SlideShare a Scribd company logo
1 of 19
CONTENT
• INTRODUCTION
• LITERATURE REVIEW
• PLASTIC CELLS
• PROCESS OF MAKING CELL FILLED PAVEMENT
• PREPARATION OF SUBGRADE AND SUBBASE
• CONSTRUCTION
• JOINTS
• CURING
• CASE STUDY
• COST COMPARISION
• ADVANTAGES & DISADVANTAGES
• CONCLUSION
• REFERENCES
8/18/2023 1
I. INTRODUCTION
 Under PMGSY, the rural road network has experienced a considerable growth. The
good quality roads being constructed, immensely contribute in the progress of the
country.
 Most of the low volume village roads being constructed are flexible pavement
provided with thin bituminous surface. Quite often these roads get damaged due to
overloaded vehicles, inadequate drainage facility and water logging problems.
 The technology developed by IIT KHARAGPUR, known as CELL FILLED
PAVEMENT, has proved to be very promising solution for this issue. It provides
long lasting concrete pavement at low initial cost which are almost maintenance
free.
8/18/2023 2
II. LITERATURE REVIEW
3
SL
NO
JOURNAL
NAME
AUTHOR
AND
YEAR
FINDING
1. Structural
Evaluation of
Self Filled
Concrete
Pavement
Sahoo
(2018)
• Constructed 250 meter long PCCP pavement
over 150 mm compacted thickness of moorum
sub-base to test its feasibility on field for low
volume roads.
• The premixed cement concrete mix used for
filling the pockets of plastic cell was mixed in
the proportion 1:1.5:3 (cement: fine aggregate:
coarse aggregate) by volume.
• The result obtained from the investigation
showed that the elastic modulus of cell filled
concrete layer were in the range 2486 to 6850
MPa and that of foundation layer (sub-base and
sub-grade) were in the range 123 to 161 MPa
which are sufficiently high for low volume
roads.
5/06/2023 4
SL
NO
JOURNAL
NAME
AUTHOR
AND
YEAR
FINDING
2. Study On Plastic
Self Filled
Pavement
Prof.
Shrikant M.
(2021)
• Carried a review study on plastic cell-
filled block pavement by constructing a
test section and concluded that PCCBP is
economical than flexible pavement
considering over all cost of construction
and maintenance and found the pavement
to be good as per PCI rating, the roughness
due to cells make little difference in riding
quality.
V. PREPARATION OF SUBGRADE AND SUBBASE
• The subgrade forms the top 300mm thick portion of the embankment and it should be
prepared as per specifications for rural roads.
• If the embankment soil is poor, the top 300mm of the subgrade may consist of good
quality material from borrow pits with CBR exceeding five. It should be compacted to
at least 100% of maximum dry density.
• The subbase may consist of laterite boulder consolidation, water bound macadam, wet
mix macadam, brick consolidation, crusher run macadam , lime-fly ash aggregate
mixtures, lime stabilized soil, cement stabilized soil and others with proprietary
stabilizers.
8/18/2023 5
Fig 8 Subbase
VI. CONSTRUCTION
• Construction of embankment, subgrade and subbase should be done as per
specifications for rural roads.
• Proper camber as applicable to rural roads should be provided. Drainage
layer also should be provided in high rainfall area as laid down in rural road
manual.
• Stone / concrete block or brick on end edge should be laid on either side of
the carriageway projecting 50 to 100mm above the subbase for the
confinement and protection of cell filled concrete of thickness 50 to
100mm.
• Hard shoulder with proper camber is necessary for the stability of the
concrete blocks since trucks travelling close to the edge may damage the
unconfined concrete blocks.
8/18/2023 6
• Formwork of plastic cells may be laid across the compacted subbase and put under
tension with iron spikes so that cells are close to squares in plan.
• Concrete should be filled into the cells to a depth of about 120mm which is about 20mm
higher than the depth of the cell.
• Some amount of water may evaporate during mixing, transportation and placing during
hot weather and this may result in a dry mix.
Fig 5.1 Filling of concrete to plastic cells Fig 5.2 Compaction using Pan Vibratory
8/18/2023 7
VII. JOINTS
• Since the concrete is in the form of blocks of size 150*150mm with plastic sheets on
the vertical interfaces, no joints are necessary.
• The concrete blocks would shrink during curing causing a gap of about 20 microns
between two neighboring blocks, Joints are therefore not necessary in the
construction.
8/18/2023 8
Fig 9 Aggregates filling in the last group of cells
VIII. CURING
 Because of camber of about 3 to 3.5% specified for rural roads, wet coir mats
and wet paddy straw provide better water curing option and light traffic can be
allowed to move on the surface as per IRC 84 -1983. And water ponding method
is done for curing
8/18/2023 9
Fig 10 Curing
XI. OPENING TO TRAFFIC:
Concrete surface can be opened to light traffic
such as bicycle. rickshaw. motorcycle etc after two
days of curing. Iron rimmed bullock carts and
heavy traffic like bus, truck, tractor etc can be
permitted after l4 days when concrete is
sufficiently strong.
X. APPEARANCE OF TOP SURFÁCE:
The outline of the plastic formwork is clearly seen.
The formwork of cells 100mm deep may not
always be visible if concrete thickness 1s more
than 100mm at some locations creaks would form
at the locations or the plastic sheets showing the
pattern of the formwork of plastic cells after
application of traffic some months.
8/18/2023 10
Fig 11 Appearance of Top SurfĂĄce
IX. CASE STUDY
ANUR HUNASENAHALLI ROAD, SIDLAGHATTA TALUK OF
CHICKABALLAPURA, KARNATAKA
The area selected was from Anur Hunasenahalli to T-07 (2.16 km) in Sidlaghatta Taluk.
• The above selected road is categorized under Village Roads (VR) and is constructed
under the Technology Demonstration Project of PMGSY phase IX.
• The objective of the work was to conduct Pavement Performance Studies on the
said road which include the Structural and Functional evaluations.
