Presentation on the status of "Achievement Under National Solar Mission (NSM)" till July'17.
The key highlight being that 13,115 MW of solar projects have been commissioned. The presentation outlays of how "100 GW" of target shall be achieved based on various schemes under progress. Also last few slides focus on Off Grid Targets under NSM.
3. National Solar Mission : Motive
Gensol Group
Initially,the Mission initiated to provide large-scale grid connected power.
Also, to reduce our dependence on fast depleting conventional sources, knowing the
fact that India has potentialmore than 750 GW from solar energy
Mission is being expanded at rapidly towards decentralized & disbursed
industrialisationto change the Rural EconomyofIndia.
Looking into the wide emergence of the solar energy applications/utilization, NSM
targets have been revised to 100 GW from 20 GW for Grid connected solar power
projects in June2015.
6. National Solar Mission : Targets Vs Achievement
Gensol Group
Phase I of NSM (2010-13) Phase-II of NSM (2013-17)
Phase-III of NSM
(2017-2022)
Segment Target
Achievements
(as on March 2013)
Target
Achievements
(as on March 2017)
Target
Grid solar power 1100 MW 1686 MW 15900 MW 10602 MW 100000 MW
Off-grid solar
applications
200 MW
252 MW Sanctioned
117 MW Installed
600 MW
713 MW Sanctioned
345 MW Installed
2000 MW
Solar Thermal
Collectors
7 Million Sq. m 7 Million Sq. m 8 Million Sq.m 5 Million Sq.m 15 Million Sq.m
NSM Targets has been divided into three phases – Phase - I, Phase II and Phase III. Achievements of Phase-I
exceeded the targetsset for the period.
7. Ambitious NSM Targets 2017-2022 : Category Wise
Gensol Group
The revised target of 100 GW is planned to be achieved in 7 years period (2015-16 to 2021-22) and broadly consist
of 40 GW Grid connected Rooftop projectsand 60 GW large and medium size ground based solar power projects
100 GW
Category I -
40 GW
40 GW –
Rooftop Solar
Category II -
60 GW
10 GW –
Small Scale
Grid projects
10 GW –
Public Sector
Undertakings
5 GW –
Large Private
Sector/IPPs
5 GW –
SECI
20 GW –
Under State
Policies
10 GW –
Ongoing
programmes
8. Grid Connected Solar Power Targets : Year- Wise
Gensol Group
Ministry has furnished Year-Wise targets to achieve 100 GW Grid connected solar power by 2022 as
follows. Government is in process of arranging with World Bank, in consultation with Ministry of
Finance, for US $ 100 million loan assistance for creating internal infrastructure of solar parks
200
4800 5000 6000 7000 8000 9000
1800
7200
10000
10000
10000
9500 8500
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
20000
2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22
MNRE Yearwise Solar Targets (MW)
MNRE Yearwise Solar Targets (MW) Roofttop MNRE Yearwise Solar Targets (MW) Ground Mounted
10. Schemes to Achieve Ambitious Targets of 100 GW
Gensol Group
1.
• To set up 300 MW of Grid connected Solar PV Power Projects by Defense Establishments under Ministry of
Defense and Para Military Forces with VGF.
2.
• To develop schemes for Solar Parks and Ultra Mega Solar Power Projects.
3.
• For development of Solar PV Power Plants on Canal Banks/ Canal Tops.
4.
• Implementation of scheme for setting up 1000 MW of Grid- Connected Solar PV Power Projects by Central
Public Sector Undertakings (CPSUS) with VGF
5.
• Implementation of Scheme for Setting up of 15000 MW of Grid connected Solar PV Power Projects under
Batch II of Phase II of National Solar Mission (by NTPC/NVVN)
6.
• Schemes for setting up of 750 MW, 2000 MW, and 5000 MW Grid connected solar power with Viability Gap
Funding through Solar Energy Corporation of India (SECI)
7.
• Development of Solar Cities Programme & Installation of Grid Connected Solar Rooftop Power Plants.
11. 1. Setting of 300 MW SPV by Defense Establishment
Gensol Group
It has been identified that cantonment and Military Stations
have high Potential of Solar Energy of approximately 5000
MWand in Ordnance Factory Boards (OFB)ofaround 950 MW
Establishments of Ministry of Defense has planned to set up
300 MW in various places like Establishments of Army, Navy,
Air Force, Ordnance Factory Board, Defense Laboratories and
Defense PSUs etc. with minimum size of the project of 1 MW.
