SlideShare a Scribd company logo
1 of 3
Download to read offline
SCHOOL OF ARCHITECTURE · BUILDING · DESIGN
Centre for Modern Architecture Studies in Southeast Asia
Bachelor of Quantity Surveying (Honours)
PROFESSIONAL PRACTICE [QSB 3614]
1. This assignment shall make up 15% weightage of the final marks.
2. This is a group assignment and shall be submitted in groups of 6 students.
3. Dateline for submission of this Coursework No. 2 is on or before 30th October 2017.
Coursework No. 2 – Preparation of Final Account.
You are appointed as the consulting Quantity Surveyor for a apartment project based on PAM
Form of Contract 2006 (With Quantities). The summary of the Contract Sum is as follows:
Bill No. 1 – Preliminaries RM 2,250,000.00
Bill No. 2 – Building Works RM 31,450,000.00
Bill No. 3 – Local Infrastructure Works RM 6,130,000.00
Bill No. 4 – P.C. and Provisional Sums RM 7,870,000.00
Contract Sum RM 47,700,000.00
Question 1.
The tender drawings shows the apartment entrance arch with guardhouse but no details were
provided. The Architect had suggested that these items be listed as Provisional Sum. However
you have forgot about this item and did not include it in your tender document. The contract
was awarded without it. The director would also like to know the significance and implications
of this omission by their office.
In addition, you are required to prepare a report to your director, explaining briefly the
adjustments of the essential elements in your preparation of this project’s final account.
(25 marks)
Question 2.
In accordance with clause 30.10 of the contract, the contractor duly submitted his Final Accounts
within 6 months after the issuance of the Certificate of Practical Completion. You are then
required to assess this application and prepare the Final Account for the apartment project
based of the following valuations and adjustments made to the Contract Sum:
(35 marks)
Information provided are as follows:
a. The Architect had granted the Contractor’s first application for extension of time and
approved additional insurance premium amounting to RM 10,000.00 in accordance with
clause 24 of the contract due to the delay in the completion of the works caused by the
Employer’s late decision on the toilet design. 



In his second application for extension of time, the Contractor submitted an loss and
expense claim for RM200,000.00 in his Final Accounts to you. Since the delay event is
1
not a relevant event listed in Clause 23.8, the Architect had rejected the Contractor’s
second application.
b. There are four variation orders carried out by the Contractor:
Addition Omission
i. Variation Order No. 1: RM 300,000.00 RM 200,000.00
Changes of toilet layout to
suit Employer’s requirements.
ii. Variation Order No. 2: RM 400,000.00 -
New lift lobby at entrance.
iii. Variation Order No. 3:
Changes from premix roads RM 1,100,000.00 RM 900,000.00
to precast concrete paver blocks
iv. Variation Order No. 4:
Omission of glass partitions - RM 96,000.00
c. The following are the nominated sub-contractor’s accounts:
Original P.C. & NSC’s
Provisional Sums final account
i. Lift Services: RM 1,700,000.00 RM 1,500,000.00
Profit @ 2% RM 34,000.00
Attendance as item RM 34,000.00
ii. Air Conditioning Services: RM 1,200,000.00 RM 1,000,000.00
Profit @ 2% RM 24,000.00
Attendance as item RM 24,000.00
iii. Electrical Services: RM 1,600,000.00 RM 2,100,000.00
Profit @ 2% RM 32,000.00
Attendance as item RM 32,000.00
iv. Provisional Sums: Entrance Porch RM 1,270,000.00 RM 1,050,000.00
RM 6,670,000.00

2
Question 3.
Explain the basis on how the following variations may be finalised and priced during the Final
Account stage:
a. Relocation of an already installed timber door including sealing up the wall opening.
Agreed at the site meeting for Contractor to claim based on Dayworks for labour,
material and plant.
(10 marks)
b. Contractor need to provide computer equipment in the Preliminaries section but item was
left unpriced, i.e. BQ item was left blank in the rate/amount column in the contract
document. Subsequently, this item was omitted by the Architect.
(10 marks)
c. A wash trough as required and priced in the Preliminaries section was not constructed
due to site constraints imposed later by the Employer. However, the vehicles leaving the
site during construction were always kept clean including the public roads using water jet
washing and full-timed workers.
(10 marks)
d. Mistake was made in the price for excavation through rocks at RM 15 per m3. Item was
not rationalised during contract documentation. However, original quantity in BQ is 100
m3 but re-measured quantity is 2,000 m3. The Contractor submitted a claim for revised
rates of RM 150 per m3 for the total quantity of 2,000 m3.
(10 marks)
3

