SlideShare a Scribd company logo
1 of 31
Download to read offline
GENSOL ENGINEERING PVT. LTD
www.gensol.in
National	Solar	Mission	(16-17)	- Highlights
Key	Points	Presented	by	Standing	Committee	on	Energy
Gensol Group
Standing Committee on Energy (16-17) has briefed the 16th Lok Sabha. The
committee has presented the 28th report on ‘National Solar Mission –An Appraisal’
on 31st July 2017. Key discussion points have been covered in the presentation.
National	Solar	Mission	:	Motive	
Gensol Group
Initially,the Mission initiated to provide large-scale grid connected power.
Also, to reduce our dependence on fast depleting conventional sources, knowing the
fact that India has potentialmore than 750 GW from solar energy
Mission is being expanded at rapidly towards decentralized & disbursed
industrialisationto change the Rural EconomyofIndia.
Looking into the wide emergence of the solar energy applications/utilization, NSM
targets have been revised to 100 GW from 20 GW for Grid connected solar power
projects in June2015.
National	Solar	Mission	:	Overview
Gensol Group
• Deployment	of	20,000	MW	revised	to	100,000	MW	of	grid	connected	solar	power	by	2022,
• 2000	MW	of	off-grid	solar	applications including	 20	million	solar	lights	by	2022
• Support	 R&D	and	capacity	building	 activities	to	achieve	grid	parity	by	2022.
• Developing	solar	manufacturing	capability	in	the	country;
• 20	million	sq.	m.	solar	thermal	collector	area
Government of India has the aggressive renewable energy (RE)
capacity addition target of 175 GW to be achieved by 2022.
India’s	Renewable	Energy	Targets	&	Achievements
Gensol Group
4385
8296
13115
32508
0.00
5000.00
10000.00
15000.00
20000.00
25000.00
30000.00
35000.00
Small	Hydro	
Power
Bio-Power Solar	Power Wind	Power
Capacity	in	MW
Renewable	Source
RE	Installed	Capacity	(MW) as	on	July	2017
Out of 175 GW RE targets, 100 GW has been embattled to come from solar. As on July 2017, overall Renewable Energy targets
reached approx. 57 GW out 175 GW ,which turns out to be 33% ,classified as 4 GW in Small hydro, 8 GW in Bio-Power, 13 GW
in Solar Energy & 32 GW in Wind Power.
National	Solar	Mission	:	Targets	Vs	Achievement	
Gensol Group
Phase	I	of	NSM	(2010-13) Phase-II	of	NSM	(2013-17)
Phase-III	of	NSM	
(2017-2022)
Segment Target	
Achievements
(as	on	March	2013)
Target	
Achievements
(as	on	March	2017)
Target
Grid	solar	power 1100	MW 1686	MW 15900	MW 10602 MW 100000	MW
Off-grid	solar	
applications	
200	MW
252	MW	Sanctioned	
117	MW	Installed
600	MW
713	MW	Sanctioned
345	MW	Installed
2000 MW
Solar	Thermal	
Collectors	
7	Million	Sq.	m 7	Million	Sq.	m 8	Million	Sq.m 5	Million	Sq.m 15	Million	Sq.m
NSM Targets has been divided into three phases – Phase - I, Phase II and Phase III. Achievements of Phase-I
exceeded the targetsset for the period.
Ambitious	NSM	Targets	2017-2022	:	Category	Wise
Gensol Group
The revised target of 100 GW is planned to be achieved in 7 years period (2015-16 to 2021-22) and broadly consist
of 40 GW Grid connected Rooftop projectsand 60 GW large and medium size ground based solar power projects
100	GW	
Category	I	-
40	GW
40	GW	–
Rooftop	Solar
Category	II	-
60	GW
10	GW	–
Small	Scale	
Grid		projects	
10	GW	–
Public	Sector	
Undertakings
5	GW	–
Large	Private	
Sector/IPPs
5	GW	–
SECI
20	GW	–
Under	State	
Policies
10	GW	–
Ongoing	
programmes
Grid	Connected	Solar	Power	Targets	:	Year- Wise
Gensol Group
Ministry has furnished Year-Wise targets to achieve 100 GW Grid connected solar power by 2022 as
follows. Government is in process of arranging with World Bank, in consultation with Ministry of
Finance, for US $ 100 million loan assistance for creating internal infrastructure of solar parks
200
4800 5000 6000 7000 8000 9000
1800
7200
10000
10000
10000
9500 8500
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
20000
2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22
MNRE	Yearwise	Solar	Targets	(MW)
MNRE	Yearwise	Solar	Targets	(MW)	Roofttop MNRE	Yearwise	Solar	Targets	(MW)	Ground	Mounted
Grid	Connected	Solar	Power	:	Target	Vs	Achievements
Gensol Group
11 36
1030
1686
2632
3744
6763
12289
13115
11 25
994
656 946 1112
3019
5526
826
0
2000
4000
6000
8000
10000
12000
14000
Upto	2010 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 2017-18
CAPACITY	IN	MW
YEAR	WISE
ANNUAL	SOLAR	PV	INSTALLATIONS	(MW)	–YOY	AS	ON	31ST JULY	2017
Cumulative Installed Capacity (MW) Annual Installed Capacity (MW)
Schemes	to	Achieve	Ambitious	Targets	of	100	GW
Gensol Group
1.
• To set up 300 MW of Grid connected Solar PV Power Projects by Defense Establishments under Ministry of
Defense and Para Military Forces with VGF.
2.
• To develop schemes for Solar Parks and Ultra Mega Solar Power Projects.
3.
• For development of Solar PV Power Plants on Canal Banks/ Canal Tops.
4.
• Implementation of scheme for setting up 1000 MW of Grid- Connected Solar PV Power Projects by Central
Public Sector Undertakings (CPSUS) with VGF
5.
• Implementation of Scheme for Setting up of 15000 MW of Grid connected Solar PV Power Projects under
Batch II of Phase II of National Solar Mission (by NTPC/NVVN)
6.
• Schemes for setting up of 750 MW, 2000 MW, and 5000 MW Grid connected solar power with Viability Gap
Funding through Solar Energy Corporation of India (SECI)
7.
• Development of Solar Cities Programme & Installation of Grid Connected Solar Rooftop Power Plants.
1.	Setting	of	300	MW	SPV	by	Defense	Establishment
Gensol Group
It has been identified that cantonment and Military Stations
have high Potential of Solar Energy of approximately 5000
MWand in Ordnance Factory Boards (OFB)ofaround 950 MW
Establishments of Ministry of Defense has planned to set up
300 MW in various places like Establishments of Army, Navy,
Air Force, Ordnance Factory Board, Defense Laboratories and
Defense PSUs etc. with minimum size of the project of 1 MW.
The projects under this Scheme will mandatorily use solar
cells/modules whichare made in India.
A total of 300 MW capacity to be added in 5 years from 2014-
19
Overall, 357.5 MW Sanctioned under which 128 MW
tendered, 52 MW order placed & 7 MW projects
commissioned.
As	on	date,	357.5	MW	has	been	allocated	under	the		scheme	:
Name	of	
Organization
Capacity	(MW) Status
Ordnance	Factory	
Board 7 Commissioned
Bharat	Electronics	Ltd. 150
35	MW:	Order	placed,	under	
construction
36	MW:	Tendering	under	process
Bharat	Dynamics	
Limited 25
5	MW:	Order	placed,	under	
construction
Department	of	
Defence 150
26	MW:	Order	placed,	under	
construction
Hindustan	Aeronautics	
Ltd.,	Nasik 15
5	MW:	Tender	issued,	 order	to	be	
placed	by	30th	May,2017
Ordnance	factory 5
Tendering	for	15	MW	to	be	done	
by	June,2017
MIDHANI 4 Tendering	in	process
Ordnance	Factory,	
Ambajhari 1.5
Tender	will	be	issued	by	
June,2017
Total 357.5
2.	Development	of	Solar	Parks	&	Ultra	Mega	Solar	Parks	
Gensol Group
20 50 60 69 100 100 200
500 500 500 500 500 600 700
1000 1000
1500
2000
2750
3351
4000
0
500
1000
1500
2000
2500
3000
3500
4000
4500
Capacity	in	MW
States	in	India
Proposed	Solar	Park	Capacity	(MW)
2.	Development	of	Solar	Parks	&	Ultra	Mega	Solar	Parks
Gensol Group
Status	of	Solar	Projects	in	Solar	Park	
Particulars Capacity	(MW)
Solar	Projects	already	commissioned	inside	Solar	Parks	
during	2016-17
1516
Solar	Projects	likely	to	be	commissioned	inside	Solar	
Parks	during	2017-18
2229
Capacity	already	tendered	out	but	may	be	
commissioned	in	2018-19
2100
Capacity	expected	to	be	tendered	out	in	2017-18	
(operational	solar	parks)
6425
Capacity	Expected	to	be	tendered	out	in	2017-18	
(activities	are	yet	to	be	started)
7730
Total 20000
The Ministry provides Central Financial
Assistance (CFA) of up to Rs. 25 lakh per solar
park for preparation of Detailed Project Report
(DPR).
CFA of up to Rs. 20.00 lakh per MW or 30% of
the project cost, including Grid-connectivity
cost, whichever is lower, grant is released by
Solar Energy Corporation of India Ltd. (SECI) as
per milestones.
The total requirement of funds estimated to
provide CFA as Rs. 4050.00 crore, of which INR
906.12 has already disbursed.
Overall, 34 solar parks in 21 states with 20
GW capacity are approved with land acquired
for 71,000 MW, 7300 MW capacity has been
tendered & 1.5 GW in 4 parks is
commissioned.
3.	Development	of	Canal	tops/Banks	:	
Targets	Vs	Achievements
Gensol Group
Rs.3 crore/MW or 30% of the project cost,
whichever is lower, for Canal Top SPV
projects and Rs. 1.5 crore/MW or 30% of
the project cost, whichever is lower, for
Canal Bank SPV projects will be assisted.
•Upto	40%	on	sanctioning	of	the	projects.	
•60%	on	successful	 commissioning	 of	the	projects.	
•Service	charge	to	SECI	@1%:	Rs.2.25	crore.	
CFA of upto Rs.225 crore for 100 MW (50
MW on Canal Tops and 50 MW on Canal
Banks) to be disbursed over a period of
maximum 2 years post sanctioning of the
plants as under:
Allocation	of	50	MW	Canal-Top	Solar	PV	Projects
State Approved	capacity	(MW) Commissioned	Capacity	(MW)
Punjab 20 5
Gujarat 10 Work in	progress
Karnataka 10 In	tendering	process
UP 6 Work	in	progress
Kerala 2 2
AP 1 1
Uttarakhand 1 Work	in	progress
Total	 50 8
Allocation	of	50	MW	Canal-Bank	Solar	PV	Projects
State Approved	capacity	(MW) Commissioned	Capacity	(MW)
Uttarakhand 19 Work	in	progress
Gujarat 15 Work	in	progress
West	Bengal 10 10
AP 5 5
Kerala 1 1
Total	 50 16
Central	Financial	Assistance	under	the	scheme-
4.	Solar	PV	Power	Projects	by	Central	Public	Sector	
Undertakings	(CPSUS)
Gensol Group
GOI	will	provide	VGF	as	under:
• a)	Rs.1	Cr.	/MW,	if	Cells	and	Modules	for	the	
project	are	manufactured	indigenously.
• b)	Rs.50	Lakh	/MW,	if	Modules	for	the	project	
are	manufactured	indigenously.
VGF	will	be	released	in	two	tranches	as	follows:
• a)	50%	on	LoI and	start	of	installation	work	at	
plant;	and
• b)	Balance	50%	on	successful	commissioning	of	
the	full	capacity	of	the	project	(CoD)”.
The	duration	of	implementation	of	the	Scheme	is	
2015-18.
MNRE has allocated 1037.26 MW (Out of which 669 MW commissioned)
capacity to following 15 CPSUs/Govt. Organizations within the sanctioned
funds of Rs. 1000 Crorefor this scheme.
680
16.5 5
200
50
6 5.76
74
62.13%
50.00%
100.00%
0.00% 0.00% 0.00%
25.00%
11.73%
0.00%
20.00%
40.00%
60.00%
80.00%
100.00%
120.00%
0
100
200
300
400
500
600
700
800
VGF	Funded	in	%
Capacity	in	MW
Capacity	Wise	(MW)	VGF	Funded	Projects
Capacity	Sanctioned	(MW) %	of	VGF	Amount	Released
5.	Bundling	Scheme	:	15000	MW	of	Grid	connected	Solar	PV	
Gensol Group
3000
5000
7000
0
1000
2000
3000
4000
5000
6000
7000
8000
2014-15	to	2016-
17	(Tranche	I)
2015-16	to	2017-
18	(Tranche	II)
2016-17	to	2018-
19	(Tranche	III)
Capacity	(MW)
Targeted	Capacity	(MW)	Tranche	Wise
Currently Tranche-I, is under implementation. In Tranche-I, which is Batch-II of Phase-II of National Solar Mission, 3000
MW (3600 MW open & 400 MW DCR Category) capacity of solar PV power plants will be based on bundling with
unallocated thermal power (1500 MW) in the ratio of 2:1 & has been already tendered , PPA signed for 2750 MW & 1090
MW projects commissioned.
1100
500 550
350
100
150
100
100
50
0
0
200
400
600
800
1000
1200
1400
Andhra	Pradesh Karnataka Rajasthan Telangana Uttar	PradeshCapacity	in	MW
Status	Of	Tranche	I	- 3000	MW	State	Specific	Bundling	Scheme	
Under	NSM	Phase-ii,	Batch-ii
Capacity	allotted	in	DCR	category	(MW)
Capacity	allotted	in	OPEN	category	(MW)
6.	Viability	Gap	Funding	through	Solar	Energy	Corporation	
of	India	(SECI)
Gensol Group
A)	750	MW	VGF	Scheme
Phase-II,	Batch-I (Implemented)
B)	2000	MW	VGF	Scheme
Phase	II,	Batch	III (Under	Implementation)
10 10 20 25 40
220
355
0
50
100
150
200
250
300
350
400
State	Wise	Commissioned
Capacity(MW)
500
325
400
100
1000
35 50
500
325
400
100
970
0
0
500
325
400
100
970
0
0
0
200
400
600
800
1000
1200
State	Wise	Allocation	of	Capacity	(MW))
RfS	issued	(MW) LoI	issued	(MW) PPA	signed	(MW)
After a transparent selection and
award process, project capacity of
680 MW (out of 750 MW) could
successfully achieve financial closure.
SECI has issued RfS for 2410 MW
capacity in 7 states. LoI has been
issued for 2295 MW. PPAs have
been signed for 2295 MW.
6.	Viability	Gap	Funding	through	Solar	Energy	
Corporation	of	India	(SECI)
Gensol Group
C)	5000	MW	VGF	Scheme
Phase	II, Batch	IV	(Under	Implementation)
400
300
750
450 450
200250 270
0
450
0 0
250 270
0
450
0 0
0
100
200
300
400
500
600
700
800
Gujarat Odisha Andhra	
Pradesh
Maharashtra Karnataka Rajasthan
VGF	Fund	Granted	- SPV	Capacity	(MW)
RfS	issued	(MW) LoI	issued	(MW) PPA	signed	(MW)
• The scheme is proposed to be implemented
by SECI in four tranches of 1250 MW each,
spread over four years, from 2015-16up to
FY 2018-19
• RfS has already been issued for 2850 MW
capacity in 6 states. LoI has been issued
for 970 MW. PPAs have been signed for
970 MW.
• Due to various mechanisms including the
reverse bidding on VGF as well as on tariff,
the discovered tariff has reduced from Rs.
17.91 to Rs. 2.44 per kWh that will benefit
both developer to Produce & sell through
SECI to DISCOMs
Overall, till date, 5260 MW tender issued, 3265
MW PPA signed and 80 MW Projects
commissioned for2000 MW & 5000 MW scheme
Bidding	– Success	Story…..
Gensol Group
The trends of solar tariff in India till 2016-17 are given below: The	reasons	for	plummeting	 of	the	cost	of	solar	power	prices	are	as	under:	
(i)	Conducive	policies	for	encouraging	solar	sector;	
(ii)	Improved	project	structuring	and	technology;	
(iii)	Better	learning	curve;	
(iv)	Decline	in	cost	of	solar	cells/modules	and	Cost	of	financing”	
Global	trend	in	solar	tariff	through	bidding	during	period	2016-17	 is	as	
given	below	
2.99
1.99
2.91
2.42
2.7
May-16
May-16
Aug-16
Sep-16
Oct-16
Abu	
DhabiDubaiChile
Abu	
DhabiMexico
World	Wide	Tariff	(US	cent/kWh)	16-17
12.1600
8.7900 8.3700
11.8250
6.5675
10.5935
4.9462
2.7986
0
5
10
15
2009-10 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17
TARIFF	(RS/KWH)
Weighted	Avg.	Price	(Rs./KWh)	2009-2017
In 16-17, steep
fall down of
the the solar
tariff recorded.
In the bidding held in February 2017 for solar projects to
be set up in Rewa Solar Park, Madhya Pradesh; the
levelized tariff has come down to Rs. 3.30 per kWh.
The solar tariff declined to Rs. 3.15 per unit in the reverse
auction done by NTPC at Kadapa Solar Park in Andhra
Pradesh in April, 2017.
The solar tariff further declined to Rs. 2.44 per unit in the
recent reverse auction done by SECI at Bhadla Phase-III
Solar Park in Rajasthan in May, 2017.
7.	Grid	Interactive	Rooftop	&	Small	SPV	Programme
Gensol Group
To meet the targets of 40 GW (Out of 100 GW) that needs to be
achieved from grid connected solar rooftops by 2022, Ministry has
introduced various subsidies have been introduced.
•The capital subsidy of 30% (70 % for special category Sates and Andaman
& Nicobar and Lakshadweep Islands) is available for residential,
institutional and social sectors.
•MNRE is implementing RTS Programme for development of 4200 MW. Out
of 4200 MW capacity, 2100 MW capacity has to be installed through CFA/
incentive in the residential, social, Government / PSU and Institutional
sectors. The balance 2100 MW is to be implemented without any subsidy.
• As on 30th April 2017, MNRE has sanctioned projects of cumulative
capacity of 2032 MWp to various State Nodal Agencies (SNAS) and Public
Sector Undertakings / Authorities (SECI, CEL, REIL, Railways, AAI, etc), of
which about 661 MW of RTS capacities have been installed including
subsidised and non-subsidised projects.
•Ministry has scaled-up budget from Rs. 600 crore during the 12th Five Year
Plan to Rs. 5000 crore for RTS to be installed up to 2019-20 that will
provide financial support for installation of 4200 MW.
The	reasons	for	slow	progress	are	as	
follows:
•Involvement of multiple approval process like
connectivity, net metering, Chief Electrical
inspection (CEI), limitation in sanctioned etc.
•Skill and knowledge gaps
•Withdrawal of subsidy/CFA in private
industrial and commercial sector
•Non-uniformity of Power Purchase
Agreement (PPA) and Engineering,
Procurement and Construction (EPC)
agreements
•Slow progress of Implementing agencies
•Lack of consumer awareness
•Non-uniform regulations across states
•Tedious process for project commissioning
and subsidy disbursement
•Frequent changes in Government Policies
•Lack of policies addressing grid connected
rooftop solar
7.	Grid	Interactive	Rooftop	&	Small	SPV	Programme
Gensol Group
16
21.44
50 60
74.81
179.5
1049.6
0
6.74 15.05
0 11.14 3.7
90.7
0
200
400
600
800
1000
1200
Capacity	in	MW
Status	and	Achievements	in	RTS	&	NCEF	Scheme	
Rooftop	Projects	under	Govt.	Dept/PSUs
Sanctioned	(MW) Overall	Commissioned	capacity	(MW)
0
20
40
60
80
100
120
Bihar
Arunachal	Pradesh
Meghalaya
Mizoram
Nagaland
Sikkim
Tripura
Dadra	&	Nagar	Haveli
Daman	&	Diu
Andaman	&	Nicobar	…
Lakshadweep
Goa
Puducherry
Jammu	&	Kashmir
West	Bengal
Odisha
Manipur
Karnataka
Himachal	Pradesh
Chhattisgarh
Uttar	Pradesh
Kerala
Haryana
Punjab
Assam
Chandigarh
Rajasthan
Andhra	Pradesh
Madhya	Pradesh
Uttarakhand
Jharkhand
Telangana
Gujarat
Delhi
Maharashtra
Tamil	Nadu
Capacity	in	MW
Status	and	Achievements	in	RTS	&	NCEF	Scheme	Rooftop	
Projects	State-wise
Sanctioned	(MW) Overall	Commissioned	capacity	(MW)
Off-Grids	&	Decentralized	Solar	Applications	
Gensol Group
30% subsidy on
the cost of the
system ranging
from Rs. 18/- per
watt peak to
Rs.142.5/-
depending on the
module capacity &
system
90% subsidy ranging from
Rs.63/- to Rs.306/- for off-
grid solar PV applications
For installation of stand-
alone SPV power plants by
Central and State Govt.
Bodies & their
establishments in Special
Category and North East
States & Islands.
subsidy of 40% of the
capital cost limited to
Rs. 136/Wp (LED based)
upto 40 Watt peak &
Rs. 80/Wp for system
above 40 Wp limited to
300 Wp through
NABARD, Regional
Rural Banks and other
Commercial Banks.
the capital subsidy
ranges from Rs.25,560
per Hp to Rs. 36,000
per Hp depending upon
category and capacity
for Solar Water
Pumping system
Solar	Pumps	Programme	:	Status	as	on	date
Gensol Group
14000
1000000
1270000
280200
0
1430000
67000
0
200000
400000
600000
800000
1000000
1200000
1400000
1600000
1992-2014 2014-2015 2015-2017 2017-2018
Solar	Pumps	Installedas	on	31st May	17	–Y0Y
No	of	Solar	Pumps	Installed Target
The Ministry provides 30% capital Subsidy through State Nodal Agencies for irrigation and drinking water and 40% capital Subsidy
through NABARD with mandatory loan. Target of 67000 pumps initiated in 2017-18 under Off-grid solar pumps. Out of that, 50000
solar pump sets has been sanctioned in the first phase. Of which, 28020 solar projects completed so far.
1000
2460
3000
3050
6000
6500
7500
10000
10000
180
0
277
0
5500
6204
6216
3517
6126
0 2000 4000 6000 8000 10000 12000 14000 16000 18000
Odisha
Maharashtra
Karnataka
Haryana
Uttar	Pradesh
Gujarat
Rajasthan
Andhra	Pradesh
Chhattisgarh
State-Wise	Sanctioned/	Completed		Solar	Pumps	2017-18	
Sanctioned	Quantity	(Nos.) Completed	so	far	(Nos.)