• For Functional evaluation, roughness was measured using MERLIN and Pavement
condition survey by longitudinal /transverse cracking, severity of potholes and area
of patching has been measured.
• In the traffic surveys different types of vehicles including commercial vehicles
have been recorded for 72 hours. In the axle load surveys, type of vehicle, number
of axles and load on each axle has been recorded to determine the Vehicle damage
factor (VDF).
8/18/2023 11
RESULTS OF THE EVALUATIONS IN ANUR
HUNASENAHALLI ROAD
From structural evaluation-
• The average characteristic deflection is found to be 0.32 mm. Cell- filled
concrete pavement showed minimum deflection than the interlocked block
pavement & flexible pavement.
• The average characteristic deflection is found to be 0.32 mm. Cell- filled
concrete pavement showed minimum deflection than the interlocked block
pavement & flexible pavement.
From functional evaluation-
• International Roughness Index (IRI) value obtained is below 3 and has a good
riding quality or riding comfort (as per TRL report). The cell-fill concrete section
has showed a little higher roughness value than other technologies due to its
exposed cells on the pavement surface.
• The PCI value of cell-filled concrete section is 94, which is much better than
other technologies. Therefore requires no maintenance.
8/18/2023 12
COST COMPARISION MADE OF PCCB AND RIGID
PAVEMENT
1. COSTING OF PCCB PAVEMENT
 Total cost for preparation of cell forms made of plastic for 3750Sqm area
= Rs 2,75,248.49
 Total cost of concrete for 3750 Sqm area = Rs 28,59,451.875/-
Total cost for PCCB pavement = RS 37,27,012.865/-
2. RIGID PAVEMENT COSTING
• Total cost of Rigid Pavement= Rs 28,18,948.25/-
• Add 5% transportation charges = Rs 1,40,947.41/-
• Grand Total cost of concrete for 3750 Sqm area = Rs 29,59,895.66/-
• Therefore, Concrete cost per Sqm area = RS 789.30/-
Total cost for rigid pavement = RS 56,00,476.96/-
COMPARATIVE STUDY
• Total cost of rigid pavement = RS 56,00,476.96/-
• Total cost of PCCB pavement = RS 37,27,012.865/-
• Difference between cost of rigid and PCCB pavement = RS 18,73,464.095/-
8/18/2023 13
• Use of recycled plastic.
• Expansion or contraction joints are not of required and hence maintenance of
joints is eliminated.
• The cost of construction is considerably reduced when compared to conventional
cement concrete pavement.
• The consumption of aggregates is almost reduced to S0% when compared to
normal CC pavements.
• Due to high stiffness, the overall crust requirement gets reduced hence
economical for low volume of roads.
• If the individual blocks fails, then it can be easily replaced without much effort
and with least cost.
8/18/2023 14
ADVANTAGES
• The preparation of the cells is cumbersome.
• The cells get disturbed while placing the concrete and hence proper care is
required.
• Placing of the concrete without disturbing the cells slows down the progress.
• Consumption of labour is more, more labour oriented work.
• Due to slow progress, the actual turn out of the men and machinery is less than
the normal construction.
• The cost of providing kerb is additional and is time consuming.
• Possibility of formwork of clod joints between two successive concrete layer
leads to observed in failure (as Karnataka) requires treatment at cold construction
joints.
8/18/2023 15
DISADVANTAGES
• Most beneficial in rural areas.
• It is essentially the best cost-efficient alternative solution to areas with
technical challenges.
• Overlays on damaged tar roads.
• Pavements and footpaths.
• Container yards.
• Parking area for heavy vehicles.
• The plastic cell filled concrete finds excellent utility in road surface
stabilization, road should stabilization, or road base stabilization.
8/18/2023 16
APPLICATIONS
CONCLUSION
 Cell filled concrete pavement can be recommended for weak base and sub-base layers instead of
flexible pavement, since it showed resistance to structural durability.
 Construction of Cell Filled Concrete Pavement is advantageous compared to Conventional Concrete
and Asphalt pavement.
 Compared to conventional materials, using road materials that include plastic waste has the following
benefits:
1. Reduces whole life cost
2. Longer service life
3. Preserves natural resources
4. Reduces plastic waste in landfills.
 Hypothetical flexible–rigid pavement structure utilising plastic waste elements, PCCBP has been
theoretically assessed for its potential to offer:
1. Good serviceability (durability, weather resilience, and riding quality)
2. Improved sustainability (higher recyclability and waste contents)
3. Cost savings
4. Positive socioeconomic impacts.
 Concrete with plastic cell filling roads could be a solution for the rural roads because of the life of
Concrete roads is much more. It’s beneficial to use cell filled in low Volume traffic condition.
17
REFERENCES:
• Roy S., (2009) “ Flexible-rigid Pavement Materials A Sustainable Solution For
Village Roads” Journal Of Indian Roads Congress.
• Sahoo UC, Reddy K S, And Pandey B B, Structural evaluation of concrete block
pavement International journal of pavement engineering and asphalt
technology(2018).
• ISSN 1997-1400 Int. J. Pavement Res. Technology Vol.5 No.4 Jul. 2012 Distress
Evaluation of Plastic Cell Filled Concrete Block Pavement Yendrembam
Arunkumar Singh1,
• International Journal of Engineering Research and General Science Volume 3, Issue
4, July-August, 2015. ISSN 2091-2730549Design aspects of cement concrete
pavement for Rural Roads in India Narender Singh Sub-Divisional Engineer, PWD
(B&R) Branch Sirsa, Haryana (India)
• Yendrembam Arun Kumar Singh, Taiborlang lyngdoh ryntathlang, konjengbam
darunkumar singh, "Economic evaluation of plastic surgery filled concrete block
pavement International journal of engineering and advanced technology ( IJEAT),
Vol. 5, Issue 3,( 2016).
8/18/2023 18
8/18/2023 19

