SlideShare a Scribd company logo
1 of 20
CONTRACT AGREEMENT
Click to edit Master subtitle style
CONTRACT AGREEMENT
• GIS (gas-insulated switchgear)
Substation package-SS01 for:
• Extension of 400/220 KV
Baripada Substation (400 KV
with GIS bay & 220 KV with AIS
bay)
• -Extension of 400 KV Maithon
Substation (with 400KV GIS bay)
• -Extension of 220 KV GIS
Substation at Kishanganj
Power Grid
Corporation of India
Ltd
&
M/s. Hyosung
Corporation, Korea
&
M/s. L&T, Chennai
(Associate)
CONTRACT AGREEMENT
• For supply of equipment and
material from outside India and
Training outside India
First contract (Off-
Shore Contract )
• For ex-works supply of
equipment and material from
within India
Second
contract(On-Shore
supply Contract)
• for all services to be performed in India
covering; inter alia handling, port clearance,
inland transportation, insurance, handling,
storage, erection
Third contract(ON-
Shore Services
Contracts)
OFF-SHORE CONTRACT
AGREEMENT
• The scope of the contract
• to engage the contractor for the
CIF supply of all equipment and
materials and Training to be
conducted outside India inter-alia
including Design, engineering,
fabrication, manufacture, testing
at manufacturer’s works,
shipment, marine transportation
M/s. POWERGRID
CORPORATION OF INDIA
&
M/s. HYOSUNG
CORPORATION OF
KOREA
24th day of November
2014
Contract price
US$ 20,315,000
(US Dollars Twenty
Million
Three Hundred
Fifteen Thousand
Only)
the break-up of the contract price is as above
Contract securities
HYOSUNG Corporation, Korea
• shall provide contract performance security for
ten percent (10%) of the value of first contract,
Second contract and third contract
L&T, Chennai (Associate)
• shall provide contract performance security
equivalent to (10%) of the Second contract and
Third Contract for the due performance of the
contract
TERMS AND PROCEDURES
OF PAYMENT
1.TERMS OF PAYMENT
A. Submission within
the 28 days:
1.Performance
securities
2.Detailed PERT
Network/Bar chart and
its approval by
employer
3.Income tax order
B. Fulfilling the
following conditions:
Approval of all designs,
drawings
Approval of quality
plans and sub-vendor
list.
Approval of type test
reports
C. Progressive payment
Seventy percent (70%)
price of the main
equipment/materials shall
be paid progressively
irrevocable letter of credit.
Twenty percent (20%) of
the CIF price of main
equipment/materials shall
be paid on receipt and
storage at site.
supply portion
TERMS AND PROCEDURES
OF PAYMENT
D. Final payment
• Balance 10% of the CIF price component of
equipment shall be paid as per the
following:
• Successful completion of erection, testing
and commissioning of substation.
• Proof of submission of required number of
reproducible, O&M manuals, maintenance
and equipment.
TERMS AND PROCEDURES
OF PAYMENT
Training Charges
• It shall be paid on successful completion of training
and on approval of the same by the employer.
Indian Agent Commission
This payment will be made in equivalent Indian rupees
as follows:
• 85% of Indian Agent’s commission shall be paid within
60 days after the receipt of material and equipment at
destinations.
• Balance 15% shall be paid on issuance of the taking
over certificate.
TERMS AND PROCEDURES
OF PAYMENT
2. PAYMENT PROCEDURES
• The Employer shall make payments
promptly within (30) days of submission
of an invoice/ claim by the contractor.
• All the payment shall be released to the
contractor directly except the payment
due on shipment, which shall be paid
through irrevocable letter of credit.
Methods of payment
TERMS AND PROCEDURES
OF PAYMENT
2. PAYMENT PROCEDURES Cont.
• The contractor may track the status of its
bills using POWERGRID’s ‘online bill
tracking system’, contractor shall register
once online at POWERGRID’s website.
Payment tracking
GUARANTEES, LIQUIDATED DAMAGES FOR
NON-PERFORMANCE
• The equipment offered shall meet the rating
performance requirements stipulated in technical
specification.
• The ratings and performance figures of the bellow
mentioned equipment are guaranteed by
contractor:
GUARANTEES, LIQUIDATED DAMAGES FOR
NON-PERFORMANCE
• If the aforementioned guarantees are not
established at factory tests, then the employer
at his discretion may reject or accept the
equipment after assessing the liquidated
damages as per table above against the
contract and such amounts shall be deducted
from the contract price.
TIME SCHEDULE
• The project completion schedule shall be as follow;
TIME SCHEDULE
• The time of completion of facilities shall be
determined from the date of the notification
of award, from 24.20.2014
• The activities under the contractor’s program
for project completion shall be in the form of a
master network (MNW) and shall identify the
various activities like design, engineering,
supply, installation, factory testing etc.
INTGRITY PACT
Between
POWERGRID
And
HYOSUNG
CORPORATION
• In order to achieve the goals,
POWERGRID and above named
Bidder/Contractor enter into this
agreement called “Integrity pact” which
will form a part the bid.
• Hereinafter referred to as;
• “The Bidder/Contractor preamble”
INTGRITY PACT
Commitments of POWERGRID
• No employee of POWERGRID, personally or
through family members, will in connection
with the tender or the execution of the
contract.
• POWERGRID will, during the tender process
treat all Bidders with equity and provide the
same information.
• Excluding of bids its such employee who has
personal interest in the companies participating
in the Bidding/Tendering process.
INTGRITY PACT
Commitments of the Contractor
A. Commits himself to take
measures necessary to prevent
corruption
B. Not to directly offer promise or
give to POWERGRID
C. will not enter into any illegal
agreement
D. when presenting his bid, disclose
any and all payments he has made
bidder/
contractor
INTGRITY PACT
Disqualification from Tender Process and Exclusion
from Future Contracts
• If the bidder, before contract award, has
committed a serious transgression, such as to
put his reliability or creditability as bidder
into question, POWERGRID may disqualify the
bidder.
• During the restoration of the damage,
POWERGRID may revoke the exclusion
prematurely.
INTGRITY PACT
PACT DURATION
This pact is begins when both parties have
legally signed it. It expires for the contractor
after the closure of the contract and for all
other bidder six months after the contract
has been awarded.

