Topic 6: Underground Mining Methods
 Cut-and-Fill stoping
Hassan Z. Harraz
hharraz2006@yahoo.com
2014- 2015
Outline of Topic 6:
 Introduction
 Application of Cut-and-Fill (C & F) stoping
 The activity cycle of the (C & F) method
 Stages of the production cycle of the C & F method
 Sequences of extracting ore bodies
 Filling in C & F Method
 About filling of stopes
 Functions of filler
 Types of fillers
 Advantages and disadvantages of the C & F method
Prof. Dr. H.Z. Harraz Presentation
Cut & Fill stoping
2
We will explore all of the above in Topic 6.
Introduction
Method in which ore is removed at horizontal slices generally upwards. The ore is
drilled, blown up and removed from the stope. The resulting empty after the ore to be
removed, is filled with a filler ("backfill"). The filler serves as a support for the sides of the
stope, and as a platform for the devices when the next slice is mined.
It is a recommended method, for example, where iron ore and / or waste are slightly
relevant, which restricts the size of underground excavations and allows little time between
the removal and the deposition of the mineral filler.
Prof. Dr. H.Z. Harraz Presentation Cut & Fill stoping
3
Introduction
 It is one of the more popular methods used for vein deposits and has recently grown in use.
 It is an expensive but selective mining method, with low ore loss and dilution.[3] (i.e., allows selective mining
and avoid mining of waste or low grade ore).
 Is relatively expensive and therefore is done only in high grade mineralization (Because the method involves
moving fill material as well as a significant amount of drilling and blasting).
 It is a method of shorthole mining used in steeply dipping or It is preferred for orebodies with irregular ore
zones and scattered mineralization.
 It requires working at face (which is less safe than longhole stoping).
 It is used:-
 in mining steeply dipping orebodies in stable rock masses (primarily in steeply dipping metal
deposits),
 in strata with good to moderate stability, and comparatively high grade mineralization.
 either fill option may be consolidated with concrete, or left unconsolidated.
 Generally uses no cement
 Bottom up mining method: Remove ore in horizontal slices, starting from a bottom undercut and
advancing upward.
 Moderate production rates.
 Good resource usage.
 Not stress friendly.
 Moderate ground support
 Ore is drilled, blasted and removed from stope.
 The ore is mined in slices: As each horizontal or slightly inclined slice is taken, the voids (Opens) are
backfilled with a variety of fill types to support the walls (i.e., the fill can be rock waste, tailings, cemented
tailings, or other suitable materials).
{(note: The fill serves both to support the stope walls and provide a working platform for equipment
when the next slice is mined)}.
Figure showing cut and fill mining method.
Remove ore in horizontal slices, starting
from a bottom undercut and advancing
upward.
As each horizontal slice is taken, the
voids (Opens) are filled with a variety of
fill types to support the walls. (i.e., the fill
can be rock waste, tailings, cemented
tailings, or other suitable materials).
Ore is drilled, blasted and
removed from stope
Introduction
 Because the method involves moving fill material as well as a significant amount of drilling and
blasting, it is relatively expensive and therefore is done only in high grade mineralization where
there is a need to be selective and avoid mining of waste or low grade ore.
 It is practiced both in the overhand (upward) and in the underhand (downward) directions.
i) Overhand (upward) cut and fill
o is applied to ore lies underneath the working area and the roof is backfill.
o involves a work area of cemented backfill while mining ore from the roof.
ii) Underhand (Downward) cut and fill ore
o is applied to ore lies beneath the working area and the roof is cemented backfill.
o ore overlies the working area and the machines work on backfill.
Note:
Drift and Fill is similar to cut and
fill, except it is used in ore zones which
are wider than the method of drifting will
allow to be mined. In this case the first
drift is developed in the ore, and is
backfilled using consolidated fill. The
second drift is driven adjacent to the first
drift. This carries on until the ore zone is
mined out to its full width, at which time
the second cut is started atop of the first
cut.
Introduction
Application of Cut-and-Fill (C & F) stoping
The C & F method is required when:
 Ore Zones are irregular in shape and orientation.
 Ore Is high grade and dilution control is critical.
 The Need contacts between ore and waste are structurally critical
but not readily visible.
 The Waste rock is weak.
 Ore Zones are large, but Their rock quality is weak.
 Localized Underground stability is required.
 Surface Disturbance must be minimized.
 The Value of the ore makes recovery of economically viable
support pillars.
 The Reduction of surface waste storage is important.
 The Need exists to advance the working platform for the upward
mining of the ore body.
Prof. Dr. H.Z. Harraz Presentation
Cut & Fill stoping
7
The C & F method
In mining C & F generally upward (overhand)
advances; there is a least common variant -
C & F underhand - where the feed is from the
top down.
C & F advancing
bottom up 
Prof. Dr. H.Z. Harraz Presentation
Cut & Fill stoping
8
overhand C & F
Prof. Dr. H.Z. Harraz Presentation
Cut & Fill stoping
9
a) drill-blast of a horizontal slice of ore, typically with
three or four feet thick, removed the roof of the
stope;
b) loading and transport of ore, mechanically removed
from the stope for orepass, and then to a lower
horizon of transportation;
c) removal of loose fragments ("cuttlefish") by the
