2. Jazan Division
11,670 km 25
Municipality
13
Governorate
31
Markez
Jazan Area
2
South Department Projects
3. NO
.
PROJECT NAME
Type of
project
Project
Progress
Statues
Contract Value
(SR)
Start Date
1 CONSTRUCTION OF NEW AL ASEELH ( ASL ) ( JAZAN -3 ) 380/132/13.8 KV BSP Critical 88.4% On going 228,000,400 01/06/2020
2
CONSTRUCTION OF TWO (2) 380KV DOUBLE CIRCUIT OHTL BETWEEN ASL –KDM ( AND ASL-
MDY
Critical 95.6% On going 61,050,000 12/07/2020
3 CONSTRUCTION OF ASL –SHQ (CKT-1) AND ASL-SHQ-2 (CKT-1) Critical 83.2% On going 190,378,997 19/10/2020
4 INSTALLATION OF DRPC AND EXPANSION OF 132 K.V. GIS AT KUDMI BSP Critical 28.1% On going 155,000,000 30/12/2020
5 CONNECTING AL-ASEELAH CENTRAL STATION TO THE NETWORK 132 KV Normal 74% On going 30,414,564 30/09/2021
6 CONSTRUCTION OF ABU ARISH-2 132/13.8 KV SS Normal 85.3% On going 41,794,500 05/02/2020
7 CONSTRUCTION OF 132KV D/C OHTLTO SUPPLY POWER TO ABU ARISH-2 132/13.8KV S/S Normal 79% On going 12,400,000 27/01/2020
8 CONSTRUCTION OF ZARGA-2 132/13.8 KV Normal 85% On going 42,609,562 23/03/2020
9 POWER SUPPLY TO HOUSING PROJECT (STAGE-1) OF MINISTRY OF DEFENCE IN JIZAN Normal 74.2% On going 100,281,838 07/02/2021
10 CONNECTION OF AL ARIDAH , AYBAN AND AD DAYIR 132KV SS IN JAZAN WITH NETWORKS Normal 83.9%
On going
Partial Energized
39,200,000 23/03/2021
11 ADDITION OF THIRD TRANSFORMER TO AL-HAQU 132/33 KV S/S Normal 95% On going 25,190,000 25/10/2017
12
CONSTRUCTION OF 132KV D/C OHTL BETWEEN ABU QAEED132KV S/S AND AL HAQU
132KV S/S
Normal 10% On going 48,104,420.00 11/05/2022
13
CONSTRUCTION OF DHAHYAH HOUSING 132/13.8 kV SUBSTATION IN JIZAN AREA
Normal 4.28% On going 74,495,088 31/05/2022
14 CONNECTION OF DHAHYAH HOUSING 132/13.8KV S/S WITH JIZAN UNIVERSITY Normal 0% On going 13,335,000 30/04/2020
15
RCJ 380/132/33KV BSP SS1A SS & OHTL BETWEEN RCJ BSP – KUDMI BSP AND RCJ BSP –
JRP BSP
Normal 3.5% On going 437,535,484 15/07/2020
Total 56.1% - 1,500,055,428 -
Projects Summary
4. PROJECT PHASE
BLOCK DIAGRAM
PROGRESS
Start Date Status TCC
01 Jun 2020 Under Commissioning 31 Mar 2023
PROJECT DETAILS
Contract Title CONSTRUCTION OF NEW AL ASEELH ( ASL )
( JAZAN -3 ) 380/132/13.8 KV BSP
Contract No 4400013230
Contractor NCC
Contract Value 228,000,400 SR.
Approved Invoices 164,046,288 (72%) SR.
Design Material Constructions Installations Commissioning
99.5% 99.6% 87% 87.8% 44%
2019 2020 2021 2022 2023
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
.
