SlideShare a Scribd company logo
1 of 70
Download to read offline
Refractory failure analysis
-K.P.PRADEEP KUMAR
Refractory failure at
Tip casting area
Castable should be heated
very carefully to control the
steam presure
ACW 1&2 - Picture before bursting
Castable bursted due to
un controlled steam pressure ,
11 hr after initial heat-up
(ACW)
Castable bursted due to
uncontrolled steam pressure . This
was due to 1) rapid heating as the
flame was much shorter . Pilot
burner- oil flame was close to the
outlet and the castable.
2) Oil spilled on the castable and
caused local heating.
Castable bursted
at nose ring area
ACW 1 & 2
It is observed that only castable
blocks at the bottom half got
damaged more.
Castable failure at the tip casting area at ACW
Causes:
(at the time of heating up kiln ,after major lining)
• too short oil flame close to the castable caused
uncontrolled steam pressure resulted in bursting of castable.
• oil spillage on the castable caused local heating
Remedies
• Elongate the flame and push the burner farther inside the kiln so
that radiation Is reduced on the castable.
• Spread clinker nodules on the refractories from tip to 10 M length
• Changed over to andalusite based castable.
APCW
cracks begin , after one month
Operation at the junction of two
monolithic blocks
This crack formation is due to
Inadequate expansion joint after
two months of kiln operation. There
is no wear but observed cracks on the
Surface and deep cracks at the junction
Of two castings.
APCW
Castable failure after 4 months operation
due to inadequate expansion joint and
Thermal shocks
APCW
Castable failure due to
Inadequate expansion joint causes
deep crack formation and spalling
after 4 months of operation.
APCW
Deep penetration of clinker liquid
Into the brick.
One monolithic casting has crossed
to the other casting and the blocks expanded
taking the casting along with, which
ended in spalling.There should be
a clear expansion joint of 10 mm between
the blocks.
APCW
Remedies
• Tip casting plates( with male and female joint) have been modified to
straight blocks .
• Castable was changed from andalusite based to
Corundum based to withstand abrasion.
• Expansion gap was increased from 5 mm 15 mm with ceramic
boards
Refractory failure on the tip casting at APCW
Causes
• Thermal shocks
• Cracking due to inadequate expansion joint . ( expansion joint closed
during vibration) Very often it is observed that the expansion gap
between the castings are filled with Castable.
This L –joint
will not allow
to give expansion
joint properlly
( overlapping due
to male
and female joint
Before modification
This straight expansion joint
allows proper expansion.
After
modification
Castable on the modified blocks APCW
Expansion joint is straight in the
Modified castings.
Tip casting blocks are not in line
This V-joint will make make the brick
ring mis aligned. The suppliers engrave the
letters on the castings on the collar which makes point contact
with the bricks. It can be engraved on the on the hot face side.
Dimension tolerance must not deviate from limit specified by OEM.
AC kiln
Tip casting
Retainer ring
a
b
c
d
e
a
b
c
d
e
Tip casting Retainer ring
A=b=c=d=e and so on a,<b =c < d=> e
Installation of castings at the kiln tip area.
Casting’s periphery at its base side must be in line.
.
.
Nose ring Blocks
Suppliers must be advised not to engrave the letters on the base
and the collar where bricks have contact with castings.
Letters can be engraved on the hot face of
the castings
Bolts must never be
protruded .This acts
like a pivot and castings
will not have contact with
the bricks. Casting must
have machined surface
and the blurs must be
ground to get fine surface
on the castings..
Engraved letters and blurs can create
point contact between the bricks and the
castings which will pinch the brick surface
and causes refractory failure at the tip.
Ensure 100 % contact between
The brick and the castings
Nose ring castings
Engraved letters and blurs can create
point contact between the bricks and the
castings which will pinch the brick surface
and causes refractory failure at the tip.
Ensure 100 % contact between
The brick and the castings
Nose ring castings
HA-70 bricks twisted at 47 m
Castings got oxidised
as well as corroded
V-joint gap due to bell mouth
Or casting got sunk. If casting
face is not smooth it can create
this gap. This need a machined
Surface. Point contact is not
acceptable. Letters engraved on the
face can also create gap because
of point contact.
AC
Bell mouth formation at
Kiln outlet
AC
Casting are oxidised too
After 3 months of operation
Thinned down to almost half.
This V gap formation is due to
bell mouth formation.
AC
AC
Bricks got crushed
The bricks on the retainer
ring were pushed by
20 – 30 mm. That time
the kiln had severe
Upset run. Huge variation
in chemistry , due to
Low silo level and flux
variation due to wetness
of red ochre.
0 –1.2 M area
The bricks are crushed
Due to excessive thrust.
Bell mouth formation is also there.
VC-3 Kiln
The castings are oxidized as well as corroded
after 3 months of operation. When we fire pet coke Nickel/ chromium Ratio needs
change .Also found that there is wear though the hard face welding is done. High
Efficiency cooler increases the secondary temperature and may burn the castings .
The dust erosion and clinker falling on the Castings can also increase the wear .Nose
ring cooling must be enhanced. Cooling air volume =400 Cum/min , and velocity
of air at nozzle t >45 M/s and the no.of nozzles , minimum is 6.
RC-3 Kiln
The gap created must be due to bell
mouth Formation or nose ring castings
got sunk because of intolerable heat.
Nose ring cooling must be enhanced
RC3 Kiln
Out let blocks are cracked
Due to over heating after the
Installation of high efficiency
Static grates cooler.
GS Kiln
Now the hot face is covered by
Castble.The life has increased to
more than one year.
GS Kiln
Nose ring cooling
For kiln Dia < 4.0 M,
cooling air volume 400 cum/min
For kiln dia > 4.0 M,
cooling air volume 500 cu m/ min
Nozzle velocity = 40 – 45 m/s
Minimum no.of nozzles =6
< 1.5 M
0 –2.2 M
VC-3 Kiln
2 nd row after tip casting
Unstable coating due to high sulfur recycle variation
Low alumina modulus. High liquid forms the coating upto
the tip. Sufur volatile factor some times reach > 3.5 and
Varied from 2 to 3.5.Petcoke sulfur exceeds 7.5%.
Refractory failures at the tip casting
in AC and VC
Causes
• bell mouth formation
• Casting loose their mechanical stability due to corrosion and
oxidised
• Insufficient cooling of nose ring
• Frequent ring formation and doslodgement at the tip and
consequent thermal shocks
• High liquid content and variation in clinker liquid quality due to
variation in sulfur cycle.Often it crossed > 3.0 .
Remedies
• change the outlet shell
• Improve the nose ring cooling air volume and cooling nozzle velocity
• Control the chemistry and sulfur cycle.
• Nickel / Chromium has to be adjusted as Nickel is vulnerable to sulfur
attack and chromium to alkali attack.
