5. WEEK 2
ZONE 1
A1a COLUMNS STARTED, A1b FOUNDATION STARTED
ZONE 2
A1 FOUNDATION STARTED, TOWER CRANE IS ERECTED
6. WEEK 3
ZONE 1
A1b FOUNDATION FINISHED, A1a COLUMNS FINISHED, TOWER CRANE IS ERECTED
ZONE 2
A1 FOUNDATION COLUMNS STARTED
7. WEEK 4
ZONE 1
A1b FOUNDATION FINISHED, A1 SLAB-ON-GRADE STARTED
ZONE 2
A1a FOUNDATION FINISHED
8. WEEK 6
ZONE 1
A2 FOUNDATION STARTED, A1 SOG FINISHED
ZONE 2
A1b FOUNDATION FINISHED
ZONE 3
A2 FOUNDATION STARTED
9. WEEK 8
ZONE 1
A2 FOUNDATION FINISHED, A2 SOG FINISHED, A1 UPPER GROUND FLOOR STARTED
ZONE 2
A2 FOUNDATION FINISHED, A1 SOG FINISHED
ZONE 3
A2b FOUNDATION STARTED, A2 SOG STARTED, TOWER CRANE IS ERECTED
10. WEEK 10
ZONE 1
A4a FOUNDATION FINISHED, A2a UPPER GROUND FLOOR FINISHED, A1 2nd FLOOR STARTED
ZONE 2
A3 FOUNDATION FINISHED, A1 SOG FINISHED, 2 TOWER CRANES ARE ERECTED
ZONE 3
A1a & A3a FOUNDATION FINISHED, A2 SOG FINISHED, A2 UPPER GROUND FLOOR STARTED
11. WEEK 12
ZONE 1
A4b FOUNDATION FINISHED, A4a SOG FINISHED, A3a UGF FINISHED, A1 2nd FLOOR FINISHED
ZONE 2
A4 FOUNDATION FINISHED, A3a SOG FINISHED, A1 UPPER GROUND FLOOR STARTED
ZONE 3
A1b & A3b FOUNDATION FINISHED, A3 & A1a SOG FINISHED, A2 UPPER GROUND FLOOR FINISHED
12. WEEK 16
ZONE 1
A6a FOUNDATION FINISHED, A5 SOG FINISHED, A4a UGF FINISHED, A2a 2nd FLOOR FINISHED
ZONE 2
A4a SOG FINISHED, A2 UPPER GROUND FLOOR FINISHED, A1 2ND FLOOR STARTED
ZONE 3
A4&A5a FOUNDATION FINISHED, A1&A4 SOG FINISHED, A3 UGF FINISHED, A1 2ND FLR. STARTED
13. WEEK 24
ZONE 1
A6 UPPER GROUND FLOOR FINISHED, A4 2nd FLOOR FINISHED, A1 3RD FLOOR STARTED
ZONE 2
A4 UPPER GROUND FLOOR FINISHED, A3a 2ND FLOOR FINISHED
ZONE 3
A5 UPPER GROUND FLOOR FINISHED, A3a 2ND FLOOR FINISHED
ZONE 4
A3 FOUNDATION FINISHED, A1 SLAB-ON-GRADE STARTED
ZONE 5
A1 FOUNDATION STARTED
14. WEEK 26
ZONE 1
A5a 2nd FLOOR FINISHED, A1a 3RD FLOOR FINISHED
ZONE 2
A3 2ND FLOOR FINISHED, A1 3RD FLOOR STARTED
ZONE 3
A1 3RD FLOOR STARTED
ZONE 4
A4 FOUNDATION FINISHED, A2 SLAB-ON-GRADE FINISHED
ZONE 5
A4 FOUNDATION FINISHED, A1 SLAB-ON-GRADE STARTED
15. WEEK 30
ZONE 1
