CONSTRUCTION METHODOLOGY
& CONCRETE VOLUME SCHEDULING
LAYING OUT AND EXCAVATION
DAY 1
LAYING OUT AND EXCAVATION
DAY 1
ZONE 1
ZONE 2
ZONE 3
ZONE 4
ZONE 5
WEEK 1
ZONE 1
A1 FOUNDATION STARTED
WEEK 2
ZONE 1
A1a COLUMNS STARTED, A1b FOUNDATION STARTED
ZONE 2
A1 FOUNDATION STARTED, TOWER CRANE IS ERECTED
WEEK 3
ZONE 1
A1b FOUNDATION FINISHED, A1a COLUMNS FINISHED, TOWER CRANE IS ERECTED
ZONE 2
A1 FOUNDATION COLUMNS STARTED
WEEK 4
ZONE 1
A1b FOUNDATION FINISHED, A1 SLAB-ON-GRADE STARTED
ZONE 2
A1a FOUNDATION FINISHED
WEEK 6
ZONE 1
A2 FOUNDATION STARTED, A1 SOG FINISHED
ZONE 2
A1b FOUNDATION FINISHED
ZONE 3
A2 FOUNDATION STARTED
WEEK 8
ZONE 1
A2 FOUNDATION FINISHED, A2 SOG FINISHED, A1 UPPER GROUND FLOOR STARTED
ZONE 2
A2 FOUNDATION FINISHED, A1 SOG FINISHED
ZONE 3
A2b FOUNDATION STARTED, A2 SOG STARTED, TOWER CRANE IS ERECTED
WEEK 10
ZONE 1
A4a FOUNDATION FINISHED, A2a UPPER GROUND FLOOR FINISHED, A1 2nd FLOOR STARTED
ZONE 2
A3 FOUNDATION FINISHED, A1 SOG FINISHED, 2 TOWER CRANES ARE ERECTED
ZONE 3
A1a & A3a FOUNDATION FINISHED, A2 SOG FINISHED, A2 UPPER GROUND FLOOR STARTED
WEEK 12
ZONE 1
A4b FOUNDATION FINISHED, A4a SOG FINISHED, A3a UGF FINISHED, A1 2nd FLOOR FINISHED
ZONE 2
A4 FOUNDATION FINISHED, A3a SOG FINISHED, A1 UPPER GROUND FLOOR STARTED
ZONE 3
A1b & A3b FOUNDATION FINISHED, A3 & A1a SOG FINISHED, A2 UPPER GROUND FLOOR FINISHED
WEEK 16
ZONE 1
A6a FOUNDATION FINISHED, A5 SOG FINISHED, A4a UGF FINISHED, A2a 2nd FLOOR FINISHED
ZONE 2
A4a SOG FINISHED, A2 UPPER GROUND FLOOR FINISHED, A1 2ND FLOOR STARTED
ZONE 3
A4&A5a FOUNDATION FINISHED, A1&A4 SOG FINISHED, A3 UGF FINISHED, A1 2ND FLR. STARTED
WEEK 24
ZONE 1
A6 UPPER GROUND FLOOR FINISHED, A4 2nd FLOOR FINISHED, A1 3RD FLOOR STARTED
ZONE 2
A4 UPPER GROUND FLOOR FINISHED, A3a 2ND FLOOR FINISHED
ZONE 3
A5 UPPER GROUND FLOOR FINISHED, A3a 2ND FLOOR FINISHED
ZONE 4
A3 FOUNDATION FINISHED, A1 SLAB-ON-GRADE STARTED
ZONE 5
A1 FOUNDATION STARTED
WEEK 26
ZONE 1
A5a 2nd FLOOR FINISHED, A1a 3RD FLOOR FINISHED
ZONE 2
A3 2ND FLOOR FINISHED, A1 3RD FLOOR STARTED
ZONE 3
A1 3RD FLOOR STARTED
ZONE 4
A4 FOUNDATION FINISHED, A2 SLAB-ON-GRADE FINISHED
ZONE 5
A4 FOUNDATION FINISHED, A1 SLAB-ON-GRADE STARTED
