SlideShare a Scribd company logo
1 of 3
Download to read offline
THERMAL EXPANSION OF WINGWALL SUPERHEATER AND ITS DISTORTION
By K.K.Parthiban, B. Tech (IIT-Madras), M.E Thermal Engineering- RECT Trichy
Distortion of wingwall superheater is experienced in many CFBC boilers. This article is about the
cause and care to be taken in design,
installation and operation of CFBC boilers, to
prevent distortion. Photo 1 shows the
distortion experienced in a CFBC installation.
The below drawing (photo 2) shows the
expansion movements given in thermal
expansion diagram by the boiler manufacturer
for this case. Plant engineers may obtain this
information from the manufacturer for their
boilers.
In this illustrated case, the wing wall
superheater is anchored at the front waterwall
panel at the bottom. The working point is at
17.851 m. The wing wall superheater outlet header is supported at 32.894 m. The absolute expansion
of the wingwall SH outlet header is 110 mm upward. The downward expansion of the anchor point is
66.7 mm. The net expansion at the
wingwall SH outlet header is 110 -
66.7 = 43.3 mm upward. The spring
movement of the constant level
hanger provided for supporting the
wing wall superheater is designed
for the upward travel of 43.3 mm.
The length of the wing wall
superheater panel is 15 m.
Most CFBC boilers are provided
with coal feed points in the front
panel. During start-up of the plant,
the combustion takes place in the
upper furnace due to the inadequate
bed material in the furnace. The
required upper bed is formed only
after sufficient fine ash is generated
in the combustion process. Only
after the sufficient fine ash is
generated, the waterwall starts
absorbing the design heat, at the
design heat flux. Without the fine
ash, the combustion takes place at
the upper furnace. This is because
Photo 1: Distortion of wingwall SH
Photo 2: Expansion movement diagram
there is no resistance available to prevent the transport
of burning coal to the top. Hence the wingwall
superheater receives high heat input and is subjected to
dry heating up without adequate cooling steam. The
thermal expansion of the wing wall superheater at start-
up would now exceed the normal expected thermal
expansion. This start-up criteria may not be envisaged
by the designer, while procurement for the constant
spring support for wingwall SH.
There is no thermocouple provided in the upper furnace,
below wingwall superheater, to monitor the gas side
temperature during start up. This is not provided, as it
could cause furnace wall tube failure due to preferential
flow of furnace inventory during normal operation. One
must observe the metal temperature of wingwall superheater outlet tubes only. The metal
temperature can go to the maximum allowable metal temperature for the SH material, which is
usually 585°C. We may note the rated pressure is
achieved gradually after the furnace inventory increases
in start-up process.
During start-up, the waterwall is cold. The rated
pressure is not achieved in the beginning. The saturation
temperature currently would be less than the rated
temperature. The downward thermal expansion at
anchor point could be much less. However, the
wingwall superheater must expand upwards as per the
maximum permitted metal temperature - 585°C. This
will cause a good amount of upward thermal expansion
of the wing wall superheater outlet header. This would
be in the order of 150 mm. However, the constant load
hanger selected may not accommodate this much
amount of expansion encountered during start up. The
seal box must also be designed to accommodate an
expansion of 150 mm and generally not designed so.
The thermal expansion of the wingwall superheater must
take place against gravity. The shape of the wing wall
superheater is such that, it can easily buckle because of
its less cross-sectional dimensions versus the height
ratio. Hence it doesn’t expand as rigid member. Given a
resistance to prevent thermal expansion, the panel
buckles. This leads to a permanent deformation.
The worst distortion can be seen in photo 3. This is from
another boiler. For this case, replacement is a must.
During every start-up, the distorted panel flexes at the
Photo 5: Spring hanger – large travel
Photo 4: Constant load hanger -limited
travel
Photo 3: Worst distortion of wingwall SH
location where the permanent deformation had taken place at the
first time. This flexing of panel is now elastic in nature. In case
of replacement wing wall superheater panels, the deformation
would take place again at some location naturally. If this must be
prevented, a constant load hanger, which can accommodate large
deflections would be required. The current model selected by
boiler maker does not take up large deflection. See photo 4
above. The Lisega (well-known manufacturer of spring supports)
make spring supports are available for large deflections. See
photo 5.
What to do with the present distortion?
In most cases, it is advisable to leave the wing wall superheater
with the deformation depending on the severity at the flex point. It is this deformation which now
accommodates the large thermal expansion, which take place during every start-up. Further relative
thermal expansion is accommodated by the constant load hangers. This can be checked during
operation.
Distorted wingwall SH panels would be subject to higher erosion rate. Regular monitoring of erosion
and thickness logging is a must. The risk carried would be similar to CFBC furnace panel erosion.
The other type of damage expected would be the cracks at the header stubs. The thermal forces
would be partly transferred to the stubs at both inlet and outlet header. Dye penetrant test is advised
to be carried out on every annual shutdown. There are cases wherein the thermal expansion forces
act on the header stubs and caused leaks. See photo 6. The number of startup & shut down cycles
would decide the initiation of stub / weldment crack at headers. This could occur after a long service.
A tube failure in wingwall SH would lead to furnace pressurization. The furnace trip protection on
high furnace pressure should not never be bypassed. Regular inspection of header stubs is advised.
Conclusion
The wingwall SH distortion can be controlled by avoiding rapid start-up during cold and hot restart
times. Even if the right type spring support is provided by the boiler maker, it is possible that the
distortion can be caused by improper operation. In the case of the worst distortion seen in photo 3
immediate replacement of the SH is required. A retractable thermocouple can be arranged below
wingwall SH. It would help the operator to monitor and prevent high gas side temperatures during
cold start up and hot restarts.
M/S Venus energy audit system – Trouble shooting of boiler failures and operational
issues. Company carries out design audit, construction audit, shut down audit and
operational audit.
M/S Sri Devi engineering consultancy and agency – engaged in non-pressure parts
spares supply for FBC / CFBC / PF boilers.
M/S Sri Devi boiler equipment and spares – engaged in supply of pressure part spares
for all type of boilers
Photo 6: SH header stub weldment
crack

