SlideShare a Scribd company logo
1 of 19
Nov, 2022
South Portfolio Projects Report
Projects Review Report
Jazan Division
11,670 km 25
Municipality
13
Governorate
31
Markez
Jazan Area
2
South Department Projects
NO
.
PROJECT NAME
Type of
project
Project
Progress
Statues
Contract Value
(SR)
Start Date
1 CONSTRUCTION OF NEW AL ASEELH ( ASL ) ( JAZAN -3 ) 380/132/13.8 KV BSP Critical 88.4% On going 228,000,400 01/06/2020
2
CONSTRUCTION OF TWO (2) 380KV DOUBLE CIRCUIT OHTL BETWEEN ASL –KDM ( AND ASL-
MDY
Critical 95.6% On going 61,050,000 12/07/2020
3 CONSTRUCTION OF ASL –SHQ (CKT-1) AND ASL-SHQ-2 (CKT-1) Critical 83.2% On going 190,378,997 19/10/2020
4 INSTALLATION OF DRPC AND EXPANSION OF 132 K.V. GIS AT KUDMI BSP Critical 28.1% On going 155,000,000 30/12/2020
5 CONNECTING AL-ASEELAH CENTRAL STATION TO THE NETWORK 132 KV Normal 74% On going 30,414,564 30/09/2021
6 CONSTRUCTION OF ABU ARISH-2 132/13.8 KV SS Normal 85.3% On going 41,794,500 05/02/2020
7 CONSTRUCTION OF 132KV D/C OHTLTO SUPPLY POWER TO ABU ARISH-2 132/13.8KV S/S Normal 79% On going 12,400,000 27/01/2020
8 CONSTRUCTION OF ZARGA-2 132/13.8 KV Normal 85% On going 42,609,562 23/03/2020
9 POWER SUPPLY TO HOUSING PROJECT (STAGE-1) OF MINISTRY OF DEFENCE IN JIZAN Normal 74.2% On going 100,281,838 07/02/2021
10 CONNECTION OF AL ARIDAH , AYBAN AND AD DAYIR 132KV SS IN JAZAN WITH NETWORKS Normal 83.9%
On going
Partial Energized
39,200,000 23/03/2021
11 ADDITION OF THIRD TRANSFORMER TO AL-HAQU 132/33 KV S/S Normal 95% On going 25,190,000 25/10/2017
12
CONSTRUCTION OF 132KV D/C OHTL BETWEEN ABU QAEED132KV S/S AND AL HAQU
132KV S/S
Normal 10% On going 48,104,420.00 11/05/2022
13
CONSTRUCTION OF DHAHYAH HOUSING 132/13.8 kV SUBSTATION IN JIZAN AREA
Normal 4.28% On going 74,495,088 31/05/2022
14 CONNECTION OF DHAHYAH HOUSING 132/13.8KV S/S WITH JIZAN UNIVERSITY Normal 0% On going 13,335,000 30/04/2020
15
RCJ 380/132/33KV BSP SS1A SS & OHTL BETWEEN RCJ BSP – KUDMI BSP AND RCJ BSP –
JRP BSP
Normal 3.5% On going 437,535,484 15/07/2020
Total 56.1% - 1,500,055,428 -
Projects Summary
PROJECT PHASE
BLOCK DIAGRAM
PROGRESS
Start Date Status TCC
01 Jun 2020 Under Commissioning 31 Mar 2023
PROJECT DETAILS
Contract Title CONSTRUCTION OF NEW AL ASEELH ( ASL )
( JAZAN -3 ) 380/132/13.8 KV BSP
Contract No 4400013230
Contractor NCC
Contract Value 228,000,400 SR.
Approved Invoices 164,046,288 (72%) SR.
Design Material Constructions Installations Commissioning
99.5% 99.6% 87% 87.8% 44%
2019 2020 2021 2022 2023
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
.
TCC(Expected)
31-03-2023
01-06-2020 88.4%
TCC(Contractual)
31-12-2021
Issues
• delays in review of submittal it was affected severely material procurement/delivery. ( solved )
• Delivery of 132kV LCC are delayed (2nd lot delivered, 3rd lot will be delivered by 10.05.2022).( Solved)
• Damaged 06 ACDB cubicles delivery . Planned delivery date at site 10.10.2022. ( solved )
• 48V Battery charger and battery bank delivery will be delivered by end of Nov2022.( solved )
Critical
Project
4
MDY 380 BSP Kudmi BSP
NEW
Existing
SHQ 1 BSP SHQ 2 BSP
NEW AL ASEELH 380
22.5KM
22.5KM
82KM
4KM
2.8KM
11.2KM
140.5KM
380kV GIS 7 Dia. (21 C.B) ABB Installation 100%
132kV GIS 30 C.B ABB, KSA Installation 100%
EHV Transformer 3*502MVA Hyosung Installation 100%
HV Transformer 3*67MVA SPTC Installation 100%
Shunt Reactor 1*120MVAR Hyosung Installation 100%
Control panels 4 Lots (216) Alfanar Installation 100%
13.8kV C.B 44 C.B Alfanar Installation 100%
SAS/FO 20 panels Alfanar Installation 100%
Communication Lot. GE, KSA Installation 90%
PROGRESS PROJECT PHASE
BLOCK DIAGRAM
Start Date Status TCC
12 Jul 2020 Under construction 31 Dec 2022
Issues
• ROW issues with landowners (Solved)
• Manpower availability due to flight restrictions. (Solved)
• Required shutdown for KDM-MDY line, plan shutdown on 18.12.20222
Length No# Tower No# Foundation
44.54 Km 116 116
42.598 Km 113 116
PROJECT DETAILS
Contract Title CONSTRUCTION OF TWO (2) 380KV D/C OHTL
BETWEEN ASL-KDM & ASL-MDY
Contract No 4400013424
Contractor NPCC
Contract Value 61,050,000 SR.
Approved Invoices 47,013,376 (77%) SR.
Design Material Constructions Installations Testing
99.5% 99.9% 100% 94.92% 0%
2019 2020 2021 2022 2023
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
.
TCC (Expected)
31-03-2023
12-07-2020 95.6%
TCC(Contractual )
31-12-2022
Critical
Project
5
MDY 380 BSP Kudmi BSP
NEW
Existing
SHQ 1 BSP SHQ 2 BSP
NEW AL ASEELH 380
22.5KM
22.5KM
82KM
4KM
2.8KM
11.2KM
140.5KM
2019 2020 2021 2022 2023
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
.
PROJECT PHASE
BLOCK DIAGRAM
PROGRESS
PROJECT DETAILS
Contract Title CONSTRUCTION OF ONE (1) 380KV D/C OHTL
BETWEEN ASL –SHQ -1 AND ASL-SHQ-2
Contract No 4400013836
Contractor NPCC
Contract Value 190,378,997 SR.
Approved Invoices 131,253,267 (68.8%) SR.
Start Date Status TCC
19 Oct 2020 Under construction 18 Jun 2022
Issues
• ROW issues with landowners and Mohafza of Sabya (Solved)
• Manpower availability due to flight restrictions. (Solved)
• ROW stop by Municipality Wady Jazan. (Solved)
• delivery of balance Spacer Dampers (54%) delayed by PTE since of AUG 2021. (Solved)
• Delay delivery of 17towers of Steel Structure from Babtain, Planned delivery date at site end of Dec-22
• Outage for around 10 No. of Existing 132kV OHTL Over Crossing and for tapping.
Length No# Tower No# Foundation
140.35 km 373 373
57.1 km 319 357
19-10-2020 83.2% TCC(Expected)
30-11-2023
Design Material Constructions Installations Testing
97.4% 99.5% 94% 66% 0%
Critical
Project
6
MDY 380 BSP Kudmi BSP
NEW
Existing
SHQ 1 BSP SHQ 2 BSP
NEW AL ASEELH 380
22.5KM
22.5KM
82KM
4KM
2.8KM
11.2KM
140.5KM
PROJECT PHASE
BLOCK DIAGRAM
PROGRESS
PROJECT DETAILS
Contract Title CONNECTING AL-ASEELAH CENTRAL STATION TO
THE NETWORK 132 KV
Contract No 4400015320
Contractor AL SHARIF GROUP FOR CONTR
Contract Value 30,414,564 SR.
Approved Invoices 21,498,804 (70%) SR.
Start Date Status TCC
30 Sep 2021 Under construction 30 Nov 2022
Issues
• Delayed work permits from the Ministry of Transport. (Solved).
• The reply from S/S Contractor regarding Steel Support inside Basement. (Solved).
• Conflict with MV contractors in the same route of power cables. (Solved).
