behavior of RC Beams (Reinforced Concrete Design I & Prof. Abd...Hossam Shafiq II
 
Lec05 Design of Rectangular Beams with Tension Steel only (Reinforced Concret...
Lec05 Design of Rectangular Beams with Tension Steel only (Reinforced Concret...Lec05 Design of Rectangular Beams with Tension Steel only (Reinforced Concret...
Lec05 Design of Rectangular Beams with Tension Steel only (Reinforced Concret...Hossam Shafiq II
 
Calulation of deflection and crack width according to is 456 2000
Calulation of deflection and crack width according to is 456 2000Calulation of deflection and crack width according to is 456 2000
Calulation of deflection and crack width according to is 456 2000Vikas Mehta
 
4-flexuralbehaviorofrcbeams-170818223637.pdf
4-flexuralbehaviorofrcbeams-170818223637.pdf4-flexuralbehaviorofrcbeams-170818223637.pdf
4-flexuralbehaviorofrcbeams-170818223637.pdfEmHetchMaidabino
 
Lecture chapter 1u
Lecture chapter 1uLecture chapter 1u
Lecture chapter 1urgo-amo
 
Research Inventy : International Journal of Engineering and Science is publis...
Research Inventy : International Journal of Engineering and Science is publis...Research Inventy : International Journal of Engineering and Science is publis...
Research Inventy : International Journal of Engineering and Science is publis...researchinventy
 
PRESTRESSED CONCRETE STRUCTURES
PRESTRESSED CONCRETE STRUCTURESPRESTRESSED CONCRETE STRUCTURES
PRESTRESSED CONCRETE STRUCTURESTarun kumar
 
IRJET - Experimental Investigation of flexural member of Beam Opening in ...
IRJET -  	  Experimental Investigation of flexural member of Beam Opening in ...IRJET -  	  Experimental Investigation of flexural member of Beam Opening in ...
IRJET - Experimental Investigation of flexural member of Beam Opening in ...IRJET Journal
 
Div_Syd_detailing_of_reinforcement_in_concrete_structures.pdf
Div_Syd_detailing_of_reinforcement_in_concrete_structures.pdfDiv_Syd_detailing_of_reinforcement_in_concrete_structures.pdf
Div_Syd_detailing_of_reinforcement_in_concrete_structures.pdfLandelSmith1
 
Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)ahsanrabbani
 
DSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxx
DSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxxDSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxx
DSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxxADITYAPILLAI29
 
Effect of creep on composite steel concrete section
Effect of creep on composite steel concrete sectionEffect of creep on composite steel concrete section
Effect of creep on composite steel concrete sectionKamel Farid
 
Shear connector 081281000409
Shear connector 081281000409Shear connector 081281000409
Shear connector 081281000409shear connector
 
Moment Resisting Frame.pdf
Moment Resisting Frame.pdfMoment Resisting Frame.pdf
Moment Resisting Frame.pdfZeinab Awada
 

Similar to Lec10 Bond and Development Length (Reinforced Concrete Design I & Prof. Abdelhamid Charif) (20)

Lec03 Flexural Behavior of RC Beams (Reinforced Concrete Design I & Prof. Abd...
Lec03 Flexural Behavior of RC Beams (Reinforced Concrete Design I & Prof. Abd...Lec03 Flexural Behavior of RC Beams (Reinforced Concrete Design I & Prof. Abd...
Lec03 Flexural Behavior of RC Beams (Reinforced Concrete Design I & Prof. Abd...
 
Lec05 Design of Rectangular Beams with Tension Steel only (Reinforced Concret...
Lec05 Design of Rectangular Beams with Tension Steel only (Reinforced Concret...Lec05 Design of Rectangular Beams with Tension Steel only (Reinforced Concret...
Lec05 Design of Rectangular Beams with Tension Steel only (Reinforced Concret...
 
Calulation of deflection and crack width according to is 456 2000
Calulation of deflection and crack width according to is 456 2000Calulation of deflection and crack width according to is 456 2000
Calulation of deflection and crack width according to is 456 2000
 
4-flexuralbehaviorofrcbeams-170818223637.pdf
4-flexuralbehaviorofrcbeams-170818223637.pdf4-flexuralbehaviorofrcbeams-170818223637.pdf
4-flexuralbehaviorofrcbeams-170818223637.pdf
 
Ductile detailing
Ductile detailingDuctile detailing
Ductile detailing
 
Lecture chapter 1u
Lecture chapter 1uLecture chapter 1u
Lecture chapter 1u
 
Research Inventy : International Journal of Engineering and Science is publis...
Research Inventy : International Journal of Engineering and Science is publis...Research Inventy : International Journal of Engineering and Science is publis...
Research Inventy : International Journal of Engineering and Science is publis...
 