This is due to bell mouth formation.
Even the spinel bricks had failed. Mortar
application is must to have more flexibility.
VC-3 Kiln
0 –2.0 M
Bricks on the retainer ring
got crushed
VC-3 Kiln
Even the bricks on the retainer ring
got shifted due to excessive axial thrust
Sudden increase in temperature on brick surface
Due to coating collapse. kiln had severe upset run
When this failure occurred.
AC kiln
Refractory failure at retainer ring area in AC and VC.
Causes
• instability of coating in this area due to change in chemistry and variation in sulfur
cycle because of petcoke firing
• Excessive axial thrust due to higher vrpm
• Flame needs tuning
• Rhino horn formation on burner tip distorts the flame.
Remedies
• Variation in chemistry needs control
• Higher grade spinel bricks will improve the life
• flame should be shaped to short , convergent and hot flame.
• Install shock blasters to dislodge the Rhino horn on the burner tip.
30 % of the brick is penetrated .
Aggressive liquid attack on brick ( 33 % liquid in
clinker)
These cracks show that the bricks
undergone severe thermo-mechanical
Stresses.
APCW
Location : 1st row after tip casting block.
The gap between the castings is much higher
than the OEM specifications.
Deep penetration of liquid into the bricks
Theses crack show that there is severe stresses on
the bricks Thermo-mechanical as well as thermo chemical
( bell mouth formation and aggressive liquid attack on the brick)
APCW
Refractory failure at kiln outlet – APCW
Causes;
• Too high liquid % which penetrate deep into even the spinel bricks and
degenerate spinels and destruct the bricks. Coating is also unstable
• Bell mouth formation causes thermo-mechanical stresses
• Casting are not in line as their dimensions have deviation than the
tolerance limits than specified by OEM.
• axial thrust
Remedies
• Optimize the liquid to reduce coating
• Castings must have tolerance limit as recommended by OEM
• Change the outlet cone shell to straight shell to reduce the axial thrust with
• installation of conical retainer rings of Magattoux.
GCW
Even the spinel bricks had been
Impenetrated by aggressive liquid
Degenerate the spinels . The bricks
losses Its strength.
GCW
GCW
GCW
GCW
Hasle D-59 A castable
Bricks are twisted
and crushed due to
high axial thrust
GCW-1
If bricks are attacked by
aggressive liquid they are
vulnerable to any stresses
Failed area
adjacent to retainer ring
GCW-1
Shell surface is rough
We have to apply mortar
Underneath the bricks .to have
full contact with the shell
and cold face of the brick.
GCW-1
GCW-1
The spinel bricks are crushed
and destructed
up to half of the brick thickness is
attacked by aggressive liquid attack.
GCW-1
Deep melt infiltration inside
The brick. The bricks had undergone
Very high thermo- chemical
And thermo mechanical load.
Almost 50 % brick is attacked by liquid
Which can destroy the ingrediants of the
brick . This is a hercynite Spinel brick , Ankral Z1.
GCW-1
Huge cracks show
the bricks undergone
Severer thermo-mechanical
stresses. The Thermochemical attack
on the bricks make more vulnerable
for thermo-mechanical stresses
GCW
Refractory failure at kiln outlet – GCW
Remedies
• High grade spinel bricks which only increases the life by giving
resistance to aggressive liquid attack. Variation in quartz has to be
reduced.
• Replacement of conical shell to straight shell to reduce axial thrust.
Conical retainer ring is the second option to arrest the thrust.
• Live ring migration at first tyre must not be more than
12mm/revolution.Proper shimming has to be done accordingly.
• Surge hopper has to be installed to collect the bag house dust to reduce
chemistry variation in kiln feed.
Causes
Very high burning zone temperature due to presence of quartz and to maintain
free lime < 1.1 %. The liquid has less viscosity and penetrate the bricks deep.
changes in chemistry when raw meal stops , variation in kiln feed LSF by 2-4
Flame gets distorted often due to rhino-horn formation on burner tip
very high variation in I tyre migration due to coating instability , ie 0 mm to 30 mm
Refractory failure at
retainer ring area - APCW
and GCW kiln
APCW Bricks got crushed at the
retainer ring
Bricks at the retainer ring got
Crushed due to excessive axial
thrust. Very high thermo-chemical
Stresses on the bricks. Liquid
had deep penetration and destructed
the spinels and The texture.of the bricks.
Crushing of the bricks
APCW
Bricks crushed at the
Retainer ring
Refractory failure at kiln outlet and near
the retainer ring – APCW and GCW.
Reasons
Frequent coating failure due chemistry variation
Too high liquid % in clinker ie.,33%
Flame and reduced conditions
Severe thermal shocks due to coating dislodgement which takes away
part of the bricks.
Remedies
Optimise the liquid
Change over to high grade spinel bricks like Almag AF or Ankral R1
Due to dusty conditions flame gets disturbed and reduced conditions
prevail . This causes the coating very unstable and causing thermal
Shocks.
Too many retainer rings are unneceassry
They act like stiffeners and when kiln shell gets
Heated up this will, shear the shell . 75 mm thick
Retainer ring is tougher than kiln shell. Therer are
4 rows of Magattoux retainer rings from 1.2 – 1.8 Meter ,
double retainer ring at 1 M
and Single retainer ring.at 0.4 M
Shell is warped at many places
Bricks are under stress
Alumina bricks is a not good selection
The conical retainer ring are meant for
Spinel bricks
HCW
Bricks have cracks
Shows that bricks are under
Thermo mechanical stress.
First row bricks are totally crushed
and washed out. The castable also
got dislodged as the brick ring moved
and created axial thrust on the castable
too. The second and other rings
moved forward by 45 mm.
Shell crack axial
Retainer ring surface is wavy
Retainer ring is burnt.
Shell crack ,
Retainer ring crack
Shell crack
crack on
retainer
Conical retainer ring of
RHI & Magattoux
Surface is wavy
Castable casted on
the tipcasting face ,done
at site
First retainer ring warped. This makes the
bricks twisting .
As the shell is having wavy surface the conical retainer ring
donot have contact surface with bricks and hence bricks
need cutting at the bottom by 12- 18 mm in many places and
mortar application underneath the bricks to fill up the gaps.
Mortar application is done at radial joints too.
After conical rings no extra
retainer ring is needed
Refractory failure at retainer ring area HCW
Remedies
Damaged outlet shell is to be replaced by new shell
Spinel bricks will be used on the conical retainer ring instead of High
alumina bricks to have better locking and arching which avoids shifting.
Retainer ring must have smooth surface and have the same curvature
of kiln.
After conical retainer ring no retainer ring is needed as recommended
by refractory suppliers
Causes
wrong selection of bricks
too may retainer rings
shell surface is wavy and warped also.
conical retainer rings are not fixed properly as it is observed that it falls at
12 O’ clock position while rotating the kiln
Thanks a lot
PRADEEP KUMAR

