SlideShare a Scribd company logo
1 of 25
Download to read offline
EMTP-RV USER GROUP MEETING, DUBROVNIK, 30 APRIL 2009



Prevention of Flashover on a Double-circuit 220 kV
                      Line


      Ivo Uglešić*, A. Xemard**, V. Milardić*, B. Filipović-Grčić*

         *Faculty of Electrical Engineering and Computing
                   University of Zagreb, Croatia
                      **EDF R&D, Paris, France                       1
OUTLINE OF PRESENTATION

 INTRODUCTION
 SIMULATION OF LIGHTNING STROKES TO
  TRANSMISSION LINE
 MODELING PROCEDURE FOR TRANSIENT
  SIMULATIONS
 SIMULATION RESULTS
 CONCLUSIONS




                                       2
INTRODUCTION

- The case study is related to the improvement of the lightning
performance of a 220 kV double-circuit overhead line, which connects
the thermo power plant to the rest of the power system.
- Several double-circuit outages provoked by lightning caused the
interruption of power supply of the power plant.

 - To avoid back-flashovers due to lightning strokes to tower or
overhead shielding wires, the tower footing resistance should be as
low as possible.
- Installation of unbalanced insulation on a double-circuit line is one of
possible solution for suppression of double-circuit simultaneous
faults.
- Installation of line surge arresters (LSA).

                                                                         3
SIMULATION OF LIGHTNING STROKES TO TRANSMISSION LINE

The goal of the simulation is to determine the distribution of lightning
current amplitudes which strike HV transmission line towers and shield
wires or the phase conductors directly.

The Monte Carlo method is used – reproducing numerically a
stochastic problem.

The log–normal distribution of lightning current amplitude:




 P - probability of occurrence of lightning current amplitude
 higher than I.
                                                                      4
SIMULATION OF LIGHTNING STROKES TO TRANSMISSION LINE

The general expression for the striking distance:



R - striking distance,
I - lightning current amplitude,
a - constant [3.3 – 10.6],
b - constant [0.5 – 0.85].

In calculations is used a=7.2, b=0.65.




                                                       5
SIMULATION OF LIGHTNING STROKES TO TRANSMISSION LINE




                           6,7 m
                           6,7 m
             4,5 m
       A       4,5 m

                           6,0 m
                           6,0 m




                 6,5 m
B                  6,5 m
                           6,0mm
                           6,0




      C      5,0 m
               5,0 m




    17,10m


    19,50m


    22,00m



    24,60m



    27,30m



    30,00m




3D model of the part of the studied transmission line
                                                        6
SIMULATION OF LIGHTNING STROKES TO TRANSMISSION LINE

-Total number of simulations 37932,
-1000 simulations finished with phase conductor strikes,
-25635 ground strikes,
-11297 with shielding wire and tower strikes,
-shielding failure occurs in 8.85% cases.

According to statistical calculation, the following characteristics of
the crest values of the current for lightning striking phase conductors
are calculated:
- average value: 15.40 kA,
- variance: 98.36 kA,
- standard deviation: 9.92 kA,
- maximal phase conductor strike current: 42.80 kA,
                                                                        7
- critical current: 47.30 kA.
SIMULATION OF LIGHTNING STROKES TO TRANSMISSION LINE

                                                Distribution of lightning currents striking phase conductors
               0,1


              0,09


              0,08


              0,07


              0,06
Probability




              0,05


              0,04


              0,03


              0,02


              0,01


                0
                      1-3   3-5   5-7   7-9   9-11 11-13 13-15 15-17 17-19 19-21 21-23 23-25 25-27 27-29 29-31 31-33 33-35 35-37 37-39 39-41   >41
                                                                              Classes (kA)



                     Distribution of lightning currents striking phase conductors                                                                    8
SIMULATION OF LIGHTNING STROKES TO TRANSMISSION LINE
                                             Distribution of lightning currents striking top of towers or shielding wire
              0,25




               0,2




              0,15
Probability




               0,1




              0,05




                0
                        0     -20     -30     - 40     -50     -60     -70     -80     -90      0          0          0          0          0          0          0          0          0          0
                     1-1    10      20      30       40      50      60      70      80      -10       -11        -12        -13        -14        -15        -16        -17        -18        -19
                                                                                           90     1 00       1 10       1 20       1 30       1 40       1 50       1 60       1 70       1 80
                                                                                           Classes (kA)



               Distribution of lightning currents striking top of towers or shielding wire
                                                                                        9
MODELING PROCEDURE FOR TRANSIENT SIMULATIONS

The lightning stroke hitting a tower or a phase conductor can be
replaced by a surge current generator and a resistor (Norton
generator).
The CIGRE Lightning Current Waveform model can approximate well
the concave form of the lightning current front.

The transmission line, conductors and earth wire is represented by
several multi-phase untransposed distributed parameter line spans at
both sides of the point of the lightning stroke impact.

Tower surge impedances are calculated using equation:



                                                                   10
MODELING PROCEDURE FOR TRANSIENT SIMULATIONS

Phase voltages at the instant at which a lightning stroke impacts the
line must be included.

Insulators are represented using the area criterion that involves
determining the instant of breakdown using the formula:
                 t
                                  k
                      U      U0 d         DE
                 T0
 U(τ) is the voltage applied at time t,
 U0 is a minimum voltage to be exceeded before any breakdown
    process can start or continue,
 k and U0 and DE are constants corresponding to an air gap
    configuration and overvoltage polarity,
 T0 is the time from which U(τ) > U0.
                                                                        11
MODELING PROCEDURE FOR TRANSIENT SIMULATIONS

Tower footing resistances are modelled taking into account ionization:




R0 - footing resistance at low current and low frequency, i.e. 50 Hz,
I - stroke current through the resistance,
Ig - limiting current to initiate sufficient soil ionization.




