SlideShare a Scribd company logo
1 of 27
Download to read offline
Summer Internship
Presentation 2015-16
JAIPRAKASH ASSOCIATES PVT LTD
Abhimanyu Saraswat
AP14268
ACM 28th Batch
NICMAR ,Pune
Safety At Site
 Jaypee Group believes it to be the responsibility of all.
 Tool box talk -2 times/week
 A safety supervisor to be always present at site ,to monitor all the
safety checklists
 PPE were worn by workers
 Safety signboards were installed at entrance
 Helmets are compulsory
ALL OF THIS WAS JUST
DOCUMENTATION, REALITY WAS
QUITE DIFFERENT…….
NO HELMET NO SAFTEY BELT
Case which happened on site
resulting in fatality
Immediate Actions taken on Case:
 This accident took place at garden isles project in Jaypee Wish
Town. After this case, the construction activity was stalled for two
days.
 Health and Safety department at Jaypee prepared an investigating
report which only contained name of person, cause of fatality and
compensation to be paid with an attached copy of the F.I.R.
Given the case to investigate
 After this case, we were asked about our opinion about the matter.
We suggested that due to this fatality the construction activity was
stopped for 2days, resulting in huge loss in the productivity.
 We also pointed out that, only on this site alone there have been 6
fatalities due to unavailability of PPE’s and improper supervision from
the In-Charge.
 So after this we were given a week’s time to investigate the reason
for the fatality, understand the mindset of workers and staff towards
safety and remedial actions which we as Nicmarian’s can suggest.
Investigation
Contd…
 So we went to site to investigate the case, and found
that there was no safety net provided while the worker
was removing the above net.
 As per safety guidelines, while removing the safety net
another net should be installed at a place just below
where the previous net existed and another net 6 floors
below that for extra protection but none of this safety
measures were taken, resulting in this fatality.
Fell from 12th floor
Was trying to remove safety net
OUR INTERVENTION
OUR INTERVENTION
WORKING WITHOUT PPE’S WORKING WITH SAFETY BELT
Visible changes on site
Caution Tape installed
New Horizontal Safety Net
Safety Belt was being used
Shortfall In Safety
 Only few workers at site wore safety shoes other all workers worked
in slippers and were allowed to do so.
 Some laborers were not wearing safety belt
 There were many duct openings were no rail or covering object was
kept.
 In basement area workers worked continuously for hours without any
PPE’s and were exposed to dust particles which are potential
occupational health hazards.
 Mosquito problem at labor camps which wasn’t addressed.
Reason given by them….
 The mindset of the workers towards safety was awful. They didn’t
imply to basic requirements of working at heights like wearing
helmet, safety boots and wearing a safety harness while working on
the edges.
 The reason given by them for not wearing PPE’s was that, it hindered
their productivity and movement. When the in-charge was present
they would wear the PPE’s but as soon he is gone they would
remove them.
 The amount of these PPE’s per worker ratio was also very less.
Remedial action suggested…
 The remedial action we suggested after the investigation was:
 Preparation of safety reports which were Job Hazard Analysis (JHA)
and Hazard Identification and Risk Assessment (HIRA), which was
accepted by company.
 Issue of sufficient amount of PPE’s for the site which was its in-house
construction from the store as per requirement given by tower-in-
charge.
JHA AND HIRA
 C:UsersABHIMANYUDesktopNew folder (2)HIRA.pdf
 C:UsersABHIMANYUDesktopNew folder (2)JHA.pdf
Contracts
 We were given three contracts documents:
 Concession agreement between TEA and Jaypee Group : studied
 Fabrication and installation of Façade in JSPI : Summarized
document prepared which was between Jaypee Group and SJ
Fabricators.
 Comparative study between CPWD conditions and contract
condition was done for : Agreement between Jaypee Group and
ARCOP
 New folder (2)Contract Assigment - By Daksh and Abhimanyu.xlsx
Quality Testing
 SIEVE ANALYSIS OF COARSE AGGREGATE (IS 2386-1983)
 FLAKINESS INDEX OF COARSE AGGREGATE (IS 2386-Part 1)
 SPECIFIC GRAVITY OF AGGREGATES by Pycnometer (IS 2386- Part 3)
 Impact and Crushing strength of Aggregates. (IS 2386- Part 4)
 Silt Content of Sand. (IS 2386- Part 2)
 Note: Cement was not tested as Jaypee Cement was used in
construction.
My Recommendations
 Use of PPE’s by all the workers on site.
 Stacking of Steel to be done on an elevated platform rather than
on the ground.
 Cleaning of cement stores & properly stacking cement bags to
avoid its spoilage from rain water.
 Adequate curing has to be carried out as shrinkage cracks are
being formed in slabs.
 Hooks to be bended properly 45o in columns.
 The steel yard can be organized properly separating the waste steel
from the stacked material and proper cover for steel yard should be
maintained protecting the steel from unexpected weather
condition.
 There is a problem of mosquito at labour camp so there is a chance
of viral infection being spread. This problem should be addressed.
 Use of MSP for planning, tracking and monitoring of the project.
My Recommendations
My Contributions in Health and Safety, QA/QC and Basic of Site Execution in Jaypee Group

