SlideShare a Scribd company logo
1 of 4
Download to read offline
39.37 TONS 31.34 TONS 6.29 TONS
79.60% 15.97%
SL # MARK NO.
MARK
LOCATION
REF. #
PRIORITY QTY WEIGHT
TOTAL
WEIGHT
FORECAST
FINISH
ACTUAL
FINISH
FORECAST
DESPATCH
ACTUAL
DESPATCH
FORECAST
START
ACTUAL
START
FORECAST
FINISH
ACTUAL
FINISH
REMARKS
8.25
DELIVERED TO SITE
PRIORITYNO.1
OVERALL SUMMARY: DELIVERED
Percent %
ERECTED
Percent %
G 15 @ Gridline 1-2/ H-K
DATE:
30-Apr-09
SPIRE TOWER: WCN 202-ROOF FRAMING w/ CLADDING [G-15]
(INTERNAL SCHEDULE)
FABRICATION DELIVERY ERECTION
1 B18 1 1 807.1 0.8071 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09
M22, M25
2 B16 1 1 2117.7 2.1177 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09
M93, M91, M102, M103
3 B28 2 1 161.3 0.1613 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09
4 B20 2 1 113.7 0.1137 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09
5 B14 1 1 3361.4 3.3614 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09
M105, M104, M95, M96, M106, M107
6 B21 2 1 228.5 0.2285 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09
7 B54 2 1 365.9 0.3659 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09
8 A1 3 1 74.8 0.3390 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09
9 A14 3 1 72.6 0.0726 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09
10 A15 3 1 74.8 0.0748 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09
DELIVERED TO SITE
PRIORITYNO.1
PRIORITYNO.2
11 B38 4 1 270.1 0.2701 25-Apr-09 24-Apr-09 26-Apr-09 26-Apr-09 27-Apr-09 27-Apr-09
12 A8 3 1 139.4 0.1394 25-Apr-09 24-Apr-09 26-Apr-09 26-Apr-09 27-Apr-09 27-Apr-09
13 B4 3 1 42.0 0.0420 25-Apr-09 24-Apr-09 26-Apr-09 26-Apr-09 27-Apr-09 27-Apr-09
14 B33 4 1 156.4 0.1564 25-Apr-09 24-Apr-09 26-Apr-09 26-Apr-09 27-Apr-09 27-Apr-09
PLEASE SEE MARK LOCATION REFERENCE:
B18
DELIVERED TO SITE
PRIORITYNO.2
Please See Mark Location Reference No:
(1) Main Assembly Frames.
(2) Horizontal Top Member.
(3) Vertical Cross Bracings.
(4) Horizontal Member.
B14 B162
3
4
1 1
B18
B16
B14
Page 1
39.37 TONS 31.34 TONS 6.29 TONS
79.60% 15.97%
SL # MARK NO.
MARK
LOCATION
REF. #
PRIORITY QTY WEIGHT
TOTAL
WEIGHT
FORECAST
FINISH
ACTUAL
FINISH
FORECAST
DESPATCH
ACTUAL
DESPATCH
FORECAST
START
ACTUAL
START
FORECAST
FINISH
ACTUAL
FINISH
REMARKS
OVERALL SUMMARY: DELIVERED
Percent %
ERECTED
Percent %
DATE:
30-Apr-09
SPIRE TOWER: WCN 202-ROOF FRAMING w/ CLADDING [G-15]
(INTERNAL SCHEDULE)
FABRICATION DELIVERY ERECTION
7.03
PRIORITYNO.2
DELIVERED TO SITE
G 15 @ Gridline 1-2/ H-K
15 B22 2 1 278.4 0.2784 25-Apr-09 24-Apr-09 26-Apr-09 26-Apr-09 27-Apr-09 27-Apr-09
16 B32 2 2 191.8 0.3836 25-Apr-09 24-Apr-09 26-Apr-09 26-Apr-09 27-Apr-09 27-Apr-09
17 A7 3 1 166.7 0.1667 25-Apr-09 24-Apr-09 26-Apr-09 26-Apr-09 27-Apr-09 27-Apr-09
18 B32 4 2 191.8 0.3836 25-Apr-09 24-Apr-09 26-Apr-09 26-Apr-09 27-Apr-09 27-Apr-09
19 A6 2 1 159.3 0.1593 25-Apr-09 24-Apr-09 26-Apr-09 26-Apr-09 27-Apr-09 27-Apr-09
PRIORITYNO.2
PRIORITYNO.3
DELIVERED TO SITE
20 B55 4 1 516.0 0.5160 26-Apr-09 24-Apr-09 27-Apr-09 26-Apr-09 28-Apr-09 28-Apr-09
21 B8 3 1 394.7 0.3947 26-Apr-09 24-Apr-09 27-Apr-09 26-Apr-09 28-Apr-09 28-Apr-09
22 B10 3 1 394.6 0.3946 26-Apr-09 24-Apr-09 27-Apr-09 26-Apr-09 28-Apr-09 28-Apr-09
23 B11 1 1 3977.5 3.9775 26-Apr-09 28-Apr-09 27-Apr-09 29-Apr-09 28-Apr-09 28-Apr-09
M177, M4, M3, M108, M94, M92
24 A12 3 1 191.8 0.1918 26-Apr-09 24-Apr-09 27-Apr-09 26-Apr-09 28-Apr-09 28-Apr-09
25 A13 3 1 185.0 0.1850 26-Apr-09 24-Apr-09 27-Apr-09 26-Apr-09 28-Apr-09 28-Apr-09