ρ - soil resistivity m ;
E0 - soil ionization gradient, recommended value: 400 kV/m .
                                                                        12
MODELING PROCEDURE FOR TRANSIENT SIMULATIONS




EMTP-RV Model of footing resistance ionization
                                                 13
MODELING PROCEDURE FOR TRANSIENT SIMULATIONS

      The model of gapless type LSA includes non-linear and dynamic
      behaviour of the arrester.
               800



               700



               600



               500
Voltage (kV)




               400



               300



               200



               100



                0
                     0,1             1                      10               100
                                             Current (kA)


               U-I characteristic of surge arrester for the 220 kV line (Ur=210 kV)   14
Shield wire




                                                  lower
                                                                   upper

                                                          middle
                                               Transmision line
                                                    10 km




                                                                           1
                                           Z=139.3 Ω


                                               Transmision line
                                                    276 m


                                           Z=139.3 Ω                       2
                                               Transmision line
                                                    343 m
                                                                           3




                                           Z=135.2 Ω


                                               Transmision line
                                                    289 m
                                                                           4




                                           Z=139.3 Ω


                                               Transmision line
                                                    402 m
                                                                           5




     Model of 220 kV double-circuit line
                                           Z=139.3 Ω
                                                                                         1000 Ω




                                               Transmision line
                                                    295 m
                                                                             6




                                           Z=139.3 Ω
                                                                                            Stroke to tower




                                               Transmision line
                                                    213 m
                                                                                                     31 kA, 72 kA,
                                                                                                    96 kA, 138 kA

                                                                             7




                                           Z=135.2 Ω


                                               Transmision line
                                                                                                                     MODELING PROCEDURE FOR TRANSIENT SIMULATIONS




                                                    459 m
                                                                             8




                                           Z=139.3 Ω

                                               Transmision line
                                                    350 m
                                                                             9




                                           Z=139.3 Ω
15




                                               Transmision line
                                                    10 km
SIMULATION RESULTS

When a lightning strikes the top of a 220 kV tower the occurrence of
the back-flashover depends on many parameters:
- peak current magnitude and maximal steepness,
- tower footing resistance,
- flashover voltage of insulation clearances,
- magnitude and phase angle of the voltage,
- atmospheric condition (rain, snow, pressure, temperature, humidity)
etc.




                                                                   16
SIMULATION RESULTS
Back-flashovers in relation to the lightning current magnitude and the
footing resistance of a tower




                                                                     17
SIMULATION RESULTS
Back-flashovers in relation to the lightning current magnitude and the
footing resistance of a tower (LSA in the upper phase)




                                                                     18
SIMULATION RESULTS
Back-flashovers in relation to the lightning current magnitude and the
footing resistance of a tower (LSA in the middle phase)




                                                                     19
SIMULATION RESULTS
Back-flashovers in relation to the lightning current magnitude and the
footing resistance of a tower (LSA in the lower phase)




                                                                     20
SIMULATION RESULTS
Back-flashovers in relation to the lightning current magnitude and the
footing resistance of a tower (LSAs in middle and lower phases)




                                                                     21
SIMULATION RESULTS
                                                             7
                                                                      NO LSA
                                                                      LSA in B
Number of Back-flashover Rates (annual, per 100km of line)




                                                                      LSA in C
                                                             6        LSAs in B and C



                                                             5



                                                             4



                                                             3



                                                             2



                                                             1



                                                             0
                                                                 0   10     20          30   40   50   60     70      80      90   100   110   120   130   140   150
                                                                                                        Tower resistance (Ohms)


                                                             Back-flashover rate of one circuit of the 220 kV line: not protected by
                                                             LSAs, protected by LSA in middle phase (B), LSA in lower phase (C)
                                                                                                                                     22
                                                             and LSAs in lower and middle phases (B and C)
SIMULATION RESULTS
                                                        8
                                                                 NO LSA
                                                                 LSA in B
                                                        7        LSA in C
Number of Flashover Rates (annual, per 100km of line)




                                                                 LSAs in B and C


                                                        6



                                                        5



                                                        4



                                                        3



                                                        2



                                                        1



                                                        0
                                                            0   10     20          30   40   50   60     70      80      90   100   110   120   130   140   150
                                                                                                   Tower resistance (Ohms)


      Total flashover rate (back and shield failure) of one circuit of the 220 kV
      line: not protected by LSAs, protected by LSA in middle phase (B), LSA
      in lower phase (C) and LSAs in lower and middle phases (B and C) 23
CONCLUSIONS

The following recommendations can be given for the purpose of
optimization of the number of LSAs:
-Improvement of footing resistances on towers if economically
justified.
-No LSA (tower footing resistance < 21 ).
-LSA in the lower phase (tower footing resistance > 21 and < 47 ).
-LSAs in the middle and lower phases (tower footing resistance > 47
   < 150 ).
-Arresters installed in all 3 phases at selected towers with tower
footing resistance > 150 (the installation of three LSAs in one circuit
will only prevent back-flashover in that circuit on that tower and back-
flashovers could occur on neighboring towers).


