Storm System GRP pipes Installation Backfilled Time Passed
1‐Jul‐15 1‐Aug‐15 Project Start Date 12‐Jun‐13
Total 
Length
Total
External
Box Culvert
Total
Internal
Previous 
Progress
This Month
Progress
This Month
Progress %
Total 
Progress
% Total Remaining Project Finish Date 11‐Jun‐15
Excavated 26288 4942 1884 21347 20227 244 1% 20471 78% 5817 # Total Duration 729
Installed 26288 4942 1884 21347 19483 300 1% 19783 75% 6505 # Progress Cut off Date 2‐Aug‐15
Tested 26288 4942 1884 21347 18379 131 0% 18510 70% 7778 # Project Delay 52
Backfilled 26288 4942 1884 21347 17905 86 0.3% 17991 68% 8297 # Elapsed Duration 781
Sewage System VC pipes Installation Backfilled Earth Work Progress
1‐Jul‐15 1‐Aug‐15
Total 
Length
Total
External
Total
Internal
Previous 
Progress
This Month
Progress
This Month
Progress %
Total 
Progress
% Total Remaining Total M3
2,840,687
Excavated 28034 1135 26899 24354 104 0% 24458 87% 3576 # Previous Progress 2,777,677
Installed 28034 1135 26899 23748 175 1% 23923 85% 4111 #
This  Month Compacted M3
8,522
Tested 28034 1135 26899 2300 21257 76% 23557 84% 4477 #
Total Compacted M3
2,786,199
Backfilled 28034 1135 26899 22968 286 1.0% 23254 83% 4780 #
Remaining M3
54,488
Potable System HDPE&DI pipes Installation Backfilled Manpower
1‐Jul‐15 1‐Aug‐15
Total 
Length
Total
External
Total
Internal
Previous 
Progress
This Month
Progress
This Month
Progress %
Total 
Progress
% Total Remaining
Excavated 42824 5940 36884 23929 940 2% 24869 58% 17955 #
Installed 42824 5940 36884 23117 440 1% 23557 55% 19267 #
Tested 42824 5940 36884 21805 0 0% 21805 51% 21019 #
Backfilled 42824 5940 36884 21422 125 0.3% 21547 50% 21277 #
Irrigation System HDPE pipes Installation Backfilled
1‐Jul‐15 1‐Aug‐15 Dewatering Pumps Status
Total 
Length
Total
External
Total
Internal
Previous 
Progress
This Month
Progress
This Month
Progress %
Total 
Progress
% Total Remaining
Excavated 35527 4751 30776 20203 1215 3% 21418 60% 14109 #
Installed 35527 4751 30776 19266 315 1% 19581 55% 15946 #
Tested 35527 4751 30776 17557 371 1% 17928 50% 17599 #
Backfilled 35527 4751 30776 17441 374 1.1% 17815 50% 17712 #
Storm MHs/CBs‐ Storm System Slab/Connected Backfilled Butt Fusion welding  Machine
1‐Jul‐15 1‐Aug‐15
Total 
No.
Total
External
Box Culvert
Total
Internal
Previous 
Progress
This Month
Progress
This Month
Progress %
Total 
Progress
% Total Remaining
Foundation 493 58 39 396 285 7 1% 292 59% 201 #
Walls/Placed 493 58 39 396 275 3 1% 278 56% 215 #
Slab/Connected 493 58 39 396 273 1 0% 274 56% 219 #
Insulation 493 58 39 396 233 6 1% 239 48% 254 #
Backfilled 493 58 39 396 217 6 1.2% 223 45% 270 #
Precast MHs‐ Sewage System Connection Backfilled
1‐Jul‐15 1‐Aug‐15 Electrical Fusion welding  Machine
Total 
No.
Total
External
Box Culvert
Total
Internal
Previous 
Progress
This Month
Progress
This Month
Progress %
Total 
Progress
% Total Remaining