More Related Content

What's hot

Report on Industrial Training
Report on Industrial TrainingReport on Industrial Training
Report on Industrial TrainingNashiyat Fyza
 
Evaluation of a Boiler performance
Evaluation of a Boiler performanceEvaluation of a Boiler performance
Evaluation of a Boiler performanceHashim Hasnain Hadi
 
Training material for air preheater
Training material for air preheaterTraining material for air preheater
Training material for air preheaterHOANG VAN DUC
 
Improving boiler efficiency by using air preheater
Improving boiler efficiency by using air preheaterImproving boiler efficiency by using air preheater
Improving boiler efficiency by using air preheaterNetha Jashuva
 
Training presentation
Training presentation Training presentation
Training presentation Keyur Patel
 
PRESSURIZED FLUIDIZED BED COMBUSTION BOILER
PRESSURIZED FLUIDIZED BED COMBUSTION BOILERPRESSURIZED FLUIDIZED BED COMBUSTION BOILER
PRESSURIZED FLUIDIZED BED COMBUSTION BOILERKRUNAL RAVAL
 
Waste Heat Recovery Vinay Shukla
Waste Heat Recovery  Vinay ShuklaWaste Heat Recovery  Vinay Shukla
Waste Heat Recovery Vinay ShuklaVinay Shukla
 
Performance optimization of Forced Draft Fan of BBGS Unit # 1
Performance optimization of Forced Draft Fan of BBGS Unit # 1Performance optimization of Forced Draft Fan of BBGS Unit # 1
Performance optimization of Forced Draft Fan of BBGS Unit # 1Saikat Halder
 
basics_of_boiler_design__1674282406.pdf
basics_of_boiler_design__1674282406.pdfbasics_of_boiler_design__1674282406.pdf
basics_of_boiler_design__1674282406.pdfDhavalpatel219430
 
