Current and past projects within current role as senior project manager:
Client: Tier 1 Contractor
Role: Project Manager
April 2016 – Present
Project management support to the design management teams on a multi-disciplinary Design
Services for TfL Pathway Stages 4 Technical Design to completion of Stage 5 Construction for the
delivery of extension of the above ground ticket hall and associated basement and roof access points
at Tottenham Hale Underground Station.
Client: Private developer
Role: Project Manager
February 2015 – Present
Project management of GRIP stages 1-3 for the construction of a Strategic Rail Freight Interchange
(SRFI) comprising an intermodal terminal rail and road served distribution units. The SRFI includes
large distribution units with direct rail access from railway main Line.
Key responsibilities:
• Leading the interface between all of the engineering disciplines
• Resourcing forecasting and pre-planning
• Preparation of project proposals and sub-consult’s contracts
• Consulting and liaising with railway infrastructure’s sponsor and engineers
Client: Private developer
Project Manager
Dec 2014 – Present
Project management for demolition of a footbridge over railway infrastructure and multi-discipline
GRIP stages 1-8 for D&B contract new access for all footbridge.
Key responsibilities:
• Develop programme and procurement strategy for demolition of old bridge
• Liaise with railway infrastructure's Asset Protection team for approvals and agreement of
demolition plans
• Lead interfaces between stakeholders, client, Network Rail and demolition contractor
• Lead railway possession planning workshops
• Managed multi-disciplinary design for GRIP stages 1-4
• Liaise with 3rd parties for agreements and approval of GRIP stage 4 designs
• Managed procurement strategy for D&B GRIP stages 5-8
2
Client: Public agency
Project Manager
Feb 2015 – Present
Responsible for managing quality of service for significant design packages (RIBA F Civils/ Structural
and RIBA E Architectural and M&E) for railway projects at North Woolwich, Plumstead and Royal
Oak Portals and Westbourne Park Elevated Bus Deck.
Key responsibilities:
• Provide direction and management of engineering staff.
• Processing Work Orders and Early Warnings
• Mobilisation and demobilisation of staff
• Procurement and management of sub-consultants
• Preparation and processing contract documentation
• Managing and assessment of resources levels
Client: Public agency
Project Manager
Aug 2014 – Mar 2015
Responsible for management of NEC Option C contract for a public agency’s Asset Recovery
Programme.
Key responsibilities:
• Responsible for £18 million NEC Option C contract administration of Civils works for
emergency recovery of assets damaged during the 2013/14 winter storms throughout 60 sites in the
South East of England.
• Liaising with the ECC Project Manager/ Supervisors, reporting to the agency Project
Managers and client for drafting and management of Project Manager’s Instructions (PMIs), Early
Warning Notices (EWNs) and Compensation Events (CEs).

More Related Content

What's hot

Steve Miller CV 2017
Steve Miller CV 2017Steve Miller CV 2017
Steve Miller CV 2017
Steven Miller
 
01 CV 2016 Simon Barkley (1)
01 CV  2016 Simon Barkley  (1)01 CV  2016 Simon Barkley  (1)
01 CV 2016 Simon Barkley (1)
Simon Barkley
 
CKS_Portfolio_Min_CH2MHILL
CKS_Portfolio_Min_CH2MHILLCKS_Portfolio_Min_CH2MHILL
CKS_Portfolio_Min_CH2MHILL
Carmen Squires
 
Recent Project History
Recent Project HistoryRecent Project History
Recent Project History
byron_cormack
 
Construction update viracopos
Construction update   viracoposConstruction update   viracopos
Construction update viracopos
TriunfoRi
 
Andrew Maynes Resume 2016
Andrew Maynes Resume 2016Andrew Maynes Resume 2016
Andrew Maynes Resume 2016
Andrew Maynes
 

What's hot (20)

Steve Miller CV 2017
Steve Miller CV 2017Steve Miller CV 2017
Steve Miller CV 2017
 
Resume_Fernando_2016
Resume_Fernando_2016Resume_Fernando_2016
Resume_Fernando_2016
 
01 CV 2016 Simon Barkley (1)
01 CV  2016 Simon Barkley  (1)01 CV  2016 Simon Barkley  (1)
01 CV 2016 Simon Barkley (1)
 
Iain Cameron CV presentation jun13
Iain Cameron CV presentation jun13Iain Cameron CV presentation jun13
Iain Cameron CV presentation jun13
 
