SlideShare a Scribd company logo
1 of 2
Download to read offline
ASIA BREWERY PROJECT –
CABUYAO, LAGUNA, PHILIPPINES
305,3/FOneCorporatePlaza,845ArnaizAve.MakatiCity,Philippines
CLIENT NAME:
AB Nutribev Corp.
PROJECT VALUE:
USD 38 Million
SERVICES PROVIDED:
Master Planning, Turnkey
Construction Management
Serices & Concept Design
Services including
Architectural, Civil, Process &
Packaging Integration for the
Entire Facility
Asia Brewery is a diversified beverage company of the LT Group Inc.
Among its beverage products are beer, bottled water, iced tea drinks, sports
drinks and alcohol mixes. In 2011, the company acquired Philippine
distribution rights for Vitamilk soy milk from Thailand's Green Spot
Company Ltd., with an option to manufacture the product under a joint-
venture agreement given certain sales milestones, thus the establishment of
AB Nutribev Corp.
AB Nutribev Corporation selected Total Developpement and Management
Inc. (TDM) to Engineering, Procurement and Construction Management
(EpCM) for their brownfield soya-based ready-to-drink manufacturing
plant.
The manufacturing facility comprises a 30,000 sq.m facility, located in
Cabuyao, Laguna, approximately 25kms. South of Manila.
The facility is designed for the phased production expansion as follows:
Phase 1: Consists of production, filling and warehousing capable of
producing 31500 RGB bottles per hour 1 (product throughput 10,000LPH).
Phase 2: The facility will be designed to allow for future expansion through
the installation of additional processing equipment and 2 x additional filling
lines up to 30,000LPH.
The project included the preparation and development of detailed
engineering design for the whole plant covering the architectural,
civil/structural, mechanical, electrical controls and plumbing; together with
the design coordination and integration of speciality process equipment.
ASIA BREWERY PROJECT –
CABUYAO, LAGUNA, PHILIPPINES
305,3/FOneCorporatePlaza,845ArnaizAve.MakatiCity,Philippines
CLIENT NAME:
AB Nutribev Corp.
PROJECT VALUE:
USD 38 Million
SERVICES PROVIDED:
Master Planning, Turnkey
Construction Management
Serices & Concept Design
Services including
Architectural, Civil, Process &
Packaging Integration for the
Entire Facility
The project tender management based upon an agreed Work Breakdown
Structure was completed in accordance with a fast track execution plan. This
methodology was adopted to allow procurement of critical and early works
packages in parallel with the engineering design development.
Project Milestone Schedule
Detailed Design: 31-Mar-15
Phase 1 (Early Work Packages) 07-May-15
Phase 2 (Main Const’n Package) 19-Oct-15
Process Equipment 29-Feb-15
Utilities Equipment 27-Nov-15
1st Production Trial Complete 31-Jan-16

More Related Content

What's hot

Group Report about San Miguel Corporation
Group Report about San Miguel CorporationGroup Report about San Miguel Corporation
Group Report about San Miguel Corporationaizellbernal
 
SAN MIGUEL CORPORATION HISTORY
SAN MIGUEL CORPORATION HISTORYSAN MIGUEL CORPORATION HISTORY
SAN MIGUEL CORPORATION HISTORYEdz Gapuz
 
Feasibility Study: Marketing , Technical and Management Aspect
Feasibility Study: Marketing , Technical and Management AspectFeasibility Study: Marketing , Technical and Management Aspect
Feasibility Study: Marketing , Technical and Management AspectLena Argosino
 
Marketing aspects of Feasibility Study
Marketing aspects of Feasibility StudyMarketing aspects of Feasibility Study
Marketing aspects of Feasibility StudyJeziel Camarillo
 
A business plan for bubble milk tea
A business plan for bubble milk teaA business plan for bubble milk tea
A business plan for bubble milk teaV Minh Tu?n
 
Consumer Buying behaviour
Consumer Buying behaviourConsumer Buying behaviour
Consumer Buying behaviourshwetarichharia
 
example of Marketing plan
example of Marketing plan example of Marketing plan
example of Marketing plan pt.mega mas
 
Picassio: Picadillong Siomai Operations Maual
Picassio: Picadillong Siomai Operations MaualPicassio: Picadillong Siomai Operations Maual
Picassio: Picadillong Siomai Operations MaualKimbo Ras
 