• Conflict with MV Contractors in the same route of power cable. (Solved).
2021 2022 2023
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
30-09-2021 74 %
TCC(Expected)
31-03-2023
NEW
Existing
JIZAN CPS -2
132.13.8
1.65
KM
Length Join Bay
6 section 4CKT * (1.65 km)*3= 19.8 km 4
4 section 16 km 1
ABU ARISH
132/33 KV
NEW AL ASEELH 380
King Fahad Hospital
132/13.8 kv
Design Material Construction Installations Testing
96% 94 % 71 % 70 % 0 %
TCC(Contractual )
30-11-2022
Normal
Project
7
8KM
3.5KM
1.5KM
PROJECT PHASE
BLOCK DIAGRAM
PROGRESS
PROJECT DETAILS
Contract Title INSTALLATION OF DRPC AND EXPANSION OF 132
K.V. GIS AT KUDMI BSP
Contract No 4400014231
Contractor SIEMENS
Contract Value 155,000,000 SR.
Approved Invoices 6,050,351(3.9%) SR.
Start Date Status TCC
30 Dec 2020 Under construction 28 Feb 2023
Issues
• Lack response from contractor.
• Design submission for remaining equipment (Capacitor Banks, Disconnections & Resistors & Earthing Switches)
• Accelerate Manufacturing for approved materials.
• Main Equipment still not Delivered Yet.
2020 2021 2022 2023
Q3Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
.
30-12-2020
TCC Contractual
28-02-2023
29 %
NEW
Existing
INSTALLATION OF
DRPC IN KUDMI
Design Material Constructions Installations Testing
61% 38% 33% 0% 0%
Critical
Project
8
600 MVA Transformer 2*600 MVA Hyundai Electric, Korea Under manufacturing
132KV GIS
1 Bay
GE, KSA Under design review
Thyristors and
Converters
2 Lot
Siemens Energy,
Germany
Delivered
MV SWGR 33 KV 2 * 33 kV Siemens, KSA Under manufacturing
Communication
Equipment
Lot Hitachi Energy, KSA Under manufacturing
Battery & Charger
2 Piece(125 VDC)
Statron, UAE
Under manufacturing
Air Core Reactor 2 Lot Trench GmbH, Germany Under manufacturing
Wall Bushings 12 Piece MGC, Germany Under manufacturing
Surge Arresters 1*120KV
Siemens Energy,
Germany
Delivered
Capacitor Banks
2 Piece
Samwah, Korea
Eaton, Germany
Under design review
MV SWGR 13.8 KV 2* 13.5 KV
Al-Fanar, KSA Under design review
PROJECT PHASE
BLOCK DIAGRAM
PROGRESS
PROJECT DETAILS
Contract Title CONSTRUCTION OF ABU ARISH-2 132/13.8 KV SS
Contract No 4400013046
Contractor HAIF COMPANY
Contract Value 41,794,500 SR.
Approved Invoices 18,573,957 (44.44%) SR.
Start Date Status TCC
05 Feb 2020 Under construction 05 Jun 2023
2020 2021 2022 2023
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
.
05-02-2020
85.3 %
TCC (Contractual)
05-06-2023
Issues
• Delivery of Power Transformers are delayed. Will be arrived at site on 30.11.2022.
Normal
Project
Design Material Constructions Installations Pre check
97% 96% 96% 98% 5%
132kV GIS 12 Bays HYOSUNG,KOREA Installation 100%
132kV Transformer 3*67MVA ABB NG SCOPE Not Delivered
(Expected delivery on
30/11/2022)
SWG 51 CB ALFANAR, KSA Installation 100%
Control panels Lot SEP ,KSA Installation 100%
AC/DC LOT ALFANAR, KSA AC/DC panels delivered
Aux TR 2 SFT, KSA Installation 100 %
Gantry &SA& CSE LOT ALNAFIE, KSA Installation 90%
SAS LOT ABB (HITACHI) Installation
Communication system LOT ABB, KSA FAT DONE
9
132
ASSALAMAH SUBSTATION
132/13.8 KV
NEW
Existing
NEW
Existing
ABU ARISH-2 132/13.8
KV SUBSTATION
5.96KM
6.8KM
15.8
KM
JAZAN CPS-2
SUBSTATION
132/33KV
PROJECT PHASE
PROGRESS
PROJECT DETAILS
Contract Title CONSTRUCTION OF 132KV D/C OHTLTO SUPPLY
POWER TO ABU ARISH-2 132/13.8KV S/S
Contract No 4400013011
Contractor NCC
Contract Value 12,400,000 SR.
Approved Invoices 7,461,044(66.4%) SR.
Start Date Status TCC
27 Jan 2020 Under construction 26 Jan 2023
Issues
• Delay of missing materials delivery to the site. (Solved).
• Outgas plan on 18.12.2022.
Length NO. of Tower No# Foundation
12 KM 36 36
7.85 KM 34 36
BLOCK DIAGRAM
132
ASSALAMAH SUBSTATION
132/13.8 KV
NEW
Existing
NEW
Existing
ABU ARISH-2 132/13.8
KV SUBSTATION
JAZAN CPS-2
SUBSTATION
132/33KV
Normal
Project
Design Material Constructions Installations Testing
86 % 98.5% 95 % 50 % 0 %
2019 2020 2021 2022 2023
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
.
27-01-2020 79 % TCC (Contractual)
26-01-2023
10
5.96KM
6.8KM
15.8
KM
PROJECT PHASE
BLOCK DIAGRAM
PROGRESS
PROJECT DETAILS
Contract Title CONSTRUCTION OF ZARGA-2 132/13.8 KV
Contract No 4400013117
Contractor AL SHARIF GROUP
Contract Value 42,609,562 SR.
Approved Invoices 26,346,723(61.82%) SR.
Start Date Status TCC
23 Mar 2020 Under construction 1 Jun 2023
2020 2021 2022 2023
Q1Q2Q3Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
.
23-03-2020
85%
Issues
• Delayed of arrived Material (power transformer) . Will be shipping to site on 15/11/2022.
• poor performance of contractor to start pre-commissioning.
TCC (Expected)
01-06-2023
132
0.2 KM
JAZAN CPS-1
132/33 KV
NEW
Existing
NEW
Existing
ZARGA-2 132/13.8 KV
SUBSTATION
KUDMI 132KV
SUBSTATION
Normal
Project
Design Material Constructions Installations Testing
99.8% 97.14% 95.25% 93.2% 0%
132kV GIS 12 Bay Hyosung Installation
Power Transformers 3*67 MVA ABB- Turkey Delivered
13.8kV Switchgear Room 48 CB ABB Installation
Control and Protection LOT ABB Installation
SAS LOT ABB FAT Done
AC/DC panels LOT ETA FAT Done
Battery Charger 2 STATRON Installation
Battery LOT HOPPECKE Installation
Communication System LOT ABB Installation
Auxiliary Xmer 2 UTEC Installation
OHTL Tower LOT AIC Installation
11
11KM
24KM
PROJECT PHASE
BLOCK DIAGRAM
PROGRESS
PROJECT DETAILS
Contract Title POWER SUPPLY TO HOUSING PROJECT (STAGE-1)
OF MINISTRY OF DEFENCE IN JIZAN
Contract No PTS16SN110
Contractor TDP
Contract Value 95,506,513.2 SR.
Approved Invoices 46,801,833 (46.67%) SR
Start Date Status TCC
01 March 2021 Under construction 07 Feb 2023
Issues
• (6) invoices payment from MOD to contractor.
• Change order for the conductors ( GZTACSR) .
• Waiting approval for shutdown.
2020 2021 2022 2023
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
.
01/03/2020 74.2 % TCC (Contractual & Expected)
07-02-2023
AD-Darb
132/33 KV
NEW
Existin
g
BAISH 132/33/13.8
KV SUBSTATION
HOUSING OF MINISTRY
OF DEFENCE IN JIZAN
1
KM
Normal
Project
Design Material Constructions Installations Testing
98 % 94% 84 % 52.2 % 0 %
33 KM
26 KM
OGW
Power Transformer 132kV 2*67MVA SPTC / Dammam Installation
GIS 132 kv 11 HHI/Korea Installation
Surge Arrester 132 kV 18 pcs TRIDELTA/Germany Installation