More Related Content

What's hot

Installation of Refractory Materials in Rotary Kilns ”Essential principles"
Installation of Refractory Materials in Rotary Kilns ”Essential principles"Installation of Refractory Materials in Rotary Kilns ”Essential principles"
Installation of Refractory Materials in Rotary Kilns ”Essential principles"Refratechnik Group
 
ENERGY MODELING OF THE PYROPROCESSING OF CLINKER IN A ROTARY CEMENT KILN
ENERGY MODELING OF THE PYROPROCESSING OF CLINKER IN A ROTARY CEMENT KILNENERGY MODELING OF THE PYROPROCESSING OF CLINKER IN A ROTARY CEMENT KILN
ENERGY MODELING OF THE PYROPROCESSING OF CLINKER IN A ROTARY CEMENT KILNISA Interchange
 
Sulphur spurrite-and-rings-in-cement-kilns-pdf
Sulphur spurrite-and-rings-in-cement-kilns-pdfSulphur spurrite-and-rings-in-cement-kilns-pdf
Sulphur spurrite-and-rings-in-cement-kilns-pdfmkpq pasha
 
Cement rotary kiln
Cement rotary kilnCement rotary kiln
Cement rotary kilnmkpq pasha
 
Microsoft power point dip tube failure
Microsoft power point   dip tube failureMicrosoft power point   dip tube failure
Microsoft power point dip tube failurepradeepdeepi
 
Sulfur formation
Sulfur formationSulfur formation
Sulfur formationmkpq pasha
 
Kiln Shell Corrosion
Kiln Shell CorrosionKiln Shell Corrosion
Kiln Shell CorrosionRicardoMosci
 
Rotary kiln handbook_new
Rotary kiln handbook_newRotary kiln handbook_new
Rotary kiln handbook_newRadiGohar1
 
Petcoke for jsw. pradeep
Petcoke for jsw. pradeepPetcoke for jsw. pradeep
Petcoke for jsw. pradeeppradeepdeepi
 
54666070 kiln-operation
54666070 kiln-operation54666070 kiln-operation
54666070 kiln-operationDin Sokreach
 
Cementformulae handbook v2
Cementformulae handbook v2Cementformulae handbook v2
Cementformulae handbook v2cesar hernandez
 
How to control kiln shell corrosion
How to control kiln shell corrosionHow to control kiln shell corrosion
How to control kiln shell corrosionAnkit Karwa
 
Use of diverting_gatesfor_kiln_preheater (1)
Use of diverting_gatesfor_kiln_preheater (1)Use of diverting_gatesfor_kiln_preheater (1)
Use of diverting_gatesfor_kiln_preheater (1)pradeepdeepi
 
Snow ball formation pradeep kumar
Snow ball formation  pradeep kumarSnow ball formation  pradeep kumar
Snow ball formation pradeep kumarpradeepdeepi
 
Red river in clinker cooler
Red river in clinker  coolerRed river in clinker  cooler
Red river in clinker coolerpradeepdeepi
 
Ln clinker cooler golden rules 2010 11 17
Ln clinker cooler golden rules 2010 11 17Ln clinker cooler golden rules 2010 11 17
Ln clinker cooler golden rules 2010 11 17mkpq pasha
 
Snowman formation pradeep kumar
Snowman formation pradeep kumarSnowman formation pradeep kumar
Snowman formation pradeep kumarpradeepdeepi
 

What's hot (20)

Installation of Refractory Materials in Rotary Kilns ”Essential principles"
Installation of Refractory Materials in Rotary Kilns ”Essential principles"Installation of Refractory Materials in Rotary Kilns ”Essential principles"
Installation of Refractory Materials in Rotary Kilns ”Essential principles"
 
ENERGY MODELING OF THE PYROPROCESSING OF CLINKER IN A ROTARY CEMENT KILN
ENERGY MODELING OF THE PYROPROCESSING OF CLINKER IN A ROTARY CEMENT KILNENERGY MODELING OF THE PYROPROCESSING OF CLINKER IN A ROTARY CEMENT KILN
ENERGY MODELING OF THE PYROPROCESSING OF CLINKER IN A ROTARY CEMENT KILN
 
Sulphur spurrite-and-rings-in-cement-kilns-pdf
Sulphur spurrite-and-rings-in-cement-kilns-pdfSulphur spurrite-and-rings-in-cement-kilns-pdf
Sulphur spurrite-and-rings-in-cement-kilns-pdf
 
Cement rotary kiln
Cement rotary kilnCement rotary kiln
Cement rotary kiln
 
Microsoft power point dip tube failure
Microsoft power point   dip tube failureMicrosoft power point   dip tube failure
Microsoft power point dip tube failure
 
Sulfur formation
Sulfur formationSulfur formation
Sulfur formation
 
Kiln Shell Corrosion
Kiln Shell CorrosionKiln Shell Corrosion
Kiln Shell Corrosion
 
Rotary kiln handbook_new
Rotary kiln handbook_newRotary kiln handbook_new
Rotary kiln handbook_new
 
Petcoke for jsw. pradeep
Petcoke for jsw. pradeepPetcoke for jsw. pradeep
Petcoke for jsw. pradeep
 
54666070 kiln-operation
54666070 kiln-operation54666070 kiln-operation
54666070 kiln-operation
 
Cementformulae handbook v2
Cementformulae handbook v2Cementformulae handbook v2
Cementformulae handbook v2
 
How to control kiln shell corrosion
How to control kiln shell corrosionHow to control kiln shell corrosion
How to control kiln shell corrosion
 
