SlideShare a Scribd company logo
1 of 9
Download to read offline
Reinforced concrete double walls
Build faster, pay less.
Strength in building technology Uses
Kerkstoel double walls have special advantages
for different applications. Because each ele-
ment is manufactured individually according
to requirements, Kerkstoel double walls are
The Kerkstoel reinforced double walls consist of
two slabs of reinforced concrete joined to each
other by lattice girders.
The wall elements are installed on the site ac-
cording to the plan and then filled with concrete.
DIMENSIONS	 length: up to 8.30 m
	 height: up to 2.80 m, possibly up to 3.50 m on request
	 thickness (outside/inside): 19-34 cm (on request 40 to 70 cm)
	 thickness of the slabs at least 5 cm each
	 other dimensions on request
WEIGHT	 approx. 250 kg per m2 with 2 x 5 cm slab thickness
CONCRETE QUALITY	 at least C25-30
SURFACE	 suitable for spray plaster or ready to wallpaper on request
the ideal construction method for just about all
building work.
Below you can find some examples of the many
applications.
The result is a solid construction and a strong
base that is virtually a monolithic concrete wall.
Kerkstoel double walls are manufactured in ac-
cordance with the strict standards of the Belgian
conformity certificate and of ISO 9001.
Private homes
Inside and outside walls, the replacement
of brickwork, an alternative for concrete
poured on-site
Large construction projects
Industrial construction, silo walls, tunnels,
underground car parks, supporting walls
Tall walls
Tall walls with a height above 8 m,
can be produced for various uses.
Storey Floors
Façade walls, dividing walls in homes, outside
walls, lifts and stairwells, partition walls
Walls as waterproof constructions
Including basements, water treatment plants,
retaining walls and swimming pools
Prefab-elements
Suitable for spray plaster or ready
to wallpaper as required
Floor slabs
Concrete poured on site
Wall open web beam
Wall reinforcement
Kerkstoel thinks of all details Kerkstoel offers technical support
We offer just-in-time logistical and qualified
assembly assistance for the smooth completion
of construction plans.
We draw up a detailed assembly schedule on
the basis of the design of the architect (plan
and cross-section), the stability calculations,
formwork and installation plans.
We develop the production plans and provide
them with all the necessary details, so that
everything goes smoothly and according to
schedule on the site.
CEILING JOINTS BASE PLATE JOINTS FOR VERTICAL JOINTS
for corners
FOR WALL JOINTS
(not reinforced)
(not reinforced)
(not reinforced)(not reinforced)
lattice glider
(not reinforced)
solid wall
(reinforced)
(reinforced)
(reinforced)(reinforced) (reinforced)
double wall
(reinforced)
double wall
open web beam
casing
What else does Kerkstoel have to offer? Built-in parts
Because each design has its own specific
properties, Kerkstoel double walls are uniquely
produced according to requirements. Not only
does each wall have its own dimensions and
openings for doors and windows, the built-in
parts for the finishing can also be immediately
provided.
The use of the latest CAD and robot techniques
allows Kerkstoel to produce double walls of
even the most individual design and all this at a
very reasonable cost.
2
6
3
5
1
4
1	 Electrical fittings
2	 Openings, passageways
3	 Pipes for the vertical powering of electrical
installations.
4	 Door frames, wooden formwork
5	 Windows or wooden formwork
6	 Reinforcement for joints with concrete
poured on-site
Kerkstoel offers technical support
1	 Provisions for electricity, distribution and
telephone.
2	 Openings for: incl. sewers, air-conditioning,
ventilation, etc.
3	 Conduit for the ease of electrical
	 installation
4	 Doorway with formwork.
All sizes are possible.
5	 Window opening with formwork.
1
3
5
2
4
Completely watertight, also at the joints Building in groundwater
The bed plate is utilising a water-resistant concrete.
The outside walls can be of a maximum thickness
and filled with water-resistant concrete.
Kerkstoel’s high quality double wall elements and
the concrete guarantee the complete watertight-
ness of the wall.
The joints are either sealed on the outside or
given a sealing layer.
Kerkstoel double walls are manufactured in
optimal and precision-controlled conditions at
the factory.
Production faults are practically excluded by
using an integrated quality management
system.
The double walls resist any water load, water
pressure and any other form of moisture to
which a building is exposed.
Kerkstoel stands for reliability, and the certainty
that all physical construction properties will be
taken into account.
VERTICAL JOINTS
HORIZONTAL JOINTS
Inner sealing for example
joint with sealing section
open web
beam
bottom foundations
bottom foundations
bottom foundations
bottom foundations
bottom foundations
bottom foundations
Roughen the area of contact
Water retaining plate
Inll concrete (water/cement <0.5)
Swell strip
joint of 3 cm
Roofing
Roughen the area of contact.
This limits the creeping of the con-
crete in relation to the foundations
Always use suitable cement.
The water/cement factor must always
be less than 0.5
The wall must be placed ±3 cm
above the foundations. This means
one can increase the contact area.
Exterior sealing
for example thick coating
Resources for water sealing
Method for good water sealing
Transport Preparation of the floor slab
Make sure that the joining reinforcement is
placed correctly with the concreting of the slab,
ensuring that there is sufficient inside space.
Do not use mesh reinforcement as starter bars.
Trace the place where the walls must be
erected with the numbers of the walls on the
ground. The information can be found on the
assembly plan.
Use base plates to accommodate unevenness