PRESTRESSED CONCRETE STRUCTURES
PRESTRESSED CONCRETE STRUCTURESPRESTRESSED CONCRETE STRUCTURES
PRESTRESSED CONCRETE STRUCTURES
 
IRJET - Experimental Investigation of flexural member of Beam Opening in ...
IRJET -  	  Experimental Investigation of flexural member of Beam Opening in ...IRJET -  	  Experimental Investigation of flexural member of Beam Opening in ...
IRJET - Experimental Investigation of flexural member of Beam Opening in ...
 
C013121320
C013121320C013121320
C013121320
 
Div_Syd_detailing_of_reinforcement_in_concrete_structures.pdf
Div_Syd_detailing_of_reinforcement_in_concrete_structures.pdfDiv_Syd_detailing_of_reinforcement_in_concrete_structures.pdf
Div_Syd_detailing_of_reinforcement_in_concrete_structures.pdf
 
Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)
 
2 literature review
2 literature review2 literature review
2 literature review
 
W04408116121
W04408116121W04408116121
W04408116121
 
DSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxx
DSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxxDSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxx
DSR chap4 shear and bond pdf.pptxxxxxxxxxxxxxxxxxxxxxx
 
Effect of creep on composite steel concrete section
Effect of creep on composite steel concrete sectionEffect of creep on composite steel concrete section
Effect of creep on composite steel concrete section
 
Shear connector 081281000409
Shear connector 081281000409Shear connector 081281000409
Shear connector 081281000409
 
9_Bond.pdf
9_Bond.pdf9_Bond.pdf
9_Bond.pdf
 
Moment Resisting Frame.pdf
Moment Resisting Frame.pdfMoment Resisting Frame.pdf
Moment Resisting Frame.pdf
 
Design of connections
Design of connectionsDesign of connections
Design of connections
 

More from Hossam Shafiq II

Basics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-Agha
Basics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-AghaBasics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-Agha
Basics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-AghaHossam Shafiq II
 
Ch8 Truss Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch8 Truss Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...Ch8 Truss Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch8 Truss Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...Hossam Shafiq II
 
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...Hossam Shafiq II
 
Ch6 Composite Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Pr...
Ch6 Composite Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Pr...Ch6 Composite Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Pr...
Ch6 Composite Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Pr...Hossam Shafiq II
 
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...Hossam Shafiq II
 
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...Hossam Shafiq II
 
Ch3 Design Considerations (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. M...
Ch3 Design Considerations (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. M...Ch3 Design Considerations (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. M...
Ch3 Design Considerations (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. M...Hossam Shafiq II
 
Ch2 Design Loads on Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr....
Ch2 Design Loads on Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr....Ch2 Design Loads on Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr....
Ch2 Design Loads on Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr....Hossam Shafiq II
 
Ch1 Introduction (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally A...
Ch1 Introduction (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally A...Ch1 Introduction (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally A...
Ch1 Introduction (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally A...Hossam Shafiq II
 
Lec05 STRUCTURE SYSTEMS to resist EARTHQUAKE (Earthquake Engineering هندسة ال...
Lec05 STRUCTURE SYSTEMS to resist EARTHQUAKE (Earthquake Engineering هندسة ال...Lec05 STRUCTURE SYSTEMS to resist EARTHQUAKE (Earthquake Engineering هندسة ال...
Lec05 STRUCTURE SYSTEMS to resist EARTHQUAKE (Earthquake Engineering هندسة ال...Hossam Shafiq II
 
Lec04 Earthquake Force Using Response Specturum Method (2) (Earthquake Engine...
Lec04 Earthquake Force Using Response Specturum Method (2) (Earthquake Engine...Lec04 Earthquake Force Using Response Specturum Method (2) (Earthquake Engine...
Lec04 Earthquake Force Using Response Specturum Method (2) (Earthquake Engine...Hossam Shafiq II
 
Lec03 Earthquake Force Using Response Specturum Method (1) (Earthquake Engine...
Lec03 Earthquake Force Using Response Specturum Method (1) (Earthquake Engine...Lec03 Earthquake Force Using Response Specturum Method (1) (Earthquake Engine...
Lec03 Earthquake Force Using Response Specturum Method (1) (Earthquake Engine...Hossam Shafiq II
 
