MS Projects - 10 MW Implementation Schedule
Gensol Engineering Limited
Gensol Engineering Limited
•
Mar. 23, 2014
•
10 likes
•
9,155 views
Download Now
243
ID Task Name Duration Start Finish
1 Solar PV Project-10 MW 120 days Tue 4/1/14 Tue 7/29/14
2 Site mobilization 2 days Tue...ID Task Name Duration Start Finish
69 Installation and Termination of SCADA system 5 days Sat 7/19/14 Wed 7/23/14
70 Exter...
1 of 3
A detailed project execution schedule including major and minor milestones for a 10
MW Plant. The EPC has been spread over 4 months. In case of larger or smaller power
plants, the activities would remain same while the timeline would change
Read more
Technology
Recommended
Project master schedule daughter station cng mini plant
Project master schedule daughter station cng mini plant
PT. ANSI MEGA INSTRUMENINDO, Gunawan Widihardjo
Solar mango corporate presentation
Solar mango corporate presentation
Anjali Khandelwal
progress of work till date
progress of work till date
Mohsen Almashharawi
CV SAIF UR REHMAN
CV SAIF UR REHMAN
Saif kharal
2. C v surveyor( Mumtaz )
C v surveyor( Mumtaz )
Mumtaz Ahmad
Sample Project Works
Sample Project Works
Rahim Virani
Management Control System- Delhi Metro_10042016
Management Control System- Delhi Metro_10042016
Anil Kumar Gupta
MS project Sample gantt chart
MS project Sample gantt chart
Dhawal Thakkar PMP
Work breakdown structure & project life cycle
Work breakdown structure & project life cycle
Sayandeep Dasgupta
Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020
Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020
Gensol Engineering Limited
More Related Content
You Might Also Like
Related Books
Free with a 30 day trial from Scribd
See all
Related Audiobooks
Free with a 30 day trial from Scribd
See all
MS Projects - 10 MW Implementation Schedule
1. ID Task Name Duration Start Finish 1 Solar PV Project-10 MW 120 days Tue 4/1/14
Tue 7/29/14 2 Site mobilization 2 days Tue 4/1/14 Wed 4/2/14 3 Array Area and
General Works 110 days Sat 4/5/14 Wed 7/23/14 4 Civil Works 93 days Sat 4/5/14 Sun
7/6/14 5 Site Levelling and Grading 15 days Sat 4/5/14 Sat 4/19/14 6 Marking and
Construction of Boundary Wall 30 days Tue 4/15/14 Wed 5/14/14 7 Foundation and
Installation of Main Entry Gate 5 days Fri 4/18/14 Tue 4/22/14 8 Foundation and
Construction of Security Cabin 5 days Fri 4/18/14 Tue 4/22/14 9 Construction of
Internal Roads 5 days Tue 4/22/14 Sat 4/26/14 10 Foundation Marking for Structures
5 days Mon 4/21/14 Fri 4/25/14 11 Excavation for Structure Foundation 20 days Tue
4/22/14 Sun 5/11/14 12 Module Mounting Structure Casting 30 days Wed 4/23/14 Thu
5/22/14 13 String Monitoring Box Foundation 5 days Sat 5/3/14 Wed 5/7/14 14 Cable
trench 7 days Fri 5/23/14 Thu 5/29/14 15 Construction of Water Collection Tank 10
days Fri 5/23/14 Sun 6/1/14 16 Construction of Drainage system 30 days Tue 5/27/14
Wed 6/25/14 17 Borewell works 3 days Fri 5/23/14 Sun 5/25/14 18 Lightening Arrester
