ID Northwestern Memorial Hospital - Chicago, IL Duration Start Finish Resource Names Predecessors
0 Northwestern Memorial Hospital - AU and Automation Systems Upgrade - Chemistry 359 days Mon 04/04/11 Fri 08/17/12
1
2 Pre-Installation Activities 219 days Mon 04/04/11 Fri 02/03/12
40
41 Phase One: Command Central Workstation 47 days Mon 02/06/12 Tue 04/10/12
51
52 Phase Two: Olson Lab (Temp Location) Testing and Validation 92 days Mon 01/23/12 Tue 05/29/12
68
82
83 Phase Three: Analyzer Mods, Delivery of New Automation, Movement Prep 26 days Thu 04/26/12 Thu 05/31/12
95
96 Phase Four: System Movement and relocations to Main Lab 38 days Mon 05/07/12 Wed 06/27/12
97 Automation Line in Main Lab Shutdown 9 days Mon 05/07/12 Thu 05/17/12
105 Online DxC#1 and DxC #2 1 day Tue 05/08/12 Tue 05/08/12
107 Online DxI #1 and DxI #2 1 day Wed 05/09/12 Wed 05/09/12
110 Flooring 3 days Fri 05/11/12 Tue 05/15/12
112 ----------AU Systems ------------------------------------- 21 days Tue 05/29/12 Tue 06/26/12
113 AU5800 9 days Tue 05/29/12 Fri 06/08/12
114 Install Main Lab water Systems 1 day Tue 05/29/12 Tue 05/29/12 Siemens Water
115 Set final spot for AU5800 Connection Unit. 0.5 days Wed 05/30/12 Wed 05/30/12 Larry Dark,Rolando
116 Relocate AU5800 from Olson to Main Lab, install Connection Kit, and test 2 days Wed 05/30/12 Thu 05/31/12 Rolando Alejandre
117 Complete Remisol Validations using Test Remisol 7 days Thu 05/31/12 Fri 06/08/12 Al Nice,Karen Zmuda
118 AU680 #2 8 days Wed 05/30/12 Fri 06/08/12
119 Relocate from Olson to Main Lab, install, test. Rack Feeder to be utilized 1 day Wed 05/30/12 Wed 05/30/12 Rolando Alejandre + Greg Boots
120 Complete Remisol Validations using Test Remisol 7 days Thu 05/31/12 Fri 06/08/12 Rolando Alejandre + Applications
121 Dictionary movement to Live Remisol (after signoff) 1 day Tue 06/12/12 Tue 06/12/12 Local Applications
122 Medical Director review and signoff 3 days Fri 06/08/12 Tue 06/12/12 Karen Zmuda,Al Nice
123 GoLive of AU5800 and AU680 #2 in Main Lab with modified Remisol dictionary 1 day Tue 06/26/12 Tue 06/26/12 Jean Coatar + Rolando + Christine
124 DxC #3 1 day Wed 06/27/12 Wed 06/27/12 123
125 Shutdown and remove from main lab (store in Olson) 1 day Wed 06/27/12 Wed 06/27/12 Local Service
126 AU680 #1 1 day Wed 06/27/12 Wed 06/27/12 123
127 Relocate from Olson to Main Lab, install, test. Rack Feeder to be utilized 1 day Wed 06/27/12 Wed 06/27/12 Rolando Alejandre
128 PROService install and test 1 day Wed 06/27/12 Wed 06/27/12 Rolando Alejandre
129 Command Central KVM install and test 1 day Wed 06/27/12 Wed 06/27/12 Rolando Alejandre
130 Connect to Live Remisol 1 day Wed 06/27/12 Wed 06/27/12 Rolando Alejandre
131 GoLive of AU680 #1 in Main Lab 1 day Wed 06/27/12 Wed 06/27/12 Jean Coatar + Rolando + Christine
132 All AU systems and both DxIs now LIVE as Standalone systems 0 days Wed 06/27/12 Wed 06/27/12 Jean Coatar + Rolando + Christine
133 Offline DxC #4 1 day Wed 06/27/12 Wed 06/27/12 132
134 Shutdown and Prep for shipment (store in Olson temporarily) 1 day Wed 06/27/12 Wed 06/27/12 Rolando + Stacey Ojeda
135 DxC #1 and DxC #2 (running in corner) 1 day Wed 06/27/12 Wed 06/27/12 132
136 Shutdown and Prep for shipment (store in Olson temporarily) 1 day Wed 06/27/12 Wed 06/27/12 Stacey Ojeda
137
138 Phase Five: Automation Line System Upgrade 59 days Tue 05/15/12 Fri 08/03/12
139 Flooring 11 days Tue 05/15/12 Tue 05/29/12
140 Floor cleanup and patchwork 10 days Tue 05/15/12 Mon 05/28/12 Joe Sivulka + NMH
141 Taping of floors for new line 1 day Tue 05/29/12 Tue 05/29/12 Larry Dark,Buck Kaster,Little Chris
142 Installation of new Automation Line 33 days Wed 05/30/12 Fri 07/13/12
143 Deliver new Automation system from Galter 16 to main lab (laborers) 1 day Wed 05/30/12 Wed 05/30/12 Larry Dark + 1 Engineer,Laborers