of the floor. If not otherwise arranged, make
sure that the joint under the wall is 3 cm.
Four supports are to be levelled out for each
element. (under both surfaces +50 cm from
both ends of the wall.)
Make sure that the crane and the deep-loaders
have unimpeded access to the site. Here you
must take account of possible street obstructi-
ons, the sharpness of bends, parked vehicles,
etc.
The transport vehicles have a length up to 18 m;
the headroom amounts to at least 4 m.
This form of transport is used for walls higher
than 2.80 m.
The permissible ground unevenness is a maxi-
mum of 25 cm over a length of 6 m.
Vertical transport with container is used for
walls with a maximum height to 2.80 m.
With horizontal delivery the base surface of the
lorries must be level.
Vertical transport with carriage
Vertical transport with container
Horizontal transport
Unloading of the supplied walls Placing the walls
Three operatives are needed for assembly.
Make sure that with the bringing in of a new
element the elements already in position are not
displaced or damaged.
Gradually lower the element and push any
protruding holding rods to the side. Place the
element in line and up to the adjusting pro-
jections. Make sure that the joints are always
perpendicular 2 cm. The position can still be
corrected with a pry bar to afterwards set the
positions with wedges.
Fix each element with two props on both sides.
Screwed sleeves are provided in the walls. The
holes needed in the floor slab still have to be
drilled.
The crane hooks may only be removed after the
elements have been fixed in place and checked.
Now apply the joint and corner reinforcement.
Do not forget to form the recesses.
Vertical
Sufficiently long hoisting cables must be used
to guarantee an angle of at least 60°. Make sure
that the element is always level. Use a pointer
Horizontal
In exceptional cases the walls are transported
horizontally.
Upon request we can also provide you with
specially designed hoisting hooks with which
one lifts the elements horizontally and stacks
them horizontally next to the lorry.
You must make sure that the ground surface is
suffi ciently stable and level for this. We advise
placing a wooden beam between the hoisting
hooks and the concrete elements to spread
any concentrated loads. One can then pull the
elements vertical with the transport anchors
placed at the factory. We also advise to place a
wooden beam between the hoisting hooks and
the concrete shells.
Always make sure that the chains or cables are
sufficiently long to guarantee an angle of 60°.
The maximum weight per hoist anchor is 2 tons.
>60°
Correct concreting Faster, less expensive and perfect construction
More cost-effectiveness
Because no formwork is needed:
■	 no rental, storage, investment costs/
	 depreciations
■	 no transport, expensive placing, removal or
	 cleaning of the formwork
■	 less dependent on personnel
■	 ideal for single-sided formwork or gap
	 construction: a possible take-over stipula-
tion is not required
■	 greater flexibility
Cost-saving
■	 insensitive to settling
■	 less sealing material required
■	 less transport and crane costs because of
less weight
■	 no mortar bed required for assembly
■	 no joint problems because of the homo-
genous nature of the concrete deposited
on-site
■	 simple connecting of base plate and ceiling
with the joint reinforcement in the infill con-
crete
Extra benefits
■	 individual production, geared to each project
■	 good acoustic insulation
■	 few limitations as regards static possibilities
■	 combination of the advantages of concrete
	 poured on-site and prefab-elements
■	 edge formwork for wide slabs already provi-
ded in the wall elements
Shorter construction time
■	 lower fi nancing costs
■	 production at the factory independent of
	 weather conditions
■	 no waiting times for the removal of form-
work
■	 no edge trestle required as support for the
wide slabs
■	 built-in elements such as windows, doors,
door frames, cable ducts and electrical
boxes can already be built in at the factory
■	 particularly smooth surface areas on the
inside and outside: suitable for spray plaster
■	 delivered ready to wallpaper on request: no
	 traditional plastering necessary
■	 just-in-time delivery
Finish the joints as follows:
■	 Horizontal joints must be propped up and
formed if necessary.
■	 Vertical joints must be formed if the joint is
larger than 1 cm. For this you must use as-
sembly foam.
Reinforce corners using angle bars or wooden
planks. Props can be used for T-joints.
You can place the wide slab before the walls
are concreted. For this the walls must be as-
sembled in a mortar bed or sufficiently wed-
ged. The inner surface of the walls must be
moistened before concreting. Concreting must
take place in accordance with the conditions
provided. The infill concrete must be properly
vibrated.
Important:
■	 The permissible concrete pressure must not
exceed 30 kN/m2.
■	 We advise you to vibrate for 60 % of the fil-
ling time.
These assembly instructions are intended as advice. The infor-
mation is based on current standards and technical approval
and our many years of experience. They are however not binding.
Our assembly supervisors under no circumstances accept the
role and the liability of the authorised supervisor.
This also applies for any employees of our company and our
suppliers on the building site. Variations in colour and surface
with respect to the prospectus material as well as technical and
static changes reserved.
Kerkstoel 2000+ NV
Industrieweg 11
B – 2280 Grobbendonk
T: 014 50 00 31
F: 014 50 15 73
info@kerkstoel.be
www.kerkstoel.be
Kerkstoel 2000+ satisfies the
highest quality standards.
CavityWalls n KerkstoelComfort®Walls n FloorPannels n KerkstoelACTIV®Floors n Floorpannelswithweight-savingcomponents