More Related Content

What's hot

5.track or permanent way and track stresses
5.track or permanent way and track stresses5.track or permanent way and track stresses
5.track or permanent way and track stressesMani Vel
 
Project report on CC road
Project report on CC roadProject report on CC road
Project report on CC roadvikash mishra
 
Failures in flexible pavement
Failures in flexible pavementFailures in flexible pavement
Failures in flexible pavementRandhir Kumar
 
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESHPRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESHImrul Quesh
 
FLEXIBLE And Rigid Pavement
FLEXIBLE And Rigid PavementFLEXIBLE And Rigid Pavement
FLEXIBLE And Rigid PavementKhaliqur Rahman
 
BITUMEN MIXES FOR ROAD
BITUMEN MIXES FOR ROADBITUMEN MIXES FOR ROAD
BITUMEN MIXES FOR ROADkumawat123
 
Dense Bituminous Macadam Road
Dense Bituminous Macadam RoadDense Bituminous Macadam Road
Dense Bituminous Macadam RoadSaratMishra4
 
PQC concrete road
PQC concrete roadPQC concrete road
PQC concrete roadpramodchavan32
 
Dense bituminous macadam
Dense bituminous macadamDense bituminous macadam
Dense bituminous macadamHimanshu Pipaliya
 
Mass Concrete, RMC, Plum Concrete
Mass Concrete, RMC, Plum ConcreteMass Concrete, RMC, Plum Concrete
Mass Concrete, RMC, Plum ConcreteJay1997Singhania
 