TCC(Expected)
31-03-2023
01-06-2020 88.4%
TCC(Contractual)
31-12-2021
Issues
• delays in review of submittal it was affected severely material procurement/delivery. ( solved )
• Delivery of 132kV LCC are delayed (2nd lot delivered, 3rd lot will be delivered by 10.05.2022).( Solved)
• Damaged 06 ACDB cubicles delivery . Planned delivery date at site 10.10.2022. ( solved )
• 48V Battery charger and battery bank delivery will be delivered by end of Nov2022.( solved )
Critical
Project
4
MDY 380 BSP Kudmi BSP
NEW
Existing
SHQ 1 BSP SHQ 2 BSP
NEW AL ASEELH 380
22.5KM
22.5KM
82KM
4KM
2.8KM
11.2KM
140.5KM
380kV GIS 7 Dia. (21 C.B) ABB Installation 100%
132kV GIS 30 C.B ABB, KSA Installation 100%
EHV Transformer 3*502MVA Hyosung Installation 100%
HV Transformer 3*67MVA SPTC Installation 100%
Shunt Reactor 1*120MVAR Hyosung Installation 100%
Control panels 4 Lots (216) Alfanar Installation 100%
13.8kV C.B 44 C.B Alfanar Installation 100%
SAS/FO 20 panels Alfanar Installation 100%
Communication Lot. GE, KSA Installation 90%
5. PROGRESS PROJECT PHASE
BLOCK DIAGRAM
Start Date Status TCC
12 Jul 2020 Under construction 31 Dec 2022
Issues
• ROW issues with landowners (Solved)
• Manpower availability due to flight restrictions. (Solved)
• Required shutdown for KDM-MDY line, plan shutdown on 18.12.20222
Length No# Tower No# Foundation
44.54 Km 116 116
42.598 Km 113 116
PROJECT DETAILS
Contract Title CONSTRUCTION OF TWO (2) 380KV D/C OHTL
BETWEEN ASL-KDM & ASL-MDY
Contract No 4400013424
Contractor NPCC
Contract Value 61,050,000 SR.
Approved Invoices 47,013,376 (77%) SR.
Design Material Constructions Installations Testing
99.5% 99.9% 100% 94.92% 0%
2019 2020 2021 2022 2023
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
.
TCC (Expected)
31-03-2023
12-07-2020 95.6%
TCC(Contractual )
31-12-2022
Critical
Project
5
MDY 380 BSP Kudmi BSP
NEW
Existing
SHQ 1 BSP SHQ 2 BSP
NEW AL ASEELH 380
22.5KM
22.5KM
82KM
4KM
2.8KM
11.2KM
140.5KM
6. 2019 2020 2021 2022 2023
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
.
PROJECT PHASE
BLOCK DIAGRAM
PROGRESS
PROJECT DETAILS
Contract Title CONSTRUCTION OF ONE (1) 380KV D/C OHTL
BETWEEN ASL –SHQ -1 AND ASL-SHQ-2
Contract No 4400013836
Contractor NPCC
Contract Value 190,378,997 SR.
Approved Invoices 131,253,267 (68.8%) SR.
Start Date Status TCC
19 Oct 2020 Under construction 18 Jun 2022
Issues
• ROW issues with landowners and Mohafza of Sabya (Solved)
• Manpower availability due to flight restrictions. (Solved)
• ROW stop by Municipality Wady Jazan. (Solved)
• delivery of balance Spacer Dampers (54%) delayed by PTE since of AUG 2021. (Solved)
• Delay delivery of 17towers of Steel Structure from Babtain, Planned delivery date at site end of Dec-22
• Outage for around 10 No. of Existing 132kV OHTL Over Crossing and for tapping.
Length No# Tower No# Foundation
140.35 km 373 373
57.1 km 319 357
19-10-2020 83.2% TCC(Expected)
30-11-2023
Design Material Constructions Installations Testing
97.4% 99.5% 94% 66% 0%
Critical
Project
6
MDY 380 BSP Kudmi BSP
NEW
Existing
SHQ 1 BSP SHQ 2 BSP
NEW AL ASEELH 380
22.5KM
22.5KM
82KM
4KM
2.8KM
11.2KM
140.5KM
7. PROJECT PHASE
BLOCK DIAGRAM
PROGRESS
PROJECT DETAILS
Contract Title CONNECTING AL-ASEELAH CENTRAL STATION TO
THE NETWORK 132 KV
Contract No 4400015320
Contractor AL SHARIF GROUP FOR CONTR
Contract Value 30,414,564 SR.
Approved Invoices 21,498,804 (70%) SR.