The projects under this Scheme will mandatorily use solar
cells/modules whichare made in India.
A total of 300 MW capacity to be added in 5 years from 2014-
19
Overall, 357.5 MW Sanctioned under which 128 MW
tendered, 52 MW order placed & 7 MW projects
commissioned.
As on date, 357.5 MW has been allocated under the scheme :
Name of
Organization
Capacity (MW) Status
Ordnance Factory
Board 7 Commissioned
Bharat Electronics Ltd. 150
35 MW: Order placed, under
construction
36 MW: Tendering under process
Bharat Dynamics
Limited 25
5 MW: Order placed, under
construction
Department of
Defence 150
26 MW: Order placed, under
construction
Hindustan Aeronautics
Ltd., Nasik 15
5 MW: Tender issued, order to be
placed by 30th May,2017
Ordnance factory 5
Tendering for 15 MW to be done
by June,2017
MIDHANI 4 Tendering in process
Ordnance Factory,
Ambajhari 1.5
Tender will be issued by
June,2017
Total 357.5
14. 3. Development of Canal tops/Banks :
Targets Vs Achievements
Gensol Group
Rs.3 crore/MW or 30% of the project cost,
whichever is lower, for Canal Top SPV
projects and Rs. 1.5 crore/MW or 30% of
the project cost, whichever is lower, for
Canal Bank SPV projects will be assisted.
•Upto 40% on sanctioning of the projects.
•60% on successful commissioning of the projects.
•Service charge to SECI @1%: Rs.2.25 crore.
CFA of upto Rs.225 crore for 100 MW (50
MW on Canal Tops and 50 MW on Canal
Banks) to be disbursed over a period of
maximum 2 years post sanctioning of the
plants as under:
Allocation of 50 MW Canal-Top Solar PV Projects
State Approved capacity (MW) Commissioned Capacity (MW)
Punjab 20 5
Gujarat 10 Work in progress
Karnataka 10 In tendering process
UP 6 Work in progress
Kerala 2 2
AP 1 1
Uttarakhand 1 Work in progress
Total 50 8
Allocation of 50 MW Canal-Bank Solar PV Projects
State Approved capacity (MW) Commissioned Capacity (MW)
Uttarakhand 19 Work in progress
Gujarat 15 Work in progress
West Bengal 10 10
AP 5 5
Kerala 1 1
Total 50 16
Central Financial Assistance under the scheme-
15. 4. Solar PV Power Projects by Central Public Sector
Undertakings (CPSUS)
Gensol Group
GOI will provide VGF as under:
• a) Rs.1 Cr. /MW, if Cells and Modules for the
project are manufactured indigenously.
• b) Rs.50 Lakh /MW, if Modules for the project
are manufactured indigenously.
VGF will be released in two tranches as follows:
• a) 50% on LoI and start of installation work at
plant; and
• b) Balance 50% on successful commissioning of
the full capacity of the project (CoD)”.
The duration of implementation of the Scheme is
2015-18.
MNRE has allocated 1037.26 MW (Out of which 669 MW commissioned)
capacity to following 15 CPSUs/Govt. Organizations within the sanctioned
funds of Rs. 1000 Crorefor this scheme.
680
16.5 5
200
50
6 5.76
74
62.13%
50.00%
100.00%
0.00% 0.00% 0.00%
25.00%
11.73%
0.00%
20.00%
40.00%
60.00%
80.00%
100.00%
120.00%
0
100
200
300
400
500
600
700
800
VGF Funded in %
Capacity in MW
Capacity Wise (MW) VGF Funded Projects
Capacity Sanctioned (MW) % of VGF Amount Released
17. 6. Viability Gap Funding through Solar Energy Corporation
of India (SECI)
Gensol Group
A) 750 MW VGF Scheme
Phase-II, Batch-I (Implemented)
B) 2000 MW VGF Scheme
Phase II, Batch III (Under Implementation)
10 10 20 25 40
220
355
0
50
100
150
200
250
300
350
400
State Wise Commissioned
Capacity(MW)
500
325
400
100
1000
35 50
500
325
400
100
970
0
0
500
325
400
100
970
0
0
0
200
400
600
800
1000
1200
State Wise Allocation of Capacity (MW))
RfS issued (MW) LoI issued (MW) PPA signed (MW)
After a transparent selection and
award process, project capacity of
680 MW (out of 750 MW) could
successfully achieve financial closure.
