1 of 4
211-C01
SPI Week NO:
Status Date (G): 26-May-12 (H): 05 Rajab 1433 0.75 8
PM: Mohd Ali Planner: Allan Leyte
Contract Title: Rabigh II Royal Commision Early Infrastracture Works SCHEDULE ACTUAL VARIANCE
Contractor: XXX 1.50% 1.12% -0.38%
CONTRACTOR STATUS REPORT
SCOPE OF WORK :
The scope of works are:Utility Corridor:
Site works preparation and earthworks, Access roads to lift stations,
Potable, Fire and sanitary Sewer System including Lift Stations,
Security Fence, Electromechanical, electrical power distribution
system and Telecommunication works. Porta Cabin Building:
Installation of Portacabin buildings including related Civil,
Mechanical, Electrical works. Sewer, Potable and Fire water system,
electrical Power and Area lighting sytem and Chain link Fence for
the labor camp.
SCHEDULE DATA :
Item
No.
Contractual Milestone Baseline
Days
Change
Remarks
Contract Duration Current Contract Weeks : 8 of 156 156 0
Award Date 9-Apr-12 9-Apr-12 A 0
Notice To Proceed 9-Apr-12 9-Apr-12 A 0
1 Complete Mobilization and Construction Start 11-Jun-12 11-Jun-12 F 0 Waiting for the availability of
laydown Area
2 Complete Existing Conditions Survey and Submission of Reports and Site Setting out 9-Jul-12 9-Jul-12 F 0
3 Complete Security Fence 26-Aug-12 26-Aug-12 F 0
4 Complete Porta cabin buildings including fence around them 6-Jan-14 6-Jan-14 F 0
5 Complete infrastracture works for Porta Cabin buildings 7-Jul-14 7-Jul-14 F 0
6 Complete all utilities: MV Power, Sanitary Wastewater, Potable Water, Telecom, within utility
corridor, including sanitary lift stations and marl road
8-Dec-14 8-Dec-14 F 0
7 Complete All Remaining Work including Testing & Commissioning, Clean-up, Closeout
Documentation and ready for Initial Acceptance
9-Mar-15 9-Mar-15 F 0
8 Complete Demobilization 6-Apr-15 6-Apr-15 F 0
Contractor's
Forecast
156
Penalty Milestones
ENVIRONMENT, SAFETY and HEALTH :
Tool box Topic Next Week:
Previous This Period Total
Health & Safety
Lost Workday Cases (LWDC) 0 0 0
First Aid (FA) 0 0 0
Near Miss Incidents 0 0 0
Contract Man-hours 1,915 620 2,535
Environmental Issues
Major Environmental Incident 0 0 0
Minor Environmental Incident 0 0 0
Schedule to date 1.50% 0.66% 0.84%
Actual to date 1.12% 0.50% 0.62%
Variance (0.38%) (0.16%) (0.22%)
Progress ( % )
Based on Earned Cost
To date This Period Previous
A. Manual Non Saudi 10 7 (3)
B. Sub-Con Manual 0 0 0
B. SN Manual 2 2 0
Total Manual 12 9 (3)
D. Non-Manual Non Saudi 17 1 (16)
E. Sub-Con Non-Manual 0 0 0
E. SN Non-Manual 1 1 0
Total Non-Manual 18 2 (16)
30 11 (19)
10.00% 27.27% 17.27%
Manpower Schedule Actual Variance
TOTAL MANPOWER
Saudi National Percentage (SC-46)
 Data Date
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
7-Apr-12
5-May-12
2-Jun-12
30-Jun-12
28-Jul-12
25-Aug-12
22-Sep-12
20-Oct-12
17-Nov-12
15-Dec-12
12-Jan-13
9-Feb-13
9-Mar-13
6-Apr-13
4-May-13
1-Jun-13
29-Jun-13
27-Jul-13
24-Aug-13
21-Sep-13
19-Oct-13
16-Nov-13
14-Dec-13
11-Jan-14
8-Feb-14
8-Mar-14
5-Apr-14
3-May-14
31-May-14
28-Jun-14
26-Jul-14
23-Aug-14
20-Sep-14
18-Oct-14
15-Nov-14
13-Dec-14
10-Jan-15
7-Feb-15
7-Mar-15
4-Apr-15
Week Beginning
Early Curve
Critical Path
Actual
Forecast
Data Date
Percent Complete Progress
STATUSAT :26-May-12
Schedule Actual Variance
1.50% 1.12% (0.38%)
211-C01