Global Production And Sourcing :- The Case Of Gardenia Bakery In South East Asia
Global Production And Sourcing :- The Case Of Gardenia Bakery In South East AsiaGlobal Production And Sourcing :- The Case Of Gardenia Bakery In South East Asia
Global Production And Sourcing :- The Case Of Gardenia Bakery In South East Asiainventionjournals
 
NEXTmanga Strategic Business Plan FINAL
NEXTmanga Strategic Business Plan FINALNEXTmanga Strategic Business Plan FINAL
NEXTmanga Strategic Business Plan FINALAbraham Wairisal
 
Chapter 4 Market feasibility study
Chapter 4 Market feasibility studyChapter 4 Market feasibility study
Chapter 4 Market feasibility studyAbd ELRahman ALFar
 
Feasibility Study Product Proposals
Feasibility Study Product ProposalsFeasibility Study Product Proposals
Feasibility Study Product ProposalsBryan Agustin Oculam
 
jollibee system proposal
jollibee system proposaljollibee system proposal
jollibee system proposaljhoy1221
 
Universal robina
Universal robinaUniversal robina
Universal robinaAko Yun
 
Philippine Political Culture
Philippine Political CulturePhilippine Political Culture
Philippine Political Culturebrianbelen
 
The Consumer Act of the Philippines
The Consumer Act of the PhilippinesThe Consumer Act of the Philippines
The Consumer Act of the PhilippinesMarie Alcober
 
J.CO Donut & Coffee Marketing ( Principles of Marketing )
J.CO Donut & Coffee Marketing ( Principles of Marketing )J.CO Donut & Coffee Marketing ( Principles of Marketing )
J.CO Donut & Coffee Marketing ( Principles of Marketing )Zulfadli Yusmar
 
Tide Market analysis
Tide Market analysisTide Market analysis
Tide Market analysisAkash Patil
 

What's hot (20)

Group Report about San Miguel Corporation
Group Report about San Miguel CorporationGroup Report about San Miguel Corporation
Group Report about San Miguel Corporation
 
SAN MIGUEL CORPORATION HISTORY
SAN MIGUEL CORPORATION HISTORYSAN MIGUEL CORPORATION HISTORY
SAN MIGUEL CORPORATION HISTORY
 
Feasibility Study: Marketing , Technical and Management Aspect
Feasibility Study: Marketing , Technical and Management AspectFeasibility Study: Marketing , Technical and Management Aspect
Feasibility Study: Marketing , Technical and Management Aspect
 
Marketing aspects of Feasibility Study
Marketing aspects of Feasibility StudyMarketing aspects of Feasibility Study
Marketing aspects of Feasibility Study
 
Resume ni Engr. renz kevin
Resume ni Engr. renz kevinResume ni Engr. renz kevin
Resume ni Engr. renz kevin
 
A business plan for bubble milk tea
A business plan for bubble milk teaA business plan for bubble milk tea
A business plan for bubble milk tea
 
Consumer Buying behaviour
Consumer Buying behaviourConsumer Buying behaviour
Consumer Buying behaviour
 
example of Marketing plan
example of Marketing plan example of Marketing plan
example of Marketing plan
 
Picassio: Picadillong Siomai Operations Maual
Picassio: Picadillong Siomai Operations MaualPicassio: Picadillong Siomai Operations Maual
Picassio: Picadillong Siomai Operations Maual
 
Global Production And Sourcing :- The Case Of Gardenia Bakery In South East Asia
Global Production And Sourcing :- The Case Of Gardenia Bakery In South East AsiaGlobal Production And Sourcing :- The Case Of Gardenia Bakery In South East Asia
Global Production And Sourcing :- The Case Of Gardenia Bakery In South East Asia
 
NEXTmanga Strategic Business Plan FINAL
NEXTmanga Strategic Business Plan FINALNEXTmanga Strategic Business Plan FINAL
NEXTmanga Strategic Business Plan FINAL
 
Chapter 4 Market feasibility study
Chapter 4 Market feasibility studyChapter 4 Market feasibility study
Chapter 4 Market feasibility study
 
Feasibility Study Product Proposals
Feasibility Study Product ProposalsFeasibility Study Product Proposals
Feasibility Study Product Proposals
 
jollibee system proposal
jollibee system proposaljollibee system proposal
jollibee system proposal
 