Foundation 5 days Sun 6/22/14 Thu 6/26/14 19 External Lighting Foundation 15 days
Sun 6/22/14 Sun 7/6/14 20 CCTV Camera Foundation 5 days Sun 6/22/14 Thu 6/26/14 21
Earth Pit Works 5 days Thu 6/12/14 Mon 6/16/14 22 Electrical Works 97 days Thu
4/17/14 Wed 7/23/14 23 Structure 57 days Thu 4/17/14 Fri 6/13/14 24 Purchase Order
for Structure 0 days Thu 4/17/14 Thu 4/17/14 25 Payment for Structure 0 days Thu
4/24/14 Thu 4/24/14 26 Receiving of Structure 25 days Fri 4/25/14 Mon 5/19/14 27
Installation of Structure 15 days Fri 5/30/14 Fri 6/13/14 28 PV Module 52 days Fri
4/25/14 Sun 6/15/14 29 Purchase Order for PV Module 0 days Fri 4/25/14 Fri 4/25/14
30 Payment for PV Module 7 days Fri 4/25/14 Fri 5/2/14 31 Receiving of PV Module 30
3. days Fri 5/2/14 Sun 6/1/14 32 Installation of PV Module 15 days Sun 6/1/14 Sun
6/15/14 33 String Monitoring Box 41 days Mon 4/21/14 Sat 5/31/14 34 Purchase Order
for SMB 0 days Mon 4/21/14 Mon 4/21/14 35 Payment for SMB 7 days Mon 4/21/14 Mon
4/28/14 36 Receiving of String Monitoring Box 30 days Mon 4/28/14 Wed 5/28/14 37
Installation of String Monitoring Box 4 days Wed 5/28/14 Sat 5/31/14 38 Inverter 69
days Sat 4/19/14 Thu 6/26/14 39 Purchase Order for Inverter 0 days Sat 4/19/14 Sat
4/19/14 40 Payment for Inverter 7 days Sat 4/19/14 Sat 4/26/14 41 Receiving of
Inverter 60 days Sat 4/26/14 Wed 6/25/14 42 Installation of Inverter 2 days Wed
6/25/14 Thu 6/26/14 43 DC Cable 64 days Tue 4/29/14 Tue 7/1/14 44 Purchase Order
for DC Cable 0 days Tue 4/29/14 Tue 4/29/14 45 Payment for DC Cable 7 days Tue
4/29/14 Tue 5/6/14 46 Receiving of DC Cable 45 days Tue 5/6/14 Fri 6/20/14 47
Laying of DC Cable 7 days Fri 6/20/14 Fri 6/27/14 48 Termination of DC Cable 5 days
Fri 6/27/14 Tue 7/1/14 49 OFC 60 days Thu 5/1/14 Sun 6/29/14 50 Purchase Order for
OFC 0 days Thu 5/1/14 Thu 5/1/14 51 Payment for OFC 7 days Thu 5/1/14 Thu 5/8/14 52
Receiving of OFC 45 days Thu 5/8/14 Sun 6/22/14 53 Laying of OFC 5 days Sun 6/22/14
Fri 6/27/14 54 Termination of OFC 3 days Fri 6/27/14 Sun 6/29/14 55 CCTV SYSTEM 40
days Sat 5/31/14 Wed 7/9/14 56 Purchase Order for CCTV 0 days Sat 5/31/14 Sat
5/31/14 57 Payment for CCTV 7 days Sat 5/31/14 Sat 6/7/14 58 Receiving of CCTV 30
days Sat 6/7/14 Mon 7/7/14 59 Installation of CCTV 3 days Mon 7/7/14 Wed 7/9/14 60
Lightening Arrestor 41 days Sat 5/31/14 Thu 7/10/14 61 Purchase order for
Lightening Arrestor 0 days Sat 5/31/14 Sat 5/31/14 62 Payment for Lightening
Arrestor 7 days Sat 5/31/14 Sat 6/7/14 63 Receiving of Lightening Arrestor 30 days
Sat 6/7/14 Mon 7/7/14 64 Installation of Lightening Arrestor 4 days Mon 7/7/14 Thu
7/10/14 65 SCADA System 72 days Tue 5/13/14 Wed 7/23/14 66 Purchase Order for SCADA
System 0 days Tue 5/13/14 Tue 5/13/14 67 Payment for SCADA System 7 days Tue
5/13/14 Tue 5/20/14 68 Receiving of SCADA 60 days Tue 5/20/14 Sat 7/19/14 /1 4/2
