ID Task 
Mode
Task Name Duration Start Finish Work
1 GENERAL REQUIREMENTS 214 days July 3, 2015 March 8, 2016 19,410 hrs
34 MATERIAL DELIVERIES 182 days July 3, 2015 January 30, 2016 0 hrs
476 SITE PREPARATION & CONCRETING ACCESS FINISH MILESTONE 132.4 days July 3, 2015 December 4, 2015 0 hrs
521 HEAP LEACH CONSTRUCTION FINISH MILESTONES 184 days August 7, 2015 March 9, 2016 0 hrs
522 PHASE 1 EERI BF (DRY PLANT) 156.4 days September 8, 2015 March 9, 2016 0 hrs
544 PHASE 2 ENIKON (WET PLANT) 122.4 days September 28, 2015February 17, 2016 0 hrs
550 PHASE 3 ENIKON (LEACH) 155 days August 7, 2015 February 4, 2016 0 hrs
561 CONSTRUCTION 247.4 days July 3, 2015 April 16, 2016 1,017,316 hrs
562 PHASE 1 EERI BF (DRY PLANT) 235 days July 3, 2015 April 1, 2016 522,354 hrs
563 EARTHWORKS & SITE PREPARATIONS (BISSA) 0 hrs
564 126‐PCS‐2 PRIMARY CRUSHER, STRUCTURE, TRAIN 2 217 days July 3, 2015 March 12, 2016 60,248 hrs
667 126‐PCS‐1 PRIMARY CRUSHER, STRUCTURE, TRAIN 1 233 days July 3, 2015 March 31, 2016 60,181 hrs
770 126‐CV‐201 SCREEN FEED CONVEYOR, TRAIN2 182.4 days July 20, 2015 February 17, 2016 10,060 hrs
800 126‐CV‐101 SCREEN FEED CONVEYOR, TRAIN 1 186 days July 20, 2015 February 22, 2016 10,060 hrs
830 126‐TMS‐02 PC TRAMP MAGNET STATION, TRAIN 2 223 days July 3, 2015 March 18, 2016 26,100 hrs
873 126‐TMS‐01 PC TRAMP MAGNET STATION, TRAIN 1 218 days July 3, 2015 March 12, 2016 26,100 hrs
916 126‐PCSS PRIMARY CRUSHER‐ MCC 195.4 days July 20, 2015 March 3, 2016 11,834 hrs
958 126‐CV‐202 PRIMARY CONVEYOR, TRAIN 2 178.4 days August 5, 2015 February 29, 2016 28,361 hrs
997 126‐CV‐102 PRIMARY CONVEYOR, TRAIN 1 137.4 days August 21, 2015 January 28, 2016 28,361 hrs
1036 126‐TU‐202 SCREEN FEED, TAKEUP TOWER, TRAIN 2 174 days July 20, 2015 February 6, 2016 18,260 hrs
1064 126‐TU‐102 SCREEN FEED, TAKEUP TOWER, TRAIN 1 175 days July 20, 2015 February 8, 2016 18,260 hrs
1092 127‐SC2 SECONDARY CRUSHING & SCREENING, TRAIN 2 235 days July 3, 2015 April 1, 2016 42,101 hrs
1177 127‐SC1 SECONDARY CRUSHING & SCREENING, TRAIN 1 222 days July 4, 2015 March 18, 2016 42,101 hrs
1262 127‐CV‐203 SC DISCHARGE CONVEYOR, TRAIN 2 195 days July 3, 2015 February 15, 2016 17,801 hrs
1298 127‐CV‐103 SC DISCHARGE CONVEYOR, TRAIN 1 195 days July 3, 2015 February 15, 2016 17,801 hrs
1334 127‐TS CONVEYOR TRANSFER STATION 96.1 days July 3, 2015 October 23, 2015 8,499 hrs
1351 128‐CVR‐OL OVERLAND MODULE TAIL END 185.5 days July 3, 2015 February 4, 2016 17,802 hrs
1385 128‐CVR‐OL OVERLAND MODULE 200.5 days July 3, 2015 February 22, 2016 25,500 hrs
1407 128‐CVR‐OL OVERLAND MODULE TAKE UP TRUSSES 192.8 days July 28, 2015 March 9, 2016 35,564 hrs
1467 128‐TU OVERLAND CONVEYOR TAKE‐UP 175.8 days August 26, 2015 March 18, 2016 7,460 hrs
1495 128‐SAMPLER REJECT COVENYOUR 186.3 days July 3, 2015 February 5, 2016 9,900 hrs