Universal robina
Universal robinaUniversal robina
Universal robina
 
13 Applied Economics.docx
13 Applied Economics.docx13 Applied Economics.docx
13 Applied Economics.docx
 
Philippine Political Culture
Philippine Political CulturePhilippine Political Culture
Philippine Political Culture
 
The Consumer Act of the Philippines
The Consumer Act of the PhilippinesThe Consumer Act of the Philippines
The Consumer Act of the Philippines
 
J.CO Donut & Coffee Marketing ( Principles of Marketing )
J.CO Donut & Coffee Marketing ( Principles of Marketing )J.CO Donut & Coffee Marketing ( Principles of Marketing )
J.CO Donut & Coffee Marketing ( Principles of Marketing )
 
Tide Market analysis
Tide Market analysisTide Market analysis
Tide Market analysis
 

Viewers also liked

Asia Pacific Breweries Project for Strategic Management in China
Asia Pacific Breweries Project for Strategic Management in ChinaAsia Pacific Breweries Project for Strategic Management in China
Asia Pacific Breweries Project for Strategic Management in ChinaDesiree Lim
 
Fx Risk Exposure Of Asia Pacific Breweries
Fx Risk Exposure Of Asia Pacific BreweriesFx Risk Exposure Of Asia Pacific Breweries
Fx Risk Exposure Of Asia Pacific BreweriesMeggiePhan
 
Coca cola case-study
Coca cola case-studyCoca cola case-study
Coca cola case-studySam Renbarger
 
V47 10 step product marketing plan tolentino
V47 10 step product marketing plan tolentinoV47 10 step product marketing plan tolentino
V47 10 step product marketing plan tolentinomikeytolentino
 
Heavy industries corporation of malaysia berhad
Heavy industries corporation of malaysia berhadHeavy industries corporation of malaysia berhad
Heavy industries corporation of malaysia berhadaldenmae
 
BPI Group Information
BPI Group InformationBPI Group Information
BPI Group Informationkathyaallen
 
San miguel flavored beer 10 step marketing plan
San miguel flavored beer 10 step marketing planSan miguel flavored beer 10 step marketing plan
San miguel flavored beer 10 step marketing plankristianf_ang
 
A Skype case study (2011)
A Skype case study (2011)A Skype case study (2011)
A Skype case study (2011)Vasia Kalavri
 
Wendy's / Case Analysis Presentation (Emerson College)
Wendy's / Case Analysis Presentation (Emerson College)Wendy's / Case Analysis Presentation (Emerson College)
Wendy's / Case Analysis Presentation (Emerson College)Yann Tong
 
02.20-21.2014, PRESENTATION, Introduction of CTL Plant Project, T. Munkhturl
02.20-21.2014, PRESENTATION, Introduction of CTL Plant Project, T. Munkhturl02.20-21.2014, PRESENTATION, Introduction of CTL Plant Project, T. Munkhturl
02.20-21.2014, PRESENTATION, Introduction of CTL Plant Project, T. MunkhturlThe Business Council of Mongolia
 
Jollibee Food Corporation-An International Expansion Case Study
Jollibee Food Corporation-An International Expansion Case StudyJollibee Food Corporation-An International Expansion Case Study
Jollibee Food Corporation-An International Expansion Case StudyKartik Mehta
 

Viewers also liked (20)

Asia brewery
Asia breweryAsia brewery
Asia brewery
 
Asia Pacific Breweries Project for Strategic Management in China
Asia Pacific Breweries Project for Strategic Management in ChinaAsia Pacific Breweries Project for Strategic Management in China
Asia Pacific Breweries Project for Strategic Management in China
 
M&A-Henieken and APB
M&A-Henieken and APBM&A-Henieken and APB
M&A-Henieken and APB
 
Fx Risk Exposure Of Asia Pacific Breweries
Fx Risk Exposure Of Asia Pacific BreweriesFx Risk Exposure Of Asia Pacific Breweries
Fx Risk Exposure Of Asia Pacific Breweries
 
Case study On KFC
Case study On KFCCase study On KFC
Case study On KFC
 
Nestlé Case Study
Nestlé Case StudyNestlé Case Study
Nestlé Case Study
 
Coca cola case-study
Coca cola case-studyCoca cola case-study
Coca cola case-study
 