144 Assemble new system 12.33 days Wed 05/30/12 Fri 06/15/12
145 Track pieces 0.67 days Wed 05/30/12 Wed 05/30/12 Larry Dark,Buck Kaster,Little Chris
20
Normal
Milestone
Summary
Entire Task
Project Summary
Preliminary Timetable for Upgrade
Bin Kallan, SE Area Project Manager
Project: Northwestern Memorial Hospit
Date: Fri 06/15/12
ID Northwestern Memorial Hospital - Chicago, IL Duration Start Finish Resource Names Predecessors
146 Wiring 2.67 days Mon 06/04/12 Wed 06/06/12 Larry Dark,Buck Kaster,Little Chris
147 Power Test 0.33 days Fri 06/15/12 Fri 06/15/12 Larry Dark,Buck Kaster,Little Chris
148 Permanent positioning of Poles (remove temporary drops) 10 days Mon 06/04/12 Fri 06/15/12 Electricians
149 Data 20 days Mon 06/18/12 Fri 07/13/12 Rick Skovira,Lori Lapolice
150 Breakin testing 15 days Mon 06/25/12 Fri 07/13/12 Rick Skovira,Lori Lapolice
151 Connect Instruments to Automation Line 13 days Thu 06/28/12 Mon 07/16/12
152 DxI800 (x2) 1.5 days Thu 06/28/12 Fri 06/29/12 Larry Dark,Local Service
153 AU680 (x2) - remove rack feeders 1 day Mon 07/02/12 Mon 07/02/12 Larry Dark,Rolando A.
154 AU5800 (connect to Line) 1.5 days Thu 07/05/12 Fri 07/06/12 Larry Dark,Rolando A.
155 Command Central Installation on Analyzers 5 days Tue 07/10/12 Mon 07/16/12 local service with Remisol Apps
156 Hardware Verification and Validation testing of full system 32 days Thu 06/21/12 Fri 08/03/12
157 Applications setup of Preplink 5.0 to analyzers 5 days Mon 06/25/12 Fri 06/29/12 Larry Dark + 1,Rick Skovira,Lori Lapolice
158 PROService connections to All Analyzers 1 day Thu 06/21/12 Thu 06/21/12 Local Service
159 Hardware Testing with full route testing to all analyzers 10 days Mon 07/09/12 Fri 07/20/12 Larry Dark + 1,Rick Skovira,Lori Lapolice
160 Hardware Testing of AU5800 connection unit and full validation 10 days Mon 07/09/12 Fri 07/20/12 Larry Dark + 1,Rick Skovira,Lori Lapolice
161 Hardware Testing of both 5K stockyards with 11,000 samples to fill both Stockyards 5 days Mon 07/09/12 Fri 07/13/12 Larry Dark + 1,Rick Skovira,Lori Lapolice
162 Remisol and Preplink Validations 10 days Mon 07/09/12 Fri 07/20/12 Christine Newton,Roy,Rick S.
163 Regulatory Paperwork review and signoff (AU5800, AU5800 conn, 5Ks) 1 day Fri 07/20/12 Fri 07/20/12 Carol Otto,Bin Kallan
164 LIS Testing and hardware testing through instruments 20 days Mon 07/09/12 Fri 08/03/12 Rick Skovira and Lori Lapolice
165
166 Phase Six: Customer Training and GoLive 11 days Mon 07/23/12 Mon 08/06/12
167 Automation Training 11 days Mon 07/23/12 Mon 08/06/12
168 Dynamic Inlet Training 5 days Mon 07/23/12 Fri 07/27/12 Rick Skovira and Lori Lapolice
169 Preplink version 5.0 software review 4 days Mon 07/23/12 Thu 07/26/12 Rick Skovira and Lori Lapolice
170 Full Automation Training with Staff 10 days Tue 07/24/12 Mon 08/06/12 Rick Skovira and Lori Lapolice
171 AU5800 Connection 10 days Tue 07/24/12 Mon 08/06/12 Rick Skovira and Lori Lapolice
172 AU680 Connections 10 days Tue 07/24/12 Mon 08/06/12 Rick Skovira and Lori Lapolice
173 5K Stockyard Training 10 days Tue 07/24/12 Mon 08/06/12 Rick Skovira and Lori Lapolice
174
175 Phase Seven: GoLive of Automation Line with new components 10 days Mon 08/06/12 Fri 08/17/12
176 GoLive of new Automation Line and return to full production with connected Analyzers 1 day Tue 08/07/12 Tue 08/07/12 Rick Skovira and Lori Lapolice
177 Post GoLive support 10 days Mon 08/06/12 Fri 08/17/12 Lori Lapolice
178
179 Phase Eight: Documentation and Signoff 1 day Tue 08/14/12 Tue 08/14/12
180 Regulatory Signoffs 1 day Tue 08/14/12 Tue 08/14/12 Carol Otto,Bin Kallan
181 Project Closeout 1 day Tue 08/14/12 Tue 08/14/12 Bin Kallan,Carol Otto
20
Normal
Milestone
Summary
Entire Task
Project Summary
Preliminary Timetable for Upgrade
Bin Kallan, SE Area Project Manager
Project: Northwestern Memorial Hospit
Date: Fri 06/15/12