More Related Content

What's hot

Assignment - Report
Assignment - ReportAssignment - Report
Assignment - ReportKai Yun Pang
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-finalashleyyeap
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final AccountKai Yun Pang
 
PP2 final report
PP2 final reportPP2 final report
PP2 final reportArissa Loh
 
Quantity surveying -scope and purpose
Quantity surveying -scope and purposeQuantity surveying -scope and purpose
Quantity surveying -scope and purposeAbhijeet Bhosale
 
Consultancy case studies
Consultancy case studiesConsultancy case studies
Consultancy case studiesgrahamelanders
 
How to start a construction company as a contractor
How to start a construction company as a contractorHow to start a construction company as a contractor
How to start a construction company as a contractorAnusha Mona
 
Smeaton and Watt- Changing Infrastructure & Road
Smeaton and Watt- Changing Infrastructure & RoadSmeaton and Watt- Changing Infrastructure & Road
Smeaton and Watt- Changing Infrastructure & RoadBarun Chatterjee
 
Fundamentals of estimating_and_costing
Fundamentals of estimating_and_costingFundamentals of estimating_and_costing
Fundamentals of estimating_and_costingPrasad Manerikar
 
Methods of estimation - Estimation, Costing and Valuation Engineering
Methods of estimation - Estimation, Costing and Valuation EngineeringMethods of estimation - Estimation, Costing and Valuation Engineering
Methods of estimation - Estimation, Costing and Valuation EngineeringShanmugasundaram N
 
Income from house property sums
Income from house property   sumsIncome from house property   sums
Income from house property sumssumit235
 
NC Monthly Expenditure Report 6-25-13
NC Monthly Expenditure Report 6-25-13NC Monthly Expenditure Report 6-25-13
NC Monthly Expenditure Report 6-25-13EmpowerLA
 
Types of estimate - Estimation, Costing and Valuation Engineering
Types of estimate - Estimation, Costing and Valuation EngineeringTypes of estimate - Estimation, Costing and Valuation Engineering
Types of estimate - Estimation, Costing and Valuation EngineeringShanmugasundaram N
 
Akuntansi keuangan ii (c1) kelompok 2
Akuntansi keuangan ii (c1)   kelompok 2Akuntansi keuangan ii (c1)   kelompok 2
Akuntansi keuangan ii (c1) kelompok 2HennyTriyanaHasibuan
 

What's hot (17)

Assignment - Report
Assignment - ReportAssignment - Report
Assignment - Report
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
 
Assignment - Final Account
Assignment - Final AccountAssignment - Final Account
Assignment - Final Account
 
PP2 final report
PP2 final reportPP2 final report
PP2 final report
 
Quantity surveying -scope and purpose
Quantity surveying -scope and purposeQuantity surveying -scope and purpose
Quantity surveying -scope and purpose
 
Consultancy case studies
Consultancy case studiesConsultancy case studies
Consultancy case studies
 
How to start a construction company as a contractor
How to start a construction company as a contractorHow to start a construction company as a contractor
How to start a construction company as a contractor
 
Smeaton and Watt- Changing Infrastructure & Road
Smeaton and Watt- Changing Infrastructure & RoadSmeaton and Watt- Changing Infrastructure & Road
Smeaton and Watt- Changing Infrastructure & Road
 
Fundamentals of estimating_and_costing
Fundamentals of estimating_and_costingFundamentals of estimating_and_costing
Fundamentals of estimating_and_costing
 
Approximate estimate
Approximate estimateApproximate estimate
Approximate estimate
 
Methods of estimation - Estimation, Costing and Valuation Engineering
Methods of estimation - Estimation, Costing and Valuation EngineeringMethods of estimation - Estimation, Costing and Valuation Engineering
Methods of estimation - Estimation, Costing and Valuation Engineering
 
Income from house property sums
Income from house property   sumsIncome from house property   sums
Income from house property sums
 
NC Monthly Expenditure Report 6-25-13
NC Monthly Expenditure Report 6-25-13NC Monthly Expenditure Report 6-25-13
NC Monthly Expenditure Report 6-25-13
 
Types of estimate - Estimation, Costing and Valuation Engineering
Types of estimate - Estimation, Costing and Valuation EngineeringTypes of estimate - Estimation, Costing and Valuation Engineering
Types of estimate - Estimation, Costing and Valuation Engineering
 