detonation and placement support / reinforcement
ceiling;
d) filling the floor of the stope (backfilling) with a layer
of composite material varied and equal in thickness
ore disassembled ceiling.
The activity cycle of the C & F method involves the
following steps:
Prof. Dr. H.Z. Harraz Presentation
Cut & Fill stoping
10
Stages of the production cycle of the C & F method :
Prof. Dr. H.Z. Harraz Presentation
Cut & Fill stoping
11
The workers perform all the activities of the production
cycle in the newly opened roof of stope. So, for the
method to be successful, one must control the behavior
of the rock on the outskirts of the stope. This is done in
several ways: by controlling the dismantling of the roof,
using reinforcement / support for openings and using
the stope backfill.
Use of roof
bolts in C & F
Prof. Dr. H.Z. Harraz Presentation
Cut & Fill stoping
12
Control ceiling by cable bolts :
Sequence of use :
Prof. Dr. H.Z. Harraz Presentation
Cut & Fill stoping
13
C & F method is versatile (there are
different configurations of extraction)
applied to bodies of different
geometries (shafts, inclined tabular or
massive deposits) can be divided into
separated by vertical pillars and
horizontal blocks.
Horizontal Pillar (i.e, Floor
pillar) separating stopes 
Prof. Dr. H.Z. Harraz Presentation
Cut & Fill stoping
14
Sequences of extracting ore bodies ...
View topic in 3.4.2 : Underground Mining Methods: engineering fundamentals
and international case studies. W.Hustrulid, R.Bullock, SME, 2001.
Prof. Dr. H.Z. Harraz Presentation
Cut & Fill stoping
15
C & F with overhand stopes separated by vertical pillars,
in this case made ​​with backfill:
Prof. Dr. H.Z. Harraz Presentation
Cut & Fill stoping
16
C & F overhand with ramp and stope access
orepass located in the footwall:
Prof. Dr. H.Z. Harraz Presentation
Cut & Fill stoping
17
The method applies to deposits with dipping 35o to 90o, in
deep or shallow bodies. Stopes may have a width
ranging from 4 to 40 m. The filler allows to work in the
presence of enclosing a low resistance. The ore should,
however, have moderate resistance to high.
Thick body
being mined in
plan and in
section 
Prof. Dr. H.Z. Harraz Presentation
Cut & Fill stoping
18
Different geometries of
openings in thick ore
bodies (seen in
section).
Prof. Dr. H.Z. Harraz Presentation
Cut & Fill stoping
19
Fig 1
Narrow body being mined: plan view (left) And
section (right).
Prof. Dr. H.Z. Harraz Presentation
Cut & Fill stoping
20
The C & F is a laborious method, requiring high value for the in situ ore. Some dilution
is expected, which occurs when the backfill is loaded with ore in the stope (usually
done by loading LHD's). Moreover, the method provides selectivity and flexibility,
allowing good control of ore contents and disposal in the stope, sterile material.
Also allows to follow irregular bodies during mining, due to the high degree of
selectivity of the drill-blast sequence
There are several benefits from an environmental standpoint, using the backfill. The
integrity of the host rocks allows less affect the hydrogeology of the mined area.
The possibility of subsidence at the surface is quite limited. Reduce the tailings
storage areas on the surface because they can be taken back to the stopes, as
backfill
Prof. Dr. H.Z. Harraz Presentation
Cut & Fill stoping
21
Variant of the C & F: Avoca method
Prof. Dr. H.Z. Harraz Presentation
Cut & Fill stoping
22
Filling in C & F Method
About filling of stopes:
 filling is done during the production cycle (and not after complete
evacuation of the stope, as in SLS);
 Hydraulic filling (water and sand particle size = hydraulic sand-fill) is the
most common, containing 60 to 70% solids and requiring deposition
techniques and special drain;
 the filling with hydraulic sand-fill, the distribution for the stopes is done
by piping;
 The stope is filled almost to the ceiling height;
 backfill needs to be the strongest, is added to the cement mixture;
 When the water is drained, a good base for moving mining equipment
while it is formed in the upper slice stope;
 the backfill, traffic person is prevented for a few hours and the vehicle for
several days.
Prof. Dr. H.Z. Harraz Presentation
Cut & Fill stoping
23
Filler Models
Prof. Dr. H.Z. Harraz Presentation
Cut & Fill stoping
24
Filling
Functions of filler:
 -preserve access to the stope;
 avoid dilution of ore;
 avoid subsidence on the surface;
 serve as a working platform for workers in
mining the next horizontal slice;
The time of placing the backfill is critical because it
must take the original load was exerted on the ore.
Prof. Dr. H.Z. Harraz Presentation
Cut & Fill stoping
25
Types of fillers
 Additional information on "backfill": read articles
 Underground Mining Methods: engineering fundamentals and international
case studies. W.Hustrulid, R.Bullock, SME, 2001, cap. 69.
Prof. Dr. H.Z. Harraz Presentation
Cut & Fill stoping
26
Types of fillers
1) Hydraulic fill (also
called slurry or sand fill)
3) Rock Fill
2) Paste fill
Prof. Dr. H.Z. Harraz Presentation
Cut & Fill stoping
27
Advantages of the method
 It is a versatile method and can be adapted to the ore bodies from
any geometrical shape
 Investments are moderated to implement the method
 minimizes subsidence
 High recovery and low dilution (selective method)
 Waste can be taken to the basement, avoiding surface
contamination
 Due to the high cost of mining, is only applicable in ores
of high value;
 Requires hand labour intensive and more specialized;
 The activity of filling complicates the production cycle,
causing reduction in production;
 There are risks of instability in mass if the backfill is not
properly sized and applied.
Disadvantages
Prof. Dr. H.Z. Harraz Presentation
Cut & Fill stoping
28

