The New Champlain Bridge is One of the largest
infrastructure projects in north America.
The Bridge will span 3.4 km and connect Montreal
to Brossard. It will replace the existing bridge.
Temporary Foundations are required to support
the construction of the Backspan of the Cable
Stayed portion of the bridge.
• THE CONSTRUCTION OF BACKSPAN TEMPORARY BENTS
FOUNDATIONS BETWEEN MST (MAINSPAN TOWER) AND
PIER W02, LOCATED IN THE SAINT LAWRENCE RIVER, OFF
THE EXISTING DYKE.
• THE FOUNDATIONS DESIGN CALLS FOR DRIVEN H-PILES AND
CONCRETE PILE CAPS AND TIE BEAMS.
• THE TEMPORARY BENTS AND THEIR FOUNDATIONS ARE
LOCATED IN THE RIGHT-OF-WAY OF THE FUTURE BRIDGE,
ON THE WESTERN SIDE OF THE SEAWAY DYKE.
Project Description:
 The Design and Construction of 15 Foundations for the Backspan temporary bents.
Project Deliverables:
 Complete geotechnical study
 Produce design documents and drawings
 Procurement
 Complete construction
 Project Objectives:
• The main objective of our project is to produce all deliverables on time and within budget.
• Perform all work and in conformance with project specification and quality plan.
• Turning in foreseen profit.
 Main Project Success Criteria:
• All the functional requirements of the project should be met.
• Project should be done within the time and budget
• Perform the work to the satisfaction of client.
• Handover and respect milestone dates.
 Project team resources: Daksh Raj Chopra, Rabih Ataya , Harmandeep singh , Harmanjeet
singh parmar
 Date Of Authorization: 22 Feb 2016
 Project Start Date: 1 April 2016
 Date Of Completion: 15 June 2016
 Budget Information: The firm has allocated $315,385 + 20% profit for the project.
 Project Manager: Parth Avinash Chauhan
STRENGTHS:
 Experienced staff
 Reputed Construction Firm
 Expertise in execution of similar projects
 Established and maintained a strong
base
WEAKNESSES:
 Scarce Manpower
 High labor cost
 Lack of modern equipment
OPPORTUNITIES:
 Government support and Tax rebates
 Relation with Client on a big Project
 Work experience
 Growing demand
THREATS:
 Climatic condition
 Increasing labor cost
 Natural calamities
 Exchange rate varies a lot
Rev. Item # Facility CRC Description
Estimated
Qty R1
Estimated
Qty R0
Delta
Unit of
Measure
Direct
Manhours
Permanent
equipment
(1)
Material
(2)
Installation
Hrs+equip.
(3)
Total
(1+2+3)
1.0 12201 21100 Indirect Costs (All other costs are included in direct costs)
1.1 12201 21100 Mobilization 1 1 Lot 4,500.00 $
1.2 12201 21100 Demobilization 1 1 Lot 1,500.00 $
The Bidder must supply the fulll breakdow n of mobilization and demobilization costs w ith its bid.
1.3 12201 21100 Insurance 1 1 Lot
1.4 12201 21100 Temporary Facilities (including but not limited to site offices, trailers, potable
water, power and maintenance)
10 10
week
500.00 $
1.5 12201 21100 Administrative support, technicians, surveyors, supervision, management, etc… 10 10 week 5,000.00 $
For items 1.4 & 1.5, the Bidder must indicate the number of w eeks for w hich this price is
applicable
1.6 12201 21100 Bonds
1.7 12201 21100 Other indirect & general costs not covered above
1.7.1 12201 21100 Define : ______________________________________________________________ 1 1 Lot
1.7.2 12201 21100 Define : ______________________________________________________________ 1 1 Lot
1.7.3 12201 21100 Define: ______________________________________________________________ 1 1 Lot
Subtotal - Indirect Prices 11,500.00 $
2.0 12201 21100 Temporary Foundations
2.1 12201 21100 Foundations for tower type 1
2.1.1 12201 21100 Formwork Installation (foundations & tie-beams) 215 -215 m2
2.1.2 12201 21100 Concrete pouring 120 -120 m3
2.1.3 12201 21100 Stripping 215 -215 m2
