Oxxxx CONTRACTING CO. L.L.C.
NO LABOUR UNIT QUANTITY WORK GROUP
1 RAFT FOUNDATIONS FORM WORK M3 3.50 STRUCTURAL
2 WALLS / COLUMNS FORM WORK M3 1.00 STRUCTURAL
3 SLABS FORM WORK M3 1.75 STRUCTURAL
4 FOUNDATIONS STEEL FIX KG. 250.00 STRUCTURAL
5 WALLS / COLUMNS STEEL FIX KG. 150.00 STRUCTURAL
6 SLABS STEEL FIX KG. 200.00 STRUCTURAL
7 FOUNDATIONS POURING (READYMIX) M3 8.00 STRUCTURAL
8 WALLS / COLUMNS POURING (READYMIX) M3 6.00 STRUCTURAL
9 SLABS POURING (READYMIX) M3 6.00 STRUCTURAL
10 FOUNDATIONS INSULATION M2 25.00 STRUCTURAL
11 MEMBRANE TOILET M2 20.00 WET TRADES
12 MEMBRANE CEILING M2 50.00 WET TRADES
13 ROOFING SYSTEM M2 10.00 WET TRADES
14 WATERPROOFING FOR POOLS M2 20.00 WET TRADES
15 ELEVATION INSULATION M2 20.00 WET TRADES
16 FOAM CONCRETE M2 50.00 WET TRADES
17 COMPACTION M2 250.00 CIVIL
18 SAND FILL M3 5.00 CIVIL
19 INTERNAL BLOCK WALLS M2 25.00 WET TRADES
20 EXTERNAL BLOCK WORKS M2 20.00 WET TRADES
21 INTERNAL WALLS PLASTERING M2 25.00 WET TRADES
22 INTERNAL CEILING PLASTERING M2 20.00 WET TRADES
23 EXTERNAL WALLS PLASTERING M2 20.00 WET TRADES
24 SCREED M2 40.00 WET TRADES
25 FLOOR EPOXY M2 15.00 WET TRADES
26 FLOOR CERAMIC M2 20.00 WET TRADES
27 WALL CERAMIC M2 15.00 WET TRADES
28 CERAMIC SKIRTING L.M 50.00 WET TRADES
PRODUCTION RATES (IN MANDAYS PER UNIT):
Oxxxx CONTRACTING CO. L.L.C.
NO LABOUR UNIT QUANTITY WORK GROUP
PRODUCTION RATES (IN MANDAYS PER UNIT):
29 MARBLE TILES M2 20.00 WET TRADES
30 MARBLE SKIRTING L.M 60.00 WET TRADES
31 MARBLE SILLS L.M 15.00 WET TRADES
32 COUNTER TOPS NO 2.00 WET TRADES
33 THRESHOLD L.M 15.00 WET TRADES
34 TIMBER FLOORING M2 10.00 INT. FINISHING
35 STONE FLOORING M2 10.00 WET TRADES
36 ELEVATION STONE M2 6.00 WET TRADES
37 GRC SILL L.M 15.00 EXT. FINISHING
38 CLAY TILES M2 10.00 EXT. FINISHING
39 INTERLOCK M2 30.00 EXT. FINISHING
40 CURBSTONE L.M 10.00 EXT. FINISHING
41 FALSE CEILING SUSPENSION M2 15.00 INT. FINISHING
42 FALSE CEILING FINAL FIX M2 35.00 INT. FINISHING
43 CARPENTER (DOORS / WINDOWS) NO 3.00 DOORS & WINDOWS
44 LOCKER / WARDROBES NO 3.00 DOORS & WINDOWS
45 ALUMINUM (DOORS / WINDOWS) NO 3.00 DOORS & WINDOWS
46 HANDRAILS L.M 10.00 METALS
47 PRIMER / STUCCO / 1ST COAT PAINT M2 25.00 NT./EXT. FINISHING
48 FINAL COAT PAINT M2 25.00 NT./EXT. FINISHING
49 COATING FOR CAR PARKING WALLS / CEILING M2 50.00 NT./EXT. FINISHING
50 RUSH COAT M2 40.00 NT./EXT. FINISHING
Prepared by :
Allan. C. Leyte
Planning Engineer

More Related Content

Viewers also liked

Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and materialALI HYDER GADHI
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsHamdija Velagic
 
Building construction ppt
Building construction pptBuilding construction ppt
Building construction pptgyan singh
 
Building Construction 1: project 1
Building Construction 1: project 1Building Construction 1: project 1
Building Construction 1: project 1Nabeel Joomun
 
Project Management Plan Template
Project Management Plan TemplateProject Management Plan Template
Project Management Plan TemplateSimplilearn
 