More Related Content

Similar to Northwestern AU+Automation Timeline REV6 6-15-12

Proposed Implementation Schedule for Chint.pdf
Proposed Implementation Schedule for Chint.pdfProposed Implementation Schedule for Chint.pdf
Proposed Implementation Schedule for Chint.pdfMarkGeraldCuadra1
 
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)  WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015) Ali Yousef
 
Performance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisPerformance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisDeborah Obasogie
 
Fitzroy-Gladestone Pipeline EPC Project - Design Schedule
Fitzroy-Gladestone Pipeline EPC Project - Design ScheduleFitzroy-Gladestone Pipeline EPC Project - Design Schedule
Fitzroy-Gladestone Pipeline EPC Project - Design ScheduleGary Hayes
 
carta gantt projek nazeq.pdf
carta gantt projek nazeq.pdfcarta gantt projek nazeq.pdf
carta gantt projek nazeq.pdfnazeqhaikal666
 
Keith odom sample microsoft project template data center move
Keith odom sample microsoft project template data center moveKeith odom sample microsoft project template data center move
Keith odom sample microsoft project template data center moveT. Keith Odom
 

Similar to Northwestern AU+Automation Timeline REV6 6-15-12 (10)

program
programprogram
program
 
MS Projects - 10 MW Implementation Schedule
MS Projects - 10 MW Implementation ScheduleMS Projects - 10 MW Implementation Schedule
MS Projects - 10 MW Implementation Schedule
 