2.2 12201 21100 Foundations for tower type 2 &3
2.2.1 12201 21100 Formwork Installation (foundations & tie-beams) 750 740 10 m2 675 20,250.00 47,250.00 67,500.00 $
2.2.2 12201 21100 Concrete pouring 600 530 70 m3 520 36,375.00 36,375.00 $
2.2.3 12201 21100 Stripping 750 740 10 m2 236 16,500.00 16,500.00 $
2.3 12201 21100 Foundations for tower type 4
2.3.1 12201 21100 Formwork Installation (foundations & tie-beams) 660 340 320 m2 594 17,820.00 41,580.00 59,400.00 $
2.3.2 12201 21100 Concrete pouring 390 280 110 m3 349 24,420.00 24,420.00 $
2.3.3 12201 21100 Stripping 660 340 320 m2 207 14,520.00 14,520.00 $
2.4 12201 21100 Foundations for tower type 5
2.4.1 12201 21100 Formwork Installation (foundations & tie-beams) 580 520 60 m2 522 15,660.00 36,540.00 52,200.00 $
2.4.2 12201 21100 Concrete pouring 320 270 50 m3 289 20,210.00 20,210.00 $
2.4.3 12201 21100 Stripping 580 520 60 m2 182 12,760.00 12,760.00 $
Subtotal - Direct Prices 3,574 53,730.00$ 250,155.00$ 303,885.00 $
3,574 53,730.00$ 250,155.00$ 315,385.00 $TOTAL
Discount Rate (Yearly)= 15% Discount Rate (Weekly)= 0.3%
Week 0 1 2 3 4 5 6 7 8 9
Payment $ 75,692.40 $ 75,692.40 $ 75,692.40 $ 75,692.40 $ 75,692.40
Procurement -$ 53,730.00
Labor+Overhead
Milestone 1 -$ 17,443.67 -$ 17,443.67 -$ 17,443.67
Milestone 2 -$ 17,443.67 -$ 17,443.67 -$ 17,443.67
Milestone 3 -$ 17,443.67 -$ 17,443.67 -$ 17,443.67
Milestone 4 -$ 17,443.67 -$ 17,443.67 -$ 17,443.67
Milestone 5 -$ 17,443.67 -$ 17,443.67 -$ 17,443.67
Total -$ 53,730.00 -$ 17,443.67 -$ 17,443.67 $ 40,805.07 -$ 34,887.33 $ 40,805.07 $ 40,805.07 -$ 34,887.33 $ 40,805.07 $ 58,248.73
PV -$ 53,730.00 -$ 17,391.49 -$ 17,339.47 $ 40,440.01 -$ 34,471.81 $ 40,198.46 $ 40,078.23 -$ 34,163.41 $ 39,838.83 $ 56,699.35
NPV $ 60,158.70
 On March 17,2016
 Group members were introduced.
 Background review of project was done.
 Project Charter and Project Scope Statement was discussed and finalized.
 Discussion of project goals and deliverables.
 Assigning responsibilities to each team member and prioritizing tasks.
•
•
•
•
•
•
•
•
•
•
LIKELIHOOD/PROBABILITY
HIGH R6, R7, R9
MEDIUM R1, R5, R10 R4
LOW R2 R3 R8
LOW MEDIUM HIGH
Risk Index Rank Risk Title Category Triggers
R1
7
Increase in raw material cost Cost
Due to
inflation/market
variation
R2
9
Delay in design Technical
Unknown scope
R3
10
Insufficient flow of
information Technical
Inefficient
communication
system
R4
2 Approval of unrealistic
deadlines Schedule
Client pressure
R5
6 Complying the quality
standards Client related
Inadequate
quality plan
R6
4
Labour issues Political
Labour strikes
R7
8 Coactivity with other
contractors Schedule
Poor planning
R8
1
Natural Risk Environment
Natural disaster
R9
5
Insufficient training of the
staff Technical
Company saving
on labour
development
R10
3
Delay due to environment
circumstances Environment
Natural
Risk
Prioritization
Qualitative
Risk Analysis
Quantitative
Risk Analysis
•
•
•
•
•
•
•
•
•
•
Project Deliverable (or Activity) Harmandeep Harmanjeet Rabih Parth Daksh
Initiation Financial Analysis Business Case Scope Statement
Project Charter
Activity Cost Estimation
R I A I C
Planning
Work Breakdown Structure Gantt Chart
Risk Register
Probability Impact Matrix Risk breakdown Structure Network
Quality Management Plan
I A C C R
Execution
Work Performance Information Procurement Management Plan Make or
Analysis
R I A I C
Monitoring and Control
Quality Assurance
Quality metrics Quality check list
A R C A I
Closing
Project Closure Checklist Project Closing Document Lessons learned
C I A C R
• UALITY ASSURANCE PLAN DRAFTED
• SET OF INSPECTION AND TESTING PLANS
• SITE LABORATORY FACILITY FORMED FOR VARIOUS TESTING
• CLIENT ENGINEERS WILL BE CONDUCTING FIELD AUDITS
EACH MONTH
•
•
•
•
•
•
•
•
•