Start Date Status TCC
30 Sep 2021 Under construction 30 Nov 2022
Issues
• Delayed work permits from the Ministry of Transport. (Solved).
• The reply from S/S Contractor regarding Steel Support inside Basement. (Solved).
• Conflict with MV contractors in the same route of power cables. (Solved).
• Conflict with MV Contractors in the same route of power cable. (Solved).
2021 2022 2023
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
30-09-2021 74 %
TCC(Expected)
31-03-2023
NEW
Existing
JIZAN CPS -2
132.13.8
1.65
KM
Length Join Bay
6 section 4CKT * (1.65 km)*3= 19.8 km 4
4 section 16 km 1
ABU ARISH
132/33 KV
NEW AL ASEELH 380
King Fahad Hospital
132/13.8 kv
Design Material Construction Installations Testing
96% 94 % 71 % 70 % 0 %
TCC(Contractual )
30-11-2022
Normal
Project
7
8KM
3.5KM
1.5KM
8. PROJECT PHASE
BLOCK DIAGRAM
PROGRESS
PROJECT DETAILS
Contract Title INSTALLATION OF DRPC AND EXPANSION OF 132
K.V. GIS AT KUDMI BSP
Contract No 4400014231
Contractor SIEMENS
Contract Value 155,000,000 SR.
Approved Invoices 6,050,351(3.9%) SR.
Start Date Status TCC
30 Dec 2020 Under construction 28 Feb 2023
Issues
• Lack response from contractor.
• Design submission for remaining equipment (Capacitor Banks, Disconnections & Resistors & Earthing Switches)
• Accelerate Manufacturing for approved materials.
• Main Equipment still not Delivered Yet.
2020 2021 2022 2023
Q3Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
.
30-12-2020
TCC Contractual
28-02-2023
29 %
NEW
Existing
INSTALLATION OF
DRPC IN KUDMI
Design Material Constructions Installations Testing
61% 38% 33% 0% 0%
Critical
Project
8
600 MVA Transformer 2*600 MVA Hyundai Electric, Korea Under manufacturing
132KV GIS
1 Bay
GE, KSA Under design review
Thyristors and
Converters
2 Lot
Siemens Energy,
Germany
Delivered
MV SWGR 33 KV 2 * 33 kV Siemens, KSA Under manufacturing
Communication
Equipment
Lot Hitachi Energy, KSA Under manufacturing
Battery & Charger
2 Piece(125 VDC)
Statron, UAE
Under manufacturing
Air Core Reactor 2 Lot Trench GmbH, Germany Under manufacturing
Wall Bushings 12 Piece MGC, Germany Under manufacturing
Surge Arresters 1*120KV
Siemens Energy,
Germany
Delivered
Capacitor Banks
2 Piece
Samwah, Korea
Eaton, Germany
Under design review
MV SWGR 13.8 KV 2* 13.5 KV
Al-Fanar, KSA Under design review
9. PROJECT PHASE
BLOCK DIAGRAM
PROGRESS
PROJECT DETAILS
Contract Title CONSTRUCTION OF ABU ARISH-2 132/13.8 KV SS
Contract No 4400013046
Contractor HAIF COMPANY
Contract Value 41,794,500 SR.
Approved Invoices 18,573,957 (44.44%) SR.
Start Date Status TCC
05 Feb 2020 Under construction 05 Jun 2023
2020 2021 2022 2023
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
.
05-02-2020
85.3 %
TCC (Contractual)
05-06-2023
Issues
• Delivery of Power Transformers are delayed. Will be arrived at site on 30.11.2022.
