SlideShare a Scribd company logo
1 of 2
Download to read offline
3D TYSON ROAD , L O N D O N , S E 2 3 3AA
P H O N E 0 7 9 1 9 8 9 5 1 8 3 • E - M A I L R T B A T T S @ G M A I L . C O M
R I C H A R D B A T T S
EDUCATION
2002 – 2007 Nottingham Trent University
MA - Property Development and Construction: September 2006 - 2007
• RICS Accredited at Masters Level. Includes: Construction Technology, Production and
Procurement. Contract Administration. Economics, Planning, Development, Sustainability,
Law.
BSc (Hons) Multimedia: 2:1 – 2
nd
Class Honours, 1
st
Division - July 2006
• Final year project (500 hours): ‘1
st
Time Buyer’ Property Website: Sales, Advice, Virtual
Property Tours.
1998 – 2000 Brighton, Hove and Sussex Sixth Form College
A levels: Media Studies (B), General Studies (B) Information Technology (C), Business Studies
and Economics (D)
1993 – 1998 Longhill High School
GCSEs: 3 A’s 6 B’s and 1 C. English Language and Literature (B,B), Double Science (B,B), Maths
(B)
EMPLOYMENT
09/2007 – Present Multiplex Construction Europe Ltd
Lead Construction Manager: 15 Bishopsgate Project: August 2015 - Present
• Lead the construction team including package, site, H&S and environmental managers and
graduates. Responsible for meeting all planning requirements with local authorities to
allow demolition and construction commencement. Strong relationships formed with TFL
and COL in the process, which have been maintained throughout the project
• Careful management of the client (Tower 42 Partnership) ensuring the Tower and their
entire estate remained in full operation at all times even when sharing their busy service
roads. A mandate of project is to build relationship with the developer with a view to
working together moving forward. Have been central to working towards this goal with
excellent and promising feedback to date
• Responsible for implementing the challenging logistics and traffic management plans with
only one dedicated vehicle entrance and crane. Extremely tight site with the Grade 1 listed
Gibson Hall façade being partly retained and flanking our building to one side, the Tower
over-sailing our building on the other and two further office blocks containing the
remaining adjacent areas of the site. Overall responsible for all temporary works
coordination to facilitate the build within the difficult constraints of site including crane
base, mega gantries, hanging scaffolds and cradles
• Responsible for reporting back to client (monthly reporting) and internally to board on
programme, quality, H&S etc. So far proven track record on present and all previous
projects without exception; completing on time, on budget and without any major incident
Construction Package Manager: 5-7 St. Helen’s Place Project: May 2012 – August 2015
• Responsible for the design coordination and project management of all main sub contracts
including the demolition, substructure, structure, temporary works and now fit out
packages on the £32m 5-7 St. Helens Place project in the City of London. A grade 1 listed
medieval church flank the south of site and live offices to the east and west, making for a
an extremely challenging job – often described by our MD as one of the most complicated
Multiplex have ever built
• Ensuring design has been coordinated and approved amongst the team and consultants in
a timely manner whilst concurrently heavily involved with the successful delivery of the
works on site. This is achieved through careful and continuous planning, monitoring and
communication with the site team and the subcontractor’s project managers
• Execute and lead the design coordination of the project through regular meetings and
workshops with the design team, our consultants and the sub-contractor package
management. Also chair weekly progress meetings with the subcontractors to aid control
of ongoing design, current site works, procurement of materials to site, urgent commercial
matters, day to day logistics and any health and safety items