•
•

•
•
•
•

•
•
•
•
Item Yes
/No
n/a comments
1. Is quality assurance plan prepared for
construction?
yes Formed during planning phase
2. Is quality assurance plan is accessible to all
stake holders?
yes Copy has been sent to each
3. Is quality metrics defined? yes Quality metrics has been made
during monitoring and controlling
process
4. Whether everyone agreed upon the metrics? yes
5. Do all the team members have access to
quality documents?
yes
6. Whether there is a contingency plan for all
the quality defects?
yes Plan was formed during planning
7. Has the quality testing of the product is done
before final approval or delivery?
yes Done by the laboratory site
engineer
9. Does project have enough resources to
facilitate quality related activities?
yes
10. Is manufacturing plan clearly defined? yes
• ITP’S
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
Foundations for New Champlain Bridge Corridor Project

More Related Content

Similar to Foundations for New Champlain Bridge Corridor Project

NPV is net present value of document.ppt
NPV is net present value of document.pptNPV is net present value of document.ppt
NPV is net present value of document.ppt
SanthoshK757191
 
Work breakdown structure WBS Columbia Southe.docx
Work breakdown structure WBS Columbia Southe.docxWork breakdown structure WBS Columbia Southe.docx
Work breakdown structure WBS Columbia Southe.docx
ericbrooks84875
 
130306 City Council Workshop
130306 City Council Workshop130306 City Council Workshop
130306 City Council Workshop
publicinvolvement
 
Fina521 lecture 3_investment_criteria_2013-10-09-1
Fina521 lecture 3_investment_criteria_2013-10-09-1Fina521 lecture 3_investment_criteria_2013-10-09-1
Fina521 lecture 3_investment_criteria_2013-10-09-1
Landry De Chabe
 
Project management
Project managementProject management
Project management
Anish Jojan
 
ch09 project communication, tracking.ppt
ch09 project communication, tracking.pptch09 project communication, tracking.ppt
ch09 project communication, tracking.ppt
ShivaniArgulwarBachu
 

Similar to Foundations for New Champlain Bridge Corridor Project (20)

PM Session 7
PM Session 7PM Session 7
PM Session 7
 
Session 21 4th edition PMP
Session 21 4th edition PMPSession 21 4th edition PMP
Session 21 4th edition PMP
 