SECI has issued RfS for 2410 MW
capacity in 7 states. LoI has been
issued for 2295 MW. PPAs have
been signed for 2295 MW.
18. 6. Viability Gap Funding through Solar Energy
Corporation of India (SECI)
Gensol Group
C) 5000 MW VGF Scheme
Phase II, Batch IV (Under Implementation)
400
300
750
450 450
200250 270
0
450
0 0
250 270
0
450
0 0
0
100
200
300
400
500
600
700
800
Gujarat Odisha Andhra
Pradesh
Maharashtra Karnataka Rajasthan
VGF Fund Granted - SPV Capacity (MW)
RfS issued (MW) LoI issued (MW) PPA signed (MW)
• The scheme is proposed to be implemented
by SECI in four tranches of 1250 MW each,
spread over four years, from 2015-16up to
FY 2018-19
• RfS has already been issued for 2850 MW
capacity in 6 states. LoI has been issued
for 970 MW. PPAs have been signed for
970 MW.
• Due to various mechanisms including the
reverse bidding on VGF as well as on tariff,
the discovered tariff has reduced from Rs.
17.91 to Rs. 2.44 per kWh that will benefit
both developer to Produce & sell through
SECI to DISCOMs
Overall, till date, 5260 MW tender issued, 3265
MW PPA signed and 80 MW Projects
commissioned for2000 MW & 5000 MW scheme
19. Bidding – Success Story…..
Gensol Group
The trends of solar tariff in India till 2016-17 are given below: The reasons for plummeting of the cost of solar power prices are as under:
(i) Conducive policies for encouraging solar sector;
(ii) Improved project structuring and technology;
(iii) Better learning curve;
(iv) Decline in cost of solar cells/modules and Cost of financing”
Global trend in solar tariff through bidding during period 2016-17 is as
given below
2.99
1.99
2.91
2.42
2.7
May-16
May-16
Aug-16
Sep-16
Oct-16
Abu
DhabiDubaiChile
Abu
DhabiMexico
World Wide Tariff (US cent/kWh) 16-17
12.1600
8.7900 8.3700
11.8250
6.5675
10.5935
4.9462
2.7986
0
5
10
15
2009-10 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17
TARIFF (RS/KWH)
Weighted Avg. Price (Rs./KWh) 2009-2017
In 16-17, steep
fall down of
the the solar
tariff recorded.
In the bidding held in February 2017 for solar projects to
be set up in Rewa Solar Park, Madhya Pradesh; the
levelized tariff has come down to Rs. 3.30 per kWh.
The solar tariff declined to Rs. 3.15 per unit in the reverse
auction done by NTPC at Kadapa Solar Park in Andhra
Pradesh in April, 2017.
The solar tariff further declined to Rs. 2.44 per unit in the
recent reverse auction done by SECI at Bhadla Phase-III
Solar Park in Rajasthan in May, 2017.
20. 7. Grid Interactive Rooftop & Small SPV Programme
Gensol Group
To meet the targets of 40 GW (Out of 100 GW) that needs to be
achieved from grid connected solar rooftops by 2022, Ministry has
introduced various subsidies have been introduced.
•The capital subsidy of 30% (70 % for special category Sates and Andaman
& Nicobar and Lakshadweep Islands) is available for residential,
institutional and social sectors.
•MNRE is implementing RTS Programme for development of 4200 MW. Out
of 4200 MW capacity, 2100 MW capacity has to be installed through CFA/
incentive in the residential, social, Government / PSU and Institutional
sectors. The balance 2100 MW is to be implemented without any subsidy.
• As on 30th April 2017, MNRE has sanctioned projects of cumulative
capacity of 2032 MWp to various State Nodal Agencies (SNAS) and Public
Sector Undertakings / Authorities (SECI, CEL, REIL, Railways, AAI, etc), of
which about 661 MW of RTS capacities have been installed including
subsidised and non-subsidised projects.
•Ministry has scaled-up budget from Rs. 600 crore during the 12th Five Year
Plan to Rs. 5000 crore for RTS to be installed up to 2019-20 that will
provide financial support for installation of 4200 MW.