Cable Terminations 132kV Lot Jeddah Cables / KSA Installation
Towers 8 No AIC Steel/KSA Installation
Conductors ( GZTACSR) 195 km Sumitomo
Electric/Japan
Partial delivery
OPGW 4 km Prysmian/Spain Installation
Switch Gear Lot AES / KSA Installation
12
PROJECT PHASE
BLOCK DIAGRAM
PROGRESS
PROJECT DETAILS
Contract Title CONNECTION OF AL ARIDAH , AYBAN AND AD
DAYIR 132KV SS IN JAZAN WITH NETWORKS
Contract No 4400013250
Contractor AL SHARIF GROUP FOR CONTR
Contract Value 39,200,000 SR.
Approved Invoices 22,295,584 (57%) SR.
Start Date Status TCC
23 Mar 2020 Under construction 22-May 2023
2020 2021 2022 2023
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
.
23-03-2020
83.9%
TCC (Expected)
13-05-2023
New Line NO. of Tower NO. of foundation
28 KM 90 90
Completed 89 89
Normal
Project
Design Material Constructions Installations Testing
98 % 89 % 96 % 75 % 0 %
Reconductoring NO. of Tower 1st 2nd Circuit
17 KM 55 55
Completed 55 0
Issues
• Substation modification Design in Ayban & Al Dayer.
• ABB response is awaited regarding finalization of CT in side GIS at Ayban S/S.
• One Tap-off Tower will be constructed during Outage of CKT-2 of Ayban - Ad Dayir line.
• Waiting Shutdown for 2nd CKT of Ayban – Ad Dayir (17km Line).
Partial Energized
05-04-2022
13
AD DAYIR SS
132/33/13.8 KV
NEW
Existing
NEW
Existing
AYBAN SS
132/33 /13.18 KV
28KM AL ARIDAH SS
132/13.8 KV
16.5 KM
170M
16.7KM
PROJECT PHASE
BLOCK DIAGRAM
PROGRESS
PROJECT DETAILS
Contract Title ADDITION OF THIRD TRANSFORMER TO AL-HAQU
132/33 KV S/S.
Contract No 4400008427
Contractor GE
Contract Value 25,190,000 SR.
Approved Invoices 17,911,440 (71.1%) SR.
Start Date Status TCC
25 Oct 2016 Under construction 22 Jul 2023
Issues
• Negative Change order approval .
NEW
Existing
NEW
Existing
AL-HAQU 132/33 KV
EXPANSION
2016 2018 2022 2023
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q3 Q4
.
25-10-2016 95%
TCC (Expected)
22-07-2023
Normal
Project
Design Material Constructions Installations Testing
100% 100% 100% 100% 60%
14
33kV SWG 13 ABB Installation
DTCB 1 ABB Installation
Capacitor 1 GE Installation
HV cable 1drum Saudi Cables Installation
MV Cable 1drum Saudi Cables Installation
Protection panels Lots GE Installation
PROGRESS PROJECT PHASE
BLOCK DIAGRAM
Start Date Status TCC
11 May 2022 Under construction 21 Aug 2023
Issues :
Delay in Route approval.
Length No# Tower No# Foundation
24.4 Km 78 78
ABU QAEED
132KV SS
ALHAQU
132KV SS
24.4 KM
PROJECT DETAILS
Contract Title CONSTRUCTION OF 132KV D/C OHTL BETWEEN
ABU QAEED132KV S/S AND AL HAQU 132KV S/S
Contract No 4400016383
Contractor Raissy
Contract Value 48,104,420.00 SR.
Approved Invoices 0.00 SR.
Design Material Constructions Installations Testing
36% 11.55% 8.5% 0% 0%
2022 2023 2024 2026
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
.
11-05-2022 11.24%
TCC(Contractual )
10-08-2023
Critical
Project
15
NEW
Existing
PROJECT PHASE
BLOCK DIAGRAM
PROGRESS
PROJECT DETAILS
Contract Title CONSTRUCTION OF DHAHYAH HOUSING 132/13.8
kV SUBSTATION IN JIZAN AREA
Contract No 4400016524
Contractor AL SHARIF GROUP & KEC LIMITED CO.
Contract Value 74,495,088 SR.
Approved Invoices -
Start Date Status TCC
31 May 2022 Under Design 30 Nov 2023
Issues
• Site office mobilization to be done post receipt of approval for Site office layout and clearances from all
concerned parties for establishment of same due to ROW issues regarding site handover.
• Soil Investigation works to be commenced immediately post provision of access which is on hold due to site
handover and local authorities.
2022 2023 2024 2025
Q3Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
.
31-05-2022 TCC Contractual
30-11-2023
4.28 %
NEW
Existing
DHAHYAH
HOUSING
132/13.8 kV S/S
General + Design Material Constructions Installations Testing
0.60% + 3.15% 0.53% 0% 0% 0%
Critical
Project
16
132 kV GIS
9 Bays + 2
Bays
Hyundai Electric,
Korea
Submission response received dt 10th Nov ,
Compliance to be submitted
132/13.8 kV Power
Transformers
2 no’s SPTC, Dammam
Submission response received dated 7th Nov
,compliance to be submitted
13.8 kV Switchgear 1 Lot Alfanar, KSA
Submission response received dated 27th
Oct ,compliance to be submitted.
Control & Protection 1 Lot Siemens, KSA Under Design review
SAS & Telecom 1 Lot Siemens, KSA Under Design review
Surge Arresters 6 x 108 kV Tridelta, Germany
Submission response received dated 7th Nov
,compliance to be submitted
LT AC & DC Panels Lot Alfanar, KSA Under Design review
Cyber Security Lot Alfanar, KSA Design to be submitted after SAS approval
Capacitor Bank 2 Set
Samwah, Korea
Eaton, Germany
Submission response received dated 7th Nov
,compliance to be submitted
Battery SET
2 Piece(125
VDC)
HOPPECKE
Submission response received dated 3rd
Nov ,compliance to be submitted.
Battery Charger 2 Sets (125
VDC)
Statron, UAE
JIZAN UNIVERSITY
132/13.8 kV S/S
BLOCK DIAGRAM
PROGRESS
PROJECT DETAILS
Contract Title CONNECTION OF DHAHYAH HOUSING 132/13.8KV
S/S WITH JIZAN UNIVERSITY
Contract No PTS15SC1032
Contractor Delta.
Contract Value 13,335,000 SR.
Approved Invoices -
Issues
• Waiting approval from Ministry Housing for extending project time.
• ROW of S/S effect also the UGTL.
2020 2021 2022
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
30-04-2020 TCC Contractual
30-06-2022
0 %
NEW
Existing
DHAHYAH
HOUSING
132/13.8 kV S/S
General + Design Material Constructions Installations Testing
0% 0% 0% 0% 0%
Critical
Project
17
JIZAN
UNIVERSITY
132/13.8 kV S/S
2.9KM
Start Date Status TCC
30 Apr 2020 Under Design 30 Jun 2022
PROJECT PHASE
BLOCK DIAGRAM
PROGRESS
PROJECT DETAILS
Contract Title RCJ 380/132/33KV BSP SS1A SS & OHTL BETWEEN
RCJ BSP – KUDMI BSP AND RCJ BSP – JRP BSP
Contract No PTS -20SN386
Contractor AL Hader.
Contract Value 437,535,484SR.
Approved Invoices -
Issues :
• Delay for approval of final PTS of OHTL.
Design Material Constructions Installations Testing
3.5% 0% 0% 0% 0%
Critical
Project
18
Start Date Status TCC
15 July 2020 Under Design 01 Oct 2025
PROJECT PHASE
JRP BSP
SS1A 380KV
Kudmi BSP 46KM 11.5KM
2020 2021 2022 2023 2024 2025
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
3.5 %
15-07-2020
TCC Contractual
01-10-2025
NEW
Existing
19
Thanks