Use of diverting_gatesfor_kiln_preheater (1)
Use of diverting_gatesfor_kiln_preheater (1)Use of diverting_gatesfor_kiln_preheater (1)
Use of diverting_gatesfor_kiln_preheater (1)
 
Snow ball formation pradeep kumar
Snow ball formation  pradeep kumarSnow ball formation  pradeep kumar
Snow ball formation pradeep kumar
 
Red river in clinker cooler
Red river in clinker  coolerRed river in clinker  cooler
Red river in clinker cooler
 
Ln clinker cooler golden rules 2010 11 17
Ln clinker cooler golden rules 2010 11 17Ln clinker cooler golden rules 2010 11 17
Ln clinker cooler golden rules 2010 11 17
 
Rotary Kiln Sizing & Design
Rotary Kiln Sizing & DesignRotary Kiln Sizing & Design
Rotary Kiln Sizing & Design
 
Kiln training
Kiln trainingKiln training
Kiln training
 
Rotary kiln
Rotary kilnRotary kiln
Rotary kiln
 
Snowman formation pradeep kumar
Snowman formation pradeep kumarSnowman formation pradeep kumar
Snowman formation pradeep kumar
 

Viewers also liked

Ring formation in kilns
Ring formation in kilnsRing formation in kilns
Ring formation in kilnspradeepdeepi
 
Bag filter operation pradeep kumar
Bag filter operation pradeep kumarBag filter operation pradeep kumar
Bag filter operation pradeep kumarpradeepdeepi
 
Refractory manufcturing,properties
Refractory  manufcturing,propertiesRefractory  manufcturing,properties
Refractory manufcturing,propertiespradeepdeepi
 
Cement raw mix characteristics
Cement raw mix characteristicsCement raw mix characteristics
Cement raw mix characteristicspradeepdeepi
 
Influence of process on quality
Influence of process on qualityInfluence of process on quality
Influence of process on qualitypradeepdeepi
 
Raw mix characteristics final
Raw mix characteristics  finalRaw mix characteristics  final
Raw mix characteristics finalpradeepdeepi
 
Bag filter operation pradeep kumar
Bag filter operation  pradeep kumarBag filter operation  pradeep kumar
Bag filter operation pradeep kumarpradeepdeepi
 
Vertical raw mill pradeep kumar
Vertical raw mill pradeep kumarVertical raw mill pradeep kumar
Vertical raw mill pradeep kumarpradeepdeepi
 
Molykote® Greases in action in India, email sales@projectsalescorp.com
Molykote® Greases in action in India, email sales@projectsalescorp.comMolykote® Greases in action in India, email sales@projectsalescorp.com
Molykote® Greases in action in India, email sales@projectsalescorp.comProject Sales Corp
 
Engineered Ferrules for High Temperature Waste Heat Boilers from Blasch Preci...
Engineered Ferrules for High Temperature Waste Heat Boilers from Blasch Preci...Engineered Ferrules for High Temperature Waste Heat Boilers from Blasch Preci...
Engineered Ferrules for High Temperature Waste Heat Boilers from Blasch Preci...Blasch Precision Ceramics
 
Ladle &amp; tundish dryers & preheaters
Ladle &amp; tundish dryers & preheatersLadle &amp; tundish dryers & preheaters
Ladle &amp; tundish dryers & preheatersStelter & Brinck
 
TFL Precast Refractory Shapes
TFL Precast Refractory ShapesTFL Precast Refractory Shapes
TFL Precast Refractory ShapesPaul Fisher
 
Teide Group presentacion
Teide Group presentacionTeide Group presentacion
Teide Group presentacioncmazorra
 
Foundry Products (Ideal Foundry
Foundry Products (Ideal FoundryFoundry Products (Ideal Foundry
Foundry Products (Ideal FoundryAlper Dayıoğlu
 
Anchoring of monolithic_refractories_-_uk
Anchoring of monolithic_refractories_-_ukAnchoring of monolithic_refractories_-_uk
Anchoring of monolithic_refractories_-_ukMandeep Singh
 

Viewers also liked (16)

Ring formation in kilns
Ring formation in kilnsRing formation in kilns
Ring formation in kilns
 
Bag filter operation pradeep kumar
Bag filter operation pradeep kumarBag filter operation pradeep kumar
Bag filter operation pradeep kumar
 
Refractory manufcturing,properties
Refractory  manufcturing,propertiesRefractory  manufcturing,properties
Refractory manufcturing,properties
 
Cement raw mix characteristics
Cement raw mix characteristicsCement raw mix characteristics
Cement raw mix characteristics
 
Influence of process on quality
Influence of process on qualityInfluence of process on quality
Influence of process on quality
 
Raw mix characteristics final
Raw mix characteristics  finalRaw mix characteristics  final
Raw mix characteristics final
 
Bag filter operation pradeep kumar
Bag filter operation  pradeep kumarBag filter operation  pradeep kumar
Bag filter operation pradeep kumar
 
Vertical raw mill pradeep kumar
Vertical raw mill pradeep kumarVertical raw mill pradeep kumar
Vertical raw mill pradeep kumar
 
Molykote® Greases in action in India, email sales@projectsalescorp.com
Molykote® Greases in action in India, email sales@projectsalescorp.comMolykote® Greases in action in India, email sales@projectsalescorp.com
Molykote® Greases in action in India, email sales@projectsalescorp.com
 
Engineered Ferrules for High Temperature Waste Heat Boilers from Blasch Preci...
Engineered Ferrules for High Temperature Waste Heat Boilers from Blasch Preci...Engineered Ferrules for High Temperature Waste Heat Boilers from Blasch Preci...
Engineered Ferrules for High Temperature Waste Heat Boilers from Blasch Preci...
 