PM: Mohd Ali Planner: Allan Leyte Status Date (G): 26-May-12
Contract Title: Early Infrastracture Works Status date (H): 05 Rajab 1433
Contractor: XXX
CONTRACTOR STATUS REPORT
CONTRACTOR'S SUBMITTALS :
Technical Submittals Code 1 Code 2 Code 3 Code 4 Technical Queries Total Submitted to date Answered to date Critical TQ Pending
3 3 2 0
Total Required Submitted To Date Under Review Remaining
TBD 29 21
Materials
Chain Link fence 01-May-12 A 01-May-12 A 09-Jun-12 S
uPVC Pipes 03-May-12 A 17-May-12 S 11-Jun-12 S
Steel Reinforcement bars 05-May-12 A 05-May-12 A 06-Jul-12 S
Concrete Mix Design 06-May-12 A 17-May-12 S 18-Jun-12 S
Butterfly valve 09-May-12 A 14-Jun-12 S 13-Jul-12 S
Air release valve 09-May-12 A 14-Jun-12 S 13-Jul-12 S
Gate valve 09-May-12 A 14-Jun-12 S 16-Jul-12 S
Fire Hydrant 09-May-12 A 28-Jun-12 S 16-Jul-12 S
PVC conduits 22-May-12 A 24-May-12 S 19-Jun-12 S
PVC fittings 13-May-12 A 28-Jun-12 S 27-Jul-12 S
Grounding rods 23-May-12 A 24-May-12 S 15-Jun-12 S
Legend:A:Actual F:Forecast S:Schedule
PROCUREMENT STATISTICS:
Submittal Date Approval Date P.O. Date Delivery Date Req'd Date
Major Construction Activities: UPCOMING ACTIVITIES for NEXT PERIOD:
PROGRESS HIGHLIGHTS for THIS PERIOD
WAITING FOR THE AVAILABILITY OF LAYDOWN AREA
CRITICAL ANALYSIS MITIGATION
PROGRESS HIGHLIGHTS
Prev. Month This Month To date
143,561 0 0 0 0 0 0 143,561
INVOICE ANALYSIS (SR x 1,000) :
Current
Contract Value
Paid
Previous Years
Paid Year to
Date
Paid
Year To Date
Invoice Status Cost to go
143,561 0 143,561 0 143,561 0 143,561 0.0%
% Change
BUDGET STATUS (SR x 1,000) :
Award
Value
Approved
Changes
Current
Contract Value
Approved
RFC's
Pending
Contract Value
Pending
Trends
Forecast
Contract Value
Status Date (G): (H): 05 Rajab 1433
PM: Mohd Ali Planner: Allan Leyte
Contract Title: Rabigh II Royal Commision Early Infrastracture Works
Contractor: XXX
MEETING MINUTES INPUT 211-C01
26-May-2012
Week 8
0 10 20 30 40 50 60 70 80 90
CONTRACTOR'S SUBMITTALS :
Technical Queries Total Submittedtodate Answered to date Critical TQ Pending Materials
0 Chain Linkfence 01-May-12 A 01-May-12 A 09-Jun-12 S
uPVCPipes 03-May-12 A 17-May-12 S 11-Jun-12 S
Steel Reinforcementbars 05-May-12 A 05-May-12 A 06-Jul-12 S
PROCUREMENT STATISTICS:
SubmittalDate ApprovalDate P.O.Date Delivery Date Req'dDate
CONTRACTOR'S SUBMITTALS :
Technical Submittals Code 1 Code 2 Code 3 Code 4
3 3 2
Total Required Submitted To Date Under Review Remaining
TBD 29 21
Progress ( % )
Manpower
Previous This Period Total
Health & Safety
Lost Workday Cases (LWDC) 0 0 0
First Aid (FA) 0 0 0
Near Miss Incidents 0 0 0
Contract Man-hours 1,915 620 2,535
Environmental Issues
Major Environmental Incident 0 0 0
Minor Environmental Incident 0 0 0
Technical Queries Total Submitted to date Answered to date Critical TQ Pending Materials
0 Chain Link fence 01-May-12 A 01-May-12 A 09-Jun-12 S
uPVC Pipes 03-May-12 A 17-May-12 S 11-Jun-12 S
Steel Reinforcement bars 05-May-12 A 05-May-12 A 06-Jul-12 S
Concrete Mix Design 06-May-12 A 17-May-12 S 18-Jun-12 S
Butterfly valve 09-May-12 A 14-Jun-12 S 13-Jul-12 S
Air release valve 09-May-12 A 14-Jun-12 S 13-Jul-12 S
Gate valve 09-May-12 A 14-Jun-12 S 16-Jul-12 S
Fire Hydrant 09-May-12 A 28-Jun-12 S 16-Jul-12 S
PVC conduits 22-May-12 A 24-May-12 S 19-Jun-12 S