Lec02 Earthquake Damage to Concrete Structure (Earthquake Engineering هندسة ا...
Lec02 Earthquake Damage to Concrete Structure (Earthquake Engineering هندسة ا...Lec02 Earthquake Damage to Concrete Structure (Earthquake Engineering هندسة ا...
Lec02 Earthquake Damage to Concrete Structure (Earthquake Engineering هندسة ا...Hossam Shafiq II
 
Lec01 Design of RC Structures under lateral load (Earthquake Engineering هندس...
Lec01 Design of RC Structures under lateral load (Earthquake Engineering هندس...Lec01 Design of RC Structures under lateral load (Earthquake Engineering هندس...
Lec01 Design of RC Structures under lateral load (Earthquake Engineering هندس...Hossam Shafiq II
 
Lec13 Continuous Beams and One Way Slabs(3) Footings (Reinforced Concrete Des...
Lec13 Continuous Beams and One Way Slabs(3) Footings (Reinforced Concrete Des...Lec13 Continuous Beams and One Way Slabs(3) Footings (Reinforced Concrete Des...
Lec13 Continuous Beams and One Way Slabs(3) Footings (Reinforced Concrete Des...Hossam Shafiq II
 
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...Hossam Shafiq II
 
Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...
Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...
Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...Hossam Shafiq II
 
Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...
Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...
Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...Hossam Shafiq II
 
Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...
Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...
Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...Hossam Shafiq II
 
Lec04 Analysis of Rectangular RC Beams (Reinforced Concrete Design I & Prof. ...
Lec04 Analysis of Rectangular RC Beams (Reinforced Concrete Design I & Prof. ...Lec04 Analysis of Rectangular RC Beams (Reinforced Concrete Design I & Prof. ...
Lec04 Analysis of Rectangular RC Beams (Reinforced Concrete Design I & Prof. ...Hossam Shafiq II
 

More from Hossam Shafiq II (20)

Basics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-Agha
Basics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-AghaBasics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-Agha
Basics of Foundation Engineering هندسة الأساسات & Eng. Ahmed S. Al-Agha
 
Ch8 Truss Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch8 Truss Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...Ch8 Truss Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch8 Truss Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
 
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
Ch7 Box Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metw...
 
Ch6 Composite Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Pr...
Ch6 Composite Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Pr...Ch6 Composite Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Pr...
Ch6 Composite Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Pr...
 
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...
Ch5 Plate Girder Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Me...
 
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
 
Ch3 Design Considerations (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. M...
Ch3 Design Considerations (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. M...Ch3 Design Considerations (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. M...
Ch3 Design Considerations (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. M...
 
Ch2 Design Loads on Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr....
Ch2 Design Loads on Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr....Ch2 Design Loads on Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr....
Ch2 Design Loads on Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr....
 
Ch1 Introduction (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally A...
Ch1 Introduction (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally A...Ch1 Introduction (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally A...
Ch1 Introduction (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally A...
 
Lec05 STRUCTURE SYSTEMS to resist EARTHQUAKE (Earthquake Engineering هندسة ال...
Lec05 STRUCTURE SYSTEMS to resist EARTHQUAKE (Earthquake Engineering هندسة ال...Lec05 STRUCTURE SYSTEMS to resist EARTHQUAKE (Earthquake Engineering هندسة ال...
Lec05 STRUCTURE SYSTEMS to resist EARTHQUAKE (Earthquake Engineering هندسة ال...
 
Lec04 Earthquake Force Using Response Specturum Method (2) (Earthquake Engine...
Lec04 Earthquake Force Using Response Specturum Method (2) (Earthquake Engine...Lec04 Earthquake Force Using Response Specturum Method (2) (Earthquake Engine...
Lec04 Earthquake Force Using Response Specturum Method (2) (Earthquake Engine...
 
Lec03 Earthquake Force Using Response Specturum Method (1) (Earthquake Engine...
Lec03 Earthquake Force Using Response Specturum Method (1) (Earthquake Engine...Lec03 Earthquake Force Using Response Specturum Method (1) (Earthquake Engine...
Lec03 Earthquake Force Using Response Specturum Method (1) (Earthquake Engine...
 
Lec02 Earthquake Damage to Concrete Structure (Earthquake Engineering هندسة ا...
Lec02 Earthquake Damage to Concrete Structure (Earthquake Engineering هندسة ا...Lec02 Earthquake Damage to Concrete Structure (Earthquake Engineering هندسة ا...
Lec02 Earthquake Damage to Concrete Structure (Earthquake Engineering هندسة ا...
 