Ladle &amp; tundish dryers & preheaters
Ladle &amp; tundish dryers & preheatersLadle &amp; tundish dryers & preheaters
Ladle &amp; tundish dryers & preheaters
 
Air heater
Air heaterAir heater
Air heater
 
TFL Precast Refractory Shapes
TFL Precast Refractory ShapesTFL Precast Refractory Shapes
TFL Precast Refractory Shapes
 
Teide Group presentacion
Teide Group presentacionTeide Group presentacion
Teide Group presentacion
 
Foundry Products (Ideal Foundry
Foundry Products (Ideal FoundryFoundry Products (Ideal Foundry
Foundry Products (Ideal Foundry
 
Anchoring of monolithic_refractories_-_uk
Anchoring of monolithic_refractories_-_ukAnchoring of monolithic_refractories_-_uk
Anchoring of monolithic_refractories_-_uk
 

Similar to Ref failur e analysis tip casting & retainer area f

Frequently Asked Questions on TURBINE Part 3
Frequently Asked Questions on TURBINE Part 3Frequently Asked Questions on TURBINE Part 3
Frequently Asked Questions on TURBINE Part 3Manohar Tatwawadi
 
Industrial coating options for circulating fluidized bed boilers
Industrial coating options for circulating fluidized bed boilersIndustrial coating options for circulating fluidized bed boilers
Industrial coating options for circulating fluidized bed boilersTeknokraft
 
PPT ON CIM ,BHEL HARIDWAR
PPT ON CIM ,BHEL HARIDWARPPT ON CIM ,BHEL HARIDWAR
PPT ON CIM ,BHEL HARIDWARABHISHEK SINGH
 
Recognizing and Eliminating Flux Concentrator Failures
Recognizing and Eliminating Flux Concentrator FailuresRecognizing and Eliminating Flux Concentrator Failures
Recognizing and Eliminating Flux Concentrator FailuresFluxtrol Inc.
 
Tube-to-Tube-Sheet.ppt
Tube-to-Tube-Sheet.pptTube-to-Tube-Sheet.ppt
Tube-to-Tube-Sheet.pptssuserea7ebc
 
120CR0393_Subrat Kumar Gaana_Seminar and Technical Writing.pptx
120CR0393_Subrat Kumar Gaana_Seminar and Technical Writing.pptx120CR0393_Subrat Kumar Gaana_Seminar and Technical Writing.pptx
120CR0393_Subrat Kumar Gaana_Seminar and Technical Writing.pptxSubrat Kumar Gaana
 
Failure in synthesis converter
Failure in synthesis converterFailure in synthesis converter
Failure in synthesis converterPrem Baboo
 
Taphole clay for blast furnace operation
Taphole clay for blast furnace operationTaphole clay for blast furnace operation
Taphole clay for blast furnace operationHarvey Yang
 
Blast furnace-Inconsistent blowing and its effects
Blast furnace-Inconsistent blowing and its effectsBlast furnace-Inconsistent blowing and its effects
Blast furnace-Inconsistent blowing and its effectsAnil Mistry
 
Er. rahul sharma circuit breaker
Er. rahul sharma circuit breakerEr. rahul sharma circuit breaker
Er. rahul sharma circuit breakerRahul Ruddra
 
Critical observations during a shut down audit of a pf boiler final
Critical observations during a shut down audit of a pf boiler  finalCritical observations during a shut down audit of a pf boiler  final
Critical observations during a shut down audit of a pf boiler finalparthi2006
 
Basic principles of_ tube_expanding
Basic principles of_ tube_expandingBasic principles of_ tube_expanding
Basic principles of_ tube_expandingUjwal Joshi
 
Methanol Synthesis Loop Troubleshooting
Methanol Synthesis Loop TroubleshootingMethanol Synthesis Loop Troubleshooting
Methanol Synthesis Loop TroubleshootingGerard B. Hawkins
 
Wingwall sh distortion in cfbc boilers by k.k.parthiban jan 2018
Wingwall sh distortion in cfbc boilers by k.k.parthiban jan 2018Wingwall sh distortion in cfbc boilers by k.k.parthiban jan 2018
Wingwall sh distortion in cfbc boilers by k.k.parthiban jan 2018parthi2006
 
Lecture 2.pptx
Lecture 2.pptxLecture 2.pptx
Lecture 2.pptxChandraV13
 

Similar to Ref failur e analysis tip casting & retainer area f (20)

Frequently Asked Questions on TURBINE Part 3
Frequently Asked Questions on TURBINE Part 3Frequently Asked Questions on TURBINE Part 3
Frequently Asked Questions on TURBINE Part 3
 
Thermoplastic Liners
Thermoplastic LinersThermoplastic Liners
Thermoplastic Liners
 
Industrial coating options for circulating fluidized bed boilers
Industrial coating options for circulating fluidized bed boilersIndustrial coating options for circulating fluidized bed boilers
Industrial coating options for circulating fluidized bed boilers
 
PPT ON CIM ,BHEL HARIDWAR
PPT ON CIM ,BHEL HARIDWARPPT ON CIM ,BHEL HARIDWAR
PPT ON CIM ,BHEL HARIDWAR
 
Recognizing and Eliminating Flux Concentrator Failures
Recognizing and Eliminating Flux Concentrator FailuresRecognizing and Eliminating Flux Concentrator Failures
Recognizing and Eliminating Flux Concentrator Failures
 
Tube-to-Tube-Sheet.ppt
Tube-to-Tube-Sheet.pptTube-to-Tube-Sheet.ppt
Tube-to-Tube-Sheet.ppt
 
120CR0393_Subrat Kumar Gaana_Seminar and Technical Writing.pptx
120CR0393_Subrat Kumar Gaana_Seminar and Technical Writing.pptx120CR0393_Subrat Kumar Gaana_Seminar and Technical Writing.pptx
120CR0393_Subrat Kumar Gaana_Seminar and Technical Writing.pptx
 
Failure in synthesis converter
Failure in synthesis converterFailure in synthesis converter
Failure in synthesis converter
 
Taphole clay for blast furnace operation
Taphole clay for blast furnace operationTaphole clay for blast furnace operation
Taphole clay for blast furnace operation
 
Blast furnace-Inconsistent blowing and its effects
Blast furnace-Inconsistent blowing and its effectsBlast furnace-Inconsistent blowing and its effects
Blast furnace-Inconsistent blowing and its effects
 
Er. rahul sharma circuit breaker
Er. rahul sharma circuit breakerEr. rahul sharma circuit breaker
Er. rahul sharma circuit breaker
 
Critical observations during a shut down audit of a pf boiler final
Critical observations during a shut down audit of a pf boiler  finalCritical observations during a shut down audit of a pf boiler  final
Critical observations during a shut down audit of a pf boiler final
 
Basic principles of_ tube_expanding
Basic principles of_ tube_expandingBasic principles of_ tube_expanding
Basic principles of_ tube_expanding
 
Methanol Synthesis Loop Troubleshooting
Methanol Synthesis Loop TroubleshootingMethanol Synthesis Loop Troubleshooting
Methanol Synthesis Loop Troubleshooting
 
