SlideShare a Scribd company logo
1 of 11
Work Contract
Estimate
1.DSR is inclusive of octroi, royalty, excise duty, Sales Tax
(VAT)
2.DSR is not inclusive of Service Tax, as such contractor
was required to pay service tax directly to tax authorities &
department used to reimburse it.
3.Total taxes on works in Pre GST era was to the tune of 24-
28%.
4.In GST era the GST on works contract is 18% for PB.
Prasar Bharti is taxable business entity.
Work Contract
Estimated Tax in Pre GST Era on Building Work
1.
2.Excluding Electrical items the tax can be
assumed as 24% in Building work
3.The taxes in Building work excluding services
can be assumed to be = 18%
Excise (on cement, steel & other items) - 12.5%
VAT - 7.5%
CST - 1%
Service Tax - 6%
Total - 27%
Works Contract
Estimate in GST - Era
1.The taxes in DSR may be assumed to be 18%
2.Present GST on Building work in PB is 18%.
3.Therefore any estimate based on DSR in GST era can be
presumed to be inclusive of GST @ 18% (inclusive of all taxes).
4.The estimate in the end will show taxes separately.
5.Say Estimated cost = 100 based on DSR
6.Taxes are as per rule 35 of CGST rules.
1. Cost excluding taxes =
100
= 84.8
118
2. CGST = 7.6
3. SGST = 7.6
Total = 100.00
Work Contract
Justification in the GST Era
1.The contractor uses material & labour as input and he is charged
taxes on input tby supplier of materials/ labour. He will get ITC on
taxes paid to suppliers.
2.The contractor supplies works contract service, which is out put
supply of contractor. He is liable to pay tax to government on out
put of works contract.
3.Net tax liability of contract = (out put tax liability on value of
works contract– ITC on materials & services.)
4.Prepare the justification on MR.
5.Add Justified Amount on MR and Net tax liability of contractor.
6.Justification is (Justified Amount on MR + out put tax on justified
amount – ITC on materials & services.)
Work Contract
NIT Conditions
1.The GST has been implemented by the Government of India
with effect from 1st
July 2017. The rates quoted by the tenders,
shall be firm and inclusive of all taxes including GST.
2.Tenderer shall examine the various provisions of CGST Act,
2017 IGST Act, 2017/ UGST Act – 2017/ SGST Act 2017 of the
respective state and up to date amendments issued from time to
time and other applicable taxes before bidding/ tendering. The
tenderer shall also confirm to the rules made under these Acts.
3.The tenderer shall ensure that benefit of Input tax credit (ITC)
likely to be availed by them is duly considered by them while
quoting rates.
Work Contract, NIT
4. The contractor shall submit the invoice of the work
executed as per rule 46 of the CGST rules. The taxes will
be calculated as per rule 35 of CGST Rules 2017.
5. As contractor’s rates are inclusive of all taxes, no
reimbursement of any tax shall be made to the contractor.
The clause 37 of GCC of NIT/contract stands modified
accordingly.
6. TDS on income tax, labour cess and other statutory
deductions shall be made at source as per prevalent
laws. TDS on GST as & when becomes applicable will
also be deducted as per relevant GST Act/ rules/
notification.
Work Contract
INVOICE
1.The contractor shall submit the invoice of the work done as per rule 46 of
the CGST rules.
2.The contractor shall mention his invoice number, GSTIN number and also
the GSTIN number of the department.
3.The invoice shall indicate CGST, SGST/ UTGST or IGST as per rules.
The taxes will be calculated as per rule 35 of CGST rules 2017.
4.Say Gross Amount of work done as per contract rates = Rs. 100
5.Amount excluding taxes =
6.GGST = x9
7.CGST = x9
8.Payable amount including GST And Taxes= 100. Further deductions shall
be made as per statutory provisions/contract.
100
118
100
118
100
118
Work Contract
1. The contractor shall file the invoice details in GSTR-1 on
GSTN portal and shall pay the GST to the Government at
the time of filling the monthly return.
2. DDO will indicate the invoice details of the contractor in
GSTR-2 of the PB. The GSTR-2 will be sent to SNO of
AIR/ DD within the stipulated date as circulated by PB.
Work Contract
Deposit Work
1. The CCW will submit estimate to client department inclusive
of departmental charges & GST & other taxes.
2. The GST will however be worked out & indicated in the
estimate.
3. GST will be applicable on full amount ie [Estimated cost
without GST + Departmental charges].
4. The CCW will make payment to contractor as per the
invoice of contractor.
5. CCW will submit invoice to client department adding
departmental charges and indicating the GST.
6. The CCW will mention AIR GSTIN and GSTIN of the client
organization (if registered)
Work Contract
Deposit Work
7. The input and output invoice details shall be sent to SNO
of AIR in GSTR-2/GSTR-1 timely so that PB /client
department may get benefit of ITC wherever permissible.
8. The GST on output supply charged from client department
will be paid to the Government by PB after availing ITC.
The PB will get ITC only when contractor files his invoice
details on GSTN portal.
THE END
THANKS