Lec01 Design of RC Structures under lateral load (Earthquake Engineering هندس...
Lec01 Design of RC Structures under lateral load (Earthquake Engineering هندس...Lec01 Design of RC Structures under lateral load (Earthquake Engineering هندس...
Lec01 Design of RC Structures under lateral load (Earthquake Engineering هندس...
 
Lec13 Continuous Beams and One Way Slabs(3) Footings (Reinforced Concrete Des...
Lec13 Continuous Beams and One Way Slabs(3) Footings (Reinforced Concrete Des...Lec13 Continuous Beams and One Way Slabs(3) Footings (Reinforced Concrete Des...
Lec13 Continuous Beams and One Way Slabs(3) Footings (Reinforced Concrete Des...
 
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
Lec12 Continuous Beams and One Way Slabs(2) Columns (Reinforced Concrete Desi...
 
Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...
Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...
Lec11 Continuous Beams and One Way Slabs(1) (Reinforced Concrete Design I & P...
 
Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...
Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...
Lec07 Analysis and Design of Doubly Reinforced Beam (Reinforced Concrete Desi...
 
Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...
Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...
Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...
 
Lec04 Analysis of Rectangular RC Beams (Reinforced Concrete Design I & Prof. ...
Lec04 Analysis of Rectangular RC Beams (Reinforced Concrete Design I & Prof. ...Lec04 Analysis of Rectangular RC Beams (Reinforced Concrete Design I & Prof. ...
Lec04 Analysis of Rectangular RC Beams (Reinforced Concrete Design I & Prof. ...
 

Recently uploaded

CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 

Recently uploaded (20)

CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 

Lec10 Bond and Development Length (Reinforced Concrete Design I & Prof. Abdelhamid Charif)