2015 09-13 mcs-apb-spent_grains
2015 09-13 mcs-apb-spent_grains2015 09-13 mcs-apb-spent_grains
2015 09-13 mcs-apb-spent_grains
 
V47 10 step product marketing plan tolentino
V47 10 step product marketing plan tolentinoV47 10 step product marketing plan tolentino
V47 10 step product marketing plan tolentino
 
Heavy industries corporation of malaysia berhad
Heavy industries corporation of malaysia berhadHeavy industries corporation of malaysia berhad
Heavy industries corporation of malaysia berhad
 
BPI Group Information
BPI Group InformationBPI Group Information
BPI Group Information
 
San miguel flavored beer 10 step marketing plan
San miguel flavored beer 10 step marketing planSan miguel flavored beer 10 step marketing plan
San miguel flavored beer 10 step marketing plan
 
RC Cola
RC ColaRC Cola
RC Cola
 
Financial Issues for Multinationals
Financial Issues for MultinationalsFinancial Issues for Multinationals
Financial Issues for Multinationals
 
BPI - Bank Account
BPI - Bank AccountBPI - Bank Account
BPI - Bank Account
 
A Skype case study (2011)
A Skype case study (2011)A Skype case study (2011)
A Skype case study (2011)
 
Wendy's / Case Analysis Presentation (Emerson College)
Wendy's / Case Analysis Presentation (Emerson College)Wendy's / Case Analysis Presentation (Emerson College)
Wendy's / Case Analysis Presentation (Emerson College)
 
BPI profile
BPI profileBPI profile
BPI profile
 
02.20-21.2014, PRESENTATION, Introduction of CTL Plant Project, T. Munkhturl
02.20-21.2014, PRESENTATION, Introduction of CTL Plant Project, T. Munkhturl02.20-21.2014, PRESENTATION, Introduction of CTL Plant Project, T. Munkhturl
02.20-21.2014, PRESENTATION, Introduction of CTL Plant Project, T. Munkhturl
 
Jollibee Food Corporation-An International Expansion Case Study
Jollibee Food Corporation-An International Expansion Case StudyJollibee Food Corporation-An International Expansion Case Study
Jollibee Food Corporation-An International Expansion Case Study
 

Similar to Asia brewery Case Study

C:\Documents And Settings\User\My Documents\Log Jne\Feeling Lucky Cv\Jaime N ...
C:\Documents And Settings\User\My Documents\Log Jne\Feeling Lucky Cv\Jaime N ...C:\Documents And Settings\User\My Documents\Log Jne\Feeling Lucky Cv\Jaime N ...
C:\Documents And Settings\User\My Documents\Log Jne\Feeling Lucky Cv\Jaime N ...james espiritu
 
Rosental Alex 19 Oct09
Rosental Alex 19 Oct09Rosental Alex 19 Oct09
Rosental Alex 19 Oct09arosental
 
Resume-Robert D Demanawa 20140225 (2) (2016_08_30 04_39_44 UTC)
Resume-Robert D Demanawa 20140225 (2) (2016_08_30 04_39_44 UTC)Resume-Robert D Demanawa 20140225 (2) (2016_08_30 04_39_44 UTC)
Resume-Robert D Demanawa 20140225 (2) (2016_08_30 04_39_44 UTC)Robert Dimanawa
 
JAS Professional Resume092016internal
JAS Professional Resume092016internalJAS Professional Resume092016internal
JAS Professional Resume092016internalJeff Sperlbaum
 
Presentation - HBC-LR
Presentation - HBC-LRPresentation - HBC-LR
Presentation - HBC-LRBrooks Childs
 
Moe Aboelela - Resume - May 17 2015 - Director
Moe Aboelela - Resume - May 17 2015 - DirectorMoe Aboelela - Resume - May 17 2015 - Director
Moe Aboelela - Resume - May 17 2015 - DirectorMohamad Aboelela
 
Robert W Bezner resume 1.1
Robert W Bezner resume 1.1Robert W Bezner resume 1.1
Robert W Bezner resume 1.1Robert Bezner
 
Bruce Shaver Operations 2011
Bruce Shaver   Operations 2011Bruce Shaver   Operations 2011
Bruce Shaver Operations 2011tbshaver
 
Alaska Milk Corp Case Study
Alaska Milk Corp Case StudyAlaska Milk Corp Case Study
Alaska Milk Corp Case StudyPTSLIMITED
 