                                                                      24
EMTP-RV USER GROUP MEETING, DUBROVNIK, 30 APRIL 2009



Prevention of Flashover on a Double-circuit 220 kV
                      Line


      Ivo Uglešić*, A. Xemard**, V. Milardić*, B. Filipović-Grčić*

         *Faculty of Electrical Engineering and Computing
                   University of Zagreb, Croatia
                      **EDF R&D, Paris, France                       25

More Related Content

What's hot

Transmission line By Lipun
Transmission line By LipunTransmission line By Lipun
Transmission line By LipunNanigopal Jena
 
Class06 transmission line_basics
Class06 transmission line_basicsClass06 transmission line_basics
Class06 transmission line_basicsbhaavan22
 
Lect2 up250 (100328)
Lect2 up250 (100328)Lect2 up250 (100328)
Lect2 up250 (100328)aicdesign
 
SPICE MODEL of RF-500TB-0.5V in SPICE PARK
SPICE MODEL of RF-500TB-0.5V in SPICE PARKSPICE MODEL of RF-500TB-0.5V in SPICE PARK
SPICE MODEL of RF-500TB-0.5V in SPICE PARKTsuyoshi Horigome
 
Transmission line analysis
Transmission line analysisTransmission line analysis
Transmission line analysisAnurag Anupam
 
Ferrite Specifications and ACME Ferrites (2)
Ferrite Specifications and ACME Ferrites (2)Ferrite Specifications and ACME Ferrites (2)
Ferrite Specifications and ACME Ferrites (2)Ray Lai
 
Microwave Devices Lecture05
Microwave Devices Lecture05Microwave Devices Lecture05
Microwave Devices Lecture05Amr Al-Awamry
 
201606_Ferrites,_CMC,_and_Power_Transformer_(1)e
201606_Ferrites,_CMC,_and_Power_Transformer_(1)e201606_Ferrites,_CMC,_and_Power_Transformer_(1)e
201606_Ferrites,_CMC,_and_Power_Transformer_(1)eRay Lai
 
Lect2 up330 (100328)
Lect2 up330 (100328)Lect2 up330 (100328)
Lect2 up330 (100328)aicdesign
 
Ferrite Specifications and ACME Ferrites (4)
Ferrite Specifications and ACME Ferrites (4)Ferrite Specifications and ACME Ferrites (4)
Ferrite Specifications and ACME Ferrites (4)Ray Lai
 
DCモーターのシンプルモデルの解説書(PSpice)
DCモーターのシンプルモデルの解説書(PSpice)DCモーターのシンプルモデルの解説書(PSpice)
DCモーターのシンプルモデルの解説書(PSpice)spicepark
 
Ec 55 transmission lines and waveguides b
Ec 55 transmission lines and waveguides bEc 55 transmission lines and waveguides b
Ec 55 transmission lines and waveguides barularumugam09
 
Simple Model of DC Motor using LTspice
Simple Model of DC Motor using LTspiceSimple Model of DC Motor using LTspice
Simple Model of DC Motor using LTspiceTsuyoshi Horigome
 
Transmission Line Basics
Transmission Line BasicsTransmission Line Basics
Transmission Line BasicsJohn Williams
 

What's hot (20)

Chap2 s11b
Chap2 s11bChap2 s11b
Chap2 s11b
 
Transmission line By Lipun
Transmission line By LipunTransmission line By Lipun
Transmission line By Lipun
 
Class06 transmission line_basics
Class06 transmission line_basicsClass06 transmission line_basics
Class06 transmission line_basics
 
Lect2 up250 (100328)
Lect2 up250 (100328)Lect2 up250 (100328)
Lect2 up250 (100328)
 
SPICE MODEL of RF-500TB-0.5V in SPICE PARK
SPICE MODEL of RF-500TB-0.5V in SPICE PARKSPICE MODEL of RF-500TB-0.5V in SPICE PARK
SPICE MODEL of RF-500TB-0.5V in SPICE PARK
 
Impedance Matching
Impedance MatchingImpedance Matching
Impedance Matching
 
Transmission line analysis
Transmission line analysisTransmission line analysis
Transmission line analysis
 
Waveguide
WaveguideWaveguide
Waveguide
 
Ferrite Specifications and ACME Ferrites (2)
Ferrite Specifications and ACME Ferrites (2)Ferrite Specifications and ACME Ferrites (2)
Ferrite Specifications and ACME Ferrites (2)
 
Microwave Devices Lecture05
Microwave Devices Lecture05Microwave Devices Lecture05
Microwave Devices Lecture05
 
201606_Ferrites,_CMC,_and_Power_Transformer_(1)e
201606_Ferrites,_CMC,_and_Power_Transformer_(1)e201606_Ferrites,_CMC,_and_Power_Transformer_(1)e
201606_Ferrites,_CMC,_and_Power_Transformer_(1)e
 
Seminario - Würth Elektronik
Seminario - Würth ElektronikSeminario - Würth Elektronik
Seminario - Würth Elektronik
 
Lect2 up330 (100328)
Lect2 up330 (100328)Lect2 up330 (100328)
Lect2 up330 (100328)
 
Ferrite Specifications and ACME Ferrites (4)
Ferrite Specifications and ACME Ferrites (4)Ferrite Specifications and ACME Ferrites (4)
Ferrite Specifications and ACME Ferrites (4)
 
Microwave Systems
Microwave SystemsMicrowave Systems
Microwave Systems
 
DCモーターのシンプルモデルの解説書(PSpice)
DCモーターのシンプルモデルの解説書(PSpice)DCモーターのシンプルモデルの解説書(PSpice)
DCモーターのシンプルモデルの解説書(PSpice)
 
Ec 55 transmission lines and waveguides b
Ec 55 transmission lines and waveguides bEc 55 transmission lines and waveguides b
Ec 55 transmission lines and waveguides b
 
Simple Model of DC Motor using LTspice
Simple Model of DC Motor using LTspiceSimple Model of DC Motor using LTspice
Simple Model of DC Motor using LTspice
 
linesense
linesenselinesense
linesense
 
Transmission Line Basics
Transmission Line BasicsTransmission Line Basics
Transmission Line Basics
 

Similar to Univ Of Zagreb Uglesic Prevention Of Flashover

Cable sizing to withstand short-circuit current - Example
Cable sizing to withstand short-circuit current - ExampleCable sizing to withstand short-circuit current - Example
Cable sizing to withstand short-circuit current - ExampleLeonardo ENERGY
 