More Related Content

Viewers also liked

Appendix A5_Summary of Analysis for Okhta Tower Facade Energy Performance
Appendix A5_Summary of Analysis for Okhta Tower Facade Energy PerformanceAppendix A5_Summary of Analysis for Okhta Tower Facade Energy Performance
Appendix A5_Summary of Analysis for Okhta Tower Facade Energy PerformanceRichard D. Ochotorena
 
Transom Window - Beautiful Stained Glass Products
Transom Window - Beautiful Stained Glass ProductsTransom Window - Beautiful Stained Glass Products
Transom Window - Beautiful Stained Glass ProductsTransom Window
 
Staticus presentation 2012
Staticus presentation 2012Staticus presentation 2012
Staticus presentation 2012Staticus
 
Facade Access Equipment (EN)
Facade Access Equipment (EN)Facade Access Equipment (EN)
Facade Access Equipment (EN)XSPlatforms
 
Final project presentation
Final project presentationFinal project presentation
Final project presentationYahya Jundi
 
Energy saving facades 01
Energy saving facades 01Energy saving facades 01
Energy saving facades 01Leads Facade
 
Indian Facade and Fenestration Association
Indian Facade and Fenestration AssociationIndian Facade and Fenestration Association
Indian Facade and Fenestration AssociationSatish Kumar
 
Appendix A8_Excerpts from Project Delivery Strategy -Tower
Appendix A8_Excerpts from Project Delivery Strategy -TowerAppendix A8_Excerpts from Project Delivery Strategy -Tower
Appendix A8_Excerpts from Project Delivery Strategy -TowerRichard D. Ochotorena
 
Health And Safety
Health And SafetyHealth And Safety
Health And SafetyLore Ochoa
 
Facility Fall Protection: Roof and Facade Maintenance
Facility Fall Protection: Roof and Facade MaintenanceFacility Fall Protection: Roof and Facade Maintenance
Facility Fall Protection: Roof and Facade MaintenanceLJB Inc.
 
Vertical Transportation Consultant BMU Facade Access Cradle Systems consultan...
Vertical Transportation Consultant BMU Facade Access Cradle Systems consultan...Vertical Transportation Consultant BMU Facade Access Cradle Systems consultan...
Vertical Transportation Consultant BMU Facade Access Cradle Systems consultan...SAMSON BABU MCIBSE
 
MENGURUS KESELAMATAN DI TEMPAT KERJA : Mengurus Keselamatan Diri
MENGURUS KESELAMATAN DI TEMPAT KERJA : Mengurus Keselamatan DiriMENGURUS KESELAMATAN DI TEMPAT KERJA : Mengurus Keselamatan Diri
MENGURUS KESELAMATAN DI TEMPAT KERJA : Mengurus Keselamatan DiriMee Ruu
 