Mark blum ubc tool box execution - powerpoint presentation
Mark blum   ubc tool box execution - powerpoint presentationMark blum   ubc tool box execution - powerpoint presentation
Mark blum ubc tool box execution - powerpoint presentation
 
NPV is net present value of document.ppt
NPV is net present value of document.pptNPV is net present value of document.ppt
NPV is net present value of document.ppt
 
Project Execution PowerPoint Presentation Slides
Project Execution PowerPoint Presentation SlidesProject Execution PowerPoint Presentation Slides
Project Execution PowerPoint Presentation Slides
 
Business Finance Chapter 8
Business Finance Chapter 8Business Finance Chapter 8
Business Finance Chapter 8
 
Work breakdown structure WBS Columbia Southe.docx
Work breakdown structure WBS Columbia Southe.docxWork breakdown structure WBS Columbia Southe.docx
Work breakdown structure WBS Columbia Southe.docx
 
Project Execution Powerpoint Presentation Slides
Project Execution Powerpoint Presentation SlidesProject Execution Powerpoint Presentation Slides
Project Execution Powerpoint Presentation Slides
 
12 Project Risk and uncertainty.ppt .
12 Project Risk and uncertainty.ppt     .12 Project Risk and uncertainty.ppt     .
12 Project Risk and uncertainty.ppt .
 
130306 City Council Workshop
130306 City Council Workshop130306 City Council Workshop
130306 City Council Workshop
 
Updating Equipment
Updating EquipmentUpdating Equipment
Updating Equipment
 
Project Performance Measurement Earned Value A Starter
Project Performance Measurement   Earned Value   A StarterProject Performance Measurement   Earned Value   A Starter
Project Performance Measurement Earned Value A Starter
 
Fina521 lecture 3_investment_criteria_2013-10-09-1
Fina521 lecture 3_investment_criteria_2013-10-09-1Fina521 lecture 3_investment_criteria_2013-10-09-1
Fina521 lecture 3_investment_criteria_2013-10-09-1
 
Work Pricing in construction projects by K C Iyer
Work Pricing in construction projects by K C IyerWork Pricing in construction projects by K C Iyer
Work Pricing in construction projects by K C Iyer
 
Project management
Project managementProject management
Project management
 
Project Management Diagnostics for Time Management
Project Management Diagnostics for Time ManagementProject Management Diagnostics for Time Management
Project Management Diagnostics for Time Management
 
Oak Harbor Rate Study
Oak Harbor Rate StudyOak Harbor Rate Study
Oak Harbor Rate Study
 
OpenText Live: Modeling your business processes to new ways of working
OpenText Live: Modeling your business processes to new ways of workingOpenText Live: Modeling your business processes to new ways of working
OpenText Live: Modeling your business processes to new ways of working
 
ch09 project communication, tracking.ppt
ch09 project communication, tracking.pptch09 project communication, tracking.ppt
ch09 project communication, tracking.ppt
 
PF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.pptPF_EarnedValuePresentation.ppt
PF_EarnedValuePresentation.ppt
 

More from Daksh Raj Chopra

More from Daksh Raj Chopra (12)

Prove/disprove of microphone used for targeting Ads
Prove/disprove of microphone used for targeting Ads Prove/disprove of microphone used for targeting Ads
Prove/disprove of microphone used for targeting Ads
 
Foundations for New Champlain Bridge Corridor Project
Foundations for New Champlain Bridge Corridor ProjectFoundations for New Champlain Bridge Corridor Project
Foundations for New Champlain Bridge Corridor Project
 
Maggi noodles Case Study
Maggi noodles Case StudyMaggi noodles Case Study
Maggi noodles Case Study
 
Internet of things (IoT) Architecture Security Analysis
Internet of things (IoT) Architecture Security AnalysisInternet of things (IoT) Architecture Security Analysis
Internet of things (IoT) Architecture Security Analysis
 