The reasons for slow progress are as
follows:
•Involvement of multiple approval process like
connectivity, net metering, Chief Electrical
inspection (CEI), limitation in sanctioned etc.
•Skill and knowledge gaps
•Withdrawal of subsidy/CFA in private
industrial and commercial sector
•Non-uniformity of Power Purchase
Agreement (PPA) and Engineering,
Procurement and Construction (EPC)
agreements
•Slow progress of Implementing agencies
•Lack of consumer awareness
•Non-uniform regulations across states
•Tedious process for project commissioning
and subsidy disbursement
•Frequent changes in Government Policies
•Lack of policies addressing grid connected
rooftop solar
21. 7. Grid Interactive Rooftop & Small SPV Programme
Gensol Group
16
21.44
50 60
74.81
179.5
1049.6
0
6.74 15.05
0 11.14 3.7
90.7
0
200
400
600
800
1000
1200
Capacity in MW
Status and Achievements in RTS & NCEF Scheme
Rooftop Projects under Govt. Dept/PSUs
Sanctioned (MW) Overall Commissioned capacity (MW)
0
20
40
60
80
100
120
Bihar
Arunachal Pradesh
Meghalaya
Mizoram
Nagaland
Sikkim
Tripura
Dadra & Nagar Haveli
Daman & Diu
Andaman & Nicobar …
Lakshadweep
Goa
Puducherry
Jammu & Kashmir
West Bengal
Odisha
Manipur
Karnataka
Himachal Pradesh
Chhattisgarh
Uttar Pradesh
Kerala
Haryana
Punjab
Assam
Chandigarh
Rajasthan
Andhra Pradesh
Madhya Pradesh
Uttarakhand
Jharkhand
Telangana
Gujarat
Delhi
Maharashtra
Tamil Nadu
Capacity in MW
Status and Achievements in RTS & NCEF Scheme Rooftop
Projects State-wise
Sanctioned (MW) Overall Commissioned capacity (MW)
22. Off-Grids & Decentralized Solar Applications
Gensol Group
30% subsidy on
the cost of the
system ranging
from Rs. 18/- per
watt peak to
Rs.142.5/-
depending on the
module capacity &
system
90% subsidy ranging from
Rs.63/- to Rs.306/- for off-
grid solar PV applications
For installation of stand-
alone SPV power plants by
Central and State Govt.
Bodies & their
establishments in Special
Category and North East
States & Islands.
subsidy of 40% of the
capital cost limited to
Rs. 136/Wp (LED based)
upto 40 Watt peak &
Rs. 80/Wp for system
above 40 Wp limited to
300 Wp through
NABARD, Regional
Rural Banks and other
Commercial Banks.
the capital subsidy
ranges from Rs.25,560
per Hp to Rs. 36,000
per Hp depending upon
category and capacity
for Solar Water
Pumping system
23. Solar Pumps Programme : Status as on date
Gensol Group
14000
1000000
1270000
280200
0
1430000
67000
0
200000
400000
600000
800000
1000000
1200000
1400000
1600000
1992-2014 2014-2015 2015-2017 2017-2018
Solar Pumps Installedas on 31st May 17 –Y0Y
No of Solar Pumps Installed Target
The Ministry provides 30% capital Subsidy through State Nodal Agencies for irrigation and drinking water and 40% capital Subsidy
through NABARD with mandatory loan. Target of 67000 pumps initiated in 2017-18 under Off-grid solar pumps. Out of that, 50000
solar pump sets has been sanctioned in the first phase. Of which, 28020 solar projects completed so far.
1000
2460
3000
3050
6000
6500
7500
10000
10000
180
0
277
0
5500
6204
6216
3517
6126
0 2000 4000 6000 8000 10000 12000 14000 16000 18000
Odisha
Maharashtra
Karnataka
Haryana
Uttar Pradesh
Gujarat
Rajasthan
Andhra Pradesh
Chhattisgarh
State-Wise Sanctioned/ Completed Solar Pumps 2017-18
Sanctioned Quantity (Nos.) Completed so far (Nos.)
25. Off-Grid Solar Program : Progress
Gensol Group
Under NSM 1st & 2nd Phase target, around 800 MW of projects for Off-Grid Solar PV
applications were targeted. Out of which, 965.5 MW Sanctioned & 462.5 MW
installed till date.