Cv marc andré gauvin en 2015
Cv marc andré gauvin en 2015Cv marc andré gauvin en 2015
Cv marc andré gauvin en 2015
 
04 02-15 Caltrain Modernization Updates
04 02-15 Caltrain Modernization Updates04 02-15 Caltrain Modernization Updates
04 02-15 Caltrain Modernization Updates
 
CKS_Portfolio_Min_CH2MHILL
CKS_Portfolio_Min_CH2MHILLCKS_Portfolio_Min_CH2MHILL
CKS_Portfolio_Min_CH2MHILL
 
Mohammad Ghayoor Khan CV oil
Mohammad Ghayoor Khan CV oilMohammad Ghayoor Khan CV oil
Mohammad Ghayoor Khan CV oil
 
Recent Project History
Recent Project HistoryRecent Project History
Recent Project History
 
New Resume for Hays
New Resume for HaysNew Resume for Hays
New Resume for Hays
 
FS CV 2016
FS CV 2016FS CV 2016
FS CV 2016
 
Construction update viracopos
Construction update   viracoposConstruction update   viracopos
Construction update viracopos
 
Hareket Magazine 27. issue-2018- English
Hareket Magazine 27. issue-2018- EnglishHareket Magazine 27. issue-2018- English
Hareket Magazine 27. issue-2018- English
 
DSD-INT 2015 - Software integration for pipelines and underground stresses  -...
DSD-INT 2015 - Software integration for pipelines and underground stresses  -...DSD-INT 2015 - Software integration for pipelines and underground stresses  -...
DSD-INT 2015 - Software integration for pipelines and underground stresses  -...
 
Andrew Maynes Resume 2016
Andrew Maynes Resume 2016Andrew Maynes Resume 2016
Andrew Maynes Resume 2016
 
South road superway project intelligent traffic system works
South road superway project intelligent traffic system worksSouth road superway project intelligent traffic system works
South road superway project intelligent traffic system works
 
AJM.PF. QCA.P1
AJM.PF. QCA.P1AJM.PF. QCA.P1
AJM.PF. QCA.P1
 
Telegraph Road Walkway Phase 1 August 2020
Telegraph Road Walkway Phase 1 August 2020Telegraph Road Walkway Phase 1 August 2020
Telegraph Road Walkway Phase 1 August 2020
 
CV - Ahmed Mounir
CV - Ahmed MounirCV - Ahmed Mounir
CV - Ahmed Mounir
 
CV_Charwin Caban
CV_Charwin CabanCV_Charwin Caban
CV_Charwin Caban
 

Similar to Current and past projects

North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
Association for Project Management
 
Richard Batts CV 2017
Richard Batts CV 2017Richard Batts CV 2017
Richard Batts CV 2017
Richard Batts
 
CV_PhilMorris_2015
CV_PhilMorris_2015CV_PhilMorris_2015
CV_PhilMorris_2015
Phil Morris
 
Husin Asran_Nov'16
Husin Asran_Nov'16Husin Asran_Nov'16
Husin Asran_Nov'16
Husin Asran
 
Henk Beekhof - English CV jan 2016
Henk Beekhof - English CV jan 2016Henk Beekhof - English CV jan 2016
Henk Beekhof - English CV jan 2016
Henk Beekhof
 
Updated C.V of water & sewerage
Updated  C.V of water & sewerageUpdated  C.V of water & sewerage
Updated C.V of water & sewerage
Khalid Pervez
 
piete resume and list of projects.2 Dec 15
piete resume and list of projects.2 Dec 15piete resume and list of projects.2 Dec 15
piete resume and list of projects.2 Dec 15
Pieter Manders
 

Similar to Current and past projects (20)

North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
 
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinarNorth West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
North West Multi-Modal Transport Hub (NWMTH) Derry – Londonderry webinar
 
grobson cv
grobson cvgrobson cv
grobson cv
 
LORENZO CABRAS CV
LORENZO CABRAS CVLORENZO CABRAS CV
LORENZO CABRAS CV
 
resume_franklin
resume_franklinresume_franklin
resume_franklin
 
Richard Batts CV 2017
Richard Batts CV 2017Richard Batts CV 2017
Richard Batts CV 2017
 