  • 1. 15-Mar-13 CE 370: Prof. Abdelhamid Charifi 1 CE 370 REINFORCED CONCRETE-I Prof. A. Charif Bond and Development Length Bond • RC design assumes perfect bond between concrete and steel • There must be no slippage between steel bars and surrounding concrete • Bond stress results from variation of axial force in bars, caused by moment variation • Bond stress is affected by development of tensile cracks. • At a point where a tensile crack crosses a reinforcing bar, all the tensile force is carried by the reinforcement. • At a short distance from the crack, tension is resisted by both the reinforcement and uncracked concrete. • Bond stress is zero at the crack, but may be large a short distance away. 2
  • 2. 15-Mar-13 CE 370: Prof. Abdelhamid Charifi 2 Bond • Note: If there is no bonding between the two materials and if the bars are not anchored at their ends, they will pull out of the concrete. As a result, the concrete beam will act as an unreinforced member and will be subject to sudden collapse as soon as the concrete cracks. 3 Mechanism of bond transfer • Bond between concrete and steel bars is due to chemical adhesion, friction and bearing of reinforcement ribs on the concrete • Adhesion and friction are lost when the bar is loaded in tension as a result of diameter reduction due to Poisson’s ratio effect • Adhesion and friction are neglected • Bond is transferred mainly by bearing of the deformed bars • Plain bars have a poor bond transfer and are no longer used • Steel bars subjected to axial compression develop a better bond because of Poisson’s ratio effect 4
  • 3. 15-Mar-13 CE 370: Prof. Abdelhamid Charifi 3 Mechanism of bond transfer Bar Bearing 5 6 Mechanism of bond transfer
  • 4. 15-Mar-13 CE 370: Prof. Abdelhamid Charifi 4 Types of Bond Failures 7  Forces in concrete have longitudinal and radial components  Wedging action of ribs against concrete produces tension in a cylindrical section around the bars (similar to a concrete pipe filled with water)  Wedging action causes cracks (splits) to occur around the reinforcement  Bond failure occurs by splitting of concrete parallel to the bar  Splitting failure surface depends on cover and bar spacing values 8 Typical splitting failure surfaces
  • 5. 15-Mar-13 CE 370: Prof. Abdelhamid Charifi 5 9 Bond stress Bond stress results from variation of axial force in bars, caused by moment variation jdd V jdd dx M V jd dxd jd M TTT b b b              armLever 12 Development length  Development length is the minimum embedment length of a bar in concrete necessary to develop the yield stress in the bar, plus some additional distance to insure toughness  If the distance from a point where the bar stress is equal to yield stress fy to the end of the bar (zero stress) is less than the development length, then the bar will pull out of the concrete 10 u by d dbu y b yb df l ld f d fATT    4 4 0 2 2   
  • 6. 15-Mar-13 CE 370: Prof. Abdelhamid Charifi 6 Tension development length  As bond in tension bars is less than bond in compressed bars, the development length expressions are different.  Many factors affect the development length:  Bar size  Bar location  Type of concrete (normal or lightweight)  Bar coating (if any)  Concrete cover and bar spacing  Transverse reinforcement effect (confinement)  ACI , SBC and all codes give simplified expressions based on experimental data 11 12 Tension development length • Bar diameter effect: Bond strength is better with larger bars • Bar location effect: Bars with more than 300 mm of fresh concrete cast below them will experience some gravity migration of mortar resulting in reduction of bond strength • Bar coating effect: Epoxy-coated bars (to protect them against corrosion) have a reduced bond • Concrete type effect: Lightweight concrete has a lower bond strength than normal concrete • Transverse steel effect: Stirrups and ties improve the bond strength • Cover and bar spacing effect: Bond strength is reduced with smaller values of cover and bar spacing.
  • 7. 15-Mar-13 CE 370: Prof. Abdelhamid Charifi 7 13 SBC / ACI Tension development length ld General Equation 5.2with 10 9 '           b tr b b trc y d d Kc d d Kcf f l (1)  mml K c d l d tr b d 300 factorsteelTransverse effectspacingbarandCover factordiameterBar factorconcretetLightweigh factorcoatingEpoxy factorlocationlocationBar mmindiameterBar mminlengthtDevelopmen              MPaff l f l cc d c d 4.69 3 25 :ofequationsallIn ofin termsexpressed lengthtDevelopmen '' '  14                              0.1:22 8.0:20 :factorsizeBar 1.3:concretetLightweigh 1.0:concreteNormal :factorconcretetLightweigh 1.2:coatingepoxyofcasesOther 1.5:6thanlessspacingclearor3thanlesscoverwithcoatingEpoxy 1.0:entreinforcemUncoated :factorcoatingEpoxy 1.0:casesOther bond)weakeningmigrationmortarwithsteeltopof(case 1.3:(splice)bardevelopedbelowcastconcretefreshofmm300thanMore :factorlocationlocationBar              mmd mmd dd b b bb SBC / ACI Tension development length