More Related Content

What's hot

Income Tax Assessment Procedures - Section 143, 144 and more
Income Tax Assessment Procedures - Section 143, 144 and moreIncome Tax Assessment Procedures - Section 143, 144 and more
Income Tax Assessment Procedures - Section 143, 144 and moreSahil Goel
 
Land Acquisition Flow Chart
Land Acquisition Flow ChartLand Acquisition Flow Chart
Land Acquisition Flow ChartAvijeet Lala
 
Marketing consultant experience letter
Marketing consultant experience letterMarketing consultant experience letter
Marketing consultant experience letterkevinjones3184
 
Gst section 16 - Input Tax Credit – Eligibility and Conditions
Gst section 16 - Input Tax Credit – Eligibility and ConditionsGst section 16 - Input Tax Credit – Eligibility and Conditions
Gst section 16 - Input Tax Credit – Eligibility and ConditionsCMA Md Rehan
 
Rera finance module - sandeep jhunjhunwala fca llb
Rera   finance module -  sandeep jhunjhunwala fca llbRera   finance module -  sandeep jhunjhunwala fca llb
Rera finance module - sandeep jhunjhunwala fca llbSandeep Jhunjhunwala
 
Real Estate Regulation Act, India (RERA)
Real Estate Regulation Act, India (RERA)Real Estate Regulation Act, India (RERA)
Real Estate Regulation Act, India (RERA)Piyali Parashari
 
Goods and Service Tax (GST)
Goods and Service Tax (GST)Goods and Service Tax (GST)
Goods and Service Tax (GST)Akash Saha
 
Mahtab khan civil foreman
Mahtab khan civil foremanMahtab khan civil foreman
Mahtab khan civil foremanMahtab khan
 
Pleadind and written statement MCQ
Pleadind and written statement MCQPleadind and written statement MCQ
Pleadind and written statement MCQRamanand Karwa
 
Board resolution (tender)
Board resolution (tender)Board resolution (tender)
Board resolution (tender)Sachin Dhamija
 
Charitable trust ppt
Charitable trust pptCharitable trust ppt
Charitable trust pptSweety Sharma
 

What's hot (20)

Income Tax Assessment Procedures - Section 143, 144 and more
Income Tax Assessment Procedures - Section 143, 144 and moreIncome Tax Assessment Procedures - Section 143, 144 and more
Income Tax Assessment Procedures - Section 143, 144 and more
 
Land Acquisition Flow Chart
Land Acquisition Flow ChartLand Acquisition Flow Chart
Land Acquisition Flow Chart
 
Marketing consultant experience letter
Marketing consultant experience letterMarketing consultant experience letter
Marketing consultant experience letter
 
Gst section 16 - Input Tax Credit – Eligibility and Conditions
Gst section 16 - Input Tax Credit – Eligibility and ConditionsGst section 16 - Input Tax Credit – Eligibility and Conditions
Gst section 16 - Input Tax Credit – Eligibility and Conditions
 