PVC fittings 13-May-12 A 28-Jun-12 S 27-Jul-12 S
Grounding rods 23-May-12 A 24-May-12 S 15-Jun-12 S
Legend:A:Actual F:Forecast S:Schedule
PROCUREMENT STATISTICS:
Submittal Date Approval Date P.O. Date Delivery Date Req'd Date
Upcoming
Schedule to date 1.50% 0.66% 0.84%
Actual to date 1.12% 0.50% 0.62%
Variance (0.38%) (0.16%) (0.22%)
2nd Week
Progress ( % )
Based on Earned Cost
To date This Period Previous
1st Week
1.83% 2.21%
0.00% 0.00%
(1.83%) (2.21%)
A. Manual Non Saudi 10 7 (3)
B. Sub-Con Manual 0 0 0
B. SN Manual 2 2 0
Total Manual 12 9 (3)
D. Non-Manual Non Saudi 17 1 (16)
E. Sub-Con Non-Manual 0 0 0
E. SN Non-Manual 1 1 0
Total Non-Manual 18 2 (16)
30 11 (19)
Manpower Schedule Actual Variance
TOTAL MANPOWER
BI-WEEKLY PROGRESS REPORT
XXX
CONTRACT No. : 211-C01
Early Infrastracture Works
Report Date :
Week : 8 of 156
A. Upcoming
Schedule to date 1.50% 0.66% 0.84%
Actual to date 1.12% 0.50% 0.62%
Variance (0.38%) (0.16%) (0.22%)
B. Upcoming
Schedule to date 2,158,974 950,614 1,208,360
Earned to date 1,609,901 715,511 894,389
Variance (549,074) (235,103) (313,971)
C. Upcoming
A. Manual Non Saudi 10 7 (3)
B. Sub-Con Manual 0 0 0
B. SN Manual 2 2 0
Total Manual 12 9 (3)
D. Non-Manual Non Saudi 17 1 (16)
E. Sub-Con Non-Manual 0 0 0
E. SN Non-Manual 1 1 0
Total Non-Manual 18 2 (16)
30 11 (19)
10.00% 27.27% 17.27% 0%
D. Baseline
Weeks 
Ahead/Behind
Contract Duration Current Contract Weeks : 8 of 156 156 156 0
9-Apr-12 9-Apr-12 A 0
1 11-Jun-12 11-Jun-12 F 0
2 9-Jul-12 9-Jul-12 F 0
3 26-Aug-12 26-Aug-12 F 0
4 6-Jan-14 6-Jan-14 F 0
5 7-Jul-14 7-Jul-14 F 0
6 8-Dec-14 8-Dec-14 F 0
7 9-Mar-15 9-Mar-15 F 0
8 6-Apr-15 6-Apr-15 F 0
E. Progress Highlights for period up to May 25, 2012
01
02
03
F. Risks / Challenges / Issues as of May 25, 2012
01
02
G. Upcoming Activities from the Period of 26 May '12 to 8 June '12
01
H. Material Procurement Schedule as of
Submittal Date Approval Date P.O. Date Required Date
01-May-12 01-May-12
03-May-12
05-May-12 05-May-12
06-May-12
09-May-12
09-May-12
09-May-12
09-May-12
22-May-12
13-May-12
23-May-12Grounding rods
Air release valve
Gate valve
Fire Hydrant
PVC conduits
PVC fittings
Steel Reinforcement bars
Concrete Mix Design
Butterfly valve
Materials Delivery Date
Chain Link fence
uPVC Pipes
Complete All Remaining Work including Testing & Commissioning, Clean-up,
Complete Demobilization
Complete Existing Conditions Survey and Submission of Reports and Site Setting out
Complete Security Fence
Complete Porta cabin buildings including fence around them
Complete infrastracture works for Porta Cabin buildings
Complete all utilities: MV Power, Sanitary Wastewater, Potable Water, Telecom,
Contractor's
Forecast
Notice To Proceed
Complete Mobilization and Construction Start
Major Contract Evets/Milestones
Saudi National Percentage (SC-46)
1 3
18 13
TOTAL MANPOWER 30 34
12 21
17 10
0 0
10 18
0 0
2 3
Manpower Schedule Actual Variance
1st Week 2nd Week
2,634,281 3,171,044
0 0
(2,634,281) (3,171,044)
Progress ( SR ) Earned Cost To date This Period Previous
1st Week 2nd Week
1.83% 2.21%
0.00% 0.00%
(1.83%) (2.21%)
2nd Week
Progress ( % )
Based on Earned Cost
To date This Period Previous
1st Week
0% 5% 10% 15% 20% 25% 30% 35% 40% 45% 50% 55% 60% 65% 70% 75% 80% 85% 90% 95% 100%
Actual to Date
Schedule to Date
0 10 20 30 40 50 60 70 80 90