More Related Content

What's hot

Low cost housing
Low cost housingLow cost housing
Low cost housingSuman Nandi
 
Cost effective construction techniques
Cost effective construction techniquesCost effective construction techniques
Cost effective construction techniquesSayali Darakh
 
BUOYANT FOUNDATION REPORT
BUOYANT FOUNDATION REPORTBUOYANT FOUNDATION REPORT
BUOYANT FOUNDATION REPORTKAUSHAL MORE
 
Roof and roof covering
Roof and roof coveringRoof and roof covering
Roof and roof coveringDivya Vishnoi
 
Lift form slab construction
Lift form slab constructionLift form slab construction
Lift form slab constructiontivar rose
 
Building study report
Building study reportBuilding study report
Building study reportsurabhi527
 
Low cost housing
Low cost housingLow cost housing
Low cost housingSAI KIRAN
 
Precast structure
Precast structurePrecast structure
Precast structurepiyush9392
 
Basement construction report
Basement construction reportBasement construction report
Basement construction reportANKITAARORA85
 
Presentation of precast concrete
Presentation of precast concretePresentation of precast concrete
Presentation of precast concreteAshik Ásh
 
Long span structures in Concrete and Steel
Long span structures in Concrete and SteelLong span structures in Concrete and Steel
Long span structures in Concrete and SteelRithika Ravishankar
 