  • 8. 15-Mar-13 CE 370: Prof. Abdelhamid Charifi 8 15 SBC / ACI Tension development length presentissteeletransversifevenzerotoequaltakenbemay planesplittingalongdevelopedbeing(wires)barsofNumber withinsteeletransversofspacingcenter-to-centerMaximum barsdevelopedalongplanesplittingpotentialthecrosseshichw spacingwithinsteeletransversallofareasection-crossTotal 10 factoreffectentreinforcemTransverse tr d tr yttr trtr K n ls sA sn fA KK     c = Minimum of : (a) Smallest distance measured from concrete surface to center of bar (b) One half of center-to-center bar spacing 16 SBC / ACI Tension development length In addition to the previous general equation (1), SBC and ACI propose other conservative simplified equations for tensile development length.
  • 9. 15-Mar-13 CE 370: Prof. Abdelhamid Charifi 9 17 Bar diam 20 mm or less and deformed bars (a) Bar diam 22 mm or more (b) Case 1: Clear spacing of bar not less than db, cover not less than db, stirrups or ties throughout ld not less than minimum or Case 2: Clear spacing of bar not less than 2db and cover not less than db Other cases (S1a)b c y d f f         ' 25 12  (S2a)b c y d f f         ' 25 18  (S2b)b c y d f f         ' 10 9  (S1b)b c y d f f         ' 5 3  SBC / ACI Tension development length ld given by simplified equations, not less than 300 mm 18 SBC / ACI Tension development length                        1.3:concretetLightweigh 1.0:concreteNormal :factorconcretetLightweigh 1.2:coatingepoxyofcasesOther 1.5:6thanlessspacingclearor3thanlesscoverandcoatingEpoxy 1.0:entreinforcemUncoated :factorcoatingEpoxy 1.0:casesOther 1.3:bardevelopedbelowcastconcretefreshofmm300thanMore :factorlocationlocationBar mmindiameterBar mminbarsdeformedoflengthtDevelopmen           bb b d dd d l
  • 10. 15-Mar-13 CE 370: Prof. Abdelhamid Charifi 10 19 SBC / ACI Compression development length (2)          by c by dc df f df l 043.0, 24.0 Max:unitsmmandNewtonIn ' Development length for bundled bars • For bundled bars, the development length shall be that of an individual bar increased by :  20 % for three-bar bundle  33 % for four-bar bundle • The value of bar diameter d0 to consider in equations shall be that of a hypothetical bar having the same area as the bundle. )4or3( 44 0 22 0  nndd d n d b b 20 Development length for wire fabric Deformed welded wire fabric The development length is that of deformed bars, times a wire fabric factor. The minimum value is 200 mm spacingWire 0.1, 5 , 240 Max ,.,              w w b y y bardwireweldd s s d f f ll   (3) Plain welded wire fabric For plain welded wire fabric, the development length shall be determined by : factorconcretetLightweigh areasectioncrossWire spacingWire 3.3 ',       w w c y w w wireplaind A s f f s A l (4)
  • 11. 15-Mar-13 CE 370: Prof. Abdelhamid Charifi 11 Hooked Anchorages  When sufficient space is not available to provide straight development lengths, hooks are used.  Hooks must satisfy geometric conditions  Hooks are not effective in compression  Standard Hooks: As defined in SBC 304: 21 Development Length for Standard Hooks 22 The development length ldh is measured from the critical section of the bar to the outside end or edge of the hooks.
  • 12. 15-Mar-13 CE 370: Prof. Abdelhamid Charifi 12 Development length for a hook 23 The development length needed for a hook is given by: casesspecialsomeinexcept1.0 1.0toequalareandcasesotherallFor concreteaggregatetlightweighfor1.3toequaltaken barscoated-eopxyfor1.2astaken .8ormm150thanlessbenotshallequationabovefromobtained 24.0 '   Factor dl Factord f f l bdh b c y dh     (5) Development length for a hook 24 0.1:taketoveconservatiisIt 0.1:casesotherallIn 8.0 3spacingwith(stirrups)lar tiesperpendicu withenclosedbars,36andHook180 8.0 3spacingwith(stirrups)tiesparallelwithin enclosedor(stirrups)lar tiesperpendicu withenclosedbars,36andHook90 7.0 hookbeyondcoverHook with90 mm60coverside,36 : 24.0 0 0 0 '                                   Factor Factor d mmd d mmd mmd Factor Factord f f l b b b b b b c y dh (5) 
  • 13. 15-Mar-13 CE 370: Prof. Abdelhamid Charifi 13 25 Development length for a hook 26 Development length for a hook Correction factor values Hook Type Hooked bar db Side cover Tail cover Stirrups or ties Factor value 1800 Any Not required 0.7 900 Not required 0.7 900 Any Any Perpendicular 0.8 900 Any Any Parallel 0.8 900 or 1800 Any Any Perpendicular 0.8 60 50 36 bds 3 6036 36 36 36 bds 3 bds 3 For all other cases : Factor = 1.0