Bituminous road construction
Bituminous road constructionBituminous road construction
Bituminous road constructionAnitha Jacob
 
road construction
road constructionroad construction
road constructionRebwar Anwar
 
HIGHWAY NETWORK SYSTEM
HIGHWAY NETWORK SYSTEMHIGHWAY NETWORK SYSTEM
HIGHWAY NETWORK SYSTEMseminarppts
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavementpjainrahul
 
Highway failure & their maintenance seminar report
Highway failure & their maintenance seminar reportHighway failure & their maintenance seminar report
Highway failure & their maintenance seminar reportBeing Deepak
 
Rigid Pavements Design Part - I
Rigid Pavements Design Part - IRigid Pavements Design Part - I
Rigid Pavements Design Part - ISachin Kulkarni
 
Construction of Road
Construction of RoadConstruction of Road
Construction of RoadAman Shakya
 

What's hot (20)

FINAL REPORT
FINAL REPORTFINAL REPORT
FINAL REPORT
 
5.track or permanent way and track stresses
5.track or permanent way and track stresses5.track or permanent way and track stresses
5.track or permanent way and track stresses
 
Project report on CC road
Project report on CC roadProject report on CC road
Project report on CC road
 
Failures in flexible pavement
Failures in flexible pavementFailures in flexible pavement
Failures in flexible pavement
 
Construction of rigid pavement
Construction of rigid pavement Construction of rigid pavement
Construction of rigid pavement
 
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESHPRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
 
FLEXIBLE And Rigid Pavement
FLEXIBLE And Rigid PavementFLEXIBLE And Rigid Pavement
FLEXIBLE And Rigid Pavement
 
BITUMEN MIXES FOR ROAD
BITUMEN MIXES FOR ROADBITUMEN MIXES FOR ROAD
BITUMEN MIXES FOR ROAD
 
Dense Bituminous Macadam Road
Dense Bituminous Macadam RoadDense Bituminous Macadam Road
Dense Bituminous Macadam Road
 
PQC concrete road
PQC concrete roadPQC concrete road
PQC concrete road
 
Pavement
PavementPavement
Pavement
 
Dense bituminous macadam
Dense bituminous macadamDense bituminous macadam
Dense bituminous macadam
 
Mass Concrete, RMC, Plum Concrete
Mass Concrete, RMC, Plum ConcreteMass Concrete, RMC, Plum Concrete
Mass Concrete, RMC, Plum Concrete
 
Bituminous road construction
Bituminous road constructionBituminous road construction
Bituminous road construction
 
road construction
road constructionroad construction
road construction
 
HIGHWAY NETWORK SYSTEM
HIGHWAY NETWORK SYSTEMHIGHWAY NETWORK SYSTEM
HIGHWAY NETWORK SYSTEM
 
Rigid pavement
Rigid pavementRigid pavement
Rigid pavement
 
Highway failure & their maintenance seminar report
Highway failure & their maintenance seminar reportHighway failure & their maintenance seminar report
Highway failure & their maintenance seminar report
 
Rigid Pavements Design Part - I
Rigid Pavements Design Part - IRigid Pavements Design Part - I
Rigid Pavements Design Part - I
 
Construction of Road
Construction of RoadConstruction of Road
Construction of Road
 

Similar to PPT FINAL.pptx

INTERLOCKING CONCRETE BLOCKS PAVEMENTS
INTERLOCKING CONCRETE BLOCKS PAVEMENTSINTERLOCKING CONCRETE BLOCKS PAVEMENTS
INTERLOCKING CONCRETE BLOCKS PAVEMENTSDileep Gowda
 
Highway network system
Highway network system Highway network system
Highway network system sanjay majumdar
 
presentation on road pavement (zeeshan)
presentation on road pavement (zeeshan)presentation on road pavement (zeeshan)
presentation on road pavement (zeeshan)alamrintu
 
IRJET- Study on Design of Polymer based Flexible Pavements for Low Volume Roads
IRJET- Study on Design of Polymer based Flexible Pavements for Low Volume RoadsIRJET- Study on Design of Polymer based Flexible Pavements for Low Volume Roads
IRJET- Study on Design of Polymer based Flexible Pavements for Low Volume RoadsIRJET Journal
 