A6 2nd FLOOR FINISHED, A2a 3RD FLOOR FINISHED
ZONE 2
A4 2ND FLOOR FINISHED, A2a 3RD FLOOR FINISHED
ZONE 3
A5a 2ND FLOOR FINISHED, A2a 3RD FLOOR FINISHED
ZONE 4
A5 FOUNDATION FINISHED,A3 SOG FINISHED, A2 UGF FINISHED
ZONE 5
A4 FOUNDATION FINISHED,A2 SOG FINISHED
16. WEEK 34
ZONE 1
A3a 3RD FLOOR FINISHED, A1 4TH FLOOR STARTED
ZONE 2
A3a 3RD FLOOR FINISHED, A1 4TH FLOOR STARTED
ZONE 3
A5 2ND FLOOR FINISHED, A3a 3RD FLOOR FINISHED
ZONE 4
A4 SOG FINISHED, A5 UPPER GROUND FLOOR FINISHED, A21 2ND FLOOR STARTED
ZONE 5
A3 FOUNDATION FINISHED,A3 SOG FINISHED, A2 UGF FINISHED
17. WEEK 38
ZONE 1
A5a 3RD FLOOR FINISHED, A2 4TH FLOOR FINISHED
ZONE 2
A4 3RD FLOOR FINISHED, A2 4TH FLOOR FINISHED
ZONE 3
A5a 3RD FLOOR FINISHED, A3 4TH FLOOR STARTED
ZONE 4
A5 UPPER GROUND FLOOR FINISHED, A5 2ND FLOOR FINISHED, A1 3RD FLOOR FINISHED
ZONE 5
A4 SOG FINISHED, A4 UGF FINISHED
18. WEEK 42
ZONE 1
A6 3RD FLOOR FINISHED, A4a 4TH FLOOR FINISHED
ZONE 2
A3 4TH FLOOR FINISHED
ZONE 3
A5 3RD FLOOR FINISHED, A4 4TH FLOOR SFINISHED
ZONE 4
A31 2ND FLOOR FINISHED, A31 3RD FLOOR FINISHED, A11 4TH FLOOR STARTED
ZONE 5
A6 FOUNDATION FINISHED, A2 SLAB-ON-GRADE FINISHED
19. WEEK 46
ZONE 1
A6 4TH FLOOR FINISHED
ZONE 2
A4 4TH FLOOR FINISHED
ZONE 3
A4 4TH FLOOR SFINISHED
ZONE 4
A31 4TH FLOOR FINISHED, A11 UPPER LEVEL STARTED
ZONE 5
A4 SLAB-ON-GRADE FINISHED, A6 UPPER GROUND FLOOR FINISHED, 2ND & 3RD FLOOR STARTED
20. WEEK 50
ZONE 1
COMPLETED
ZONE 2
COMPLETED
ZONE 3
COMPLETED
ZONE 4
A31 UPPER LEVEL FINISHED
ZONE 5
A6 SOG FINISHED, A6 UGF FINISHED, A4 2ND FLOOR FINISHED, A2 3RD FLOOR FINISHED
21. WEEK 54
ZONE 1
COMPLETED
ZONE 2
COMPLETED
ZONE 3
COMPLETED
ZONE 4
COMPLETED
ZONE 5
A6 UGF FINISHED, A6 2ND FLOOR FINISHED, A6RD FLOOR FINISHED, A2 4TH FLOOR FINISHED
22. WEEK 58
ZONE 1
COMPLETED
ZONE 2
COMPLETED
ZONE 3
COMPLETED
ZONE 4
COMPLETED
ZONE 5
A6 3RD FLOOR FINISHED, A4 4TH FLOOR FINISHED
23. WEEK 60
ZONE 1
COMPLETED
ZONE 2
COMPLETED
ZONE 3
COMPLETED
ZONE 4
COMPLETED
ZONE 5
A6 4TH FLOOR FINISHED, A2 UPPER LEVEL FINISHED
TOTAL CONCRETE
VOLUME as per
DD02Jul=54,000 m3