Placed 469 15 454 347 8 2% 355 76% 114 #
Connected 469 15 454 332 9 2% 341 73% 128 #
Insulation 469 15 454 278 14 3% 292 62% 177 #
Backfilled 469 15 454 266 13 2.8% 279 59% 190 #
ROAD GULLIES            Connection           Backfilled
1‐Jul‐15 1‐Aug‐15
Total 
No.
Total
External
Box Culvert
Total
Internal
Previous 
Progress
This Month
Progress
This Month
Progress %
Total 
Progress
% Total Remaining
Placed 507 108 73 326 88 34 7% 122 37% 385 #
Connected 507 108 73 326 55 10 2% 65 20% 442 #
Backfilled 507 108 73 326 41 0 0.0% 41 13% 466 #
ELECTRICAL MV,LV STREET LIGHITNG INSTALL
1‐Jul‐15 1‐Aug‐15 MV  LV
Total Length
Total      
No
Previous 
Progress
This Month
Progress
This Month
Progress %
Total Progress % Total Remaining
MV CABLE  131689 33571 498 0.4% 34069 26% 97620 #
FOC Cable 131689 34304 705 1% 35009 27% 96680 #
LV Cable 70817 5134 6406 9.0% 11540 16% 59277 #
I.R Control Cable 47530 22318 540 1% 22858 48% 24672 #
St. Ligthing (LV Cable)  79000 3130 450 1% 3580 5% 75420 #
ST. Lighting Foundation 1500 59 0 0% 59 4% 1441 #
St. Lighting Poles 1500 0 0 0% 0 0% 1500 #
Telecom Network Telecom HDPE Conduit      Telecom Hand Holes
1‐Jul‐15 1‐Aug‐15
Total 
Length
Total No
Previous 
Progress
This Month
Progress
This Month
Progress %
Total 
Progress
% Total Remaining
Telecom HDPE Conduit 950000 238466 20688 2.2% 259154 27% 690846 #
Telecom SMALL M.H 42 8 0 0% 8 19% 34 #
TELECOM H.H 132 11 18 13.6% 29 22% 103 #
SUBSTATIONS/MINIPILLARS
2‐Jan‐15 1‐Aug‐15 Substation           RMU
Total 
No.
Previous 
Progress
This Month
Progress
This Month
Progress %
Total 
Progress
% Total Remaining
ROOM STRUCTURE 48 48 0 0% 48 100% 0 #
GATE/FENCE 48 6 0 0% 6 13% 42 #
SUBSTATIONS 48 48 0 0.0% 48 100% 0 #
RMU INSTALL 48 0 20 41.7% 20 42% 28 #
MINIPILLARS 322 0 21 7% 21 7% 301 #
ROADS NETWORK Asphalt         Curb Stone
1‐Jul‐15 1‐Aug‐15
Total 
M3
Total M2
Total 
Length
Total
Internal
Previous 
Progress
This Month
Progress
This Month
Progress %
Total 
Progress
% Total Remaining
SUBGRADE 254451 202361 25256 34549 14% 59805 24% 194646 #
SUBBASE 108708 84020 9624 5306 5% 14930 14% 93778 #
ASPHALT 562935 420102 24291 0 0.0% 24291 4% 538644 #
CURSTONE 109272 85791 5458 102 0.1% 5560 5% 103712 #
RHCP‐JEDDAH DASHBOARD PROGRESS AS OF 02‐Aug‐2015
17991
18510
19783
20471
26288
Backfilled
Tested
Installed
Excavated
Total…
23254
23557
23923
24458
28034
Backfilled
Tested
Installed
Excavated
Total…
21547
21805
23557
24869
36884
Backfilled
Tested
Installed
Excavated
Total…
17815
17928
19581
21418
30776
Backfilled
Tested
Installed
Excavated
Total…
98%
0% 2%
Previous Progress
This  Month Compacted M3
Remaining M3
71%
29%
NCRs OVER ALL Progress 
Closed
Open
18.21
13.55
8.45
4.07
5.79
2.55
3.75 4.23
3.11
7.22 7.31 7.70 7.58
6.00
9.67
12.40
4.69
5.49
10.72
15.24
0
2
4
6
8
10
12
14
16
18
20
Sep‐13
Oct‐13
Nov‐13
Dec‐13
Jan‐14
Feb‐14
Mar‐14
Apr‐14
May‐14
Jun‐14
Jul‐14
Aug‐14
