Unit 4: Levelling
Definition of Levelling:
Levelling is defined as “an art of determining the relative height of different points on, above
or below the surface.
Principle of Levelling:
The principle of levelling is to obtain horizontal line of sight with respect to which vertical
distances of the points above or below this line of sight are found.
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
Terminologies: Level surfaces, Horizontal and Vertical surfaces, Datum :
i. Level surface: It is the surface parallel to the mean spheroidal surface of the earth. The
Surface of still water is an example of level surface.
ii. Horizontal plane or surface: Horizontal plane through a point is a plane tangential to level
surface.
iii. Horizontal line: It is a straight line tangential to level line.
iv. Datum: Terms used in levelling Datum “It is an arbitrary level surface from which elevation of
points may be referred”. In India mean sea level (MSL) is considered as datum of zero
elevation it is situated at Karachi. Mean Sea Level is the average height of sea for all stages of
tides it is derived by averaging the hourly tide height over a period of 19 years.
v. Elevation or Reduced level: It is height or depth of any point above or below any datum. It is
denoted as R.L.
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
Terminologies: Bench Marks- GTS, Permanent, Arbitrary and Temporary
Reduced Level:
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
Terminologies: Bench Marks- GTS, Permanent, Arbitrary and Temporary
Reduced Level:
Definition of Bench Mark (B.M.) It is a fixed reference point of known elevation
with respect to datum.
Classification of Bench Mark (B.M.)
There are 4 kinds of bench marks
a) GTS (Great Trigonometrically survey Bench Mark)
b) Permanent bench mark
c) Arbitrary bench mark
d) Temporary bench mark
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
Terminologies: Bench Marks- GTS, Permanent, Arbitrary and Temporary
Reduced Level:
Classification of Bench Mark (B.M.)
a) GTS (Great Trigonometrically survey Bench Mark)
They are the bench marks established with very high degree of precision at
regular intervals by the survey of India Department all over the country.
Their position and R.Ls values above mean seal level which was earlier located
at Karachi and now it is taken at Bombay High, Mumbai and is given in
catalogue formed by the department.
b) Permanent bench mark
Permanent bench marks are fixed in between GTS benchmarks by govt.
agencies such as railways, PWD, etc. This benchmarks are written on
permanent objects such as milestones, culverts, bridges etc., their values
are clearly written and their position are recorded for future reference.
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
Terminologies: Bench Marks- GTS, Permanent, Arbitrary and Temporary
Reduced Level:
c) Arbitrary Bench Marks
These are reference points whose R.L.s are arbitrarily assumed. They are
used in small works such bench mark may be assumed as 100.000m or
50.000m
d) Temporary Bench Marks
They are the reference points established during the levelling operations when
there is a break in work, or at the end of day’s work the value of reduced
levels are marked on some permanent objects such as stones, trees etc.
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
Terminologies: Rise, Fall, Line of collimation, Station, Back sight, Fore sight,
intermediate sight, Change point, Height of instruments:
a) Line of collimation:
It is a line joining the intersection of cross hairs of diaphragm to the optical centre of
object glass and its continuation. It is also known as line of sight.
b) Back Sight (B. S.)
Back sight It is a staff reading taken at a known elevation. It is the first staff reading
taken after setup of instrument.
c) Fore Sight (F. S.):
Fore sight It is the last staff reading taken denoting the shifting of the instrument.
d) Intermediate sight.(I.S.):
It is staff reading taken on a point whose elevation is to be determined. All staff
reading between B.S. and F.S. are Intermediate sight.
e) Change Point (T.P.):
It is a point on which both fore and back sight are taken.
f) Height of instrument:
It is the elevation of line of collimation with respect to datum.
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
Terminologies: Rise, Fall, Line of collimation, Station, Back sight, Fore sight,
intermediate sight, Change point, Height of instruments:
a) Line of collimation:
b) Back Sight (B. S.)
c) Fore Sight (F. S.):
d) Intermediate sight.(I.S.):
e) Change Point (T.P.):
f) Height of instrument:
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
Types of levels: Dumpy level:
The Dumpy level is a simple, compact and stable instrument. The telescope is rigidly
fixed to its supports. Hence it cannot be rotated about horizontal axis
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
Types of levels: Tilting Level:
It consists of a telescope attached with a level tube which can be tilted within few
degrees in vertical plane by a tilting screw.
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
Types of levels: Auto Level:
It The fundamental difference between automatic and the classic spirit level is that in
the former the line of sight is no longer levelled manually using a tubular spirit level,
but is levelled automatically within a certain tilt range. This is achieved by
compensator in the telescope.
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
Types of levels: Auto Level:
It The fundamental difference between automatic and the classic spirit level is that in
the former the line of sight is no longer levelled manually using a tubular spirit level,
but is levelled automatically within a certain tilt range. This is achieved by
compensator in the telescope.
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
Types of levels: Components of Dumpy Level and its fundamental axes, Temporary
adjustments of Level.
Dumpy level consists the following parts or components
 Telescope
 Longitudinal Bubble tube
 Eye piece
 Focussing Screw
 Vertical spindle
 Tribrach screws
 Foot screws
 Leveling head
 Tripod
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
Types of levels: Components of Dumpy Level and its fundamental axes, Temporary
adjustments of Level.
Temporary Adjustment of Level
1. Setting up of the level
2. Levelling by foot screws
3. Focussing the eye-piece
4. Focussing the object glass.
1. Setting up of the level
The instrument is fixed to the tripod stand using clamp screws. Spread the tripod legs and
position the instrument at convenient height. Firstly fix the two legs in the ground at a
point and centering of bubble in the bubble tubes is done by adjusting third leg.
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