1517 PHASE 2 ENIKON (WET PLANT) 247.4 days July 3, 2015 April 16, 2016 209,332 hrs
1975 PHASE 3 ENIKON (LEACH) 229.4 days July 3, 2015 March 26, 2016 285,630 hrs
2507 PRECOMMISSIONINGS & COMMISSIONINGS 215.6 days October 14, 2015 June 22, 2016 34,200 hrs
2508 EXTERNAL CONNECTION WORKS 116.8 days November 13, 2015 March 29, 2016 27,550 hrs
2509 ELECTRICAL CONNECTIONS TO AREAS 116.8 days November 13, 2015 March 29, 2016 9,050 hrs
2560 COMMUNICATION & CONTROL ROOM 55 days December 26, 2015 February 29, 2016 3,500 hrs
2601 MECHANICAL PIPING CONNECTION TO AREAS 31 days January 18, 2016 February 22, 2016 15,000 hrs
2632 COMMISSIONING SCHEDULE 215.6 days October 14, 2015 June 22, 2016 6,650 hrs
2633 TEMPORARY 11kV POWER to TRAIN 2 CRUSHING 
TRANSFORMER
101 days December 22, 2015 April 16, 2016 600 hrs
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0
0%
0%
0%
0%
0
0%
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2016
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start‐only
Finish‐only
Duration‐only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
BHP01‐1.6(Bouly Baseline)
Page 1
ID Task 
Mode
Task Name Duration Start Finish Work
2647 TEMPORARY 11kV POWER to TRAIN 1 CRUSHING 
TRANSFORMER
60 days February 6, 2016 April 15, 2016 500 hrs
2659 CONVEYING & STACKING 72.8 days January 2, 2016 March 28, 2016 500 hrs
2671 AGGLOMERATION SWITCHROOM COMMISSIONING 43 days February 15, 2016 April 5, 2016 450 hrs
2682 HEAP LEACH SWITCHROOM 13.8 days March 19, 2016 April 5, 2016 150 hrs
2683 Electrictrical Tie in 13.8 days March 19, 2016 April 5, 2016 150 hrs
2687 RAW WATER SYSTEM (OS‐15) 151.2 days October 14, 2015 April 7, 2016 1,450 hrs
2719 BLS SYSTEM (OS‐008) 47.8 days February 9, 2016 April 5, 2016 300 hrs
2728 ILS SYSTEM (OS‐009) 71 days February 24, 2016 May 17, 2016 250 hrs
2736 PLS SYSTEM (OS‐010) 80.8 days February 24, 2016 May 28, 2016 300 hrs
2745 ADSORPTION (OS‐012) 41.4 days February 25, 2016 April 13, 2016 300 hrs
2754 CAUSTIC & CYANIDE (OS‐13 & OS‐14) 51.4 days February 6, 2016 April 6, 2016 300 hrs
2763 PLANT AIR CRUSHER (OS‐017A) 0.8 days March 25, 2016 March 26, 2016 50 hrs
2765 PLANT AIR TREATMENT(OS‐017B) 26.2 days February 1, 2016 March 2, 2016 150 hrs
2769 CRUSHING WATER 0.8 days March 1, 2016 March 2, 2016 50 hrs
2771 ORE COMMISSIONING 59.2 days April 14, 2016 June 22, 2016 1,300 hrs
2779 GOLD POUR 0 days June 22, 2016 June 22, 2016 0 hrs
2781 HAND‐OVER & COMPLETION 0 days June 22, 2016 June 22, 2016 0 hrs
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0
6
6
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun
2016
Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start‐only
Finish‐only
Duration‐only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
BHP01‐1.6(Bouly Baseline)
Page 2