Final ppt
Final pptFinal ppt
Final ppt
 
Case Studies on CFBC Boilers
Case Studies on CFBC BoilersCase Studies on CFBC Boilers
Case Studies on CFBC Boilers
 
Wingwall sh distortion in cfbc boilers by k.k.parthiban jan 2018
Wingwall sh distortion in cfbc boilers by k.k.parthiban jan 2018Wingwall sh distortion in cfbc boilers by k.k.parthiban jan 2018
Wingwall sh distortion in cfbc boilers by k.k.parthiban jan 2018
 
Cylinder head
Cylinder headCylinder head
Cylinder head
 
Lecture 2.pptx
Lecture 2.pptxLecture 2.pptx
Lecture 2.pptx
 
Casting defects
Casting defectsCasting defects
Casting defects
 

More from pradeepdeepi

Influence of process on quality
Influence of process on qualityInfluence of process on quality
Influence of process on qualitypradeepdeepi
 
Process for non process1
Process for non process1Process for non process1
Process for non process1pradeepdeepi
 
Anchor design-pradeep kumar
Anchor design-pradeep kumarAnchor design-pradeep kumar
Anchor design-pradeep kumarpradeepdeepi
 
Lump formation in cement silo
Lump formation in  cement siloLump formation in  cement silo
Lump formation in cement silopradeepdeepi
 
Lump formation in cement silo
Lump formation in  cement siloLump formation in  cement silo
Lump formation in cement silopradeepdeepi
 
Lump formation in cement silo
Lump formation in  cement siloLump formation in  cement silo
Lump formation in cement silopradeepdeepi
 
Microsoft power point bag house corrosion
Microsoft power point   bag house corrosionMicrosoft power point   bag house corrosion
Microsoft power point bag house corrosionpradeepdeepi
 

More from pradeepdeepi (9)

Influence of process on quality
Influence of process on qualityInfluence of process on quality
Influence of process on quality
 
Process for non process1
Process for non process1Process for non process1
Process for non process1
 
Anchor design-pradeep kumar
Anchor design-pradeep kumarAnchor design-pradeep kumar
Anchor design-pradeep kumar
 
Lump formation in cement silo
Lump formation in  cement siloLump formation in  cement silo
Lump formation in cement silo
 
Lump formation in cement silo
Lump formation in  cement siloLump formation in  cement silo
Lump formation in cement silo
 
Lump formation in cement silo
Lump formation in  cement siloLump formation in  cement silo
Lump formation in cement silo
 
Anchor design
Anchor designAnchor design
Anchor design
 
Anchor design
Anchor designAnchor design
Anchor design
 
Microsoft power point bag house corrosion
Microsoft power point   bag house corrosionMicrosoft power point   bag house corrosion
Microsoft power point bag house corrosion
 

Recently uploaded

Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...amitlee9823
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...Aggregage
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataExhibitors Data
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsP&CO
 
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...Anamikakaur10
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting
 
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceEluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceDamini Dixit
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1kcpayne
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...rajveerescorts2022
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptxnandhinijagan9867
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noidadlhescort
 
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...lizamodels9
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...daisycvs
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...amitlee9823
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with CultureSeta Wicaksana
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwaitdaisycvs
 
Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel
 
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000dlhescort
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 

Recently uploaded (20)

Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
Nelamangala Call Girls: 🍓 7737669865 🍓 High Profile Model Escorts | Bangalore...
 
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
The Path to Product Excellence: Avoiding Common Pitfalls and Enhancing Commun...
 
RSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors DataRSA Conference Exhibitor List 2024 - Exhibitors Data
RSA Conference Exhibitor List 2024 - Exhibitors Data
 
Value Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and painsValue Proposition canvas- Customer needs and pains
Value Proposition canvas- Customer needs and pains
 
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
Call Now ☎️🔝 9332606886🔝 Call Girls ❤ Service In Bhilwara Female Escorts Serv...
 
Falcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investorsFalcon Invoice Discounting: The best investment platform in india for investors
Falcon Invoice Discounting: The best investment platform in india for investors
 
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort ServiceEluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
Eluru Call Girls Service ☎ ️93326-06886 ❤️‍🔥 Enjoy 24/7 Escort Service
 
Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1Katrina Personal Brand Project and portfolio 1
Katrina Personal Brand Project and portfolio 1
 
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
👉Chandigarh Call Girls 👉9878799926👉Just Call👉Chandigarh Call Girl In Chandiga...
 
Phases of Negotiation .pptx
 Phases of Negotiation .pptx Phases of Negotiation .pptx
Phases of Negotiation .pptx
 
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service NoidaCall Girls In Noida 959961⊹3876 Independent Escort Service Noida
Call Girls In Noida 959961⊹3876 Independent Escort Service Noida
 
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
Russian Call Girls In Rajiv Chowk Gurgaon ❤️8448577510 ⊹Best Escorts Service ...
 
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
Quick Doctor In Kuwait +2773`7758`557 Kuwait Doha Qatar Dubai Abu Dhabi Sharj...
 
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
Call Girls Kengeri Satellite Town Just Call 👗 7737669865 👗 Top Class Call Gir...
 
Organizational Transformation Lead with Culture
Organizational Transformation Lead with CultureOrganizational Transformation Lead with Culture
Organizational Transformation Lead with Culture
 
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai KuwaitThe Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
The Abortion pills for sale in Qatar@Doha [+27737758557] []Deira Dubai Kuwait
 
Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024Marel Q1 2024 Investor Presentation from May 8, 2024
Marel Q1 2024 Investor Presentation from May 8, 2024
 
Falcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in indiaFalcon Invoice Discounting platform in india
Falcon Invoice Discounting platform in india
 
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000
Call Girls In Majnu Ka Tilla 959961~3876 Shot 2000 Night 8000
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 