Types of levels: Components of Dumpy Level and its fundamental axes, Temporary
adjustments of Level.
Temporary Adjustment of Level
2. Levelling by foot screws:
Levelling is done with the help of foot screws. The purpose of levelling is to make vertical
axis truly vertical.
It is done with the help of foot screws
a) Place the telescope/longitudinal bubble tube parallel to a pair (i. e. any two) of foot
screw then hold the foot screws between thumb and first finger and turn them either
inward or outward until the longitudinal bubble comes in the centre.
b)Turn the telescope through 900 so that it lies parallel to third foot screw, rotate the third
foot screw clockwise or anti-clockwise until the bubble comes in the centre.
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
Types of levels: Components of Dumpy Level and its fundamental axes, Temporary
adjustments of Level.
Temporary Adjustment of Level
2. Levelling by foot screws:
c) Again bring the telescope/longitudinal bubble tube back to original position i. e. parallel
to any two foot screws and bring bubble to the centre.
d) Now turn the telescope through 900 so that it lies parallel to third foot screw, turn the
screw until the bubble comes in the centre.
e) Repeat the same procedure three times.
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
Types of levels: Components of Dumpy Level and its fundamental axes, Temporary
adjustments of Level.
Temporary Adjustment of Level
3. Focussing the eye-piece:
To focus the eye piece, hold a white paper in front of object glass, and (rotate eye piece
clockwise or anti-clock wise direction) move the eye piece in or out till the cross hair
are clear & distinctly seen.
4. Focusing of object glass:
Direct the telescope to the levelling staff and on looking through the telescope, turn the
focusing screw in forward or reverse direction till the image appears clear and sharp.
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
Types of Leveling Staffs:
1. Self-reading staff 2. Target staff.
1. Self-reading staff:
The self reading staff can be read directly by the level man looking through the telescope.
Common types of self reading staffs
1. Ordinary staff- The one length staff, is solid and made of seasoned wood, it is 3 m long
and graduated in the same way as the telescopic staff
2. Sop-with telescopic staff- Such a staff is arranged in three lengths placed one into the
other. It can be extended to its full length by pulling. The top portion is solid and the
central box is hollow the total length of staff is 4 m. • The staff is graduated in such a way
that smallest division is of 5 mm. the value in m are marked in red on the left and those in
decimeter are in black on the right.
3. Folding Staff- The folding staff is made up of well seasoned timber such as Cyprus. It
consists of two 2 m wooden pieces with a joint assembly. Each piece of the staff is made
of one longitudinal strip without any joint. The folding joint is of the detachable type with
a locking device at the back. The staff is joined together in such a way that the staff may be
folded from one another when required. • The staff has brass cap at the bottom. It has two
folding handles, with spring action. It is provided with a circular bubble fitted at the back.
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
Types of Leveling Staffs:
1. Self-reading staff
1. Self-reading staff:
1. Ordinary staff-
2. Sop-with telescopic staff-
3. Folding Staff-
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
Types of Leveling Staffs:
2. Target staff- For very precise works and sight target staff are used. A movable target is
provided in this staff. • A vernier is provided on target to give precise reading. In target
staff level man directs the staff man to move the target up and down until it bisects by the
line of sight. The staff man observe the staff reading.
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
4.4 Reduction of level by Line of collimation method and Rise/ Fall Method:
4.5 Methods to find the R. L. in Level Book by H.I.
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
4.6 Methods: Rise and Fall Methods with necessary checks.
ΣB.S. – ƩF.S. = ΣRise – ΣFall = Last R. L. – First R. L.
6.100 – 5.950 = 2.350 – 2.200 = 240.150 – 240.000
0.150 = 0.150 = 0.150Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
4.6 Methods: Rise and Fall Methods with necessary checks.
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
4.4 Reduction of level by Line of collimation method and Rise/ Fall Method:
4.5 Methods to find the R. L. in Level Book by H.I.
4.6 Methods: Rise and Fall Methods with necessary checks.
On Blackboard
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
4.7 Leveling Types: Simple, Differential.
Simple levelling:
It is the simplest method used, when it is required to find the difference in elevation
between 2 points.
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
4.7 Leveling Types: Simple, Differential.
Differential levelling:
This method is used to find the difference in the elevation between points if they are
too far apart or the difference in elevation between them is too much. It is also called as
“Compound Levelling.”
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
4.7 Fly, Profile and Reciprocal Leveling.
Fly levelling:
This Fly levelling is just like differential levelling carried out to check the accuracy of
levelling work. In fly levelling only B.S. and F.S. are taken
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
4.7 Fly, Profile and Reciprocal Leveling.
Fly levelling:
This Fly levelling is just like differential levelling carried out to check the accuracy of
levelling work. In fly levelling only B.S. and F.S. are taken
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
4.7 Fly, Profile and Reciprocal Leveling.
Profile levelling or L- section:
This method is used for taking levels along the centre line of any alignment like road,
railway canal etc. The object is to determine the undulations of the ground surface along the
alignment.
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
4.7 Fly, Profile and Reciprocal Leveling.
Profile levelling or L- section:
This method is used for taking levels along the centre line of any alignment like road,
railway canal etc. The object is to determine the undulations of the ground surface along the
alignment.
Prepared by- Mr. Abhay Abhale
Unit 4: Levelling
4.7 Fly, Profile and Reciprocal Leveling.
Reciprocal levelling:
When it is not possible to locate the leveling instrument in between the inter visible
points, reciprocal leveling is performed. This case appears in case of ponds or rivers etc. in
case of reciprocal leveling, instrument is set nearer to 1st station and sighted towards 2nd
station.
Prepared by- Mr. Abhay Abhale