• Headed up and managed the vastly complex temporary works required to retain and dig
under the 1920’s Portland Stone facade, thus allowing the 3 storey basement construction
to take place. As the Temporary Works Coordinator for both this and the 100 Bishopsgate
Project, was also responsible for the successful and safe execution of any none
permanent elements required to build the job, including the facade retention system,
basement propping, party wall restraint and installation of multi staged underpinning
• Entered project into the Ground Engineering awards 2014 for the above works for which
we were commended as finalists
Site Construction Manager: 100 Bishopsgate Project: February 2011 – May 2012
• Site manager on the £430m 100 BG Project during the demolition and Stage 1 construction
phase. Over several months oversaw the fast yet safe demolition of 5 existing buildings
(whilst retaining 1 stone facade). Following this managed the ‘de-risk’ works to complete
the first stage of the project. This included looking after the clearance of all archaeology,
relocating 2 electrical sub-stations, carrying out the bulk excavation of the 2 acre site and
completing the initial piling contract to allow for works to re-start in 2014 without
delay
• Ensured coordination and delivery of all trades once on site in a safe, timely manner and
with control of the budget through a detailed understanding of the sub-contracts enabling
only very minimal variations
• Control of quality by developing inspection and test plans with the sub-contractors
• Third party first point of contact for City of London, building control and project
neighbours
• Considerate Contractor Bronze Award winner 2012
Site Manager: Strata SE1: February 2009 – February 2011
• Joined the project as a site manager for the fit out and cladding of the 43 storey landmark
tower with a build cost of £73m. Later progressed to construction manager of the Pavillion
building, successfully delivering it’s completion on time and on budget. This included
building 9 apartments, a plant room and on the ground floor 2 units for retail usage.
• Following completion worked closely with the client PM to see through the defects liability
period to a stage where BMCE presence was no longer required. This included the
management and close out of several thousand snags and defects
Section Manager: Eden Shopping Centre and Apartments: September 2007 – February 2009
• Initiated with Multiplex at the High Wycombe Town Centre Extension on the graduate
programme. Responsible for the area coordination and construction development of
18 shop units and car park
• Managed the RFI process between consultant and sub- contractor. A ssisted in the
design coordination and review between all disciplines.
• Responsible for de-snagging the entire project to see out the defect liability period. This
involved completing works whilst the centre remained open and careful coordination
without detriment to any of the retailers or in the case of the residential areas, working with
the tenants to ensure end user satisfaction with minimum disruption
ADDITIONAL SKILLS AND INTERESTS
• Excellent interpersonal, communication and team working skills developed by managing
large teams of people from the labour on site or the consultants responsible for
architecture and structural engineering to the City of London and third party clients
• Active member of the Corporate Social Responsibility (CSR) Committee – Competed in
numerous fund raising sporting events each year, most recently the 2016 Tower 42
Vertical Rush Challenge and in winning team for the Multiplex Quadratlon,
• Keen cyclist, distance runner, snowboarder and skier. Competing in many 10K, half
marathon runs and London to Brighton events in recent months and years
• Highly creative multimedia background and proficient in all office programmes and I.T.
systems as well good basic knowledge / skills in CAD, BIM & basic 3D modelling software
• CIOB Member, Crane AP, TWC, SMSTS & CSCS trained, first aider, crane rescue
REFERENCES: Available on request