Circulating fluidizing bed combustion Boiler presentation
Circulating fluidizing bed combustion Boiler presentation Circulating fluidizing bed combustion Boiler presentation
Circulating fluidizing bed combustion Boiler presentation Sawan Vaja
 
Fired Equipment presentation on Types, Classification and governing Equations...
Fired Equipment presentation on Types, Classification and governing Equations...Fired Equipment presentation on Types, Classification and governing Equations...
Fired Equipment presentation on Types, Classification and governing Equations...Hassan ElBanhawi
 
Steam turbine performance & condition assessment (Case Study)
Steam turbine performance & condition assessment (Case Study)Steam turbine performance & condition assessment (Case Study)
Steam turbine performance & condition assessment (Case Study)Pichai Chaibamrung
 
Boiler circulation theory
Boiler circulation theoryBoiler circulation theory
Boiler circulation theoryNaumanKalshekar
 
Heat recovery steam generator
Heat recovery steam generatorHeat recovery steam generator
Heat recovery steam generatorumar farooq
 

What's hot (20)

Report on Industrial Training
Report on Industrial TrainingReport on Industrial Training
Report on Industrial Training
 
Pptfbc
PptfbcPptfbc
Pptfbc
 
Evaluation of a Boiler performance
Evaluation of a Boiler performanceEvaluation of a Boiler performance
Evaluation of a Boiler performance
 
Training material for air preheater
Training material for air preheaterTraining material for air preheater
Training material for air preheater
 
Improving boiler efficiency by using air preheater
Improving boiler efficiency by using air preheaterImproving boiler efficiency by using air preheater
Improving boiler efficiency by using air preheater
 
Training presentation
Training presentation Training presentation
Training presentation
 
PRESSURIZED FLUIDIZED BED COMBUSTION BOILER
PRESSURIZED FLUIDIZED BED COMBUSTION BOILERPRESSURIZED FLUIDIZED BED COMBUSTION BOILER
PRESSURIZED FLUIDIZED BED COMBUSTION BOILER
 
Waste Heat Recovery Vinay Shukla
Waste Heat Recovery  Vinay ShuklaWaste Heat Recovery  Vinay Shukla
Waste Heat Recovery Vinay Shukla
 
Performance optimization of Forced Draft Fan of BBGS Unit # 1
Performance optimization of Forced Draft Fan of BBGS Unit # 1Performance optimization of Forced Draft Fan of BBGS Unit # 1
Performance optimization of Forced Draft Fan of BBGS Unit # 1
 
basics_of_boiler_design__1674282406.pdf
basics_of_boiler_design__1674282406.pdfbasics_of_boiler_design__1674282406.pdf
basics_of_boiler_design__1674282406.pdf
 
Circulating fluidizing bed combustion Boiler presentation
Circulating fluidizing bed combustion Boiler presentation Circulating fluidizing bed combustion Boiler presentation
Circulating fluidizing bed combustion Boiler presentation
 
combustion in boilers
combustion in boilerscombustion in boilers
combustion in boilers
 
Steam generator part 2
Steam generator part 2Steam generator part 2
Steam generator part 2
 
Rankine cycle
Rankine cycleRankine cycle
Rankine cycle
 
Fired Equipment presentation on Types, Classification and governing Equations...
Fired Equipment presentation on Types, Classification and governing Equations...Fired Equipment presentation on Types, Classification and governing Equations...
Fired Equipment presentation on Types, Classification and governing Equations...
 