PLEASE SEE MARK LOCATION REFERENCE:
PRIORITYNO.3
DELIVERED TO SITE
B11 B14
2
3
4
1 1
B14
B11Please See Mark Location Reference No:
(1) Main Assembly Frames.
(2) Horizontal Top Member.
(3) Vertical Cross Bracings.
(4) Horizontal Member.
Page 2
39.37 TONS 31.34 TONS 6.29 TONS
79.60% 15.97%
SL # MARK NO.
MARK
LOCATION
REF. #
PRIORITY QTY WEIGHT
TOTAL
WEIGHT
FORECAST
FINISH
ACTUAL
FINISH
FORECAST
DESPATCH
ACTUAL
DESPATCH
FORECAST
START
ACTUAL
START
FORECAST
FINISH
ACTUAL
FINISH
REMARKS
OVERALL SUMMARY: DELIVERED
Percent %
ERECTED
Percent %
DATE:
30-Apr-09
SPIRE TOWER: WCN 202-ROOF FRAMING w/ CLADDING [G-15]
(INTERNAL SCHEDULE)
FABRICATION DELIVERY ERECTION
4.83
PRIORITYNO.3
DELIVERED TO SITE
G 15 @ Gridline 1-2/ H-K
26 C2 1 1 1839.9 1.8399 26-Apr-09 24-Apr-09 27-Apr-09 26-Apr-09 28-Apr-09 28-Apr-09
27 A4 3 1 122.9 0.1229 26-Apr-09 25-Apr-09 27-Apr-09 26-Apr-09 28-Apr-09 28-Apr-09
28 B29 4 1 126.9 0.1269 26-Apr-09 24-Apr-09 27-Apr-09 26-Apr-09 28-Apr-09 28-Apr-09
29 A3 3 2 130.8 0.2616 26-Apr-09 24-Apr-09 27-Apr-09 26-Apr-09 28-Apr-09 28-Apr-09
PRIORITYNO.3
PRIORITYNO.4
DELIVERED TO SITE
30 B30 4 1 131.2 0.1312 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09
31 A5 3 2 134.9 0.2698 27-Apr-09 25-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09
32 B31 4 1 130.1 0.1301 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09
33 B19 2 1 181.3 0.1813 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09
34 B57 2 1 366.7 0.3667 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09
35 B36 4 1 294.8 0.2948 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09
36 A16 3 1 168.7 0.1687 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09
37 B24 4 1 297.3 0.2973 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09
38 A17 3 1 173.1 0.1731 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09
39 B34 4 1 297.3 0.2973 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09
40 A18 3 1 165.5 0.1655 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09
PLEASE SEE MARK LOCATION REFERENCE:
PRIORITYNO.4
DELIVERED TO SITE
C2 B11
2
3
4
1 1
B11
C2
Please See Mark Location Reference No:
(1) Main Assembly Frames.
(2) Horizontal Top Member.
(3) Vertical Cross Bracings.
(4) Horizontal Member.
Page 3
DATE:
SPIRE TOWER PROJECT
9-Apr-09
WCN -203
SPIRE TOWER with CLADDING,47M LEVEL 70
SECTION 1
Fab'n: 22-Mar-09
Deliver to Site: 15-Apr-09
Erection Start: 16-Apr-09
SECTION 3
Fab'n: 23-Mar-09
Deliver to Site: 17-Apr-09
Erection Start: 19-Apr-09
Weld Splice: 20-Apr-09
SECTION 6
Fab'n: 24-Mar-09
Deliver to Site: 21-Apr-09
Erection Start: 25-Apr-09
Weld Splice: 26-Apr-09
SECTION 8
Fab'n: 25-Mar-09
Deliver to Site: 23-Apr-09
Erection Start: 29-Apr-09
Weld Splice: 30-Apr-09
SECTION 10
Fab'n: 26-Mar-09
Deliver to Site: 24-Apr-09
Erection Start: 03-May-09
Weld Splice: 04-May-09
SECTION 11
Fab'n: 27-Mar-09
Deliver to Site: 24-Apr-09
Erection Starts: 05-May-09
Weld Splice: 06-May-09
Line& Level: 07-May-09
Inspection: 08-May-09
SECTION 9
Fab'n: 26-Mar-09
Deliver to Site: 23-Apr-09
Erection Start: 01-May-09
Weld Splice: 02-May-09
SECTION 7
Fab'n: 25-Mar-09
Deliver to Site: 22-Apr-09
Erection Start: 27-Apr-09
Weld splice: 28-Apr-09
SECTION 5
Fab'n: 24-Mar-09
Deliver to Site: 20-Apr-09
Erection Start: 23-Apr-09
Weld Splice: 24-April-09
SECTION 4
Fab'n: 23-Mar-09
Deliver to Site: 19-Apr-09
Erection Start: 21-Apr-09
Weld Splice: 22-Apr-09
SECTION 2
Fab'n: 22-Mar-09
Deliver to Site: 15-Apr-09
Erection Start: 17-Apr-09
Weld Splice: 18-Apr-09