More Related Content

What's hot

Room & Pillar Mining Method
Room & Pillar Mining MethodRoom & Pillar Mining Method
Room & Pillar Mining MethodAyon Saha
 
Sublevel open stopping assignment
Sublevel open stopping assignmentSublevel open stopping assignment
Sublevel open stopping assignmentvirendrasuryawanshi
 
Underground mining methods
Underground mining methodsUnderground mining methods
Underground mining methodsTayyab Anwar
 
Mine Opening and Development
Mine Opening and DevelopmentMine Opening and Development
Mine Opening and DevelopmentAnurag Jha
 
Underground mining method
Underground mining methodUnderground mining method
Underground mining methodSafdar Ali
 
Underground metal mining methods
Underground metal mining methodsUnderground metal mining methods
Underground metal mining methodsSafdar Ali
 
Design of Bord and Pillar method in coal mines
Design of Bord and Pillar method in coal minesDesign of Bord and Pillar method in coal mines
Design of Bord and Pillar method in coal minesaashutosh chhirolya
 
Lectures on metal mining
Lectures on metal miningLectures on metal mining
Lectures on metal miningRanjeet Kumar
 
Longwall Mining
Longwall MiningLongwall Mining
Longwall MiningVR M
 
Longwall mining (Multisling mining - Horizontal slicing) NIT ROURKELA
Longwall mining (Multisling mining - Horizontal slicing) NIT ROURKELALongwall mining (Multisling mining - Horizontal slicing) NIT ROURKELA
Longwall mining (Multisling mining - Horizontal slicing) NIT ROURKELAIndrajeetKumar110
 
13surface mining
13surface mining13surface mining
13surface miningArun Kumar
 

What's hot (20)

Topic 5: Mining Methods-Part I-Surface mining
Topic 5: Mining Methods-Part I-Surface mining Topic 5: Mining Methods-Part I-Surface mining
Topic 5: Mining Methods-Part I-Surface mining
 
Room & Pillar Mining Method
Room & Pillar Mining MethodRoom & Pillar Mining Method
Room & Pillar Mining Method
 
ore dilution and ore recovery
ore dilution and ore recoveryore dilution and ore recovery
ore dilution and ore recovery
 
Open pit mining
Open pit miningOpen pit mining
Open pit mining
 
Underground mining
Underground miningUnderground mining
Underground mining
 
Sublevel open stopping assignment
Sublevel open stopping assignmentSublevel open stopping assignment
Sublevel open stopping assignment
 
Underground mining methods
Underground mining methodsUnderground mining methods
Underground mining methods
 
Mine Opening and Development
Mine Opening and DevelopmentMine Opening and Development
Mine Opening and Development
 