WEEK 30
ZONE 1
A6 2nd FLOOR FINISHED, A2a 3RD FLOOR FINISHED
ZONE 2
A4 2ND FLOOR FINISHED, A2a 3RD FLOOR FINISHED
ZONE 3
A5a 2ND FLOOR FINISHED, A2a 3RD FLOOR FINISHED
ZONE 4
A5 FOUNDATION FINISHED,A3 SOG FINISHED, A2 UGF FINISHED
ZONE 5
A4 FOUNDATION FINISHED,A2 SOG FINISHED
WEEK 34
ZONE 1
A3a 3RD FLOOR FINISHED, A1 4TH FLOOR STARTED
ZONE 2
A3a 3RD FLOOR FINISHED, A1 4TH FLOOR STARTED
ZONE 3
A5 2ND FLOOR FINISHED, A3a 3RD FLOOR FINISHED
ZONE 4
A4 SOG FINISHED, A5 UPPER GROUND FLOOR FINISHED, A21 2ND FLOOR STARTED
ZONE 5
A3 FOUNDATION FINISHED,A3 SOG FINISHED, A2 UGF FINISHED
WEEK 38
ZONE 1
A5a 3RD FLOOR FINISHED, A2 4TH FLOOR FINISHED
ZONE 2
A4 3RD FLOOR FINISHED, A2 4TH FLOOR FINISHED
ZONE 3
A5a 3RD FLOOR FINISHED, A3 4TH FLOOR STARTED
ZONE 4
A5 UPPER GROUND FLOOR FINISHED, A5 2ND FLOOR FINISHED, A1 3RD FLOOR FINISHED
ZONE 5
A4 SOG FINISHED, A4 UGF FINISHED
WEEK 42
ZONE 1
A6 3RD FLOOR FINISHED, A4a 4TH FLOOR FINISHED
ZONE 2
A3 4TH FLOOR FINISHED
ZONE 3
A5 3RD FLOOR FINISHED, A4 4TH FLOOR SFINISHED
ZONE 4
A31 2ND FLOOR FINISHED, A31 3RD FLOOR FINISHED, A11 4TH FLOOR STARTED
ZONE 5
A6 FOUNDATION FINISHED, A2 SLAB-ON-GRADE FINISHED
WEEK 46
ZONE 1
A6 4TH FLOOR FINISHED
ZONE 2
A4 4TH FLOOR FINISHED
ZONE 3
A4 4TH FLOOR SFINISHED
ZONE 4
A31 4TH FLOOR FINISHED, A11 UPPER LEVEL STARTED
ZONE 5
A4 SLAB-ON-GRADE FINISHED, A6 UPPER GROUND FLOOR FINISHED, 2ND & 3RD FLOOR STARTED
WEEK 50
ZONE 1
COMPLETED
ZONE 2
COMPLETED
ZONE 3
COMPLETED
ZONE 4
A31 UPPER LEVEL FINISHED
ZONE 5
A6 SOG FINISHED, A6 UGF FINISHED, A4 2ND FLOOR FINISHED, A2 3RD FLOOR FINISHED
WEEK 54
ZONE 1
COMPLETED
ZONE 2
COMPLETED
ZONE 3
COMPLETED
ZONE 4
COMPLETED
ZONE 5
A6 UGF FINISHED, A6 2ND FLOOR FINISHED, A6RD FLOOR FINISHED, A2 4TH FLOOR FINISHED
WEEK 58
ZONE 1
COMPLETED
ZONE 2
COMPLETED
ZONE 3
COMPLETED
ZONE 4
COMPLETED
ZONE 5
A6 3RD FLOOR FINISHED, A4 4TH FLOOR FINISHED
WEEK 60
ZONE 1
COMPLETED
ZONE 2
COMPLETED
ZONE 3
COMPLETED
ZONE 4
COMPLETED
ZONE 5
A6 4TH FLOOR FINISHED, A2 UPPER LEVEL FINISHED
TOTAL CONCRETE
VOLUME as per
DD02Jul=54,000 m3
WEEK 60
ZONE 1
COMPLETED
ZONE 2
COMPLETED
ZONE 3
COMPLETED
ZONE 4
COMPLETED
ZONE 5
COMPLETED