More Related Content

What's hot

Pp2 coursework 2 BRIEF 201708
Pp2 coursework 2  BRIEF  201708Pp2 coursework 2  BRIEF  201708
Pp2 coursework 2 BRIEF 201708Pang Khai Shuen
 
PP2 final report
PP2 final reportPP2 final report
PP2 final reportArissa Loh
 
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Ss 07 training fidic moustafa ismail  2018 _ lec 7_aSs 07 training fidic moustafa ismail  2018 _ lec 7_a
Ss 07 training fidic moustafa ismail 2018 _ lec 7_aMoustafa Ismail Abu Dief
 
WORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-IWORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-IAvinash Kumar Gupta
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808ashleyyeap
 
Strategic Location Analysis for setting up of Manufacturing Facility
Strategic Location Analysis for setting up of Manufacturing FacilityStrategic Location Analysis for setting up of Manufacturing Facility
Strategic Location Analysis for setting up of Manufacturing FacilityDragon Sourcing
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808Arissa Loh
 
ICI Project 2 - Building and process & sample document
ICI Project 2 - Building and process & sample documentICI Project 2 - Building and process & sample document
ICI Project 2 - Building and process & sample documentHaziq1511
 
General conditions of_contract_july_2014_22_07_14
General conditions of_contract_july_2014_22_07_14General conditions of_contract_july_2014_22_07_14
General conditions of_contract_july_2014_22_07_14Suresh Haldipur
 
PP2 - Assignment
PP2 - AssignmentPP2 - Assignment
PP2 - AssignmentQuo Ming
 
Seminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerSeminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerKai Yun Pang
 
Site possession
Site possessionSite possession
Site possessionAmir Ibrahim
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-finalashleyyeap
 