Underground mining method
Underground mining methodUnderground mining method
Underground mining method
 
High Wall Mining
High Wall MiningHigh Wall Mining
High Wall Mining
 
Mine planning
Mine planning Mine planning
Mine planning
 
Underground metal mining methods
Underground metal mining methodsUnderground metal mining methods
Underground metal mining methods
 
Unit operations of mining
Unit operations of miningUnit operations of mining
Unit operations of mining
 
Standards of Mine Closure Planning
Standards of Mine Closure PlanningStandards of Mine Closure Planning
Standards of Mine Closure Planning
 
Design of Bord and Pillar method in coal mines
Design of Bord and Pillar method in coal minesDesign of Bord and Pillar method in coal mines
Design of Bord and Pillar method in coal mines
 
Lectures on metal mining
Lectures on metal miningLectures on metal mining
Lectures on metal mining
 
Longwall Mining
Longwall MiningLongwall Mining
Longwall Mining
 
Longwall mining (Multisling mining - Horizontal slicing) NIT ROURKELA
Longwall mining (Multisling mining - Horizontal slicing) NIT ROURKELALongwall mining (Multisling mining - Horizontal slicing) NIT ROURKELA
Longwall mining (Multisling mining - Horizontal slicing) NIT ROURKELA
 
13surface mining
13surface mining13surface mining
13surface mining
 
Caving Underground Mining Methods (longwall, Sublevel caving, & Block caving)
Caving Underground Mining Methods (longwall, Sublevel caving, &  Block caving)Caving Underground Mining Methods (longwall, Sublevel caving, &  Block caving)
Caving Underground Mining Methods (longwall, Sublevel caving, & Block caving)
 

Similar to Cut and Fill Stoping

Topic5-MiningMethods-PartI-Surfacemining.pdf
Topic5-MiningMethods-PartI-Surfacemining.pdfTopic5-MiningMethods-PartI-Surfacemining.pdf
Topic5-MiningMethods-PartI-Surfacemining.pdfShems192009
 
Underground mining methods + swot analysis of maddhapara granite
Underground mining methods + swot analysis of maddhapara graniteUnderground mining methods + swot analysis of maddhapara granite
Underground mining methods + swot analysis of maddhapara graniteShahadat Saimon
 
Classification of Mining systems mne.pdf
Classification of Mining systems mne.pdfClassification of Mining systems mne.pdf
Classification of Mining systems mne.pdfeaglesniper008
 
Underground mining method natural support and caving
Underground mining method natural support and cavingUnderground mining method natural support and caving
Underground mining method natural support and cavingrazaullahwazir
 
Underground mining system
Underground mining systemUnderground mining system
Underground mining systemSrimontorumpa
 
BLOCK CAVING ATRI.ppt
BLOCK CAVING ATRI.pptBLOCK CAVING ATRI.ppt
BLOCK CAVING ATRI.pptAnshul Yadav
 
Advance Construction equipment's reports
Advance Construction equipment's reports Advance Construction equipment's reports
Advance Construction equipment's reports ssuser061280
 
Mining terminology
Mining terminologyMining terminology
Mining terminologyalokpptshare
 
2General Element of Mining.pptx
2General Element of Mining.pptx2General Element of Mining.pptx
2General Element of Mining.pptxSatyaPrakashRai17
 

Similar to Cut and Fill Stoping (20)

Surface mining planning and design of open pit mining
Surface mining planning and design of open pit miningSurface mining planning and design of open pit mining
Surface mining planning and design of open pit mining
 
Topic5-MiningMethods-PartI-Surfacemining.pdf
Topic5-MiningMethods-PartI-Surfacemining.pdfTopic5-MiningMethods-PartI-Surfacemining.pdf
Topic5-MiningMethods-PartI-Surfacemining.pdf
 
Underground mining methods + swot analysis of maddhapara granite
Underground mining methods + swot analysis of maddhapara graniteUnderground mining methods + swot analysis of maddhapara granite
Underground mining methods + swot analysis of maddhapara granite
 
Classification of Mining systems mne.pdf
Classification of Mining systems mne.pdfClassification of Mining systems mne.pdf
Classification of Mining systems mne.pdf
 
Open pit mining
Open pit miningOpen pit mining
Open pit mining
 
Mining ppt 2014
Mining ppt 2014Mining ppt 2014
Mining ppt 2014
 
Mine waste dump
Mine waste dumpMine waste dump
Mine waste dump
 
Ch2 before
Ch2 beforeCh2 before
Ch2 before
 
Cut & fill mining method
Cut & fill mining methodCut & fill mining method
Cut & fill mining method
 