Status	of	Solar	Pumps	for	Irrigation	&	Drinking	Water	
Sanctioned	and	Achievement	as		on	31.05.17
Gensol Group
0
5000
10000
15000
20000
25000
30000
35000
40000
45000
CAPACITY		IN	MW
STATES
Status	of	Solar	Pumps	for	Irrigation	&	Drinking	Water	(2015-2017)
Total	Sanctioned Installed	as	on	31.5.2017
About	1.27	lakh	solar	pumps	against	the	target	of		1.43	lakhs	installed	under	the	programme	 FY	2015-2017		till	
31st	May	2017	for	irrigation,	 drinking	water	etc.	Out	of	1.43	lakhs	solar	pumps,	2833	solar	pumps	are	funded	by	
NABARD.
Off-Grid	Solar	Program	:	Progress
Gensol Group
Under NSM 1st & 2nd Phase target, around 800 MW of projects for Off-Grid Solar PV
applications were targeted. Out of which, 965.5 MW Sanctioned & 462.5 MW
installed till date.
MNRE in cooperation with Deutsche Gesellschaftfuer Internationale Zusammenarbiet
(GIZ), is implementing a project on “Solar Thermal Solution for Space Heating in
Ladakh (SolLad)”. As a result of this, Kargil Renewable Energy Development Agency has
come up with a proposal to install 1000 Nos. of Solar Space Heating systems in the
region of Leh and Kargil.
Under NSM, targets of installing solar collectors are 15 million square meters up to
2017 and 20 million square meter up to 2022 respectively. Out of which, around 1
million square meter collector area has been installed by 31st March 2016.Water
Heating System subsidy discontinued w.e.f. 1st Oct 2014 with 12 million sq.m
installations so far.
Under Atal Jyoti Yojana, Ministry targeted installation of 2,97,440 street lights in 169
constituencies in Uttar Pradesh, Bihar, Jharkhand, Odisha and Assam by 2018 . Out of
which, only 9401 lights are installed as on date. The main constrain is availability of
batteries, which are needed to be imported.
Performance	Under	DCR	Category	in	India
Gensol Group
To promote solar manufacturing in India, MNRE had been following the policy of Domestic Content Requirement (DCR) under its
various Schemes for solar projects with support through Viability Gap Funding (VGF) or bundling of thermal power. But now this
policy itself has been challenged in WTO. 100 MW in AP under 2000 MW VGF Scheme & 350 MW under 5000 MW VGF scheme got
cancelled after WTO ruling.
0
250
300
375
750
1000
4200
400
100
300
355
25
1000
2347
0 1000 2000 3000 4000
Batch	- II/Tranche	- I	(Bundling	Scheme)
Batch	- III	(2000	MW	VGF	Scheme)
300	MW	Defense	Scheme
Batch	- I	(Grid	Connected)
Batch	-IV	(5000	MW	VGF	Scheme)
1000	MW	CSPU	Scheme
RTS	Scheme	(MNRE)
Phase	-2		DCR		Category	Targets
Target	Achieved	(MW) Target	Capacity	(MW)
150
350
70 70
0
50
100
150
200
250
300
350
400
Batch	- I Batch	- II
Axis	Title
Phase	1- NSM	Batch	I	&	II	(DCR	Category)
TargetCapcity	(MW)	under	DCR	Category Target	Achieved	(MW)
Skill	Development	in	India
Gensol Group
According to the MNRE, Research & Development activities aims at resource assessment, technology development, demonstration
and commercialization for promoting the large scale use of new and renewable energy (solar, wind, biogas, biofuel, hydrogen and
fuel cells, geothermal, etc) across the country.
2000.00
7000.00
12000.00
14000.00
15000.00
2713
8,300
0 0 0
0
2000
4000
6000
8000
10000
12000
14000
16000
2015-16 2016-17 2017-18 2018-19 2019-20
No	of	Person
Year	Wise	Human	Resource	Targets
No.	of	persons	to	be	trained No.	of	persons	trained
•Development and demonstration of 1 MW capacity solar
thermal power R&D project with 16-hour thermal storage at
Mount Abu, with co-funding from German Ministry and Indian
industry.
•SECI is implementing a R&D project entitled “Development of
Solar PV and wind hybrid power plant with large scale battery
storageat Kaza,Himachal Pradesh consisting of 2.5
MW solar and wind hybrid with 1 MWh battery storage
•The Ministry has launched the Suryamitra Training programme
on 28th May, 2015 with a target of training 50,000 persons as
Solar PV Technicians in the various statesby 2019
•The Ministry has sanctioned/released an amount of total Rs.
41.91 crores to National Institute of Solar Energy (NISE) for
implementation of Surya Mitra programme and NISE has
spent Rs. 35.4 crores as on 31.03.2017
R	&	D	Activities
Observations	&	Recommendations	to	achieve	NSM	Targets
Gensol Group
Key highlights
A target of 175 GW has been set to be achieved by 2022. The success of the mission solely and squarely hinges on
the success of solar energy programmes.
More schemes should be initiated with respect to financial investment like providing access to loans at more
favorable rate of interests, introduce Green Bonds through SECI, approaching international donors, arranging
finances from Green Climate fund etc.
Under Development of Solar Parks and Ultra Mega Solar Power Project only 1516 MW capacity, out of 20,000
MW capacity, have been commissioned inside Solar Parks. All necessary actions should be taken to expedite the
development of Solar Parks.
CFA actually released for preparation of DPR for solar park is only INR 906.12 Crores i.e. about 45% short of the
target (INR 1650 Crores). Reasons for low disbursement of funds should be identified and remedial measures should
be taken in this regard.
In the view of falling solar tariff, there is no justification in paying the developers INR 4.43 per kWh as solar tariff
under VGF scheme. Reconsideration in the VGF Scheme in the CPSUs sector should be done, due to floundering of
projects.
Under Bundling Scheme 15000 MW through NTPC, only 1090 MW has been commissioned (under tranche I i.e
3000 MW); 64% short of the target. The aim of bundling thermal power with solar power is to incentivize the solar
power. However, in the view of dropping solartariff, thermal power is getting incentivized.
Observations	&	Recommendations	to	achieve	NSM	Targets
Gensol Group
Key highlights Single Window Clearance System should be adopted in RTS for approvals like connectivity, net-metering, electricity
inspection, limitation in sanctioned load,etc. and the process of subsidy disbursement should be madesimpler.
To give boost to rooftop solar systems, operationalization of Net Metering is of utmost importance. However,
DISCOMs are reluctant to operationalize the Net-Metering Regulations as it may reduce their income from high-
paying customers. Micro cooperative grid in a standalone manner should be explored wherein a group of
consumers/ householdscan be pooled in for availing thesolar rooftop benefits among themselves.
As the Solar Pumps scheme is mainly focused on small and marginal farmers who may not be able to bring
upfrontcapital, the procedure foravailing loansshould bemade easier and simpler.
Off-Grid applications are uneconomical since they face obstacles including high capital cost, complicated
procedure of subsidy disbursal, difficulty in local operation and maintenance. Hence, Public-Private Partnership
with rural entrepreneurs should beencouraged.
DCR: Per unit price of solar power has dropped from INR 10.95 in December 2010 to INR 2.44 in May 2017. For
arriving at lower tariff, the bidder may have considered a lower Return of Equity (ROE) which makes the quality of
the material used in an apprehensive state. Hence, High Anti-Dumping Duty or Duty based on efficiency of the
material imported should be imposed so as to discourage import of poor quality material.
Despite of low labour cost, Indian Manufacturers are not able to compete with Chinese Firms. Urgently a dedicated
Programme should be formulated to establish India as a Solar Manufacturing Hub so as to provide policy support
to the complete value chain.
About	Gensol
Solar Advisory Services Solar EPC Services Solar O&M Services
6,490 MW 42 MW 776 MW
Gensol Group
Gensol provides concept to commissioning solar advisory, execution and operations services for Solar Projects in India and abroad.
103 Projects 65 Execution Engineers71 Design & Supply Chain Engineers
Anmol Singh
Evangelist
+91 7698833311
anmoljaggi@gensol.in
Imran Naqvi
Head of Strategic Advisory
& Business Development
+91 9327016962
imrannaqvi@gensol.in
Gurpreet Singh
Head of Engineering &
Operations
+91 9725544301
gurpreetsingh@gensol.in
Puneet Singh Jaggi
Director
+91 9998025820
puneetjaggi@gensol.in
Pranay Mundra
President
+91 9850673664
pranaymundra@gensol.in
Shivya Singhal
Head of Supply Chain & Group
CFO
+91 9376703846
shivyasinghal@gensol.in
Gensol is one of the leading consultants and system integrators for Solar Power Plants. We boast of a portfolio of over 6000 MW of Solar Photovoltaic Plants. Gensol is also a channel
partner to Ministry of New & Renewable Energy and installs kW scale Solar Rooftop systems on a turnkey basis with more than 42 MW of cumulative installations across the country.
The information contained herein is of a general nature and is not intended to address the circumstances of any particular individual or entity. Although we endeavor to provide
accurate and timely information, there can be no guarantee that such information is accurate as of the date it is received or that it will continue to be accurate in the future. No one
should act on such information without appropriate professional advice after a thorough examination of the particular situation.
Email: solar@gensol.in | Web: www.gensol.in | Phone: +91 79 40068235 | Twitter: gensol_tweets
Gensol Engineering Pvt Ltd | Gensol Consultants Pvt Ltd | Solarig Gensol Utilities Pvt Ltd
Corporate Office
108, Pinnacle Business Park, Opp. Royal Arcade, Prahladnagar, Ahmedabad, Gujarat. India - 380015