Transients Caused by Switching of 420 kV Three-Phase Variable Shunt Reactor
Transients Caused by Switching of 420 kV Three-Phase Variable Shunt ReactorTransients Caused by Switching of 420 kV Three-Phase Variable Shunt Reactor
Transients Caused by Switching of 420 kV Three-Phase Variable Shunt ReactorBérengère VIGNAUX
 
General condition-relating-to-electricity new
General condition-relating-to-electricity newGeneral condition-relating-to-electricity new
General condition-relating-to-electricity newDineshsenthil
 
Circuit-based method for extracting the resistive leakage current of metal ox...
Circuit-based method for extracting the resistive leakage current of metal ox...Circuit-based method for extracting the resistive leakage current of metal ox...
Circuit-based method for extracting the resistive leakage current of metal ox...journalBEEI
 
Ferroresonance Conditions in Wind Parks
Ferroresonance Conditions in Wind Parks Ferroresonance Conditions in Wind Parks
Ferroresonance Conditions in Wind Parks Bérengère VIGNAUX
 
SEBA KMT Cable Fault Locators, Surge Generators (Thumpers) - SEBA KMT Cable F...
SEBA KMT Cable Fault Locators, Surge Generators (Thumpers) - SEBA KMT Cable F...SEBA KMT Cable Fault Locators, Surge Generators (Thumpers) - SEBA KMT Cable F...
SEBA KMT Cable Fault Locators, Surge Generators (Thumpers) - SEBA KMT Cable F...Thorne & Derrick International
 
Powerelectronics Chapter7 090331060223 Phpapp02
Powerelectronics Chapter7 090331060223 Phpapp02Powerelectronics Chapter7 090331060223 Phpapp02
Powerelectronics Chapter7 090331060223 Phpapp02kuppam engg college
 
Power Electronics Chapter 7
Power Electronics  Chapter 7Power Electronics  Chapter 7
Power Electronics Chapter 7guest8ae54cfb
 
Modelling of 25 kV Electric Railway System
Modelling of 25 kV Electric Railway SystemModelling of 25 kV Electric Railway System
Modelling of 25 kV Electric Railway SystemBérengère VIGNAUX
 
Chapter 3 transmission line performance
Chapter 3  transmission line performanceChapter 3  transmission line performance
Chapter 3 transmission line performancefiraoltemesgen1
 
SWAN/DWS micro-behavioral power/gnd plane modelling.
SWAN/DWS micro-behavioral power/gnd plane modelling.SWAN/DWS micro-behavioral power/gnd plane modelling.
SWAN/DWS micro-behavioral power/gnd plane modelling.Piero Belforte
 
Transmission Line presentation______.ppt
Transmission Line presentation______.pptTransmission Line presentation______.ppt
Transmission Line presentation______.pptssuserc3b807
 
Case Study: Cyclic Voltametric Measurement
Case Study: Cyclic Voltametric MeasurementCase Study: Cyclic Voltametric Measurement
Case Study: Cyclic Voltametric MeasurementHasnain Ali
 
TDR-BASED DWS MODELING OF PASSIVE COMPONENTS
TDR-BASED DWS MODELING OF PASSIVE COMPONENTSTDR-BASED DWS MODELING OF PASSIVE COMPONENTS
TDR-BASED DWS MODELING OF PASSIVE COMPONENTSPiero Belforte
 
Short circuit test in brief
Short circuit test in briefShort circuit test in brief
Short circuit test in briefMuthar Hussain
 

Similar to Univ Of Zagreb Uglesic Prevention Of Flashover (20)

Cable sizing to withstand short-circuit current - Example
Cable sizing to withstand short-circuit current - ExampleCable sizing to withstand short-circuit current - Example
Cable sizing to withstand short-circuit current - Example
 
Transients Caused by Switching of 420 kV Three-Phase Variable Shunt Reactor
Transients Caused by Switching of 420 kV Three-Phase Variable Shunt ReactorTransients Caused by Switching of 420 kV Three-Phase Variable Shunt Reactor
Transients Caused by Switching of 420 kV Three-Phase Variable Shunt Reactor
 
General condition-relating-to-electricity new
General condition-relating-to-electricity newGeneral condition-relating-to-electricity new
General condition-relating-to-electricity new
 
Ehv ac transmission line
Ehv ac transmission lineEhv ac transmission line
Ehv ac transmission line
 
Circuit-based method for extracting the resistive leakage current of metal ox...
Circuit-based method for extracting the resistive leakage current of metal ox...Circuit-based method for extracting the resistive leakage current of metal ox...
Circuit-based method for extracting the resistive leakage current of metal ox...
 
H010526975
H010526975H010526975
H010526975
 
Ferroresonance Conditions in Wind Parks
Ferroresonance Conditions in Wind Parks Ferroresonance Conditions in Wind Parks
Ferroresonance Conditions in Wind Parks
 
SEBA KMT Cable Fault Locators, Surge Generators (Thumpers) - SEBA KMT Cable F...
SEBA KMT Cable Fault Locators, Surge Generators (Thumpers) - SEBA KMT Cable F...SEBA KMT Cable Fault Locators, Surge Generators (Thumpers) - SEBA KMT Cable F...
SEBA KMT Cable Fault Locators, Surge Generators (Thumpers) - SEBA KMT Cable F...
 
Ce31533536
Ce31533536Ce31533536
Ce31533536
 
Powerelectronics Chapter7 090331060223 Phpapp02
Powerelectronics Chapter7 090331060223 Phpapp02Powerelectronics Chapter7 090331060223 Phpapp02
Powerelectronics Chapter7 090331060223 Phpapp02
 
Power Electronics Chapter 7
Power Electronics  Chapter 7Power Electronics  Chapter 7
Power Electronics Chapter 7
 
Modelling of 25 kV Electric Railway System
Modelling of 25 kV Electric Railway SystemModelling of 25 kV Electric Railway System
Modelling of 25 kV Electric Railway System
 
Chapter 3 transmission line performance
Chapter 3  transmission line performanceChapter 3  transmission line performance
Chapter 3 transmission line performance
 
SWAN/DWS micro-behavioral power/gnd plane modelling.
SWAN/DWS micro-behavioral power/gnd plane modelling.SWAN/DWS micro-behavioral power/gnd plane modelling.
SWAN/DWS micro-behavioral power/gnd plane modelling.
 