Underground mining method natural support and caving
Underground mining method natural support and cavingUnderground mining method natural support and caving
Underground mining method natural support and caving
 
Shaft sinking 2
Shaft  sinking 2Shaft  sinking 2
Shaft sinking 2
 
Underground mining system
Underground mining systemUnderground mining system
Underground mining system
 
BLOCK CAVING ATRI.ppt
BLOCK CAVING ATRI.pptBLOCK CAVING ATRI.ppt
BLOCK CAVING ATRI.ppt
 
Topic 7-mining methods-part iii -surface mining- placer mining
Topic 7-mining methods-part iii -surface mining- placer miningTopic 7-mining methods-part iii -surface mining- placer mining
Topic 7-mining methods-part iii -surface mining- placer mining
 
geotechnical design for dilution control in underground mining
geotechnical design for dilution control in underground mininggeotechnical design for dilution control in underground mining
geotechnical design for dilution control in underground mining
 
Advance Construction equipment's reports
Advance Construction equipment's reports Advance Construction equipment's reports
Advance Construction equipment's reports
 
Mining terminology
Mining terminologyMining terminology
Mining terminology
 
Sublevel stoping..Underground mining methods
Sublevel stoping..Underground mining methodsSublevel stoping..Underground mining methods
Sublevel stoping..Underground mining methods
 
2General Element of Mining.pptx
2General Element of Mining.pptx2General Element of Mining.pptx
2General Element of Mining.pptx
 
PDF document lecture 3.pdf
PDF document lecture 3.pdfPDF document lecture 3.pdf
PDF document lecture 3.pdf
 

More from Geology Department, Faculty of Science, Tanta University

More from Geology Department, Faculty of Science, Tanta University (20)

ESSENTIALS OF IRON ORE DEPOSITS and INDUSTRIES.pdf
ESSENTIALS OF IRON ORE DEPOSITS and INDUSTRIES.pdfESSENTIALS OF IRON ORE DEPOSITS and INDUSTRIES.pdf
ESSENTIALS OF IRON ORE DEPOSITS and INDUSTRIES.pdf
 
Minerals phase transformation by hydrogen reduction.pdf
Minerals phase transformation by hydrogen reduction.pdfMinerals phase transformation by hydrogen reduction.pdf
Minerals phase transformation by hydrogen reduction.pdf
 
Magnetization Roasting of Refractory Iron.pdf
Magnetization Roasting of Refractory Iron.pdfMagnetization Roasting of Refractory Iron.pdf
Magnetization Roasting of Refractory Iron.pdf
 
GLOBAL IRON ORE.pdf
GLOBAL IRON ORE.pdfGLOBAL IRON ORE.pdf
GLOBAL IRON ORE.pdf
 
Ferrous Scrap FUTURE.pdf
Ferrous Scrap  FUTURE.pdfFerrous Scrap  FUTURE.pdf
Ferrous Scrap FUTURE.pdf
 
Pelletizing Process.pdf
Pelletizing Process.pdfPelletizing Process.pdf
Pelletizing Process.pdf
 
Direct Reduced Iron-Production.pdf
Direct Reduced Iron-Production.pdfDirect Reduced Iron-Production.pdf
Direct Reduced Iron-Production.pdf
 
A REVIEW OF IRONMAKING BY DIRECT REDUCTION PROCESSES.pdf
A REVIEW OF IRONMAKING BY DIRECT REDUCTION PROCESSES.pdfA REVIEW OF IRONMAKING BY DIRECT REDUCTION PROCESSES.pdf
A REVIEW OF IRONMAKING BY DIRECT REDUCTION PROCESSES.pdf
 
IRONWORKS.pdf
IRONWORKS.pdfIRONWORKS.pdf
IRONWORKS.pdf
 
ENRICHMENT IRON BY REDUCTION ROASTING-MAGNETIC SEPARATION.pdf
ENRICHMENT IRON BY REDUCTION ROASTING-MAGNETIC SEPARATION.pdfENRICHMENT IRON BY REDUCTION ROASTING-MAGNETIC SEPARATION.pdf
ENRICHMENT IRON BY REDUCTION ROASTING-MAGNETIC SEPARATION.pdf
 
Processes for phosphorus removal from iron ore -.pdf
Processes for phosphorus removal from iron ore -.pdfProcesses for phosphorus removal from iron ore -.pdf
Processes for phosphorus removal from iron ore -.pdf
 
Iron Types-HBI-DRI.pdf
Iron Types-HBI-DRI.pdfIron Types-HBI-DRI.pdf
Iron Types-HBI-DRI.pdf
 