More Related Content

What's hot

INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING Ram1239
 
Safety management for construction machines & equipments
 Safety management for construction machines & equipments Safety management for construction machines & equipments
Safety management for construction machines & equipmentsSelva Prakash
 
Assessment report template
Assessment report templateAssessment report template
Assessment report templateTogkz123
 
Monthly Progress Report Sample
Monthly Progress Report SampleMonthly Progress Report Sample
Monthly Progress Report SampleElias Ibrahim
 
SMM7 Bill of Quantities
SMM7 Bill of QuantitiesSMM7 Bill of Quantities
SMM7 Bill of QuantitiesNatalie Reid
 
Koppolu abishek prying action
Koppolu abishek   prying actionKoppolu abishek   prying action
Koppolu abishek prying actionKoppolu Abishek
 
Steel Structure Fabrication and erection (Ravi Choudhary).pptx
Steel Structure Fabrication and erection (Ravi Choudhary).pptxSteel Structure Fabrication and erection (Ravi Choudhary).pptx
Steel Structure Fabrication and erection (Ravi Choudhary).pptxmrujjavalsinghvarana
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001Minh Bui Si
 
Presentation on steel, fabrication & erection Munger Ganga Bridge
Presentation on steel, fabrication & erection  Munger Ganga BridgePresentation on steel, fabrication & erection  Munger Ganga Bridge
Presentation on steel, fabrication & erection Munger Ganga BridgeAshish Kumar Yadav
 
Method statement for structure excavation
Method statement for structure excavationMethod statement for structure excavation
Method statement for structure excavationAl-Amin Ahmed Nabin
 
106769120-General-Connection-in-Steel-Structures.ppt
106769120-General-Connection-in-Steel-Structures.ppt106769120-General-Connection-in-Steel-Structures.ppt
106769120-General-Connection-in-Steel-Structures.pptMario Marcelo
 
PICE SPECIALIST MEMBER FAQs
PICE SPECIALIST MEMBER FAQsPICE SPECIALIST MEMBER FAQs
PICE SPECIALIST MEMBER FAQsDanilo Villamor
 
Advance building measurement NRM 2
Advance building measurement NRM 2Advance building measurement NRM 2
Advance building measurement NRM 2Danushka Prädeep
 

What's hot (20)

INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
 
Main_book_CSWIP_3_1_Welding_Inspector_WI.pdf
Main_book_CSWIP_3_1_Welding_Inspector_WI.pdfMain_book_CSWIP_3_1_Welding_Inspector_WI.pdf
Main_book_CSWIP_3_1_Welding_Inspector_WI.pdf
 
Safety management for construction machines & equipments
 Safety management for construction machines & equipments Safety management for construction machines & equipments
Safety management for construction machines & equipments
 
Assessment report template
Assessment report templateAssessment report template
Assessment report template
 
Monthly Progress Report Sample
Monthly Progress Report SampleMonthly Progress Report Sample
Monthly Progress Report Sample
 
EQS - RATE ANALYSIS.pdf
EQS -  RATE ANALYSIS.pdfEQS -  RATE ANALYSIS.pdf
EQS - RATE ANALYSIS.pdf
 
SMM7 Bill of Quantities
SMM7 Bill of QuantitiesSMM7 Bill of Quantities
SMM7 Bill of Quantities
 
Koppolu abishek prying action
Koppolu abishek   prying actionKoppolu abishek   prying action
Koppolu abishek prying action
 