Cafe construction project report
Cafe construction project reportCafe construction project report
Cafe construction project reportHagi Sahib
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction Mereia Kali
 
Building construction-report (1)
Building construction-report (1)Building construction-report (1)
Building construction-report (1)Soh Shing
 
Building Construction
Building ConstructionBuilding Construction
Building ConstructionWilden How
 
Sample project plan
Sample project planSample project plan
Sample project planmamoonnift
 
project on construction of house report.
project on construction of house report.project on construction of house report.
project on construction of house report.Hagi Sahib
 

Viewers also liked (12)

Analysis of rates for labour and material
Analysis of rates for labour and materialAnalysis of rates for labour and material
Analysis of rates for labour and material
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldings
 
Building construction ppt
Building construction pptBuilding construction ppt
Building construction ppt
 
Building Construction 1: project 1
Building Construction 1: project 1Building Construction 1: project 1
Building Construction 1: project 1
 
Project Management Plan Template
Project Management Plan TemplateProject Management Plan Template
Project Management Plan Template
 
Cafe construction project report
Cafe construction project reportCafe construction project report
Cafe construction project report
 
Stages in Construction
Stages in Construction Stages in Construction
Stages in Construction
 
Building construction-report (1)
Building construction-report (1)Building construction-report (1)
Building construction-report (1)
 
Building services
Building servicesBuilding services
Building services
 
Building Construction
Building ConstructionBuilding Construction
Building Construction
 
Sample project plan
Sample project planSample project plan
Sample project plan
 
project on construction of house report.
project on construction of house report.project on construction of house report.
project on construction of house report.
 

More from Allan Leyte

Construction Methodology Scheduling1
Construction Methodology Scheduling1Construction Methodology Scheduling1
Construction Methodology Scheduling1Allan Leyte
 
Sample MSProject with 16 DivisionFormat Variation(EOT)
Sample MSProject with 16 DivisionFormat Variation(EOT)Sample MSProject with 16 DivisionFormat Variation(EOT)
Sample MSProject with 16 DivisionFormat Variation(EOT)Allan Leyte
 
BHP01-0 Bouly baseline on MSproject Format
BHP01-0 Bouly baseline on MSproject FormatBHP01-0 Bouly baseline on MSproject Format
BHP01-0 Bouly baseline on MSproject FormatAllan Leyte
 
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)Allan Leyte
 
Sample of Structural Steel Scheduling
Sample of Structural Steel SchedulingSample of Structural Steel Scheduling
Sample of Structural Steel SchedulingAllan Leyte
 
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)Allan Leyte
 
Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Allan Leyte
 
Booster Pump cause of delay analysis
Booster Pump cause of delay analysisBooster Pump cause of delay analysis
Booster Pump cause of delay analysisAllan Leyte
 
Sample Bidcom Presentation - Structural Works 12-28-11
Sample Bidcom Presentation - Structural Works 12-28-11Sample Bidcom Presentation - Structural Works 12-28-11
Sample Bidcom Presentation - Structural Works 12-28-11Allan Leyte
 
Scheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPMScheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPMAllan Leyte
 
Offshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocolOffshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocolAllan Leyte
 
Town Center presentation
Town Center presentationTown Center presentation
Town Center presentationAllan Leyte
 

More from Allan Leyte (16)

Construction Methodology Scheduling1
Construction Methodology Scheduling1Construction Methodology Scheduling1
Construction Methodology Scheduling1
 
Sample MSProject with 16 DivisionFormat Variation(EOT)
Sample MSProject with 16 DivisionFormat Variation(EOT)Sample MSProject with 16 DivisionFormat Variation(EOT)
Sample MSProject with 16 DivisionFormat Variation(EOT)
 
BHP01-0 Bouly baseline on MSproject Format
BHP01-0 Bouly baseline on MSproject FormatBHP01-0 Bouly baseline on MSproject Format
BHP01-0 Bouly baseline on MSproject Format
 
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
 
WEIGHTING TABLE
WEIGHTING TABLEWEIGHTING TABLE
WEIGHTING TABLE
 
Sample of Structural Steel Scheduling
Sample of Structural Steel SchedulingSample of Structural Steel Scheduling
Sample of Structural Steel Scheduling
 
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
Non Software Scheduling (Weekly Planned Concrete Pour Vs Actual Poured)
 
p3 s-curves
p3 s-curvesp3 s-curves
p3 s-curves
 
Wreport
WreportWreport
Wreport
 
Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016
 
Booster Pump cause of delay analysis
Booster Pump cause of delay analysisBooster Pump cause of delay analysis
Booster Pump cause of delay analysis
 
Sample Bidcom Presentation - Structural Works 12-28-11
Sample Bidcom Presentation - Structural Works 12-28-11Sample Bidcom Presentation - Structural Works 12-28-11
Sample Bidcom Presentation - Structural Works 12-28-11
 
Scheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPMScheduling SLEX (FS)-InitialCPM
Scheduling SLEX (FS)-InitialCPM
 
Offshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocolOffshore Programme using QP-P3 protocol
Offshore Programme using QP-P3 protocol
 
progress photos
progress photosprogress photos
progress photos
 
Town Center presentation
Town Center presentationTown Center presentation
Town Center presentation
 

PRODUCTION RATE APPX. NEW

  • 1. Oxxxx CONTRACTING CO. L.L.C. NO LABOUR UNIT QUANTITY WORK GROUP 1 RAFT FOUNDATIONS FORM WORK M3 3.50 STRUCTURAL 2 WALLS / COLUMNS FORM WORK M3 1.00 STRUCTURAL 3 SLABS FORM WORK M3 1.75 STRUCTURAL 4 FOUNDATIONS STEEL FIX KG. 250.00 STRUCTURAL 5 WALLS / COLUMNS STEEL FIX KG. 150.00 STRUCTURAL 6 SLABS STEEL FIX KG. 200.00 STRUCTURAL 7 FOUNDATIONS POURING (READYMIX) M3 8.00 STRUCTURAL 8 WALLS / COLUMNS POURING (READYMIX) M3 6.00 STRUCTURAL 9 SLABS POURING (READYMIX) M3 6.00 STRUCTURAL 10 FOUNDATIONS INSULATION M2 25.00 STRUCTURAL 11 MEMBRANE TOILET M2 20.00 WET TRADES 12 MEMBRANE CEILING M2 50.00 WET TRADES 13 ROOFING SYSTEM M2 10.00 WET TRADES 14 WATERPROOFING FOR POOLS M2 20.00 WET TRADES 15 ELEVATION INSULATION M2 20.00 WET TRADES 16 FOAM CONCRETE M2 50.00 WET TRADES 17 COMPACTION M2 250.00 CIVIL 18 SAND FILL M3 5.00 CIVIL 19 INTERNAL BLOCK WALLS M2 25.00 WET TRADES 20 EXTERNAL BLOCK WORKS M2 20.00 WET TRADES 21 INTERNAL WALLS PLASTERING M2 25.00 WET TRADES 22 INTERNAL CEILING PLASTERING M2 20.00 WET TRADES 23 EXTERNAL WALLS PLASTERING M2 20.00 WET TRADES 24 SCREED M2 40.00 WET TRADES 25 FLOOR EPOXY M2 15.00 WET TRADES 26 FLOOR CERAMIC M2 20.00 WET TRADES 27 WALL CERAMIC M2 15.00 WET TRADES 28 CERAMIC SKIRTING L.M 50.00 WET TRADES PRODUCTION RATES (IN MANDAYS PER UNIT):
  • 2. Oxxxx CONTRACTING CO. L.L.C. NO LABOUR UNIT QUANTITY WORK GROUP PRODUCTION RATES (IN MANDAYS PER UNIT): 29 MARBLE TILES M2 20.00 WET TRADES 30 MARBLE SKIRTING L.M 60.00 WET TRADES 31 MARBLE SILLS L.M 15.00 WET TRADES 32 COUNTER TOPS NO 2.00 WET TRADES 33 THRESHOLD L.M 15.00 WET TRADES 34 TIMBER FLOORING M2 10.00 INT. FINISHING 35 STONE FLOORING M2 10.00 WET TRADES 36 ELEVATION STONE M2 6.00 WET TRADES 37 GRC SILL L.M 15.00 EXT. FINISHING 38 CLAY TILES M2 10.00 EXT. FINISHING 39 INTERLOCK M2 30.00 EXT. FINISHING 40 CURBSTONE L.M 10.00 EXT. FINISHING 41 FALSE CEILING SUSPENSION M2 15.00 INT. FINISHING 42 FALSE CEILING FINAL FIX M2 35.00 INT. FINISHING 43 CARPENTER (DOORS / WINDOWS) NO 3.00 DOORS & WINDOWS 44 LOCKER / WARDROBES NO 3.00 DOORS & WINDOWS 45 ALUMINUM (DOORS / WINDOWS) NO 3.00 DOORS & WINDOWS 46 HANDRAILS L.M 10.00 METALS 47 PRIMER / STUCCO / 1ST COAT PAINT M2 25.00 NT./EXT. FINISHING 48 FINAL COAT PAINT M2 25.00 NT./EXT. FINISHING 49 COATING FOR CAR PARKING WALLS / CEILING M2 50.00 NT./EXT. FINISHING 50 RUSH COAT M2 40.00 NT./EXT. FINISHING Prepared by : Allan. C. Leyte Planning Engineer