BeachSAMP Stakeholder Meeting
December 9th, 2013
Robert W. Fairbanks, P.E., President
Fairbanks Engineering Corp.
Richard N. St. Jean, P.E., President
St. Jean Engineering, LLC
Call Girls in DELHI Cantt, ( Call Me )-8377877756-Female Escort- In Delhi / Ncr
Robert W. Fairbanks and Richard N. St. Jean, Coastal Shoreline Protection Using Hard Structures
1. COASTAL SHORELINE PROTECTION
USING HARD STRUCTURES
Robert W. Fairbanks, P.E., President
Fairbanks Engineering Corp.
Richard N. St. Jean, P.E., President
St. Jean Engineering, LLC
2. TYPES OF SHORELINE PROTECTION
STRUCTURES
• NON STRUCTURAL PROTECTION
• SEAWALLS
• REVETMENT
• BREAKWATERS
• GROINS
3. EXAMPLES OF MANMADE
CHANGES TO THE SHORELINE IN
RHODE ISLAND
USING SEAWALLS, REVETMENTS,
BREAKWATERS AND GROINS
4. Quonset Point War Effort
Quonset Point 1939
Before World War II
Quonset Point Today
5. Allen Harbor, North Kingstown
Allen Harbor Pre World
War II Effort
Allen Harbor Today
6. Quonochontaug Breachway
• 1952 Before State of RI
Constructed Breachway
• 1981 Aerial showing
Breachway Constructed
in 1962, and Sediment
Entering Pond
30. Shoreline Adjacent to SYC Breakwater
North of Breakwater
High Energy as Shown by Rocky Shore
South of Breakwater
High Energy as Shown by Rocky Shore
31. Beach Formed On South Side of SYC Breakwater
Breakwater Acting As a Groin, Trapping Sand
34. Typical Groins Along Lake Michigan
Groins Typically Interrupt & Trap Sand Moving Down the Coast Replenishing
Beaches but Starve Down Shore Beaches Leading to More Aggressive Erosion.
Tee Type Groin
Standard Groin
35. SHORELINE PROTECTION
• These structures have a place
• Many coastal shoreline areas have been protected
adequately by these structures across the country
• Ports require deep water at dock faces
• Ports require protection from waves to allow cargo to
be loaded and unloaded
• Municipalities need to protect infrastructure
• Homeowners need to protect property
– However these structures typically protect the shoreline
better than they protect the structures behind
36. Non Structural Measures Pros:
Environmentally Friendly
Relatively Inexpensive to Construct and Maintain if Vegetative
Blends into Natural Shoreline and Provides Essential Habitat
Typically Does not Cause Erosion of Adjacent Properties
Preferred Method in Low Energy Locations (Coves, Protected Areas)
Easy to Permit
Non Structural Measures Cons:
Ineffective for Large Fetch Areas Where Waves are in Excess of Approx. 2 Feet
Required Frequent Maintenance After Storm Events
Requires a Large Footprint Perpendicular to the Shore
37. Seawalls Pros:
Can Provide Deep Water Adjacent to Quay Walls, Ports Piers
Small Footprint Seaward, Providing Additional Room for Navigation
Excellent Earth Retention with Little to No Loss of Soil Behind Wall When Maintained
When Properly Designed Can Sustain High Surcharge Loads at Piers and Adjacent
Railways
Can Incorporate Cleats, Bollards and Mooring Bits for Docking
Seawall Cons:
Large Wave Reflection Which Can Almost Double the Incoming Wave Height If Wave
Phases Line Up Causing Damage to Marina Facilities
Can Cause Excessive Erosion At Beginning and Ends of Wall
Costly to Construct
Short Life if not Properly Maintained (30 to 50 years)
Possibly Shorter Life if in a Marina Environment Due to Stray Electric Current
Permitted in Only Certain Water Types
38. Breakwater Pros:
Provides Excellent Energy Absorption with Little Wave Reflection
Durable If Properly Designed With Adequate Stone Sizes & Geometry
Provides Fish and Sea Creature Habitat
Long Lasting if Properly Designed with Durable Stones
Ideal for Creating a Refuge Area for Port Facilities and Quiet Water for Pier
Operations
Breakwater Cons:
Very Costly to Construct and Maintain
Upsets Natural Circulation and Sediment Patterns Possibly for Long