More Related Content

What's hot

Potential of Solar Power in India
Potential of Solar Power in IndiaPotential of Solar Power in India
Potential of Solar Power in India
Akash Jauhari
 
Bridge to-india the-india-solar-handbook-june-2014-edition
Bridge to-india the-india-solar-handbook-june-2014-editionBridge to-india the-india-solar-handbook-june-2014-edition
Bridge to-india the-india-solar-handbook-june-2014-edition
Sanman Rajput
 
Solar policys in india and state comparison
Solar policys in india and state comparison Solar policys in india and state comparison
Solar policys in india and state comparison
Nilesh Dayalapwar
 
Draft explanatory-memorandum solar-power-projects
Draft explanatory-memorandum solar-power-projectsDraft explanatory-memorandum solar-power-projects
Draft explanatory-memorandum solar-power-projects
Sanman Rajput
 
Ceew cef market_handbook_q1_2020
Ceew cef market_handbook_q1_2020Ceew cef market_handbook_q1_2020
Ceew cef market_handbook_q1_2020
Mayank Munjal
 

What's hot (20)

Potential of Solar Power in India
Potential of Solar Power in IndiaPotential of Solar Power in India
Potential of Solar Power in India
 
The Indian Solar Market: New Market - New Chances
The Indian Solar Market: New Market - New ChancesThe Indian Solar Market: New Market - New Chances
The Indian Solar Market: New Market - New Chances
 
Bridge to-india the-india-solar-handbook-june-2014-edition
Bridge to-india the-india-solar-handbook-june-2014-editionBridge to-india the-india-solar-handbook-june-2014-edition
Bridge to-india the-india-solar-handbook-june-2014-edition
 
Market Outlook for Energy Storage in India
Market Outlook for Energy Storage in IndiaMarket Outlook for Energy Storage in India
Market Outlook for Energy Storage in India
 
Power of sun and solar energy (india power)
Power of sun and solar energy (india power)Power of sun and solar energy (india power)
Power of sun and solar energy (india power)
 
Solar Power 2020: India On A National Solar Mission
Solar Power 2020: India On A National Solar MissionSolar Power 2020: India On A National Solar Mission
Solar Power 2020: India On A National Solar Mission
 
Solar policys in india and state comparison
Solar policys in india and state comparison Solar policys in india and state comparison
Solar policys in india and state comparison
 
Solar Power Technology in India by S Kumar
Solar Power Technology in India by S Kumar Solar Power Technology in India by S Kumar
Solar Power Technology in India by S Kumar
 
Nl energy july18 -24, 2015
Nl energy july18 -24, 2015Nl energy july18 -24, 2015
Nl energy july18 -24, 2015
 
Solar News from around the world for week 2 of June 2021
Solar News from around the world for week 2 of June 2021Solar News from around the world for week 2 of June 2021
Solar News from around the world for week 2 of June 2021
 
JNNSM Solar Power in India
JNNSM Solar Power in IndiaJNNSM Solar Power in India
JNNSM Solar Power in India
 
India’s solar policies
India’s solar policiesIndia’s solar policies
India’s solar policies
 
Nl energy aug 22 - aug 28, 2015
Nl energy aug 22 - aug 28, 2015Nl energy aug 22 - aug 28, 2015
Nl energy aug 22 - aug 28, 2015
 
Draft explanatory-memorandum solar-power-projects
Draft explanatory-memorandum solar-power-projectsDraft explanatory-memorandum solar-power-projects
Draft explanatory-memorandum solar-power-projects
 
Solar News from India for week 1 July 2021- Solar Policy change, Minister app...
Solar News from India for week 1 July 2021- Solar Policy change, Minister app...Solar News from India for week 1 July 2021- Solar Policy change, Minister app...
Solar News from India for week 1 July 2021- Solar Policy change, Minister app...
 
Ceew cef market_handbook_q1_2020
Ceew cef market_handbook_q1_2020Ceew cef market_handbook_q1_2020
Ceew cef market_handbook_q1_2020
 
RE 2022
RE 2022RE 2022
RE 2022
 
How China become Solar PV manufacturing hub ?
How China become Solar PV manufacturing hub ?How China become Solar PV manufacturing hub ?
How China become Solar PV manufacturing hub ?
 
Rfp document for Solar PV Project in Delhi
Rfp document for Solar PV Project in DelhiRfp document for Solar PV Project in Delhi
Rfp document for Solar PV Project in Delhi
 
Feasibility Study of Solar Power in India
Feasibility Study of Solar Power in IndiaFeasibility Study of Solar Power in India
Feasibility Study of Solar Power in India
 

Similar to National Solar Mission Status (July'17)

Draft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeDraft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-scheme
Sanman Rajput
 
Draft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeDraft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-scheme
Sanman Rajput
 
Green Corner l2010
Green Corner l2010Green Corner l2010
Green Corner l2010
Amit Bharti
 

Similar to National Solar Mission Status (July'17) (20)

India's National Solar Mission Phase 2 Batch 3 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 3 Tranche 1 Guidelines - DraftIndia's National Solar Mission Phase 2 Batch 3 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 3 Tranche 1 Guidelines - Draft
 
Solar India - Sun Power is Solution to India's Energy Crisis
Solar India - Sun Power is Solution to India's Energy CrisisSolar India - Sun Power is Solution to India's Energy Crisis
Solar India - Sun Power is Solution to India's Energy Crisis
 
Draft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeDraft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-scheme
 
Draft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-schemeDraft guidelines-of-2000 mw-vgf-scheme
Draft guidelines-of-2000 mw-vgf-scheme
 
Various Schemes of Renewable Energy.pptx
Various Schemes of Renewable Energy.pptxVarious Schemes of Renewable Energy.pptx
Various Schemes of Renewable Energy.pptx
 
Solar rooftop opportunities and challenges
Solar rooftop opportunities and challengesSolar rooftop opportunities and challenges
Solar rooftop opportunities and challenges
 
India's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - DraftIndia's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - Draft
India's National Solar Mission Phase 2 Batch 2 Tranche 1 Guidelines - Draft
 
Rbsa Research Report rise of solar power in India
Rbsa Research Report  rise of solar power in IndiaRbsa Research Report  rise of solar power in India
Rbsa Research Report rise of solar power in India
 
The national solar mission
The national solar missionThe national solar mission
The national solar mission
 
Success Story of Solar Parks in India
Success Story of Solar Parks in IndiaSuccess Story of Solar Parks in India
Success Story of Solar Parks in India
 
Jawaharlal nehru national solar mission
Jawaharlal nehru national solar missionJawaharlal nehru national solar mission
Jawaharlal nehru national solar mission
 