KAB Resume 201601
KAB Resume 201601KAB Resume 201601
KAB Resume 201601Kurt Busse
 

Similar to Asia brewery Case Study (20)

ADITYA KAUSHIK Resume
ADITYA KAUSHIK ResumeADITYA KAUSHIK Resume
ADITYA KAUSHIK Resume
 
Rev Bio Times
Rev Bio TimesRev Bio Times
Rev Bio Times
 
C:\Documents And Settings\User\My Documents\Log Jne\Feeling Lucky Cv\Jaime N ...
C:\Documents And Settings\User\My Documents\Log Jne\Feeling Lucky Cv\Jaime N ...C:\Documents And Settings\User\My Documents\Log Jne\Feeling Lucky Cv\Jaime N ...
C:\Documents And Settings\User\My Documents\Log Jne\Feeling Lucky Cv\Jaime N ...
 
Rosental Alex 19 Oct09
Rosental Alex 19 Oct09Rosental Alex 19 Oct09
Rosental Alex 19 Oct09
 
Resume-Robert D Demanawa 20140225 (2) (2016_08_30 04_39_44 UTC)
Resume-Robert D Demanawa 20140225 (2) (2016_08_30 04_39_44 UTC)Resume-Robert D Demanawa 20140225 (2) (2016_08_30 04_39_44 UTC)
Resume-Robert D Demanawa 20140225 (2) (2016_08_30 04_39_44 UTC)
 
JAS Professional Resume092016internal
JAS Professional Resume092016internalJAS Professional Resume092016internal
JAS Professional Resume092016internal
 
John John_ Resume
John John_ ResumeJohn John_ Resume
John John_ Resume
 
Resume- updated
Resume- updatedResume- updated
Resume- updated
 
Presentation - HBC-LR
Presentation - HBC-LRPresentation - HBC-LR
Presentation - HBC-LR
 
rolly resume
rolly resumerolly resume
rolly resume
 
MEL ROSE DRIZ Resume
MEL ROSE DRIZ ResumeMEL ROSE DRIZ Resume
MEL ROSE DRIZ Resume
 
Moe Aboelela - Resume - May 17 2015 - Director
Moe Aboelela - Resume - May 17 2015 - DirectorMoe Aboelela - Resume - May 17 2015 - Director
Moe Aboelela - Resume - May 17 2015 - Director
 
RESUME-Reynaldo Cruz Jr.
RESUME-Reynaldo Cruz Jr.RESUME-Reynaldo Cruz Jr.
RESUME-Reynaldo Cruz Jr.
 
Robert W Bezner resume 1.1
Robert W Bezner resume 1.1Robert W Bezner resume 1.1
Robert W Bezner resume 1.1
 
Bruce Shaver Operations 2011
Bruce Shaver   Operations 2011Bruce Shaver   Operations 2011
Bruce Shaver Operations 2011
 
Alaska Milk Corp Case Study
Alaska Milk Corp Case StudyAlaska Milk Corp Case Study
Alaska Milk Corp Case Study
 
Alaska Milk Corp Case Study
Alaska Milk Corp Case StudyAlaska Milk Corp Case Study
Alaska Milk Corp Case Study
 
KAB Resume 201601
KAB Resume 201601KAB Resume 201601
KAB Resume 201601
 
CVanup kumar dutta2
CVanup kumar dutta2CVanup kumar dutta2
CVanup kumar dutta2
 
dipankar bandyopadhyay_6787_GR_A
dipankar bandyopadhyay_6787_GR_Adipankar bandyopadhyay_6787_GR_A
dipankar bandyopadhyay_6787_GR_A
 

Recently uploaded

Maher Othman Interior Design Portfolio..
Maher Othman Interior Design Portfolio..Maher Othman Interior Design Portfolio..
Maher Othman Interior Design Portfolio..MaherOthman7
 
CLOUD COMPUTING SERVICES - Cloud Reference Modal
CLOUD COMPUTING SERVICES - Cloud Reference ModalCLOUD COMPUTING SERVICES - Cloud Reference Modal
CLOUD COMPUTING SERVICES - Cloud Reference ModalSwarnaSLcse
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxkalpana413121
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...josephjonse
 
Circuit Breakers for Engineering Students
Circuit Breakers for Engineering StudentsCircuit Breakers for Engineering Students
Circuit Breakers for Engineering Studentskannan348865
 