Ideas Engineering & Architectural Services Pvt.Ltd., Hyderabad, De Signs
 Ideas Engineering & Architectural Services Pvt.Ltd., Hyderabad, De Signs Ideas Engineering & Architectural Services Pvt.Ltd., Hyderabad, De Signs
Ideas Engineering & Architectural Services Pvt.Ltd., Hyderabad, De SignsIndiaMART InterMESH Limited
 
BMU (Building Maintenance Unit)
BMU (Building Maintenance Unit) BMU (Building Maintenance Unit)
BMU (Building Maintenance Unit) Jawad Ali Shah
 
VTME dubai Rajan Samson Facade access equipment bmu design planning by samson...
VTME dubai Rajan Samson Facade access equipment bmu design planning by samson...VTME dubai Rajan Samson Facade access equipment bmu design planning by samson...
VTME dubai Rajan Samson Facade access equipment bmu design planning by samson...SAMSON BABU MCIBSE
 
Pengenalan industri binaan ok
Pengenalan industri binaan okPengenalan industri binaan ok
Pengenalan industri binaan okamoi amore
 

Viewers also liked (19)

Appendix A5_Summary of Analysis for Okhta Tower Facade Energy Performance
Appendix A5_Summary of Analysis for Okhta Tower Facade Energy PerformanceAppendix A5_Summary of Analysis for Okhta Tower Facade Energy Performance
Appendix A5_Summary of Analysis for Okhta Tower Facade Energy Performance
 
Transom Window - Beautiful Stained Glass Products
Transom Window - Beautiful Stained Glass ProductsTransom Window - Beautiful Stained Glass Products
Transom Window - Beautiful Stained Glass Products
 
Staticus presentation 2012
Staticus presentation 2012Staticus presentation 2012
Staticus presentation 2012
 
Facade Access Equipment (EN)
Facade Access Equipment (EN)Facade Access Equipment (EN)
Facade Access Equipment (EN)
 
Final project presentation
Final project presentationFinal project presentation
Final project presentation
 
Energy saving facades 01
Energy saving facades 01Energy saving facades 01
Energy saving facades 01
 
Indian Facade and Fenestration Association
Indian Facade and Fenestration AssociationIndian Facade and Fenestration Association
Indian Facade and Fenestration Association
 
2.frame
2.frame2.frame
2.frame
 
Appendix A8_Excerpts from Project Delivery Strategy -Tower
Appendix A8_Excerpts from Project Delivery Strategy -TowerAppendix A8_Excerpts from Project Delivery Strategy -Tower
Appendix A8_Excerpts from Project Delivery Strategy -Tower
 
Health And Safety
Health And SafetyHealth And Safety
Health And Safety
 
Facility Fall Protection: Roof and Facade Maintenance
Facility Fall Protection: Roof and Facade MaintenanceFacility Fall Protection: Roof and Facade Maintenance
Facility Fall Protection: Roof and Facade Maintenance
 
Curtain walls
Curtain wallsCurtain walls
Curtain walls
 
Vertical Transportation Consultant BMU Facade Access Cradle Systems consultan...
Vertical Transportation Consultant BMU Facade Access Cradle Systems consultan...Vertical Transportation Consultant BMU Facade Access Cradle Systems consultan...
Vertical Transportation Consultant BMU Facade Access Cradle Systems consultan...
 
Contractor safety management system
Contractor safety  management systemContractor safety  management system
Contractor safety management system
 
MENGURUS KESELAMATAN DI TEMPAT KERJA : Mengurus Keselamatan Diri
MENGURUS KESELAMATAN DI TEMPAT KERJA : Mengurus Keselamatan DiriMENGURUS KESELAMATAN DI TEMPAT KERJA : Mengurus Keselamatan Diri
MENGURUS KESELAMATAN DI TEMPAT KERJA : Mengurus Keselamatan Diri
 