Sep‐14
Oct‐14
Nov‐14
Dec‐14
Jan‐15
Feb‐15
Mar‐15
Apr‐15
May‐15
Jun‐15
Millions
Actual Paid Not Paid
74%
1%
25%
Previous
Progress
This Month
Progress
Remaining
85%
0%
15%
Previous
Progress
This Month
Progress
Remaining
54%
1%
45%
Previous
Progress
This Month
Progress
Remaining
54%
1%
45%
Previous
Progress
This Month
Progress
Remaining
55%
0%
45%
Previous
Progress
This Month
Progress
Remaining
71%
2%
27%
Previous
Progress
This Month
Progress
Remaining
279
292
341
355
469
Backfilled
Insulation
Connected
Placed
Total…
223
239
274
278
292
493
Backfilled
Insulation
Slab/Connected
Walls/Placed
Foundation
Total…
44
44
Jun‐15 Jul‐15
12 12 12
May‐15 Jun‐15 Jul‐15
12 12 12
May‐15 Jun‐15 Jul‐15
68%0%
32%
Previous
Progress
This Month
Progress
Remaining
82%
1%
17%
Previous
Progress
This Month
Progress
Remaining
50%
0%
50%
Previous
Progress
This Month
Progress
Remaining
49%
1%
50%
Previous
Progress
This Month
Progress
Remaining
44%
1%
55%
Previous
Progress
This Month
Progress
Remaining
57%
3%
40%
Previous
Progress
This Month
Progress
Remaining
52 
781 
729 
Project Delay
Elapsed Duration
Total Duration
41
65
122
507
Backfilled
Connected
Placed
Total
No.
11%
2%
87%
Previous
Progress
This Month
Progress
Remaining
8%
0%
92%
Previous
Progress
This Month
Progress
Remaining
34069
131689
35009
131689
11540
70817
22858
47530
3580
79000
Progress LM
MV Total Length
Progress LM
FOC Total Length
Progress LM
LV Total Length
Progress LM
I.R Control Cable…
Progress LM
St. Ligthing Total…
259154
950000
Telecom HDPE
Conduit
Total
Length
7%
9%
84%
Previous
Progress
This Month
Progress
Remaining
0%
26%
74%
Previous
Progress
This Month
Progress
Remaining
25%
2%
73%
Previous
Progress
This Month
Progress
Remaining
8%
14%
78%
Previous
Progress
This Month
Progress
Remaining
21
322
20
48
48
48
MINIPILLARS
Total…
RMU INSTALL
Total…
SUBSTATIONS
Total…
100%
0%
0%
Previous
Progress
This Month
Progress
Remaining
0%
42%
58%
Previous
Progress
This Month
Progress
Remaining
5560
109272
24291
562935
14930
108708
59805
254451
CURSTONE
ASPHALT
SUBBASE
SUBGRADE
4% 0%
96%
Previous
Progress
This Month
Progress
Remaining
5%0%
95%
Previous
Progress
This Month
Progress
Remaining
8
2
1
4
1 1
7
11
8
16
17
18 18
17
18
17
18
17
19
0
8
16
24
W102 W103 W104 W105 W106 W107 W108 W109 W110 W111 W112 W113 W114 W115 W116 W117 W118 W119 W120
Actual closed Plan to close
360
512
627 626 634
741
816
930
735
627 655 684 667
0
200
400
600
800
1000
Jul‐14 Aug‐14 Sep‐14 Oct‐14 Nov‐14 Dec‐14 Jan‐15 Feb‐15 Mar‐15 Apr‐15 May‐15 Jun‐15 Jul‐15
143
136
194
153
171
155
116
93
82
66
88
60
84
0
50
100
150
200
250
8‐May‐15 15‐May‐15 22‐May‐15 29‐May‐15 5‐Jun‐15 12‐Jun‐15 19‐Jun‐15 26‐Jun‐15 3‐Jul‐15 10‐Jul‐15 17‐Jul‐15 24‐Jul‐15 31‐Jul‐15
Inspection Requests Progress
30%
3%
67%
IPC Status
Previous
This
Period
Remaining
8/6/2015
Prepared By: Eng. Aamir  (Sr.Plannging Engineer)
E‐Mail: amir86_sohail@yahoo.com