More Related Content

What's hot

61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 2014112961T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
James Zhang (Chi, Zhang)
 

What's hot (6)

Steven Vukusic Resume
Steven Vukusic ResumeSteven Vukusic Resume
Steven Vukusic Resume
 
Land Development Update: Oct. 8, 2015
Land Development Update: Oct. 8, 2015Land Development Update: Oct. 8, 2015
Land Development Update: Oct. 8, 2015
 
Abdul basit resume
Abdul basit resumeAbdul basit resume
Abdul basit resume
 
Land Development Update-NAIOP/NVBIA Joint Meeting: Dec. 10, 2015
Land Development Update-NAIOP/NVBIA Joint Meeting: Dec. 10, 2015Land Development Update-NAIOP/NVBIA Joint Meeting: Dec. 10, 2015
Land Development Update-NAIOP/NVBIA Joint Meeting: Dec. 10, 2015
 
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 2014112961T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
 
Foundations for New Champlain Bridge Corridor Project
Foundations for New Champlain Bridge Corridor ProjectFoundations for New Champlain Bridge Corridor Project
Foundations for New Champlain Bridge Corridor Project
 

Similar to Wreport

Power Point BLCC End of year Review
Power Point BLCC End of year ReviewPower Point BLCC End of year Review
Power Point BLCC End of year Review
Tom Atkinson
 
243-249 MANN STREET GOSFORD 1 s
243-249 MANN STREET GOSFORD 1 s243-249 MANN STREET GOSFORD 1 s
243-249 MANN STREET GOSFORD 1 s
Mike Darwich
 
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityHSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
Roumik Mukherjee
 
Final Majarrah rev 0
Final Majarrah rev 0Final Majarrah rev 0
Final Majarrah rev 0
Ahmed Mehrem
 

Similar to Wreport (20)

KVMRT Dashboard V2 July 16.pdf
KVMRT Dashboard V2 July 16.pdfKVMRT Dashboard V2 July 16.pdf
KVMRT Dashboard V2 July 16.pdf
 
Power Point BLCC End of year Review
Power Point BLCC End of year ReviewPower Point BLCC End of year Review
Power Point BLCC End of year Review
 
Weekly report no 19
Weekly report no 19Weekly report no 19
Weekly report no 19
 
2022-01-13-ALALAMEEN 08-WR08.docx
2022-01-13-ALALAMEEN 08-WR08.docx2022-01-13-ALALAMEEN 08-WR08.docx
2022-01-13-ALALAMEEN 08-WR08.docx
 
Monthly Progress Report No.05 - June-2012
Monthly Progress Report No.05 - June-2012Monthly Progress Report No.05 - June-2012
Monthly Progress Report No.05 - June-2012
 
Presentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxPresentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptx
 
C&I July-2022.pptx
C&I July-2022.pptxC&I July-2022.pptx
C&I July-2022.pptx
 
Report for po no 7400005491.docx
Report for po no 7400005491.docxReport for po no 7400005491.docx
Report for po no 7400005491.docx
 
243-249 MANN STREET GOSFORD 1 s
243-249 MANN STREET GOSFORD 1 s243-249 MANN STREET GOSFORD 1 s
243-249 MANN STREET GOSFORD 1 s
 
Departmental Briefing to Secretary Works on 08-02-2023.pptx
Departmental Briefing to Secretary Works on 08-02-2023.pptxDepartmental Briefing to Secretary Works on 08-02-2023.pptx
Departmental Briefing to Secretary Works on 08-02-2023.pptx
 
StudentRecord
StudentRecordStudentRecord
StudentRecord
 
May 16, 2012 Transportation Interim Committee Presentations
May 16, 2012 Transportation Interim Committee PresentationsMay 16, 2012 Transportation Interim Committee Presentations
May 16, 2012 Transportation Interim Committee Presentations
 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptx
 
B12
B12B12
B12
 
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
 
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule finalSeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
 
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityHSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
 
Final Majarrah rev 0
Final Majarrah rev 0Final Majarrah rev 0
Final Majarrah rev 0
 