History of sand casting
History of sand castingHistory of sand casting
History of sand casting
 
Steel Structure Fabrication and erection (Ravi Choudhary).pptx
Steel Structure Fabrication and erection (Ravi Choudhary).pptxSteel Structure Fabrication and erection (Ravi Choudhary).pptx
Steel Structure Fabrication and erection (Ravi Choudhary).pptx
 
Welding electrode
Welding electrodeWelding electrode
Welding electrode
 
Slope deflection method
Slope deflection methodSlope deflection method
Slope deflection method
 
Building work method statement cm - ms- bw - 001
Building work method statement  cm - ms- bw - 001Building work method statement  cm - ms- bw - 001
Building work method statement cm - ms- bw - 001
 
Schedule-Delay Analysis
Schedule-Delay AnalysisSchedule-Delay Analysis
Schedule-Delay Analysis
 
Presentation on steel, fabrication & erection Munger Ganga Bridge
Presentation on steel, fabrication & erection  Munger Ganga BridgePresentation on steel, fabrication & erection  Munger Ganga Bridge
Presentation on steel, fabrication & erection Munger Ganga Bridge
 
Method statement for structure excavation
Method statement for structure excavationMethod statement for structure excavation
Method statement for structure excavation
 
Risk management
Risk managementRisk management
Risk management
 
106769120-General-Connection-in-Steel-Structures.ppt
106769120-General-Connection-in-Steel-Structures.ppt106769120-General-Connection-in-Steel-Structures.ppt
106769120-General-Connection-in-Steel-Structures.ppt
 
PICE SPECIALIST MEMBER FAQs
PICE SPECIALIST MEMBER FAQsPICE SPECIALIST MEMBER FAQs
PICE SPECIALIST MEMBER FAQs
 
Advance building measurement NRM 2
Advance building measurement NRM 2Advance building measurement NRM 2
Advance building measurement NRM 2
 

Viewers also liked

Sample MSProject with 16 DivisionFormat Variation(EOT)
Sample MSProject with 16 DivisionFormat Variation(EOT)Sample MSProject with 16 DivisionFormat Variation(EOT)
Sample MSProject with 16 DivisionFormat Variation(EOT)Allan Leyte
 
Visio-Planning FlowChart-3
Visio-Planning FlowChart-3Visio-Planning FlowChart-3
Visio-Planning FlowChart-3Allan Leyte
 
Construction Methodology Scheduling1
Construction Methodology Scheduling1Construction Methodology Scheduling1
Construction Methodology Scheduling1Allan Leyte
 
PRODUCTION RATE APPX. NEW
PRODUCTION RATE APPX. NEWPRODUCTION RATE APPX. NEW
PRODUCTION RATE APPX. NEWAllan Leyte
 
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationHarish Mahavar
 
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Allan Leyte
 
Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & SequenceDavid H Moloney
 

Viewers also liked (8)

Sample MSProject with 16 DivisionFormat Variation(EOT)
Sample MSProject with 16 DivisionFormat Variation(EOT)Sample MSProject with 16 DivisionFormat Variation(EOT)
Sample MSProject with 16 DivisionFormat Variation(EOT)
 
WEIGHTING TABLE
WEIGHTING TABLEWEIGHTING TABLE
WEIGHTING TABLE
 
Visio-Planning FlowChart-3
Visio-Planning FlowChart-3Visio-Planning FlowChart-3
Visio-Planning FlowChart-3
 
Construction Methodology Scheduling1
Construction Methodology Scheduling1Construction Methodology Scheduling1
Construction Methodology Scheduling1
 
PRODUCTION RATE APPX. NEW
PRODUCTION RATE APPX. NEWPRODUCTION RATE APPX. NEW
PRODUCTION RATE APPX. NEW
 
Boq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping stationBoq of khadeja storage tank, well, and booster pumping station
Boq of khadeja storage tank, well, and booster pumping station
 
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
Programme Sync with BOQ from contract, Cost & ResEqp Loaded (Initial Stage)
 
Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & Sequence
 

Similar to Sample of Structural Steel Scheduling

Equipment Arrival Status.pptx
Equipment Arrival Status.pptxEquipment Arrival Status.pptx
Equipment Arrival Status.pptxMehmanNasibov1
 
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2Arun Bharadwaj
 
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityHSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityRoumik Mukherjee
 
Copy of 4th & 1 Plays '09-'11
Copy of 4th & 1 Plays '09-'11Copy of 4th & 1 Plays '09-'11
Copy of 4th & 1 Plays '09-'11Dajuan Brown
 