Transmission Line presentation______.ppt
Transmission Line presentation______.pptTransmission Line presentation______.ppt
Transmission Line presentation______.ppt
 
Case Study: Cyclic Voltametric Measurement
Case Study: Cyclic Voltametric MeasurementCase Study: Cyclic Voltametric Measurement
Case Study: Cyclic Voltametric Measurement
 
TDR-BASED DWS MODELING OF PASSIVE COMPONENTS
TDR-BASED DWS MODELING OF PASSIVE COMPONENTSTDR-BASED DWS MODELING OF PASSIVE COMPONENTS
TDR-BASED DWS MODELING OF PASSIVE COMPONENTS
 
Short circuit test in brief
Short circuit test in briefShort circuit test in brief
Short circuit test in brief
 
Transformers Protection
Transformers ProtectionTransformers Protection
Transformers Protection
 
PFC - Ducati ANIE 2009
PFC - Ducati ANIE 2009PFC - Ducati ANIE 2009
PFC - Ducati ANIE 2009
 

More from corinne rocherieux

Rte Lebranchu Compensation And Transient Studies Onalong Ehv Overheadline
Rte Lebranchu Compensation And Transient Studies Onalong Ehv OverheadlineRte Lebranchu Compensation And Transient Studies Onalong Ehv Overheadline
Rte Lebranchu Compensation And Transient Studies Onalong Ehv Overheadlinecorinne rocherieux
 
Rte Dufour Protection Systemforactives Substation
Rte Dufour Protection Systemforactives SubstationRte Dufour Protection Systemforactives Substation
Rte Dufour Protection Systemforactives Substationcorinne rocherieux
 
Edf R&D Xemard Coupling Between Transmission Underground Cables And Pipelines
Edf R&D Xemard Coupling Between Transmission Underground Cables And PipelinesEdf R&D Xemard Coupling Between Transmission Underground Cables And Pipelines
Edf R&D Xemard Coupling Between Transmission Underground Cables And Pipelinescorinne rocherieux
 
Hydro Quebec Roumy Interfacing Emtp Rv Withothersoftware Using C++
Hydro Quebec Roumy Interfacing Emtp Rv Withothersoftware Using C++Hydro Quebec Roumy Interfacing Emtp Rv Withothersoftware Using C++
Hydro Quebec Roumy Interfacing Emtp Rv Withothersoftware Using C++corinne rocherieux
 
Opal Rt Giroux Scrpting In Emtp Works
Opal Rt Giroux Scrpting In Emtp WorksOpal Rt Giroux Scrpting In Emtp Works
Opal Rt Giroux Scrpting In Emtp Workscorinne rocherieux
 
Emtp User Group092008 Supelec Stab Transitoire Web
Emtp User Group092008 Supelec Stab Transitoire WebEmtp User Group092008 Supelec Stab Transitoire Web
Emtp User Group092008 Supelec Stab Transitoire Webcorinne rocherieux
 
Emtp User Group092008 Sicae Raccordement Resau Web
Emtp User Group092008 Sicae Raccordement Resau WebEmtp User Group092008 Sicae Raccordement Resau Web
Emtp User Group092008 Sicae Raccordement Resau Webcorinne rocherieux
 
Emtp User Group092008 Sadovic Etudes Web
Emtp User Group092008 Sadovic Etudes WebEmtp User Group092008 Sadovic Etudes Web
Emtp User Group092008 Sadovic Etudes Webcorinne rocherieux
 
Emtp User Group092008 Rte Etudes Ttr Web
Emtp User Group092008 Rte Etudes Ttr WebEmtp User Group092008 Rte Etudes Ttr Web
Emtp User Group092008 Rte Etudes Ttr Webcorinne rocherieux
 
Emtp User Group092008 Polytechnique Montreal Nouveaux Dvpts Web
Emtp User Group092008 Polytechnique Montreal Nouveaux Dvpts WebEmtp User Group092008 Polytechnique Montreal Nouveaux Dvpts Web
Emtp User Group092008 Polytechnique Montreal Nouveaux Dvpts Webcorinne rocherieux
 
Emtp User Group092008 Idea P Vprotection Web
Emtp User Group092008 Idea P Vprotection WebEmtp User Group092008 Idea P Vprotection Web
Emtp User Group092008 Idea P Vprotection Webcorinne rocherieux
 
Emtp User Group092008 Idea P Vgeneration Web
Emtp User Group092008 Idea P Vgeneration WebEmtp User Group092008 Idea P Vgeneration Web
Emtp User Group092008 Idea P Vgeneration Webcorinne rocherieux
 
Emtp User Group092008 Edf Ttr Discordance Phase Web
Emtp User Group092008 Edf Ttr Discordance Phase WebEmtp User Group092008 Edf Ttr Discordance Phase Web
Emtp User Group092008 Edf Ttr Discordance Phase Webcorinne rocherieux
 
Emtp User Group092008 Edf Sectionneurs Web
Emtp User Group092008 Edf Sectionneurs WebEmtp User Group092008 Edf Sectionneurs Web
Emtp User Group092008 Edf Sectionneurs Webcorinne rocherieux
 
Emtp User Group092008 Edf Programme Web
Emtp User Group092008 Edf Programme WebEmtp User Group092008 Edf Programme Web
Emtp User Group092008 Edf Programme Webcorinne rocherieux
 
Etudes Raccordement Emtp 24092008
Etudes Raccordement Emtp   24092008Etudes Raccordement Emtp   24092008
Etudes Raccordement Emtp 24092008corinne rocherieux
 