Research Methodolgy & Intellectual Property Rights Series 1
Research Methodolgy & Intellectual Property Rights Series 1Research Methodolgy & Intellectual Property Rights Series 1
Research Methodolgy & Intellectual Property Rights Series 1T.D. Shashikala
 
engineering chemistry power point presentation
engineering chemistry  power point presentationengineering chemistry  power point presentation
engineering chemistry power point presentationsj9399037128
 
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas SachpazisSeismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas SachpazisDr.Costas Sachpazis
 
Adsorption (mass transfer operations 2) ppt
Adsorption (mass transfer operations 2) pptAdsorption (mass transfer operations 2) ppt
Adsorption (mass transfer operations 2) pptjigup7320
 
Intro to Design (for Engineers) at Sydney Uni
Intro to Design (for Engineers) at Sydney UniIntro to Design (for Engineers) at Sydney Uni
Intro to Design (for Engineers) at Sydney UniR. Sosa
 
Dynamo Scripts for Task IDs and Space Naming.pptx
Dynamo Scripts for Task IDs and Space Naming.pptxDynamo Scripts for Task IDs and Space Naming.pptx
Dynamo Scripts for Task IDs and Space Naming.pptxMustafa Ahmed
 
Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxMustafa Ahmed
 
electrical installation and maintenance.
electrical installation and maintenance.electrical installation and maintenance.
electrical installation and maintenance.benjamincojr
 
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...drjose256
 
Passive Air Cooling System and Solar Water Heater.ppt
Passive Air Cooling System and Solar Water Heater.pptPassive Air Cooling System and Solar Water Heater.ppt
Passive Air Cooling System and Solar Water Heater.pptamrabdallah9
 
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and ToolsMaximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Toolssoginsider
 
Independent Solar-Powered Electric Vehicle Charging Station
Independent Solar-Powered Electric Vehicle Charging StationIndependent Solar-Powered Electric Vehicle Charging Station
Independent Solar-Powered Electric Vehicle Charging Stationsiddharthteach18
 
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024EMMANUELLEFRANCEHELI
 
UNIT-2 image enhancement.pdf Image Processing Unit 2 AKTU
UNIT-2 image enhancement.pdf Image Processing Unit 2 AKTUUNIT-2 image enhancement.pdf Image Processing Unit 2 AKTU
UNIT-2 image enhancement.pdf Image Processing Unit 2 AKTUankushspencer015
 
Final DBMS Manual (2).pdf final lab manual
Final DBMS Manual (2).pdf final lab manualFinal DBMS Manual (2).pdf final lab manual
Final DBMS Manual (2).pdf final lab manualBalamuruganV28
 

Recently uploaded (20)

Maher Othman Interior Design Portfolio..
Maher Othman Interior Design Portfolio..Maher Othman Interior Design Portfolio..
Maher Othman Interior Design Portfolio..
 
CLOUD COMPUTING SERVICES - Cloud Reference Modal
CLOUD COMPUTING SERVICES - Cloud Reference ModalCLOUD COMPUTING SERVICES - Cloud Reference Modal
CLOUD COMPUTING SERVICES - Cloud Reference Modal
 
UNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptxUNIT 4 PTRP final Convergence in probability.pptx
UNIT 4 PTRP final Convergence in probability.pptx
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
 
Circuit Breakers for Engineering Students
Circuit Breakers for Engineering StudentsCircuit Breakers for Engineering Students
Circuit Breakers for Engineering Students
 
Research Methodolgy & Intellectual Property Rights Series 1
Research Methodolgy & Intellectual Property Rights Series 1Research Methodolgy & Intellectual Property Rights Series 1
Research Methodolgy & Intellectual Property Rights Series 1
 
engineering chemistry power point presentation
engineering chemistry  power point presentationengineering chemistry  power point presentation
engineering chemistry power point presentation
 
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas SachpazisSeismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
 
Adsorption (mass transfer operations 2) ppt
Adsorption (mass transfer operations 2) pptAdsorption (mass transfer operations 2) ppt
Adsorption (mass transfer operations 2) ppt
 
Intro to Design (for Engineers) at Sydney Uni
Intro to Design (for Engineers) at Sydney UniIntro to Design (for Engineers) at Sydney Uni
Intro to Design (for Engineers) at Sydney Uni
 
Dynamo Scripts for Task IDs and Space Naming.pptx
Dynamo Scripts for Task IDs and Space Naming.pptxDynamo Scripts for Task IDs and Space Naming.pptx
Dynamo Scripts for Task IDs and Space Naming.pptx
 
Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptx
 
electrical installation and maintenance.
electrical installation and maintenance.electrical installation and maintenance.
electrical installation and maintenance.
 