Slipform construction
Slipform constructionSlipform construction
Slipform constructiontivar rose
 
Cost effective materials
Cost effective materialsCost effective materials
Cost effective materialsSarthak Kaura
 

What's hot (20)

Modern Method
Modern MethodModern Method
Modern Method
 
Low cost housing
Low cost housingLow cost housing
Low cost housing
 
Cost effective construction techniques
Cost effective construction techniquesCost effective construction techniques
Cost effective construction techniques
 
BUOYANT FOUNDATION REPORT
BUOYANT FOUNDATION REPORTBUOYANT FOUNDATION REPORT
BUOYANT FOUNDATION REPORT
 
Roof and roof covering
Roof and roof coveringRoof and roof covering
Roof and roof covering
 
Lift form slab construction
Lift form slab constructionLift form slab construction
Lift form slab construction
 
Building study report
Building study reportBuilding study report
Building study report
 
Low cost housing
Low cost housingLow cost housing
Low cost housing
 
Precast structure
Precast structurePrecast structure
Precast structure
 
Prefabricated structures
Prefabricated structuresPrefabricated structures
Prefabricated structures
 
JUMP FORM WORK
JUMP FORM WORKJUMP FORM WORK
JUMP FORM WORK
 
Basement construction report
Basement construction reportBasement construction report
Basement construction report
 
Presentation of precast concrete
Presentation of precast concretePresentation of precast concrete
Presentation of precast concrete
 
High rise
High riseHigh rise
High rise
 
Long span structures in Concrete and Steel
Long span structures in Concrete and SteelLong span structures in Concrete and Steel
Long span structures in Concrete and Steel
 
Mudarchitecture,
Mudarchitecture,Mudarchitecture,
Mudarchitecture,
 
Prestressed construction
Prestressed constructionPrestressed construction
Prestressed construction
 
Slipform construction
Slipform constructionSlipform construction
Slipform construction
 
Buildings Structure system
Buildings Structure systemBuildings Structure system
Buildings Structure system
 
Cost effective materials
Cost effective materialsCost effective materials
Cost effective materials
 

Viewers also liked

Hormigon
Hormigon Hormigon
Hormigon parg
 
Pouring concrete into formwork
Pouring concrete into formwork Pouring concrete into formwork
Pouring concrete into formwork Dosy21
 
Armtec Engineering's Top Picks - Case Studies and Design Review
Armtec Engineering's Top Picks - Case Studies and Design ReviewArmtec Engineering's Top Picks - Case Studies and Design Review
Armtec Engineering's Top Picks - Case Studies and Design ReviewCommunications Branding
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete constructionRamin Vaghei
 
Ceramicas trabajo de materiales para la construccion
Ceramicas   trabajo de materiales para la construccionCeramicas   trabajo de materiales para la construccion
Ceramicas trabajo de materiales para la construccionmpenuela
 
COMO TRANSPORTAR LA CERAMICA
COMO TRANSPORTAR LA CERAMICACOMO TRANSPORTAR LA CERAMICA
COMO TRANSPORTAR LA CERAMICAmpenuela
 
Formwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyFormwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyI'mMiss Lily
 
A study on the construction process (Precast concrete, In-situ cast concrete,...
A study on the construction process (Precast concrete, In-situ cast concrete,...A study on the construction process (Precast concrete, In-situ cast concrete,...
A study on the construction process (Precast concrete, In-situ cast concrete,...Bhaddin Al-Naqshabandi
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete constructionMadan Mohan Jana
 
Precast Concrete Steps Construction Tutorial by Armtec Ltd.
Precast Concrete Steps Construction Tutorial by Armtec Ltd.Precast Concrete Steps Construction Tutorial by Armtec Ltd.
Precast Concrete Steps Construction Tutorial by Armtec Ltd.Communications Branding
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structuresRithika Ravishankar
 

Viewers also liked (17)