Steam turbine performance & condition assessment (Case Study)
Steam turbine performance & condition assessment (Case Study)Steam turbine performance & condition assessment (Case Study)
Steam turbine performance & condition assessment (Case Study)
 
Boiler circulation theory
Boiler circulation theoryBoiler circulation theory
Boiler circulation theory
 
CFBC Boiler vs Pulverized Fired Boiler
CFBC Boiler vs Pulverized Fired BoilerCFBC Boiler vs Pulverized Fired Boiler
CFBC Boiler vs Pulverized Fired Boiler
 
Heat recovery steam generator
Heat recovery steam generatorHeat recovery steam generator
Heat recovery steam generator
 
4.1 boiler
4.1 boiler4.1 boiler
4.1 boiler
 

Similar to Wingwall sh distortion in cfbc boilers by k.k.parthiban jan 2018

Critical observations during a shut down audit of a pf boiler final
Critical observations during a shut down audit of a pf boiler  finalCritical observations during a shut down audit of a pf boiler  final
Critical observations during a shut down audit of a pf boiler finalparthi2006
 
Standard erection manual (pressure parts)
Standard erection manual (pressure parts)Standard erection manual (pressure parts)
Standard erection manual (pressure parts)Ashutosh Sachan
 
Soot Blowing Optimization- Field Experience
Soot Blowing Optimization- Field ExperienceSoot Blowing Optimization- Field Experience
Soot Blowing Optimization- Field ExperiencePooja Agarwal
 
Guide to Furnace Sootblowing
Guide to Furnace SootblowingGuide to Furnace Sootblowing
Guide to Furnace SootblowingRichard Smith
 
Feedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsFeedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsSHIVAJI CHOUDHURY
 
Wolverine sthe designing
Wolverine sthe designingWolverine sthe designing
Wolverine sthe designingDisha Jain
 
Surging & blow out of loop seals in a CFBC boiler
Surging & blow out of loop seals in a CFBC boilerSurging & blow out of loop seals in a CFBC boiler
Surging & blow out of loop seals in a CFBC boilerVENUS ENERGY AUDIT SYSTEM
 
2nd Revised FYP Reporting
2nd Revised FYP Reporting2nd Revised FYP Reporting
2nd Revised FYP ReportingBurhan Ahmed
 
Three Mile Island Nuclear Plant steam generator safety is suspect
Three Mile Island Nuclear Plant steam generator safety is suspectThree Mile Island Nuclear Plant steam generator safety is suspect
Three Mile Island Nuclear Plant steam generator safety is suspectScott Portzline
 
Ref failur e analysis tip casting & retainer area f
Ref failur e analysis tip casting & retainer area  fRef failur e analysis tip casting & retainer area  f
Ref failur e analysis tip casting & retainer area fpradeepdeepi
 
electric arc furnace
electric arc furnaceelectric arc furnace
electric arc furnaceSanjitDhar
 
Steam distribution system by Varun Pratap Singh
Steam distribution system by Varun Pratap SinghSteam distribution system by Varun Pratap Singh
Steam distribution system by Varun Pratap SinghVarun Pratap Singh
 

Similar to Wingwall sh distortion in cfbc boilers by k.k.parthiban jan 2018 (20)

Critical observations during a shut down audit of a pf boiler final
Critical observations during a shut down audit of a pf boiler  finalCritical observations during a shut down audit of a pf boiler  final
Critical observations during a shut down audit of a pf boiler final
 
Standard erection manual (pressure parts)
Standard erection manual (pressure parts)Standard erection manual (pressure parts)
Standard erection manual (pressure parts)
 
M01267378
M01267378M01267378
M01267378
 
Boiler safety
Boiler safetyBoiler safety
Boiler safety
 
Soot Blowing Optimization- Field Experience
Soot Blowing Optimization- Field ExperienceSoot Blowing Optimization- Field Experience
Soot Blowing Optimization- Field Experience
 
Heat Treatment
Heat TreatmentHeat Treatment
Heat Treatment
 
Guide to Furnace Sootblowing
Guide to Furnace SootblowingGuide to Furnace Sootblowing
Guide to Furnace Sootblowing
 