Distances
Covers a Large Footprint at the Mud Line
Requires Frequent Dredging At Harbor Entrances and Within Basin
Navigation Hazard if Not Properly Marked
Very Difficult to Permit
39. DESIGN PARAMETERS
• 100 Year (1%) Storm Generated Forces (FEMA)
– Wave Height
– Current Velocity
– Debris Loads
• Water Depth (Bathymetric Survey)
• Shoreline Profile
40. DESIGN WAVE HEIGHT
• FEMA Flood Study & FIRM MAP
• Case By Case Study Considering Unobstructed
Fetch (Partially or Fully Developed Seas) and
Water Depth Approaching Structure Location
Typical Design Parameters for Critical Structures
– 100 yr Return (1%) Stillwater Elevation (SWL)
– 100 yr Return (1%) Maximum Wave Crest Elevation
(May Use a More Frequent Storm Event for Structures
That Can Sustain Some Damage Without Loss of Life,
Can be Readily Repaired, and Small Economic Impact)
41. DESIGN WAVE HEIGHT
• Significant Wave Height, Hs
– Hs = (Max Wave Crest El – SWL) /0.7
• Example for Max Wave Crest El = 12.0 ft & SWL = 9.0 ft
• Hs = 12.0 ft – 9.0 ft/0.7 = 4.28 ft
• Design for H10 = 1.27 Hs
42. EFFECT OF WAVE HEIGHT
• Forces on vertical walls1
– 4 ft wave = 8000 lbs/lf
– 8 ft wave = 16,000 lbs/lf
– 12 ft wave = 24,000 lbs/lf
1 – Coastal Construction Manual, Figure 11-8
43. EFFECT OF WAVE HEIGHT
• Forces & increased wave height at vertical walls
44. EFFECT OF WAVE HEIGHT
• Revetment stone size2
– W = (Wr)(H3)/Kd(Sr – 1)3 (Cotan >)
• Stone size required for 1.5H: 1.0V slope; 2 stone armor layer
–
–
–
–
4 ft wave = 2200 lbs (2.4 ft stone)
8 ft wave= 18,000 lbs (4.8 ft stone)
12 ft wave = 60,000 lbs (7 ft stone)
16 ft wave = 142,000 lbs (9.5 ft stone)
2 – US Army Corps of Engineers, Shore Protection Manual, 1984
45. EFFECT OF WAVE HEIGHT
• Typical breakwater section2
2 – US Army Corps of Engineers, Shore Protection Manual, 1984
46. RI SHORELINE PROJECTS
• Block Island’s Old Harbor Sheetpile Bulkhead
– PZC-34 steel sheets; 41 ft long
– Bulkhead length is 242 lf
– Cost $732,000 or $3,025/lf
47. RI SHORELINE PROJECTS
• Matunuck Beach Road Bulkhead & Revetment,
South Kingstown
– 202 lf of PZ-35 steel sheetpile (45 ft long sheets)
– 202 lf of 11 ton armor stone (2 layers)
– Cost $1,000,000 or $4,950/lf
48. CARRIBEAN SHORELINE PROJECTS
• Tender Pier Anchored Bulkhead
Road Town, Tortola, BVI
– 331 lf of PZ-27 Steel Sheetpile (36 ft long sheets)
– Buried Concrete Deadman w/ Steel Tie-rods
– Cost $1,200,000 or $3,625/lf
49. RI SHORELINE PROJECTS
• Larkin Road Seawall, Watch Hill
– 185 lf of Concrete Seawall (17 ft high)
– 18” -30” thick stem & 9 ft wide footing
– Cost $500,000 or $2,700/lf
50. RI SHORELINE PROJECTS
• Whipple Ave Revetment, Warwick
– 100 lf of stone revetment
– 5000 to 8000 lb stone, 2 stone armor layer
– Cost $25,000 or $250/lf
51. RI SHORELINE PROJECTS
• 75 Surfside Ave, Charlestown
– 150 lf of stone revetment
– 12000 lb stone, 2 stone armor layer
– Cost $150,000 or $1,000/lf
52. RI SHORELINE PROJECTS
• 89 Surfside Ave, Charlestown
– 70 lf of stone revetment
– 12000 lb stone, 2 stone armor layer
– Cost $93,000 or $1,330/lf
53. RI SHORELINE PROJECTS
• Baker Road, Portsmouth
– 90 lf of stone revetment
– 8000 lb stone, 2 stone armor layer
– Estimated Cost $90,000 Or $1,000/lf
54. RI SHORELINE PROJECTS
• Watch Hill Lighthouse Revetment, Watch Hill
– 1,700 lf+- of existing stone revetment repairs
– 20,000 lb stones or larger
– 22 ft design wave heights
– Estimated Cost N/A
55. RI SHORELINE PROJECTS
• Larkin Ave Groin, Watch Hill
– 150 lf+- of existing stone groin repairs
– 3,000 to 4,000 lb stones
– Estimated Cost $25,000+- or $170+-/lf
56. CARRIBEAN SHORELINE PROJECTS
• Tender & Ferry Pier Breakwater
Road Town, Tortola, BVI
– 200 lf stone breakwater
– 6,000 to 8,000 lb stones (2 stone armor layer)
– Estimated Cost $620,000 or $3,100/lf