4/5 4/19 4/15 5/14 4/18 4/22 4/18 4/22 4/22 4/26 4/21 4/25 4/22 5/11 4/23 5/22 5/3
5/7 5/23 5/29 5/23 6/1 5/27 6/25 5/23 5/25 6/22 6/26 6/22 7/6 6/22 6/26 6/12 6/16
4/17 4/24 4/25 5/19 5/30 6/13 4/25 4/25 5/2 5/2 6/1 6/1 6/15 4/21 4/21 4/28 4/28
5/28 5/28 5/31 4/19 4/19 4/26 4/26 6/25 6/25 6/26 4/29 4/29 5/6 5/6 6/20 6/20 6/27
6/27 7/1 5/1 5/1 5/8 5/8 6/22 6/22 6/27 6/27 6/29 5/31 5/31 6/7 6/7 7/7 7/7 7/9
5/31 5/31 6/7 6/7 7/7 7/7 7/10 5/13 5/13 5/20 5/20 7/19 30 2 5 8 11 14 17 20 23 26
29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28
April 2014 May 2014 June 2014 July 2014 Task Progress Milestone Summary Rolled Up
Task Rolled Up Milestone Rolled Up Progress Split External Tasks Project Summary
Group By Summary Deadline Page 1 Project: Template PIS Date: Wed 3/19/14
2. ID Task Name Duration Start Finish 69 Installation and Termination of SCADA
system 5 days Sat 7/19/14 Wed 7/23/14 70 External Lighting 57 days Wed 5/21/14 Wed
7/16/14 71 Purchase Order for Poles and Lights 0 days Wed 5/21/14 Wed 5/21/14 72
Payment for Lighting System 7 days Wed 5/21/14 Wed 5/28/14 73 Receiving of Lighting
System 40 days Wed 5/28/14 Mon 7/7/14 74 Installation and Termination of Lighting
System 10 days Mon 7/7/14 Wed 7/16/14 75 Array Earthing 57 days Sun 5/18/14 Sun
7/13/14 76 Purchase Order for Earthing Equipments 0 days Sun 5/18/14 Sun 5/18/14 77
Payment for Earthing Equipments 7 days Sun 5/18/14 Sun 5/25/14 78 Receiving of
Earthing Equipments 40 days Sun 5/25/14 Fri 7/4/14 79 Array Earthing Installation
and Connection 10 days Fri 7/4/14 Sun 7/13/14 80 Main Control Room & Substation 86
days Thu 4/24/14 Fri 7/18/14 81 Civil Work in MCR & Substation 60 days Sat 4/26/14
Tue 6/24/14 82 Marking 2 days Sat 4/26/14 Sun 4/27/14 83 Excavation 3 days Mon
4/28/14 Wed 4/30/14 84 RCC Foundation 20 days Thu 5/1/14 Tue 5/20/14 85 Brick work
15 days Wed 5/21/14 Wed 6/4/14 86 Internal Plaster 7 days Thu 6/5/14 Wed 6/11/14 87
4. Flooring & Trenching 7 days Thu 6/12/14 Wed 6/18/14 88 Windows & Doors Fixing 7
days Thu 6/12/14 Wed 6/18/14 89 Painting work 7 days Thu 6/12/14 Wed 6/18/14 90
Finishing work of Substation Building 10 days Sun 6/15/14 Tue 6/24/14 91 Power and
Aux. Transformer Foundation 15 days Tue 5/6/14 Tue 5/20/14 92 Switch Yard Earthing
Mat Construction 7 days Fri 5/16/14 Thu 5/22/14 93 Switch Yard Equipment Foundation
15 days Fri 5/23/14 Fri 6/6/14 94 Foundation for Transmission Towers 30 days Fri
5/23/14 Sat 6/21/14 95 Electrical Works 86 days Thu 4/24/14 Fri 7/18/14 96
Transformers(Power and Aux.) 72 days Thu 4/24/14 Fri 7/4/14 97 Purchase Order for
Transformer 0 days Thu 4/24/14 Thu 4/24/14 98 Payment for Transformer 7 days Thu
4/24/14 Thu 5/1/14 99 Receiving of Transformer 60 days Thu 5/1/14 Mon 6/30/14 100
Installation of Transformer 5 days Mon 6/30/14 Fri 7/4/14 101 33 kV bay station 73
days Tue 4/29/14 Thu 7/10/14 102 Purchase Order for
VCB,Conductors,Isolator,CT,PT,Structure2 days Tue 4/29/14 Thu 5/1/14 103 Payment