More Related Content

Viewers also liked

Uv susie crawford-3
Uv   susie crawford-3Uv   susie crawford-3
Uv susie crawford-3room18merrin
 
Lei 2332.2015 com anexos
Lei 2332.2015 com anexosLei 2332.2015 com anexos
Lei 2332.2015 com anexosWagner Rocha
 
CIENCIAS DEL DEPORTE
CIENCIAS DEL DEPORTECIENCIAS DEL DEPORTE
CIENCIAS DEL DEPORTEnovaudca
 
Nota mucama-pachelo-5-6-03
Nota mucama-pachelo-5-6-03Nota mucama-pachelo-5-6-03
Nota mucama-pachelo-5-6-03Caso Belsunce
 
Slide share
Slide shareSlide share
Slide sharedk2200
 
Automation
AutomationAutomation
AutomationMphasis
 
Chabas
ChabasChabas
Chabaspaula
 
REQUERIMENTO VERBAL 037-2005 - OLIVANIO - Idoso
REQUERIMENTO VERBAL 037-2005 - OLIVANIO - IdosoREQUERIMENTO VERBAL 037-2005 - OLIVANIO - Idoso
REQUERIMENTO VERBAL 037-2005 - OLIVANIO - IdosoOlivânio Remígio
 
Shaun Stafford at The Leasing Foundation Third Annual Conference
Shaun Stafford at The Leasing Foundation Third Annual ConferenceShaun Stafford at The Leasing Foundation Third Annual Conference
Shaun Stafford at The Leasing Foundation Third Annual ConferenceThe Leasing Foundation
 
Prebenjamin a
Prebenjamin aPrebenjamin a
Prebenjamin afbcat
 
Talking SMAC !!! How Social, Mobile, Analytics & Cloud Reshaping Your Busines...
Talking SMAC !!! How Social, Mobile, Analytics & Cloud Reshaping Your Busines...Talking SMAC !!! How Social, Mobile, Analytics & Cloud Reshaping Your Busines...
Talking SMAC !!! How Social, Mobile, Analytics & Cloud Reshaping Your Busines...C.K. Kumar
 

Viewers also liked (14)

Uv susie crawford-3
Uv   susie crawford-3Uv   susie crawford-3
Uv susie crawford-3
 
Lei 2332.2015 com anexos
Lei 2332.2015 com anexosLei 2332.2015 com anexos
Lei 2332.2015 com anexos
 
CIENCIAS DEL DEPORTE
CIENCIAS DEL DEPORTECIENCIAS DEL DEPORTE
CIENCIAS DEL DEPORTE
 
Nota mucama-pachelo-5-6-03
Nota mucama-pachelo-5-6-03Nota mucama-pachelo-5-6-03
Nota mucama-pachelo-5-6-03
 
Slide share
Slide shareSlide share
Slide share
 
Automation
AutomationAutomation
Automation
 
Chabas
ChabasChabas
Chabas
 
REQUERIMENTO VERBAL 037-2005 - OLIVANIO - Idoso
REQUERIMENTO VERBAL 037-2005 - OLIVANIO - IdosoREQUERIMENTO VERBAL 037-2005 - OLIVANIO - Idoso
REQUERIMENTO VERBAL 037-2005 - OLIVANIO - Idoso
 
Contreras mayo-2003
Contreras mayo-2003Contreras mayo-2003
Contreras mayo-2003
 
Id card
Id cardId card
Id card
 
Shaun Stafford at The Leasing Foundation Third Annual Conference
Shaun Stafford at The Leasing Foundation Third Annual ConferenceShaun Stafford at The Leasing Foundation Third Annual Conference
Shaun Stafford at The Leasing Foundation Third Annual Conference
 
Prebenjamin a
Prebenjamin aPrebenjamin a
Prebenjamin a
 
Dip tema 1 saia
Dip tema 1 saiaDip tema 1 saia
Dip tema 1 saia
 
Talking SMAC !!! How Social, Mobile, Analytics & Cloud Reshaping Your Busines...
Talking SMAC !!! How Social, Mobile, Analytics & Cloud Reshaping Your Busines...Talking SMAC !!! How Social, Mobile, Analytics & Cloud Reshaping Your Busines...
Talking SMAC !!! How Social, Mobile, Analytics & Cloud Reshaping Your Busines...
 