Akuntansi keuangan ii (c1) kelompok 2
Akuntansi keuangan ii (c1)   kelompok 2Akuntansi keuangan ii (c1)   kelompok 2
Akuntansi keuangan ii (c1) kelompok 2
 
C.V-Ayman
C.V-Ayman  C.V-Ayman
C.V-Ayman
 
Practice for Quantity Surveyors
Practice for Quantity SurveyorsPractice for Quantity Surveyors
Practice for Quantity Surveyors
 

Similar to Pp2 coursework 2 brief

Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-finalashleyyeap
 
PP2 - Group Assignment
PP2 - Group AssignmentPP2 - Group Assignment
PP2 - Group AssignmentLin Hui
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignmentlohwenjun
 
PP1 Project 3 Cover letter
PP1 Project 3 Cover letterPP1 Project 3 Cover letter
PP1 Project 3 Cover letterTeo Kean Hui
 
PP2 - Assignment
PP2 - AssignmentPP2 - Assignment
PP2 - AssignmentQuo Ming
 
Pp2 assignment
Pp2 assignmentPp2 assignment
Pp2 assignmentfareezsham
 
Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice IIseenyeeyong
 
PP2 Assignment: Group
PP2 Assignment: GroupPP2 Assignment: Group
PP2 Assignment: GroupFarah Sham
 
Draft Bid Evaluation Report-2.docx
Draft Bid Evaluation Report-2.docxDraft Bid Evaluation Report-2.docx
Draft Bid Evaluation Report-2.docxArshadMahmood155695
 
Measurement iv
Measurement ivMeasurement iv
Measurement ivtfkc1212
 
Building Economics:Tender Report
Building Economics:Tender ReportBuilding Economics:Tender Report
Building Economics:Tender Report마 이환
 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptxTalebAlfihan
 
A Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptxA Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptxMahSobeh
 
Brainstorm Slideshow TU.pptx
Brainstorm Slideshow TU.pptxBrainstorm Slideshow TU.pptx
Brainstorm Slideshow TU.pptxssuser914470
 

Similar to Pp2 coursework 2 brief (20)

PP2 - Assignment
PP2 - Assignment PP2 - Assignment
PP2 - Assignment
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
 
PP2 - Group Assignment
PP2 - Group AssignmentPP2 - Group Assignment
PP2 - Group Assignment
 
Pp2 group assignment
Pp2 group assignmentPp2 group assignment
Pp2 group assignment
 
PP1 Project 3 Cover letter
PP1 Project 3 Cover letterPP1 Project 3 Cover letter
PP1 Project 3 Cover letter
 
PP2 - Assignment
PP2 - AssignmentPP2 - Assignment
PP2 - Assignment
 
Pp2 assignment
Pp2 assignmentPp2 assignment
Pp2 assignment
 
Cl report final
Cl report finalCl report final
Cl report final
 
Kandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _bKandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _b
 
Professional Practice II
Professional Practice IIProfessional Practice II
Professional Practice II
 
PP2 Assignment: Group
PP2 Assignment: GroupPP2 Assignment: Group
PP2 Assignment: Group
 
Draft Bid Evaluation Report-2.docx
Draft Bid Evaluation Report-2.docxDraft Bid Evaluation Report-2.docx
Draft Bid Evaluation Report-2.docx
 
Measurement iv
Measurement ivMeasurement iv
Measurement iv
 
Building Economics:Tender Report
Building Economics:Tender ReportBuilding Economics:Tender Report
Building Economics:Tender Report
 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptx
 
A Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptxA Claim submitted by the contractor during for slides.pptx
A Claim submitted by the contractor during for slides.pptx
 
Cm mitemrate ver270206
Cm mitemrate ver270206Cm mitemrate ver270206
Cm mitemrate ver270206
 
M4ppt
M4pptM4ppt
M4ppt
 
Contract presentation
Contract presentation  Contract presentation
Contract presentation
 
Brainstorm Slideshow TU.pptx
Brainstorm Slideshow TU.pptxBrainstorm Slideshow TU.pptx
Brainstorm Slideshow TU.pptx
 

More from Doreen Yeo

Value management presentation slides
Value management presentation slidesValue management presentation slides
Value management presentation slidesDoreen Yeo
 
Project management assignment slides
Project management assignment slidesProject management assignment slides
Project management assignment slidesDoreen Yeo
 