Proposed Implementation Schedule for Chint.pdf
Proposed Implementation Schedule for Chint.pdfProposed Implementation Schedule for Chint.pdf
Proposed Implementation Schedule for Chint.pdf
 
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)  WC-14-NXE-007-00-Sch Rev 0.0  (29 May,2015)
WC-14-NXE-007-00-Sch Rev 0.0 (29 May,2015)
 
Performance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisPerformance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value Analysis
 
Fitzroy-Gladestone Pipeline EPC Project - Design Schedule
Fitzroy-Gladestone Pipeline EPC Project - Design ScheduleFitzroy-Gladestone Pipeline EPC Project - Design Schedule
Fitzroy-Gladestone Pipeline EPC Project - Design Schedule
 
CPM
CPMCPM
CPM
 
Slide4 mp psht1of6
Slide4 mp psht1of6Slide4 mp psht1of6
Slide4 mp psht1of6
 
carta gantt projek nazeq.pdf
carta gantt projek nazeq.pdfcarta gantt projek nazeq.pdf
carta gantt projek nazeq.pdf
 
Keith odom sample microsoft project template data center move
Keith odom sample microsoft project template data center moveKeith odom sample microsoft project template data center move
Keith odom sample microsoft project template data center move
 

Northwestern AU+Automation Timeline REV6 6-15-12

  • 1. ID Northwestern Memorial Hospital - Chicago, IL Duration Start Finish Resource Names Predecessors 0 Northwestern Memorial Hospital - AU and Automation Systems Upgrade - Chemistry 359 days Mon 04/04/11 Fri 08/17/12 1 2 Pre-Installation Activities 219 days Mon 04/04/11 Fri 02/03/12 40 41 Phase One: Command Central Workstation 47 days Mon 02/06/12 Tue 04/10/12 51 52 Phase Two: Olson Lab (Temp Location) Testing and Validation 92 days Mon 01/23/12 Tue 05/29/12 68 82 83 Phase Three: Analyzer Mods, Delivery of New Automation, Movement Prep 26 days Thu 04/26/12 Thu 05/31/12 95 96 Phase Four: System Movement and relocations to Main Lab 38 days Mon 05/07/12 Wed 06/27/12 97 Automation Line in Main Lab Shutdown 9 days Mon 05/07/12 Thu 05/17/12 105 Online DxC#1 and DxC #2 1 day Tue 05/08/12 Tue 05/08/12 107 Online DxI #1 and DxI #2 1 day Wed 05/09/12 Wed 05/09/12 110 Flooring 3 days Fri 05/11/12 Tue 05/15/12 112 ----------AU Systems ------------------------------------- 21 days Tue 05/29/12 Tue 06/26/12 113 AU5800 9 days Tue 05/29/12 Fri 06/08/12 114 Install Main Lab water Systems 1 day Tue 05/29/12 Tue 05/29/12 Siemens Water 115 Set final spot for AU5800 Connection Unit. 0.5 days Wed 05/30/12 Wed 05/30/12 Larry Dark,Rolando 116 Relocate AU5800 from Olson to Main Lab, install Connection Kit, and test 2 days Wed 05/30/12 Thu 05/31/12 Rolando Alejandre 117 Complete Remisol Validations using Test Remisol 7 days Thu 05/31/12 Fri 06/08/12 Al Nice,Karen Zmuda 118 AU680 #2 8 days Wed 05/30/12 Fri 06/08/12 119 Relocate from Olson to Main Lab, install, test. Rack Feeder to be utilized 1 day Wed 05/30/12 Wed 05/30/12 Rolando Alejandre + Greg Boots 120 Complete Remisol Validations using Test Remisol 7 days Thu 05/31/12 Fri 06/08/12 