More Related Content

Similar to Projects Review Report

Pkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptx
Pkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptxPkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptx
Pkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptxVenkatesh Dontha
 
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)hepemod733
 
ACCF- PCM19- MM Brief to Client- 26.10.21_At.pptx
ACCF- PCM19- MM Brief to Client- 26.10.21_At.pptxACCF- PCM19- MM Brief to Client- 26.10.21_At.pptx
ACCF- PCM19- MM Brief to Client- 26.10.21_At.pptxRamKumar957449
 
Complete Report Of Nelum Jehlum Hydro Electric Project
Complete Report Of Nelum Jehlum Hydro Electric ProjectComplete Report Of Nelum Jehlum Hydro Electric Project
Complete Report Of Nelum Jehlum Hydro Electric ProjectEngr_Emad Khan
 
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptx
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptxFinal Presentation for 1st GMs-PDs Conference 03.02.2023.pptx
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptxhurain5
 
Departmental Briefing to Secretary Works on 08-02-2023.pptx
Departmental Briefing to Secretary Works on 08-02-2023.pptxDepartmental Briefing to Secretary Works on 08-02-2023.pptx
Departmental Briefing to Secretary Works on 08-02-2023.pptxsheikhInayat5
 
Presentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxPresentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxFaisalGulzar19
 
R01.RDSS-PPT _Ver-1.0 (28.04.23) New (1).pptx
R01.RDSS-PPT _Ver-1.0 (28.04.23) New (1).pptxR01.RDSS-PPT _Ver-1.0 (28.04.23) New (1).pptx
R01.RDSS-PPT _Ver-1.0 (28.04.23) New (1).pptxSudipDutta53
 
General Project report standing abrevation stock fy mou rt if olc hgf hhb h ...
General Project report standing abrevation stock fy mou rt if olc hgf  hhb h ...General Project report standing abrevation stock fy mou rt if olc hgf  hhb h ...
General Project report standing abrevation stock fy mou rt if olc hgf hhb h ...r66025007
 
DURGAPUR STEEL PLANT Project Review_07.01.23_KC.pptx
DURGAPUR STEEL PLANT Project Review_07.01.23_KC.pptxDURGAPUR STEEL PLANT Project Review_07.01.23_KC.pptx
DURGAPUR STEEL PLANT Project Review_07.01.23_KC.pptxkaustav_ju
 
AGTL Project Status and Progress_20-01-2021.pptx
AGTL Project Status and Progress_20-01-2021.pptxAGTL Project Status and Progress_20-01-2021.pptx
AGTL Project Status and Progress_20-01-2021.pptxMdAbuNaser13
 
Buildings so r 14 15
Buildings so r 14 15Buildings so r 14 15
Buildings so r 14 15Ptpg Stuc
 
Yhh jsn trae trge hba haga njj hgV1.pptx
Yhh jsn trae trge hba haga njj hgV1.pptxYhh jsn trae trge hba haga njj hgV1.pptx
Yhh jsn trae trge hba haga njj hgV1.pptxKheljitSingh
 
Cost Components in a MW Scale Solar Power Project
Cost Components in a MW Scale Solar Power ProjectCost Components in a MW Scale Solar Power Project
Cost Components in a MW Scale Solar Power ProjectSrini Chopakatla, PE, PMP
 