More from corinne rocherieux (19)

Rte Guerrier Lips Toolbox
Rte Guerrier Lips ToolboxRte Guerrier Lips Toolbox
Rte Guerrier Lips Toolbox
 
Rte Lebranchu Compensation And Transient Studies Onalong Ehv Overheadline
Rte Lebranchu Compensation And Transient Studies Onalong Ehv OverheadlineRte Lebranchu Compensation And Transient Studies Onalong Ehv Overheadline
Rte Lebranchu Compensation And Transient Studies Onalong Ehv Overheadline
 
Rte Dufour Protection Systemforactives Substation
Rte Dufour Protection Systemforactives SubstationRte Dufour Protection Systemforactives Substation
Rte Dufour Protection Systemforactives Substation
 
Emtp Mahseredjian R&D
Emtp Mahseredjian R&DEmtp Mahseredjian R&D
Emtp Mahseredjian R&D
 
Edf R&D Xemard Coupling Between Transmission Underground Cables And Pipelines
Edf R&D Xemard Coupling Between Transmission Underground Cables And PipelinesEdf R&D Xemard Coupling Between Transmission Underground Cables And Pipelines
Edf R&D Xemard Coupling Between Transmission Underground Cables And Pipelines
 
Hydro Quebec Roumy Interfacing Emtp Rv Withothersoftware Using C++
Hydro Quebec Roumy Interfacing Emtp Rv Withothersoftware Using C++Hydro Quebec Roumy Interfacing Emtp Rv Withothersoftware Using C++
Hydro Quebec Roumy Interfacing Emtp Rv Withothersoftware Using C++
 
Opal Rt Giroux Scrpting In Emtp Works
Opal Rt Giroux Scrpting In Emtp WorksOpal Rt Giroux Scrpting In Emtp Works
Opal Rt Giroux Scrpting In Emtp Works
 
Edf R&D Dennetiere Hvdc Emtp
Edf R&D Dennetiere Hvdc EmtpEdf R&D Dennetiere Hvdc Emtp
Edf R&D Dennetiere Hvdc Emtp
 
Emtp User Group092008 Supelec Stab Transitoire Web
Emtp User Group092008 Supelec Stab Transitoire WebEmtp User Group092008 Supelec Stab Transitoire Web
Emtp User Group092008 Supelec Stab Transitoire Web
 
Emtp User Group092008 Sicae Raccordement Resau Web
Emtp User Group092008 Sicae Raccordement Resau WebEmtp User Group092008 Sicae Raccordement Resau Web
Emtp User Group092008 Sicae Raccordement Resau Web
 
Emtp User Group092008 Sadovic Etudes Web
Emtp User Group092008 Sadovic Etudes WebEmtp User Group092008 Sadovic Etudes Web
Emtp User Group092008 Sadovic Etudes Web
 
Emtp User Group092008 Rte Etudes Ttr Web
Emtp User Group092008 Rte Etudes Ttr WebEmtp User Group092008 Rte Etudes Ttr Web
Emtp User Group092008 Rte Etudes Ttr Web
 
Emtp User Group092008 Polytechnique Montreal Nouveaux Dvpts Web
Emtp User Group092008 Polytechnique Montreal Nouveaux Dvpts WebEmtp User Group092008 Polytechnique Montreal Nouveaux Dvpts Web
Emtp User Group092008 Polytechnique Montreal Nouveaux Dvpts Web
 
Emtp User Group092008 Idea P Vprotection Web
Emtp User Group092008 Idea P Vprotection WebEmtp User Group092008 Idea P Vprotection Web
Emtp User Group092008 Idea P Vprotection Web
 
Emtp User Group092008 Idea P Vgeneration Web
Emtp User Group092008 Idea P Vgeneration WebEmtp User Group092008 Idea P Vgeneration Web
Emtp User Group092008 Idea P Vgeneration Web
 
Emtp User Group092008 Edf Ttr Discordance Phase Web
Emtp User Group092008 Edf Ttr Discordance Phase WebEmtp User Group092008 Edf Ttr Discordance Phase Web
Emtp User Group092008 Edf Ttr Discordance Phase Web
 
Emtp User Group092008 Edf Sectionneurs Web
Emtp User Group092008 Edf Sectionneurs WebEmtp User Group092008 Edf Sectionneurs Web
Emtp User Group092008 Edf Sectionneurs Web
 
Emtp User Group092008 Edf Programme Web
Emtp User Group092008 Edf Programme WebEmtp User Group092008 Edf Programme Web
Emtp User Group092008 Edf Programme Web
 
Etudes Raccordement Emtp 24092008
Etudes Raccordement Emtp   24092008Etudes Raccordement Emtp   24092008
Etudes Raccordement Emtp 24092008
 

Recently uploaded

Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...DianaGray10
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoffsammart93
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Jeffrey Haguewood
 
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...apidays
 
ICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesrafiqahmad00786416
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxRustici Software
 
Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024The Digital Insurer
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century educationjfdjdjcjdnsjd
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDropbox
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyKhushali Kathiriya
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherRemote DBA Services
 
Spring Boot vs Quarkus the ultimate battle - DevoxxUK
Spring Boot vs Quarkus the ultimate battle - DevoxxUKSpring Boot vs Quarkus the ultimate battle - DevoxxUK
Spring Boot vs Quarkus the ultimate battle - DevoxxUKJago de Vreede
 
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Angeliki Cooney
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc
 
Ransomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdfRansomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdfOverkill Security
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native ApplicationsWSO2
 
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...Zilliz
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...Martijn de Jong
 
CNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In PakistanCNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In Pakistandanishmna97
 

Recently uploaded (20)

Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
Web Form Automation for Bonterra Impact Management (fka Social Solutions Apri...
 