IRJET - Design of Improved Drainage System using Pervious Concrete
IRJET  -  	  Design of Improved Drainage System using Pervious ConcreteIRJET  -  	  Design of Improved Drainage System using Pervious Concrete
IRJET - Design of Improved Drainage System using Pervious ConcreteIRJET Journal
 
IRJET - Experimental Investigation on No-Fines Concrete with Tyre as a Partia...
IRJET - Experimental Investigation on No-Fines Concrete with Tyre as a Partia...IRJET - Experimental Investigation on No-Fines Concrete with Tyre as a Partia...
IRJET - Experimental Investigation on No-Fines Concrete with Tyre as a Partia...IRJET Journal
 
Technical textiles in Central Public Works Department
Technical textiles in Central Public Works DepartmentTechnical textiles in Central Public Works Department
Technical textiles in Central Public Works DepartmentDr K M SONI
 
PREETHAM B PPT.pptx
PREETHAM B   PPT.pptxPREETHAM B   PPT.pptx
PREETHAM B PPT.pptxSanjayS980435
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concreteMylene Delmoro
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concreteMylene Delmoro
 
RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)Anil Gupta
 
ugmented Reality (AR) emerges SEMINAR PPT.pptx
ugmented Reality (AR) emerges SEMINAR PPT.pptxugmented Reality (AR) emerges SEMINAR PPT.pptx
ugmented Reality (AR) emerges SEMINAR PPT.pptxPrasannaKs15
 
Presentation.pptx
Presentation.pptxPresentation.pptx
Presentation.pptxPranavKd
 
Village networking ppt
Village networking pptVillage networking ppt
Village networking pptPatel Tapan
 
Design of Flexible Pavements for an Existing Road
Design of Flexible Pavements for an Existing RoadDesign of Flexible Pavements for an Existing Road
Design of Flexible Pavements for an Existing RoadIRJET Journal
 
IRJET- A Review on Box Pushing Technique
IRJET- A Review on Box Pushing TechniqueIRJET- A Review on Box Pushing Technique
IRJET- A Review on Box Pushing TechniqueIRJET Journal
 
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdfROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdfDanielWisman1
 
Lowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure servicesLowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure servicesAr Jitendra
 
Subgrade, ETB and Asphalt Site Organisation construction procedure-2.pptx
Subgrade, ETB and Asphalt Site Organisation construction procedure-2.pptxSubgrade, ETB and Asphalt Site Organisation construction procedure-2.pptx
Subgrade, ETB and Asphalt Site Organisation construction procedure-2.pptxEricNikorido1
 

Similar to PPT FINAL.pptx (20)

INTERLOCKING CONCRETE BLOCKS PAVEMENTS
INTERLOCKING CONCRETE BLOCKS PAVEMENTSINTERLOCKING CONCRETE BLOCKS PAVEMENTS
INTERLOCKING CONCRETE BLOCKS PAVEMENTS
 
Highway network system
Highway network system Highway network system
Highway network system
 
presentation on road pavement (zeeshan)
presentation on road pavement (zeeshan)presentation on road pavement (zeeshan)
presentation on road pavement (zeeshan)
 
IRJET- Study on Design of Polymer based Flexible Pavements for Low Volume Roads
IRJET- Study on Design of Polymer based Flexible Pavements for Low Volume RoadsIRJET- Study on Design of Polymer based Flexible Pavements for Low Volume Roads
IRJET- Study on Design of Polymer based Flexible Pavements for Low Volume Roads
 
IRJET - Design of Improved Drainage System using Pervious Concrete
IRJET  -  	  Design of Improved Drainage System using Pervious ConcreteIRJET  -  	  Design of Improved Drainage System using Pervious Concrete
IRJET - Design of Improved Drainage System using Pervious Concrete
 
IRJET - Experimental Investigation on No-Fines Concrete with Tyre as a Partia...
IRJET - Experimental Investigation on No-Fines Concrete with Tyre as a Partia...IRJET - Experimental Investigation on No-Fines Concrete with Tyre as a Partia...
IRJET - Experimental Investigation on No-Fines Concrete with Tyre as a Partia...
 