2014年11月度のアップデート(スパイス・パーク)
2014年11月度のアップデート(スパイス・パーク)2014年11月度のアップデート(スパイス・パーク)
2014年11月度のアップデート(スパイス・パーク)Tsuyoshi Horigome
 
Coastal joinery hardware specialist ironmongery - catalogue version v.03 pa...
Coastal joinery hardware   specialist ironmongery - catalogue version v.03 pa...Coastal joinery hardware   specialist ironmongery - catalogue version v.03 pa...
Coastal joinery hardware specialist ironmongery - catalogue version v.03 pa...Coastal Joinery Hardware
 
Update Data of APR2014 in SPICEPARK
Update Data of APR2014 in SPICEPARK Update Data of APR2014 in SPICEPARK
Update Data of APR2014 in SPICEPARK Tsuyoshi Horigome
 
MONTHLY REPORT_MARITIM PRIMA 1
MONTHLY REPORT_MARITIM PRIMA 1MONTHLY REPORT_MARITIM PRIMA 1
MONTHLY REPORT_MARITIM PRIMA 1Eko Untung
 
132-18 41th RD steel shop drawing 11_21_2015
132-18 41th RD steel shop drawing 11_21_2015132-18 41th RD steel shop drawing 11_21_2015
132-18 41th RD steel shop drawing 11_21_2015Peter Zhang
 
Samarium Cobalt Magnets SmCo5 Sm2Co17 - China Rare Earth Magnet Limited
Samarium Cobalt Magnets SmCo5 Sm2Co17 - China Rare Earth Magnet LimitedSamarium Cobalt Magnets SmCo5 Sm2Co17 - China Rare Earth Magnet Limited
Samarium Cobalt Magnets SmCo5 Sm2Co17 - China Rare Earth Magnet LimitedChina Rare Earth Magnet Limited
 
Ellis Patents AR2-A31 Atlas Trefoil Cable Cleat - 24-26mm - Spec Sheet
Ellis Patents AR2-A31 Atlas Trefoil Cable Cleat - 24-26mm - Spec SheetEllis Patents AR2-A31 Atlas Trefoil Cable Cleat - 24-26mm - Spec Sheet
Ellis Patents AR2-A31 Atlas Trefoil Cable Cleat - 24-26mm - Spec SheetThorne & Derrick International
 
Mechanical Building redesign
Mechanical Building redesignMechanical Building redesign
Mechanical Building redesignAli Abuzant
 

Similar to Sample of Structural Steel Scheduling (20)

Equipment Arrival Status.pptx
Equipment Arrival Status.pptxEquipment Arrival Status.pptx
Equipment Arrival Status.pptx
 
ERUP WBS
ERUP WBSERUP WBS
ERUP WBS
 
Machinery schedule
Machinery scheduleMachinery schedule
Machinery schedule
 
Machinery schedule
Machinery scheduleMachinery schedule
Machinery schedule
 
IC3D example dwgs
IC3D example dwgsIC3D example dwgs
IC3D example dwgs
 
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2
 
HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityHSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
 
Copy of 4th & 1 Plays '09-'11
Copy of 4th & 1 Plays '09-'11Copy of 4th & 1 Plays '09-'11
Copy of 4th & 1 Plays '09-'11
 
2014年11月度のアップデート(スパイス・パーク)
2014年11月度のアップデート(スパイス・パーク)2014年11月度のアップデート(スパイス・パーク)
2014年11月度のアップデート(スパイス・パーク)
 
Coastal joinery hardware specialist ironmongery - catalogue version v.03 pa...
Coastal joinery hardware   specialist ironmongery - catalogue version v.03 pa...Coastal joinery hardware   specialist ironmongery - catalogue version v.03 pa...
Coastal joinery hardware specialist ironmongery - catalogue version v.03 pa...
 
12777 coastal single pages part43
12777  coastal single pages part4312777  coastal single pages part43
12777 coastal single pages part43
 
Update Data of APR2014 in SPICEPARK
Update Data of APR2014 in SPICEPARK Update Data of APR2014 in SPICEPARK
Update Data of APR2014 in SPICEPARK
 
MONTHLY REPORT_MARITIM PRIMA 1
MONTHLY REPORT_MARITIM PRIMA 1MONTHLY REPORT_MARITIM PRIMA 1
MONTHLY REPORT_MARITIM PRIMA 1
 
Project Portfolio
Project PortfolioProject Portfolio
Project Portfolio
 
Ellis Patents Atlas Cable Cleats
Ellis Patents Atlas Cable CleatsEllis Patents Atlas Cable Cleats
Ellis Patents Atlas Cable Cleats
 