Green Corner l2010
Green Corner l2010Green Corner l2010
Green Corner l2010
 
Session 13 national policy & regulatory framework & available incentives
Session 13   national policy & regulatory framework & available incentivesSession 13   national policy & regulatory framework & available incentives
Session 13 national policy & regulatory framework & available incentives
 
Harnessing solar in telangana
Harnessing solar in telanganaHarnessing solar in telangana
Harnessing solar in telangana
 
Future of solar Power Projects in India
Future of solar Power Projects in IndiaFuture of solar Power Projects in India
Future of solar Power Projects in India
 
SOLAR MISSION
SOLAR MISSION SOLAR MISSION
SOLAR MISSION
 
Introduction to JNNSM- India's National Solar Mission
Introduction to JNNSM- India's National Solar MissionIntroduction to JNNSM- India's National Solar Mission
Introduction to JNNSM- India's National Solar Mission
 
Consultancy Projects - Presentation
Consultancy Projects - Presentation Consultancy Projects - Presentation
Consultancy Projects - Presentation
 
Solar power - A developer prespective
Solar power - A developer prespectiveSolar power - A developer prespective
Solar power - A developer prespective
 
Final draft 3000 MW Phase 2 Batch 2 Tranche 1 Draft Guidelines
Final draft 3000 MW Phase 2 Batch 2 Tranche 1 Draft GuidelinesFinal draft 3000 MW Phase 2 Batch 2 Tranche 1 Draft Guidelines
Final draft 3000 MW Phase 2 Batch 2 Tranche 1 Draft Guidelines
 

More from Gensol Engineering Limited

More from Gensol Engineering Limited (20)

Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020
Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020
Factors Enhancing Bifacial Gain in India & Middle East_06.03.2020
 
Ground measured data vs meteo data sets:57 locations in India_01.01.2020
Ground measured data vs meteo data sets:57 locations in India_01.01.2020Ground measured data vs meteo data sets:57 locations in India_01.01.2020
Ground measured data vs meteo data sets:57 locations in India_01.01.2020
 
Gensol Engineering Limited - Investor Deck_26.09.2019
Gensol Engineering Limited - Investor Deck_26.09.2019Gensol Engineering Limited - Investor Deck_26.09.2019
Gensol Engineering Limited - Investor Deck_26.09.2019
 
Electric Vehicles - Tax Benefits & Incentives_20.09.19
Electric Vehicles - Tax Benefits & Incentives_20.09.19Electric Vehicles - Tax Benefits & Incentives_20.09.19
Electric Vehicles - Tax Benefits & Incentives_20.09.19
 
Phases of Construction & Erection for Wind Power Project_03 09 2019
Phases of Construction & Erection for Wind Power Project_03 09 2019Phases of Construction & Erection for Wind Power Project_03 09 2019
Phases of Construction & Erection for Wind Power Project_03 09 2019
 
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
Highlights on 1200MW RE Tender with Assured Peak Power Supply_26 08 2019
 
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
Bill of Material of 132/33 KV 15 MVA Pooling Substation (15-07-2019)
 
List of Solar PV Tenders Floated in India - 11.03.2019
List of Solar PV Tenders Floated in India - 11.03.2019List of Solar PV Tenders Floated in India - 11.03.2019
List of Solar PV Tenders Floated in India - 11.03.2019
 
List of successful bidders 11.03.2019
List of successful bidders 11.03.2019List of successful bidders 11.03.2019
List of successful bidders 11.03.2019
 
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
Comparative Study on Forecasting & Scheduling - Solar & Wind 05.03.19
 
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
Tamil Nadu (TN) Solar Policy 2019 Highlights_07.02.2019
 
Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019Comparison of Solar-Wind Hybrid Policies-07.02.2019
Comparison of Solar-Wind Hybrid Policies-07.02.2019
 
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid TenderTender summary for SECI 2500 MW Wind-Solar Hybrid Tender
Tender summary for SECI 2500 MW Wind-Solar Hybrid Tender
 
Emerging Opportunities - Wind Solar Hybrid System
Emerging Opportunities - Wind Solar Hybrid System Emerging Opportunities - Wind Solar Hybrid System
Emerging Opportunities - Wind Solar Hybrid System
 
Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18
Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18
Wind Turbine Generator (WTG) Audit Checklist by Gensol - 16.06.18
 
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
Tender Summary for SECI 150 MW Rihand Dam Floating Solar - 13.05.2018
 
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
Quality Inspection for Solar Modules - Raw Material, Manufacturing & Lab Test...
 
Technical Risks in Solar PV Projects 18.03.18
Technical Risks in Solar PV Projects 18.03.18Technical Risks in Solar PV Projects 18.03.18
Technical Risks in Solar PV Projects 18.03.18
 
Gensol's Lender Engineer Credentials - 20.03.18
Gensol's Lender Engineer Credentials - 20.03.18Gensol's Lender Engineer Credentials - 20.03.18
Gensol's Lender Engineer Credentials - 20.03.18
 
Basics of Solar PV O&M - Solarig Gensol
Basics of Solar PV O&M - Solarig GensolBasics of Solar PV O&M - Solarig Gensol
Basics of Solar PV O&M - Solarig Gensol
 

Recently uploaded

Future of Trade 2024 - Decoupled and Reconfigured - Snapshot Report
Future of Trade 2024 - Decoupled and Reconfigured - Snapshot ReportFuture of Trade 2024 - Decoupled and Reconfigured - Snapshot Report
Future of Trade 2024 - Decoupled and Reconfigured - Snapshot Report
Dubai Multi Commodity Centre
 
Powerpoint showing results from tik tok metrics
Powerpoint showing results from tik tok metricsPowerpoint showing results from tik tok metrics
Powerpoint showing results from tik tok metrics
CaitlinCummins3
 
Presentation4 (2) survey responses clearly labelled
Presentation4 (2) survey responses clearly labelledPresentation4 (2) survey responses clearly labelled
Presentation4 (2) survey responses clearly labelled
CaitlinCummins3
 

Recently uploaded (20)

Guide to Networking Essentials 8th Edition by Greg Tomsho solution manual.doc
Guide to Networking Essentials 8th Edition by Greg Tomsho solution manual.docGuide to Networking Essentials 8th Edition by Greg Tomsho solution manual.doc
Guide to Networking Essentials 8th Edition by Greg Tomsho solution manual.doc
 
NFS- Operations Presentation - Recurrent
NFS- Operations Presentation - RecurrentNFS- Operations Presentation - Recurrent
NFS- Operations Presentation - Recurrent
 
Inside the Black Box of Venture Capital (VC)
Inside the Black Box of Venture Capital (VC)Inside the Black Box of Venture Capital (VC)
Inside the Black Box of Venture Capital (VC)
 
Powers and Functions of CPCB - The Water Act 1974.pdf
Powers and Functions of CPCB - The Water Act 1974.pdfPowers and Functions of CPCB - The Water Act 1974.pdf
Powers and Functions of CPCB - The Water Act 1974.pdf
 
Future of Trade 2024 - Decoupled and Reconfigured - Snapshot Report
Future of Trade 2024 - Decoupled and Reconfigured - Snapshot ReportFuture of Trade 2024 - Decoupled and Reconfigured - Snapshot Report
Future of Trade 2024 - Decoupled and Reconfigured - Snapshot Report
 
stock price prediction using machine learning
stock price prediction using machine learningstock price prediction using machine learning
stock price prediction using machine learning
 
Creative Ideas for Interactive Team Presentations
Creative Ideas for Interactive Team PresentationsCreative Ideas for Interactive Team Presentations
Creative Ideas for Interactive Team Presentations
 
Raising Seed Capital by Steve Schlafman at RRE Ventures
Raising Seed Capital by Steve Schlafman at RRE VenturesRaising Seed Capital by Steve Schlafman at RRE Ventures
Raising Seed Capital by Steve Schlafman at RRE Ventures
 
Stages of Startup Funding - An Explainer
Stages of Startup Funding - An ExplainerStages of Startup Funding - An Explainer
Stages of Startup Funding - An Explainer
 
Elevate Your Online Presence with SEO Services
Elevate Your Online Presence with SEO ServicesElevate Your Online Presence with SEO Services
Elevate Your Online Presence with SEO Services
 
1Q24_EN hyundai capital 1q performance
1Q24_EN   hyundai capital 1q performance1Q24_EN   hyundai capital 1q performance
1Q24_EN hyundai capital 1q performance
 
Special Purpose Vehicle (Purpose, Formation & examples)
Special Purpose Vehicle (Purpose, Formation & examples)Special Purpose Vehicle (Purpose, Formation & examples)
Special Purpose Vehicle (Purpose, Formation & examples)
 
The Truth About Dinesh Bafna's Situation.pdf
The Truth About Dinesh Bafna's Situation.pdfThe Truth About Dinesh Bafna's Situation.pdf
The Truth About Dinesh Bafna's Situation.pdf
 
How to Maintain Healthy Life style.pptx
How to Maintain  Healthy Life style.pptxHow to Maintain  Healthy Life style.pptx
How to Maintain Healthy Life style.pptx
 
Powerpoint showing results from tik tok metrics
Powerpoint showing results from tik tok metricsPowerpoint showing results from tik tok metrics
Powerpoint showing results from tik tok metrics
 
How Do Venture Capitalists Make Decisions?
How Do Venture Capitalists Make Decisions?How Do Venture Capitalists Make Decisions?
How Do Venture Capitalists Make Decisions?
 