Rera finance module - sandeep jhunjhunwala fca llb
Rera   finance module -  sandeep jhunjhunwala fca llbRera   finance module -  sandeep jhunjhunwala fca llb
Rera finance module - sandeep jhunjhunwala fca llb
 
Real Estate Regulation Act, India (RERA)
Real Estate Regulation Act, India (RERA)Real Estate Regulation Act, India (RERA)
Real Estate Regulation Act, India (RERA)
 
Goods and Service Tax (GST)
Goods and Service Tax (GST)Goods and Service Tax (GST)
Goods and Service Tax (GST)
 
Mahtab khan civil foreman
Mahtab khan civil foremanMahtab khan civil foreman
Mahtab khan civil foreman
 
Cover letter
Cover letterCover letter
Cover letter
 
JINTOMON WELDER .C.V.
JINTOMON WELDER .C.V.JINTOMON WELDER .C.V.
JINTOMON WELDER .C.V.
 
HVAC Engineer Resume
HVAC Engineer ResumeHVAC Engineer Resume
HVAC Engineer Resume
 
Pleadind and written statement MCQ
Pleadind and written statement MCQPleadind and written statement MCQ
Pleadind and written statement MCQ
 
Internship certificate - Shahrukh
Internship certificate - ShahrukhInternship certificate - Shahrukh
Internship certificate - Shahrukh
 
Types of returns under gst
Types of returns under gstTypes of returns under gst
Types of returns under gst
 
Board resolution (tender)
Board resolution (tender)Board resolution (tender)
Board resolution (tender)
 
Kerala Land Conservancy Act Solve your land problems in Kerala - bhoomi thram...
Kerala Land Conservancy Act Solve your land problems in Kerala - bhoomi thram...Kerala Land Conservancy Act Solve your land problems in Kerala - bhoomi thram...
Kerala Land Conservancy Act Solve your land problems in Kerala - bhoomi thram...
 
Trade License: Registration, Process & Renewal
Trade License: Registration, Process & RenewalTrade License: Registration, Process & Renewal
Trade License: Registration, Process & Renewal
 
Charitable trust ppt
Charitable trust pptCharitable trust ppt
Charitable trust ppt
 
Land Assignment Act.
Land Assignment Act.Land Assignment Act.
Land Assignment Act.
 
Gst concept, impact analysis
Gst concept, impact analysisGst concept, impact analysis
Gst concept, impact analysis
 

Viewers also liked (13)

Fiber reinforce concrete and polymer concrete
Fiber reinforce concrete and polymer concreteFiber reinforce concrete and polymer concrete
Fiber reinforce concrete and polymer concrete
 
Illustrations. repairing of structures
Illustrations. repairing of structuresIllustrations. repairing of structures
Illustrations. repairing of structures
 
Application and advances of polymers
Application and advances of polymersApplication and advances of polymers
Application and advances of polymers
 
Advanced Polymer Nanocomposites for 3D printing in Space
Advanced Polymer Nanocomposites for 3D printing in SpaceAdvanced Polymer Nanocomposites for 3D printing in Space
Advanced Polymer Nanocomposites for 3D printing in Space
 
Polymer concrete
Polymer concretePolymer concrete
Polymer concrete
 
Communication process and levels of communication
Communication process and levels of communicationCommunication process and levels of communication
Communication process and levels of communication
 
Polymer industries
Polymer industriesPolymer industries
Polymer industries
 
Cracks in Buildings
Cracks in BuildingsCracks in Buildings
Cracks in Buildings
 
Polymer concrete
Polymer concretePolymer concrete
Polymer concrete
 
Polymer concrete
Polymer concretePolymer concrete
Polymer concrete
 
Polymer concrete and fiber reinforced polymer concrete
Polymer concrete and fiber reinforced polymer concretePolymer concrete and fiber reinforced polymer concrete
Polymer concrete and fiber reinforced polymer concrete
 