8 bit Multiplier Accumulator
8 bit Multiplier Accumulator8 bit Multiplier Accumulator
8 bit Multiplier Accumulator
 
Simulation of a Wireless Sub Network using QualNET
Simulation of a Wireless Sub Network using QualNETSimulation of a Wireless Sub Network using QualNET
Simulation of a Wireless Sub Network using QualNET
 
Safety guard for blind
Safety guard for blindSafety guard for blind
Safety guard for blind
 
Self Organizing Maps
Self Organizing MapsSelf Organizing Maps
Self Organizing Maps
 
MATLAB IMPLEMENTATION OF SELF-ORGANIZING MAPS FOR CLUSTERING OF REMOTE SENSIN...
MATLAB IMPLEMENTATION OF SELF-ORGANIZING MAPS FOR CLUSTERING OF REMOTE SENSIN...MATLAB IMPLEMENTATION OF SELF-ORGANIZING MAPS FOR CLUSTERING OF REMOTE SENSIN...
MATLAB IMPLEMENTATION OF SELF-ORGANIZING MAPS FOR CLUSTERING OF REMOTE SENSIN...
 
DTMF based Home Automation System
DTMF based Home Automation SystemDTMF based Home Automation System
DTMF based Home Automation System
 
Advance Microcontroller AVR
Advance Microcontroller AVRAdvance Microcontroller AVR
Advance Microcontroller AVR
 
DTMF based Home Applicance System
DTMF based Home Applicance SystemDTMF based Home Applicance System
DTMF based Home Applicance System
 

Recently uploaded

Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Christo Ananth
 

Recently uploaded (20)

Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Glass Ceramics: Processing and Properties
Glass Ceramics: Processing and PropertiesGlass Ceramics: Processing and Properties
Glass Ceramics: Processing and Properties
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)Java Programming :Event Handling(Types of Events)
Java Programming :Event Handling(Types of Events)
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 