Pp2 assignment
Pp2 assignmentPp2 assignment
Pp2 assignmentfareezsham
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementASHISH KUMAR SINGH
 
Pp2 coursework 2
Pp2 coursework  2Pp2 coursework  2
Pp2 coursework 2tfkc1212
 
Payments provisions in CPWD CONTRACT
Payments provisions in CPWD CONTRACTPayments provisions in CPWD CONTRACT
Payments provisions in CPWD CONTRACTAvinash Kumar Gupta
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignmentlohwenjun
 

What's hot (20)

Pp2 coursework 2 BRIEF 201708
Pp2 coursework 2  BRIEF  201708Pp2 coursework 2  BRIEF  201708
Pp2 coursework 2 BRIEF 201708
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
PP2 final report
PP2 final reportPP2 final report
PP2 final report
 
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
Ss 07 training fidic moustafa ismail  2018 _ lec 7_aSs 07 training fidic moustafa ismail  2018 _ lec 7_a
Ss 07 training fidic moustafa ismail 2018 _ lec 7_a
 
WORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-IWORKS MANAGEMENT IN CPWD PART-I
WORKS MANAGEMENT IN CPWD PART-I
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808
 
GST on works contract
GST on  works contractGST on  works contract
GST on works contract
 
Strategic Location Analysis for setting up of Manufacturing Facility
Strategic Location Analysis for setting up of Manufacturing FacilityStrategic Location Analysis for setting up of Manufacturing Facility
Strategic Location Analysis for setting up of Manufacturing Facility
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808
 
ICI Project 2 - Building and process & sample document
ICI Project 2 - Building and process & sample documentICI Project 2 - Building and process & sample document
ICI Project 2 - Building and process & sample document
 
General conditions of_contract_july_2014_22_07_14
General conditions of_contract_july_2014_22_07_14General conditions of_contract_july_2014_22_07_14
General conditions of_contract_july_2014_22_07_14
 
PP2 - Assignment
PP2 - AssignmentPP2 - Assignment
PP2 - Assignment
 
Seminar - Partial Possession by Employer
Seminar - Partial Possession by EmployerSeminar - Partial Possession by Employer
Seminar - Partial Possession by Employer
 
Site possession
Site possessionSite possession
Site possession
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
 
Pp2 assignment
Pp2 assignmentPp2 assignment
Pp2 assignment
 
FIDIC-Relevant to Time Management
FIDIC-Relevant to Time ManagementFIDIC-Relevant to Time Management
FIDIC-Relevant to Time Management
 
Pp2 coursework 2
Pp2 coursework  2Pp2 coursework  2
Pp2 coursework 2
 
Payments provisions in CPWD CONTRACT
Payments provisions in CPWD CONTRACTPayments provisions in CPWD CONTRACT
Payments provisions in CPWD CONTRACT
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignment
 

Similar to Presentation on contract agreement of gis

Transmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission LinesTransmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission LinesMANTHAN CHAUHAN
 
Types of contracts
Types of contractsTypes of contracts
Types of contractsTulsi Pokhrel
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variationVj NiroSh
 
contract procedure
contract procedurecontract procedure
contract procedurehasyimah ismail
 
Rules for Enlistment of Contractors in CPWD, 2023-1.pptx
Rules for Enlistment of Contractors in CPWD, 2023-1.pptxRules for Enlistment of Contractors in CPWD, 2023-1.pptx
Rules for Enlistment of Contractors in CPWD, 2023-1.pptxTTconstructionspvtlt
 
CV Pholapatra Latest Rev 05
CV Pholapatra Latest Rev 05CV Pholapatra Latest Rev 05
CV Pholapatra Latest Rev 05Paula Intra Lohit
 
1217 loc tenders
1217 loc tenders1217 loc tenders
1217 loc tendersAntonio Bove
 
Mohammad Romzan Ali Updated(Format-2)
Mohammad Romzan Ali Updated(Format-2)Mohammad Romzan Ali Updated(Format-2)
Mohammad Romzan Ali Updated(Format-2)Mohammad Romzan Ali
 