More Related Content

What's hot

HANI ISMAIL HARZALLAH - Latest
HANI ISMAIL HARZALLAH - LatestHANI ISMAIL HARZALLAH - Latest
HANI ISMAIL HARZALLAH - LatestHani Herzallah
 
RBR Profile Aug 2013
RBR Profile Aug 2013 RBR Profile Aug 2013
RBR Profile Aug 2013 Ronan Hogan
 
Stephen Groombridge-CV-1 (1)
Stephen Groombridge-CV-1 (1)Stephen Groombridge-CV-1 (1)
Stephen Groombridge-CV-1 (1)Steve Groombridge
 
Leveraging Hospitality Expertise - Nashville, Tennessee
Leveraging Hospitality Expertise - Nashville, TennesseeLeveraging Hospitality Expertise - Nashville, Tennessee
Leveraging Hospitality Expertise - Nashville, TennesseeMcKenney's Inc
 
CV_GFlanagan current 2016
CV_GFlanagan current 2016CV_GFlanagan current 2016
CV_GFlanagan current 2016Gareth Flanagan
 
Joseph John Kish, Master 2016
Joseph John Kish, Master 2016Joseph John Kish, Master 2016
Joseph John Kish, Master 2016Joseph Kish
 
Lyle Mitrovich Portfolio
Lyle Mitrovich PortfolioLyle Mitrovich Portfolio
Lyle Mitrovich PortfolioLyle Mitrovich
 
Mike Okey CV FM1 Linked in
Mike Okey  CV FM1 Linked inMike Okey  CV FM1 Linked in
Mike Okey CV FM1 Linked inMike Okey
 
resume for john rhynold 2015 #2
resume for john rhynold 2015 #2resume for john rhynold 2015 #2
resume for john rhynold 2015 #2john rhynold
 
RobRuhlmanResume_11_16
RobRuhlmanResume_11_16RobRuhlmanResume_11_16
RobRuhlmanResume_11_16Rob Ruhlman
 
Resume-Ted Murphy 2015
Resume-Ted Murphy 2015Resume-Ted Murphy 2015
Resume-Ted Murphy 2015Ted Murphy
 
Typical challenges in tunnelling
Typical challenges in tunnellingTypical challenges in tunnelling
Typical challenges in tunnellingAntti Nykänen
 
Rupert Davison latest CV
Rupert Davison latest CVRupert Davison latest CV
Rupert Davison latest CVRupert Davison
 

What's hot (20)

HANI ISMAIL HARZALLAH - Latest
HANI ISMAIL HARZALLAH - LatestHANI ISMAIL HARZALLAH - Latest
HANI ISMAIL HARZALLAH - Latest
 
GLL-CV JAN 2017
GLL-CV JAN 2017GLL-CV JAN 2017
GLL-CV JAN 2017
 
RBR Profile Aug 2013
RBR Profile Aug 2013 RBR Profile Aug 2013
RBR Profile Aug 2013
 
Survey Engr
Survey EngrSurvey Engr
Survey Engr
 
fpbcurrent1
fpbcurrent1fpbcurrent1
fpbcurrent1
 
Stephen Groombridge-CV-1 (1)
Stephen Groombridge-CV-1 (1)Stephen Groombridge-CV-1 (1)
Stephen Groombridge-CV-1 (1)
 
Leveraging Hospitality Expertise - Nashville, Tennessee
Leveraging Hospitality Expertise - Nashville, TennesseeLeveraging Hospitality Expertise - Nashville, Tennessee
Leveraging Hospitality Expertise - Nashville, Tennessee
 
Mohammad Ghayoor Khan CV oil
Mohammad Ghayoor Khan CV oilMohammad Ghayoor Khan CV oil
Mohammad Ghayoor Khan CV oil
 
CV_GFlanagan current 2016
CV_GFlanagan current 2016CV_GFlanagan current 2016
CV_GFlanagan current 2016
 
Joseph John Kish, Master 2016
Joseph John Kish, Master 2016Joseph John Kish, Master 2016
Joseph John Kish, Master 2016
 
Lyle Mitrovich Portfolio
Lyle Mitrovich PortfolioLyle Mitrovich Portfolio
Lyle Mitrovich Portfolio
 
Mike Okey CV FM1 Linked in
Mike Okey  CV FM1 Linked inMike Okey  CV FM1 Linked in
Mike Okey CV FM1 Linked in
 
Prajeesh K. CV - Sep 2016
Prajeesh K. CV - Sep 2016Prajeesh K. CV - Sep 2016
Prajeesh K. CV - Sep 2016
 
resume for john rhynold 2015 #2
resume for john rhynold 2015 #2resume for john rhynold 2015 #2
resume for john rhynold 2015 #2
 
Muhammad Qasim Zaib C.V
Muhammad Qasim Zaib C.VMuhammad Qasim Zaib C.V
Muhammad Qasim Zaib C.V
 