More Related Content

What's hot

Lec. 11 setting out simple circular curve
Lec. 11 setting out simple circular curveLec. 11 setting out simple circular curve
Lec. 11 setting out simple circular curveAhmed Qasim
 
Levelling in Surveying
Levelling in SurveyingLevelling in Surveying
Levelling in SurveyingPhurba Tamang
 
Computation of area
Computation of areaComputation of area
Computation of areaKavin Raval
 
Classification of triangulation
Classification of triangulationClassification of triangulation
Classification of triangulationFayaz Ahamed A P
 
Fly Levelling
Fly LevellingFly Levelling
Fly LevellingBahzad5
 
Moment Distribution Method
Moment Distribution MethodMoment Distribution Method
Moment Distribution MethodBhavik A Shah
 
Tacheometric surveying ppt
Tacheometric surveying pptTacheometric surveying ppt
Tacheometric surveying pptNaufil Sayyad
 
INTRODUCTION TO SURVEYING
INTRODUCTION TO SURVEYINGINTRODUCTION TO SURVEYING
INTRODUCTION TO SURVEYINGfarhana saiyed
 
Analysis of non sway frame portal frames by slopeand deflection method
Analysis of non sway frame portal frames by slopeand deflection methodAnalysis of non sway frame portal frames by slopeand deflection method
Analysis of non sway frame portal frames by slopeand deflection methodnawalesantosh35
 
Compass survey part 2
Compass survey part 2Compass survey part 2
Compass survey part 2ArunRavi43
 
Trigonometric leveling 02
Trigonometric leveling  02Trigonometric leveling  02
Trigonometric leveling 02Rajesh Rajguru
 
Chapter 3-analysis of statically determinate trusses
Chapter 3-analysis of statically determinate trussesChapter 3-analysis of statically determinate trusses
Chapter 3-analysis of statically determinate trussesISET NABEUL
 
Traverse Survey Part 2/2
Traverse Survey Part 2/2Traverse Survey Part 2/2
Traverse Survey Part 2/2Muhammad Zubair
 
Minor instruments in surveying
Minor instruments in surveyingMinor instruments in surveying
Minor instruments in surveyingShikhar Malhotra
 
Theodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversingTheodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversingDolat Ram
 

What's hot (20)