Foundations for New Champlain Bridge Corridor Project

  • 1.
  • 2. The New Champlain Bridge is One of the largest infrastructure projects in north America. The Bridge will span 3.4 km and connect Montreal to Brossard. It will replace the existing bridge. Temporary Foundations are required to support the construction of the Backspan of the Cable Stayed portion of the bridge.
  • 3.
  • 4. • THE CONSTRUCTION OF BACKSPAN TEMPORARY BENTS FOUNDATIONS BETWEEN MST (MAINSPAN TOWER) AND PIER W02, LOCATED IN THE SAINT LAWRENCE RIVER, OFF THE EXISTING DYKE. • THE FOUNDATIONS DESIGN CALLS FOR DRIVEN H-PILES AND CONCRETE PILE CAPS AND TIE BEAMS. • THE TEMPORARY BENTS AND THEIR FOUNDATIONS ARE LOCATED IN THE RIGHT-OF-WAY OF THE FUTURE BRIDGE, ON THE WESTERN SIDE OF THE SEAWAY DYKE.
  • 5.
  • 6. Project Description:  The Design and Construction of 15 Foundations for the Backspan temporary bents. Project Deliverables:  Complete geotechnical study  Produce design documents and drawings  Procurement  Complete construction
  • 7.  Project Objectives: • The main objective of our project is to produce all deliverables on time and within budget. • Perform all work and in conformance with project specification and quality plan. • Turning in foreseen profit.  Main Project Success Criteria: • All the functional requirements of the project should be met. • Project should be done within the time and budget • Perform the work to the satisfaction of client. • Handover and respect milestone dates.  Project team resources: Daksh Raj Chopra, Rabih Ataya , Harmandeep singh , Harmanjeet singh parmar  Date Of Authorization: 22 Feb 2016  Project Start Date: 1 April 2016  Date Of Completion: 15 June 2016  Budget Information: The firm has allocated $315,385 + 20% profit for the project.  Project Manager: Parth Avinash Chauhan
  • 8. STRENGTHS:  Experienced staff  Reputed Construction Firm  Expertise in execution of similar projects  Established and maintained a strong base WEAKNESSES:  Scarce Manpower  High labor cost  Lack of modern equipment OPPORTUNITIES:  Government support and Tax rebates  Relation with Client on a big Project  Work experience  Growing demand THREATS:  Climatic condition  Increasing labor cost  Natural calamities  Exchange rate varies a lot
  • 9. Rev. Item # Facility CRC Description Estimated Qty R1 Estimated Qty R0 Delta Unit of Measure Direct Manhours Permanent equipment (1) Material (2) Installation Hrs+equip. (3) Total (1+2+3) 1.0 12201 21100 Indirect Costs (All other costs are included in direct costs) 1.1 12201 21100 Mobilization 1 1 Lot 4,500.00 $ 1.2 12201 21100 Demobilization 1 1 Lot 1,500.00 $ The Bidder must supply the fulll breakdow n of mobilization and demobilization costs w ith its bid. 1.3 12201 21100 Insurance 1 1 Lot 1.4 12201 21100 Temporary Facilities (including but not limited to site offices, trailers, potable water, power and maintenance) 10 10 week 500.00 $ 1.5 12201 21100 Administrative support, technicians, surveyors, supervision, management, etc… 10 10 week 5,000.00 $ For items 1.4 & 1.5, the Bidder must indicate the number of w eeks for w hich this price is applicable 1.6 12201 21100 Bonds 1.7 12201 21100 Other indirect & general costs not covered above 1.7.1 12201 21100 Define : ______________________________________________________________ 1 1 Lot 1.7.2 12201 21100 Define : ______________________________________________________________ 1 1 Lot 1.7.3 12201 21100 Define: ______________________________________________________________ 1 1 Lot Subtotal - Indirect Prices 11,500.00 $ 2.0 12201 21100 Temporary Foundations 2.1 12201 21100 Foundations for tower type 1 2.1.1 12201 21100 Formwork Installation (foundations & tie-beams) 215 -215 m2 2.1.2 12201 21100 Concrete pouring 120 -120 m3 2.1.3 12201 21100 Stripping 215 -215 m2 2.2 12201 21100 Foundations for tower type 2 &3 2.2.1 12201 21100 Formwork Installation (foundations & tie-beams) 750 740 10 m2 675 20,250.00 47,250.00 67,500.00 $ 2.2.2 12201 21100 Concrete pouring 600 530 70 m3 520 36,375.00 36,375.00 $ 2.2.3 12201 21100 Stripping 750 740 10 m2 236 16,500.00 16,500.00 $ 2.3 12201 21100 Foundations for tower type 4 2.3.1 12201 21100 