SAG NPD PPT APR2022 (00000002) (1).pptx
SAG NPD PPT  APR2022 (00000002) (1).pptxSAG NPD PPT  APR2022 (00000002) (1).pptx
SAG NPD PPT APR2022 (00000002) (1).pptx
 
Projects Review Report
Projects  Review ReportProjects  Review Report
Projects Review Report
 

More from Allan Leyte

Construction Methodology Scheduling1
Construction Methodology Scheduling1Construction Methodology Scheduling1
Construction Methodology Scheduling1
Allan Leyte
 
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Allan Leyte
 
Sample MSProject with 16 DivisionFormat Variation(EOT)
Sample MSProject with 16 DivisionFormat Variation(EOT)Sample MSProject with 16 DivisionFormat Variation(EOT)
Sample MSProject with 16 DivisionFormat Variation(EOT)
Allan Leyte
 
BHP01-0 Bouly baseline on MSproject Format
BHP01-0 Bouly baseline on MSproject FormatBHP01-0 Bouly baseline on MSproject Format
BHP01-0 Bouly baseline on MSproject Format
Allan Leyte
 
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Allan Leyte
 
PRODUCTION RATE APPX. NEW
PRODUCTION RATE APPX. NEWPRODUCTION RATE APPX. NEW
PRODUCTION RATE APPX. NEW
Allan Leyte
 
Sample of Structural Steel Scheduling
Sample of Structural Steel SchedulingSample of Structural Steel Scheduling
Sample of Structural Steel Scheduling
Allan Leyte
 
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Allan Leyte
 
Visio-Planning FlowChart-3
Visio-Planning FlowChart-3Visio-Planning FlowChart-3
Visio-Planning FlowChart-3
Allan Leyte
 
Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016
Allan Leyte
 
Booster Pump cause of delay analysis
Booster Pump cause of delay analysisBooster Pump cause of delay analysis
Booster Pump cause of delay analysis
Allan Leyte
 
Sample Bidcom Presentation - Structural Works 12-28-11
Sample Bidcom Presentation - Structural Works 12-28-11Sample Bidcom Presentation - Structural Works 12-28-11
Sample Bidcom Presentation - Structural Works 12-28-11
Allan Leyte
 
Scheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPMScheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPM
Allan Leyte
 
Offshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocolOffshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocol
Allan Leyte
 
Town Center presentation
Town Center presentationTown Center presentation
Town Center presentation
Allan Leyte
 

More from Allan Leyte (18)

Construction Methodology Scheduling1
Construction Methodology Scheduling1Construction Methodology Scheduling1
Construction Methodology Scheduling1
 
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
 
Sample MSProject with 16 DivisionFormat Variation(EOT)
Sample MSProject with 16 DivisionFormat Variation(EOT)Sample MSProject with 16 DivisionFormat Variation(EOT)
Sample MSProject with 16 DivisionFormat Variation(EOT)
 
BHP01-0 Bouly baseline on MSproject Format
BHP01-0 Bouly baseline on MSproject FormatBHP01-0 Bouly baseline on MSproject Format
BHP01-0 Bouly baseline on MSproject Format
 
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
 
WEIGHTING TABLE
WEIGHTING TABLEWEIGHTING TABLE
WEIGHTING TABLE
 
PRODUCTION RATE APPX. NEW
PRODUCTION RATE APPX. NEWPRODUCTION RATE APPX. NEW
PRODUCTION RATE APPX. NEW
 
Sample of Structural Steel Scheduling
Sample of Structural Steel SchedulingSample of Structural Steel Scheduling
Sample of Structural Steel Scheduling
 
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
 
p3 s-curves
p3 s-curvesp3 s-curves
p3 s-curves
 
Visio-Planning FlowChart-3
Visio-Planning FlowChart-3Visio-Planning FlowChart-3
Visio-Planning FlowChart-3
 
Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016
 
Booster Pump cause of delay analysis
Booster Pump cause of delay analysisBooster Pump cause of delay analysis
Booster Pump cause of delay analysis
 
Sample Bidcom Presentation - Structural Works 12-28-11
Sample Bidcom Presentation - Structural Works 12-28-11Sample Bidcom Presentation - Structural Works 12-28-11
Sample Bidcom Presentation - Structural Works 12-28-11
 
Scheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPMScheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPM
 
Offshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocolOffshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocol
 
progress photos
progress photosprogress photos
progress photos
 
Town Center presentation
Town Center presentationTown Center presentation
Town Center presentation
 