Technical textiles in Central Public Works Department
Technical textiles in Central Public Works DepartmentTechnical textiles in Central Public Works Department
Technical textiles in Central Public Works Department
 
PREETHAM B PPT.pptx
PREETHAM B   PPT.pptxPREETHAM B   PPT.pptx
PREETHAM B PPT.pptx
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concrete
 
Road pavements-of-cement-concrete
Road pavements-of-cement-concreteRoad pavements-of-cement-concrete
Road pavements-of-cement-concrete
 
Roadstab 2017
Roadstab 2017Roadstab 2017
Roadstab 2017
 
RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)RIGID PAVEMENT -ANIL GUPTA (P.W.D)
RIGID PAVEMENT -ANIL GUPTA (P.W.D)
 
ugmented Reality (AR) emerges SEMINAR PPT.pptx
ugmented Reality (AR) emerges SEMINAR PPT.pptxugmented Reality (AR) emerges SEMINAR PPT.pptx
ugmented Reality (AR) emerges SEMINAR PPT.pptx
 
Presentation.pptx
Presentation.pptxPresentation.pptx
Presentation.pptx
 
Village networking ppt
Village networking pptVillage networking ppt
Village networking ppt
 
Design of Flexible Pavements for an Existing Road
Design of Flexible Pavements for an Existing RoadDesign of Flexible Pavements for an Existing Road
Design of Flexible Pavements for an Existing Road
 
IRJET- A Review on Box Pushing Technique
IRJET- A Review on Box Pushing TechniqueIRJET- A Review on Box Pushing Technique
IRJET- A Review on Box Pushing Technique
 
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdfROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
ROAD CONSTRUCTION (FLEXIBLE & RIGID) - SLIDES.pdf
 
Lowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure servicesLowcost prefebrication and infrastructure services
Lowcost prefebrication and infrastructure services
 
Subgrade, ETB and Asphalt Site Organisation construction procedure-2.pptx
Subgrade, ETB and Asphalt Site Organisation construction procedure-2.pptxSubgrade, ETB and Asphalt Site Organisation construction procedure-2.pptx
Subgrade, ETB and Asphalt Site Organisation construction procedure-2.pptx
 

Recently uploaded

High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 

Recently uploaded (20)