MNRE in cooperation with Deutsche Gesellschaftfuer Internationale Zusammenarbiet
(GIZ), is implementing a project on “Solar Thermal Solution for Space Heating in
Ladakh (SolLad)”. As a result of this, Kargil Renewable Energy Development Agency has
come up with a proposal to install 1000 Nos. of Solar Space Heating systems in the
region of Leh and Kargil.
Under NSM, targets of installing solar collectors are 15 million square meters up to
2017 and 20 million square meter up to 2022 respectively. Out of which, around 1
million square meter collector area has been installed by 31st March 2016.Water
Heating System subsidy discontinued w.e.f. 1st Oct 2014 with 12 million sq.m
installations so far.
Under Atal Jyoti Yojana, Ministry targeted installation of 2,97,440 street lights in 169
constituencies in Uttar Pradesh, Bihar, Jharkhand, Odisha and Assam by 2018 . Out of
which, only 9401 lights are installed as on date. The main constrain is availability of
batteries, which are needed to be imported.
26. Performance Under DCR Category in India
Gensol Group
To promote solar manufacturing in India, MNRE had been following the policy of Domestic Content Requirement (DCR) under its
various Schemes for solar projects with support through Viability Gap Funding (VGF) or bundling of thermal power. But now this
policy itself has been challenged in WTO. 100 MW in AP under 2000 MW VGF Scheme & 350 MW under 5000 MW VGF scheme got
cancelled after WTO ruling.
0
250
300
375
750
1000
4200
400
100
300
355
25
1000
2347
0 1000 2000 3000 4000
Batch - II/Tranche - I (Bundling Scheme)
Batch - III (2000 MW VGF Scheme)
300 MW Defense Scheme
Batch - I (Grid Connected)
Batch -IV (5000 MW VGF Scheme)
1000 MW CSPU Scheme
RTS Scheme (MNRE)
Phase -2 DCR Category Targets
Target Achieved (MW) Target Capacity (MW)
150
350
70 70
0
50
100
150
200
250
300
350
400
Batch - I Batch - II
Axis Title
Phase 1- NSM Batch I & II (DCR Category)
TargetCapcity (MW) under DCR Category Target Achieved (MW)
27. Skill Development in India
Gensol Group
According to the MNRE, Research & Development activities aims at resource assessment, technology development, demonstration
and commercialization for promoting the large scale use of new and renewable energy (solar, wind, biogas, biofuel, hydrogen and
fuel cells, geothermal, etc) across the country.
2000.00
7000.00
12000.00
14000.00
15000.00
2713
8,300
0 0 0
0
2000
4000
6000
8000
10000
12000
14000
16000
2015-16 2016-17 2017-18 2018-19 2019-20
No of Person
Year Wise Human Resource Targets
No. of persons to be trained No. of persons trained
•Development and demonstration of 1 MW capacity solar
thermal power R&D project with 16-hour thermal storage at
Mount Abu, with co-funding from German Ministry and Indian
industry.
•SECI is implementing a R&D project entitled “Development of
Solar PV and wind hybrid power plant with large scale battery
storageat Kaza,Himachal Pradesh consisting of 2.5
MW solar and wind hybrid with 1 MWh battery storage
•The Ministry has launched the Suryamitra Training programme
on 28th May, 2015 with a target of training 50,000 persons as
Solar PV Technicians in the various statesby 2019
•The Ministry has sanctioned/released an amount of total Rs.
41.91 crores to National Institute of Solar Energy (NISE) for
implementation of Surya Mitra programme and NISE has
spent Rs. 35.4 crores as on 31.03.2017
R & D Activities
28. Observations & Recommendations to achieve NSM Targets
Gensol Group
Key highlights
A target of 175 GW has been set to be achieved by 2022. The success of the mission solely and squarely hinges on
the success of solar energy programmes.
More schemes should be initiated with respect to financial investment like providing access to loans at more
favorable rate of interests, introduce Green Bonds through SECI, approaching international donors, arranging
finances from Green Climate fund etc.
Under Development of Solar Parks and Ultra Mega Solar Power Project only 1516 MW capacity, out of 20,000
MW capacity, have been commissioned inside Solar Parks. All necessary actions should be taken to expedite the
development of Solar Parks.