MichaelStarkes_UncutGemsProjectSummary.pdf
MichaelStarkes_UncutGemsProjectSummary.pdfMichaelStarkes_UncutGemsProjectSummary.pdf
MichaelStarkes_UncutGemsProjectSummary.pdf
 
Your Work Matters to God RestorationChurch.pptx
Your Work Matters to God RestorationChurch.pptxYour Work Matters to God RestorationChurch.pptx
Your Work Matters to God RestorationChurch.pptx
 
Blinkit: Revolutionizing the On-Demand Grocery Delivery Service.pptx
Blinkit: Revolutionizing the On-Demand Grocery Delivery Service.pptxBlinkit: Revolutionizing the On-Demand Grocery Delivery Service.pptx
Blinkit: Revolutionizing the On-Demand Grocery Delivery Service.pptx
 
Presentation4 (2) survey responses clearly labelled
Presentation4 (2) survey responses clearly labelledPresentation4 (2) survey responses clearly labelled
Presentation4 (2) survey responses clearly labelled
 

National Solar Mission Status (July'17)

  • 1. GENSOL ENGINEERING PVT. LTD www.gensol.in National Solar Mission (16-17) - Highlights
  • 2. Key Points Presented by Standing Committee on Energy Gensol Group Standing Committee on Energy (16-17) has briefed the 16th Lok Sabha. The committee has presented the 28th report on ‘National Solar Mission –An Appraisal’ on 31st July 2017. Key discussion points have been covered in the presentation.
  • 3. National Solar Mission : Motive Gensol Group Initially,the Mission initiated to provide large-scale grid connected power. Also, to reduce our dependence on fast depleting conventional sources, knowing the fact that India has potentialmore than 750 GW from solar energy Mission is being expanded at rapidly towards decentralized & disbursed industrialisationto change the Rural EconomyofIndia. Looking into the wide emergence of the solar energy applications/utilization, NSM targets have been revised to 100 GW from 20 GW for Grid connected solar power projects in June2015.
  • 4. National Solar Mission : Overview Gensol Group • Deployment of 20,000 MW revised to 100,000 MW of grid connected solar power by 2022, • 2000 MW of off-grid solar applications including 20 million solar lights by 2022 • Support R&D and capacity building activities to achieve grid parity by 2022. • Developing solar manufacturing capability in the country; • 20 million sq. m. solar thermal collector area Government of India has the aggressive renewable energy (RE) capacity addition target of 175 GW to be achieved by 2022.
  • 5. India’s Renewable Energy Targets & Achievements Gensol Group 4385 8296 13115 32508 0.00 5000.00 10000.00 15000.00 20000.00 25000.00 30000.00 35000.00 Small Hydro Power Bio-Power Solar Power Wind Power Capacity in MW Renewable Source RE Installed Capacity (MW) as on July 2017 Out of 175 GW RE targets, 100 GW has been embattled to come from solar. As on July 2017, overall Renewable Energy targets reached approx. 57 GW out 175 GW ,which turns out to be 33% ,classified as 4 GW in Small hydro, 8 GW in Bio-Power, 13 GW in Solar Energy & 32 GW in Wind Power.
  • 6. National Solar Mission : Targets Vs Achievement Gensol Group Phase I of NSM (2010-13) Phase-II of NSM (2013-17) Phase-III of NSM (2017-2022) Segment Target Achievements (as on March 2013) Target Achievements (as on March 2017) Target Grid solar power 1100 MW 1686 MW 15900 MW 10602 MW 100000 MW Off-grid solar applications 200 MW 252 MW Sanctioned 117 MW Installed 600 MW 713 MW Sanctioned 345 MW Installed 2000 MW Solar Thermal Collectors 7 Million Sq. m 7 Million Sq. m 8 Million Sq.m 5 Million Sq.m 15 Million Sq.m NSM Targets has been divided into three phases – Phase - I, Phase II and Phase III. Achievements of Phase-I exceeded the targetsset for the period.
  • 7. Ambitious NSM Targets 2017-2022 : Category Wise Gensol Group The revised target of 100 GW is planned to be achieved in 7 years period (2015-16 to 2021-22) and broadly consist of 40 GW Grid connected Rooftop projectsand 60 GW large and medium size ground based solar power projects 100 GW Category I - 40 GW 40 GW – Rooftop Solar Category II - 60 GW 10 GW – Small Scale Grid projects 10 GW – Public Sector Undertakings 5 GW – Large Private Sector/IPPs 5 GW – SECI 20 GW – Under State Policies 10 GW – Ongoing programmes
  • 8. Grid Connected Solar Power Targets : Year- Wise Gensol Group Ministry has furnished Year-Wise targets to achieve 100 GW Grid connected solar power by 2022 as follows. Government is in process of arranging with World Bank, in consultation with Ministry of Finance, for US $ 100 million loan assistance for creating internal infrastructure of solar parks 200 4800 5000 6000 7000 8000 9000 1800 7200 10000 10000 10000 9500 8500 0 2000 4000 6000 8000 10000 12000 14000 16000 18000 20000 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 MNRE Yearwise Solar Targets (MW) MNRE Yearwise Solar Targets (MW) Roofttop MNRE Yearwise Solar Targets (MW) Ground Mounted
  • 9. Grid Connected Solar Power : Target Vs Achievements Gensol Group 11 36 1030 1686 2632 3744 6763 12289 13115 11 25 994 656 946 1112 3019 5526 826 0 2000 4000 6000 8000 10000 12000 14000 Upto 2010 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 2017-18 CAPACITY IN MW YEAR WISE ANNUAL SOLAR PV INSTALLATIONS (MW) –YOY AS ON 31ST JULY 2017 Cumulative Installed Capacity (MW) Annual Installed Capacity (MW)
  • 10. Schemes to Achieve Ambitious Targets of 100 GW Gensol Group 1. • To set up 300 MW of Grid connected Solar PV Power Projects by Defense Establishments under Ministry of Defense and Para Military Forces with VGF. 2. • To develop schemes for Solar Parks and Ultra Mega Solar Power Projects. 3. • For development of Solar PV Power Plants on Canal Banks/ Canal Tops. 4. • Implementation of scheme for setting up 1000 MW of Grid- Connected Solar PV Power Projects by Central Public Sector Undertakings (CPSUS) with VGF 5. • Implementation of Scheme for Setting up of 15000 MW of Grid connected Solar PV Power Projects under Batch II of Phase II of National Solar Mission (by NTPC/NVVN) 6. • Schemes for setting up of 750 MW, 2000 MW, and 5000 MW Grid connected solar power with Viability Gap Funding through Solar Energy Corporation of India (SECI) 7. • Development of Solar Cities Programme & Installation of Grid Connected Solar Rooftop Power Plants.
  • 11. 1. Setting of 300 MW SPV by Defense Establishment Gensol Group It has been identified that cantonment and Military Stations have high Potential of Solar Energy of approximately 5000 MWand in Ordnance Factory Boards (OFB)ofaround 950 MW Establishments of Ministry of Defense has planned to set up 300 MW in various places like Establishments of Army, Navy, Air Force, Ordnance Factory Board, Defense Laboratories and Defense PSUs etc. with minimum size of the project of 1 MW. The projects under this Scheme will mandatorily use solar cells/modules whichare made in India. A total of 300 MW capacity to be added in 5 years from 2014- 19 Overall, 357.5 MW Sanctioned under which 128 MW tendered, 52 MW order placed & 7 MW projects commissioned. As on date, 357.5 MW has been allocated under the scheme : Name of Organization Capacity (MW) Status Ordnance Factory Board 7 Commissioned Bharat Electronics Ltd. 150 35 MW: Order placed, under construction 36 MW: Tendering under process Bharat Dynamics Limited 25 5 MW: Order placed, under construction Department of Defence 150 26 MW: Order placed, under construction Hindustan Aeronautics Ltd., Nasik 15 5 MW: Tender issued, order to be placed by 30th May,2017 Ordnance factory 5 Tendering for 15 MW to be done by June,2017 MIDHANI 4 Tendering in process Ordnance Factory, Ambajhari 1.5 Tender will be issued by June,2017 Total 357.5
  • 12. 2. Development of Solar Parks & Ultra Mega Solar Parks Gensol Group 20 50 60 69 100 100 200 500 500 500 500 500 600 700 1000 1000 1500 2000 2750 3351 4000 0 500 1000 1500 2000 2500 3000 3500 4000 4500 Capacity in MW States in India Proposed Solar Park Capacity (MW)
  • 13. 2. Development of Solar Parks & Ultra Mega Solar Parks Gensol Group Status of Solar Projects in Solar Park Particulars Capacity (MW) Solar Projects already commissioned inside Solar Parks during 2016-17 1516 Solar Projects likely to be commissioned inside Solar Parks during 2017-18 2229 Capacity already tendered out but may be commissioned in 2018-19 2100 Capacity expected to be tendered out in 2017-18 (operational solar parks) 6425 Capacity Expected to be tendered out in 2017-18 (activities are yet to be started) 7730 Total 20000 The Ministry provides Central Financial Assistance (CFA) of up to Rs. 25 lakh per solar park for preparation of Detailed Project Report (DPR). CFA of up to Rs. 20.00 lakh per MW or 30% of the project cost, including Grid-connectivity cost, whichever is lower, grant is released by Solar Energy Corporation of India Ltd. (SECI) as per milestones. The total requirement of funds estimated to provide CFA as Rs. 4050.00 crore, of which INR 906.12 has already disbursed. Overall, 34 solar parks in 21 states with 20 GW capacity are approved with land acquired for 71,000 MW, 7300 MW capacity has been tendered & 1.5 GW in 4 parks is commissioned.