More Related Content

More from Allan Leyte

Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Allan Leyte
 
Sample MSProject with 16 DivisionFormat Variation(EOT)
Sample MSProject with 16 DivisionFormat Variation(EOT)Sample MSProject with 16 DivisionFormat Variation(EOT)
Sample MSProject with 16 DivisionFormat Variation(EOT)Allan Leyte
 
BHP01-0 Bouly baseline on MSproject Format
BHP01-0 Bouly baseline on MSproject FormatBHP01-0 Bouly baseline on MSproject Format
BHP01-0 Bouly baseline on MSproject FormatAllan Leyte
 
PRODUCTION RATE APPX. NEW
PRODUCTION RATE APPX. NEWPRODUCTION RATE APPX. NEW
PRODUCTION RATE APPX. NEWAllan Leyte
 
Sample of Structural Steel Scheduling
Sample of Structural Steel SchedulingSample of Structural Steel Scheduling
Sample of Structural Steel SchedulingAllan Leyte
 
Visio-Planning FlowChart-3
Visio-Planning FlowChart-3Visio-Planning FlowChart-3
Visio-Planning FlowChart-3Allan Leyte
 
Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Allan Leyte
 
Booster Pump cause of delay analysis
Booster Pump cause of delay analysisBooster Pump cause of delay analysis
Booster Pump cause of delay analysisAllan Leyte
 
Sample Bidcom Presentation - Structural Works 12-28-11
Sample Bidcom Presentation - Structural Works 12-28-11Sample Bidcom Presentation - Structural Works 12-28-11
Sample Bidcom Presentation - Structural Works 12-28-11Allan Leyte
 
Scheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPMScheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPMAllan Leyte
 
Offshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocolOffshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocolAllan Leyte
 
Town Center presentation
Town Center presentationTown Center presentation
Town Center presentationAllan Leyte
 

More from Allan Leyte (16)

Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
 
Sample MSProject with 16 DivisionFormat Variation(EOT)
Sample MSProject with 16 DivisionFormat Variation(EOT)Sample MSProject with 16 DivisionFormat Variation(EOT)
Sample MSProject with 16 DivisionFormat Variation(EOT)
 
BHP01-0 Bouly baseline on MSproject Format
BHP01-0 Bouly baseline on MSproject FormatBHP01-0 Bouly baseline on MSproject Format
BHP01-0 Bouly baseline on MSproject Format
 
WEIGHTING TABLE
WEIGHTING TABLEWEIGHTING TABLE
WEIGHTING TABLE
 
PRODUCTION RATE APPX. NEW
PRODUCTION RATE APPX. NEWPRODUCTION RATE APPX. NEW
PRODUCTION RATE APPX. NEW
 
Sample of Structural Steel Scheduling
Sample of Structural Steel SchedulingSample of Structural Steel Scheduling
Sample of Structural Steel Scheduling
 
p3 s-curves
p3 s-curvesp3 s-curves
p3 s-curves
 
Wreport
WreportWreport
Wreport
 
Visio-Planning FlowChart-3
Visio-Planning FlowChart-3Visio-Planning FlowChart-3
Visio-Planning FlowChart-3
 
Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016
 
Booster Pump cause of delay analysis
Booster Pump cause of delay analysisBooster Pump cause of delay analysis
Booster Pump cause of delay analysis
 
Sample Bidcom Presentation - Structural Works 12-28-11
Sample Bidcom Presentation - Structural Works 12-28-11Sample Bidcom Presentation - Structural Works 12-28-11
Sample Bidcom Presentation - Structural Works 12-28-11
 
Scheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPMScheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPM
 
Offshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocolOffshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocol
 
progress photos
progress photosprogress photos
progress photos
 
Town Center presentation
Town Center presentationTown Center presentation
Town Center presentation
 

Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)