Dirgi shabozai 8 9-2019
Dirgi shabozai 8 9-2019Dirgi shabozai 8 9-2019
Dirgi shabozai 8 9-2019Munir Hussain
 

Similar to Projects Review Report (20)

Pkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptx
Pkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptxPkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptx
Pkg-1&2-Project Status on 31.01.2022 (To HO) (1).pptx
 
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
 
ACCF- PCM19- MM Brief to Client- 26.10.21_At.pptx
ACCF- PCM19- MM Brief to Client- 26.10.21_At.pptxACCF- PCM19- MM Brief to Client- 26.10.21_At.pptx
ACCF- PCM19- MM Brief to Client- 26.10.21_At.pptx
 
Complete Report Of Nelum Jehlum Hydro Electric Project
Complete Report Of Nelum Jehlum Hydro Electric ProjectComplete Report Of Nelum Jehlum Hydro Electric Project
Complete Report Of Nelum Jehlum Hydro Electric Project
 
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptx
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptxFinal Presentation for 1st GMs-PDs Conference 03.02.2023.pptx
Final Presentation for 1st GMs-PDs Conference 03.02.2023.pptx
 
H 1.ppt
H 1.pptH 1.ppt
H 1.ppt
 
Departmental Briefing to Secretary Works on 08-02-2023.pptx
Departmental Briefing to Secretary Works on 08-02-2023.pptxDepartmental Briefing to Secretary Works on 08-02-2023.pptx
Departmental Briefing to Secretary Works on 08-02-2023.pptx
 
Presentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxPresentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptx
 
R01.RDSS-PPT _Ver-1.0 (28.04.23) New (1).pptx
R01.RDSS-PPT _Ver-1.0 (28.04.23) New (1).pptxR01.RDSS-PPT _Ver-1.0 (28.04.23) New (1).pptx
R01.RDSS-PPT _Ver-1.0 (28.04.23) New (1).pptx
 
FQUP PPT.pptx
FQUP PPT.pptxFQUP PPT.pptx
FQUP PPT.pptx
 
General Project report standing abrevation stock fy mou rt if olc hgf hhb h ...
General Project report standing abrevation stock fy mou rt if olc hgf  hhb h ...General Project report standing abrevation stock fy mou rt if olc hgf  hhb h ...
General Project report standing abrevation stock fy mou rt if olc hgf hhb h ...
 
DURGAPUR STEEL PLANT Project Review_07.01.23_KC.pptx
DURGAPUR STEEL PLANT Project Review_07.01.23_KC.pptxDURGAPUR STEEL PLANT Project Review_07.01.23_KC.pptx
DURGAPUR STEEL PLANT Project Review_07.01.23_KC.pptx
 
AGTL Project Status and Progress_20-01-2021.pptx
AGTL Project Status and Progress_20-01-2021.pptxAGTL Project Status and Progress_20-01-2021.pptx
AGTL Project Status and Progress_20-01-2021.pptx
 
sn-ladakh.pdf
sn-ladakh.pdfsn-ladakh.pdf
sn-ladakh.pdf
 
Buildings so r 14 15
Buildings so r 14 15Buildings so r 14 15
Buildings so r 14 15
 
total report
total reporttotal report
total report
 
Yhh jsn trae trge hba haga njj hgV1.pptx
Yhh jsn trae trge hba haga njj hgV1.pptxYhh jsn trae trge hba haga njj hgV1.pptx
Yhh jsn trae trge hba haga njj hgV1.pptx
 
COBRA PRESENTATION
COBRA  PRESENTATIONCOBRA  PRESENTATION
COBRA PRESENTATION
 
Cost Components in a MW Scale Solar Power Project
Cost Components in a MW Scale Solar Power ProjectCost Components in a MW Scale Solar Power Project
Cost Components in a MW Scale Solar Power Project
 
Dirgi shabozai 8 9-2019
Dirgi shabozai 8 9-2019Dirgi shabozai 8 9-2019
Dirgi shabozai 8 9-2019
 

Recently uploaded

result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdfankushspencer015
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...ranjana rawat
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 

Recently uploaded (20)

result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
The Most Attractive Pune Call Girls Manchar 8250192130 Will You Miss This Cha...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 