IRON ORE DEPOSITS.pdf
IRON ORE DEPOSITS.pdfIRON ORE DEPOSITS.pdf
IRON ORE DEPOSITS.pdf
 
STEEL INDUSTRY IN EGYPT-Companies and Markets.pdf
STEEL INDUSTRY IN EGYPT-Companies and Markets.pdfSTEEL INDUSTRY IN EGYPT-Companies and Markets.pdf
STEEL INDUSTRY IN EGYPT-Companies and Markets.pdf
 
Cv english-harraz
Cv english-harrazCv english-harraz
Cv english-harraz
 
Rodruin prospecting area conf
Rodruin prospecting area confRodruin prospecting area conf
Rodruin prospecting area conf
 
Crusher; Crushing; and Classification Equipment
Crusher; Crushing; and Classification EquipmentCrusher; Crushing; and Classification Equipment
Crusher; Crushing; and Classification Equipment
 
The garnet group
The garnet groupThe garnet group
The garnet group
 
Hydrothermal alterations
Hydrothermal alterationsHydrothermal alterations
Hydrothermal alterations
 
Lecture 10 textures of ore deposits and associated features
Lecture 10 textures of ore deposits and associated featuresLecture 10 textures of ore deposits and associated features
Lecture 10 textures of ore deposits and associated features
 

Recently uploaded

General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...Poonam Aher Patil
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfSherif Taha
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...ZurliaSoop
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17Celine George
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.MaryamAhmad92
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsMebane Rash
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfNirmal Dwivedi
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxVishalSingh1417
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfagholdier
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.christianmathematics
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxJisc
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Association for Project Management
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptxMaritesTamaniVerdade
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdfQucHHunhnh
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structuredhanjurrannsibayan2
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxVishalSingh1417
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17Celine George
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxRamakrishna Reddy Bijjam
 

Recently uploaded (20)

General Principles of Intellectual Property: Concepts of Intellectual Proper...
General Principles of Intellectual Property: Concepts of Intellectual  Proper...General Principles of Intellectual Property: Concepts of Intellectual  Proper...
General Principles of Intellectual Property: Concepts of Intellectual Proper...
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdfUGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
UGC NET Paper 1 Mathematical Reasoning & Aptitude.pdf
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.This PowerPoint helps students to consider the concept of infinity.
This PowerPoint helps students to consider the concept of infinity.
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...Making communications land - Are they received and understood as intended? we...
Making communications land - Are they received and understood as intended? we...
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structure
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Unit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptxUnit-IV- Pharma. Marketing Channels.pptx
Unit-IV- Pharma. Marketing Channels.pptx
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 