Normal
Project
Design Material Constructions Installations Pre check
97% 96% 96% 98% 5%
132kV GIS 12 Bays HYOSUNG,KOREA Installation 100%
132kV Transformer 3*67MVA ABB NG SCOPE Not Delivered
(Expected delivery on
30/11/2022)
SWG 51 CB ALFANAR, KSA Installation 100%
Control panels Lot SEP ,KSA Installation 100%
AC/DC LOT ALFANAR, KSA AC/DC panels delivered
Aux TR 2 SFT, KSA Installation 100 %
Gantry &SA& CSE LOT ALNAFIE, KSA Installation 90%
SAS LOT ABB (HITACHI) Installation
Communication system LOT ABB, KSA FAT DONE
9
132
ASSALAMAH SUBSTATION
132/13.8 KV
NEW
Existing
NEW
Existing
ABU ARISH-2 132/13.8
KV SUBSTATION
5.96KM
6.8KM
15.8
KM
JAZAN CPS-2
SUBSTATION
132/33KV
10. PROJECT PHASE
PROGRESS
PROJECT DETAILS
Contract Title CONSTRUCTION OF 132KV D/C OHTLTO SUPPLY
POWER TO ABU ARISH-2 132/13.8KV S/S
Contract No 4400013011
Contractor NCC
Contract Value 12,400,000 SR.
Approved Invoices 7,461,044(66.4%) SR.
Start Date Status TCC
27 Jan 2020 Under construction 26 Jan 2023
Issues
• Delay of missing materials delivery to the site. (Solved).
• Outgas plan on 18.12.2022.
Length NO. of Tower No# Foundation
12 KM 36 36
7.85 KM 34 36
BLOCK DIAGRAM
132
ASSALAMAH SUBSTATION
132/13.8 KV
NEW
Existing
NEW
Existing
ABU ARISH-2 132/13.8
KV SUBSTATION
JAZAN CPS-2
SUBSTATION
132/33KV
Normal
Project
Design Material Constructions Installations Testing
86 % 98.5% 95 % 50 % 0 %
2019 2020 2021 2022 2023
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
.
27-01-2020 79 % TCC (Contractual)
26-01-2023
10
5.96KM
6.8KM
15.8
KM
11. PROJECT PHASE
BLOCK DIAGRAM
PROGRESS
PROJECT DETAILS
Contract Title CONSTRUCTION OF ZARGA-2 132/13.8 KV
Contract No 4400013117
Contractor AL SHARIF GROUP
Contract Value 42,609,562 SR.
Approved Invoices 26,346,723(61.82%) SR.
Start Date Status TCC
23 Mar 2020 Under construction 1 Jun 2023
2020 2021 2022 2023
Q1Q2Q3Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
.
23-03-2020
85%
Issues
• Delayed of arrived Material (power transformer) . Will be shipping to site on 15/11/2022.
• poor performance of contractor to start pre-commissioning.
TCC (Expected)
01-06-2023
132
0.2 KM
JAZAN CPS-1
132/33 KV
NEW
Existing
NEW
Existing
ZARGA-2 132/13.8 KV
SUBSTATION
KUDMI 132KV
SUBSTATION
Normal
Project
Design Material Constructions Installations Testing
99.8% 97.14% 95.25% 93.2% 0%
132kV GIS 12 Bay Hyosung Installation
Power Transformers 3*67 MVA ABB- Turkey Delivered
13.8kV Switchgear Room 48 CB ABB Installation
Control and Protection LOT ABB Installation
SAS LOT ABB FAT Done
AC/DC panels LOT ETA FAT Done
Battery Charger 2 STATRON Installation
Battery LOT HOPPECKE Installation
Communication System LOT ABB Installation
Auxiliary Xmer 2 UTEC Installation
OHTL Tower LOT AIC Installation
11
11KM
24KM
12. PROJECT PHASE
BLOCK DIAGRAM
PROGRESS
PROJECT DETAILS
Contract Title POWER SUPPLY TO HOUSING PROJECT (STAGE-1)
OF MINISTRY OF DEFENCE IN JIZAN
Contract No PTS16SN110
Contractor TDP
Contract Value 95,506,513.2 SR.
Approved Invoices 46,801,833 (46.67%) SR
Start Date Status TCC
01 March 2021 Under construction 07 Feb 2023
Issues
• (6) invoices payment from MOD to contractor.
• Change order for the conductors ( GZTACSR) .
• Waiting approval for shutdown.
2020 2021 2022 2023
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
.