RobRuhlmanResume_11_16
RobRuhlmanResume_11_16RobRuhlmanResume_11_16
RobRuhlmanResume_11_16
 
Resume-Ted Murphy 2015
Resume-Ted Murphy 2015Resume-Ted Murphy 2015
Resume-Ted Murphy 2015
 
Typical challenges in tunnelling
Typical challenges in tunnellingTypical challenges in tunnelling
Typical challenges in tunnelling
 
AnthonyCurrent HTR
AnthonyCurrent HTRAnthonyCurrent HTR
AnthonyCurrent HTR
 
Rupert Davison latest CV
Rupert Davison latest CVRupert Davison latest CV
Rupert Davison latest CV
 

Similar to Richard Batts CV 2017

CV_Andy_Coupland (1)
CV_Andy_Coupland (1)CV_Andy_Coupland (1)
CV_Andy_Coupland (1)Andy Coupland
 
Rodwell Murwisi CV site manager 1
Rodwell Murwisi CV site manager 1Rodwell Murwisi CV site manager 1
Rodwell Murwisi CV site manager 1Rodi Murwisi
 
CVnz - Andrew Nash
CVnz - Andrew NashCVnz - Andrew Nash
CVnz - Andrew NashAndrew Nash
 
Key experience Feb 2016
Key experience Feb 2016Key experience Feb 2016
Key experience Feb 2016Kim Barry
 
Adrians Job ApplicationRecent 2015
Adrians Job ApplicationRecent 2015Adrians Job ApplicationRecent 2015
Adrians Job ApplicationRecent 2015Adrian Taylor
 
rodney-robinson-cv-1st-revision-1
rodney-robinson-cv-1st-revision-1rodney-robinson-cv-1st-revision-1
rodney-robinson-cv-1st-revision-1Rodney Robinson
 
Robert_Hesketh_CV_Senior_Project_Manager
Robert_Hesketh_CV_Senior_Project_ManagerRobert_Hesketh_CV_Senior_Project_Manager
Robert_Hesketh_CV_Senior_Project_ManagerRobert Hesketh
 
Jacobs Curriculum Vitae
Jacobs Curriculum VitaeJacobs Curriculum Vitae
Jacobs Curriculum VitaeJames King
 
Project management in construction
Project management in constructionProject management in construction
Project management in constructionNAVNEET KUMAR JHA
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.NAVNEET KUMAR JHA
 

Similar to Richard Batts CV 2017 (20)

DaveGriffithsCV
DaveGriffithsCVDaveGriffithsCV
DaveGriffithsCV
 
CV_Andy_Coupland (1)
CV_Andy_Coupland (1)CV_Andy_Coupland (1)
CV_Andy_Coupland (1)
 
Rodwell Murwisi CV site manager 1
Rodwell Murwisi CV site manager 1Rodwell Murwisi CV site manager 1
Rodwell Murwisi CV site manager 1
 
20100730 Jordan Cv
20100730 Jordan Cv20100730 Jordan Cv
20100730 Jordan Cv
 
Manal ibrahim.cv 17.docx
Manal ibrahim.cv 17.docxManal ibrahim.cv 17.docx
Manal ibrahim.cv 17.docx
 
CV
CVCV
CV
 
CVnz - Andrew Nash
CVnz - Andrew NashCVnz - Andrew Nash
CVnz - Andrew Nash
 
Key experience Feb 2016
Key experience Feb 2016Key experience Feb 2016
Key experience Feb 2016
 
LORENZO CABRAS CV
LORENZO CABRAS CVLORENZO CABRAS CV
LORENZO CABRAS CV
 
Adrians Job ApplicationRecent 2015
Adrians Job ApplicationRecent 2015Adrians Job ApplicationRecent 2015
Adrians Job ApplicationRecent 2015
 