Hormigon
Hormigon Hormigon
Hormigon
 
2015 10 06_sem_pref_watanabe_chile_presentationoct2015(part1)
2015 10 06_sem_pref_watanabe_chile_presentationoct2015(part1)2015 10 06_sem_pref_watanabe_chile_presentationoct2015(part1)
2015 10 06_sem_pref_watanabe_chile_presentationoct2015(part1)
 
Pouring concrete into formwork
Pouring concrete into formwork Pouring concrete into formwork
Pouring concrete into formwork
 
Armtec Engineering's Top Picks - Case Studies and Design Review
Armtec Engineering's Top Picks - Case Studies and Design ReviewArmtec Engineering's Top Picks - Case Studies and Design Review
Armtec Engineering's Top Picks - Case Studies and Design Review
 
Costruction ppt
Costruction pptCostruction ppt
Costruction ppt
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
 
Ceramicas trabajo de materiales para la construccion
Ceramicas   trabajo de materiales para la construccionCeramicas   trabajo de materiales para la construccion
Ceramicas trabajo de materiales para la construccion
 
Formwork
FormworkFormwork
Formwork
 
Ceramica
CeramicaCeramica
Ceramica
 
COMO TRANSPORTAR LA CERAMICA
COMO TRANSPORTAR LA CERAMICACOMO TRANSPORTAR LA CERAMICA
COMO TRANSPORTAR LA CERAMICA
 
Column formwork
Column formworkColumn formwork
Column formwork
 
Formwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyFormwork Presentation for Construction Technology
Formwork Presentation for Construction Technology
 
A study on the construction process (Precast concrete, In-situ cast concrete,...
A study on the construction process (Precast concrete, In-situ cast concrete,...A study on the construction process (Precast concrete, In-situ cast concrete,...
A study on the construction process (Precast concrete, In-situ cast concrete,...
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
 
Precast Concrete Steps Construction Tutorial by Armtec Ltd.
Precast Concrete Steps Construction Tutorial by Armtec Ltd.Precast Concrete Steps Construction Tutorial by Armtec Ltd.
Precast Concrete Steps Construction Tutorial by Armtec Ltd.
 
Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structures
 
Formwork
FormworkFormwork
Formwork
 

Similar to REINFORCED CONCRETE PRECAST TWIN WALLS

UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURESUNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURESVenkateswaran S
 
visual dictionary final project
visual dictionary final projectvisual dictionary final project
visual dictionary final projectAuburn University
 
Sanfer System build process and solutions
Sanfer System build process and solutionsSanfer System build process and solutions
Sanfer System build process and solutionsRichard Carey-Evans
 
Speedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSpeedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSOUMYA KHANDELWAL
 
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdfSAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdfSakshiMahadik3
 
Repair,Retrofitting and Rehabilitation
Repair,Retrofitting and RehabilitationRepair,Retrofitting and Rehabilitation
Repair,Retrofitting and RehabilitationIshwar Chauhan
 
AintreeInfra Gypsum Block
AintreeInfra Gypsum BlockAintreeInfra Gypsum Block
AintreeInfra Gypsum BlockMerina Kunjumon
 
EMRULLAH ETE-126565-civil engineering
EMRULLAH ETE-126565-civil engineeringEMRULLAH ETE-126565-civil engineering
EMRULLAH ETE-126565-civil engineeringEMRULLAH ETE
 
alternate wall technologies.pdf
alternate wall technologies.pdfalternate wall technologies.pdf
alternate wall technologies.pdfNithyashree594058
 
Bolderstone brochure
Bolderstone brochureBolderstone brochure
Bolderstone brochurekristenjames
 
AAC Installation Guidelines
AAC Installation GuidelinesAAC Installation Guidelines
AAC Installation GuidelinesBENAY MUNDA
 
national building code
national building codenational building code
national building codeRuhiya Garg
 
Masonry of Building
Masonry of Building Masonry of Building
Masonry of Building Yasir Hussain
 
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...Deepak Verma
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxVinayak247538
 

Similar to REINFORCED CONCRETE PRECAST TWIN WALLS (20)

UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURESUNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
 