High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 

PPT FINAL.pptx

  • 1. CONTENT • INTRODUCTION • LITERATURE REVIEW • PLASTIC CELLS • PROCESS OF MAKING CELL FILLED PAVEMENT • PREPARATION OF SUBGRADE AND SUBBASE • CONSTRUCTION • JOINTS • CURING • CASE STUDY • COST COMPARISION • ADVANTAGES & DISADVANTAGES • CONCLUSION • REFERENCES 8/18/2023 1
  • 2. I. INTRODUCTION  Under PMGSY, the rural road network has experienced a considerable growth. The good quality roads being constructed, immensely contribute in the progress of the country.  Most of the low volume village roads being constructed are flexible pavement provided with thin bituminous surface. Quite often these roads get damaged due to overloaded vehicles, inadequate drainage facility and water logging problems.  The technology developed by IIT KHARAGPUR, known as CELL FILLED PAVEMENT, has proved to be very promising solution for this issue. It provides long lasting concrete pavement at low initial cost which are almost maintenance free. 8/18/2023 2
  • 3. II. LITERATURE REVIEW 3 SL NO JOURNAL NAME AUTHOR AND YEAR FINDING 1. Structural Evaluation of Self Filled Concrete Pavement Sahoo (2018) • Constructed 250 meter long PCCP pavement over 150 mm compacted thickness of moorum sub-base to test its feasibility on field for low volume roads. • The premixed cement concrete mix used for filling the pockets of plastic cell was mixed in the proportion 1:1.5:3 (cement: fine aggregate: coarse aggregate) by volume. • The result obtained from the investigation showed that the elastic modulus of cell filled concrete layer were in the range 2486 to 6850 MPa and that of foundation layer (sub-base and sub-grade) were in the range 123 to 161 MPa which are sufficiently high for low volume roads.
  • 4. 5/06/2023 4 SL NO JOURNAL NAME AUTHOR AND YEAR FINDING 2. Study On Plastic Self Filled Pavement Prof. Shrikant M. (2021) • Carried a review study on plastic cell- filled block pavement by constructing a test section and concluded that PCCBP is economical than flexible pavement considering over all cost of construction and maintenance and found the pavement to be good as per PCI rating, the roughness due to cells make little difference in riding quality.
  • 5. V. PREPARATION OF SUBGRADE AND SUBBASE • The subgrade forms the top 300mm thick portion of the embankment and it should be prepared as per specifications for rural roads. • If the embankment soil is poor, the top 300mm of the subgrade may consist of good quality material from borrow pits with CBR exceeding five. It should be compacted to at least 100% of maximum dry density. • The subbase may consist of laterite boulder consolidation, water bound macadam, wet mix macadam, brick consolidation, crusher run macadam , lime-fly ash aggregate mixtures, lime stabilized soil, cement stabilized soil and others with proprietary stabilizers. 8/18/2023 5 Fig 8 Subbase
  • 6. VI. CONSTRUCTION • Construction of embankment, subgrade and subbase should be done as per specifications for rural roads. • Proper camber as applicable to rural roads should be provided. Drainage layer also should be provided in high rainfall area as laid down in rural road manual. • Stone / concrete block or brick on end edge should be laid on either side of the carriageway projecting 50 to 100mm above the subbase for the confinement and protection of cell filled concrete of thickness 50 to 100mm. • Hard shoulder with proper camber is necessary for the stability of the concrete blocks since trucks travelling close to the edge may damage the unconfined concrete blocks. 8/18/2023 6
  • 7. • Formwork of plastic cells may be laid across the compacted subbase and put under tension with iron spikes so that cells are close to squares in plan. • Concrete should be filled into the cells to a depth of about 120mm which is about 20mm higher than the depth of the cell. • Some amount of water may evaporate during mixing, transportation and placing during hot weather and this may result in a dry mix. Fig 5.1 Filling of concrete to plastic cells Fig 5.2 Compaction using Pan Vibratory 8/18/2023 7
  • 8. VII. JOINTS • Since the concrete is in the form of blocks of size 150*150mm with plastic sheets on the vertical interfaces, no joints are necessary. • The concrete blocks would shrink during curing causing a gap of about 20 microns between two neighboring blocks, Joints are therefore not necessary in the construction. 8/18/2023 8 Fig 9 Aggregates filling in the last group of cells
  • 9. VIII. CURING  Because of camber of about 3 to 3.5% specified for rural roads, wet coir mats and wet paddy straw provide better water curing option and light traffic can be allowed to move on the surface as per IRC 84 -1983. And water ponding method is done for curing 8/18/2023 9 Fig 10 Curing
  • 10. XI. OPENING TO TRAFFIC: Concrete surface can be opened to light traffic such as bicycle. rickshaw. motorcycle etc after two days of curing. Iron rimmed bullock carts and heavy traffic like bus, truck, tractor etc can be permitted after l4 days when concrete is sufficiently strong. X. APPEARANCE OF TOP SURFÁCE: The outline of the plastic formwork is clearly seen. The formwork of cells 100mm deep may not always be visible if concrete thickness 1s more than 100mm at some locations creaks would form at the locations or the plastic sheets showing the pattern of the formwork of plastic cells after application of traffic some months. 8/18/2023 10 Fig 11 Appearance of Top SurfĂĄce