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
Apidays New York 2024 - The Good, the Bad and the Governed by David O'Neill, ...
 
ICT role in 21st century education and its challenges
ICT role in 21st century education and its challengesICT role in 21st century education and its challenges
ICT role in 21st century education and its challenges
 
Corporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptxCorporate and higher education May webinar.pptx
Corporate and higher education May webinar.pptx
 
Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024Manulife - Insurer Transformation Award 2024
Manulife - Insurer Transformation Award 2024
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
DBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor PresentationDBX First Quarter 2024 Investor Presentation
DBX First Quarter 2024 Investor Presentation
 
Artificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : UncertaintyArtificial Intelligence Chap.5 : Uncertainty
Artificial Intelligence Chap.5 : Uncertainty
 
Strategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a FresherStrategies for Landing an Oracle DBA Job as a Fresher
Strategies for Landing an Oracle DBA Job as a Fresher
 
Spring Boot vs Quarkus the ultimate battle - DevoxxUK
Spring Boot vs Quarkus the ultimate battle - DevoxxUKSpring Boot vs Quarkus the ultimate battle - DevoxxUK
Spring Boot vs Quarkus the ultimate battle - DevoxxUK
 
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
Biography Of Angeliki Cooney | Senior Vice President Life Sciences | Albany, ...
 
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data DiscoveryTrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
TrustArc Webinar - Unlock the Power of AI-Driven Data Discovery
 
Ransomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdfRansomware_Q4_2023. The report. [EN].pdf
Ransomware_Q4_2023. The report. [EN].pdf
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
Architecting Cloud Native Applications
Architecting Cloud Native ApplicationsArchitecting Cloud Native Applications
Architecting Cloud Native Applications
 
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
Emergent Methods: Multi-lingual narrative tracking in the news - real-time ex...
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
CNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In PakistanCNIC Information System with Pakdata Cf In Pakistan
CNIC Information System with Pakdata Cf In Pakistan
 