Ref failur e analysis tip casting & retainer area f

  • 3. Castable should be heated very carefully to control the steam presure ACW 1&2 - Picture before bursting
  • 4. Castable bursted due to un controlled steam pressure , 11 hr after initial heat-up (ACW)
  • 5. Castable bursted due to uncontrolled steam pressure . This was due to 1) rapid heating as the flame was much shorter . Pilot burner- oil flame was close to the outlet and the castable. 2) Oil spilled on the castable and caused local heating. Castable bursted at nose ring area ACW 1 & 2 It is observed that only castable blocks at the bottom half got damaged more.
  • 6. Castable failure at the tip casting area at ACW Causes: (at the time of heating up kiln ,after major lining) • too short oil flame close to the castable caused uncontrolled steam pressure resulted in bursting of castable. • oil spillage on the castable caused local heating Remedies • Elongate the flame and push the burner farther inside the kiln so that radiation Is reduced on the castable. • Spread clinker nodules on the refractories from tip to 10 M length • Changed over to andalusite based castable.
  • 7. APCW cracks begin , after one month Operation at the junction of two monolithic blocks
  • 8. This crack formation is due to Inadequate expansion joint after two months of kiln operation. There is no wear but observed cracks on the Surface and deep cracks at the junction Of two castings. APCW
  • 9. Castable failure after 4 months operation due to inadequate expansion joint and Thermal shocks APCW
  • 10. Castable failure due to Inadequate expansion joint causes deep crack formation and spalling after 4 months of operation. APCW Deep penetration of clinker liquid Into the brick.
  • 11. One monolithic casting has crossed to the other casting and the blocks expanded taking the casting along with, which ended in spalling.There should be a clear expansion joint of 10 mm between the blocks. APCW
  • 12. Remedies • Tip casting plates( with male and female joint) have been modified to straight blocks . • Castable was changed from andalusite based to Corundum based to withstand abrasion. • Expansion gap was increased from 5 mm 15 mm with ceramic boards Refractory failure on the tip casting at APCW Causes • Thermal shocks • Cracking due to inadequate expansion joint . ( expansion joint closed during vibration) Very often it is observed that the expansion gap between the castings are filled with Castable.
  • 13. This L –joint will not allow to give expansion joint properlly ( overlapping due to male and female joint Before modification
  • 14. This straight expansion joint allows proper expansion. After modification
  • 15. Castable on the modified blocks APCW Expansion joint is straight in the Modified castings.
  • 16. Tip casting blocks are not in line This V-joint will make make the brick ring mis aligned. The suppliers engrave the letters on the castings on the collar which makes point contact with the bricks. It can be engraved on the on the hot face side. Dimension tolerance must not deviate from limit specified by OEM. AC kiln
  • 17. Tip casting Retainer ring a b c d e a b c d e Tip casting Retainer ring A=b=c=d=e and so on a,<b =c < d=> e Installation of castings at the kiln tip area. Casting’s periphery at its base side must be in line.
  • 18. . . Nose ring Blocks Suppliers must be advised not to engrave the letters on the base and the collar where bricks have contact with castings. Letters can be engraved on the hot face of the castings Bolts must never be protruded .This acts like a pivot and castings will not have contact with the bricks. Casting must have machined surface and the blurs must be ground to get fine surface on the castings..
  • 19. Engraved letters and blurs can create point contact between the bricks and the castings which will pinch the brick surface and causes refractory failure at the tip. Ensure 100 % contact between The brick and the castings Nose ring castings
  • 20. Engraved letters and blurs can create point contact between the bricks and the castings which will pinch the brick surface and causes refractory failure at the tip. Ensure 100 % contact between The brick and the castings Nose ring castings
  • 21. HA-70 bricks twisted at 47 m Castings got oxidised as well as corroded V-joint gap due to bell mouth Or casting got sunk. If casting face is not smooth it can create this gap. This need a machined Surface. Point contact is not acceptable. Letters engraved on the face can also create gap because of point contact. AC
  • 22. Bell mouth formation at Kiln outlet AC Casting are oxidised too After 3 months of operation Thinned down to almost half.
  • 23. This V gap formation is due to bell mouth formation. AC
  • 24. AC Bricks got crushed The bricks on the retainer ring were pushed by 20 – 30 mm. That time the kiln had severe Upset run. Huge variation in chemistry , due to Low silo level and flux variation due to wetness of red ochre.
  • 25. 0 –1.2 M area The bricks are crushed Due to excessive thrust. Bell mouth formation is also there. VC-3 Kiln
  • 26. The castings are oxidized as well as corroded after 3 months of operation. When we fire pet coke Nickel/ chromium Ratio needs change .Also found that there is wear though the hard face welding is done. High Efficiency cooler increases the secondary temperature and may burn the castings . The dust erosion and clinker falling on the Castings can also increase the wear .Nose ring cooling must be enhanced. Cooling air volume =400 Cum/min , and velocity of air at nozzle t >45 M/s and the no.of nozzles , minimum is 6. RC-3 Kiln
  • 27. The gap created must be due to bell mouth Formation or nose ring castings got sunk because of intolerable heat. Nose ring cooling must be enhanced RC3 Kiln
  • 28. Out let blocks are cracked Due to over heating after the Installation of high efficiency Static grates cooler. GS Kiln
  • 29. Now the hot face is covered by Castble.The life has increased to more than one year. GS Kiln
  • 30. Nose ring cooling For kiln Dia < 4.0 M, cooling air volume 400 cum/min For kiln dia > 4.0 M, cooling air volume 500 cu m/ min Nozzle velocity = 40 – 45 m/s Minimum no.of nozzles =6 < 1.5 M
  • 31. 0 –2.2 M VC-3 Kiln 2 nd row after tip casting Unstable coating due to high sulfur recycle variation Low alumina modulus. High liquid forms the coating upto the tip. Sufur volatile factor some times reach > 3.5 and Varied from 2 to 3.5.Petcoke sulfur exceeds 7.5%.
  • 32. Refractory failures at the tip casting in AC and VC Causes • bell mouth formation • Casting loose their mechanical stability due to corrosion and oxidised • Insufficient cooling of nose ring • Frequent ring formation and doslodgement at the tip and consequent thermal shocks • High liquid content and variation in clinker liquid quality due to variation in sulfur cycle.Often it crossed > 3.0 . Remedies • change the outlet shell • Improve the nose ring cooling air volume and cooling nozzle velocity • Control the chemistry and sulfur cycle. • Nickel / Chromium has to be adjusted as Nickel is vulnerable to sulfur attack and chromium to alkali attack.