Thermal fatigue failure in a FBC boiler
Thermal fatigue failure in a FBC boilerThermal fatigue failure in a FBC boiler
Thermal fatigue failure in a FBC boiler
 
Case Studies on CFBC Boilers
Case Studies on CFBC BoilersCase Studies on CFBC Boilers
Case Studies on CFBC Boilers
 
Feedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsFeedwater heaters in thermal power plants
Feedwater heaters in thermal power plants
 
Wolverine sthe designing
Wolverine sthe designingWolverine sthe designing
Wolverine sthe designing
 
Surging & blow out of loop seals in a CFBC boiler
Surging & blow out of loop seals in a CFBC boilerSurging & blow out of loop seals in a CFBC boiler
Surging & blow out of loop seals in a CFBC boiler
 
2nd Revised FYP Reporting
2nd Revised FYP Reporting2nd Revised FYP Reporting
2nd Revised FYP Reporting
 
780148
780148780148
780148
 
Three Mile Island Nuclear Plant steam generator safety is suspect
Three Mile Island Nuclear Plant steam generator safety is suspectThree Mile Island Nuclear Plant steam generator safety is suspect
Three Mile Island Nuclear Plant steam generator safety is suspect
 
Ref failur e analysis tip casting & retainer area f
Ref failur e analysis tip casting & retainer area  fRef failur e analysis tip casting & retainer area  f
Ref failur e analysis tip casting & retainer area f
 
electric arc furnace
electric arc furnaceelectric arc furnace
electric arc furnace
 
Steam distribution system by Varun Pratap Singh
Steam distribution system by Varun Pratap SinghSteam distribution system by Varun Pratap Singh
Steam distribution system by Varun Pratap Singh
 
5451 5455.output
5451 5455.output5451 5455.output
5451 5455.output
 
5451 5455.output
5451 5455.output5451 5455.output
5451 5455.output
 

Recently uploaded

Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 

Recently uploaded (20)