Tanmay presentation
Tanmay presentationTanmay presentation
Tanmay presentationTanmayBhatt22
 
Circuit poc alabama
Circuit poc alabamaCircuit poc alabama
Circuit poc alabamaDarin Walker
 
Pre qualification stages and tender selection
Pre qualification stages and tender selectionPre qualification stages and tender selection
Pre qualification stages and tender selectionanojan kanagarathnam
 
Engr. Abo ElSoud CV-2017
Engr.  Abo ElSoud CV-2017Engr.  Abo ElSoud CV-2017
Engr. Abo ElSoud CV-2017mohamed aboelsoud
 
Episode 28 : Project Management Contract
Episode 28 : Project Management ContractEpisode 28 : Project Management Contract
Episode 28 : Project Management ContractSAJJAD KHUDHUR ABBAS
 
Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Processarpantripathi2
 
Procurement Management
Procurement ManagementProcurement Management
Procurement Managementlearnafren
 
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationHarish Mahavar
 

Similar to Presentation on contract agreement of gis (20)

Contract closing ppt
Contract closing pptContract closing ppt
Contract closing ppt
 
Transmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission LinesTransmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission Lines
 
Types of contracts
Types of contractsTypes of contracts
Types of contracts
 
Contract payment and variation
Contract payment and variationContract payment and variation
Contract payment and variation
 
CV-Sounder
CV-SounderCV-Sounder
CV-Sounder
 
contract procedure
contract procedurecontract procedure
contract procedure
 
sounder
soundersounder
sounder
 
Rules for Enlistment of Contractors in CPWD, 2023-1.pptx
Rules for Enlistment of Contractors in CPWD, 2023-1.pptxRules for Enlistment of Contractors in CPWD, 2023-1.pptx
Rules for Enlistment of Contractors in CPWD, 2023-1.pptx
 
CV Pholapatra Latest Rev 05
CV Pholapatra Latest Rev 05CV Pholapatra Latest Rev 05
CV Pholapatra Latest Rev 05
 
1217 loc tenders
1217 loc tenders1217 loc tenders
1217 loc tenders
 
Mohammad Romzan Ali Updated(Format-2)
Mohammad Romzan Ali Updated(Format-2)Mohammad Romzan Ali Updated(Format-2)
Mohammad Romzan Ali Updated(Format-2)
 
Tanmay presentation
Tanmay presentationTanmay presentation
Tanmay presentation
 
Circuit poc alabama
Circuit poc alabamaCircuit poc alabama
Circuit poc alabama
 
Pre qualification stages and tender selection
Pre qualification stages and tender selectionPre qualification stages and tender selection
Pre qualification stages and tender selection
 
Engr. Abo ElSoud CV-2017
Engr.  Abo ElSoud CV-2017Engr.  Abo ElSoud CV-2017
Engr. Abo ElSoud CV-2017
 
Episode 28 : Project Management Contract
Episode 28 : Project Management ContractEpisode 28 : Project Management Contract
Episode 28 : Project Management Contract
 
Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Process
 
Procurement Management
Procurement ManagementProcurement Management
Procurement Management
 
TURNKEY PROJECT.pptx
TURNKEY PROJECT.pptxTURNKEY PROJECT.pptx
TURNKEY PROJECT.pptx
 
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping station
 

More from Hafizullah Sadat

Concrete mix design by packing density method
Concrete mix design by packing density methodConcrete mix design by packing density method
Concrete mix design by packing density methodHafizullah Sadat
 
Plasticizers (solid content, expose chloride, etc.)
Plasticizers (solid content, expose chloride, etc.) Plasticizers (solid content, expose chloride, etc.)
Plasticizers (solid content, expose chloride, etc.) Hafizullah Sadat
 
Self compacting concrete Mix
Self compacting concrete MixSelf compacting concrete Mix
Self compacting concrete MixHafizullah Sadat
 