Cut and Fill Stoping

  • 1. This material is intended for use in lectures, presentations and as handouts to students, and is provided in Power point format so as to allow customization for the individual needs of course instructors. Permission of the author and publisher is required for any other usage. Please see hharraz2006@yahoo.com for contact details. Topic 6: Underground Mining Methods  Cut-and-Fill stoping Hassan Z. Harraz hharraz2006@yahoo.com 2014- 2015
  • 2. Outline of Topic 6:  Introduction  Application of Cut-and-Fill (C & F) stoping  The activity cycle of the (C & F) method  Stages of the production cycle of the C & F method  Sequences of extracting ore bodies  Filling in C & F Method  About filling of stopes  Functions of filler  Types of fillers  Advantages and disadvantages of the C & F method Prof. Dr. H.Z. Harraz Presentation Cut & Fill stoping 2 We will explore all of the above in Topic 6.
  • 3. Introduction Method in which ore is removed at horizontal slices generally upwards. The ore is drilled, blown up and removed from the stope. The resulting empty after the ore to be removed, is filled with a filler ("backfill"). The filler serves as a support for the sides of the stope, and as a platform for the devices when the next slice is mined. It is a recommended method, for example, where iron ore and / or waste are slightly relevant, which restricts the size of underground excavations and allows little time between the removal and the deposition of the mineral filler. Prof. Dr. H.Z. Harraz Presentation Cut & Fill stoping 3
  • 4. Introduction  It is one of the more popular methods used for vein deposits and has recently grown in use.  It is an expensive but selective mining method, with low ore loss and dilution.[3] (i.e., allows selective mining and avoid mining of waste or low grade ore).  Is relatively expensive and therefore is done only in high grade mineralization (Because the method involves moving fill material as well as a significant amount of drilling and blasting).  It is a method of shorthole mining used in steeply dipping or It is preferred for orebodies with irregular ore zones and scattered mineralization.  It requires working at face (which is less safe than longhole stoping).  It is used:-  in mining steeply dipping orebodies in stable rock masses (primarily in steeply dipping metal deposits),  in strata with good to moderate stability, and comparatively high grade mineralization.  either fill option may be consolidated with concrete, or left unconsolidated.  Generally uses no cement  Bottom up mining method: Remove ore in horizontal slices, starting from a bottom undercut and advancing upward.  Moderate production rates.  Good resource usage.  Not stress friendly.  Moderate ground support  Ore is drilled, blasted and removed from stope.  The ore is mined in slices: As each horizontal or slightly inclined slice is taken, the voids (Opens) are backfilled with a variety of fill types to support the walls (i.e., the fill can be rock waste, tailings, cemented tailings, or other suitable materials). {(note: The fill serves both to support the stope walls and provide a working platform for equipment when the next slice is mined)}.
  • 5. Figure showing cut and fill mining method. Remove ore in horizontal slices, starting from a bottom undercut and advancing upward. As each horizontal slice is taken, the voids (Opens) are filled with a variety of fill types to support the walls. (i.e., the fill can be rock waste, tailings, cemented tailings, or other suitable materials). Ore is drilled, blasted and removed from stope Introduction
  • 6.  Because the method involves moving fill material as well as a significant amount of drilling and blasting, it is relatively expensive and therefore is done only in high grade mineralization where there is a need to be selective and avoid mining of waste or low grade ore.  It is practiced both in the overhand (upward) and in the underhand (downward) directions. i) Overhand (upward) cut and fill o is applied to ore lies underneath the working area and the roof is backfill. o involves a work area of cemented backfill while mining ore from the roof. ii) Underhand (Downward) cut and fill ore o is applied to ore lies beneath the working area and the roof is cemented backfill. o ore overlies the working area and the machines work on backfill. Note: Drift and Fill is similar to cut and fill, except it is used in ore zones which are wider than the method of drifting will allow to be mined. In this case the first drift is developed in the ore, and is backfilled using consolidated fill. The second drift is driven adjacent to the first drift. This carries on until the ore zone is mined out to its full width, at which time the second cut is started atop of the first cut. Introduction
  • 7. Application of Cut-and-Fill (C & F) stoping The C & F method is required when:  Ore Zones are irregular in shape and orientation.  Ore Is high grade and dilution control is critical.  The Need contacts between ore and waste are structurally critical but not readily visible.  The Waste rock is weak.  Ore Zones are large, but Their rock quality is weak.  Localized Underground stability is required.  Surface Disturbance must be minimized.  The Value of the ore makes recovery of economically viable support pillars.  The Reduction of surface waste storage is important.  The Need exists to advance the working platform for the upward mining of the ore body. Prof. Dr. H.Z. Harraz Presentation Cut & Fill stoping 7
  • 8. The C & F method In mining C & F generally upward (overhand) advances; there is a least common variant - C & F underhand - where the feed is from the top down. C & F advancing bottom up  Prof. Dr. H.Z. Harraz Presentation Cut & Fill stoping 8
  • 9. overhand C & F Prof. Dr. H.Z. Harraz Presentation Cut & Fill stoping 9