CIPAA presentation
CIPAA presentationCIPAA presentation
CIPAA presentationDoreen Yeo
 
Financial Management Report
Financial Management ReportFinancial Management Report
Financial Management ReportDoreen Yeo
 
BE presentation slides
BE presentation slidesBE presentation slides
BE presentation slidesDoreen Yeo
 
BE cost appraisal
BE cost appraisalBE cost appraisal
BE cost appraisalDoreen Yeo
 
Estimating seminar 2 glazing answer
Estimating seminar 2 glazing answerEstimating seminar 2 glazing answer
Estimating seminar 2 glazing answerDoreen Yeo
 
Estimating seminar 1 slides
Estimating seminar 1 slidesEstimating seminar 1 slides
Estimating seminar 1 slidesDoreen Yeo
 
Assignment ceiling finishes
Assignment ceiling finishesAssignment ceiling finishes
Assignment ceiling finishesDoreen Yeo
 
PP1 assignment presentation slides
PP1 assignment presentation slidesPP1 assignment presentation slides
PP1 assignment presentation slidesDoreen Yeo
 
Software Application presentation slides
Software Application presentation slidesSoftware Application presentation slides
Software Application presentation slidesDoreen Yeo
 
Measurement IV assignment presentation slides
Measurement IV assignment presentation slides Measurement IV assignment presentation slides
Measurement IV assignment presentation slides Doreen Yeo
 
Building Services ll Assignment
Building Services ll AssignmentBuilding Services ll Assignment
Building Services ll AssignmentDoreen Yeo
 
Management Science Report
Management Science ReportManagement Science Report
Management Science ReportDoreen Yeo
 
Site surveying report 2
Site surveying report 2Site surveying report 2
Site surveying report 2Doreen Yeo
 
Site surveying report 1
Site surveying report 1Site surveying report 1
Site surveying report 1Doreen Yeo
 
Stormwater management presentation slides
Stormwater management presentation slidesStormwater management presentation slides
Stormwater management presentation slidesDoreen Yeo
 

More from Doreen Yeo (20)

Value management presentation slides
Value management presentation slidesValue management presentation slides
Value management presentation slides
 
Project management assignment slides
Project management assignment slidesProject management assignment slides
Project management assignment slides
 
CIPAA presentation
CIPAA presentationCIPAA presentation
CIPAA presentation
 
Financial Management Report
Financial Management ReportFinancial Management Report
Financial Management Report
 
CSI Report
CSI ReportCSI Report
CSI Report
 
BE Cost Plan
BE Cost Plan BE Cost Plan
BE Cost Plan
 
BE presentation slides
BE presentation slidesBE presentation slides
BE presentation slides
 
BE cost appraisal
BE cost appraisalBE cost appraisal
BE cost appraisal
 
Estimating seminar 2 glazing answer
Estimating seminar 2 glazing answerEstimating seminar 2 glazing answer
Estimating seminar 2 glazing answer
 
Estimating seminar 1 slides
Estimating seminar 1 slidesEstimating seminar 1 slides
Estimating seminar 1 slides
 
Assignment ceiling finishes
Assignment ceiling finishesAssignment ceiling finishes
Assignment ceiling finishes
 
PP1 report
PP1 reportPP1 report
PP1 report
 
PP1 assignment presentation slides
PP1 assignment presentation slidesPP1 assignment presentation slides
PP1 assignment presentation slides
 
Software Application presentation slides
Software Application presentation slidesSoftware Application presentation slides
Software Application presentation slides
 
Measurement IV assignment presentation slides
Measurement IV assignment presentation slides Measurement IV assignment presentation slides
Measurement IV assignment presentation slides
 
Building Services ll Assignment
Building Services ll AssignmentBuilding Services ll Assignment
Building Services ll Assignment
 
Management Science Report
Management Science ReportManagement Science Report
Management Science Report
 
Site surveying report 2
Site surveying report 2Site surveying report 2
Site surveying report 2
 
Site surveying report 1
Site surveying report 1Site surveying report 1
Site surveying report 1
 
Stormwater management presentation slides
Stormwater management presentation slidesStormwater management presentation slides
Stormwater management presentation slides
 

Recently uploaded

ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupJonathanParaisoCruz
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfadityarao40181
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaVirag Sontakke
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersSabitha Banu
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxsocialsciencegdgrohi
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceSamikshaHamane
 

Recently uploaded (20)

ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized Group
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdf
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of India
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginners
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in Pharmacovigilance
 