132-18 41th RD steel shop drawing 11_21_2015
132-18 41th RD steel shop drawing 11_21_2015132-18 41th RD steel shop drawing 11_21_2015
132-18 41th RD steel shop drawing 11_21_2015
 
Samarium Cobalt Magnets SmCo5 Sm2Co17 - China Rare Earth Magnet Limited
Samarium Cobalt Magnets SmCo5 Sm2Co17 - China Rare Earth Magnet LimitedSamarium Cobalt Magnets SmCo5 Sm2Co17 - China Rare Earth Magnet Limited
Samarium Cobalt Magnets SmCo5 Sm2Co17 - China Rare Earth Magnet Limited
 
Ellis Patents AR2-A31 Atlas Trefoil Cable Cleat - 24-26mm - Spec Sheet
Ellis Patents AR2-A31 Atlas Trefoil Cable Cleat - 24-26mm - Spec SheetEllis Patents AR2-A31 Atlas Trefoil Cable Cleat - 24-26mm - Spec Sheet
Ellis Patents AR2-A31 Atlas Trefoil Cable Cleat - 24-26mm - Spec Sheet
 
Mechanical Building redesign
Mechanical Building redesignMechanical Building redesign
Mechanical Building redesign
 
Project Schedule - Level IV Schedule
Project Schedule - Level IV ScheduleProject Schedule - Level IV Schedule
Project Schedule - Level IV Schedule
 

More from Allan Leyte

BHP01-0 Bouly baseline on MSproject Format
BHP01-0 Bouly baseline on MSproject FormatBHP01-0 Bouly baseline on MSproject Format
BHP01-0 Bouly baseline on MSproject FormatAllan Leyte
 
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)Allan Leyte
 
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)Allan Leyte
 
Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Allan Leyte
 
Booster Pump cause of delay analysis
Booster Pump cause of delay analysisBooster Pump cause of delay analysis
Booster Pump cause of delay analysisAllan Leyte
 
Sample Bidcom Presentation - Structural Works 12-28-11
Sample Bidcom Presentation - Structural Works 12-28-11Sample Bidcom Presentation - Structural Works 12-28-11
Sample Bidcom Presentation - Structural Works 12-28-11Allan Leyte
 
Scheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPMScheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPMAllan Leyte
 
Offshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocolOffshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocolAllan Leyte
 
Town Center presentation
Town Center presentationTown Center presentation
Town Center presentationAllan Leyte
 

More from Allan Leyte (12)

BHP01-0 Bouly baseline on MSproject Format
BHP01-0 Bouly baseline on MSproject FormatBHP01-0 Bouly baseline on MSproject Format
BHP01-0 Bouly baseline on MSproject Format
 
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
 
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
 
p3 s-curves
p3 s-curvesp3 s-curves
p3 s-curves
 
Wreport
WreportWreport
Wreport
 
Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016
 
Booster Pump cause of delay analysis
Booster Pump cause of delay analysisBooster Pump cause of delay analysis
Booster Pump cause of delay analysis
 
Sample Bidcom Presentation - Structural Works 12-28-11
Sample Bidcom Presentation - Structural Works 12-28-11Sample Bidcom Presentation - Structural Works 12-28-11
Sample Bidcom Presentation - Structural Works 12-28-11
 
Scheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPMScheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPM
 
Offshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocolOffshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocol
 
progress photos
progress photosprogress photos
progress photos
 
Town Center presentation
Town Center presentationTown Center presentation
Town Center presentation
 