Univ Of Zagreb Uglesic Prevention Of Flashover

  • 1. EMTP-RV USER GROUP MEETING, DUBROVNIK, 30 APRIL 2009 Prevention of Flashover on a Double-circuit 220 kV Line Ivo Uglešić*, A. Xemard**, V. Milardić*, B. Filipović-Grčić* *Faculty of Electrical Engineering and Computing University of Zagreb, Croatia **EDF R&D, Paris, France 1
  • 2. OUTLINE OF PRESENTATION  INTRODUCTION  SIMULATION OF LIGHTNING STROKES TO TRANSMISSION LINE  MODELING PROCEDURE FOR TRANSIENT SIMULATIONS  SIMULATION RESULTS  CONCLUSIONS 2
  • 3. INTRODUCTION - The case study is related to the improvement of the lightning performance of a 220 kV double-circuit overhead line, which connects the thermo power plant to the rest of the power system. - Several double-circuit outages provoked by lightning caused the interruption of power supply of the power plant. - To avoid back-flashovers due to lightning strokes to tower or overhead shielding wires, the tower footing resistance should be as low as possible. - Installation of unbalanced insulation on a double-circuit line is one of possible solution for suppression of double-circuit simultaneous faults. - Installation of line surge arresters (LSA). 3
  • 4. SIMULATION OF LIGHTNING STROKES TO TRANSMISSION LINE The goal of the simulation is to determine the distribution of lightning current amplitudes which strike HV transmission line towers and shield wires or the phase conductors directly. The Monte Carlo method is used – reproducing numerically a stochastic problem. The log–normal distribution of lightning current amplitude: P - probability of occurrence of lightning current amplitude higher than I. 4
  • 5. SIMULATION OF LIGHTNING STROKES TO TRANSMISSION LINE The general expression for the striking distance: R - striking distance, I - lightning current amplitude, a - constant [3.3 – 10.6], b - constant [0.5 – 0.85]. In calculations is used a=7.2, b=0.65. 5
  • 6. SIMULATION OF LIGHTNING STROKES TO TRANSMISSION LINE 6,7 m 6,7 m 4,5 m A 4,5 m 6,0 m 6,0 m 6,5 m B 6,5 m 6,0mm 6,0 C 5,0 m 5,0 m 17,10m 19,50m 22,00m 24,60m 27,30m 30,00m 3D model of the part of the studied transmission line 6
  • 7. SIMULATION OF LIGHTNING STROKES TO TRANSMISSION LINE -Total number of simulations 37932, -1000 simulations finished with phase conductor strikes, -25635 ground strikes, -11297 with shielding wire and tower strikes, -shielding failure occurs in 8.85% cases. According to statistical calculation, the following characteristics of the crest values of the current for lightning striking phase conductors are calculated: - average value: 15.40 kA, - variance: 98.36 kA, - standard deviation: 9.92 kA, - maximal phase conductor strike current: 42.80 kA, 7 - critical current: 47.30 kA.
  • 8. SIMULATION OF LIGHTNING STROKES TO TRANSMISSION LINE Distribution of lightning currents striking phase conductors 0,1 0,09 0,08 0,07 0,06 Probability 0,05 0,04 0,03 0,02 0,01 0 1-3 3-5 5-7 7-9 9-11 11-13 13-15 15-17 17-19 19-21 21-23 23-25 25-27 27-29 29-31 31-33 33-35 35-37 37-39 39-41 >41 Classes (kA) Distribution of lightning currents striking phase conductors 8
  • 9. SIMULATION OF LIGHTNING STROKES TO TRANSMISSION LINE Distribution of lightning currents striking top of towers or shielding wire 0,25 0,2 0,15 Probability 0,1 0,05 0 0 -20 -30 - 40 -50 -60 -70 -80 -90 0 0 0 0 0 0 0 0 0 0 1-1 10 20 30 40 50 60 70 80 -10 -11 -12 -13 -14 -15 -16 -17 -18 -19 90 1 00 1 10 1 20 1 30 1 40 1 50 1 60 1 70 1 80 Classes (kA) Distribution of lightning currents striking top of towers or shielding wire 9
  • 10. MODELING PROCEDURE FOR TRANSIENT SIMULATIONS The lightning stroke hitting a tower or a phase conductor can be replaced by a surge current generator and a resistor (Norton generator). The CIGRE Lightning Current Waveform model can approximate well the concave form of the lightning current front. The transmission line, conductors and earth wire is represented by several multi-phase untransposed distributed parameter line spans at both sides of the point of the lightning stroke impact. Tower surge impedances are calculated using equation: 10
  • 11. MODELING PROCEDURE FOR TRANSIENT SIMULATIONS Phase voltages at the instant at which a lightning stroke impacts the line must be included. Insulators are represented using the area criterion that involves determining the instant of breakdown using the formula: t k U U0 d DE T0 U(τ) is the voltage applied at time t, U0 is a minimum voltage to be exceeded before any breakdown process can start or continue, k and U0 and DE are constants corresponding to an air gap configuration and overvoltage polarity, T0 is the time from which U(τ) > U0. 11
  • 12. MODELING PROCEDURE FOR TRANSIENT SIMULATIONS Tower footing resistances are modelled taking into account ionization: R0 - footing resistance at low current and low frequency, i.e. 50 Hz, I - stroke current through the resistance, Ig - limiting current to initiate sufficient soil ionization. ρ - soil resistivity m ; E0 - soil ionization gradient, recommended value: 400 kV/m . 12
  • 13. MODELING PROCEDURE FOR TRANSIENT SIMULATIONS EMTP-RV Model of footing resistance ionization 13
  • 14. MODELING PROCEDURE FOR TRANSIENT SIMULATIONS The model of gapless type LSA includes non-linear and dynamic behaviour of the arrester. 800 700 600 500 Voltage (kV) 400 300 200 100 0 0,1 1 10 100 Current (kA) U-I characteristic of surge arrester for the 220 kV line (Ur=210 kV) 14
  • 15. Shield wire lower upper middle Transmision line 10 km 1 Z=139.3 Ω Transmision line 276 m Z=139.3 Ω 2 Transmision line 343 m 3 Z=135.2 Ω Transmision line 289 m 4 Z=139.3 Ω Transmision line 402 m 5 Model of 220 kV double-circuit line Z=139.3 Ω 1000 Ω Transmision line 295 m 6 Z=139.3 Ω Stroke to tower Transmision line 213 m 31 kA, 72 kA, 96 kA, 138 kA 7 Z=135.2 Ω Transmision line MODELING PROCEDURE FOR TRANSIENT SIMULATIONS 459 m 8 Z=139.3 Ω Transmision line 350 m 9 Z=139.3 Ω 15 Transmision line 10 km
  • 16. SIMULATION RESULTS When a lightning strikes the top of a 220 kV tower the occurrence of the back-flashover depends on many parameters: - peak current magnitude and maximal steepness, - tower footing resistance, - flashover voltage of insulation clearances, - magnitude and phase angle of the voltage, - atmospheric condition (rain, snow, pressure, temperature, humidity) etc. 16
  • 17. SIMULATION RESULTS Back-flashovers in relation to the lightning current magnitude and the footing resistance of a tower 17
  • 18. SIMULATION RESULTS Back-flashovers in relation to the lightning current magnitude and the footing resistance of a tower (LSA in the upper phase) 18
  • 19. SIMULATION RESULTS Back-flashovers in relation to the lightning current magnitude and the footing resistance of a tower (LSA in the middle phase) 19
  • 20. SIMULATION RESULTS Back-flashovers in relation to the lightning current magnitude and the footing resistance of a tower (LSA in the lower phase) 20
  • 21. SIMULATION RESULTS Back-flashovers in relation to the lightning current magnitude and the footing resistance of a tower (LSAs in middle and lower phases) 21
  • 22. SIMULATION RESULTS 7 NO LSA LSA in B Number of Back-flashover Rates (annual, per 100km of line) LSA in C 6 LSAs in B and C 5 4 3 2 1 0 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 Tower resistance (Ohms) Back-flashover rate of one circuit of the 220 kV line: not protected by LSAs, protected by LSA in middle phase (B), LSA in lower phase (C) 22 and LSAs in lower and middle phases (B and C)
  • 23. SIMULATION RESULTS 8 NO LSA LSA in B 7 LSA in C Number of Flashover Rates (annual, per 100km of line) LSAs in B and C 6 5 4 3 2 1 0 0 10 20 30 40 50 60 70 80 90 100 110 120 130 140 150 Tower resistance (Ohms) Total flashover rate (back and shield failure) of one circuit of the 220 kV line: not protected by LSAs, protected by LSA in middle phase (B), LSA in lower phase (C) and LSAs in lower and middle phases (B and C) 23
  • 24. CONCLUSIONS The following recommendations can be given for the purpose of optimization of the number of LSAs: -Improvement of footing resistances on towers if economically justified. -No LSA (tower footing resistance < 21 ). -LSA in the lower phase (tower footing resistance > 21 and < 47 ). -LSAs in the middle and lower phases (tower footing resistance > 47 < 150 ). -Arresters installed in all 3 phases at selected towers with tower footing resistance > 150 (the installation of three LSAs in one circuit will only prevent back-flashover in that circuit on that tower and back- flashovers could occur on neighboring towers). 24
  • 25. EMTP-RV USER GROUP MEETING, DUBROVNIK, 30 APRIL 2009 Prevention of Flashover on a Double-circuit 220 kV Line Ivo Uglešić*, A. Xemard**, V. Milardić*, B. Filipović-Grčić* *Faculty of Electrical Engineering and Computing University of Zagreb, Croatia **EDF R&D, Paris, France 25