Stelian Dragomir-CV
Stelian Dragomir-CVStelian Dragomir-CV
Stelian Dragomir-CV
 
rodney-robinson-cv-1st-revision-1
rodney-robinson-cv-1st-revision-1rodney-robinson-cv-1st-revision-1
rodney-robinson-cv-1st-revision-1
 
Robert_Hesketh_CV_Senior_Project_Manager
Robert_Hesketh_CV_Senior_Project_ManagerRobert_Hesketh_CV_Senior_Project_Manager
Robert_Hesketh_CV_Senior_Project_Manager
 
Schoonraad Resume - 2016
Schoonraad Resume - 2016Schoonraad Resume - 2016
Schoonraad Resume - 2016
 
Maulik_Mistri_1
Maulik_Mistri_1Maulik_Mistri_1
Maulik_Mistri_1
 
Jacobs Curriculum Vitae
Jacobs Curriculum VitaeJacobs Curriculum Vitae
Jacobs Curriculum Vitae
 
Project management in construction
Project management in constructionProject management in construction
Project management in construction
 
Project management in construction.
Project management in construction.Project management in construction.
Project management in construction.
 
Michelle Jepp 15
Michelle Jepp 15Michelle Jepp 15
Michelle Jepp 15
 
Yenimi CV Version 2
Yenimi CV Version 2Yenimi CV Version 2
Yenimi CV Version 2
 

Richard Batts CV 2017

  • 1. 3D TYSON ROAD , L O N D O N , S E 2 3 3AA P H O N E 0 7 9 1 9 8 9 5 1 8 3 • E - M A I L R T B A T T S @ G M A I L . C O M R I C H A R D B A T T S EDUCATION 2002 – 2007 Nottingham Trent University MA - Property Development and Construction: September 2006 - 2007 • RICS Accredited at Masters Level. Includes: Construction Technology, Production and Procurement. Contract Administration. Economics, Planning, Development, Sustainability, Law. BSc (Hons) Multimedia: 2:1 – 2 nd Class Honours, 1 st Division - July 2006 • Final year project (500 hours): ‘1 st Time Buyer’ Property Website: Sales, Advice, Virtual Property Tours. 1998 – 2000 Brighton, Hove and Sussex Sixth Form College A levels: Media Studies (B), General Studies (B) Information Technology (C), Business Studies and Economics (D) 1993 – 1998 Longhill High School GCSEs: 3 A’s 6 B’s and 1 C. English Language and Literature (B,B), Double Science (B,B), Maths (B) EMPLOYMENT 09/2007 – Present Multiplex Construction Europe Ltd Lead Construction Manager: 15 Bishopsgate Project: August 2015 - Present • Lead the construction team including package, site, H&S and environmental managers and graduates. Responsible for meeting all planning requirements with local authorities to allow demolition and construction commencement. Strong relationships formed with TFL and COL in the process, which have been maintained throughout the project • Careful management of the client (Tower 42 Partnership) ensuring the Tower and their entire estate remained in full operation at all times even when sharing their busy service roads. A mandate of project is to build relationship with the developer with a view to working together moving forward. Have been central to working towards this goal with excellent and promising feedback to date • Responsible for implementing the challenging logistics and traffic management plans with only one dedicated vehicle entrance and crane. Extremely tight site with the Grade 1 listed Gibson Hall façade being partly retained and flanking our building to one side, the Tower over-sailing our building on the other and two further office blocks containing the remaining adjacent areas of the site. Overall responsible for all temporary works coordination to facilitate the build within the difficult constraints of site including crane base, mega gantries, hanging scaffolds and cradles • Responsible for reporting back to client (monthly reporting) and internally to board on programme, quality, H&S etc. So far proven track record on present and all previous projects without exception; completing on time, on budget and without any major incident Construction Package Manager: 5-7 St. Helen’s Place Project: May 2012 – August 2015 • Responsible for the design coordination and project management of all main sub contracts including the demolition, substructure, structure, temporary works and now fit out packages on the £32m 5-7 St. Helens Place project in the City of London. A grade 1 listed medieval church flank the south of site and live offices to the east and west, making for a an extremely challenging job – often described by our MD as one of the most complicated Multiplex have ever built • Ensuring design has been coordinated and approved amongst the team and consultants in a timely manner whilst concurrently heavily involved with the successful delivery of the works on site. This is achieved through careful and continuous planning, monitoring and communication with the site team and the subcontractor’s project managers • Execute and lead the design coordination of the project through regular meetings and workshops with the design team, our consultants and the sub-contractor package