Formwork Installation (foundations & tie-beams) 660 340 320 m2 594 17,820.00 41,580.00 59,400.00 $ 2.3.2 12201 21100 Concrete pouring 390 280 110 m3 349 24,420.00 24,420.00 $ 2.3.3 12201 21100 Stripping 660 340 320 m2 207 14,520.00 14,520.00 $ 2.4 12201 21100 Foundations for tower type 5 2.4.1 12201 21100 Formwork Installation (foundations & tie-beams) 580 520 60 m2 522 15,660.00 36,540.00 52,200.00 $ 2.4.2 12201 21100 Concrete pouring 320 270 50 m3 289 20,210.00 20,210.00 $ 2.4.3 12201 21100 Stripping 580 520 60 m2 182 12,760.00 12,760.00 $ Subtotal - Direct Prices 3,574 53,730.00$ 250,155.00$ 303,885.00 $ 3,574 53,730.00$ 250,155.00$ 315,385.00 $TOTAL
  • 10. Discount Rate (Yearly)= 15% Discount Rate (Weekly)= 0.3% Week 0 1 2 3 4 5 6 7 8 9 Payment $ 75,692.40 $ 75,692.40 $ 75,692.40 $ 75,692.40 $ 75,692.40 Procurement -$ 53,730.00 Labor+Overhead Milestone 1 -$ 17,443.67 -$ 17,443.67 -$ 17,443.67 Milestone 2 -$ 17,443.67 -$ 17,443.67 -$ 17,443.67 Milestone 3 -$ 17,443.67 -$ 17,443.67 -$ 17,443.67 Milestone 4 -$ 17,443.67 -$ 17,443.67 -$ 17,443.67 Milestone 5 -$ 17,443.67 -$ 17,443.67 -$ 17,443.67 Total -$ 53,730.00 -$ 17,443.67 -$ 17,443.67 $ 40,805.07 -$ 34,887.33 $ 40,805.07 $ 40,805.07 -$ 34,887.33 $ 40,805.07 $ 58,248.73 PV -$ 53,730.00 -$ 17,391.49 -$ 17,339.47 $ 40,440.01 -$ 34,471.81 $ 40,198.46 $ 40,078.23 -$ 34,163.41 $ 39,838.83 $ 56,699.35 NPV $ 60,158.70
  • 11.  On March 17,2016  Group members were introduced.  Background review of project was done.  Project Charter and Project Scope Statement was discussed and finalized.  Discussion of project goals and deliverables.  Assigning responsibilities to each team member and prioritizing tasks.
  • 12.
  • 13.
  • 14.
  • 15.
  • 17. LIKELIHOOD/PROBABILITY HIGH R6, R7, R9 MEDIUM R1, R5, R10 R4 LOW R2 R3 R8 LOW MEDIUM HIGH Risk Index Rank Risk Title Category Triggers R1 7 Increase in raw material cost Cost Due to inflation/market variation R2 9 Delay in design Technical Unknown scope R3 10 Insufficient flow of information Technical Inefficient communication system R4 2 Approval of unrealistic deadlines Schedule Client pressure R5 6 Complying the quality standards Client related Inadequate quality plan R6 4 Labour issues Political Labour strikes R7 8 Coactivity with other contractors Schedule Poor planning R8 1 Natural Risk Environment Natural disaster R9 5 Insufficient training of the staff Technical Company saving on labour development R10 3 Delay due to environment circumstances Environment Natural Risk Prioritization Qualitative Risk Analysis Quantitative Risk Analysis
  • 19. Project Deliverable (or Activity) Harmandeep Harmanjeet Rabih Parth Daksh Initiation Financial Analysis Business Case Scope Statement Project Charter Activity Cost Estimation R I A I C Planning Work Breakdown Structure Gantt Chart Risk Register Probability Impact Matrix Risk breakdown Structure Network Quality Management Plan I A C C R Execution Work Performance Information Procurement Management Plan Make or Analysis R I A I C Monitoring and Control Quality Assurance Quality metrics Quality check list A R C A I Closing Project Closure Checklist Project Closing Document Lessons learned C I A C R
  • 20. • UALITY ASSURANCE PLAN DRAFTED • SET OF INSPECTION AND TESTING PLANS • SITE LABORATORY FACILITY FORMED FOR VARIOUS TESTING • CLIENT ENGINEERS WILL BE CONDUCTING FIELD AUDITS EACH MONTH
  • 25. Item Yes /No n/a comments 1. Is quality assurance plan prepared for construction? yes Formed during planning phase 2. Is quality assurance plan is accessible to all stake holders? yes Copy has been sent to each 3. Is quality metrics defined? yes Quality metrics has been made during monitoring and controlling process 4. Whether everyone agreed upon the metrics? yes 5. Do all the team members have access to quality documents? yes 6. Whether there is a contingency plan for all the quality defects? yes Plan was formed during planning 7. Has the quality testing of the product is done before final approval or delivery? yes Done by the laboratory site engineer 9. Does project have enough resources to facilitate quality related activities? yes 10. Is manufacturing plan clearly defined? yes