Aac
AacAac
Aac
 
Low-Cost-Housing.ppt
Low-Cost-Housing.pptLow-Cost-Housing.ppt
Low-Cost-Housing.ppt
 
visual dictionary
visual dictionaryvisual dictionary
visual dictionary
 
visual dictionary final project
visual dictionary final projectvisual dictionary final project
visual dictionary final project
 
Sanfer System build process and solutions
Sanfer System build process and solutionsSanfer System build process and solutions
Sanfer System build process and solutions
 
Uniflex Brochure_English
Uniflex Brochure_EnglishUniflex Brochure_English
Uniflex Brochure_English
 
Speedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALSSpeedy construction- FORMS AND MATERIALS
Speedy construction- FORMS AND MATERIALS
 
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdfSAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
SAKSHI MAHADIK_PRECAST ROOFING_FINAL SUBMISSION.pdf
 
Repair,Retrofitting and Rehabilitation
Repair,Retrofitting and RehabilitationRepair,Retrofitting and Rehabilitation
Repair,Retrofitting and Rehabilitation
 
AintreeInfra Gypsum Block
AintreeInfra Gypsum BlockAintreeInfra Gypsum Block
AintreeInfra Gypsum Block
 
EMRULLAH ETE-126565-civil engineering
EMRULLAH ETE-126565-civil engineeringEMRULLAH ETE-126565-civil engineering
EMRULLAH ETE-126565-civil engineering
 
alternate wall technologies.pdf
alternate wall technologies.pdfalternate wall technologies.pdf
alternate wall technologies.pdf
 
Bolderstone brochure
Bolderstone brochureBolderstone brochure
Bolderstone brochure
 
AAC Installation Guidelines
AAC Installation GuidelinesAAC Installation Guidelines
AAC Installation Guidelines
 
national building code
national building codenational building code
national building code
 
Masonry of Building
Masonry of Building Masonry of Building
Masonry of Building
 
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
 
Aerocon bricks
Aerocon bricksAerocon bricks
Aerocon bricks
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptx
 

Recently uploaded

Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 

Recently uploaded (20)

Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 

REINFORCED CONCRETE PRECAST TWIN WALLS

  • 1. Reinforced concrete double walls Build faster, pay less.
  • 2. Strength in building technology Uses Kerkstoel double walls have special advantages for different applications. Because each ele- ment is manufactured individually according to requirements, Kerkstoel double walls are The Kerkstoel reinforced double walls consist of two slabs of reinforced concrete joined to each other by lattice girders. The wall elements are installed on the site ac- cording to the plan and then filled with concrete. DIMENSIONS length: up to 8.30 m height: up to 2.80 m, possibly up to 3.50 m on request thickness (outside/inside): 19-34 cm (on request 40 to 70 cm) thickness of the slabs at least 5 cm each other dimensions on request WEIGHT approx. 250 kg per m2 with 2 x 5 cm slab thickness CONCRETE QUALITY at least C25-30 SURFACE suitable for spray plaster or ready to wallpaper on request the ideal construction method for just about all building work. Below you can find some examples of the many applications. The result is a solid construction and a strong base that is virtually a monolithic concrete wall. Kerkstoel double walls are manufactured in ac- cordance with the strict standards of the Belgian conformity certificate and of ISO 9001. Private homes Inside and outside walls, the replacement of brickwork, an alternative for concrete poured on-site Large construction projects Industrial construction, silo walls, tunnels, underground car parks, supporting walls Tall walls Tall walls with a height above 8 m, can be produced for various uses. Storey Floors Façade walls, dividing walls in homes, outside walls, lifts and stairwells, partition walls Walls as waterproof constructions Including basements, water treatment plants, retaining walls and swimming pools Prefab-elements Suitable for spray plaster or ready to wallpaper as required Floor slabs Concrete poured on site Wall open web beam Wall reinforcement
  • 3. Kerkstoel thinks of all details Kerkstoel offers technical support We offer just-in-time logistical and qualified assembly assistance for the smooth completion of construction plans. We draw up a detailed assembly schedule on the basis of the design of the architect (plan and cross-section), the stability calculations, formwork and installation plans. We develop the production plans and provide them with all the necessary details, so that everything goes smoothly and according to schedule on the site. CEILING JOINTS BASE PLATE JOINTS FOR VERTICAL JOINTS for corners FOR WALL JOINTS (not reinforced) (not reinforced) (not reinforced)(not reinforced) lattice glider (not reinforced) solid wall (reinforced) (reinforced) (reinforced)(reinforced) (reinforced) double wall (reinforced) double wall open web beam casing
  • 4. What else does Kerkstoel have to offer? Built-in parts Because each design has its own specific properties, Kerkstoel double walls are uniquely produced according to requirements. Not only does each wall have its own dimensions and openings for doors and windows, the built-in parts for the finishing can also be immediately provided. The use of the latest CAD and robot techniques allows Kerkstoel to produce double walls of even the most individual design and all this at a very reasonable cost. 2 6 3 5 1 4 1 Electrical fittings 2 Openings, passageways 3 Pipes for the vertical powering of electrical installations. 4 Door frames, wooden formwork 5 Windows or wooden formwork 6 Reinforcement for joints with concrete poured on-site Kerkstoel offers technical support 1 Provisions for electricity, distribution and telephone. 2 Openings for: incl. sewers, air-conditioning, ventilation, etc. 3 Conduit for the ease of electrical installation 4 Doorway with formwork. All sizes are possible. 5 Window opening with formwork. 1 3 5 2 4
  • 5. Completely watertight, also at the joints Building in groundwater The bed plate is utilising a water-resistant concrete. The outside walls can be of a maximum thickness and filled with water-resistant concrete. Kerkstoel’s high quality double wall elements and the concrete guarantee the complete watertight- ness of the wall. The joints are either sealed on the outside or given a sealing layer. Kerkstoel double walls are manufactured in optimal and precision-controlled conditions at the factory. Production faults are practically excluded by using an integrated quality management system. The double walls resist any water load, water pressure and any other form of moisture to which a building is exposed. Kerkstoel stands for reliability, and the certainty that all physical construction properties will be taken into account. VERTICAL JOINTS HORIZONTAL JOINTS Inner sealing for example joint with sealing section open web beam bottom foundations bottom foundations bottom foundations bottom foundations bottom foundations bottom foundations Roughen the area of contact Water retaining plate Inll concrete (water/cement <0.5) Swell strip joint of 3 cm Roofing Roughen the area of contact. This limits the creeping of the con- crete in relation to the foundations Always use suitable cement. The water/cement factor must always be less than 0.5 The wall must be placed ±3 cm above the foundations. This means one can increase the contact area. Exterior sealing for example thick coating Resources for water sealing Method for good water sealing