Ideas Engineering & Architectural Services Pvt.Ltd., Hyderabad, De Signs
 Ideas Engineering & Architectural Services Pvt.Ltd., Hyderabad, De Signs Ideas Engineering & Architectural Services Pvt.Ltd., Hyderabad, De Signs
Ideas Engineering & Architectural Services Pvt.Ltd., Hyderabad, De Signs
 
BMU (Building Maintenance Unit)
BMU (Building Maintenance Unit) BMU (Building Maintenance Unit)
BMU (Building Maintenance Unit)
 
VTME dubai Rajan Samson Facade access equipment bmu design planning by samson...
VTME dubai Rajan Samson Facade access equipment bmu design planning by samson...VTME dubai Rajan Samson Facade access equipment bmu design planning by samson...
VTME dubai Rajan Samson Facade access equipment bmu design planning by samson...
 
Pengenalan industri binaan ok
Pengenalan industri binaan okPengenalan industri binaan ok
Pengenalan industri binaan ok
 

Similar to My Contributions in Health and Safety, QA/QC and Basic of Site Execution in Jaypee Group

Eversendai - HSE Performance Management Systems-R1.pptx
Eversendai - HSE Performance Management Systems-R1.pptxEversendai - HSE Performance Management Systems-R1.pptx
Eversendai - HSE Performance Management Systems-R1.pptxADILRASHID54
 
Safety and Risk Summary Example for Clients
Safety and Risk Summary Example for ClientsSafety and Risk Summary Example for Clients
Safety and Risk Summary Example for ClientsMatthew Bennett
 
MYP –HSE-P5-WT-0044 - 14-10-2021.pptx
MYP –HSE-P5-WT-0044 - 14-10-2021.pptxMYP –HSE-P5-WT-0044 - 14-10-2021.pptx
MYP –HSE-P5-WT-0044 - 14-10-2021.pptxmahmood107739
 
Job Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..docJob Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..docAtif767782
 
Dr024 needle gunning operations
Dr024   needle gunning operationsDr024   needle gunning operations
Dr024 needle gunning operationsYousif Fikry
 
Core Risk Assessment for Office work.docx
Core  Risk Assessment for Office work.docxCore  Risk Assessment for Office work.docx
Core Risk Assessment for Office work.docxIbrahimEsmat
 
EngineeredAirGroupB_final_report_7_copies
EngineeredAirGroupB_final_report_7_copiesEngineeredAirGroupB_final_report_7_copies
EngineeredAirGroupB_final_report_7_copiesMatthew Beacock
 
OH&S Audit Report- JSW Nandyal.doc
OH&S Audit Report- JSW Nandyal.docOH&S Audit Report- JSW Nandyal.doc
OH&S Audit Report- JSW Nandyal.docMirza Saifullah Baig
 
Celebrate_Safety_ARGENTINA_EEII
Celebrate_Safety_ARGENTINA_EEIICelebrate_Safety_ARGENTINA_EEII
Celebrate_Safety_ARGENTINA_EEIIAndres Galvis
 
IRJET- Design, Testing and Analysis of Spherical and Aerodynamic Helmet in Op...
IRJET- Design, Testing and Analysis of Spherical and Aerodynamic Helmet in Op...IRJET- Design, Testing and Analysis of Spherical and Aerodynamic Helmet in Op...
IRJET- Design, Testing and Analysis of Spherical and Aerodynamic Helmet in Op...IRJET Journal
 
Boom Lift - working from_2.docx
Boom Lift - working from_2.docxBoom Lift - working from_2.docx
Boom Lift - working from_2.docxolorunyomi wale
 
Usage of Personal Protective Equipment
Usage of Personal Protective Equipment Usage of Personal Protective Equipment
Usage of Personal Protective Equipment Reliance
 
IRJET- Design and Finite Element Analysis(FEA) of Formula Student Chassis
IRJET- Design and Finite Element Analysis(FEA) of Formula Student ChassisIRJET- Design and Finite Element Analysis(FEA) of Formula Student Chassis
IRJET- Design and Finite Element Analysis(FEA) of Formula Student ChassisIRJET Journal
 