  • 14. 15-Mar-13 CE 370: Prof. Abdelhamid Charifi 14 27 Problem-1: Anchorage of a Straight Bar A 400 x 450 mm cantilever beam frames into a 400 mm thick wall. The three 25-mm top bars are assumed to be yielding at 420 MPa. point A (face of the wall). Compute the minimum embedment of the bars inside the wall. 20 MPa lightweight concrete is used. 28 Problem-1: Anchorage of a Straight Bar Construction joints are located as shown. The beam has closed 10-mm stirrups with 300 MPa yield stress and 180 mm spacing. Cover is 40 mm. The three 25-mm bars (in tension) are inside 14-mm bars of grade 420 at 300 mm in each face of the wall
  • 15. 15-Mar-13 CE 370: Prof. Abdelhamid Charifi 15 29 Solution-1a: General Equation mm22ismm)(25diameterbarbecause1.0 usedisconcretehlightweigtbecause1.3 coatedepoxynotarebarsbecause1.0 barstopthebelowcastconcretefreshof mm300thanmorebewilltherebecause3.1 10 9 '                  (1)b b trc y d d d Kcf f l c = Minimum of : (a) Smallest distance measured from concrete surface to center of bar (b) One half of center-to-center bar spacing No stirrups in wall but 14-mm bars play role of transverse steel 30 c = Minimum of : (a) Smallest distance measured from concrete surface to center of bar in wall = 40 + 14 + 25/2 = 66.5 mm (b) One half of center-to-center bar spacing Solution-1a: General Equation mmc mm 5.66 75.66 2 5.662400 5.0          36.14 330010 4208.307 3:anchoredbeingbarsofNumber 300:withinsteeletransversofspacingMaximum face)eachatmm300atbarmm14vertical(onesplitting ofplanecrossingsteeletransversallofareasection-crossTotal 8.307 4 14 2420 10 2 2        tr d tr tryt yttr tr Knn mmsls - A mmAMPaf sn fA K 
  • 16. 15-Mar-13 CE 370: Prof. Abdelhamid Charifi 16 31 resultthechangenotwill,0Taking:Note walltheintom1.5barsExtend 4.142825 5.2 3.10.10.13.1 20 420 10 9 5.25.22.3 25 36.145.66 10 9 '                    tr d b tr b tr b b trc y d K mml d Kc d Kc d d Kcf f l (1)  Solution-1a: General Equation 32 Solution-1b: Simplified Equations (S1b)equationsimplifiedusethuswe ,25withand(2)caseisThis barscover toclear2spacingbarClear 4.40.110 2 253-52.52-400 spacingbarClear mm52.55.2140barsthecover tosideClear        mmd dd dmm b bb b equationgeneralrepect towith veconservatieryequation vSimplified:Note walltheintom2.5barsExtend 7.238025 205 3.10.13.14203 5 3 '                   mmld f f l db c y d (S1b) 
  • 17. 15-Mar-13 CE 370: Prof. Abdelhamid Charifi 17 33 Problem-2: Development of a Bar in a Cantilever Previous example with same data. The beam has closed 10-mm stirrups with 300 MPa yield stress and 180 mm spacing. Check whether there is sufficient distance in the span for the development of the three 25-mm bars. If not what is the maximum bar diameter that can be used ? 34 Solution 2 The maximum yield stress in the bars is at point A (face of the wall). The bars must extend a distance ld into the wall support and a distance ld into the span. The span is 1.5 m long. The development length for 25-mm bars has been determined in example 1. The only difference is in the transverse reinforcement. We use the simplified equations. Clear bar spacing determined in example 1 is 91.5 mm = 3.66 db Stirrup spacing (180 mm) is less than maximum spacing value d/2 = 385/2 = 192.5 mm For 180 mm spacing, the minimum stirrup area is: min, 2 2 2 ' min, 0.157 4 10 2:areastirrupActual 0.80 300 180400 3 1 , 16 20 Max 3 1 , 16 Max vv y wc v AmmA mm f sbf A                      
  • 18. 15-Mar-13 CE 370: Prof. Abdelhamid Charifi 18 35 Solution 2 Since the clear bar spacing is at least equal to db and stirrup area exceeds minimum value, this in fact corresponds to case 1, and 25-mm bars, equation (S1b) is to be used. We find the same solution as in solution 2 of example1: mmld f f l db c y d 7.238025 205 3.10.13.14203 5 3 '                  (S1b)  The maximum distance for bar extension is equal to the span length minus the cover : 1500 – 40 = 1460 mm This distance is insufficient for the straight development length of 2381 mm. Thus 25-mm bars cannot be used. We must use smaller diameter bars. Three 25-mm bars (1472 mm2) can be replaced by six 18-mm bars (1526 mm2). 36 Solution 2 Three 25-mm bars replaced by six 18-mm bars (1526 mm2). (S1a)equationsimplifiedusethuswe )20(,18withand(1)caseisThis value,minimumexceedsareastirrupand,spacingbarClear 16.28.38 5 816-942-400 spacingbarClear mm94940wallin thebarsthecover tosideClear        mmmmd d dmm b b b mml ld f f l d db c y d 1.1371 18 2025 3.10.13.142012 25 12 '                   (S1a)  The available distance (1460 mm) is sufficient for this development length. 18-mm bars can thus be used for this cantilever beam.