Similar to Dashboard

Project Controls planning & Scheduling Engineer-Portfolio
Project Controls planning & Scheduling Engineer-PortfolioProject Controls planning & Scheduling Engineer-Portfolio
Project Controls planning & Scheduling Engineer-PortfolioSyed Arafath, PMI-SP certified
 
Single Family Gantt Chart-John Mueller
Single Family Gantt Chart-John MuellerSingle Family Gantt Chart-John Mueller
Single Family Gantt Chart-John MuellerJohn Mueller
 
Presentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxPresentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxFaisalGulzar19
 
Monthly report of maintenance by Swamina International Ltd.
Monthly report of maintenance by Swamina International Ltd.Monthly report of maintenance by Swamina International Ltd.
Monthly report of maintenance by Swamina International Ltd.TusarKole
 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptxTalebAlfihan
 
CPUC - Typhoon Maysak - Restoration Report To 20 June 2015
CPUC - Typhoon Maysak - Restoration Report To 20 June 2015CPUC - Typhoon Maysak - Restoration Report To 20 June 2015
CPUC - Typhoon Maysak - Restoration Report To 20 June 2015K-Andrea Evarose Limol
 
EMC e City - Rev meeting Aug 2018.ppt
EMC e City - Rev meeting Aug 2018.pptEMC e City - Rev meeting Aug 2018.ppt
EMC e City - Rev meeting Aug 2018.pptSrikanthTirluka1
 
VVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBG
VVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBGVVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBG
VVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBGIndrani7
 
Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Allan Leyte
 
Weekly Progress.521-67
Weekly Progress.521-67Weekly Progress.521-67
Weekly Progress.521-67Usama Athar
 
Rice Co-Op Presentation
Rice Co-Op PresentationRice Co-Op Presentation
Rice Co-Op PresentationScott Rice
 
Bgl solar update210614
Bgl solar update210614Bgl solar update210614
Bgl solar update210614Tejas Kale
 

Similar to Dashboard (20)

Project Controls planning & Scheduling Engineer-Portfolio
Project Controls planning & Scheduling Engineer-PortfolioProject Controls planning & Scheduling Engineer-Portfolio
Project Controls planning & Scheduling Engineer-Portfolio
 
Single Family Gantt Chart-John Mueller
Single Family Gantt Chart-John MuellerSingle Family Gantt Chart-John Mueller
Single Family Gantt Chart-John Mueller
 
Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011
 
Presentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptxPresentation for DHA on project progress(08-09-22).pptx
Presentation for DHA on project progress(08-09-22).pptx
 
CPM
CPMCPM
CPM
 
Monthly report of maintenance by Swamina International Ltd.
Monthly report of maintenance by Swamina International Ltd.Monthly report of maintenance by Swamina International Ltd.
Monthly report of maintenance by Swamina International Ltd.
 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptx
 
Weekly report no 19
Weekly report no 19Weekly report no 19
Weekly report no 19
 
2 l 65z
2 l 65z2 l 65z
2 l 65z
 
Project Quality control Progress .pptx
Project Quality control  Progress .pptxProject Quality control  Progress .pptx
Project Quality control Progress .pptx
 
CPUC - Typhoon Maysak - Restoration Report To 20 June 2015
CPUC - Typhoon Maysak - Restoration Report To 20 June 2015CPUC - Typhoon Maysak - Restoration Report To 20 June 2015
CPUC - Typhoon Maysak - Restoration Report To 20 June 2015
 
01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
 
EMC e City - Rev meeting Aug 2018.ppt
EMC e City - Rev meeting Aug 2018.pptEMC e City - Rev meeting Aug 2018.ppt
EMC e City - Rev meeting Aug 2018.ppt
 
DRAFT LHD-2 PEMT SKED V - Portfolio Example
DRAFT LHD-2 PEMT SKED V - Portfolio ExampleDRAFT LHD-2 PEMT SKED V - Portfolio Example
DRAFT LHD-2 PEMT SKED V - Portfolio Example
 
VVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBG
VVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBGVVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBG
VVGBJNRGGGGTGTGTGHTHGTGTGTJGNUGNURIEGNRIEUGBUBG
 
Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016Bissa Upgrade weekly report 09May2016
Bissa Upgrade weekly report 09May2016
 
Weekly Progress.521-67
Weekly Progress.521-67Weekly Progress.521-67
Weekly Progress.521-67
 
kolligars-I-1
kolligars-I-1kolligars-I-1
kolligars-I-1
 
Rice Co-Op Presentation
Rice Co-Op PresentationRice Co-Op Presentation
Rice Co-Op Presentation
 
Bgl solar update210614
Bgl solar update210614Bgl solar update210614
Bgl solar update210614
 

Dashboard

  • 1. Storm System GRP pipes Installation Backfilled Time Passed 1‐Jul‐15 1‐Aug‐15 Project Start Date 12‐Jun‐13 Total  Length Total External Box Culvert Total Internal Previous  Progress This Month Progress This Month Progress % Total  Progress % Total Remaining Project Finish Date 11‐Jun‐15 Excavated 26288 4942 1884 21347 20227 244 1% 20471 78% 5817 # Total Duration 729 Installed 26288 4942 1884 21347 19483 300 1% 19783 75% 6505 # Progress Cut off Date 2‐Aug‐15 Tested 26288 4942 1884 21347 18379 131 0% 18510 70% 7778 # Project Delay 52 Backfilled 26288 4942 1884 21347 17905 86 0.3% 17991 68% 8297 # Elapsed Duration 781 Sewage System VC pipes Installation Backfilled Earth Work Progress 1‐Jul‐15 1‐Aug‐15 Total  Length Total External Total Internal Previous  Progress This Month Progress This Month Progress % Total  Progress % Total Remaining Total M3 2,840,687 Excavated 28034 1135 26899 24354 104 0% 24458 87% 3576 # Previous Progress 2,777,677 Installed 28034 1135 26899 23748 175 1% 23923 85% 4111 # This  Month Compacted M3 8,522 Tested 28034 1135 26899 2300 21257 76% 23557 84% 4477 # Total Compacted M3 2,786,199 Backfilled 28034 1135 26899 22968 286 1.0% 23254 83% 4780 # Remaining M3 54,488 Potable System HDPE&DI pipes Installation Backfilled Manpower 1‐Jul‐15 1‐Aug‐15 Total  Length Total External Total Internal Previous  Progress This Month Progress This Month Progress % Total  Progress % Total Remaining Excavated 42824 5940 36884 23929 940 2% 24869 58% 17955 # Installed 42824 5940 36884 23117 440 1% 23557 55% 19267 # Tested 42824 5940 36884 21805 0 0% 21805 51% 21019 # Backfilled 42824 5940 36884 21422 125 0.3% 21547 50% 21277 # Irrigation System HDPE pipes Installation Backfilled 1‐Jul‐15 1‐Aug‐15 Dewatering Pumps Status Total  Length Total External Total Internal Previous  Progress This Month Progress This Month Progress % Total  Progress % Total Remaining Excavated 35527 4751 30776 20203 1215 3% 21418 60% 14109 # Installed 35527 4751 30776 19266 315 1% 19581 55% 15946 # Tested 35527 4751 30776 17557 371 1% 17928 50% 17599 # Backfilled 35527 4751 30776 17441 374 1.1% 17815 50% 17712 # Storm MHs/CBs‐ Storm System Slab/Connected Backfilled Butt Fusion welding  Machine 1‐Jul‐15 1‐Aug‐15 Total  No. Total External Box Culvert Total Internal Previous  Progress This Month Progress This Month Progress % Total  Progress % Total Remaining Foundation 493 58 39 396 