  • 11. IX. CASE STUDY ANUR HUNASENAHALLI ROAD, SIDLAGHATTA TALUK OF CHICKABALLAPURA, KARNATAKA The area selected was from Anur Hunasenahalli to T-07 (2.16 km) in Sidlaghatta Taluk. • The above selected road is categorized under Village Roads (VR) and is constructed under the Technology Demonstration Project of PMGSY phase IX. • The objective of the work was to conduct Pavement Performance Studies on the said road which include the Structural and Functional evaluations. • For Functional evaluation, roughness was measured using MERLIN and Pavement condition survey by longitudinal /transverse cracking, severity of potholes and area of patching has been measured. • In the traffic surveys different types of vehicles including commercial vehicles have been recorded for 72 hours. In the axle load surveys, type of vehicle, number of axles and load on each axle has been recorded to determine the Vehicle damage factor (VDF). 8/18/2023 11
  • 12. RESULTS OF THE EVALUATIONS IN ANUR HUNASENAHALLI ROAD From structural evaluation- • The average characteristic deflection is found to be 0.32 mm. Cell- filled concrete pavement showed minimum deflection than the interlocked block pavement & flexible pavement. • The average characteristic deflection is found to be 0.32 mm. Cell- filled concrete pavement showed minimum deflection than the interlocked block pavement & flexible pavement. From functional evaluation- • International Roughness Index (IRI) value obtained is below 3 and has a good riding quality or riding comfort (as per TRL report). The cell-fill concrete section has showed a little higher roughness value than other technologies due to its exposed cells on the pavement surface. • The PCI value of cell-filled concrete section is 94, which is much better than other technologies. Therefore requires no maintenance. 8/18/2023 12
  • 13. COST COMPARISION MADE OF PCCB AND RIGID PAVEMENT 1. COSTING OF PCCB PAVEMENT  Total cost for preparation of cell forms made of plastic for 3750Sqm area = Rs 2,75,248.49  Total cost of concrete for 3750 Sqm area = Rs 28,59,451.875/- Total cost for PCCB pavement = RS 37,27,012.865/- 2. RIGID PAVEMENT COSTING • Total cost of Rigid Pavement= Rs 28,18,948.25/- • Add 5% transportation charges = Rs 1,40,947.41/- • Grand Total cost of concrete for 3750 Sqm area = Rs 29,59,895.66/- • Therefore, Concrete cost per Sqm area = RS 789.30/- Total cost for rigid pavement = RS 56,00,476.96/- COMPARATIVE STUDY • Total cost of rigid pavement = RS 56,00,476.96/- • Total cost of PCCB pavement = RS 37,27,012.865/- • Difference between cost of rigid and PCCB pavement = RS 18,73,464.095/- 8/18/2023 13
  • 14. • Use of recycled plastic. • Expansion or contraction joints are not of required and hence maintenance of joints is eliminated. • The cost of construction is considerably reduced when compared to conventional cement concrete pavement. • The consumption of aggregates is almost reduced to S0% when compared to normal CC pavements. • Due to high stiffness, the overall crust requirement gets reduced hence economical for low volume of roads. • If the individual blocks fails, then it can be easily replaced without much effort and with least cost. 8/18/2023 14 ADVANTAGES
  • 15. • The preparation of the cells is cumbersome. • The cells get disturbed while placing the concrete and hence proper care is required. • Placing of the concrete without disturbing the cells slows down the progress. • Consumption of labour is more, more labour oriented work. • Due to slow progress, the actual turn out of the men and machinery is less than the normal construction. • The cost of providing kerb is additional and is time consuming. • Possibility of formwork of clod joints between two successive concrete layer leads to observed in failure (as Karnataka) requires treatment at cold construction joints. 8/18/2023 15 DISADVANTAGES
  • 16. • Most beneficial in rural areas. • It is essentially the best cost-efficient alternative solution to areas with technical challenges. • Overlays on damaged tar roads. • Pavements and footpaths. • Container yards. • Parking area for heavy vehicles. • The plastic cell filled concrete finds excellent utility in road surface stabilization, road should stabilization, or road base stabilization. 8/18/2023 16 APPLICATIONS
  • 17. CONCLUSION  Cell filled concrete pavement can be recommended for weak base and sub-base layers instead of flexible pavement, since it showed resistance to structural durability.  Construction of Cell Filled Concrete Pavement is advantageous compared to Conventional Concrete and Asphalt pavement.  Compared to conventional materials, using road materials that include plastic waste has the following benefits: 1. Reduces whole life cost 2. Longer service life 3. Preserves natural resources 4. Reduces plastic waste in landfills.  Hypothetical flexible–rigid pavement structure utilising plastic waste elements, PCCBP has been theoretically assessed for its potential to offer: 1. Good serviceability (durability, weather resilience, and riding quality) 2. Improved sustainability (higher recyclability and waste contents) 3. Cost savings 4. Positive socioeconomic impacts.  Concrete with plastic cell filling roads could be a solution for the rural roads because of the life of Concrete roads is much more. It’s beneficial to use cell filled in low Volume traffic condition. 17
  • 18. REFERENCES: • Roy S., (2009) “ Flexible-rigid Pavement Materials A Sustainable Solution For Village Roads” Journal Of Indian Roads Congress. • Sahoo UC, Reddy K S, And Pandey B B, Structural evaluation of concrete block pavement International journal of pavement engineering and asphalt technology(2018). • ISSN 1997-1400 Int. J. Pavement Res. Technology Vol.5 No.4 Jul. 2012 Distress Evaluation of Plastic Cell Filled Concrete Block Pavement Yendrembam Arunkumar Singh1, • International Journal of Engineering Research and General Science Volume 3, Issue 4, July-August, 2015. ISSN 2091-2730549Design aspects of cement concrete pavement for Rural Roads in India Narender Singh Sub-Divisional Engineer, PWD (B&R) Branch Sirsa, Haryana (India) • Yendrembam Arun Kumar Singh, Taiborlang lyngdoh ryntathlang, konjengbam darunkumar singh, "Economic evaluation of plastic surgery filled concrete block pavement International journal of engineering and advanced technology ( IJEAT), Vol. 5, Issue 3,( 2016). 8/18/2023 18