A Review study on the Design of Wind Screen Using Finite Element Approach
A Review study on the Design of Wind Screen Using Finite Element ApproachA Review study on the Design of Wind Screen Using Finite Element Approach
A Review study on the Design of Wind Screen Using Finite Element ApproachIRJET Journal
 
Development of Forging Bolster for Quick Die Setup
Development of Forging Bolster for Quick Die SetupDevelopment of Forging Bolster for Quick Die Setup
Development of Forging Bolster for Quick Die SetupIRJET Journal
 
2007-049 Matthee Conveyor idlers
2007-049 Matthee Conveyor idlers2007-049 Matthee Conveyor idlers
2007-049 Matthee Conveyor idlersHennie Matthee
 

Similar to My Contributions in Health and Safety, QA/QC and Basic of Site Execution in Jaypee Group (20)

Eversendai - HSE Performance Management Systems-R1.pptx
Eversendai - HSE Performance Management Systems-R1.pptxEversendai - HSE Performance Management Systems-R1.pptx
Eversendai - HSE Performance Management Systems-R1.pptx
 
Safety and Risk Summary Example for Clients
Safety and Risk Summary Example for ClientsSafety and Risk Summary Example for Clients
Safety and Risk Summary Example for Clients
 
Introduction 1
Introduction 1Introduction 1
Introduction 1
 
MYP –HSE-P5-WT-0044 - 14-10-2021.pptx
MYP –HSE-P5-WT-0044 - 14-10-2021.pptxMYP –HSE-P5-WT-0044 - 14-10-2021.pptx
MYP –HSE-P5-WT-0044 - 14-10-2021.pptx
 
Job Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..docJob Safety Analyses For Energization of Substation..doc
Job Safety Analyses For Energization of Substation..doc
 
Dr024 needle gunning operations
Dr024   needle gunning operationsDr024   needle gunning operations
Dr024 needle gunning operations
 
Core Risk Assessment for Office work.docx
Core  Risk Assessment for Office work.docxCore  Risk Assessment for Office work.docx
Core Risk Assessment for Office work.docx
 
EngineeredAirGroupB_final_report_7_copies
EngineeredAirGroupB_final_report_7_copiesEngineeredAirGroupB_final_report_7_copies
EngineeredAirGroupB_final_report_7_copies
 
evaporater types.pdf
evaporater types.pdfevaporater types.pdf
evaporater types.pdf
 
OH&S Audit Report- JSW Nandyal.doc
OH&S Audit Report- JSW Nandyal.docOH&S Audit Report- JSW Nandyal.doc
OH&S Audit Report- JSW Nandyal.doc
 
Presentation on cooling tower
Presentation on cooling towerPresentation on cooling tower
Presentation on cooling tower
 
Celebrate_Safety_ARGENTINA_EEII
Celebrate_Safety_ARGENTINA_EEIICelebrate_Safety_ARGENTINA_EEII
Celebrate_Safety_ARGENTINA_EEII
 
IRJET- Design, Testing and Analysis of Spherical and Aerodynamic Helmet in Op...
IRJET- Design, Testing and Analysis of Spherical and Aerodynamic Helmet in Op...IRJET- Design, Testing and Analysis of Spherical and Aerodynamic Helmet in Op...
IRJET- Design, Testing and Analysis of Spherical and Aerodynamic Helmet in Op...
 
cpwd training
cpwd trainingcpwd training
cpwd training
 
Boom Lift - working from_2.docx
Boom Lift - working from_2.docxBoom Lift - working from_2.docx
Boom Lift - working from_2.docx
 
Usage of Personal Protective Equipment
Usage of Personal Protective Equipment Usage of Personal Protective Equipment
Usage of Personal Protective Equipment
 
IRJET- Design and Finite Element Analysis(FEA) of Formula Student Chassis
IRJET- Design and Finite Element Analysis(FEA) of Formula Student ChassisIRJET- Design and Finite Element Analysis(FEA) of Formula Student Chassis
IRJET- Design and Finite Element Analysis(FEA) of Formula Student Chassis
 