285 7 1% 292 59% 201 # Walls/Placed 493 58 39 396 275 3 1% 278 56% 215 # Slab/Connected 493 58 39 396 273 1 0% 274 56% 219 # Insulation 493 58 39 396 233 6 1% 239 48% 254 # Backfilled 493 58 39 396 217 6 1.2% 223 45% 270 # Precast MHs‐ Sewage System Connection Backfilled 1‐Jul‐15 1‐Aug‐15 Electrical Fusion welding  Machine Total  No. Total External Box Culvert Total Internal Previous  Progress This Month Progress This Month Progress % Total  Progress % Total Remaining Placed 469 15 454 347 8 2% 355 76% 114 # Connected 469 15 454 332 9 2% 341 73% 128 # Insulation 469 15 454 278 14 3% 292 62% 177 # Backfilled 469 15 454 266 13 2.8% 279 59% 190 # ROAD GULLIES            Connection           Backfilled 1‐Jul‐15 1‐Aug‐15 Total  No. Total External Box Culvert Total Internal Previous  Progress This Month Progress This Month Progress % Total  Progress % Total Remaining Placed 507 108 73 326 88 34 7% 122 37% 385 # Connected 507 108 73 326 55 10 2% 65 20% 442 # Backfilled 507 108 73 326 41 0 0.0% 41 13% 466 # ELECTRICAL MV,LV STREET LIGHITNG INSTALL 1‐Jul‐15 1‐Aug‐15 MV  LV Total Length Total       No Previous  Progress This Month Progress This Month Progress % Total Progress % Total Remaining MV CABLE  131689 33571 498 0.4% 34069 26% 97620 # FOC Cable 131689 34304 705 1% 35009 27% 96680 # LV Cable 70817 5134 6406 9.0% 11540 16% 59277 # I.R Control Cable 47530 22318 540 1% 22858 48% 24672 # St. Ligthing (LV Cable)  79000 3130 450 1% 3580 5% 75420 # ST. Lighting Foundation 1500 59 0 0% 59 4% 1441 # St. Lighting Poles 1500 0 0 0% 0 0% 1500 # Telecom Network Telecom HDPE Conduit      Telecom Hand Holes 1‐Jul‐15 1‐Aug‐15 Total  Length Total No Previous  Progress This Month Progress This Month Progress % Total  Progress % Total Remaining Telecom HDPE Conduit 950000 238466 20688 2.2% 259154 27% 690846 # Telecom SMALL M.H 42 8 0 0% 8 19% 34 # TELECOM H.H 132 11 18 13.6% 29 22% 103 # SUBSTATIONS/MINIPILLARS 2‐Jan‐15 1‐Aug‐15 Substation           RMU Total  No. Previous  Progress This Month Progress This Month Progress % Total  Progress % Total Remaining ROOM STRUCTURE 48 48 0 0% 48 100% 0 # GATE/FENCE 48 6 0 0% 6 13% 42 # SUBSTATIONS 48 48 0 0.0% 48 100% 0 # RMU INSTALL 48 0 20 41.7% 20 42% 28 # MINIPILLARS 322 0 21 7% 21 7% 301 # ROADS NETWORK Asphalt         Curb Stone 1‐Jul‐15 1‐Aug‐15 Total  M3 Total M2 Total  Length Total Internal Previous  Progress This Month Progress This Month Progress % Total  Progress % Total Remaining SUBGRADE 254451 202361 25256 34549 14% 59805 24% 194646 # SUBBASE 108708 84020 9624 5306 5% 14930 14% 93778 # ASPHALT 562935 420102 24291 0 0.0% 24291 4% 538644 # CURSTONE 109272 85791 5458 102 0.1% 5560 5% 103712 # RHCP‐JEDDAH DASHBOARD PROGRESS AS OF 02‐Aug‐2015 17991 18510 19783 20471 26288 Backfilled Tested Installed Excavated Total… 23254 23557 23923 24458 28034 Backfilled Tested Installed Excavated Total… 21547 21805 23557 24869 36884 Backfilled Tested Installed Excavated Total… 17815 17928 19581 21418 30776 Backfilled Tested Installed Excavated Total… 98% 0% 2% Previous Progress This  Month Compacted M3 Remaining M3 71% 29% NCRs OVER ALL