  • 33. This is due to bell mouth formation. Even the spinel bricks had failed. Mortar application is must to have more flexibility. VC-3 Kiln
  • 34. 0 –2.0 M Bricks on the retainer ring got crushed VC-3 Kiln
  • 35. Even the bricks on the retainer ring got shifted due to excessive axial thrust Sudden increase in temperature on brick surface Due to coating collapse. kiln had severe upset run When this failure occurred. AC kiln
  • 36. Refractory failure at retainer ring area in AC and VC. Causes • instability of coating in this area due to change in chemistry and variation in sulfur cycle because of petcoke firing • Excessive axial thrust due to higher vrpm • Flame needs tuning • Rhino horn formation on burner tip distorts the flame. Remedies • Variation in chemistry needs control • Higher grade spinel bricks will improve the life • flame should be shaped to short , convergent and hot flame. • Install shock blasters to dislodge the Rhino horn on the burner tip.
  • 37. 30 % of the brick is penetrated . Aggressive liquid attack on brick ( 33 % liquid in clinker) These cracks show that the bricks undergone severe thermo-mechanical Stresses. APCW Location : 1st row after tip casting block. The gap between the castings is much higher than the OEM specifications.
  • 38. Deep penetration of liquid into the bricks Theses crack show that there is severe stresses on the bricks Thermo-mechanical as well as thermo chemical ( bell mouth formation and aggressive liquid attack on the brick) APCW
  • 39. Refractory failure at kiln outlet – APCW Causes; • Too high liquid % which penetrate deep into even the spinel bricks and degenerate spinels and destruct the bricks. Coating is also unstable • Bell mouth formation causes thermo-mechanical stresses • Casting are not in line as their dimensions have deviation than the tolerance limits than specified by OEM. • axial thrust Remedies • Optimize the liquid to reduce coating • Castings must have tolerance limit as recommended by OEM • Change the outlet cone shell to straight shell to reduce the axial thrust with • installation of conical retainer rings of Magattoux.
  • 40. GCW Even the spinel bricks had been Impenetrated by aggressive liquid Degenerate the spinels . The bricks losses Its strength.
  • 41. GCW
  • 42. GCW
  • 43. GCW
  • 44. GCW
  • 45. Hasle D-59 A castable Bricks are twisted and crushed due to high axial thrust GCW-1 If bricks are attacked by aggressive liquid they are vulnerable to any stresses
  • 46. Failed area adjacent to retainer ring GCW-1
  • 47. Shell surface is rough We have to apply mortar Underneath the bricks .to have full contact with the shell and cold face of the brick. GCW-1
  • 48. GCW-1 The spinel bricks are crushed and destructed
  • 49. up to half of the brick thickness is attacked by aggressive liquid attack. GCW-1
  • 50. Deep melt infiltration inside The brick. The bricks had undergone Very high thermo- chemical And thermo mechanical load. Almost 50 % brick is attacked by liquid Which can destroy the ingrediants of the brick . This is a hercynite Spinel brick , Ankral Z1. GCW-1
  • 51. Huge cracks show the bricks undergone Severer thermo-mechanical stresses. The Thermochemical attack on the bricks make more vulnerable for thermo-mechanical stresses GCW
  • 52. Refractory failure at kiln outlet – GCW Remedies • High grade spinel bricks which only increases the life by giving resistance to aggressive liquid attack. Variation in quartz has to be reduced. • Replacement of conical shell to straight shell to reduce axial thrust. Conical retainer ring is the second option to arrest the thrust. • Live ring migration at first tyre must not be more than 12mm/revolution.Proper shimming has to be done accordingly. • Surge hopper has to be installed to collect the bag house dust to reduce chemistry variation in kiln feed. Causes Very high burning zone temperature due to presence of quartz and to maintain free lime < 1.1 %. The liquid has less viscosity and penetrate the bricks deep. changes in chemistry when raw meal stops , variation in kiln feed LSF by 2-4 Flame gets distorted often due to rhino-horn formation on burner tip very high variation in I tyre migration due to coating instability , ie 0 mm to 30 mm
  • 53. Refractory failure at retainer ring area - APCW and GCW kiln
  • 54. APCW Bricks got crushed at the retainer ring
  • 55. Bricks at the retainer ring got Crushed due to excessive axial thrust. Very high thermo-chemical Stresses on the bricks. Liquid had deep penetration and destructed the spinels and The texture.of the bricks.
  • 56. Crushing of the bricks APCW
  • 57. Bricks crushed at the Retainer ring
  • 58. Refractory failure at kiln outlet and near the retainer ring – APCW and GCW. Reasons Frequent coating failure due chemistry variation Too high liquid % in clinker ie.,33% Flame and reduced conditions Severe thermal shocks due to coating dislodgement which takes away part of the bricks. Remedies Optimise the liquid Change over to high grade spinel bricks like Almag AF or Ankral R1 Due to dusty conditions flame gets disturbed and reduced conditions prevail . This causes the coating very unstable and causing thermal Shocks.
  • 59. Too many retainer rings are unneceassry They act like stiffeners and when kiln shell gets Heated up this will, shear the shell . 75 mm thick Retainer ring is tougher than kiln shell. Therer are 4 rows of Magattoux retainer rings from 1.2 – 1.8 Meter , double retainer ring at 1 M and Single retainer ring.at 0.4 M Shell is warped at many places
  • 60. Bricks are under stress Alumina bricks is a not good selection The conical retainer ring are meant for Spinel bricks HCW
  • 61. Bricks have cracks Shows that bricks are under Thermo mechanical stress. First row bricks are totally crushed and washed out. The castable also got dislodged as the brick ring moved and created axial thrust on the castable too. The second and other rings moved forward by 45 mm.
  • 63. Retainer ring surface is wavy Retainer ring is burnt.
  • 65. Shell crack crack on retainer Conical retainer ring of RHI & Magattoux Surface is wavy
  • 66. Castable casted on the tipcasting face ,done at site First retainer ring warped. This makes the bricks twisting .
  • 67. As the shell is having wavy surface the conical retainer ring donot have contact surface with bricks and hence bricks need cutting at the bottom by 12- 18 mm in many places and mortar application underneath the bricks to fill up the gaps. Mortar application is done at radial joints too.
  • 68. After conical rings no extra retainer ring is needed
  • 69. Refractory failure at retainer ring area HCW Remedies Damaged outlet shell is to be replaced by new shell Spinel bricks will be used on the conical retainer ring instead of High alumina bricks to have better locking and arching which avoids shifting. Retainer ring must have smooth surface and have the same curvature of kiln. After conical retainer ring no retainer ring is needed as recommended by refractory suppliers Causes wrong selection of bricks too may retainer rings shell surface is wavy and warped also. conical retainer rings are not fixed properly as it is observed that it falls at 12 O’ clock position while rotating the kiln