Polymer concrete
Polymer concretePolymer concrete
Polymer concrete
 
Cracks in Buildings
Cracks in BuildingsCracks in Buildings
Cracks in Buildings
 

Similar to GST on works contract

Appliacbility Issues & Solutions under GST by CA. VInay Bhushan
Appliacbility Issues & Solutions under GST by CA. VInay BhushanAppliacbility Issues & Solutions under GST by CA. VInay Bhushan
Appliacbility Issues & Solutions under GST by CA. VInay BhushanTAXPERT PROFESSIONALS
 
Wct a detailed guide
Wct a detailed guideWct a detailed guide
Wct a detailed guideParag Jain
 
Job Work under Central Goods and Services Act
Job Work under Central Goods and Services ActJob Work under Central Goods and Services Act
Job Work under Central Goods and Services Actssuser7cf02c
 
Input tax-credit-mechanism-onlineversion-07june2017
Input tax-credit-mechanism-onlineversion-07june2017Input tax-credit-mechanism-onlineversion-07june2017
Input tax-credit-mechanism-onlineversion-07june2017KIRANKUMARPASALA1
 
Presentation on Industry 2020: Emerging GST Issues due to COVID-19
Presentation on Industry 2020: Emerging GST Issues due to COVID-19Presentation on Industry 2020: Emerging GST Issues due to COVID-19
Presentation on Industry 2020: Emerging GST Issues due to COVID-19Taxmann
 
4. Indian Taxation. Service Tax
4. Indian Taxation. Service Tax4. Indian Taxation. Service Tax
4. Indian Taxation. Service TaxDivyanshu Dayal
 
Gst input tax credit ppt
Gst input tax credit pptGst input tax credit ppt
Gst input tax credit pptJibin Varghese
 
Guide for job work under gst
Guide for job work under gst Guide for job work under gst
Guide for job work under gst Natajkumar
 
Treatment of Input Tax Credit on Works Contract Under GST by Aakash Tiwari
Treatment of Input Tax Credit on Works Contract Under GST by Aakash TiwariTreatment of Input Tax Credit on Works Contract Under GST by Aakash Tiwari
Treatment of Input Tax Credit on Works Contract Under GST by Aakash TiwariAAKASH TIWARI
 
Impact of gst on real estate sector satara 21042017 print out ca umesh sharma
Impact of gst on real estate sector satara 21042017 print out ca umesh sharmaImpact of gst on real estate sector satara 21042017 print out ca umesh sharma
Impact of gst on real estate sector satara 21042017 print out ca umesh sharmaakshay khatri
 
Input Credit Under GST & GST Presentation
Input Credit Under GST & GST PresentationInput Credit Under GST & GST Presentation
Input Credit Under GST & GST PresentationCA-Amit
 
GST in 14 Days - Day 8
GST in 14 Days  - Day 8GST in 14 Days  - Day 8
GST in 14 Days - Day 8Chinmay Panda
 

Similar to GST on works contract (20)

Appliacbility Issues & Solutions under GST by CA. VInay Bhushan
Appliacbility Issues & Solutions under GST by CA. VInay BhushanAppliacbility Issues & Solutions under GST by CA. VInay Bhushan
Appliacbility Issues & Solutions under GST by CA. VInay Bhushan
 
Job Work under GST
Job Work under GSTJob Work under GST
Job Work under GST
 
Wct
WctWct
Wct
 
Wct a detailed guide
Wct a detailed guideWct a detailed guide
Wct a detailed guide
 
Job Work under Central Goods and Services Act
Job Work under Central Goods and Services ActJob Work under Central Goods and Services Act
Job Work under Central Goods and Services Act
 
Input tax-credit-mechanism-onlineversion-07june2017
Input tax-credit-mechanism-onlineversion-07june2017Input tax-credit-mechanism-onlineversion-07june2017
Input tax-credit-mechanism-onlineversion-07june2017
 