A Review study on the Design of Wind Screen Using Finite Element Approach
A Review study on the Design of Wind Screen Using Finite Element ApproachA Review study on the Design of Wind Screen Using Finite Element Approach
A Review study on the Design of Wind Screen Using Finite Element Approach
 
Development of Forging Bolster for Quick Die Setup
Development of Forging Bolster for Quick Die SetupDevelopment of Forging Bolster for Quick Die Setup
Development of Forging Bolster for Quick Die Setup
 
2007-049 Matthee Conveyor idlers
2007-049 Matthee Conveyor idlers2007-049 Matthee Conveyor idlers
2007-049 Matthee Conveyor idlers
 

More from Abhimanyu Saraswat

Job Hazard Analysis for a Residential Tower
Job Hazard Analysis for a Residential TowerJob Hazard Analysis for a Residential Tower
Job Hazard Analysis for a Residential TowerAbhimanyu Saraswat
 
Summer Internship in Jaypee Group
Summer Internship in Jaypee Group Summer Internship in Jaypee Group
Summer Internship in Jaypee Group Abhimanyu Saraswat
 
Summer internship in Jaypee Group
Summer internship in Jaypee GroupSummer internship in Jaypee Group
Summer internship in Jaypee GroupAbhimanyu Saraswat
 
RMC Plant and its components, Testing and Design Mix
RMC Plant and its components, Testing and Design MixRMC Plant and its components, Testing and Design Mix
RMC Plant and its components, Testing and Design MixAbhimanyu Saraswat
 
Investigation of behaviour of concrete on adding crumb
Investigation of behaviour of concrete on adding crumbInvestigation of behaviour of concrete on adding crumb
Investigation of behaviour of concrete on adding crumbAbhimanyu Saraswat
 

More from Abhimanyu Saraswat (7)

Job Hazard Analysis for a Residential Tower
Job Hazard Analysis for a Residential TowerJob Hazard Analysis for a Residential Tower
Job Hazard Analysis for a Residential Tower
 
Summer Internship in Jaypee Group
Summer Internship in Jaypee Group Summer Internship in Jaypee Group
Summer Internship in Jaypee Group
 
Summer internship in Jaypee Group
Summer internship in Jaypee GroupSummer internship in Jaypee Group
Summer internship in Jaypee Group
 
RMC Plant and its components, Testing and Design Mix
RMC Plant and its components, Testing and Design MixRMC Plant and its components, Testing and Design Mix
RMC Plant and its components, Testing and Design Mix
 
Trench less Technology
Trench less Technology Trench less Technology
Trench less Technology
 
THESIS
THESISTHESIS
THESIS
 
Investigation of behaviour of concrete on adding crumb
Investigation of behaviour of concrete on adding crumbInvestigation of behaviour of concrete on adding crumb
Investigation of behaviour of concrete on adding crumb
 

Recently uploaded

VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 

Recently uploaded (20)

VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 

My Contributions in Health and Safety, QA/QC and Basic of Site Execution in Jaypee Group