01/03/2020 74.2 % TCC (Contractual & Expected)
07-02-2023
AD-Darb
132/33 KV
NEW
Existin
g
BAISH 132/33/13.8
KV SUBSTATION
HOUSING OF MINISTRY
OF DEFENCE IN JIZAN
1
KM
Normal
Project
Design Material Constructions Installations Testing
98 % 94% 84 % 52.2 % 0 %
33 KM
26 KM
OGW
Power Transformer 132kV 2*67MVA SPTC / Dammam Installation
GIS 132 kv 11 HHI/Korea Installation
Surge Arrester 132 kV 18 pcs TRIDELTA/Germany Installation
Cable Terminations 132kV Lot Jeddah Cables / KSA Installation
Towers 8 No AIC Steel/KSA Installation
Conductors ( GZTACSR) 195 km Sumitomo
Electric/Japan
Partial delivery
OPGW 4 km Prysmian/Spain Installation
Switch Gear Lot AES / KSA Installation
12
13. PROJECT PHASE
BLOCK DIAGRAM
PROGRESS
PROJECT DETAILS
Contract Title CONNECTION OF AL ARIDAH , AYBAN AND AD
DAYIR 132KV SS IN JAZAN WITH NETWORKS
Contract No 4400013250
Contractor AL SHARIF GROUP FOR CONTR
Contract Value 39,200,000 SR.
Approved Invoices 22,295,584 (57%) SR.
Start Date Status TCC
23 Mar 2020 Under construction 22-May 2023
2020 2021 2022 2023
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
.
23-03-2020
83.9%
TCC (Expected)
13-05-2023
New Line NO. of Tower NO. of foundation
28 KM 90 90
Completed 89 89
Normal
Project
Design Material Constructions Installations Testing
98 % 89 % 96 % 75 % 0 %
Reconductoring NO. of Tower 1st 2nd Circuit
17 KM 55 55
Completed 55 0
Issues
• Substation modification Design in Ayban & Al Dayer.
• ABB response is awaited regarding finalization of CT in side GIS at Ayban S/S.
• One Tap-off Tower will be constructed during Outage of CKT-2 of Ayban - Ad Dayir line.
• Waiting Shutdown for 2nd CKT of Ayban – Ad Dayir (17km Line).
Partial Energized
05-04-2022
13
AD DAYIR SS
132/33/13.8 KV
NEW
Existing
NEW
Existing
AYBAN SS
132/33 /13.18 KV
28KM AL ARIDAH SS
132/13.8 KV
16.5 KM
170M
16.7KM
14. PROJECT PHASE
BLOCK DIAGRAM
PROGRESS
PROJECT DETAILS
Contract Title ADDITION OF THIRD TRANSFORMER TO AL-HAQU
132/33 KV S/S.
Contract No 4400008427
Contractor GE
Contract Value 25,190,000 SR.
Approved Invoices 17,911,440 (71.1%) SR.
Start Date Status TCC
25 Oct 2016 Under construction 22 Jul 2023
Issues
• Negative Change order approval .
NEW
Existing
NEW
Existing
AL-HAQU 132/33 KV
EXPANSION
2016 2018 2022 2023
Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q3 Q4
.
25-10-2016 95%
TCC (Expected)
22-07-2023
Normal
Project
Design Material Constructions Installations Testing
100% 100% 100% 100% 60%
14
33kV SWG 13 ABB Installation
DTCB 1 ABB Installation
Capacitor 1 GE Installation
HV cable 1drum Saudi Cables Installation
MV Cable 1drum Saudi Cables Installation
Protection panels Lots GE Installation
15. PROGRESS PROJECT PHASE
BLOCK DIAGRAM
Start Date Status TCC
11 May 2022 Under construction 21 Aug 2023
Issues :
Delay in Route approval.
Length No# Tower No# Foundation
24.4 Km 78 78
ABU QAEED
132KV SS
ALHAQU
132KV SS
24.4 KM
PROJECT DETAILS
Contract Title CONSTRUCTION OF 132KV D/C OHTL BETWEEN
ABU QAEED132KV S/S AND AL HAQU 132KV S/S
Contract No 4400016383
Contractor Raissy
Contract Value 48,104,420.00 SR.
Approved Invoices 0.00 SR.
Design Material Constructions Installations Testing
36% 11.55% 8.5% 0% 0%
2022 2023 2024 2026
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
.