Sample of Structural Steel Scheduling

  • 1. 39.37 TONS 31.34 TONS 6.29 TONS 79.60% 15.97% SL # MARK NO. MARK LOCATION REF. # PRIORITY QTY WEIGHT TOTAL WEIGHT FORECAST FINISH ACTUAL FINISH FORECAST DESPATCH ACTUAL DESPATCH FORECAST START ACTUAL START FORECAST FINISH ACTUAL FINISH REMARKS 8.25 DELIVERED TO SITE PRIORITYNO.1 OVERALL SUMMARY: DELIVERED Percent % ERECTED Percent % G 15 @ Gridline 1-2/ H-K DATE: 30-Apr-09 SPIRE TOWER: WCN 202-ROOF FRAMING w/ CLADDING [G-15] (INTERNAL SCHEDULE) FABRICATION DELIVERY ERECTION 1 B18 1 1 807.1 0.8071 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09 M22, M25 2 B16 1 1 2117.7 2.1177 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09 M93, M91, M102, M103 3 B28 2 1 161.3 0.1613 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09 4 B20 2 1 113.7 0.1137 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09 5 B14 1 1 3361.4 3.3614 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09 M105, M104, M95, M96, M106, M107 6 B21 2 1 228.5 0.2285 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09 7 B54 2 1 365.9 0.3659 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09 8 A1 3 1 74.8 0.3390 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09 9 A14 3 1 72.6 0.0726 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09 10 A15 3 1 74.8 0.0748 24-Apr-09 24-Apr-09 25-Apr-09 26-Apr-09 26-Apr-09 26-Apr-09 DELIVERED TO SITE PRIORITYNO.1 PRIORITYNO.2 11 B38 4 1 270.1 0.2701 25-Apr-09 24-Apr-09 26-Apr-09 26-Apr-09 27-Apr-09 27-Apr-09 12 A8 3 1 139.4 0.1394 25-Apr-09 24-Apr-09 26-Apr-09 26-Apr-09 27-Apr-09 27-Apr-09 13 B4 3 1 42.0 0.0420 25-Apr-09 24-Apr-09 26-Apr-09 26-Apr-09 27-Apr-09 27-Apr-09 14 B33 4 1 156.4 0.1564 25-Apr-09 24-Apr-09 26-Apr-09 26-Apr-09 27-Apr-09 27-Apr-09 PLEASE SEE MARK LOCATION REFERENCE: B18 DELIVERED TO SITE PRIORITYNO.2 Please See Mark Location Reference No: (1) Main Assembly Frames. (2) Horizontal Top Member. (3) Vertical Cross Bracings. (4) Horizontal Member. B14 B162 3 4 1 1 B18 B16 B14 Page 1
  • 2. 39.37 TONS 31.34 TONS 6.29 TONS 79.60% 15.97% SL # MARK NO. MARK LOCATION REF. # PRIORITY QTY WEIGHT TOTAL WEIGHT FORECAST FINISH ACTUAL FINISH FORECAST DESPATCH ACTUAL DESPATCH FORECAST START ACTUAL START FORECAST FINISH ACTUAL FINISH REMARKS OVERALL SUMMARY: DELIVERED Percent % ERECTED Percent % DATE: 30-Apr-09 SPIRE TOWER: WCN 202-ROOF FRAMING w/ CLADDING [G-15] (INTERNAL SCHEDULE) FABRICATION DELIVERY ERECTION 7.03 PRIORITYNO.2 DELIVERED TO SITE G 15 @ Gridline 1-2/ H-K 15 B22 2 1 278.4 0.2784 25-Apr-09 24-Apr-09 26-Apr-09 26-Apr-09 27-Apr-09 27-Apr-09 16 B32 2 2 191.8 0.3836 25-Apr-09 24-Apr-09 26-Apr-09 26-Apr-09 27-Apr-09 27-Apr-09 17 A7 3 1 166.7 0.1667 25-Apr-09 24-Apr-09 26-Apr-09 26-Apr-09 27-Apr-09 27-Apr-09 18 B32 4 2 191.8 0.3836 25-Apr-09 24-Apr-09 26-Apr-09 26-Apr-09 27-Apr-09 27-Apr-09 19 A6 2 1 159.3 0.1593 25-Apr-09 24-Apr-09 26-Apr-09 26-Apr-09 27-Apr-09 27-Apr-09 PRIORITYNO.2 PRIORITYNO.3 DELIVERED TO SITE 20 B55 4 1 516.0 0.5160 26-Apr-09 24-Apr-09 27-Apr-09 26-Apr-09 28-Apr-09 28-Apr-09 21 B8 3 1 394.7 0.3947 26-Apr-09 24-Apr-09 27-Apr-09 26-Apr-09 28-Apr-09 28-Apr-09 22 B10 3 1 394.6 0.3946 26-Apr-09 24-Apr-09 27-Apr-09 26-Apr-09 28-Apr-09 28-Apr-09 23 B11 1 1 3977.5 3.9775 26-Apr-09 28-Apr-09 27-Apr-09 29-Apr-09 28-Apr-09 28-Apr-09 M177, M4, M3, M108, M94, M92 24 A12 3 1 191.8 0.1918 26-Apr-09 24-Apr-09 27-Apr-09 26-Apr-09 28-Apr-09 28-Apr-09 25 A13 3 1 185.0 0.1850 26-Apr-09 24-Apr-09 27-Apr-09 26-Apr-09 28-Apr-09 28-Apr-09 PLEASE SEE MARK LOCATION REFERENCE: PRIORITYNO.3 DELIVERED TO SITE B11 B14 2 3 4 1 1 B14 B11Please See Mark Location Reference No: (1) Main Assembly Frames. (2) Horizontal Top Member. (3) Vertical Cross Bracings. (4) Horizontal Member. Page 2