  • 6. Transport Preparation of the floor slab Make sure that the joining reinforcement is placed correctly with the concreting of the slab, ensuring that there is sufficient inside space. Do not use mesh reinforcement as starter bars. Trace the place where the walls must be erected with the numbers of the walls on the ground. The information can be found on the assembly plan. Use base plates to accommodate unevenness of the floor. If not otherwise arranged, make sure that the joint under the wall is 3 cm. Four supports are to be levelled out for each element. (under both surfaces +50 cm from both ends of the wall.) Make sure that the crane and the deep-loaders have unimpeded access to the site. Here you must take account of possible street obstructi- ons, the sharpness of bends, parked vehicles, etc. The transport vehicles have a length up to 18 m; the headroom amounts to at least 4 m. This form of transport is used for walls higher than 2.80 m. The permissible ground unevenness is a maxi- mum of 25 cm over a length of 6 m. Vertical transport with container is used for walls with a maximum height to 2.80 m. With horizontal delivery the base surface of the lorries must be level. Vertical transport with carriage Vertical transport with container Horizontal transport
  • 7. Unloading of the supplied walls Placing the walls Three operatives are needed for assembly. Make sure that with the bringing in of a new element the elements already in position are not displaced or damaged. Gradually lower the element and push any protruding holding rods to the side. Place the element in line and up to the adjusting pro- jections. Make sure that the joints are always perpendicular 2 cm. The position can still be corrected with a pry bar to afterwards set the positions with wedges. Fix each element with two props on both sides. Screwed sleeves are provided in the walls. The holes needed in the floor slab still have to be drilled. The crane hooks may only be removed after the elements have been fixed in place and checked. Now apply the joint and corner reinforcement. Do not forget to form the recesses. Vertical Sufficiently long hoisting cables must be used to guarantee an angle of at least 60°. Make sure that the element is always level. Use a pointer Horizontal In exceptional cases the walls are transported horizontally. Upon request we can also provide you with specially designed hoisting hooks with which one lifts the elements horizontally and stacks them horizontally next to the lorry. You must make sure that the ground surface is suffi ciently stable and level for this. We advise placing a wooden beam between the hoisting hooks and the concrete elements to spread any concentrated loads. One can then pull the elements vertical with the transport anchors placed at the factory. We also advise to place a wooden beam between the hoisting hooks and the concrete shells. Always make sure that the chains or cables are sufficiently long to guarantee an angle of 60°. The maximum weight per hoist anchor is 2 tons. >60°
  • 8. Correct concreting Faster, less expensive and perfect construction More cost-effectiveness Because no formwork is needed: ■ no rental, storage, investment costs/ depreciations ■ no transport, expensive placing, removal or cleaning of the formwork ■ less dependent on personnel ■ ideal for single-sided formwork or gap construction: a possible take-over stipula- tion is not required ■ greater flexibility Cost-saving ■ insensitive to settling ■ less sealing material required ■ less transport and crane costs because of less weight ■ no mortar bed required for assembly ■ no joint problems because of the homo- genous nature of the concrete deposited on-site ■ simple connecting of base plate and ceiling with the joint reinforcement in the infill con- crete Extra benefits ■ individual production, geared to each project ■ good acoustic insulation ■ few limitations as regards static possibilities ■ combination of the advantages of concrete poured on-site and prefab-elements ■ edge formwork for wide slabs already provi- ded in the wall elements Shorter construction time ■ lower fi nancing costs ■ production at the factory independent of weather conditions ■ no waiting times for the removal of form- work ■ no edge trestle required as support for the wide slabs ■ built-in elements such as windows, doors, door frames, cable ducts and electrical boxes can already be built in at the factory ■ particularly smooth surface areas on the inside and outside: suitable for spray plaster ■ delivered ready to wallpaper on request: no traditional plastering necessary ■ just-in-time delivery Finish the joints as follows: ■ Horizontal joints must be propped up and formed if necessary. ■ Vertical joints must be formed if the joint is larger than 1 cm. For this you must use as- sembly foam. Reinforce corners using angle bars or wooden planks. Props can be used for T-joints. You can place the wide slab before the walls are concreted. For this the walls must be as- sembled in a mortar bed or sufficiently wed- ged. The inner surface of the walls must be moistened before concreting. Concreting must take place in accordance with the conditions provided. The infill concrete must be properly vibrated. Important: ■ The permissible concrete pressure must not exceed 30 kN/m2. ■ We advise you to vibrate for 60 % of the fil- ling time.
  • 9. These assembly instructions are intended as advice. The infor- mation is based on current standards and technical approval and our many years of experience. They are however not binding. Our assembly supervisors under no circumstances accept the role and the liability of the authorised supervisor. This also applies for any employees of our company and our suppliers on the building site. Variations in colour and surface with respect to the prospectus material as well as technical and static changes reserved. Kerkstoel 2000+ NV Industrieweg 11 B – 2280 Grobbendonk T: 014 50 00 31 F: 014 50 15 73 info@kerkstoel.be www.kerkstoel.be Kerkstoel 2000+ satisfies the highest quality standards. CavityWalls n KerkstoelComfort®Walls n FloorPannels n KerkstoelACTIV®Floors n Floorpannelswithweight-savingcomponents