Lec. 11 setting out simple circular curve
Lec. 11 setting out simple circular curveLec. 11 setting out simple circular curve
Lec. 11 setting out simple circular curve
 
Levelling in Surveying
Levelling in SurveyingLevelling in Surveying
Levelling in Surveying
 
Computation of area
Computation of areaComputation of area
Computation of area
 
Types of level
Types of levelTypes of level
Types of level
 
Classification of triangulation
Classification of triangulationClassification of triangulation
Classification of triangulation
 
Fly Levelling
Fly LevellingFly Levelling
Fly Levelling
 
Moment Distribution Method
Moment Distribution MethodMoment Distribution Method
Moment Distribution Method
 
Tacheometric surveying ppt
Tacheometric surveying pptTacheometric surveying ppt
Tacheometric surveying ppt
 
Curves
CurvesCurves
Curves
 
INTRODUCTION TO SURVEYING
INTRODUCTION TO SURVEYINGINTRODUCTION TO SURVEYING
INTRODUCTION TO SURVEYING
 
Vertical Curves (Part 1)
Vertical Curves (Part 1)Vertical Curves (Part 1)
Vertical Curves (Part 1)
 
Survey 2 curves1
Survey 2 curves1Survey 2 curves1
Survey 2 curves1
 
Curves
CurvesCurves
Curves
 
Analysis of non sway frame portal frames by slopeand deflection method
Analysis of non sway frame portal frames by slopeand deflection methodAnalysis of non sway frame portal frames by slopeand deflection method
Analysis of non sway frame portal frames by slopeand deflection method
 
Compass survey part 2
Compass survey part 2Compass survey part 2
Compass survey part 2
 
Trigonometric leveling 02
Trigonometric leveling  02Trigonometric leveling  02
Trigonometric leveling 02
 
Chapter 3-analysis of statically determinate trusses
Chapter 3-analysis of statically determinate trussesChapter 3-analysis of statically determinate trusses
Chapter 3-analysis of statically determinate trusses
 
Traverse Survey Part 2/2
Traverse Survey Part 2/2Traverse Survey Part 2/2
Traverse Survey Part 2/2
 
Minor instruments in surveying
Minor instruments in surveyingMinor instruments in surveying
Minor instruments in surveying
 
Theodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversingTheodolite traversing, purpose and principles of theodolite traversing
Theodolite traversing, purpose and principles of theodolite traversing
 

Similar to Chapter 4 Levelling

Lecture 11- M4_Level Survey_L1.pdf
Lecture 11- M4_Level Survey_L1.pdfLecture 11- M4_Level Survey_L1.pdf
Lecture 11- M4_Level Survey_L1.pdfPranayaKishoreRaycho
 
Levelling.pptx for civil engineering and b tech
Levelling.pptx for civil engineering and b techLevelling.pptx for civil engineering and b tech
Levelling.pptx for civil engineering and b techAnupamShukla99
 
Leveling surveying
Leveling surveyingLeveling surveying
Leveling surveyingMohammed_82
 
levelling and contouring
 levelling and  contouring levelling and  contouring
levelling and contouringAbdul Majid
 
Leveling, Instruments of Leveling, Bearings (Surveying, ECE)
Leveling, Instruments of Leveling, Bearings (Surveying, ECE) Leveling, Instruments of Leveling, Bearings (Surveying, ECE)
Leveling, Instruments of Leveling, Bearings (Surveying, ECE) Kaushal Mehta
 
Levelling, terms related to levelling, methods of levelling
Levelling, terms related to levelling, methods of levellingLevelling, terms related to levelling, methods of levelling
Levelling, terms related to levelling, methods of levellingMir Zafarullah
 
3_ORDINARY SPIRIT LEVELLING.pptx
3_ORDINARY SPIRIT LEVELLING.pptx3_ORDINARY SPIRIT LEVELLING.pptx
3_ORDINARY SPIRIT LEVELLING.pptxMartin Murimi
 
Basicsofsurveying 090509013902-phpapp01
Basicsofsurveying 090509013902-phpapp01Basicsofsurveying 090509013902-phpapp01
Basicsofsurveying 090509013902-phpapp01Sunilkumar Mandal
 
Basics Of Surveying
Basics Of SurveyingBasics Of Surveying
Basics Of Surveyingstooty s
 
B.sc. agri i foswce unit 2 leveling
B.sc. agri i foswce unit 2 levelingB.sc. agri i foswce unit 2 leveling
B.sc. agri i foswce unit 2 levelingRai University
 
B.sc. agri i foswce unit 2 leveling
B.sc. agri i foswce unit 2 levelingB.sc. agri i foswce unit 2 leveling
B.sc. agri i foswce unit 2 levelingRai University
 