KWKCV16
KWKCV16KWKCV16
KWKCV16
 
Rao Yagitila CV
Rao Yagitila CVRao Yagitila CV
Rao Yagitila CV
 
Subhash CV Dec 2016
Subhash CV Dec 2016Subhash CV Dec 2016
Subhash CV Dec 2016
 
CV_PhilMorris_2015
CV_PhilMorris_2015CV_PhilMorris_2015
CV_PhilMorris_2015
 
DML CV 17
DML CV 17DML CV 17
DML CV 17
 
Project Engineer
Project EngineerProject Engineer
Project Engineer
 
Firas Abbawy CV - Atkins
Firas Abbawy CV - AtkinsFiras Abbawy CV - Atkins
Firas Abbawy CV - Atkins
 
Husin Asran_Nov'16
Husin Asran_Nov'16Husin Asran_Nov'16
Husin Asran_Nov'16
 
JDG CV_160413
JDG CV_160413JDG CV_160413
JDG CV_160413
 
Henk Beekhof - English CV jan 2016
Henk Beekhof - English CV jan 2016Henk Beekhof - English CV jan 2016
Henk Beekhof - English CV jan 2016
 
Updated C.V of water & sewerage
Updated  C.V of water & sewerageUpdated  C.V of water & sewerage
Updated C.V of water & sewerage
 
piete resume and list of projects.2 Dec 15
piete resume and list of projects.2 Dec 15piete resume and list of projects.2 Dec 15
piete resume and list of projects.2 Dec 15
 
Detailed Experiance - REV01
Detailed Experiance - REV01Detailed Experiance - REV01
Detailed Experiance - REV01
 
CV-Kunwar Aftab Ahmad Khan-29Oct2015
CV-Kunwar Aftab Ahmad Khan-29Oct2015CV-Kunwar Aftab Ahmad Khan-29Oct2015
CV-Kunwar Aftab Ahmad Khan-29Oct2015
 

Current and past projects

  • 1. 1 Current and past projects within current role as senior project manager: Client: Tier 1 Contractor Role: Project Manager April 2016 – Present Project management support to the design management teams on a multi-disciplinary Design Services for TfL Pathway Stages 4 Technical Design to completion of Stage 5 Construction for the delivery of extension of the above ground ticket hall and associated basement and roof access points at Tottenham Hale Underground Station. Client: Private developer Role: Project Manager February 2015 – Present Project management of GRIP stages 1-3 for the construction of a Strategic Rail Freight Interchange (SRFI) comprising an intermodal terminal rail and road served distribution units. The SRFI includes large distribution units with direct rail access from railway main Line. Key responsibilities: • Leading the interface between all of the engineering disciplines • Resourcing forecasting and pre-planning • Preparation of project proposals and sub-consult’s contracts • Consulting and liaising with railway infrastructure’s sponsor and engineers Client: Private developer Project Manager Dec 2014 – Present Project management for demolition of a footbridge over railway infrastructure and multi-discipline GRIP stages 1-8 for D&B contract new access for all footbridge. Key responsibilities: • Develop programme and procurement strategy for demolition of old bridge • Liaise with railway infrastructure's Asset Protection team for approvals and agreement of demolition plans • Lead interfaces between stakeholders, client, Network Rail and demolition contractor • Lead railway possession planning workshops • Managed multi-disciplinary design for GRIP stages 1-4 • Liaise with 3rd parties for agreements and approval of GRIP stage 4 designs • Managed procurement strategy for D&B GRIP stages 5-8
  • 2. 2 Client: Public agency Project Manager Feb 2015 – Present Responsible for managing quality of service for significant design packages (RIBA F Civils/ Structural and RIBA E Architectural and M&E) for railway projects at North Woolwich, Plumstead and Royal Oak Portals and Westbourne Park Elevated Bus Deck. Key responsibilities: • Provide direction and management of engineering staff. • Processing Work Orders and Early Warnings • Mobilisation and demobilisation of staff • Procurement and management of sub-consultants • Preparation and processing contract documentation • Managing and assessment of resources levels Client: Public agency Project Manager Aug 2014 – Mar 2015 Responsible for management of NEC Option C contract for a public agency’s Asset Recovery Programme. Key responsibilities: • Responsible for £18 million NEC Option C contract administration of Civils works for emergency recovery of assets damaged during the 2013/14 winter storms throughout 60 sites in the South East of England. • Liaising with the ECC Project Manager/ Supervisors, reporting to the agency Project Managers and client for drafting and management of Project Manager’s Instructions (PMIs), Early Warning Notices (EWNs) and Compensation Events (CEs).