  • 19. 15-Mar-13 CE 370: Prof. Abdelhamid Charifi 19 37 Problem-3: Hooked Bar Anchorage into a Column The end of 400 x 600 mm beam frames into a 650 x 650 mm column. The column has four 36-mm bars. The top reinforcement of the beam consists of four 25-mm bars. 20 MPa normal concrete and 420 MPa steel are used. Design the anchorage of the four 25-mm bars. 38 Problem-3: Hooked Bar Anchorage into a Column
  • 20. 15-Mar-13 CE 370: Prof. Abdelhamid Charifi 20 39 Solution 3 As the column reinforcement provides considerable confinement, we will use general equation (1) for a straight development length : mm22ismm)(25diameterbarbecause1.0 usedisconcretenormalbecause1.0 coatedepoxynotarebarsbecause1.0 barstopthebelowcastconcretefreshof mm300thanmorebewilltherebecause3.1 10 9 '                  (1)b b trc y d d d Kcf f l 40 c = Minimum of : (a) Smallest distance measured from concrete surface to center of bar = 125 + 40 + 10 + 25/2 = 187.5 mm (b) One half of center-to-center bar spacing mmc mm 83.45 83.45 3 )5.121040(2400 5.0          6.41 451410 4207.2035 4:anchoredbeingbarsofNumber 514)2/361040(2650:steeletransversofSpacing bars)mm36vertical(twosplitting ofplanecrossingsteeletransversallofareasection-crossTotal 7.2035 4 36 2420 10 2 2        tr tr tryt yttr tr Knn mmss - A mmAMPaf sn fA K  Solution 3
  • 21. 15-Mar-13 CE 370: Prof. Abdelhamid Charifi 21 41 Solution 3 mml d Kc d Kc d d Kcf f l d b tr b tr b b trc y d 8.109825 5.2 0.10.10.13.1 20 420 10 9 5.25.25.3 25 6.4183.45 10 9 '                  (1)  This development length exceeds the column width. It is thus necessary to use hooks to anchor the bars. 42 mm563.5oflengthtdevelopmenhookfor thesufficientisdistanceThis mm60050650coverTail-650hookforavailableDistance 5.563OK 144)8,150(Max5.56325 20 4200.10.124.0 0.1factorcorrectionunitconsiderWe bars)forcoating-epoxynoandconcrete(Normal1.0 .8ormm150thanlessbenotshallequationabovefromobtained 24.0 '         mml mmdmml Factor dl Factord f f l dh bdh bdh b c y dh   (5) Solution 3 The development length for a hook is given by equation (5):
  • 22. 15-Mar-13 CE 370: Prof. Abdelhamid Charifi 22 43 Solution 3 heightmm600joint withcolumn-beamin thefitwilldistanceThis 40016 312 2 12hookofheightVertical 5.563 mmd dddd D d mml b bbbbb dh    Bar Cutoff • RC flexural design is usually performed at the maximum moment point. • At other points, the required reinforcement is smaller and the number of bars may be reduced by stopping some of them (bar cutoff) • A bar can be stopped when it is no longer required. It must however be extended at a sufficient distance. • The bar must be extended by a distance equal to the development length plus an extra distance (due to shear effect) equal to Max(d , 12db) where d is the steel depth and db is the bar diameter 44
  • 23. 15-Mar-13 CE 370: Prof. Abdelhamid Charifi 23 Capacity and demand diagrams (offer > demand) with bar cutoff for simply supported beam– BMD on tension side in RC For real structures, bar cutoff must be performed using the envelope of moment diagram using all load combinations Bar Cutoff 46 Bar Cutoff
  • 24. 15-Mar-13 CE 370: Prof. Abdelhamid Charifi 24 Bar Splices • Reinforcing bars must frequently be spliced because of: – Limited bar lengths available (bar length usually limited to 12 m and exceptionally to 18 m) – Requirement at construction joints – Changes from larger bars to smaller bars • There are three splice types:  Lapped splices  Mechanical splices  Welded splices 47 Lap Splices • Lap splices are achieved by overlapping the bars over a certain length, thereby enabling the transfer of axial force from the terminating bar to the connecting bar through the mechanism of anchorage (development) bond with the surrounding concrete. • Lap splices are usually not permitted for very large diameter bars (Ф > 36 mm), for which welded splices are recommended (except at footing-column joints). 48
  • 25. 15-Mar-13 CE 370: Prof. Abdelhamid Charifi 25 49 Tension Lap Splice Tension Lap Splice • Center-to-center distance between lapped bars not greater than minimum of (one fifth of lap splice , 150 mm) • There are two classes of tension lap splices:  Class A splice : 1.0 ld  Class B splice : 1.3 ld • The required lap class is selected as shown : 50 Amount of steel spliced Stress ratio fs / fy 50 % or less spliced More than 50 % spliced 0.5 or less Class A Class B More than 0.5 Class B Class B
  • 26. 15-Mar-13 CE 370: Prof. Abdelhamid Charifi 26 Welded Splices and Mechanical Connections • Welded splices and mechanical connections are particularly suitable for large diameter bars. • This reduces consumption of reinforcing steel. 51 52 Compression Lap Splice Compression lap splices will be described in the Column Chapter