  • 2. LAYING OUT AND EXCAVATION DAY 1
  • 3. LAYING OUT AND EXCAVATION DAY 1 ZONE 1 ZONE 2 ZONE 3 ZONE 4 ZONE 5
  • 4. WEEK 1 ZONE 1 A1 FOUNDATION STARTED
  • 5. WEEK 2 ZONE 1 A1a COLUMNS STARTED, A1b FOUNDATION STARTED ZONE 2 A1 FOUNDATION STARTED, TOWER CRANE IS ERECTED
  • 6. WEEK 3 ZONE 1 A1b FOUNDATION FINISHED, A1a COLUMNS FINISHED, TOWER CRANE IS ERECTED ZONE 2 A1 FOUNDATION COLUMNS STARTED
  • 7. WEEK 4 ZONE 1 A1b FOUNDATION FINISHED, A1 SLAB-ON-GRADE STARTED ZONE 2 A1a FOUNDATION FINISHED
  • 8. WEEK 6 ZONE 1 A2 FOUNDATION STARTED, A1 SOG FINISHED ZONE 2 A1b FOUNDATION FINISHED ZONE 3 A2 FOUNDATION STARTED
  • 9. WEEK 8 ZONE 1 A2 FOUNDATION FINISHED, A2 SOG FINISHED, A1 UPPER GROUND FLOOR STARTED ZONE 2 A2 FOUNDATION FINISHED, A1 SOG FINISHED ZONE 3 A2b FOUNDATION STARTED, A2 SOG STARTED, TOWER CRANE IS ERECTED
  • 10. WEEK 10 ZONE 1 A4a FOUNDATION FINISHED, A2a UPPER GROUND FLOOR FINISHED, A1 2nd FLOOR STARTED ZONE 2 A3 FOUNDATION FINISHED, A1 SOG FINISHED, 2 TOWER CRANES ARE ERECTED ZONE 3 A1a & A3a FOUNDATION FINISHED, A2 SOG FINISHED, A2 UPPER GROUND FLOOR STARTED
  • 11. WEEK 12 ZONE 1 A4b FOUNDATION FINISHED, A4a SOG FINISHED, A3a UGF FINISHED, A1 2nd FLOOR FINISHED ZONE 2 A4 FOUNDATION FINISHED, A3a SOG FINISHED, A1 UPPER GROUND FLOOR STARTED ZONE 3 A1b & A3b FOUNDATION FINISHED, A3 & A1a SOG FINISHED, A2 UPPER GROUND FLOOR FINISHED
  • 12. WEEK 16 ZONE 1 A6a FOUNDATION FINISHED, A5 SOG FINISHED, A4a UGF FINISHED, A2a 2nd FLOOR FINISHED ZONE 2 A4a SOG FINISHED, A2 UPPER GROUND FLOOR FINISHED, A1 2ND FLOOR STARTED ZONE 3 A4&A5a FOUNDATION FINISHED, A1&A4 SOG FINISHED, A3 UGF FINISHED, A1 2ND FLR. STARTED
  • 13. WEEK 24 ZONE 1 A6 UPPER GROUND FLOOR FINISHED, A4 2nd FLOOR FINISHED, A1 3RD FLOOR STARTED ZONE 2 A4 UPPER GROUND FLOOR FINISHED, A3a 2ND FLOOR FINISHED ZONE 3 A5 UPPER GROUND FLOOR FINISHED, A3a 2ND FLOOR FINISHED ZONE 4 A3 FOUNDATION FINISHED, A1 SLAB-ON-GRADE STARTED ZONE 5 A1 FOUNDATION STARTED
  • 14. WEEK 26 ZONE 1 A5a 2nd FLOOR FINISHED, A1a 3RD FLOOR FINISHED ZONE 2 A3 2ND FLOOR FINISHED, A1 3RD FLOOR STARTED ZONE 3 A1 3RD FLOOR STARTED ZONE 4 A4 FOUNDATION FINISHED, A2 SLAB-ON-GRADE FINISHED ZONE 5 A4 FOUNDATION FINISHED, A1 SLAB-ON-GRADE STARTED