More Related Content

Similar to BHP01-0 Bouly baseline on MSproject Format (8)

Sample MSProject with 16 DivisionFormat Variation(EOT)
Sample MSProject with 16 DivisionFormat Variation(EOT)Sample MSProject with 16 DivisionFormat Variation(EOT)
Sample MSProject with 16 DivisionFormat Variation(EOT)
 
Project master schedule daughter station cng mini plant
Project master schedule daughter station cng mini plantProject master schedule daughter station cng mini plant
Project master schedule daughter station cng mini plant
 
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)  WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
 
QCon2015 NoSQLWithCachingSearchAndRealTimeAnalytics
QCon2015 NoSQLWithCachingSearchAndRealTimeAnalyticsQCon2015 NoSQLWithCachingSearchAndRealTimeAnalytics
QCon2015 NoSQLWithCachingSearchAndRealTimeAnalytics
 
Project Planning And Control Club house design with MSP
Project Planning And Control Club house design with MSPProject Planning And Control Club house design with MSP
Project Planning And Control Club house design with MSP
 
PCAPP Update 30 April 2014
PCAPP Update 30 April 2014PCAPP Update 30 April 2014
PCAPP Update 30 April 2014
 
Slide4 mp psht1of6
Slide4 mp psht1of6Slide4 mp psht1of6
Slide4 mp psht1of6
 
G-K Section PPT .pptx
G-K Section PPT .pptxG-K Section PPT .pptx
G-K Section PPT .pptx
 

More from Allan Leyte

Construction Methodology Scheduling1
Construction Methodology Scheduling1Construction Methodology Scheduling1
Construction Methodology Scheduling1
Allan Leyte
 
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Allan Leyte
 
PRODUCTION RATE APPX. NEW
PRODUCTION RATE APPX. NEWPRODUCTION RATE APPX. NEW
PRODUCTION RATE APPX. NEW
Allan Leyte
 
Sample of Structural Steel Scheduling
Sample of Structural Steel SchedulingSample of Structural Steel Scheduling
Sample of Structural Steel Scheduling
Allan Leyte
 
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Allan Leyte
 
Visio-Planning FlowChart-3
Visio-Planning FlowChart-3Visio-Planning FlowChart-3
Visio-Planning FlowChart-3
Allan Leyte
 
Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016
Allan Leyte
 
Booster Pump cause of delay analysis
Booster Pump cause of delay analysisBooster Pump cause of delay analysis
Booster Pump cause of delay analysis
Allan Leyte
 
Sample Bidcom Presentation - Structural Works 12-28-11
Sample Bidcom Presentation - Structural Works 12-28-11Sample Bidcom Presentation - Structural Works 12-28-11
Sample Bidcom Presentation - Structural Works 12-28-11
Allan Leyte
 
Scheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPMScheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPM
Allan Leyte
 
Offshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocolOffshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocol
Allan Leyte
 
Town Center presentation
Town Center presentationTown Center presentation
Town Center presentation
Allan Leyte
 

More from Allan Leyte (16)

Construction Methodology Scheduling1
Construction Methodology Scheduling1Construction Methodology Scheduling1
Construction Methodology Scheduling1
 
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
 
WEIGHTING TABLE
WEIGHTING TABLEWEIGHTING TABLE
WEIGHTING TABLE
 
PRODUCTION RATE APPX. NEW
PRODUCTION RATE APPX. NEWPRODUCTION RATE APPX. NEW
PRODUCTION RATE APPX. NEW
 
Sample of Structural Steel Scheduling
Sample of Structural Steel SchedulingSample of Structural Steel Scheduling
Sample of Structural Steel Scheduling
 
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
 
p3 s-curves
p3 s-curvesp3 s-curves
p3 s-curves
 
Wreport
WreportWreport
Wreport
 
Visio-Planning FlowChart-3
Visio-Planning FlowChart-3Visio-Planning FlowChart-3
Visio-Planning FlowChart-3
 
Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016
 
Booster Pump cause of delay analysis
Booster Pump cause of delay analysisBooster Pump cause of delay analysis
Booster Pump cause of delay analysis
 
Sample Bidcom Presentation - Structural Works 12-28-11
Sample Bidcom Presentation - Structural Works 12-28-11Sample Bidcom Presentation - Structural Works 12-28-11
Sample Bidcom Presentation - Structural Works 12-28-11
 
Scheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPMScheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPM
 
Offshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocolOffshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocol
 
progress photos
progress photosprogress photos
progress photos
 
Town Center presentation
Town Center presentationTown Center presentation
Town Center presentation
 