9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 

Wingwall sh distortion in cfbc boilers by k.k.parthiban jan 2018

  • 1. THERMAL EXPANSION OF WINGWALL SUPERHEATER AND ITS DISTORTION By K.K.Parthiban, B. Tech (IIT-Madras), M.E Thermal Engineering- RECT Trichy Distortion of wingwall superheater is experienced in many CFBC boilers. This article is about the cause and care to be taken in design, installation and operation of CFBC boilers, to prevent distortion. Photo 1 shows the distortion experienced in a CFBC installation. The below drawing (photo 2) shows the expansion movements given in thermal expansion diagram by the boiler manufacturer for this case. Plant engineers may obtain this information from the manufacturer for their boilers. In this illustrated case, the wing wall superheater is anchored at the front waterwall panel at the bottom. The working point is at 17.851 m. The wing wall superheater outlet header is supported at 32.894 m. The absolute expansion of the wingwall SH outlet header is 110 mm upward. The downward expansion of the anchor point is 66.7 mm. The net expansion at the wingwall SH outlet header is 110 - 66.7 = 43.3 mm upward. The spring movement of the constant level hanger provided for supporting the wing wall superheater is designed for the upward travel of 43.3 mm. The length of the wing wall superheater panel is 15 m. Most CFBC boilers are provided with coal feed points in the front panel. During start-up of the plant, the combustion takes place in the upper furnace due to the inadequate bed material in the furnace. The required upper bed is formed only after sufficient fine ash is generated in the combustion process. Only after the sufficient fine ash is generated, the waterwall starts absorbing the design heat, at the design heat flux. Without the fine ash, the combustion takes place at the upper furnace. This is because Photo 1: Distortion of wingwall SH Photo 2: Expansion movement diagram
  • 2. there is no resistance available to prevent the transport of burning coal to the top. Hence the wingwall superheater receives high heat input and is subjected to dry heating up without adequate cooling steam. The thermal expansion of the wing wall superheater at start- up would now exceed the normal expected thermal expansion. This start-up criteria may not be envisaged by the designer, while procurement for the constant spring support for wingwall SH. There is no thermocouple provided in the upper furnace, below wingwall superheater, to monitor the gas side temperature during start up. This is not provided, as it could cause furnace wall tube failure due to preferential flow of furnace inventory during normal operation. One must observe the metal temperature of wingwall superheater outlet tubes only. The metal temperature can go to the maximum allowable metal temperature for the SH material, which is usually 585°C. We may note the rated pressure is achieved gradually after the furnace inventory increases in start-up process. During start-up, the waterwall is cold. The rated pressure is not achieved in the beginning. The saturation temperature currently would be less than the rated temperature. The downward thermal expansion at anchor point could be much less. However, the wingwall superheater must expand upwards as per the maximum permitted metal temperature - 585°C. This will cause a good amount of upward thermal expansion of the wing wall superheater outlet header. This would be in the order of 150 mm. However, the constant load hanger selected may not accommodate this much amount of expansion encountered during start up. The seal box must also be designed to accommodate an expansion of 150 mm and generally not designed so. The thermal expansion of the wingwall superheater must take place against gravity. The shape of the wing wall superheater is such that, it can easily buckle because of its less cross-sectional dimensions versus the height ratio. Hence it doesn’t expand as rigid member. Given a resistance to prevent thermal expansion, the panel buckles. This leads to a permanent deformation. The worst distortion can be seen in photo 3. This is from another boiler. For this case, replacement is a must. During every start-up, the distorted panel flexes at the Photo 5: Spring hanger – large travel Photo 4: Constant load hanger -limited travel Photo 3: Worst distortion of wingwall SH
  • 3. location where the permanent deformation had taken place at the first time. This flexing of panel is now elastic in nature. In case of replacement wing wall superheater panels, the deformation would take place again at some location naturally. If this must be prevented, a constant load hanger, which can accommodate large deflections would be required. The current model selected by boiler maker does not take up large deflection. See photo 4 above. The Lisega (well-known manufacturer of spring supports) make spring supports are available for large deflections. See photo 5. What to do with the present distortion? In most cases, it is advisable to leave the wing wall superheater with the deformation depending on the severity at the flex point. It is this deformation which now accommodates the large thermal expansion, which take place during every start-up. Further relative thermal expansion is accommodated by the constant load hangers. This can be checked during operation. Distorted wingwall SH panels would be subject to higher erosion rate. Regular monitoring of erosion and thickness logging is a must. The risk carried would be similar to CFBC furnace panel erosion. The other type of damage expected would be the cracks at the header stubs. The thermal forces would be partly transferred to the stubs at both inlet and outlet header. Dye penetrant test is advised to be carried out on every annual shutdown. There are cases wherein the thermal expansion forces act on the header stubs and caused leaks. See photo 6. The number of startup & shut down cycles would decide the initiation of stub / weldment crack at headers. This could occur after a long service. A tube failure in wingwall SH would lead to furnace pressurization. The furnace trip protection on high furnace pressure should not never be bypassed. Regular inspection of header stubs is advised. Conclusion The wingwall SH distortion can be controlled by avoiding rapid start-up during cold and hot restart times. Even if the right type spring support is provided by the boiler maker, it is possible that the distortion can be caused by improper operation. In the case of the worst distortion seen in photo 3 immediate replacement of the SH is required. A retractable thermocouple can be arranged below wingwall SH. It would help the operator to monitor and prevent high gas side temperatures during cold start up and hot restarts. M/S Venus energy audit system – Trouble shooting of boiler failures and operational issues. Company carries out design audit, construction audit, shut down audit and operational audit. M/S Sri Devi engineering consultancy and agency – engaged in non-pressure parts spares supply for FBC / CFBC / PF boilers. M/S Sri Devi boiler equipment and spares – engaged in supply of pressure part spares for all type of boilers Photo 6: SH header stub weldment crack