  • 14. 3. Development of Canal tops/Banks : Targets Vs Achievements Gensol Group Rs.3 crore/MW or 30% of the project cost, whichever is lower, for Canal Top SPV projects and Rs. 1.5 crore/MW or 30% of the project cost, whichever is lower, for Canal Bank SPV projects will be assisted. •Upto 40% on sanctioning of the projects. •60% on successful commissioning of the projects. •Service charge to SECI @1%: Rs.2.25 crore. CFA of upto Rs.225 crore for 100 MW (50 MW on Canal Tops and 50 MW on Canal Banks) to be disbursed over a period of maximum 2 years post sanctioning of the plants as under: Allocation of 50 MW Canal-Top Solar PV Projects State Approved capacity (MW) Commissioned Capacity (MW) Punjab 20 5 Gujarat 10 Work in progress Karnataka 10 In tendering process UP 6 Work in progress Kerala 2 2 AP 1 1 Uttarakhand 1 Work in progress Total 50 8 Allocation of 50 MW Canal-Bank Solar PV Projects State Approved capacity (MW) Commissioned Capacity (MW) Uttarakhand 19 Work in progress Gujarat 15 Work in progress West Bengal 10 10 AP 5 5 Kerala 1 1 Total 50 16 Central Financial Assistance under the scheme-
  • 15. 4. Solar PV Power Projects by Central Public Sector Undertakings (CPSUS) Gensol Group GOI will provide VGF as under: • a) Rs.1 Cr. /MW, if Cells and Modules for the project are manufactured indigenously. • b) Rs.50 Lakh /MW, if Modules for the project are manufactured indigenously. VGF will be released in two tranches as follows: • a) 50% on LoI and start of installation work at plant; and • b) Balance 50% on successful commissioning of the full capacity of the project (CoD)”. The duration of implementation of the Scheme is 2015-18. MNRE has allocated 1037.26 MW (Out of which 669 MW commissioned) capacity to following 15 CPSUs/Govt. Organizations within the sanctioned funds of Rs. 1000 Crorefor this scheme. 680 16.5 5 200 50 6 5.76 74 62.13% 50.00% 100.00% 0.00% 0.00% 0.00% 25.00% 11.73% 0.00% 20.00% 40.00% 60.00% 80.00% 100.00% 120.00% 0 100 200 300 400 500 600 700 800 VGF Funded in % Capacity in MW Capacity Wise (MW) VGF Funded Projects Capacity Sanctioned (MW) % of VGF Amount Released
  • 16. 5. Bundling Scheme : 15000 MW of Grid connected Solar PV Gensol Group 3000 5000 7000 0 1000 2000 3000 4000 5000 6000 7000 8000 2014-15 to 2016- 17 (Tranche I) 2015-16 to 2017- 18 (Tranche II) 2016-17 to 2018- 19 (Tranche III) Capacity (MW) Targeted Capacity (MW) Tranche Wise Currently Tranche-I, is under implementation. In Tranche-I, which is Batch-II of Phase-II of National Solar Mission, 3000 MW (3600 MW open & 400 MW DCR Category) capacity of solar PV power plants will be based on bundling with unallocated thermal power (1500 MW) in the ratio of 2:1 & has been already tendered , PPA signed for 2750 MW & 1090 MW projects commissioned. 1100 500 550 350 100 150 100 100 50 0 0 200 400 600 800 1000 1200 1400 Andhra Pradesh Karnataka Rajasthan Telangana Uttar PradeshCapacity in MW Status Of Tranche I - 3000 MW State Specific Bundling Scheme Under NSM Phase-ii, Batch-ii Capacity allotted in DCR category (MW) Capacity allotted in OPEN category (MW)
  • 17. 6. Viability Gap Funding through Solar Energy Corporation of India (SECI) Gensol Group A) 750 MW VGF Scheme Phase-II, Batch-I (Implemented) B) 2000 MW VGF Scheme Phase II, Batch III (Under Implementation) 10 10 20 25 40 220 355 0 50 100 150 200 250 300 350 400 State Wise Commissioned Capacity(MW) 500 325 400 100 1000 35 50 500 325 400 100 970 0 0 500 325 400 100 970 0 0 0 200 400 600 800 1000 1200 State Wise Allocation of Capacity (MW)) RfS issued (MW) LoI issued (MW) PPA signed (MW) After a transparent selection and award process, project capacity of 680 MW (out of 750 MW) could successfully achieve financial closure. SECI has issued RfS for 2410 MW capacity in 7 states. LoI has been issued for 2295 MW. PPAs have been signed for 2295 MW.
  • 18. 6. Viability Gap Funding through Solar Energy Corporation of India (SECI) Gensol Group C) 5000 MW VGF Scheme Phase II, Batch IV (Under Implementation) 400 300 750 450 450 200250 270 0 450 0 0 250 270 0 450 0 0 0 100 200 300 400 500 600 700 800 Gujarat Odisha Andhra Pradesh Maharashtra Karnataka Rajasthan VGF Fund Granted - SPV Capacity (MW) RfS issued (MW) LoI issued (MW) PPA signed (MW) • The scheme is proposed to be implemented by SECI in four tranches of 1250 MW each, spread over four years, from 2015-16up to FY 2018-19 • RfS has already been issued for 2850 MW capacity in 6 states. LoI has been issued for 970 MW. PPAs have been signed for 970 MW. • Due to various mechanisms including the reverse bidding on VGF as well as on tariff, the discovered tariff has reduced from Rs. 17.91 to Rs. 2.44 per kWh that will benefit both developer to Produce & sell through SECI to DISCOMs Overall, till date, 5260 MW tender issued, 3265 MW PPA signed and 80 MW Projects commissioned for2000 MW & 5000 MW scheme
  • 19. Bidding – Success Story….. Gensol Group The trends of solar tariff in India till 2016-17 are given below: The reasons for plummeting of the cost of solar power prices are as under: (i) Conducive policies for encouraging solar sector; (ii) Improved project structuring and technology; (iii) Better learning curve; (iv) Decline in cost of solar cells/modules and Cost of financing” Global trend in solar tariff through bidding during period 2016-17 is as given below 2.99 1.99 2.91 2.42 2.7 May-16 May-16 Aug-16 Sep-16 Oct-16 Abu DhabiDubaiChile Abu DhabiMexico World Wide Tariff (US cent/kWh) 16-17 12.1600 8.7900 8.3700 11.8250 6.5675 10.5935 4.9462 2.7986 0 5 10 15 2009-10 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 TARIFF (RS/KWH) Weighted Avg. Price (Rs./KWh) 2009-2017 In 16-17, steep fall down of the the solar tariff recorded. In the bidding held in February 2017 for solar projects to be set up in Rewa Solar Park, Madhya Pradesh; the levelized tariff has come down to Rs. 3.30 per kWh. The solar tariff declined to Rs. 3.15 per unit in the reverse auction done by NTPC at Kadapa Solar Park in Andhra Pradesh in April, 2017. The solar tariff further declined to Rs. 2.44 per unit in the recent reverse auction done by SECI at Bhadla Phase-III Solar Park in Rajasthan in May, 2017.
  • 20. 7. Grid Interactive Rooftop & Small SPV Programme Gensol Group To meet the targets of 40 GW (Out of 100 GW) that needs to be achieved from grid connected solar rooftops by 2022, Ministry has introduced various subsidies have been introduced. •The capital subsidy of 30% (70 % for special category Sates and Andaman & Nicobar and Lakshadweep Islands) is available for residential, institutional and social sectors. •MNRE is implementing RTS Programme for development of 4200 MW. Out of 4200 MW capacity, 2100 MW capacity has to be installed through CFA/ incentive in the residential, social, Government / PSU and Institutional sectors. The balance 2100 MW is to be implemented without any subsidy. • As on 30th April 2017, MNRE has sanctioned projects of cumulative capacity of 2032 MWp to various State Nodal Agencies (SNAS) and Public Sector Undertakings / Authorities (SECI, CEL, REIL, Railways, AAI, etc), of which about 661 MW of RTS capacities have been installed including subsidised and non-subsidised projects. •Ministry has scaled-up budget from Rs. 600 crore during the 12th Five Year Plan to Rs. 5000 crore for RTS to be installed up to 2019-20 that will provide financial support for installation of 4200 MW. The reasons for slow progress are as follows: •Involvement of multiple approval process like connectivity, net metering, Chief Electrical inspection (CEI), limitation in sanctioned etc. •Skill and knowledge gaps •Withdrawal of subsidy/CFA in private industrial and commercial sector •Non-uniformity of Power Purchase Agreement (PPA) and Engineering, Procurement and Construction (EPC) agreements •Slow progress of Implementing agencies •Lack of consumer awareness •Non-uniform regulations across states •Tedious process for project commissioning and subsidy disbursement •Frequent changes in Government Policies •Lack of policies addressing grid connected rooftop solar
  • 21. 7. Grid Interactive Rooftop & Small SPV Programme Gensol Group 16 21.44 50 60 74.81 179.5 1049.6 0 6.74 15.05 0 11.14 3.7 90.7 0 200 400 600 800 1000 1200 Capacity in MW Status and Achievements in RTS & NCEF Scheme Rooftop Projects under Govt. Dept/PSUs Sanctioned (MW) Overall Commissioned capacity (MW) 0 20 40 60 80 100 120 Bihar Arunachal Pradesh Meghalaya Mizoram Nagaland Sikkim Tripura Dadra & Nagar Haveli Daman & Diu Andaman & Nicobar … Lakshadweep Goa Puducherry Jammu & Kashmir West Bengal Odisha Manipur Karnataka Himachal Pradesh Chhattisgarh Uttar Pradesh Kerala Haryana Punjab Assam Chandigarh Rajasthan Andhra Pradesh Madhya Pradesh Uttarakhand Jharkhand Telangana Gujarat Delhi Maharashtra Tamil Nadu Capacity in MW Status and Achievements in RTS & NCEF Scheme Rooftop Projects State-wise Sanctioned (MW) Overall Commissioned capacity (MW)
  • 22. Off-Grids & Decentralized Solar Applications Gensol Group 30% subsidy on the cost of the system ranging from Rs. 18/- per watt peak to Rs.142.5/- depending on the module capacity & system 90% subsidy ranging from Rs.63/- to Rs.306/- for off- grid solar PV applications For installation of stand- alone SPV power plants by Central and State Govt. Bodies & their establishments in Special Category and North East States & Islands. subsidy of 40% of the capital cost limited to Rs. 136/Wp (LED based) upto 40 Watt peak & Rs. 80/Wp for system above 40 Wp limited to 300 Wp through NABARD, Regional Rural Banks and other Commercial Banks. the capital subsidy ranges from Rs.25,560 per Hp to Rs. 36,000 per Hp depending upon category and capacity for Solar Water Pumping system