for VCB,Conductors,Isolator,CT,PT,Structure7 days Thu 5/1/14 Thu 5/8/14 104
Receiving of Equipments 50 days Thu 5/8/14 Fri 6/27/14 105 Installation of
Equipments 7 days Fri 6/27/14 Thu 7/3/14 106 Termination of Conductors 7 days Fri
7/4/14 Thu 7/10/14 107 HT Panels 61 days Fri 5/9/14 Tue 7/8/14 108 Purchase Order
for HT Panels 0 days Fri 5/9/14 Fri 5/9/14 109 Payment for HT Panels 7 days Fri
5/9/14 Fri 5/16/14 110 Receiving of HT Panels 50 days Fri 5/16/14 Sat 7/5/14 111
Installation of HT Panels 4 days Sat 7/5/14 Tue 7/8/14 112 LT Panels 61 days Fri
5/9/14 Tue 7/8/14 113 Purchase Order for LT Panels 0 days Fri 5/9/14 Fri 5/9/14 114
Payment for LT Panels 7 days Fri 5/9/14 Fri 5/16/14 115 Receiving of LT Panels 50
days Fri 5/16/14 Sat 7/5/14 116 Installation of LT Panels 4 days Sat 7/5/14 Tue
7/8/14 117 LT Cable 72 days Sat 5/3/14 Sun 7/13/14 118 Purchase Order for LT Cable
0 days Sat 5/3/14 Sat 5/3/14 119 Payment for LT Cable 7 days Sat 5/3/14 Sat 5/10/14
120 Receiving of LT Cable 50 days Sat 5/10/14 Sun 6/29/14 121 Laying of LT Cable 5
days Sun 6/29/14 Thu 7/3/14 122 Terination of LT Cable 5 days Wed 7/9/14 Sun
7/13/14 123 HT Cable & Conductors 70 days Mon 5/5/14 Sun 7/13/14 124 Purchase Order
for HT Cable 0 days Mon 5/5/14 Mon 5/5/14 125 Payment for HT Cable 7 days Mon
5/5/14 Mon 5/12/14 126 Receiving of HT Cables 50 days Mon 5/12/14 Tue 7/1/14 127
Laying of HT Cable 5 days Tue 7/1/14 Sat 7/5/14 128 Termination of HT Cable 5 days
Wed 7/9/14 Sun 7/13/14 129 Control Cable 63 days Sat 5/10/14 Fri 7/11/14 130
Purchase Order for Control Cable 0 days Sat 5/10/14 Sat 5/10/14 131 Payment for
Control Cable 7 days Sat 5/10/14 Sat 5/17/14 132 Receiving of Control Cables 45
days Sat 5/17/14 Tue 7/1/14 133 Laying of Control Cable 4 days Tue 7/1/14 Fri
7/4/14 134 Termination of Control Cable 3 days Wed 7/9/14 Fri 7/11/14 135
Lightening Protection System 32 days Wed 5/21/14 Sat 6/21/14 136 Purchase Order for
LA 0 days Wed 5/21/14 Wed 5/21/14 7/19 7/23 5/21 5/21 5/28 5/28 7/7 7/7 7/16 5/18
5/18 5/25 5/25 7/4 7/4 7/13 4/26 4/27 4/28 4/30 5/1 5/20 5/21 6/4 6/5 6/11 6/12
6/18 6/12 6/18 6/12 6/18 6/15 6/24 5/6 5/20 5/16 5/22 5/23 6/6 5/23 6/21 4/24 4/24
5/1 5/1 6/30 6/30 7/4 4/29 5/1 5/1 5/8 5/8 6/27 6/27 7/3 7/4 7/10 5/9 5/9 5/16 5/16
7/5 7/5 7/8 5/9 5/9 5/16 5/16 7/5 7/5 7/8 5/3 5/3 5/10 5/10 6/29 6/29 7/3 7/9 7/13
5/5 5/5 5/12 5/12 7/1 7/1 7/5 7/9 7/13 5/10 5/10 5/17 5/17 7/1 7/1 7/4 7/9 7/11
5/21 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 7 10 13 16 19 22
25 28 1 4 7 10 13 16 19 22 25 28 April 2014 May 2014 June 2014 July 2014 Task
Progress Milestone Summary Rolled Up Task Rolled Up Milestone Rolled Up Progress
Split External Tasks Project Summary Group By Summary Deadline Page 2 Project:
Template PIS Date: Wed 3/19/14
3. ID Task Name Duration Start Finish 137 Payment for LA 7 days Wed 5/21/14 Wed
5/28/14 138 Receiving of LA 20 days Wed 5/28/14 Tue 6/17/14 139 Installation of LA