Presentation on Industry 2020: Emerging GST Issues due to COVID-19
Presentation on Industry 2020: Emerging GST Issues due to COVID-19Presentation on Industry 2020: Emerging GST Issues due to COVID-19
Presentation on Industry 2020: Emerging GST Issues due to COVID-19
 
4. Indian Taxation. Service Tax
4. Indian Taxation. Service Tax4. Indian Taxation. Service Tax
4. Indian Taxation. Service Tax
 
Gst - A Door Step Away
Gst - A Door Step AwayGst - A Door Step Away
Gst - A Door Step Away
 
GST -PPT
GST -PPTGST -PPT
GST -PPT
 
Gst input tax credit ppt
Gst input tax credit pptGst input tax credit ppt
Gst input tax credit ppt
 
Goods and services tax
Goods and services taxGoods and services tax
Goods and services tax
 
Goods and services Tax
Goods and services TaxGoods and services Tax
Goods and services Tax
 
WORK CONTRACT
WORK CONTRACTWORK CONTRACT
WORK CONTRACT
 
Guide for job work under gst
Guide for job work under gst Guide for job work under gst
Guide for job work under gst
 
Works contract under GST
Works contract under GSTWorks contract under GST
Works contract under GST
 
Treatment of Input Tax Credit on Works Contract Under GST by Aakash Tiwari
Treatment of Input Tax Credit on Works Contract Under GST by Aakash TiwariTreatment of Input Tax Credit on Works Contract Under GST by Aakash Tiwari
Treatment of Input Tax Credit on Works Contract Under GST by Aakash Tiwari
 
Impact of gst on real estate sector satara 21042017 print out ca umesh sharma
Impact of gst on real estate sector satara 21042017 print out ca umesh sharmaImpact of gst on real estate sector satara 21042017 print out ca umesh sharma
Impact of gst on real estate sector satara 21042017 print out ca umesh sharma
 
Input Credit Under GST & GST Presentation
Input Credit Under GST & GST PresentationInput Credit Under GST & GST Presentation
Input Credit Under GST & GST Presentation
 
GST in 14 Days - Day 8
GST in 14 Days  - Day 8GST in 14 Days  - Day 8
GST in 14 Days - Day 8
 

More from Avinash Kumar Gupta

Time schedule for preparation &and completion of APAR
Time schedule for preparation &and completion of APARTime schedule for preparation &and completion of APAR
Time schedule for preparation &and completion of APARAvinash Kumar Gupta
 
Engaging consultants, service providers in govrnment part i
Engaging consultants, service providers in govrnment part iEngaging consultants, service providers in govrnment part i
Engaging consultants, service providers in govrnment part iAvinash Kumar Gupta
 
Procurement of goods , GFR provisions
Procurement of goods , GFR provisionsProcurement of goods , GFR provisions
Procurement of goods , GFR provisionsAvinash Kumar Gupta
 
Construction and repair chemicals
Construction and repair  chemicalsConstruction and repair  chemicals
Construction and repair chemicalsAvinash Kumar Gupta
 
Condition survey and non destructive evalution of concrete
Condition survey and non destructive evalution of concreteCondition survey and non destructive evalution of concrete
Condition survey and non destructive evalution of concreteAvinash Kumar Gupta
 
Materials for rcc repairs and rehabilitation
Materials for rcc repairs and rehabilitationMaterials for rcc repairs and rehabilitation
Materials for rcc repairs and rehabilitationAvinash Kumar Gupta
 
Payments provisions in CPWD CONTRACT
Payments provisions in CPWD CONTRACTPayments provisions in CPWD CONTRACT
Payments provisions in CPWD CONTRACTAvinash Kumar Gupta
 
Suspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractSuspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractAvinash Kumar Gupta
 
AMENDMENT IN ARBITRATION LAW IN INDIA 2016
AMENDMENT IN ARBITRATION LAW IN INDIA 2016AMENDMENT IN ARBITRATION LAW IN INDIA 2016
AMENDMENT IN ARBITRATION LAW IN INDIA 2016Avinash Kumar Gupta
 