  • 23. Solar Pumps Programme : Status as on date Gensol Group 14000 1000000 1270000 280200 0 1430000 67000 0 200000 400000 600000 800000 1000000 1200000 1400000 1600000 1992-2014 2014-2015 2015-2017 2017-2018 Solar Pumps Installedas on 31st May 17 –Y0Y No of Solar Pumps Installed Target The Ministry provides 30% capital Subsidy through State Nodal Agencies for irrigation and drinking water and 40% capital Subsidy through NABARD with mandatory loan. Target of 67000 pumps initiated in 2017-18 under Off-grid solar pumps. Out of that, 50000 solar pump sets has been sanctioned in the first phase. Of which, 28020 solar projects completed so far. 1000 2460 3000 3050 6000 6500 7500 10000 10000 180 0 277 0 5500 6204 6216 3517 6126 0 2000 4000 6000 8000 10000 12000 14000 16000 18000 Odisha Maharashtra Karnataka Haryana Uttar Pradesh Gujarat Rajasthan Andhra Pradesh Chhattisgarh State-Wise Sanctioned/ Completed Solar Pumps 2017-18 Sanctioned Quantity (Nos.) Completed so far (Nos.)
  • 25. Off-Grid Solar Program : Progress Gensol Group Under NSM 1st & 2nd Phase target, around 800 MW of projects for Off-Grid Solar PV applications were targeted. Out of which, 965.5 MW Sanctioned & 462.5 MW installed till date. MNRE in cooperation with Deutsche Gesellschaftfuer Internationale Zusammenarbiet (GIZ), is implementing a project on “Solar Thermal Solution for Space Heating in Ladakh (SolLad)”. As a result of this, Kargil Renewable Energy Development Agency has come up with a proposal to install 1000 Nos. of Solar Space Heating systems in the region of Leh and Kargil. Under NSM, targets of installing solar collectors are 15 million square meters up to 2017 and 20 million square meter up to 2022 respectively. Out of which, around 1 million square meter collector area has been installed by 31st March 2016.Water Heating System subsidy discontinued w.e.f. 1st Oct 2014 with 12 million sq.m installations so far. Under Atal Jyoti Yojana, Ministry targeted installation of 2,97,440 street lights in 169 constituencies in Uttar Pradesh, Bihar, Jharkhand, Odisha and Assam by 2018 . Out of which, only 9401 lights are installed as on date. The main constrain is availability of batteries, which are needed to be imported.
  • 26. Performance Under DCR Category in India Gensol Group To promote solar manufacturing in India, MNRE had been following the policy of Domestic Content Requirement (DCR) under its various Schemes for solar projects with support through Viability Gap Funding (VGF) or bundling of thermal power. But now this policy itself has been challenged in WTO. 100 MW in AP under 2000 MW VGF Scheme & 350 MW under 5000 MW VGF scheme got cancelled after WTO ruling. 0 250 300 375 750 1000 4200 400 100 300 355 25 1000 2347 0 1000 2000 3000 4000 Batch - II/Tranche - I (Bundling Scheme) Batch - III (2000 MW VGF Scheme) 300 MW Defense Scheme Batch - I (Grid Connected) Batch -IV (5000 MW VGF Scheme) 1000 MW CSPU Scheme RTS Scheme (MNRE) Phase -2 DCR Category Targets Target Achieved (MW) Target Capacity (MW) 150 350 70 70 0 50 100 150 200 250 300 350 400 Batch - I Batch - II Axis Title Phase 1- NSM Batch I & II (DCR Category) TargetCapcity (MW) under DCR Category Target Achieved (MW)
  • 27. Skill Development in India Gensol Group According to the MNRE, Research & Development activities aims at resource assessment, technology development, demonstration and commercialization for promoting the large scale use of new and renewable energy (solar, wind, biogas, biofuel, hydrogen and fuel cells, geothermal, etc) across the country. 2000.00 7000.00 12000.00 14000.00 15000.00 2713 8,300 0 0 0 0 2000 4000 6000 8000 10000 12000 14000 16000 2015-16 2016-17 2017-18 2018-19 2019-20 No of Person Year Wise Human Resource Targets No. of persons to be trained No. of persons trained •Development and demonstration of 1 MW capacity solar thermal power R&D project with 16-hour thermal storage at Mount Abu, with co-funding from German Ministry and Indian industry. •SECI is implementing a R&D project entitled “Development of Solar PV and wind hybrid power plant with large scale battery storageat Kaza,Himachal Pradesh consisting of 2.5 MW solar and wind hybrid with 1 MWh battery storage •The Ministry has launched the Suryamitra Training programme on 28th May, 2015 with a target of training 50,000 persons as Solar PV Technicians in the various statesby 2019 •The Ministry has sanctioned/released an amount of total Rs. 41.91 crores to National Institute of Solar Energy (NISE) for implementation of Surya Mitra programme and NISE has spent Rs. 35.4 crores as on 31.03.2017 R & D Activities
  • 28. Observations & Recommendations to achieve NSM Targets Gensol Group Key highlights A target of 175 GW has been set to be achieved by 2022. The success of the mission solely and squarely hinges on the success of solar energy programmes. More schemes should be initiated with respect to financial investment like providing access to loans at more favorable rate of interests, introduce Green Bonds through SECI, approaching international donors, arranging finances from Green Climate fund etc. Under Development of Solar Parks and Ultra Mega Solar Power Project only 1516 MW capacity, out of 20,000 MW capacity, have been commissioned inside Solar Parks. All necessary actions should be taken to expedite the development of Solar Parks. CFA actually released for preparation of DPR for solar park is only INR 906.12 Crores i.e. about 45% short of the target (INR 1650 Crores). Reasons for low disbursement of funds should be identified and remedial measures should be taken in this regard. In the view of falling solar tariff, there is no justification in paying the developers INR 4.43 per kWh as solar tariff under VGF scheme. Reconsideration in the VGF Scheme in the CPSUs sector should be done, due to floundering of projects. Under Bundling Scheme 15000 MW through NTPC, only 1090 MW has been commissioned (under tranche I i.e 3000 MW); 64% short of the target. The aim of bundling thermal power with solar power is to incentivize the solar power. However, in the view of dropping solartariff, thermal power is getting incentivized.
  • 29. Observations & Recommendations to achieve NSM Targets Gensol Group Key highlights Single Window Clearance System should be adopted in RTS for approvals like connectivity, net-metering, electricity inspection, limitation in sanctioned load,etc. and the process of subsidy disbursement should be madesimpler. To give boost to rooftop solar systems, operationalization of Net Metering is of utmost importance. However, DISCOMs are reluctant to operationalize the Net-Metering Regulations as it may reduce their income from high- paying customers. Micro cooperative grid in a standalone manner should be explored wherein a group of consumers/ householdscan be pooled in for availing thesolar rooftop benefits among themselves. As the Solar Pumps scheme is mainly focused on small and marginal farmers who may not be able to bring upfrontcapital, the procedure foravailing loansshould bemade easier and simpler. Off-Grid applications are uneconomical since they face obstacles including high capital cost, complicated procedure of subsidy disbursal, difficulty in local operation and maintenance. Hence, Public-Private Partnership with rural entrepreneurs should beencouraged. DCR: Per unit price of solar power has dropped from INR 10.95 in December 2010 to INR 2.44 in May 2017. For arriving at lower tariff, the bidder may have considered a lower Return of Equity (ROE) which makes the quality of the material used in an apprehensive state. Hence, High Anti-Dumping Duty or Duty based on efficiency of the material imported should be imposed so as to discourage import of poor quality material. Despite of low labour cost, Indian Manufacturers are not able to compete with Chinese Firms. Urgently a dedicated Programme should be formulated to establish India as a Solar Manufacturing Hub so as to provide policy support to the complete value chain.
  • 30. About Gensol Solar Advisory Services Solar EPC Services Solar O&M Services 6,490 MW 42 MW 776 MW Gensol Group Gensol provides concept to commissioning solar advisory, execution and operations services for Solar Projects in India and abroad. 103 Projects 65 Execution Engineers71 Design & Supply Chain Engineers Anmol Singh Evangelist +91 7698833311 anmoljaggi@gensol.in Imran Naqvi Head of Strategic Advisory & Business Development +91 9327016962 imrannaqvi@gensol.in Gurpreet Singh Head of Engineering & Operations +91 9725544301 gurpreetsingh@gensol.in Puneet Singh Jaggi Director +91 9998025820 puneetjaggi@gensol.in Pranay Mundra President +91 9850673664 pranaymundra@gensol.in Shivya Singhal Head of Supply Chain & Group CFO +91 9376703846 shivyasinghal@gensol.in
  • 31. Gensol is one of the leading consultants and system integrators for Solar Power Plants. We boast of a portfolio of over 6000 MW of Solar Photovoltaic Plants. Gensol is also a channel partner to Ministry of New & Renewable Energy and installs kW scale Solar Rooftop systems on a turnkey basis with more than 42 MW of cumulative installations across the country. The information contained herein is of a general nature and is not intended to address the circumstances of any particular individual or entity. Although we endeavor to provide accurate and timely information, there can be no guarantee that such information is accurate as of the date it is received or that it will continue to be accurate in the future. No one should act on such information without appropriate professional advice after a thorough examination of the particular situation. Email: solar@gensol.in | Web: www.gensol.in | Phone: +91 79 40068235 | Twitter: gensol_tweets Gensol Engineering Pvt Ltd | Gensol Consultants Pvt Ltd | Solarig Gensol Utilities Pvt Ltd Corporate Office 108, Pinnacle Business Park, Opp. Royal Arcade, Prahladnagar, Ahmedabad, Gujarat. India - 380015