Projects Review Report

  • 1. Nov, 2022 South Portfolio Projects Report Projects Review Report
  • 2. Jazan Division 11,670 km 25 Municipality 13 Governorate 31 Markez Jazan Area 2 South Department Projects
  • 3. NO . PROJECT NAME Type of project Project Progress Statues Contract Value (SR) Start Date 1 CONSTRUCTION OF NEW AL ASEELH ( ASL ) ( JAZAN -3 ) 380/132/13.8 KV BSP Critical 88.4% On going 228,000,400 01/06/2020 2 CONSTRUCTION OF TWO (2) 380KV DOUBLE CIRCUIT OHTL BETWEEN ASL –KDM ( AND ASL- MDY Critical 95.6% On going 61,050,000 12/07/2020 3 CONSTRUCTION OF ASL –SHQ (CKT-1) AND ASL-SHQ-2 (CKT-1) Critical 83.2% On going 190,378,997 19/10/2020 4 INSTALLATION OF DRPC AND EXPANSION OF 132 K.V. GIS AT KUDMI BSP Critical 28.1% On going 155,000,000 30/12/2020 5 CONNECTING AL-ASEELAH CENTRAL STATION TO THE NETWORK 132 KV Normal 74% On going 30,414,564 30/09/2021 6 CONSTRUCTION OF ABU ARISH-2 132/13.8 KV SS Normal 85.3% On going 41,794,500 05/02/2020 7 CONSTRUCTION OF 132KV D/C OHTLTO SUPPLY POWER TO ABU ARISH-2 132/13.8KV S/S Normal 79% On going 12,400,000 27/01/2020 8 CONSTRUCTION OF ZARGA-2 132/13.8 KV Normal 85% On going 42,609,562 23/03/2020 9 POWER SUPPLY TO HOUSING PROJECT (STAGE-1) OF MINISTRY OF DEFENCE IN JIZAN Normal 74.2% On going 100,281,838 07/02/2021 10 CONNECTION OF AL ARIDAH , AYBAN AND AD DAYIR 132KV SS IN JAZAN WITH NETWORKS Normal 83.9% On going Partial Energized 39,200,000 23/03/2021 11 ADDITION OF THIRD TRANSFORMER TO AL-HAQU 132/33 KV S/S Normal 95% On going 25,190,000 25/10/2017 12 CONSTRUCTION OF 132KV D/C OHTL BETWEEN ABU QAEED132KV S/S AND AL HAQU 132KV S/S Normal 10% On going 48,104,420.00 11/05/2022 13 CONSTRUCTION OF DHAHYAH HOUSING 132/13.8 kV SUBSTATION IN JIZAN AREA Normal 4.28% On going 74,495,088 31/05/2022 14 CONNECTION OF DHAHYAH HOUSING 132/13.8KV S/S WITH JIZAN UNIVERSITY Normal 0% On going 13,335,000 30/04/2020 15 RCJ 380/132/33KV BSP SS1A SS & OHTL BETWEEN RCJ BSP – KUDMI BSP AND RCJ BSP – JRP BSP Normal 3.5% On going 437,535,484 15/07/2020 Total 56.1% - 1,500,055,428 - Projects Summary
  • 4. PROJECT PHASE BLOCK DIAGRAM PROGRESS Start Date Status TCC 01 Jun 2020 Under Commissioning 31 Mar 2023 PROJECT DETAILS Contract Title CONSTRUCTION OF NEW AL ASEELH ( ASL ) ( JAZAN -3 ) 380/132/13.8 KV BSP Contract No 4400013230 Contractor NCC Contract Value 228,000,400 SR. Approved Invoices 164,046,288 (72%) SR. Design Material Constructions Installations Commissioning 99.5% 99.6% 87% 87.8% 44% 2019 2020 2021 2022 2023 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 . TCC(Expected) 31-03-2023 01-06-2020 88.4% TCC(Contractual) 31-12-2021 Issues • delays in review of submittal it was affected severely material procurement/delivery. ( solved ) • Delivery of 132kV LCC are delayed (2nd lot delivered, 3rd lot will be delivered by 10.05.2022).( Solved) • Damaged 06 ACDB cubicles delivery . Planned delivery date at site 10.10.2022. ( solved ) • 48V Battery charger and battery bank delivery will be delivered by end of Nov2022.( solved ) Critical Project 4 MDY 380 BSP Kudmi BSP NEW Existing SHQ 1 BSP SHQ 2 BSP NEW AL ASEELH 380 22.5KM 22.5KM 82KM 4KM 2.8KM 11.2KM 140.5KM 380kV GIS 7 Dia. (21 C.B) ABB Installation 100% 132kV GIS 30 C.B ABB, KSA Installation 100% EHV Transformer 3*502MVA Hyosung Installation 100% HV Transformer 3*67MVA SPTC Installation 100% Shunt Reactor 1*120MVAR Hyosung Installation 100% Control panels 4 Lots (216) Alfanar Installation 100% 13.8kV C.B 44 C.B Alfanar Installation 100% SAS/FO 20 panels Alfanar Installation 100% Communication Lot. GE, KSA Installation 90%
  • 5. PROGRESS PROJECT PHASE BLOCK DIAGRAM Start Date Status TCC 12 Jul 2020 Under construction 31 Dec 2022 Issues • ROW issues with landowners (Solved) • Manpower availability due to flight restrictions. (Solved) • Required shutdown for KDM-MDY line, plan shutdown on 18.12.20222 Length No# Tower No# Foundation 44.54 Km 116 116 42.598 Km 113 116 PROJECT DETAILS Contract Title CONSTRUCTION OF TWO (2) 380KV D/C OHTL BETWEEN ASL-KDM & ASL-MDY Contract No 4400013424 Contractor NPCC Contract Value 61,050,000 SR. Approved Invoices 47,013,376 (77%) SR. Design Material Constructions Installations Testing 99.5% 99.9% 100% 94.92% 0% 2019 2020 2021 2022 2023 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 . TCC (Expected) 31-03-2023 12-07-2020 95.6% TCC(Contractual ) 31-12-2022 Critical Project 5 MDY 380 BSP Kudmi BSP NEW Existing SHQ 1 BSP SHQ 2 BSP NEW AL ASEELH 380 22.5KM 22.5KM 82KM 4KM 2.8KM 11.2KM 140.5KM
  • 6. 2019 2020 2021 2022 2023 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 . PROJECT PHASE BLOCK DIAGRAM PROGRESS PROJECT DETAILS Contract Title CONSTRUCTION OF ONE (1) 380KV D/C OHTL BETWEEN ASL –SHQ -1 AND ASL-SHQ-2 Contract No 4400013836 Contractor NPCC Contract Value 190,378,997 SR. Approved Invoices 131,253,267 (68.8%) SR. Start Date Status TCC 19 Oct 2020 Under construction 18 Jun 2022 Issues • ROW issues with landowners and Mohafza of Sabya (Solved) • Manpower availability due to flight restrictions. (Solved) • ROW stop by Municipality Wady Jazan. (Solved) • delivery of balance Spacer Dampers (54%) delayed by PTE since of AUG 2021. (Solved) • Delay delivery of 17towers of Steel Structure from Babtain, Planned delivery date at site end of Dec-22 • Outage for around 10 No. of Existing 132kV OHTL Over Crossing and for tapping. Length No# Tower No# Foundation 140.35 km 373 373 57.1 km 319 357 19-10-2020 83.2% TCC(Expected) 30-11-2023 Design Material Constructions Installations Testing 97.4% 99.5% 94% 66% 0% Critical Project 6 MDY 380 BSP Kudmi BSP NEW Existing SHQ 1 BSP SHQ 2 BSP NEW AL ASEELH 380 22.5KM 22.5KM 82KM 4KM 2.8KM 11.2KM 140.5KM
  • 7. PROJECT PHASE BLOCK DIAGRAM PROGRESS PROJECT DETAILS Contract Title CONNECTING AL-ASEELAH CENTRAL STATION TO THE NETWORK 132 KV Contract No 4400015320 Contractor AL SHARIF GROUP FOR CONTR Contract Value 30,414,564 SR. Approved Invoices 21,498,804 (70%) SR. Start Date Status TCC 30 Sep 2021 Under construction 30 Nov 2022 Issues • Delayed work permits from the Ministry of Transport. (Solved). • The reply from S/S Contractor regarding Steel Support inside Basement. (Solved). • Conflict with MV contractors in the same route of power cables. (Solved). • Conflict with MV Contractors in the same route of power cable. (Solved). 2021 2022 2023 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 30-09-2021 74 % TCC(Expected) 31-03-2023 NEW Existing JIZAN CPS -2 132.13.8 1.65 KM Length Join Bay 6 section 4CKT * (1.65 km)*3= 19.8 km 4 4 section 16 km 1 ABU ARISH 132/33 KV NEW AL ASEELH 380 King Fahad Hospital 132/13.8 kv Design Material Construction Installations Testing 96% 94 % 71 % 70 % 0 % TCC(Contractual ) 30-11-2022 Normal Project 7 8KM 3.5KM 1.5KM