Development of Transport Infrastructure in Afghanistan
Development of Transport Infrastructure in AfghanistanDevelopment of Transport Infrastructure in Afghanistan
Development of Transport Infrastructure in AfghanistanHafizullah Sadat
 
Forecasting, Assignment
Forecasting, Assignment Forecasting, Assignment
Forecasting, Assignment Hafizullah Sadat
 
Airport Runway Construction
Airport Runway ConstructionAirport Runway Construction
Airport Runway ConstructionHafizullah Sadat
 
Normal Consistency and Sitting times of cement paste
Normal Consistency and Sitting times of cement pasteNormal Consistency and Sitting times of cement paste
Normal Consistency and Sitting times of cement pasteHafizullah Sadat
 

More from Hafizullah Sadat (8)

Concrete mix design by packing density method
Concrete mix design by packing density methodConcrete mix design by packing density method
Concrete mix design by packing density method
 
Pozzolans
PozzolansPozzolans
Pozzolans
 
Plasticizers (solid content, expose chloride, etc.)
Plasticizers (solid content, expose chloride, etc.) Plasticizers (solid content, expose chloride, etc.)
Plasticizers (solid content, expose chloride, etc.)
 
Self compacting concrete Mix
Self compacting concrete MixSelf compacting concrete Mix
Self compacting concrete Mix
 
Development of Transport Infrastructure in Afghanistan
Development of Transport Infrastructure in AfghanistanDevelopment of Transport Infrastructure in Afghanistan
Development of Transport Infrastructure in Afghanistan
 
Forecasting, Assignment
Forecasting, Assignment Forecasting, Assignment
Forecasting, Assignment
 
Airport Runway Construction
Airport Runway ConstructionAirport Runway Construction
Airport Runway Construction
 
Normal Consistency and Sitting times of cement paste
Normal Consistency and Sitting times of cement pasteNormal Consistency and Sitting times of cement paste
Normal Consistency and Sitting times of cement paste
 

Recently uploaded

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEslot gacor bisa pakai pulsa
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 

Recently uploaded (20)

