1. ASIA BREWERY PROJECT –
CABUYAO, LAGUNA, PHILIPPINES
305,3/FOneCorporatePlaza,845ArnaizAve.MakatiCity,Philippines
CLIENT NAME:
AB Nutribev Corp.
PROJECT VALUE:
USD 38 Million
SERVICES PROVIDED:
Master Planning, Turnkey
Construction Management
Serices & Concept Design
Services including
Architectural, Civil, Process &
Packaging Integration for the
Entire Facility
Asia Brewery is a diversified beverage company of the LT Group Inc.
Among its beverage products are beer, bottled water, iced tea drinks, sports
drinks and alcohol mixes. In 2011, the company acquired Philippine
distribution rights for Vitamilk soy milk from Thailand's Green Spot
Company Ltd., with an option to manufacture the product under a joint-
venture agreement given certain sales milestones, thus the establishment of
AB Nutribev Corp.
AB Nutribev Corporation selected Total Developpement and Management
Inc. (TDM) to Engineering, Procurement and Construction Management
(EpCM) for their brownfield soya-based ready-to-drink manufacturing
plant.
The manufacturing facility comprises a 30,000 sq.m facility, located in
Cabuyao, Laguna, approximately 25kms. South of Manila.
The facility is designed for the phased production expansion as follows:
Phase 1: Consists of production, filling and warehousing capable of
producing 31500 RGB bottles per hour 1 (product throughput 10,000LPH).
Phase 2: The facility will be designed to allow for future expansion through
the installation of additional processing equipment and 2 x additional filling
lines up to 30,000LPH.
The project included the preparation and development of detailed
engineering design for the whole plant covering the architectural,
civil/structural, mechanical, electrical controls and plumbing; together with
the design coordination and integration of speciality process equipment.
2. ASIA BREWERY PROJECT –
CABUYAO, LAGUNA, PHILIPPINES
305,3/FOneCorporatePlaza,845ArnaizAve.MakatiCity,Philippines
CLIENT NAME:
AB Nutribev Corp.
PROJECT VALUE:
USD 38 Million
SERVICES PROVIDED:
Master Planning, Turnkey
Construction Management
Serices & Concept Design
Services including
Architectural, Civil, Process &
Packaging Integration for the
Entire Facility
The project tender management based upon an agreed Work Breakdown
Structure was completed in accordance with a fast track execution plan. This
methodology was adopted to allow procurement of critical and early works
packages in parallel with the engineering design development.
Project Milestone Schedule
Detailed Design: 31-Mar-15
Phase 1 (Early Work Packages) 07-May-15
Phase 2 (Main Const’n Package) 19-Oct-15
Process Equipment 29-Feb-15
Utilities Equipment 27-Nov-15
1st Production Trial Complete 31-Jan-16