Successfully reported this slideshow.
We use your LinkedIn profile and activity data to personalize ads and to show you more relevant ads. You can change your ad preferences anytime.
1
CROSSTOWN LRT
Construction Liaison Committee
January 2020
2
Leaside Station Update
3
Leaside Station: Ongoing Construction
Activities
Area Current Activities
•
•
•
•
•
•
•
•
•
•
4
Leaside Station: Look Ahead
Year What to Expect
•
•
•
•
•
5
Current Traffic Staging
5
No S/B Right
Turn on Red.
6
January 15, 2020 through to spring 2020
•
•
•
•
7
Leaside Station Progress Photos
STATION BOX MAIN ENTRANCE
SOUTH TUNNEL SECONDARY ENTRANCE
8
Emergency Exit 3 Site
(Leaside High School)
9
Emergency Exit 3 Update
•
•
•
•
10
Emergency Exit 3 Sidewalk Restoration
• As early as January 16, 2020, crews will be restoring the permanent sidewalk on...
11
Laird Station Update
12
Laird Station: Ongoing Construction
Activities
Area Current Activities
•
•
•
•
•
13
Laird Station: Look Ahead
•
•
•
•
•
14
15
Laird Station Progress Photos
CONCRETE AND REBAR
WORKS IN THE CAVERN
ARCH FORM REMOVAL IN
CAVERN CONCRETE AND REBAR WOR...
Upcoming SlideShare
Loading in …5
×

of

Leaside  Laird Construction Liaison Committee (CLC) Meeting Presentation Slide 1 Leaside  Laird Construction Liaison Committee (CLC) Meeting Presentation Slide 2 Leaside  Laird Construction Liaison Committee (CLC) Meeting Presentation Slide 3 Leaside  Laird Construction Liaison Committee (CLC) Meeting Presentation Slide 4 Leaside  Laird Construction Liaison Committee (CLC) Meeting Presentation Slide 5 Leaside  Laird Construction Liaison Committee (CLC) Meeting Presentation Slide 6 Leaside  Laird Construction Liaison Committee (CLC) Meeting Presentation Slide 7 Leaside  Laird Construction Liaison Committee (CLC) Meeting Presentation Slide 8 Leaside  Laird Construction Liaison Committee (CLC) Meeting Presentation Slide 9 Leaside  Laird Construction Liaison Committee (CLC) Meeting Presentation Slide 10 Leaside  Laird Construction Liaison Committee (CLC) Meeting Presentation Slide 11 Leaside  Laird Construction Liaison Committee (CLC) Meeting Presentation Slide 12 Leaside  Laird Construction Liaison Committee (CLC) Meeting Presentation Slide 13 Leaside  Laird Construction Liaison Committee (CLC) Meeting Presentation Slide 14 Leaside  Laird Construction Liaison Committee (CLC) Meeting Presentation Slide 15
Upcoming SlideShare
What to Upload to SlideShare
Next
Download to read offline and view in fullscreen.

0 Likes

Share

Download to read offline

Leaside Laird Construction Liaison Committee (CLC) Meeting Presentation

Download to read offline

Construction updates for Leaside and Laird Stations presented to the CLC on January 13, 2020.

  • Be the first to like this

Leaside Laird Construction Liaison Committee (CLC) Meeting Presentation

  1. 1. 1 CROSSTOWN LRT Construction Liaison Committee January 2020
  2. 2. 2 Leaside Station Update
  3. 3. 3 Leaside Station: Ongoing Construction Activities Area Current Activities • • • • • • • • • •
  4. 4. 4 Leaside Station: Look Ahead Year What to Expect • • • • •
  5. 5. 5 Current Traffic Staging 5 No S/B Right Turn on Red.
  6. 6. 6 January 15, 2020 through to spring 2020 • • • •
  7. 7. 7 Leaside Station Progress Photos STATION BOX MAIN ENTRANCE SOUTH TUNNEL SECONDARY ENTRANCE
  8. 8. 8 Emergency Exit 3 Site (Leaside High School)
  9. 9. 9 Emergency Exit 3 Update • • • •
  10. 10. 10 Emergency Exit 3 Sidewalk Restoration • As early as January 16, 2020, crews will be restoring the permanent sidewalk on the south side of Eglinton Avenue East across from Donlea Drive. • Work is expected to continue for approximately six (6) days. • The work will require a temporary closure of the eastbound HOV lane on Eglinton Avenue East (depicted below). • Pedestrians will be rerouted around the work zone.
  11. 11. 11 Laird Station Update
  12. 12. 12 Laird Station: Ongoing Construction Activities Area Current Activities • • • • •
  13. 13. 13 Laird Station: Look Ahead • • • • •
  14. 14. 14
  15. 15. 15 Laird Station Progress Photos CONCRETE AND REBAR WORKS IN THE CAVERN ARCH FORM REMOVAL IN CAVERN CONCRETE AND REBAR WORKS IN THE CAVERN

Construction updates for Leaside and Laird Stations presented to the CLC on January 13, 2020.

Views

Total views

344

On Slideshare

0

From embeds

0

Number of embeds

266

Actions

Downloads

0

Shares

0

Comments

0

Likes

0

×