Wreport

  • 1. 211-C01 SPI Week NO: Status Date (G): 26-May-12 (H): 05 Rajab 1433 0.75 8 PM: Mohd Ali Planner: Allan Leyte Contract Title: Rabigh II Royal Commision Early Infrastracture Works SCHEDULE ACTUAL VARIANCE Contractor: XXX 1.50% 1.12% -0.38% CONTRACTOR STATUS REPORT SCOPE OF WORK : The scope of works are:Utility Corridor: Site works preparation and earthworks, Access roads to lift stations, Potable, Fire and sanitary Sewer System including Lift Stations, Security Fence, Electromechanical, electrical power distribution system and Telecommunication works. Porta Cabin Building: Installation of Portacabin buildings including related Civil, Mechanical, Electrical works. Sewer, Potable and Fire water system, electrical Power and Area lighting sytem and Chain link Fence for the labor camp. SCHEDULE DATA : Item No. Contractual Milestone Baseline Days Change Remarks Contract Duration Current Contract Weeks : 8 of 156 156 0 Award Date 9-Apr-12 9-Apr-12 A 0 Notice To Proceed 9-Apr-12 9-Apr-12 A 0 1 Complete Mobilization and Construction Start 11-Jun-12 11-Jun-12 F 0 Waiting for the availability of laydown Area 2 Complete Existing Conditions Survey and Submission of Reports and Site Setting out 9-Jul-12 9-Jul-12 F 0 3 Complete Security Fence 26-Aug-12 26-Aug-12 F 0 4 Complete Porta cabin buildings including fence around them 6-Jan-14 6-Jan-14 F 0 5 Complete infrastracture works for Porta Cabin buildings 7-Jul-14 7-Jul-14 F 0 6 Complete all utilities: MV Power, Sanitary Wastewater, Potable Water, Telecom, within utility corridor, including sanitary lift stations and marl road 8-Dec-14 8-Dec-14 F 0 7 Complete All Remaining Work including Testing & Commissioning, Clean-up, Closeout Documentation and ready for Initial Acceptance 9-Mar-15 9-Mar-15 F 0 8 Complete Demobilization 6-Apr-15 6-Apr-15 F 0 Contractor's Forecast 156 Penalty Milestones ENVIRONMENT, SAFETY and HEALTH : Tool box Topic Next Week: Previous This Period Total Health & Safety Lost Workday Cases (LWDC) 0 0 0 First Aid (FA) 0 0 0 Near Miss Incidents 0 0 0 Contract Man-hours 1,915 620 2,535 Environmental Issues Major Environmental Incident 0 0 0 Minor Environmental Incident 0 0 0 Schedule to date 1.50% 0.66% 0.84% Actual to date 1.12% 0.50% 0.62% Variance (0.38%) (0.16%) (0.22%) Progress ( % ) Based on Earned Cost To date This Period Previous A. Manual Non Saudi 10 7 (3) B. Sub-Con Manual 0 0 0 B. SN Manual 2 2 0 Total Manual 12 9 (3) D. Non-Manual Non Saudi 17 1 (16) E. Sub-Con Non-Manual 0 0 0 E. SN Non-Manual 1 1 0 Total Non-Manual 18 2 (16) 30 11 (19) 10.00% 27.27% 17.27% Manpower Schedule Actual Variance TOTAL MANPOWER Saudi National Percentage (SC-46)  Data Date 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 7-Apr-12 5-May-12 2-Jun-12 30-Jun-12 28-Jul-12 25-Aug-12 22-Sep-12 20-Oct-12 17-Nov-12 15-Dec-12 12-Jan-13 9-Feb-13 9-Mar-13 6-Apr-13 4-May-13 1-Jun-13 29-Jun-13 27-Jul-13 24-Aug-13 21-Sep-13 19-Oct-13 16-Nov-13 14-Dec-13 11-Jan-14 8-Feb-14 8-Mar-14 5-Apr-14 3-May-14 31-May-14 28-Jun-14 26-Jul-14 23-Aug-14 20-Sep-14 18-Oct-14 15-Nov-14 13-Dec-14 10-Jan-15 7-Feb-15 7-Mar-15 4-Apr-15 Week Beginning Early Curve Critical Path Actual Forecast Data Date Percent Complete Progress STATUSAT :26-May-12 Schedule Actual Variance 1.50% 1.12% (0.38%)