More from Avinash Kumar Gupta (20)

Principles of natural justice
Principles of natural justicePrinciples of natural justice
Principles of natural justice
 
Time schedule for preparation &and completion of APAR
Time schedule for preparation &and completion of APARTime schedule for preparation &and completion of APAR
Time schedule for preparation &and completion of APAR
 
Orders regarding apar
Orders regarding apar Orders regarding apar
Orders regarding apar
 
APAR guidelines
APAR  guidelinesAPAR  guidelines
APAR guidelines
 
Total station
Total stationTotal station
Total station
 
GPS surveying/DIGITAL SURVEYING
GPS  surveying/DIGITAL SURVEYINGGPS  surveying/DIGITAL SURVEYING
GPS surveying/DIGITAL SURVEYING
 
Service contracts ii
Service contracts iiService contracts ii
Service contracts ii
 
Engaging consultants, service providers in govrnment part i
Engaging consultants, service providers in govrnment part iEngaging consultants, service providers in govrnment part i
Engaging consultants, service providers in govrnment part i
 
Procurement of goods , GFR provisions
Procurement of goods , GFR provisionsProcurement of goods , GFR provisions
Procurement of goods , GFR provisions
 
Procurement of services
Procurement of  servicesProcurement of  services
Procurement of services
 
Soil penetration tests
Soil penetration testsSoil penetration tests
Soil penetration tests
 
Soil exploration part i
Soil exploration part  iSoil exploration part  i
Soil exploration part i
 
Construction and repair chemicals
Construction and repair  chemicalsConstruction and repair  chemicals
Construction and repair chemicals
 
Condition survey and non destructive evalution of concrete
Condition survey and non destructive evalution of concreteCondition survey and non destructive evalution of concrete
Condition survey and non destructive evalution of concrete
 
Materials for rcc repairs and rehabilitation
Materials for rcc repairs and rehabilitationMaterials for rcc repairs and rehabilitation
Materials for rcc repairs and rehabilitation
 
Rehabilitation methods
Rehabilitation methodsRehabilitation methods
Rehabilitation methods
 
Payments provisions in CPWD CONTRACT
Payments provisions in CPWD CONTRACTPayments provisions in CPWD CONTRACT
Payments provisions in CPWD CONTRACT
 
Suspensions and Delays in Construction Contract
Suspensions and Delays in Construction ContractSuspensions and Delays in Construction Contract
Suspensions and Delays in Construction Contract
 
AMENDMENT IN ARBITRATION LAW IN INDIA 2016
AMENDMENT IN ARBITRATION LAW IN INDIA 2016AMENDMENT IN ARBITRATION LAW IN INDIA 2016
AMENDMENT IN ARBITRATION LAW IN INDIA 2016
 
Ready mix concrete
Ready mix concreteReady mix concrete
Ready mix concrete
 

Recently uploaded

Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 

Recently uploaded (20)

Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 

GST on works contract

  • 1. Work Contract Estimate 1.DSR is inclusive of octroi, royalty, excise duty, Sales Tax (VAT) 2.DSR is not inclusive of Service Tax, as such contractor was required to pay service tax directly to tax authorities & department used to reimburse it. 3.Total taxes on works in Pre GST era was to the tune of 24- 28%. 4.In GST era the GST on works contract is 18% for PB. Prasar Bharti is taxable business entity.
  • 2. Work Contract Estimated Tax in Pre GST Era on Building Work 1. 2.Excluding Electrical items the tax can be assumed as 24% in Building work 3.The taxes in Building work excluding services can be assumed to be = 18% Excise (on cement, steel & other items) - 12.5% VAT - 7.5% CST - 1% Service Tax - 6% Total - 27%
  • 3. Works Contract Estimate in GST - Era 1.The taxes in DSR may be assumed to be 18% 2.Present GST on Building work in PB is 18%. 3.Therefore any estimate based on DSR in GST era can be presumed to be inclusive of GST @ 18% (inclusive of all taxes). 4.The estimate in the end will show taxes separately. 5.Say Estimated cost = 100 based on DSR 6.Taxes are as per rule 35 of CGST rules. 1. Cost excluding taxes = 100 = 84.8 118 2. CGST = 7.6 3. SGST = 7.6 Total = 100.00
  • 4. Work Contract Justification in the GST Era 1.The contractor uses material & labour as input and he is charged taxes on input tby supplier of materials/ labour. He will get ITC on taxes paid to suppliers. 2.The contractor supplies works contract service, which is out put supply of contractor. He is liable to pay tax to government on out put of works contract. 3.Net tax liability of contract = (out put tax liability on value of works contract– ITC on materials & services.) 4.Prepare the justification on MR. 5.Add Justified Amount on MR and Net tax liability of contractor. 6.Justification is (Justified Amount on MR + out put tax on justified amount – ITC on materials & services.)
  • 5. Work Contract NIT Conditions 1.The GST has been implemented by the Government of India with effect from 1st July 2017. The rates quoted by the tenders, shall be firm and inclusive of all taxes including GST. 2.Tenderer shall examine the various provisions of CGST Act, 2017 IGST Act, 2017/ UGST Act – 2017/ SGST Act 2017 of the respective state and up to date amendments issued from time to time and other applicable taxes before bidding/ tendering. The tenderer shall also confirm to the rules made under these Acts. 3.The tenderer shall ensure that benefit of Input tax credit (ITC) likely to be availed by them is duly considered by them while quoting rates.
  • 6. Work Contract, NIT 4. The contractor shall submit the invoice of the work executed as per rule 46 of the CGST rules. The taxes will be calculated as per rule 35 of CGST Rules 2017. 5. As contractor’s rates are inclusive of all taxes, no reimbursement of any tax shall be made to the contractor. The clause 37 of GCC of NIT/contract stands modified accordingly. 6. TDS on income tax, labour cess and other statutory deductions shall be made at source as per prevalent laws. TDS on GST as & when becomes applicable will also be deducted as per relevant GST Act/ rules/ notification.
  • 7. Work Contract INVOICE 1.The contractor shall submit the invoice of the work done as per rule 46 of the CGST rules. 2.The contractor shall mention his invoice number, GSTIN number and also the GSTIN number of the department. 3.The invoice shall indicate CGST, SGST/ UTGST or IGST as per rules. The taxes will be calculated as per rule 35 of CGST rules 2017. 4.Say Gross Amount of work done as per contract rates = Rs. 100 5.Amount excluding taxes = 6.GGST = x9 7.CGST = x9 8.Payable amount including GST And Taxes= 100. Further deductions shall be made as per statutory provisions/contract. 100 118 100 118 100 118
  • 8. Work Contract 1. The contractor shall file the invoice details in GSTR-1 on GSTN portal and shall pay the GST to the Government at the time of filling the monthly return. 2. DDO will indicate the invoice details of the contractor in GSTR-2 of the PB. The GSTR-2 will be sent to SNO of AIR/ DD within the stipulated date as circulated by PB.
  • 9. Work Contract Deposit Work 1. The CCW will submit estimate to client department inclusive of departmental charges & GST & other taxes. 2. The GST will however be worked out & indicated in the estimate. 3. GST will be applicable on full amount ie [Estimated cost without GST + Departmental charges]. 4. The CCW will make payment to contractor as per the invoice of contractor. 5. CCW will submit invoice to client department adding departmental charges and indicating the GST. 6. The CCW will mention AIR GSTIN and GSTIN of the client organization (if registered)
  • 10. Work Contract Deposit Work 7. The input and output invoice details shall be sent to SNO of AIR in GSTR-2/GSTR-1 timely so that PB /client department may get benefit of ITC wherever permissible. 8. The GST on output supply charged from client department will be paid to the Government by PB after availing ITC. The PB will get ITC only when contractor files his invoice details on GSTN portal.