Rolando Alejandre + Applications 121 Dictionary movement to Live Remisol (after signoff) 1 day Tue 06/12/12 Tue 06/12/12 Local Applications 122 Medical Director review and signoff 3 days Fri 06/08/12 Tue 06/12/12 Karen Zmuda,Al Nice 123 GoLive of AU5800 and AU680 #2 in Main Lab with modified Remisol dictionary 1 day Tue 06/26/12 Tue 06/26/12 Jean Coatar + Rolando + Christine 124 DxC #3 1 day Wed 06/27/12 Wed 06/27/12 123 125 Shutdown and remove from main lab (store in Olson) 1 day Wed 06/27/12 Wed 06/27/12 Local Service 126 AU680 #1 1 day Wed 06/27/12 Wed 06/27/12 123 127 Relocate from Olson to Main Lab, install, test. Rack Feeder to be utilized 1 day Wed 06/27/12 Wed 06/27/12 Rolando Alejandre 128 PROService install and test 1 day Wed 06/27/12 Wed 06/27/12 Rolando Alejandre 129 Command Central KVM install and test 1 day Wed 06/27/12 Wed 06/27/12 Rolando Alejandre 130 Connect to Live Remisol 1 day Wed 06/27/12 Wed 06/27/12 Rolando Alejandre 131 GoLive of AU680 #1 in Main Lab 1 day Wed 06/27/12 Wed 06/27/12 Jean Coatar + Rolando + Christine 132 All AU systems and both DxIs now LIVE as Standalone systems 0 days Wed 06/27/12 Wed 06/27/12 Jean Coatar + Rolando + Christine 133 Offline DxC #4 1 day Wed 06/27/12 Wed 06/27/12 132 134 Shutdown and Prep for shipment (store in Olson temporarily) 1 day Wed 06/27/12 Wed 06/27/12 Rolando + Stacey Ojeda 135 DxC #1 and DxC #2 (running in corner) 1 day Wed 06/27/12 Wed 06/27/12 132 136 Shutdown and Prep for shipment (store in Olson temporarily) 1 day Wed 06/27/12 Wed 06/27/12 Stacey Ojeda 137 138 Phase Five: Automation Line System Upgrade 59 days Tue 05/15/12 Fri 08/03/12 139 Flooring 11 days Tue 05/15/12 Tue 05/29/12 140 Floor cleanup and patchwork 10 days Tue 05/15/12 Mon 05/28/12 Joe Sivulka + NMH 141 Taping of floors for new line 1 day Tue 05/29/12 Tue 05/29/12 Larry Dark,Buck Kaster,Little Chris 142 Installation of new Automation Line 33 days Wed 05/30/12 Fri 07/13/12 143 Deliver new Automation system from Galter 16 to main lab (laborers) 1 day Wed 05/30/12 Wed 05/30/12 Larry Dark + 1 Engineer,Laborers 144 Assemble new system 12.33 days Wed 05/30/12 Fri 06/15/12 145 Track pieces 0.67 days Wed 05/30/12 Wed 05/30/12 Larry Dark,Buck Kaster,Little Chris 20 Normal Milestone Summary Entire Task Project Summary Preliminary Timetable for Upgrade Bin Kallan, SE Area Project Manager Project: Northwestern Memorial Hospit Date: Fri 06/15/12
  • 2. ID Northwestern Memorial Hospital - Chicago, IL Duration Start Finish Resource Names Predecessors 146 Wiring 2.67 days Mon 06/04/12 Wed 06/06/12 Larry Dark,Buck Kaster,Little Chris 147 Power Test 0.33 days Fri 06/15/12 Fri 06/15/12 Larry Dark,Buck Kaster,Little Chris 148 Permanent positioning of Poles (remove temporary drops) 10 days Mon 06/04/12 Fri 06/15/12 Electricians 149 Data 20 days Mon 06/18/12 Fri 07/13/12 Rick Skovira,Lori Lapolice 150 Breakin testing 15 days Mon 06/25/12 Fri 07/13/12 Rick Skovira,Lori Lapolice 151 Connect Instruments