BHP01-0 Bouly baseline on MSproject Format

  • 1. ID Task  Mode Task Name Duration Start Finish Work 1 GENERAL REQUIREMENTS 214 days July 3, 2015 March 8, 2016 19,410 hrs 34 MATERIAL DELIVERIES 182 days July 3, 2015 January 30, 2016 0 hrs 476 SITE PREPARATION & CONCRETING ACCESS FINISH MILESTONE 132.4 days July 3, 2015 December 4, 2015 0 hrs 521 HEAP LEACH CONSTRUCTION FINISH MILESTONES 184 days August 7, 2015 March 9, 2016 0 hrs 522 PHASE 1 EERI BF (DRY PLANT) 156.4 days September 8, 2015 March 9, 2016 0 hrs 544 PHASE 2 ENIKON (WET PLANT) 122.4 days September 28, 2015February 17, 2016 0 hrs 550 PHASE 3 ENIKON (LEACH) 155 days August 7, 2015 February 4, 2016 0 hrs 561 CONSTRUCTION 247.4 days July 3, 2015 April 16, 2016 1,017,316 hrs 562 PHASE 1 EERI BF (DRY PLANT) 235 days July 3, 2015 April 1, 2016 522,354 hrs 563 EARTHWORKS & SITE PREPARATIONS (BISSA) 0 hrs 564 126‐PCS‐2 PRIMARY CRUSHER, STRUCTURE, TRAIN 2 217 days July 3, 2015 March 12, 2016 60,248 hrs 667 126‐PCS‐1 PRIMARY CRUSHER, STRUCTURE, TRAIN 1 233 days July 3, 2015 March 31, 2016 60,181 hrs 770 126‐CV‐201 SCREEN FEED CONVEYOR, TRAIN2 182.4 days July 20, 2015 February 17, 2016 10,060 hrs 800 126‐CV‐101 SCREEN FEED CONVEYOR, TRAIN 1 186 days July 20, 2015 February 22, 2016 10,060 hrs 830 126‐TMS‐02 PC TRAMP MAGNET STATION, TRAIN 2 223 days July 3, 2015 March 18, 2016 26,100 hrs 873 126‐TMS‐01 PC TRAMP MAGNET STATION, TRAIN 1 218 days July 3, 2015 March 12, 2016 26,100 hrs 916 126‐PCSS PRIMARY CRUSHER‐ MCC 195.4 days July 20, 2015 March 3, 2016 11,834 hrs 958 126‐CV‐202 PRIMARY CONVEYOR, TRAIN 2 178.4 days August 5, 2015 February 29, 2016 28,361 hrs 997 126‐CV‐102 PRIMARY CONVEYOR, TRAIN 1 137.4 days August 21, 2015 January 28, 2016 28,361 hrs 1036 126‐TU‐202 SCREEN FEED, TAKEUP TOWER, TRAIN 2 174 days July 20, 2015 February 6, 2016 18,260 hrs 1064 126‐TU‐102 SCREEN FEED, TAKEUP TOWER, TRAIN 1 175 days July 20, 2015 February 8, 2016 18,260 hrs 1092 127‐SC2 SECONDARY CRUSHING & SCREENING, TRAIN 2 235 days July 3, 2015 April 1, 2016 42,101 hrs 1177 127‐SC1 SECONDARY CRUSHING & SCREENING, TRAIN 1 222 days July 4, 2015 March 18, 2016 42,101 hrs 1262 127‐CV‐203 SC DISCHARGE CONVEYOR, TRAIN 2 195 days July 3, 2015 February 15, 2016 17,801 hrs 1298 127‐CV‐103 SC DISCHARGE CONVEYOR, TRAIN 1 195 days July 3, 2015 February 15, 2016 17,801 hrs 1334 127‐TS CONVEYOR TRANSFER STATION 96.1 days July 3, 2015 October 23, 2015 8,499 hrs 1351 128‐CVR‐OL OVERLAND MODULE TAIL END 185.5 days July 3, 2015 February 4, 2016 17,802 hrs 1385 128‐CVR‐OL OVERLAND MODULE 200.5 days July 3, 2015 February 22, 2016 25,500 hrs 1407 128‐CVR‐OL OVERLAND MODULE TAKE UP TRUSSES 192.8 days July 28, 2015 March 9, 2016 35,564 hrs 1467 128‐TU OVERLAND CONVEYOR TAKE‐UP 175.8 days August 26, 2015 March 18, 2016 7,460 hrs 1495 128‐SAMPLER REJECT COVENYOUR 186.3 days July 3, 2015 February 5, 2016 9,900 hrs 1517 PHASE 2 ENIKON (WET PLANT) 247.4 days July 3, 2015 April 16, 2016 