Pp2 coursework 2 brief

  • 1. SCHOOL OF ARCHITECTURE · BUILDING · DESIGN Centre for Modern Architecture Studies in Southeast Asia Bachelor of Quantity Surveying (Honours) PROFESSIONAL PRACTICE [QSB 3614] 1. This assignment shall make up 15% weightage of the final marks. 2. This is a group assignment and shall be submitted in groups of 6 students. 3. Dateline for submission of this Coursework No. 2 is on or before 30th October 2017. Coursework No. 2 – Preparation of Final Account. You are appointed as the consulting Quantity Surveyor for a apartment project based on PAM Form of Contract 2006 (With Quantities). The summary of the Contract Sum is as follows: Bill No. 1 – Preliminaries RM 2,250,000.00 Bill No. 2 – Building Works RM 31,450,000.00 Bill No. 3 – Local Infrastructure Works RM 6,130,000.00 Bill No. 4 – P.C. and Provisional Sums RM 7,870,000.00 Contract Sum RM 47,700,000.00 Question 1. The tender drawings shows the apartment entrance arch with guardhouse but no details were provided. The Architect had suggested that these items be listed as Provisional Sum. However you have forgot about this item and did not include it in your tender document. The contract was awarded without it. The director would also like to know the significance and implications of this omission by their office. In addition, you are required to prepare a report to your director, explaining briefly the adjustments of the essential elements in your preparation of this project’s final account. (25 marks) Question 2. In accordance with clause 30.10 of the contract, the contractor duly submitted his Final Accounts within 6 months after the issuance of the Certificate of Practical Completion. You are then required to assess this application and prepare the Final Account for the apartment project based of the following valuations and adjustments made to the Contract Sum: (35 marks) Information provided are as follows: a. The Architect had granted the Contractor’s first application for extension of time and approved additional insurance premium amounting to RM 10,000.00 in accordance with clause 24 of the contract due to the delay in the completion of the works caused by the Employer’s late decision on the toilet design. 
 
 In his second application for extension of time, the Contractor submitted an loss and expense claim for RM200,000.00 in his Final Accounts to you. Since the delay event is 1
  • 2. not a relevant event listed in Clause 23.8, the Architect had rejected the Contractor’s second application. b. There are four variation orders carried out by the Contractor: Addition Omission i. Variation Order No. 1: RM 300,000.00 RM 200,000.00 Changes of toilet layout to suit Employer’s requirements. ii. Variation Order No. 2: RM 400,000.00 - New lift lobby at entrance. iii. Variation Order No. 3: Changes from premix roads RM 1,100,000.00 RM 900,000.00 to precast concrete paver blocks iv. Variation Order No. 4: Omission of glass partitions - RM 96,000.00 c. The following are the nominated sub-contractor’s accounts: Original P.C. & NSC’s Provisional Sums final account i. Lift Services: RM 1,700,000.00 RM 1,500,000.00 Profit @ 2% RM 34,000.00 Attendance as item RM 34,000.00 ii. Air Conditioning Services: RM 1,200,000.00 RM 1,000,000.00 Profit @ 2% RM 24,000.00 Attendance as item RM 24,000.00 iii. Electrical Services: RM 1,600,000.00 RM 2,100,000.00 Profit @ 2% RM 32,000.00 Attendance as item RM 32,000.00 iv. Provisional Sums: Entrance Porch RM 1,270,000.00 RM 1,050,000.00 RM 6,670,000.00
 2
  • 3. Question 3. Explain the basis on how the following variations may be finalised and priced during the Final Account stage: a. Relocation of an already installed timber door including sealing up the wall opening. Agreed at the site meeting for Contractor to claim based on Dayworks for labour, material and plant. (10 marks) b. Contractor need to provide computer equipment in the Preliminaries section but item was left unpriced, i.e. BQ item was left blank in the rate/amount column in the contract document. Subsequently, this item was omitted by the Architect. (10 marks) c. A wash trough as required and priced in the Preliminaries section was not constructed due to site constraints imposed later by the Employer. However, the vehicles leaving the site during construction were always kept clean including the public roads using water jet washing and full-timed workers. (10 marks) d. Mistake was made in the price for excavation through rocks at RM 15 per m3. Item was not rationalised during contract documentation. However, original quantity in BQ is 100 m3 but re-measured quantity is 2,000 m3. The Contractor submitted a claim for revised rates of RM 150 per m3 for the total quantity of 2,000 m3. (10 marks) 3