3. It is one of the main hubs
in the eastern Mediterranean
4. The wharfs’ working platforms suffered severe cracking
and deterioration, requiring maintenance every 6
months.
THE CHALLENGE
5. 100-ton cranes and container loads
caused voids in the structural layers over sand subgrade
cracking in the asphalt surface
6. Conventional Approach :
35 cm thick steel reinforced
concrete – expensive
High-quality aggregates –
high cost
Lengthy construction process –
downtime
7. WHY PRS NEOLOY® GEOCELL?
• High-load bearing capacity
• Use of sea dredged sand for structural infill
• Long-term durability and lifespan
Israel Shipyards need fast, durable and cost-efficient reinforcement
for unstable subgrade