  • 8. PROJECT PHASE BLOCK DIAGRAM PROGRESS PROJECT DETAILS Contract Title INSTALLATION OF DRPC AND EXPANSION OF 132 K.V. GIS AT KUDMI BSP Contract No 4400014231 Contractor SIEMENS Contract Value 155,000,000 SR. Approved Invoices 6,050,351(3.9%) SR. Start Date Status TCC 30 Dec 2020 Under construction 28 Feb 2023 Issues • Lack response from contractor. • Design submission for remaining equipment (Capacitor Banks, Disconnections & Resistors & Earthing Switches) • Accelerate Manufacturing for approved materials. • Main Equipment still not Delivered Yet. 2020 2021 2022 2023 Q3Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 . 30-12-2020 TCC Contractual 28-02-2023 29 % NEW Existing INSTALLATION OF DRPC IN KUDMI Design Material Constructions Installations Testing 61% 38% 33% 0% 0% Critical Project 8 600 MVA Transformer 2*600 MVA Hyundai Electric, Korea Under manufacturing 132KV GIS 1 Bay GE, KSA Under design review Thyristors and Converters 2 Lot Siemens Energy, Germany Delivered MV SWGR 33 KV 2 * 33 kV Siemens, KSA Under manufacturing Communication Equipment Lot Hitachi Energy, KSA Under manufacturing Battery & Charger 2 Piece(125 VDC) Statron, UAE Under manufacturing Air Core Reactor 2 Lot Trench GmbH, Germany Under manufacturing Wall Bushings 12 Piece MGC, Germany Under manufacturing Surge Arresters 1*120KV Siemens Energy, Germany Delivered Capacitor Banks 2 Piece Samwah, Korea Eaton, Germany Under design review MV SWGR 13.8 KV 2* 13.5 KV Al-Fanar, KSA Under design review
  • 9. PROJECT PHASE BLOCK DIAGRAM PROGRESS PROJECT DETAILS Contract Title CONSTRUCTION OF ABU ARISH-2 132/13.8 KV SS Contract No 4400013046 Contractor HAIF COMPANY Contract Value 41,794,500 SR. Approved Invoices 18,573,957 (44.44%) SR. Start Date Status TCC 05 Feb 2020 Under construction 05 Jun 2023 2020 2021 2022 2023 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 . 05-02-2020 85.3 % TCC (Contractual) 05-06-2023 Issues • Delivery of Power Transformers are delayed. Will be arrived at site on 30.11.2022. Normal Project Design Material Constructions Installations Pre check 97% 96% 96% 98% 5% 132kV GIS 12 Bays HYOSUNG,KOREA Installation 100% 132kV Transformer 3*67MVA ABB NG SCOPE Not Delivered (Expected delivery on 30/11/2022) SWG 51 CB ALFANAR, KSA Installation 100% Control panels Lot SEP ,KSA Installation 100% AC/DC LOT ALFANAR, KSA AC/DC panels delivered Aux TR 2 SFT, KSA Installation 100 % Gantry &SA& CSE LOT ALNAFIE, KSA Installation 90% SAS LOT ABB (HITACHI) Installation Communication system LOT ABB, KSA FAT DONE 9 132 ASSALAMAH SUBSTATION 132/13.8 KV NEW Existing NEW Existing ABU ARISH-2 132/13.8 KV SUBSTATION 5.96KM 6.8KM 15.8 KM JAZAN CPS-2 SUBSTATION 132/33KV
  • 10. PROJECT PHASE PROGRESS PROJECT DETAILS Contract Title CONSTRUCTION OF 132KV D/C OHTLTO SUPPLY POWER TO ABU ARISH-2 132/13.8KV S/S Contract No 4400013011 Contractor NCC Contract Value 12,400,000 SR. Approved Invoices 7,461,044(66.4%) SR. Start Date Status TCC 27 Jan 2020 Under construction 26 Jan 2023 Issues • Delay of missing materials delivery to the site. (Solved). • Outgas plan on 18.12.2022. Length NO. of Tower No# Foundation 12 KM 36 36 7.85 KM 34 36 BLOCK DIAGRAM 132 ASSALAMAH SUBSTATION 132/13.8 KV NEW Existing NEW Existing ABU ARISH-2 132/13.8 KV SUBSTATION JAZAN CPS-2 SUBSTATION 132/33KV Normal Project Design Material Constructions Installations Testing 86 % 98.5% 95 % 50 % 0 % 2019 2020 2021 2022 2023 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 . 27-01-2020 79 % TCC (Contractual) 26-01-2023 10 5.96KM 6.8KM 15.8 KM
  • 11. PROJECT PHASE BLOCK DIAGRAM PROGRESS PROJECT DETAILS Contract Title CONSTRUCTION OF ZARGA-2 132/13.8 KV Contract No 4400013117 Contractor AL SHARIF GROUP Contract Value 42,609,562 SR. Approved Invoices 26,346,723(61.82%) SR. Start Date Status TCC 23 Mar 2020 Under construction 1 Jun 2023 2020 2021 2022 2023 Q1Q2Q3Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 . 23-03-2020 85% Issues • Delayed of arrived Material (power transformer) . Will be shipping to site on 15/11/2022. • poor performance of contractor to start pre-commissioning. TCC (Expected) 01-06-2023 132 0.2 KM JAZAN CPS-1 132/33 KV NEW Existing NEW Existing ZARGA-2 132/13.8 KV SUBSTATION KUDMI 132KV SUBSTATION Normal Project Design Material Constructions Installations Testing 99.8% 97.14% 95.25% 93.2% 0% 132kV GIS 12 Bay Hyosung Installation Power Transformers 3*67 MVA ABB- Turkey Delivered 13.8kV Switchgear Room 48 CB ABB Installation Control and Protection LOT ABB Installation SAS LOT ABB FAT Done AC/DC panels LOT ETA FAT Done Battery Charger 2 STATRON Installation Battery LOT HOPPECKE Installation Communication System LOT ABB Installation Auxiliary Xmer 2 UTEC Installation OHTL Tower LOT AIC Installation 11 11KM 24KM
  • 12. PROJECT PHASE BLOCK DIAGRAM PROGRESS PROJECT DETAILS Contract Title POWER SUPPLY TO HOUSING PROJECT (STAGE-1) OF MINISTRY OF DEFENCE IN JIZAN Contract No PTS16SN110 Contractor TDP Contract Value 95,506,513.2 SR. Approved Invoices 46,801,833 (46.67%) SR Start Date Status TCC 01 March 2021 Under construction 07 Feb 2023 Issues • (6) invoices payment from MOD to contractor. • Change order for the conductors ( GZTACSR) . • Waiting approval for shutdown. 2020 2021 2022 2023 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 . 01/03/2020 74.2 % TCC (Contractual & Expected) 07-02-2023 AD-Darb 132/33 KV NEW Existin g BAISH 132/33/13.8 KV SUBSTATION HOUSING OF MINISTRY OF DEFENCE IN JIZAN 1 KM Normal Project Design Material Constructions Installations Testing 98 % 94% 84 % 52.2 % 0 % 33 KM 26 KM OGW Power Transformer 132kV 2*67MVA SPTC / Dammam Installation GIS 132 kv 11 HHI/Korea Installation Surge Arrester 132 kV 18 pcs TRIDELTA/Germany Installation Cable Terminations 132kV Lot Jeddah Cables / KSA Installation Towers 8 No AIC Steel/KSA Installation Conductors ( GZTACSR) 195 km Sumitomo Electric/Japan Partial delivery OPGW 4 km Prysmian/Spain Installation Switch Gear Lot AES / KSA Installation 12