Progress  Closed Open 18.21 13.55 8.45 4.07 5.79 2.55 3.75 4.23 3.11 7.22 7.31 7.70 7.58 6.00 9.67 12.40 4.69 5.49 10.72 15.24 0 2 4 6 8 10 12 14 16 18 20 Sep‐13 Oct‐13 Nov‐13 Dec‐13 Jan‐14 Feb‐14 Mar‐14 Apr‐14 May‐14 Jun‐14 Jul‐14 Aug‐14 Sep‐14 Oct‐14 Nov‐14 Dec‐14 Jan‐15 Feb‐15 Mar‐15 Apr‐15 May‐15 Jun‐15 Millions Actual Paid Not Paid 74% 1% 25% Previous Progress This Month Progress Remaining 85% 0% 15% Previous Progress This Month Progress Remaining 54% 1% 45% Previous Progress This Month Progress Remaining 54% 1% 45% Previous Progress This Month Progress Remaining 55% 0% 45% Previous Progress This Month Progress Remaining 71% 2% 27% Previous Progress This Month Progress Remaining 279 292 341 355 469 Backfilled Insulation Connected Placed Total… 223 239 274 278 292 493 Backfilled Insulation Slab/Connected Walls/Placed Foundation Total… 44 44 Jun‐15 Jul‐15 12 12 12 May‐15 Jun‐15 Jul‐15 12 12 12 May‐15 Jun‐15 Jul‐15 68%0% 32% Previous Progress This Month Progress Remaining 82% 1% 17% Previous Progress This Month Progress Remaining 50% 0% 50% Previous Progress This Month Progress Remaining 49% 1% 50% Previous Progress This Month Progress Remaining 44% 1% 55% Previous Progress This Month Progress Remaining 57% 3% 40% Previous Progress This Month Progress Remaining 52  781  729  Project Delay Elapsed Duration Total Duration 41 65 122 507 Backfilled Connected Placed Total No. 11% 2% 87% Previous Progress This Month Progress Remaining 8% 0% 92% Previous Progress This Month Progress Remaining 34069 131689 35009 131689 11540 70817 22858 47530 3580 79000 Progress LM MV Total Length Progress LM FOC Total Length Progress LM LV Total Length Progress LM I.R Control Cable… Progress LM St. Ligthing Total… 259154 950000 Telecom HDPE Conduit Total Length 7% 9% 84% Previous Progress This Month Progress Remaining 0% 26% 74% Previous Progress This Month Progress Remaining 25% 2% 73% Previous Progress This Month Progress Remaining 8% 14% 78% Previous Progress This Month Progress Remaining 21 322 20 48 48 48 MINIPILLARS Total… RMU INSTALL Total… SUBSTATIONS Total… 100% 0% 0% Previous Progress This Month Progress Remaining 0% 42% 58% Previous Progress This Month Progress Remaining 5560 109272 24291 562935 14930 108708 59805 254451 CURSTONE ASPHALT SUBBASE SUBGRADE 4% 0% 96% Previous Progress This Month Progress Remaining 5%0% 95% Previous Progress This Month Progress Remaining 8 2 1 4 1 1 7 11 8 16 17 18 18 17 18 17 18 17 19 0 8 16 24 W102 W103 W104 W105 W106 W107 W108 W109 W110 W111 W112 W113 W114 W115 W116 W117 W118 W119 W120 Actual closed Plan to close 360 512 627 626 634 741 816 930 735 627 655 684 667 0 200 400 600 800 1000 Jul‐14 Aug‐14 Sep‐14 Oct‐14 Nov‐14 Dec‐14 Jan‐15 Feb‐15 Mar‐15 Apr‐15 May‐15 Jun‐15 Jul‐15 143 136 194 153 171 155 116 93 82 66 88 60 84 0 50 100 150 200 250 8‐May‐15 15‐May‐15 22‐May‐15 29‐May‐15 5‐Jun‐15 12‐Jun‐15 19‐Jun‐15 26‐Jun‐15 3‐Jul‐15 10‐Jul‐15 17‐Jul‐15 24‐Jul‐15 31‐Jul‐15 Inspection Requests Progress 30% 3% 67% IPC Status Previous This Period Remaining 8/6/2015 Prepared By: Eng. Aamir  (Sr.Plannging Engineer) E‐Mail: amir86_sohail@yahoo.com