Lecture_3_The Principles of Levelling_fec6a71b84edc28ee2998f7ced9ddf68.pdf
Lecture_3_The Principles of Levelling_fec6a71b84edc28ee2998f7ced9ddf68.pdfLecture_3_The Principles of Levelling_fec6a71b84edc28ee2998f7ced9ddf68.pdf
Lecture_3_The Principles of Levelling_fec6a71b84edc28ee2998f7ced9ddf68.pdfAlwandBarzani
 

Similar to Chapter 4 Levelling (20)

Levelling
LevellingLevelling
Levelling
 
UNIT FOUR.pptx
UNIT FOUR.pptxUNIT FOUR.pptx
UNIT FOUR.pptx
 
Levelling
LevellingLevelling
Levelling
 
Lecture 11- M4_Level Survey_L1.pdf
Lecture 11- M4_Level Survey_L1.pdfLecture 11- M4_Level Survey_L1.pdf
Lecture 11- M4_Level Survey_L1.pdf
 
Levelling
LevellingLevelling
Levelling
 
Levelling.pptx for civil engineering and b tech
Levelling.pptx for civil engineering and b techLevelling.pptx for civil engineering and b tech
Levelling.pptx for civil engineering and b tech
 
Levelling
LevellingLevelling
Levelling
 
Leveling surveying
Leveling surveyingLeveling surveying
Leveling surveying
 
Mohammed kareem
Mohammed kareemMohammed kareem
Mohammed kareem
 
levelling and contouring
 levelling and  contouring levelling and  contouring
levelling and contouring
 
Leveling, Instruments of Leveling, Bearings (Surveying, ECE)
Leveling, Instruments of Leveling, Bearings (Surveying, ECE) Leveling, Instruments of Leveling, Bearings (Surveying, ECE)
Leveling, Instruments of Leveling, Bearings (Surveying, ECE)
 
Module-IV SURVEYING-I [BTCVC304]
Module-IV SURVEYING-I [BTCVC304]Module-IV SURVEYING-I [BTCVC304]
Module-IV SURVEYING-I [BTCVC304]
 
Levelling, terms related to levelling, methods of levelling
Levelling, terms related to levelling, methods of levellingLevelling, terms related to levelling, methods of levelling
Levelling, terms related to levelling, methods of levelling
 
3_ORDINARY SPIRIT LEVELLING.pptx
3_ORDINARY SPIRIT LEVELLING.pptx3_ORDINARY SPIRIT LEVELLING.pptx
3_ORDINARY SPIRIT LEVELLING.pptx
 
Basicsofsurveying 090509013902-phpapp01
Basicsofsurveying 090509013902-phpapp01Basicsofsurveying 090509013902-phpapp01
Basicsofsurveying 090509013902-phpapp01
 
Basics Of Surveying
Basics Of SurveyingBasics Of Surveying
Basics Of Surveying
 
B.sc. agri i foswce unit 2 leveling
B.sc. agri i foswce unit 2 levelingB.sc. agri i foswce unit 2 leveling
B.sc. agri i foswce unit 2 leveling
 
B.sc. agri i foswce unit 2 leveling
B.sc. agri i foswce unit 2 levelingB.sc. agri i foswce unit 2 leveling
B.sc. agri i foswce unit 2 leveling
 
Lecture_3_The Principles of Levelling_fec6a71b84edc28ee2998f7ced9ddf68.pdf
Lecture_3_The Principles of Levelling_fec6a71b84edc28ee2998f7ced9ddf68.pdfLecture_3_The Principles of Levelling_fec6a71b84edc28ee2998f7ced9ddf68.pdf
Lecture_3_The Principles of Levelling_fec6a71b84edc28ee2998f7ced9ddf68.pdf
 
Unit 3
Unit 3Unit 3
Unit 3
 

Recently uploaded

Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . pptDineshKumar4165
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesRAJNEESHKUMAR341697
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueBhangaleSonal
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxJuliansyahHarahap1
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdfKamal Acharya
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdfKamal Acharya
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTbhaskargani46
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxchumtiyababu
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaOmar Fathy
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptNANDHAKUMARA10
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiessarkmank1
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersMairaAshraf6
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptDineshKumar4165
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxSCMS School of Architecture
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...drmkjayanthikannan
 

Recently uploaded (20)

Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
Integrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - NeometrixIntegrated Test Rig For HTFE-25 - Neometrix
Integrated Test Rig For HTFE-25 - Neometrix
 