  • 13. PROJECT PHASE BLOCK DIAGRAM PROGRESS PROJECT DETAILS Contract Title CONNECTION OF AL ARIDAH , AYBAN AND AD DAYIR 132KV SS IN JAZAN WITH NETWORKS Contract No 4400013250 Contractor AL SHARIF GROUP FOR CONTR Contract Value 39,200,000 SR. Approved Invoices 22,295,584 (57%) SR. Start Date Status TCC 23 Mar 2020 Under construction 22-May 2023 2020 2021 2022 2023 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 . 23-03-2020 83.9% TCC (Expected) 13-05-2023 New Line NO. of Tower NO. of foundation 28 KM 90 90 Completed 89 89 Normal Project Design Material Constructions Installations Testing 98 % 89 % 96 % 75 % 0 % Reconductoring NO. of Tower 1st 2nd Circuit 17 KM 55 55 Completed 55 0 Issues • Substation modification Design in Ayban & Al Dayer. • ABB response is awaited regarding finalization of CT in side GIS at Ayban S/S. • One Tap-off Tower will be constructed during Outage of CKT-2 of Ayban - Ad Dayir line. • Waiting Shutdown for 2nd CKT of Ayban – Ad Dayir (17km Line). Partial Energized 05-04-2022 13 AD DAYIR SS 132/33/13.8 KV NEW Existing NEW Existing AYBAN SS 132/33 /13.18 KV 28KM AL ARIDAH SS 132/13.8 KV 16.5 KM 170M 16.7KM
  • 14. PROJECT PHASE BLOCK DIAGRAM PROGRESS PROJECT DETAILS Contract Title ADDITION OF THIRD TRANSFORMER TO AL-HAQU 132/33 KV S/S. Contract No 4400008427 Contractor GE Contract Value 25,190,000 SR. Approved Invoices 17,911,440 (71.1%) SR. Start Date Status TCC 25 Oct 2016 Under construction 22 Jul 2023 Issues • Negative Change order approval . NEW Existing NEW Existing AL-HAQU 132/33 KV EXPANSION 2016 2018 2022 2023 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q3 Q4 . 25-10-2016 95% TCC (Expected) 22-07-2023 Normal Project Design Material Constructions Installations Testing 100% 100% 100% 100% 60% 14 33kV SWG 13 ABB Installation DTCB 1 ABB Installation Capacitor 1 GE Installation HV cable 1drum Saudi Cables Installation MV Cable 1drum Saudi Cables Installation Protection panels Lots GE Installation
  • 15. PROGRESS PROJECT PHASE BLOCK DIAGRAM Start Date Status TCC 11 May 2022 Under construction 21 Aug 2023 Issues : Delay in Route approval. Length No# Tower No# Foundation 24.4 Km 78 78 ABU QAEED 132KV SS ALHAQU 132KV SS 24.4 KM PROJECT DETAILS Contract Title CONSTRUCTION OF 132KV D/C OHTL BETWEEN ABU QAEED132KV S/S AND AL HAQU 132KV S/S Contract No 4400016383 Contractor Raissy Contract Value 48,104,420.00 SR. Approved Invoices 0.00 SR. Design Material Constructions Installations Testing 36% 11.55% 8.5% 0% 0% 2022 2023 2024 2026 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 . 11-05-2022 11.24% TCC(Contractual ) 10-08-2023 Critical Project 15 NEW Existing
  • 16. PROJECT PHASE BLOCK DIAGRAM PROGRESS PROJECT DETAILS Contract Title CONSTRUCTION OF DHAHYAH HOUSING 132/13.8 kV SUBSTATION IN JIZAN AREA Contract No 4400016524 Contractor AL SHARIF GROUP & KEC LIMITED CO. Contract Value 74,495,088 SR. Approved Invoices - Start Date Status TCC 31 May 2022 Under Design 30 Nov 2023 Issues • Site office mobilization to be done post receipt of approval for Site office layout and clearances from all concerned parties for establishment of same due to ROW issues regarding site handover. • Soil Investigation works to be commenced immediately post provision of access which is on hold due to site handover and local authorities. 2022 2023 2024 2025 Q3Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 . 31-05-2022 TCC Contractual 30-11-2023 4.28 % NEW Existing DHAHYAH HOUSING 132/13.8 kV S/S General + Design Material Constructions Installations Testing 0.60% + 3.15% 0.53% 0% 0% 0% Critical Project 16 132 kV GIS 9 Bays + 2 Bays Hyundai Electric, Korea Submission response received dt 10th Nov , Compliance to be submitted 132/13.8 kV Power Transformers 2 no’s SPTC, Dammam Submission response received dated 7th Nov ,compliance to be submitted 13.8 kV Switchgear 1 Lot Alfanar, KSA Submission response received dated 27th Oct ,compliance to be submitted. Control & Protection 1 Lot Siemens, KSA Under Design review SAS & Telecom 1 Lot Siemens, KSA Under Design review Surge Arresters 6 x 108 kV Tridelta, Germany Submission response received dated 7th Nov ,compliance to be submitted LT AC & DC Panels Lot Alfanar, KSA Under Design review Cyber Security Lot Alfanar, KSA Design to be submitted after SAS approval Capacitor Bank 2 Set Samwah, Korea Eaton, Germany Submission response received dated 7th Nov ,compliance to be submitted Battery SET 2 Piece(125 VDC) HOPPECKE Submission response received dated 3rd Nov ,compliance to be submitted. Battery Charger 2 Sets (125 VDC) Statron, UAE JIZAN UNIVERSITY 132/13.8 kV S/S
  • 17. BLOCK DIAGRAM PROGRESS PROJECT DETAILS Contract Title CONNECTION OF DHAHYAH HOUSING 132/13.8KV S/S WITH JIZAN UNIVERSITY Contract No PTS15SC1032 Contractor Delta. Contract Value 13,335,000 SR. Approved Invoices - Issues • Waiting approval from Ministry Housing for extending project time. • ROW of S/S effect also the UGTL. 2020 2021 2022 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 30-04-2020 TCC Contractual 30-06-2022 0 % NEW Existing DHAHYAH HOUSING 132/13.8 kV S/S General + Design Material Constructions Installations Testing 0% 0% 0% 0% 0% Critical Project 17 JIZAN UNIVERSITY 132/13.8 kV S/S 2.9KM Start Date Status TCC 30 Apr 2020 Under Design 30 Jun 2022 PROJECT PHASE
  • 18. BLOCK DIAGRAM PROGRESS PROJECT DETAILS Contract Title RCJ 380/132/33KV BSP SS1A SS & OHTL BETWEEN RCJ BSP – KUDMI BSP AND RCJ BSP – JRP BSP Contract No PTS -20SN386 Contractor AL Hader. Contract Value 437,535,484SR. Approved Invoices - Issues : • Delay for approval of final PTS of OHTL. Design Material Constructions Installations Testing 3.5% 0% 0% 0% 0% Critical Project 18 Start Date Status TCC 15 July 2020 Under Design 01 Oct 2025 PROJECT PHASE JRP BSP SS1A 380KV Kudmi BSP 46KM 11.5KM 2020 2021 2022 2023 2024 2025 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 3.5 % 15-07-2020 TCC Contractual 01-10-2025 NEW Existing