209,332 hrs 1975 PHASE 3 ENIKON (LEACH) 229.4 days July 3, 2015 March 26, 2016 285,630 hrs 2507 PRECOMMISSIONINGS & COMMISSIONINGS 215.6 days October 14, 2015 June 22, 2016 34,200 hrs 2508 EXTERNAL CONNECTION WORKS 116.8 days November 13, 2015 March 29, 2016 27,550 hrs 2509 ELECTRICAL CONNECTIONS TO AREAS 116.8 days November 13, 2015 March 29, 2016 9,050 hrs 2560 COMMUNICATION & CONTROL ROOM 55 days December 26, 2015 February 29, 2016 3,500 hrs 2601 MECHANICAL PIPING CONNECTION TO AREAS 31 days January 18, 2016 February 22, 2016 15,000 hrs 2632 COMMISSIONING SCHEDULE 215.6 days October 14, 2015 June 22, 2016 6,650 hrs 2633 TEMPORARY 11kV POWER to TRAIN 2 CRUSHING  TRANSFORMER 101 days December 22, 2015 April 16, 2016 600 hrs 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0 0% 0% 0% 0% 0 0% Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2016 Critical Critical Split Critical Progress Task Split Task Progress Manual Task Start‐only Finish‐only Duration‐only Baseline Baseline Split Baseline Milestone Milestone Summary Progress Summary Manual Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Deadline BHP01‐1.6(Bouly Baseline) Page 1
  • 2. ID Task  Mode Task Name Duration Start Finish Work 2647 TEMPORARY 11kV POWER to TRAIN 1 CRUSHING  TRANSFORMER 60 days February 6, 2016 April 15, 2016 500 hrs 2659 CONVEYING & STACKING 72.8 days January 2, 2016 March 28, 2016 500 hrs 2671 AGGLOMERATION SWITCHROOM COMMISSIONING 43 days February 15, 2016 April 5, 2016 450 hrs 2682 HEAP LEACH SWITCHROOM 13.8 days March 19, 2016 April 5, 2016 150 hrs 2683 Electrictrical Tie in 13.8 days March 19, 2016 April 5, 2016 150 hrs 2687 RAW WATER SYSTEM (OS‐15) 151.2 days October 14, 2015 April 7, 2016 1,450 hrs 2719 BLS SYSTEM (OS‐008) 47.8 days February 9, 2016 April 5, 2016 300 hrs 2728 ILS SYSTEM (OS‐009) 71 days February 24, 2016 May 17, 2016 250 hrs 2736 PLS SYSTEM (OS‐010) 80.8 days February 24, 2016 May 28, 2016 300 hrs 2745 ADSORPTION (OS‐012) 41.4 days February 25, 2016 April 13, 2016 300 hrs 2754 CAUSTIC & CYANIDE (OS‐13 & OS‐14) 51.4 days February 6, 2016 April 6, 2016 300 hrs 2763 PLANT AIR CRUSHER (OS‐017A) 0.8 days March 25, 2016 March 26, 2016 50 hrs 2765 PLANT AIR TREATMENT(OS‐017B) 26.2 days February 1, 2016 March 2, 2016 150 hrs 2769 CRUSHING WATER 0.8 days March 1, 2016 March 2, 2016 50 hrs 2771 ORE COMMISSIONING 59.2 days April 14, 2016 June 22, 2016 1,300 hrs 2779 GOLD POUR 0 days June 22, 2016 June 22, 2016 0 hrs 2781 HAND‐OVER & COMPLETION 0 days June 22, 2016 June 22, 2016 0 hrs 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0 6 6 Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2016 Critical Critical Split Critical Progress Task Split Task Progress Manual Task Start‐only Finish‐only Duration‐only Baseline Baseline Split Baseline Milestone Milestone Summary Progress Summary Manual Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Deadline BHP01‐1.6(Bouly Baseline) Page 2