11-05-2022 11.24%
TCC(Contractual )
10-08-2023
Critical
Project
15
NEW
Existing
16. PROJECT PHASE
BLOCK DIAGRAM
PROGRESS
PROJECT DETAILS
Contract Title CONSTRUCTION OF DHAHYAH HOUSING 132/13.8
kV SUBSTATION IN JIZAN AREA
Contract No 4400016524
Contractor AL SHARIF GROUP & KEC LIMITED CO.
Contract Value 74,495,088 SR.
Approved Invoices -
Start Date Status TCC
31 May 2022 Under Design 30 Nov 2023
Issues
• Site office mobilization to be done post receipt of approval for Site office layout and clearances from all
concerned parties for establishment of same due to ROW issues regarding site handover.
• Soil Investigation works to be commenced immediately post provision of access which is on hold due to site
handover and local authorities.
2022 2023 2024 2025
Q3Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
.
31-05-2022 TCC Contractual
30-11-2023
4.28 %
NEW
Existing
DHAHYAH
HOUSING
132/13.8 kV S/S
General + Design Material Constructions Installations Testing
0.60% + 3.15% 0.53% 0% 0% 0%
Critical
Project
16
132 kV GIS
9 Bays + 2
Bays
Hyundai Electric,
Korea
Submission response received dt 10th Nov ,
Compliance to be submitted
132/13.8 kV Power
Transformers
2 no’s SPTC, Dammam
Submission response received dated 7th Nov
,compliance to be submitted
13.8 kV Switchgear 1 Lot Alfanar, KSA
Submission response received dated 27th
Oct ,compliance to be submitted.
Control & Protection 1 Lot Siemens, KSA Under Design review
SAS & Telecom 1 Lot Siemens, KSA Under Design review
Surge Arresters 6 x 108 kV Tridelta, Germany
Submission response received dated 7th Nov
,compliance to be submitted
LT AC & DC Panels Lot Alfanar, KSA Under Design review
Cyber Security Lot Alfanar, KSA Design to be submitted after SAS approval
Capacitor Bank 2 Set
Samwah, Korea
Eaton, Germany
Submission response received dated 7th Nov
,compliance to be submitted
Battery SET
2 Piece(125
VDC)
HOPPECKE
Submission response received dated 3rd
Nov ,compliance to be submitted.
Battery Charger 2 Sets (125
VDC)
Statron, UAE
JIZAN UNIVERSITY
132/13.8 kV S/S
17. BLOCK DIAGRAM
PROGRESS
PROJECT DETAILS
Contract Title CONNECTION OF DHAHYAH HOUSING 132/13.8KV
S/S WITH JIZAN UNIVERSITY
Contract No PTS15SC1032
Contractor Delta.
Contract Value 13,335,000 SR.
Approved Invoices -
Issues
• Waiting approval from Ministry Housing for extending project time.
• ROW of S/S effect also the UGTL.
2020 2021 2022
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
30-04-2020 TCC Contractual
30-06-2022
0 %
NEW
Existing
DHAHYAH
HOUSING
132/13.8 kV S/S
General + Design Material Constructions Installations Testing
0% 0% 0% 0% 0%
Critical
Project
17
JIZAN
UNIVERSITY
132/13.8 kV S/S
2.9KM
Start Date Status TCC
30 Apr 2020 Under Design 30 Jun 2022
PROJECT PHASE
18. BLOCK DIAGRAM
PROGRESS
PROJECT DETAILS
Contract Title RCJ 380/132/33KV BSP SS1A SS & OHTL BETWEEN
RCJ BSP – KUDMI BSP AND RCJ BSP – JRP BSP
Contract No PTS -20SN386
Contractor AL Hader.
Contract Value 437,535,484SR.
Approved Invoices -
Issues :
• Delay for approval of final PTS of OHTL.
Design Material Constructions Installations Testing
3.5% 0% 0% 0% 0%
Critical
Project
18
Start Date Status TCC
15 July 2020 Under Design 01 Oct 2025
PROJECT PHASE
JRP BSP
SS1A 380KV
Kudmi BSP 46KM 11.5KM
2020 2021 2022 2023 2024 2025
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3
3.5 %
15-07-2020
TCC Contractual
01-10-2025
NEW
Existing