  • 2. management. Also chair weekly progress meetings with the subcontractors to aid control of ongoing design, current site works, procurement of materials to site, urgent commercial matters, day to day logistics and any health and safety items • Headed up and managed the vastly complex temporary works required to retain and dig under the 1920’s Portland Stone facade, thus allowing the 3 storey basement construction to take place. As the Temporary Works Coordinator for both this and the 100 Bishopsgate Project, was also responsible for the successful and safe execution of any none permanent elements required to build the job, including the facade retention system, basement propping, party wall restraint and installation of multi staged underpinning • Entered project into the Ground Engineering awards 2014 for the above works for which we were commended as finalists Site Construction Manager: 100 Bishopsgate Project: February 2011 – May 2012 • Site manager on the £430m 100 BG Project during the demolition and Stage 1 construction phase. Over several months oversaw the fast yet safe demolition of 5 existing buildings (whilst retaining 1 stone facade). Following this managed the ‘de-risk’ works to complete the first stage of the project. This included looking after the clearance of all archaeology, relocating 2 electrical sub-stations, carrying out the bulk excavation of the 2 acre site and completing the initial piling contract to allow for works to re-start in 2014 without delay • Ensured coordination and delivery of all trades once on site in a safe, timely manner and with control of the budget through a detailed understanding of the sub-contracts enabling only very minimal variations • Control of quality by developing inspection and test plans with the sub-contractors • Third party first point of contact for City of London, building control and project neighbours • Considerate Contractor Bronze Award winner 2012 Site Manager: Strata SE1: February 2009 – February 2011 • Joined the project as a site manager for the fit out and cladding of the 43 storey landmark tower with a build cost of £73m. Later progressed to construction manager of the Pavillion building, successfully delivering it’s completion on time and on budget. This included building 9 apartments, a plant room and on the ground floor 2 units for retail usage. • Following completion worked closely with the client PM to see through the defects liability period to a stage where BMCE presence was no longer required. This included the management and close out of several thousand snags and defects Section Manager: Eden Shopping Centre and Apartments: September 2007 – February 2009 • Initiated with Multiplex at the High Wycombe Town Centre Extension on the graduate programme. Responsible for the area coordination and construction development of 18 shop units and car park • Managed the RFI process between consultant and sub- contractor. A ssisted in the design coordination and review between all disciplines. • Responsible for de-snagging the entire project to see out the defect liability period. This involved completing works whilst the centre remained open and careful coordination without detriment to any of the retailers or in the case of the residential areas, working with the tenants to ensure end user satisfaction with minimum disruption ADDITIONAL SKILLS AND INTERESTS • Excellent interpersonal, communication and team working skills developed by managing large teams of people from the labour on site or the consultants responsible for architecture and structural engineering to the City of London and third party clients • Active member of the Corporate Social Responsibility (CSR) Committee – Competed in numerous fund raising sporting events each year, most recently the 2016 Tower 42 Vertical Rush Challenge and in winning team for the Multiplex Quadratlon, • Keen cyclist, distance runner, snowboarder and skier. Competing in many 10K, half marathon runs and London to Brighton events in recent months and years • Highly creative multimedia background and proficient in all office programmes and I.T. systems as well good basic knowledge / skills in CAD, BIM & basic 3D modelling software • CIOB Member, Crane AP, TWC, SMSTS & CSCS trained, first aider, crane rescue REFERENCES: Available on request