  • 2. 211-C01 PM: Mohd Ali Planner: Allan Leyte Status Date (G): 26-May-12 Contract Title: Early Infrastracture Works Status date (H): 05 Rajab 1433 Contractor: XXX CONTRACTOR STATUS REPORT CONTRACTOR'S SUBMITTALS : Technical Submittals Code 1 Code 2 Code 3 Code 4 Technical Queries Total Submitted to date Answered to date Critical TQ Pending 3 3 2 0 Total Required Submitted To Date Under Review Remaining TBD 29 21 Materials Chain Link fence 01-May-12 A 01-May-12 A 09-Jun-12 S uPVC Pipes 03-May-12 A 17-May-12 S 11-Jun-12 S Steel Reinforcement bars 05-May-12 A 05-May-12 A 06-Jul-12 S Concrete Mix Design 06-May-12 A 17-May-12 S 18-Jun-12 S Butterfly valve 09-May-12 A 14-Jun-12 S 13-Jul-12 S Air release valve 09-May-12 A 14-Jun-12 S 13-Jul-12 S Gate valve 09-May-12 A 14-Jun-12 S 16-Jul-12 S Fire Hydrant 09-May-12 A 28-Jun-12 S 16-Jul-12 S PVC conduits 22-May-12 A 24-May-12 S 19-Jun-12 S PVC fittings 13-May-12 A 28-Jun-12 S 27-Jul-12 S Grounding rods 23-May-12 A 24-May-12 S 15-Jun-12 S Legend:A:Actual F:Forecast S:Schedule PROCUREMENT STATISTICS: Submittal Date Approval Date P.O. Date Delivery Date Req'd Date Major Construction Activities: UPCOMING ACTIVITIES for NEXT PERIOD: PROGRESS HIGHLIGHTS for THIS PERIOD WAITING FOR THE AVAILABILITY OF LAYDOWN AREA CRITICAL ANALYSIS MITIGATION PROGRESS HIGHLIGHTS Prev. Month This Month To date 143,561 0 0 0 0 0 0 143,561 INVOICE ANALYSIS (SR x 1,000) : Current Contract Value Paid Previous Years Paid Year to Date Paid Year To Date Invoice Status Cost to go 143,561 0 143,561 0 143,561 0 143,561 0.0% % Change BUDGET STATUS (SR x 1,000) : Award Value Approved Changes Current Contract Value Approved RFC's Pending Contract Value Pending Trends Forecast Contract Value
  • 3. Status Date (G): (H): 05 Rajab 1433 PM: Mohd Ali Planner: Allan Leyte Contract Title: Rabigh II Royal Commision Early Infrastracture Works Contractor: XXX MEETING MINUTES INPUT 211-C01 26-May-2012 Week 8 0 10 20 30 40 50 60 70 80 90 CONTRACTOR'S SUBMITTALS : Technical Queries Total Submittedtodate Answered to date Critical TQ Pending Materials 0 Chain Linkfence 01-May-12 A 01-May-12 A 09-Jun-12 S uPVCPipes 03-May-12 A 17-May-12 S 11-Jun-12 S Steel Reinforcementbars 05-May-12 A 05-May-12 A 06-Jul-12 S PROCUREMENT STATISTICS: SubmittalDate ApprovalDate P.O.Date Delivery Date Req'dDate CONTRACTOR'S SUBMITTALS : Technical Submittals Code 1 Code 2 Code 3 Code 4 3 3 2 Total Required Submitted To Date Under Review Remaining TBD 29 21 Progress ( % ) Manpower Previous This Period Total Health & Safety Lost Workday Cases (LWDC) 0 0 0 First Aid (FA) 0 0 0 Near Miss Incidents 0 0 0 Contract Man-hours 1,915 620 2,535 Environmental Issues Major Environmental Incident 0 0 0 Minor Environmental Incident 0 0 0 Technical Queries Total Submitted to date Answered to date Critical TQ Pending Materials 0 Chain Link fence 01-May-12 A 01-May-12 A 09-Jun-12 S uPVC Pipes 03-May-12 A 17-May-12 S 11-Jun-12 S Steel Reinforcement bars 05-May-12 A 05-May-12 A 06-Jul-12 S Concrete Mix Design 06-May-12 A 17-May-12 S 18-Jun-12 S Butterfly valve 09-May-12 A 14-Jun-12 S 13-Jul-12 S Air release valve 09-May-12 A 14-Jun-12 S 13-Jul-12 S Gate valve 09-May-12 A 14-Jun-12 S 16-Jul-12 S Fire Hydrant 09-May-12 A 28-Jun-12 S 16-Jul-12 S PVC conduits 22-May-12 A 24-May-12 S 19-Jun-12 S PVC fittings 