  • 10. a) drill-blast of a horizontal slice of ore, typically with three or four feet thick, removed the roof of the stope; b) loading and transport of ore, mechanically removed from the stope for orepass, and then to a lower horizon of transportation; c) removal of loose fragments ("cuttlefish") by the detonation and placement support / reinforcement ceiling; d) filling the floor of the stope (backfilling) with a layer of composite material varied and equal in thickness ore disassembled ceiling. The activity cycle of the C & F method involves the following steps: Prof. Dr. H.Z. Harraz Presentation Cut & Fill stoping 10
  • 11. Stages of the production cycle of the C & F method : Prof. Dr. H.Z. Harraz Presentation Cut & Fill stoping 11
  • 12. The workers perform all the activities of the production cycle in the newly opened roof of stope. So, for the method to be successful, one must control the behavior of the rock on the outskirts of the stope. This is done in several ways: by controlling the dismantling of the roof, using reinforcement / support for openings and using the stope backfill. Use of roof bolts in C & F Prof. Dr. H.Z. Harraz Presentation Cut & Fill stoping 12
  • 13. Control ceiling by cable bolts : Sequence of use : Prof. Dr. H.Z. Harraz Presentation Cut & Fill stoping 13
  • 14. C & F method is versatile (there are different configurations of extraction) applied to bodies of different geometries (shafts, inclined tabular or massive deposits) can be divided into separated by vertical pillars and horizontal blocks. Horizontal Pillar (i.e, Floor pillar) separating stopes  Prof. Dr. H.Z. Harraz Presentation Cut & Fill stoping 14
  • 15. Sequences of extracting ore bodies ... View topic in 3.4.2 : Underground Mining Methods: engineering fundamentals and international case studies. W.Hustrulid, R.Bullock, SME, 2001. Prof. Dr. H.Z. Harraz Presentation Cut & Fill stoping 15
  • 16. C & F with overhand stopes separated by vertical pillars, in this case made ​​with backfill: Prof. Dr. H.Z. Harraz Presentation Cut & Fill stoping 16
  • 17. C & F overhand with ramp and stope access orepass located in the footwall: Prof. Dr. H.Z. Harraz Presentation Cut & Fill stoping 17
  • 18. The method applies to deposits with dipping 35o to 90o, in deep or shallow bodies. Stopes may have a width ranging from 4 to 40 m. The filler allows to work in the presence of enclosing a low resistance. The ore should, however, have moderate resistance to high. Thick body being mined in plan and in section  Prof. Dr. H.Z. Harraz Presentation Cut & Fill stoping 18
  • 19. Different geometries of openings in thick ore bodies (seen in section). Prof. Dr. H.Z. Harraz Presentation Cut & Fill stoping 19
  • 20. Fig 1 Narrow body being mined: plan view (left) And section (right). Prof. Dr. H.Z. Harraz Presentation Cut & Fill stoping 20
  • 21. The C & F is a laborious method, requiring high value for the in situ ore. Some dilution is expected, which occurs when the backfill is loaded with ore in the stope (usually done by loading LHD's). Moreover, the method provides selectivity and flexibility, allowing good control of ore contents and disposal in the stope, sterile material. Also allows to follow irregular bodies during mining, due to the high degree of selectivity of the drill-blast sequence There are several benefits from an environmental standpoint, using the backfill. The integrity of the host rocks allows less affect the hydrogeology of the mined area. The possibility of subsidence at the surface is quite limited. Reduce the tailings storage areas on the surface because they can be taken back to the stopes, as backfill Prof. Dr. H.Z. Harraz Presentation Cut & Fill stoping 21
  • 22. Variant of the C & F: Avoca method Prof. Dr. H.Z. Harraz Presentation Cut & Fill stoping 22
  • 23. Filling in C & F Method About filling of stopes:  filling is done during the production cycle (and not after complete evacuation of the stope, as in SLS);  Hydraulic filling (water and sand particle size = hydraulic sand-fill) is the most common, containing 60 to 70% solids and requiring deposition techniques and special drain;  the filling with hydraulic sand-fill, the distribution for the stopes is done by piping;  The stope is filled almost to the ceiling height;  backfill needs to be the strongest, is added to the cement mixture;  When the water is drained, a good base for moving mining equipment while it is formed in the upper slice stope;  the backfill, traffic person is prevented for a few hours and the vehicle for several days. Prof. Dr. H.Z. Harraz Presentation Cut & Fill stoping 23
  • 24. Filler Models Prof. Dr. H.Z. Harraz Presentation Cut & Fill stoping 24
  • 25. Filling Functions of filler:  -preserve access to the stope;  avoid dilution of ore;  avoid subsidence on the surface;  serve as a working platform for workers in mining the next horizontal slice; The time of placing the backfill is critical because it must take the original load was exerted on the ore. Prof. Dr. H.Z. Harraz Presentation Cut & Fill stoping 25
  • 26. Types of fillers  Additional information on "backfill": read articles  Underground Mining Methods: engineering fundamentals and international case studies. W.Hustrulid, R.Bullock, SME, 2001, cap. 69. Prof. Dr. H.Z. Harraz Presentation Cut & Fill stoping 26
  • 27. Types of fillers 1) Hydraulic fill (also called slurry or sand fill) 3) Rock Fill 2) Paste fill Prof. Dr. H.Z. Harraz Presentation Cut & Fill stoping 27
  • 28. Advantages of the method  It is a versatile method and can be adapted to the ore bodies from any geometrical shape  Investments are moderated to implement the method  minimizes subsidence  High recovery and low dilution (selective method)  Waste can be taken to the basement, avoiding surface contamination  Due to the high cost of mining, is only applicable in ores of high value;  Requires hand labour intensive and more specialized;  The activity of filling complicates the production cycle, causing reduction in production;  There are risks of instability in mass if the backfill is not properly sized and applied. Disadvantages Prof. Dr. H.Z. Harraz Presentation Cut & Fill stoping 28