  • 1. Summer Internship Presentation 2015-16 JAIPRAKASH ASSOCIATES PVT LTD Abhimanyu Saraswat AP14268 ACM 28th Batch NICMAR ,Pune
  • 2. Safety At Site  Jaypee Group believes it to be the responsibility of all.  Tool box talk -2 times/week  A safety supervisor to be always present at site ,to monitor all the safety checklists  PPE were worn by workers  Safety signboards were installed at entrance  Helmets are compulsory
  • 3.
  • 4. ALL OF THIS WAS JUST DOCUMENTATION, REALITY WAS QUITE DIFFERENT…….
  • 5. NO HELMET NO SAFTEY BELT
  • 6. Case which happened on site resulting in fatality
  • 7. Immediate Actions taken on Case:  This accident took place at garden isles project in Jaypee Wish Town. After this case, the construction activity was stalled for two days.  Health and Safety department at Jaypee prepared an investigating report which only contained name of person, cause of fatality and compensation to be paid with an attached copy of the F.I.R.
  • 8. Given the case to investigate  After this case, we were asked about our opinion about the matter. We suggested that due to this fatality the construction activity was stopped for 2days, resulting in huge loss in the productivity.  We also pointed out that, only on this site alone there have been 6 fatalities due to unavailability of PPE’s and improper supervision from the In-Charge.  So after this we were given a week’s time to investigate the reason for the fatality, understand the mindset of workers and staff towards safety and remedial actions which we as Nicmarian’s can suggest.
  • 10. Contd…  So we went to site to investigate the case, and found that there was no safety net provided while the worker was removing the above net.  As per safety guidelines, while removing the safety net another net should be installed at a place just below where the previous net existed and another net 6 floors below that for extra protection but none of this safety measures were taken, resulting in this fatality.
  • 11. Fell from 12th floor
  • 12. Was trying to remove safety net
  • 14. OUR INTERVENTION WORKING WITHOUT PPE’S WORKING WITH SAFETY BELT
  • 18. Safety Belt was being used
  • 19. Shortfall In Safety  Only few workers at site wore safety shoes other all workers worked in slippers and were allowed to do so.  Some laborers were not wearing safety belt  There were many duct openings were no rail or covering object was kept.  In basement area workers worked continuously for hours without any PPE’s and were exposed to dust particles which are potential occupational health hazards.  Mosquito problem at labor camps which wasn’t addressed.
  • 20. Reason given by them….  The mindset of the workers towards safety was awful. They didn’t imply to basic requirements of working at heights like wearing helmet, safety boots and wearing a safety harness while working on the edges.  The reason given by them for not wearing PPE’s was that, it hindered their productivity and movement. When the in-charge was present they would wear the PPE’s but as soon he is gone they would remove them.  The amount of these PPE’s per worker ratio was also very less.
  • 21. Remedial action suggested…  The remedial action we suggested after the investigation was:  Preparation of safety reports which were Job Hazard Analysis (JHA) and Hazard Identification and Risk Assessment (HIRA), which was accepted by company.  Issue of sufficient amount of PPE’s for the site which was its in-house construction from the store as per requirement given by tower-in- charge.
  • 22. JHA AND HIRA  C:UsersABHIMANYUDesktopNew folder (2)HIRA.pdf  C:UsersABHIMANYUDesktopNew folder (2)JHA.pdf
  • 23. Contracts  We were given three contracts documents:  Concession agreement between TEA and Jaypee Group : studied  Fabrication and installation of Façade in JSPI : Summarized document prepared which was between Jaypee Group and SJ Fabricators.  Comparative study between CPWD conditions and contract condition was done for : Agreement between Jaypee Group and ARCOP  New folder (2)Contract Assigment - By Daksh and Abhimanyu.xlsx
  • 24. Quality Testing  SIEVE ANALYSIS OF COARSE AGGREGATE (IS 2386-1983)  FLAKINESS INDEX OF COARSE AGGREGATE (IS 2386-Part 1)  SPECIFIC GRAVITY OF AGGREGATES by Pycnometer (IS 2386- Part 3)  Impact and Crushing strength of Aggregates. (IS 2386- Part 4)  Silt Content of Sand. (IS 2386- Part 2)  Note: Cement was not tested as Jaypee Cement was used in construction.
  • 25. My Recommendations  Use of PPE’s by all the workers on site.  Stacking of Steel to be done on an elevated platform rather than on the ground.  Cleaning of cement stores & properly stacking cement bags to avoid its spoilage from rain water.  Adequate curing has to be carried out as shrinkage cracks are being formed in slabs.  Hooks to be bended properly 45o in columns.  The steel yard can be organized properly separating the waste steel from the stacked material and proper cover for steel yard should be maintained protecting the steel from unexpected weather condition.
  • 26.  There is a problem of mosquito at labour camp so there is a chance of viral infection being spread. This problem should be addressed.  Use of MSP for planning, tracking and monitoring of the project. My Recommendations