to Automation Line 13 days Thu 06/28/12 Mon 07/16/12 152 DxI800 (x2) 1.5 days Thu 06/28/12 Fri 06/29/12 Larry Dark,Local Service 153 AU680 (x2) - remove rack feeders 1 day Mon 07/02/12 Mon 07/02/12 Larry Dark,Rolando A. 154 AU5800 (connect to Line) 1.5 days Thu 07/05/12 Fri 07/06/12 Larry Dark,Rolando A. 155 Command Central Installation on Analyzers 5 days Tue 07/10/12 Mon 07/16/12 local service with Remisol Apps 156 Hardware Verification and Validation testing of full system 32 days Thu 06/21/12 Fri 08/03/12 157 Applications setup of Preplink 5.0 to analyzers 5 days Mon 06/25/12 Fri 06/29/12 Larry Dark + 1,Rick Skovira,Lori Lapolice 158 PROService connections to All Analyzers 1 day Thu 06/21/12 Thu 06/21/12 Local Service 159 Hardware Testing with full route testing to all analyzers 10 days Mon 07/09/12 Fri 07/20/12 Larry Dark + 1,Rick Skovira,Lori Lapolice 160 Hardware Testing of AU5800 connection unit and full validation 10 days Mon 07/09/12 Fri 07/20/12 Larry Dark + 1,Rick Skovira,Lori Lapolice 161 Hardware Testing of both 5K stockyards with 11,000 samples to fill both Stockyards 5 days Mon 07/09/12 Fri 07/13/12 Larry Dark + 1,Rick Skovira,Lori Lapolice 162 Remisol and Preplink Validations 10 days Mon 07/09/12 Fri 07/20/12 Christine Newton,Roy,Rick S. 163 Regulatory Paperwork review and signoff (AU5800, AU5800 conn, 5Ks) 1 day Fri 07/20/12 Fri 07/20/12 Carol Otto,Bin Kallan 164 LIS Testing and hardware testing through instruments 20 days Mon 07/09/12 Fri 08/03/12 Rick Skovira and Lori Lapolice 165 166 Phase Six: Customer Training and GoLive 11 days Mon 07/23/12 Mon 08/06/12 167 Automation Training 11 days Mon 07/23/12 Mon 08/06/12 168 Dynamic Inlet Training 5 days Mon 07/23/12 Fri 07/27/12 Rick Skovira and Lori Lapolice 169 Preplink version 5.0 software review 4 days Mon 07/23/12 Thu 07/26/12 Rick Skovira and Lori Lapolice 170 Full Automation Training with Staff 10 days Tue 07/24/12 Mon 08/06/12 Rick Skovira and Lori Lapolice 171 AU5800 Connection 10 days Tue 07/24/12 Mon 08/06/12 Rick Skovira and Lori Lapolice 172 AU680 Connections 10 days Tue 07/24/12 Mon 08/06/12 Rick Skovira and Lori Lapolice 173 5K Stockyard Training 10 days Tue 07/24/12 Mon 08/06/12 Rick Skovira and Lori Lapolice 174 175 Phase Seven: GoLive of Automation Line with new components 10 days Mon 08/06/12 Fri 08/17/12 176 GoLive of new Automation Line and return to full production with connected Analyzers 1 day Tue 08/07/12 Tue 08/07/12 Rick Skovira and Lori Lapolice 177 Post GoLive support 10 days Mon 08/06/12 Fri 08/17/12 Lori Lapolice 178 179 Phase Eight: Documentation and Signoff 1 day Tue 08/14/12 Tue 08/14/12 180 Regulatory Signoffs 1 day Tue 08/14/12 Tue 08/14/12 Carol Otto,Bin Kallan 181 Project Closeout 1 day Tue 08/14/12 Tue 08/14/12 Bin Kallan,Carol Otto 20 Normal Milestone Summary Entire Task Project Summary Preliminary Timetable for Upgrade Bin Kallan, SE Area Project Manager Project: Northwestern Memorial Hospit Date: Fri 06/15/12