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 

Presentation on contract agreement of gis

  • 1. CONTRACT AGREEMENT Click to edit Master subtitle style
  • 2. CONTRACT AGREEMENT • GIS (gas-insulated switchgear) Substation package-SS01 for: • Extension of 400/220 KV Baripada Substation (400 KV with GIS bay & 220 KV with AIS bay) • -Extension of 400 KV Maithon Substation (with 400KV GIS bay) • -Extension of 220 KV GIS Substation at Kishanganj Power Grid Corporation of India Ltd & M/s. Hyosung Corporation, Korea & M/s. L&T, Chennai (Associate)
  • 3. CONTRACT AGREEMENT • For supply of equipment and material from outside India and Training outside India First contract (Off- Shore Contract ) • For ex-works supply of equipment and material from within India Second contract(On-Shore supply Contract) • for all services to be performed in India covering; inter alia handling, port clearance, inland transportation, insurance, handling, storage, erection Third contract(ON- Shore Services Contracts)
  • 4. OFF-SHORE CONTRACT AGREEMENT • The scope of the contract • to engage the contractor for the CIF supply of all equipment and materials and Training to be conducted outside India inter-alia including Design, engineering, fabrication, manufacture, testing at manufacturer’s works, shipment, marine transportation M/s. POWERGRID CORPORATION OF INDIA & M/s. HYOSUNG CORPORATION OF KOREA 24th day of November 2014
  • 5. Contract price US$ 20,315,000 (US Dollars Twenty Million Three Hundred Fifteen Thousand Only) the break-up of the contract price is as above
  • 6. Contract securities HYOSUNG Corporation, Korea • shall provide contract performance security for ten percent (10%) of the value of first contract, Second contract and third contract L&T, Chennai (Associate) • shall provide contract performance security equivalent to (10%) of the Second contract and Third Contract for the due performance of the contract
  • 7. TERMS AND PROCEDURES OF PAYMENT 1.TERMS OF PAYMENT A. Submission within the 28 days: 1.Performance securities 2.Detailed PERT Network/Bar chart and its approval by employer 3.Income tax order B. Fulfilling the following conditions: Approval of all designs, drawings Approval of quality plans and sub-vendor list. Approval of type test reports C. Progressive payment Seventy percent (70%) price of the main equipment/materials shall be paid progressively irrevocable letter of credit. Twenty percent (20%) of the CIF price of main equipment/materials shall be paid on receipt and storage at site. supply portion
  • 8. TERMS AND PROCEDURES OF PAYMENT D. Final payment • Balance 10% of the CIF price component of equipment shall be paid as per the following: • Successful completion of erection, testing and commissioning of substation. • Proof of submission of required number of reproducible, O&M manuals, maintenance and equipment.
  • 9. TERMS AND PROCEDURES OF PAYMENT Training Charges • It shall be paid on successful completion of training and on approval of the same by the employer. Indian Agent Commission This payment will be made in equivalent Indian rupees as follows: • 85% of Indian Agent’s commission shall be paid within 60 days after the receipt of material and equipment at destinations. • Balance 15% shall be paid on issuance of the taking over certificate.
  • 10. TERMS AND PROCEDURES OF PAYMENT 2. PAYMENT PROCEDURES • The Employer shall make payments promptly within (30) days of submission of an invoice/ claim by the contractor. • All the payment shall be released to the contractor directly except the payment due on shipment, which shall be paid through irrevocable letter of credit. Methods of payment
  • 11. TERMS AND PROCEDURES OF PAYMENT 2. PAYMENT PROCEDURES Cont. • The contractor may track the status of its bills using POWERGRID’s ‘online bill tracking system’, contractor shall register once online at POWERGRID’s website. Payment tracking
  • 12. GUARANTEES, LIQUIDATED DAMAGES FOR NON-PERFORMANCE • The equipment offered shall meet the rating performance requirements stipulated in technical specification. • The ratings and performance figures of the bellow mentioned equipment are guaranteed by contractor:
  • 13. GUARANTEES, LIQUIDATED DAMAGES FOR NON-PERFORMANCE • If the aforementioned guarantees are not established at factory tests, then the employer at his discretion may reject or accept the equipment after assessing the liquidated damages as per table above against the contract and such amounts shall be deducted from the contract price.
  • 14. TIME SCHEDULE • The project completion schedule shall be as follow;
  • 15. TIME SCHEDULE • The time of completion of facilities shall be determined from the date of the notification of award, from 24.20.2014 • The activities under the contractor’s program for project completion shall be in the form of a master network (MNW) and shall identify the various activities like design, engineering, supply, installation, factory testing etc.
  • 16. INTGRITY PACT Between POWERGRID And HYOSUNG CORPORATION • In order to achieve the goals, POWERGRID and above named Bidder/Contractor enter into this agreement called “Integrity pact” which will form a part the bid. • Hereinafter referred to as; • “The Bidder/Contractor preamble”
  • 17. INTGRITY PACT Commitments of POWERGRID • No employee of POWERGRID, personally or through family members, will in connection with the tender or the execution of the contract. • POWERGRID will, during the tender process treat all Bidders with equity and provide the same information. • Excluding of bids its such employee who has personal interest in the companies participating in the Bidding/Tendering process.
  • 18. INTGRITY PACT Commitments of the Contractor A. Commits himself to take measures necessary to prevent corruption B. Not to directly offer promise or give to POWERGRID C. will not enter into any illegal agreement D. when presenting his bid, disclose any and all payments he has made bidder/ contractor
  • 19. INTGRITY PACT Disqualification from Tender Process and Exclusion from Future Contracts • If the bidder, before contract award, has committed a serious transgression, such as to put his reliability or creditability as bidder into question, POWERGRID may disqualify the bidder. • During the restoration of the damage, POWERGRID may revoke the exclusion prematurely.
  • 20. INTGRITY PACT PACT DURATION This pact is begins when both parties have legally signed it. It expires for the contractor after the closure of the contract and for all other bidder six months after the contract has been awarded.