  • 3. 39.37 TONS 31.34 TONS 6.29 TONS 79.60% 15.97% SL # MARK NO. MARK LOCATION REF. # PRIORITY QTY WEIGHT TOTAL WEIGHT FORECAST FINISH ACTUAL FINISH FORECAST DESPATCH ACTUAL DESPATCH FORECAST START ACTUAL START FORECAST FINISH ACTUAL FINISH REMARKS OVERALL SUMMARY: DELIVERED Percent % ERECTED Percent % DATE: 30-Apr-09 SPIRE TOWER: WCN 202-ROOF FRAMING w/ CLADDING [G-15] (INTERNAL SCHEDULE) FABRICATION DELIVERY ERECTION 4.83 PRIORITYNO.3 DELIVERED TO SITE G 15 @ Gridline 1-2/ H-K 26 C2 1 1 1839.9 1.8399 26-Apr-09 24-Apr-09 27-Apr-09 26-Apr-09 28-Apr-09 28-Apr-09 27 A4 3 1 122.9 0.1229 26-Apr-09 25-Apr-09 27-Apr-09 26-Apr-09 28-Apr-09 28-Apr-09 28 B29 4 1 126.9 0.1269 26-Apr-09 24-Apr-09 27-Apr-09 26-Apr-09 28-Apr-09 28-Apr-09 29 A3 3 2 130.8 0.2616 26-Apr-09 24-Apr-09 27-Apr-09 26-Apr-09 28-Apr-09 28-Apr-09 PRIORITYNO.3 PRIORITYNO.4 DELIVERED TO SITE 30 B30 4 1 131.2 0.1312 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09 31 A5 3 2 134.9 0.2698 27-Apr-09 25-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09 32 B31 4 1 130.1 0.1301 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09 33 B19 2 1 181.3 0.1813 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09 34 B57 2 1 366.7 0.3667 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09 35 B36 4 1 294.8 0.2948 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09 36 A16 3 1 168.7 0.1687 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09 37 B24 4 1 297.3 0.2973 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09 38 A17 3 1 173.1 0.1731 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09 39 B34 4 1 297.3 0.2973 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09 40 A18 3 1 165.5 0.1655 27-Apr-09 24-Apr-09 28-Apr-09 26-Apr-09 29-Apr-09 29-Apr-09 PLEASE SEE MARK LOCATION REFERENCE: PRIORITYNO.4 DELIVERED TO SITE C2 B11 2 3 4 1 1 B11 C2 Please See Mark Location Reference No: (1) Main Assembly Frames. (2) Horizontal Top Member. (3) Vertical Cross Bracings. (4) Horizontal Member. Page 3
  • 4. DATE: SPIRE TOWER PROJECT 9-Apr-09 WCN -203 SPIRE TOWER with CLADDING,47M LEVEL 70 SECTION 1 Fab'n: 22-Mar-09 Deliver to Site: 15-Apr-09 Erection Start: 16-Apr-09 SECTION 3 Fab'n: 23-Mar-09 Deliver to Site: 17-Apr-09 Erection Start: 19-Apr-09 Weld Splice: 20-Apr-09 SECTION 6 Fab'n: 24-Mar-09 Deliver to Site: 21-Apr-09 Erection Start: 25-Apr-09 Weld Splice: 26-Apr-09 SECTION 8 Fab'n: 25-Mar-09 Deliver to Site: 23-Apr-09 Erection Start: 29-Apr-09 Weld Splice: 30-Apr-09 SECTION 10 Fab'n: 26-Mar-09 Deliver to Site: 24-Apr-09 Erection Start: 03-May-09 Weld Splice: 04-May-09 SECTION 11 Fab'n: 27-Mar-09 Deliver to Site: 24-Apr-09 Erection Starts: 05-May-09 Weld Splice: 06-May-09 Line& Level: 07-May-09 Inspection: 08-May-09 SECTION 9 Fab'n: 26-Mar-09 Deliver to Site: 23-Apr-09 Erection Start: 01-May-09 Weld Splice: 02-May-09 SECTION 7 Fab'n: 25-Mar-09 Deliver to Site: 22-Apr-09 Erection Start: 27-Apr-09 Weld splice: 28-Apr-09 SECTION 5 Fab'n: 24-Mar-09 Deliver to Site: 20-Apr-09 Erection Start: 23-Apr-09 Weld Splice: 24-April-09 SECTION 4 Fab'n: 23-Mar-09 Deliver to Site: 19-Apr-09 Erection Start: 21-Apr-09 Weld Splice: 22-Apr-09 SECTION 2 Fab'n: 22-Mar-09 Deliver to Site: 15-Apr-09 Erection Start: 17-Apr-09 Weld Splice: 18-Apr-09