Double Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torqueDouble Revolving field theory-how the rotor develops torque
Double Revolving field theory-how the rotor develops torque
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Verification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptxVerification of thevenin's theorem for BEEE Lab (1).pptx
Verification of thevenin's theorem for BEEE Lab (1).pptx
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptxS1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
S1S2 B.Arch MGU - HOA1&2 Module 3 -Temple Architecture of Kerala.pptx
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 

Chapter 4 Levelling

  • 1. Unit 4: Levelling Definition of Levelling: Levelling is defined as “an art of determining the relative height of different points on, above or below the surface. Principle of Levelling: The principle of levelling is to obtain horizontal line of sight with respect to which vertical distances of the points above or below this line of sight are found. Prepared by- Mr. Abhay Abhale
  • 2. Unit 4: Levelling Terminologies: Level surfaces, Horizontal and Vertical surfaces, Datum : i. Level surface: It is the surface parallel to the mean spheroidal surface of the earth. The Surface of still water is an example of level surface. ii. Horizontal plane or surface: Horizontal plane through a point is a plane tangential to level surface. iii. Horizontal line: It is a straight line tangential to level line. iv. Datum: Terms used in levelling Datum “It is an arbitrary level surface from which elevation of points may be referred”. In India mean sea level (MSL) is considered as datum of zero elevation it is situated at Karachi. Mean Sea Level is the average height of sea for all stages of tides it is derived by averaging the hourly tide height over a period of 19 years. v. Elevation or Reduced level: It is height or depth of any point above or below any datum. It is denoted as R.L. Prepared by- Mr. Abhay Abhale
  • 3. Unit 4: Levelling Terminologies: Bench Marks- GTS, Permanent, Arbitrary and Temporary Reduced Level: Prepared by- Mr. Abhay Abhale
  • 4. Unit 4: Levelling Terminologies: Bench Marks- GTS, Permanent, Arbitrary and Temporary Reduced Level: Definition of Bench Mark (B.M.) It is a fixed reference point of known elevation with respect to datum. Classification of Bench Mark (B.M.) There are 4 kinds of bench marks a) GTS (Great Trigonometrically survey Bench Mark) b) Permanent bench mark c) Arbitrary bench mark d) Temporary bench mark Prepared by- Mr. Abhay Abhale
  • 5. Unit 4: Levelling Terminologies: Bench Marks- GTS, Permanent, Arbitrary and Temporary Reduced Level: Classification of Bench Mark (B.M.) a) GTS (Great Trigonometrically survey Bench Mark) They are the bench marks established with very high degree of precision at regular intervals by the survey of India Department all over the country. Their position and R.Ls values above mean seal level which was earlier located at Karachi and now it is taken at Bombay High, Mumbai and is given in catalogue formed by the department. b) Permanent bench mark Permanent bench marks are fixed in between GTS benchmarks by govt. agencies such as railways, PWD, etc. This benchmarks are written on permanent objects such as milestones, culverts, bridges etc., their values are clearly written and their position are recorded for future reference. Prepared by- Mr. Abhay Abhale
  • 6. Unit 4: Levelling Terminologies: Bench Marks- GTS, Permanent, Arbitrary and Temporary Reduced Level: c) Arbitrary Bench Marks These are reference points whose R.L.s are arbitrarily assumed. They are used in small works such bench mark may be assumed as 100.000m or 50.000m d) Temporary Bench Marks They are the reference points established during the levelling operations when there is a break in work, or at the end of day’s work the value of reduced levels are marked on some permanent objects such as stones, trees etc. Prepared by- Mr. Abhay Abhale
  • 7. Unit 4: Levelling Terminologies: Rise, Fall, Line of collimation, Station, Back sight, Fore sight, intermediate sight, Change point, Height of instruments: a) Line of collimation: It is a line joining the intersection of cross hairs of diaphragm to the optical centre of object glass and its continuation. It is also known as line of sight. b) Back Sight (B. S.) Back sight It is a staff reading taken at a known elevation. It is the first staff reading taken after setup of instrument. c) Fore Sight (F. S.): Fore sight It is the last staff reading taken denoting the shifting of the instrument. d) Intermediate sight.(I.S.): It is staff reading taken on a point whose elevation is to be determined. All staff reading between B.S. and F.S. are Intermediate sight. e) Change Point (T.P.): It is a point on which both fore and back sight are taken. f) Height of instrument: It is the elevation of line of collimation with respect to datum. Prepared by- Mr. Abhay Abhale