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
 
Passive Air Cooling System and Solar Water Heater.ppt
Passive Air Cooling System and Solar Water Heater.pptPassive Air Cooling System and Solar Water Heater.ppt
Passive Air Cooling System and Solar Water Heater.ppt
 
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and ToolsMaximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
Maximizing Incident Investigation Efficacy in Oil & Gas: Techniques and Tools
 
Independent Solar-Powered Electric Vehicle Charging Station
Independent Solar-Powered Electric Vehicle Charging StationIndependent Solar-Powered Electric Vehicle Charging Station
Independent Solar-Powered Electric Vehicle Charging Station
 
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
NEWLETTER FRANCE HELICES/ SDS SURFACE DRIVES - MAY 2024
 
UNIT-2 image enhancement.pdf Image Processing Unit 2 AKTU
UNIT-2 image enhancement.pdf Image Processing Unit 2 AKTUUNIT-2 image enhancement.pdf Image Processing Unit 2 AKTU
UNIT-2 image enhancement.pdf Image Processing Unit 2 AKTU
 
Final DBMS Manual (2).pdf final lab manual
Final DBMS Manual (2).pdf final lab manualFinal DBMS Manual (2).pdf final lab manual
Final DBMS Manual (2).pdf final lab manual
 

Asia brewery Case Study

  • 1. ASIA BREWERY PROJECT – CABUYAO, LAGUNA, PHILIPPINES 305,3/FOneCorporatePlaza,845ArnaizAve.MakatiCity,Philippines CLIENT NAME: AB Nutribev Corp. PROJECT VALUE: USD 38 Million SERVICES PROVIDED: Master Planning, Turnkey Construction Management Serices & Concept Design Services including Architectural, Civil, Process & Packaging Integration for the Entire Facility Asia Brewery is a diversified beverage company of the LT Group Inc. Among its beverage products are beer, bottled water, iced tea drinks, sports drinks and alcohol mixes. In 2011, the company acquired Philippine distribution rights for Vitamilk soy milk from Thailand's Green Spot Company Ltd., with an option to manufacture the product under a joint- venture agreement given certain sales milestones, thus the establishment of AB Nutribev Corp. AB Nutribev Corporation selected Total Developpement and Management Inc. (TDM) to Engineering, Procurement and Construction Management (EpCM) for their brownfield soya-based ready-to-drink manufacturing plant. The manufacturing facility comprises a 30,000 sq.m facility, located in Cabuyao, Laguna, approximately 25kms. South of Manila. The facility is designed for the phased production expansion as follows: Phase 1: Consists of production, filling and warehousing capable of producing 31500 RGB bottles per hour 1 (product throughput 10,000LPH). Phase 2: The facility will be designed to allow for future expansion through the installation of additional processing equipment and 2 x additional filling lines up to 30,000LPH. The project included the preparation and development of detailed engineering design for the whole plant covering the architectural, civil/structural, mechanical, electrical controls and plumbing; together with the design coordination and integration of speciality process equipment.
  • 2. ASIA BREWERY PROJECT – CABUYAO, LAGUNA, PHILIPPINES 305,3/FOneCorporatePlaza,845ArnaizAve.MakatiCity,Philippines CLIENT NAME: AB Nutribev Corp. PROJECT VALUE: USD 38 Million SERVICES PROVIDED: Master Planning, Turnkey Construction Management Serices & Concept Design Services including Architectural, Civil, Process & Packaging Integration for the Entire Facility The project tender management based upon an agreed Work Breakdown Structure was completed in accordance with a fast track execution plan. This methodology was adopted to allow procurement of critical and early works packages in parallel with the engineering design development. Project Milestone Schedule Detailed Design: 31-Mar-15 Phase 1 (Early Work Packages) 07-May-15 Phase 2 (Main Const’n Package) 19-Oct-15 Process Equipment 29-Feb-15 Utilities Equipment 27-Nov-15 1st Production Trial Complete 31-Jan-16