  • 15. WEEK 30 ZONE 1 A6 2nd FLOOR FINISHED, A2a 3RD FLOOR FINISHED ZONE 2 A4 2ND FLOOR FINISHED, A2a 3RD FLOOR FINISHED ZONE 3 A5a 2ND FLOOR FINISHED, A2a 3RD FLOOR FINISHED ZONE 4 A5 FOUNDATION FINISHED,A3 SOG FINISHED, A2 UGF FINISHED ZONE 5 A4 FOUNDATION FINISHED,A2 SOG FINISHED
  • 16. WEEK 34 ZONE 1 A3a 3RD FLOOR FINISHED, A1 4TH FLOOR STARTED ZONE 2 A3a 3RD FLOOR FINISHED, A1 4TH FLOOR STARTED ZONE 3 A5 2ND FLOOR FINISHED, A3a 3RD FLOOR FINISHED ZONE 4 A4 SOG FINISHED, A5 UPPER GROUND FLOOR FINISHED, A21 2ND FLOOR STARTED ZONE 5 A3 FOUNDATION FINISHED,A3 SOG FINISHED, A2 UGF FINISHED
  • 17. WEEK 38 ZONE 1 A5a 3RD FLOOR FINISHED, A2 4TH FLOOR FINISHED ZONE 2 A4 3RD FLOOR FINISHED, A2 4TH FLOOR FINISHED ZONE 3 A5a 3RD FLOOR FINISHED, A3 4TH FLOOR STARTED ZONE 4 A5 UPPER GROUND FLOOR FINISHED, A5 2ND FLOOR FINISHED, A1 3RD FLOOR FINISHED ZONE 5 A4 SOG FINISHED, A4 UGF FINISHED
  • 18. WEEK 42 ZONE 1 A6 3RD FLOOR FINISHED, A4a 4TH FLOOR FINISHED ZONE 2 A3 4TH FLOOR FINISHED ZONE 3 A5 3RD FLOOR FINISHED, A4 4TH FLOOR SFINISHED ZONE 4 A31 2ND FLOOR FINISHED, A31 3RD FLOOR FINISHED, A11 4TH FLOOR STARTED ZONE 5 A6 FOUNDATION FINISHED, A2 SLAB-ON-GRADE FINISHED
  • 19. WEEK 46 ZONE 1 A6 4TH FLOOR FINISHED ZONE 2 A4 4TH FLOOR FINISHED ZONE 3 A4 4TH FLOOR SFINISHED ZONE 4 A31 4TH FLOOR FINISHED, A11 UPPER LEVEL STARTED ZONE 5 A4 SLAB-ON-GRADE FINISHED, A6 UPPER GROUND FLOOR FINISHED, 2ND & 3RD FLOOR STARTED
  • 20. WEEK 50 ZONE 1 COMPLETED ZONE 2 COMPLETED ZONE 3 COMPLETED ZONE 4 A31 UPPER LEVEL FINISHED ZONE 5 A6 SOG FINISHED, A6 UGF FINISHED, A4 2ND FLOOR FINISHED, A2 3RD FLOOR FINISHED
  • 21. WEEK 54 ZONE 1 COMPLETED ZONE 2 COMPLETED ZONE 3 COMPLETED ZONE 4 COMPLETED ZONE 5 A6 UGF FINISHED, A6 2ND FLOOR FINISHED, A6RD FLOOR FINISHED, A2 4TH FLOOR FINISHED
  • 22. WEEK 58 ZONE 1 COMPLETED ZONE 2 COMPLETED ZONE 3 COMPLETED ZONE 4 COMPLETED ZONE 5 A6 3RD FLOOR FINISHED, A4 4TH FLOOR FINISHED
  • 23. WEEK 60 ZONE 1 COMPLETED ZONE 2 COMPLETED ZONE 3 COMPLETED ZONE 4 COMPLETED ZONE 5 A6 4TH FLOOR FINISHED, A2 UPPER LEVEL FINISHED TOTAL CONCRETE VOLUME as per DD02Jul=54,000 m3
  • 24. WEEK 60 ZONE 1 COMPLETED ZONE 2 COMPLETED ZONE 3 COMPLETED ZONE 4 COMPLETED ZONE 5 COMPLETED