  • 8. Unit 4: Levelling Terminologies: Rise, Fall, Line of collimation, Station, Back sight, Fore sight, intermediate sight, Change point, Height of instruments: a) Line of collimation: b) Back Sight (B. S.) c) Fore Sight (F. S.): d) Intermediate sight.(I.S.): e) Change Point (T.P.): f) Height of instrument: Prepared by- Mr. Abhay Abhale
  • 9. Unit 4: Levelling Types of levels: Dumpy level: The Dumpy level is a simple, compact and stable instrument. The telescope is rigidly fixed to its supports. Hence it cannot be rotated about horizontal axis Prepared by- Mr. Abhay Abhale
  • 10. Unit 4: Levelling Types of levels: Tilting Level: It consists of a telescope attached with a level tube which can be tilted within few degrees in vertical plane by a tilting screw. Prepared by- Mr. Abhay Abhale
  • 11. Unit 4: Levelling Types of levels: Auto Level: It The fundamental difference between automatic and the classic spirit level is that in the former the line of sight is no longer levelled manually using a tubular spirit level, but is levelled automatically within a certain tilt range. This is achieved by compensator in the telescope. Prepared by- Mr. Abhay Abhale
  • 12. Unit 4: Levelling Types of levels: Auto Level: It The fundamental difference between automatic and the classic spirit level is that in the former the line of sight is no longer levelled manually using a tubular spirit level, but is levelled automatically within a certain tilt range. This is achieved by compensator in the telescope. Prepared by- Mr. Abhay Abhale
  • 13. Unit 4: Levelling Types of levels: Components of Dumpy Level and its fundamental axes, Temporary adjustments of Level. Dumpy level consists the following parts or components  Telescope  Longitudinal Bubble tube  Eye piece  Focussing Screw  Vertical spindle  Tribrach screws  Foot screws  Leveling head  Tripod Prepared by- Mr. Abhay Abhale
  • 14. Unit 4: Levelling Types of levels: Components of Dumpy Level and its fundamental axes, Temporary adjustments of Level. Temporary Adjustment of Level 1. Setting up of the level 2. Levelling by foot screws 3. Focussing the eye-piece 4. Focussing the object glass. 1. Setting up of the level The instrument is fixed to the tripod stand using clamp screws. Spread the tripod legs and position the instrument at convenient height. Firstly fix the two legs in the ground at a point and centering of bubble in the bubble tubes is done by adjusting third leg. Prepared by- Mr. Abhay Abhale
  • 15. Unit 4: Levelling Types of levels: Components of Dumpy Level and its fundamental axes, Temporary adjustments of Level. Temporary Adjustment of Level 2. Levelling by foot screws: Levelling is done with the help of foot screws. The purpose of levelling is to make vertical axis truly vertical. It is done with the help of foot screws a) Place the telescope/longitudinal bubble tube parallel to a pair (i. e. any two) of foot screw then hold the foot screws between thumb and first finger and turn them either inward or outward until the longitudinal bubble comes in the centre. b)Turn the telescope through 900 so that it lies parallel to third foot screw, rotate the third foot screw clockwise or anti-clockwise until the bubble comes in the centre. Prepared by- Mr. Abhay Abhale
  • 16. Unit 4: Levelling Types of levels: Components of Dumpy Level and its fundamental axes, Temporary adjustments of Level. Temporary Adjustment of Level 2. Levelling by foot screws: c) Again bring the telescope/longitudinal bubble tube back to original position i. e. parallel to any two foot screws and bring bubble to the centre. d) Now turn the telescope through 900 so that it lies parallel to third foot screw, turn the screw until the bubble comes in the centre. e) Repeat the same procedure three times. Prepared by- Mr. Abhay Abhale
  • 17. Unit 4: Levelling Types of levels: Components of Dumpy Level and its fundamental axes, Temporary adjustments of Level. Temporary Adjustment of Level 3. Focussing the eye-piece: To focus the eye piece, hold a white paper in front of object glass, and (rotate eye piece clockwise or anti-clock wise direction) move the eye piece in or out till the cross hair are clear & distinctly seen. 4. Focusing of object glass: Direct the telescope to the levelling staff and on looking through the telescope, turn the focusing screw in forward or reverse direction till the image appears clear and sharp. Prepared by- Mr. Abhay Abhale