13-May-12 A 28-Jun-12 S 27-Jul-12 S Grounding rods 23-May-12 A 24-May-12 S 15-Jun-12 S Legend:A:Actual F:Forecast S:Schedule PROCUREMENT STATISTICS: Submittal Date Approval Date P.O. Date Delivery Date Req'd Date Upcoming Schedule to date 1.50% 0.66% 0.84% Actual to date 1.12% 0.50% 0.62% Variance (0.38%) (0.16%) (0.22%) 2nd Week Progress ( % ) Based on Earned Cost To date This Period Previous 1st Week 1.83% 2.21% 0.00% 0.00% (1.83%) (2.21%) A. Manual Non Saudi 10 7 (3) B. Sub-Con Manual 0 0 0 B. SN Manual 2 2 0 Total Manual 12 9 (3) D. Non-Manual Non Saudi 17 1 (16) E. Sub-Con Non-Manual 0 0 0 E. SN Non-Manual 1 1 0 Total Non-Manual 18 2 (16) 30 11 (19) Manpower Schedule Actual Variance TOTAL MANPOWER
  • 4. BI-WEEKLY PROGRESS REPORT XXX CONTRACT No. : 211-C01 Early Infrastracture Works Report Date : Week : 8 of 156 A. Upcoming Schedule to date 1.50% 0.66% 0.84% Actual to date 1.12% 0.50% 0.62% Variance (0.38%) (0.16%) (0.22%) B. Upcoming Schedule to date 2,158,974 950,614 1,208,360 Earned to date 1,609,901 715,511 894,389 Variance (549,074) (235,103) (313,971) C. Upcoming A. Manual Non Saudi 10 7 (3) B. Sub-Con Manual 0 0 0 B. SN Manual 2 2 0 Total Manual 12 9 (3) D. Non-Manual Non Saudi 17 1 (16) E. Sub-Con Non-Manual 0 0 0 E. SN Non-Manual 1 1 0 Total Non-Manual 18 2 (16) 30 11 (19) 10.00% 27.27% 17.27% 0% D. Baseline Weeks  Ahead/Behind Contract Duration Current Contract Weeks : 8 of 156 156 156 0 9-Apr-12 9-Apr-12 A 0 1 11-Jun-12 11-Jun-12 F 0 2 9-Jul-12 9-Jul-12 F 0 3 26-Aug-12 26-Aug-12 F 0 4 6-Jan-14 6-Jan-14 F 0 5 7-Jul-14 7-Jul-14 F 0 6 8-Dec-14 8-Dec-14 F 0 7 9-Mar-15 9-Mar-15 F 0 8 6-Apr-15 6-Apr-15 F 0 E. Progress Highlights for period up to May 25, 2012 01 02 03 F. Risks / Challenges / Issues as of May 25, 2012 01 02 G. Upcoming Activities from the Period of 26 May '12 to 8 June '12 01 H. Material Procurement Schedule as of Submittal Date Approval Date P.O. Date Required Date 01-May-12 01-May-12 03-May-12 05-May-12 05-May-12 06-May-12 09-May-12 09-May-12 09-May-12 09-May-12 22-May-12 13-May-12 23-May-12Grounding rods Air release valve Gate valve Fire Hydrant PVC conduits PVC fittings Steel Reinforcement bars Concrete Mix Design Butterfly valve Materials Delivery Date Chain Link fence uPVC Pipes Complete All Remaining Work including Testing & Commissioning, Clean-up, Complete Demobilization Complete Existing Conditions Survey and Submission of Reports and Site Setting out Complete Security Fence Complete Porta cabin buildings including fence around them Complete infrastracture works for Porta Cabin buildings Complete all utilities: MV Power, Sanitary Wastewater, Potable Water, Telecom, Contractor's Forecast Notice To Proceed Complete Mobilization and Construction Start Major Contract Evets/Milestones Saudi National Percentage (SC-46) 1 3 18 13 TOTAL MANPOWER 30 34 12 21 17 10 0 0 10 18 0 0 2 3 Manpower Schedule Actual Variance 1st Week 2nd Week 2,634,281 3,171,044 0 0 (2,634,281) (3,171,044) Progress ( SR ) Earned Cost To date This Period Previous 1st Week 2nd Week 1.83% 2.21% 0.00% 0.00% (1.83%) (2.21%) 2nd Week Progress ( % ) Based on Earned Cost To date This Period Previous 1st Week 0% 5% 10% 15% 20% 25% 30% 35% 40% 45% 50% 55% 60% 65% 70% 75% 80% 85% 90% 95% 100% Actual to Date Schedule to Date 0 10 20 30 40 50 60 70 80 90