CFA actually released for preparation of DPR for solar park is only INR 906.12 Crores i.e. about 45% short of the
target (INR 1650 Crores). Reasons for low disbursement of funds should be identified and remedial measures should
be taken in this regard.
In the view of falling solar tariff, there is no justification in paying the developers INR 4.43 per kWh as solar tariff
under VGF scheme. Reconsideration in the VGF Scheme in the CPSUs sector should be done, due to floundering of
projects.
Under Bundling Scheme 15000 MW through NTPC, only 1090 MW has been commissioned (under tranche I i.e
3000 MW); 64% short of the target. The aim of bundling thermal power with solar power is to incentivize the solar
power. However, in the view of dropping solartariff, thermal power is getting incentivized.
29. Observations & Recommendations to achieve NSM Targets
Gensol Group
Key highlights Single Window Clearance System should be adopted in RTS for approvals like connectivity, net-metering, electricity
inspection, limitation in sanctioned load,etc. and the process of subsidy disbursement should be madesimpler.
To give boost to rooftop solar systems, operationalization of Net Metering is of utmost importance. However,
DISCOMs are reluctant to operationalize the Net-Metering Regulations as it may reduce their income from high-
paying customers. Micro cooperative grid in a standalone manner should be explored wherein a group of
consumers/ householdscan be pooled in for availing thesolar rooftop benefits among themselves.
As the Solar Pumps scheme is mainly focused on small and marginal farmers who may not be able to bring
upfrontcapital, the procedure foravailing loansshould bemade easier and simpler.
Off-Grid applications are uneconomical since they face obstacles including high capital cost, complicated
procedure of subsidy disbursal, difficulty in local operation and maintenance. Hence, Public-Private Partnership
with rural entrepreneurs should beencouraged.
DCR: Per unit price of solar power has dropped from INR 10.95 in December 2010 to INR 2.44 in May 2017. For
arriving at lower tariff, the bidder may have considered a lower Return of Equity (ROE) which makes the quality of
the material used in an apprehensive state. Hence, High Anti-Dumping Duty or Duty based on efficiency of the
material imported should be imposed so as to discourage import of poor quality material.
Despite of low labour cost, Indian Manufacturers are not able to compete with Chinese Firms. Urgently a dedicated
Programme should be formulated to establish India as a Solar Manufacturing Hub so as to provide policy support
to the complete value chain.
30. About Gensol
Solar Advisory Services Solar EPC Services Solar O&M Services
6,490 MW 42 MW 776 MW
Gensol Group
Gensol provides concept to commissioning solar advisory, execution and operations services for Solar Projects in India and abroad.
103 Projects 65 Execution Engineers71 Design & Supply Chain Engineers
Anmol Singh
Evangelist
+91 7698833311
anmoljaggi@gensol.in
Imran Naqvi
Head of Strategic Advisory
& Business Development
+91 9327016962
imrannaqvi@gensol.in
Gurpreet Singh
Head of Engineering &
Operations
+91 9725544301
gurpreetsingh@gensol.in
Puneet Singh Jaggi
Director
+91 9998025820
puneetjaggi@gensol.in
Pranay Mundra
President
+91 9850673664
pranaymundra@gensol.in
Shivya Singhal
Head of Supply Chain & Group
CFO
+91 9376703846
shivyasinghal@gensol.in
31. Gensol is one of the leading consultants and system integrators for Solar Power Plants. We boast of a portfolio of over 6000 MW of Solar Photovoltaic Plants. Gensol is also a channel
partner to Ministry of New & Renewable Energy and installs kW scale Solar Rooftop systems on a turnkey basis with more than 42 MW of cumulative installations across the country.
The information contained herein is of a general nature and is not intended to address the circumstances of any particular individual or entity. Although we endeavor to provide
accurate and timely information, there can be no guarantee that such information is accurate as of the date it is received or that it will continue to be accurate in the future. No one
should act on such information without appropriate professional advice after a thorough examination of the particular situation.
Email: solar@gensol.in | Web: www.gensol.in | Phone: +91 79 40068235 | Twitter: gensol_tweets
Gensol Engineering Pvt Ltd | Gensol Consultants Pvt Ltd | Solarig Gensol Utilities Pvt Ltd
Corporate Office
108, Pinnacle Business Park, Opp. Royal Arcade, Prahladnagar, Ahmedabad, Gujarat. India - 380015