  • 18. Unit 4: Levelling Types of Leveling Staffs: 1. Self-reading staff 2. Target staff. 1. Self-reading staff: The self reading staff can be read directly by the level man looking through the telescope. Common types of self reading staffs 1. Ordinary staff- The one length staff, is solid and made of seasoned wood, it is 3 m long and graduated in the same way as the telescopic staff 2. Sop-with telescopic staff- Such a staff is arranged in three lengths placed one into the other. It can be extended to its full length by pulling. The top portion is solid and the central box is hollow the total length of staff is 4 m. • The staff is graduated in such a way that smallest division is of 5 mm. the value in m are marked in red on the left and those in decimeter are in black on the right. 3. Folding Staff- The folding staff is made up of well seasoned timber such as Cyprus. It consists of two 2 m wooden pieces with a joint assembly. Each piece of the staff is made of one longitudinal strip without any joint. The folding joint is of the detachable type with a locking device at the back. The staff is joined together in such a way that the staff may be folded from one another when required. • The staff has brass cap at the bottom. It has two folding handles, with spring action. It is provided with a circular bubble fitted at the back. Prepared by- Mr. Abhay Abhale
  • 19. Unit 4: Levelling Types of Leveling Staffs: 1. Self-reading staff 1. Self-reading staff: 1. Ordinary staff- 2. Sop-with telescopic staff- 3. Folding Staff- Prepared by- Mr. Abhay Abhale
  • 20. Unit 4: Levelling Types of Leveling Staffs: 2. Target staff- For very precise works and sight target staff are used. A movable target is provided in this staff. • A vernier is provided on target to give precise reading. In target staff level man directs the staff man to move the target up and down until it bisects by the line of sight. The staff man observe the staff reading. Prepared by- Mr. Abhay Abhale
  • 21. Unit 4: Levelling 4.4 Reduction of level by Line of collimation method and Rise/ Fall Method: 4.5 Methods to find the R. L. in Level Book by H.I. Prepared by- Mr. Abhay Abhale
  • 22. Unit 4: Levelling 4.6 Methods: Rise and Fall Methods with necessary checks. ΣB.S. – ƩF.S. = ΣRise – ΣFall = Last R. L. – First R. L. 6.100 – 5.950 = 2.350 – 2.200 = 240.150 – 240.000 0.150 = 0.150 = 0.150Prepared by- Mr. Abhay Abhale
  • 23. Unit 4: Levelling 4.6 Methods: Rise and Fall Methods with necessary checks. Prepared by- Mr. Abhay Abhale
  • 24. Unit 4: Levelling 4.4 Reduction of level by Line of collimation method and Rise/ Fall Method: 4.5 Methods to find the R. L. in Level Book by H.I. 4.6 Methods: Rise and Fall Methods with necessary checks. On Blackboard Prepared by- Mr. Abhay Abhale
  • 25. Unit 4: Levelling 4.7 Leveling Types: Simple, Differential. Simple levelling: It is the simplest method used, when it is required to find the difference in elevation between 2 points. Prepared by- Mr. Abhay Abhale
  • 26. Unit 4: Levelling 4.7 Leveling Types: Simple, Differential. Differential levelling: This method is used to find the difference in the elevation between points if they are too far apart or the difference in elevation between them is too much. It is also called as “Compound Levelling.” Prepared by- Mr. Abhay Abhale
  • 27. Unit 4: Levelling 4.7 Fly, Profile and Reciprocal Leveling. Fly levelling: This Fly levelling is just like differential levelling carried out to check the accuracy of levelling work. In fly levelling only B.S. and F.S. are taken Prepared by- Mr. Abhay Abhale
  • 28. Unit 4: Levelling 4.7 Fly, Profile and Reciprocal Leveling. Fly levelling: This Fly levelling is just like differential levelling carried out to check the accuracy of levelling work. In fly levelling only B.S. and F.S. are taken Prepared by- Mr. Abhay Abhale
  • 29. Unit 4: Levelling 4.7 Fly, Profile and Reciprocal Leveling. Profile levelling or L- section: This method is used for taking levels along the centre line of any alignment like road, railway canal etc. The object is to determine the undulations of the ground surface along the alignment. Prepared by- Mr. Abhay Abhale
  • 30. Unit 4: Levelling 4.7 Fly, Profile and Reciprocal Leveling. Profile levelling or L- section: This method is used for taking levels along the centre line of any alignment like road, railway canal etc. The object is to determine the undulations of the ground surface along the alignment. Prepared by- Mr. Abhay Abhale
  • 31. Unit 4: Levelling 4.7 Fly, Profile and Reciprocal Leveling. Reciprocal levelling: When it is not possible to locate the leveling instrument in between the inter visible points, reciprocal leveling is performed. This case appears in case of ponds or rivers etc. in case of reciprocal leveling, instrument is set nearer to 1st station and sighted towards 2nd station. Prepared by- Mr. Abhay Abhale