SlideShare a Scribd company logo
1 of 24
Download to read offline
Project Handbook
Biogas Powerplant Project
Project Handbook
Biogas Powerplant Project
Version 1.0
Project Manager: Carsten
Group Members:
Ujjwal Kumar Joshi
Project Handbook
Biogas Powerplant Project
Contents
1. Short description of project
2. Project assignment
3. Plan of objectives
4. Description of pre- and post-project phase
5. Project environment analysis
6. Connection between the project, other projects and the organization’s strategy
7. Project organization chart
8. Work breakdown structure (WBS)
9. Project work-package specifications
10. Project responsibility matrix
11. Milestone plan
12. Project bar chart
13. Personnel planning
14. Project cost plan
Project Handbook
Biogas Powerplant Project
1. Short description of project
The production of biogas and the conversion into electricity is subsidized in Germany via the EEG law.
This allowed the construction of biogas power plants with up to 500 kW electrical powers as
agricultural facilities in the farms.
The biogas power plant project is planned to be implemented within a farm in the Westphalian
countryside. This farm produces piglets (young pigs) which are produced by hosting around 400 sows
(mother pigs). The pigs produced also 2000 cbm of waste, in which it must be stored to be used as
fuel for producing heating and electricity.
The biogas power plant will use the liquid waste to produce methane gas for heating of the farm. The
power plant also need apart from biogas, energy from crops like corn or grass. Electricity will also be
produced from the power plant, which will be sold to local energy provider for fixed price and have a
guaranteed price by law for the next 20 years. The project is intended to produce electricity in 2009.
The prerequisite for the permit to build the power plant is that there must be an agreed contract
with local farmers to purchase energy crops over 5 years. After the prerequisite is fulfilled, the power
plant construction can be started, in which it consisted of 3 main building blocks which is crop silo,
block power and heat plant, fermentation and waste facilities. Biogas will be produced 3-4 weeks
after starting to feed the fermentation pots.
The project is planned to be finished at the end 2009 so that the goal to produce electricity can be
achieved.
Project Handbook
Biogas Powerplant Project
2. Project Assignment
Project Assignment
project start event:
Contracts with local farmers are secured
project start date:
24-08-2009
project end event:
Production of biogas energy
project end date:
31-12-2009
project objectives:
 Process waste and crops to produce
electricity and heating (biogas energy)
 Constructing silo & weighing machine
 Constructing block heat & power plant
 Constructing fermentation & waste
facilities
non-objectives:
 Securing contract with local farmers
 Selling of electricity
main tasks (project phases):
 Project management
 Project setup
 Silo & weighing machine
 Block heat & power plant
 Fermentation & waste facilities
 Production (one time test production)
 Review & sign off
project resources and costs:
Resource/cost type unit cost (euro)
 Silo
 Weighing Machine
 Trafo
 Block heat and power
plant
 Auxiliary heating
facility
 Fermentation facilities
 Ground movement +
traffic areas
 Small building
 Crops harvest
 Materials, bio diesel,
oil
TOTAL
200,000
30,000
50,000
200,000
25,000
800,000
100,000
30,000
150,000
10,000
1,595,000
project owner:
Daniel and Anton
project manager:
Carsten
project team:
 Marco (Planner)
 Axel (Project Manager Ground Work)
 Willi (Project Manager Silo)
 Sven (Project Manager Fermenter + Block
Power and Heat Plant)
 Hans (Project Manager Trafo)
 Gerd (Project Manager Weighing Machine)
project coach:
……………………………………………………… …………………………………………………………..
Carsten (project manager) Daniel and Anton (project owners)
Project Handbook
Biogas Powerplant Project
3. Plan of objectives
Plan of goals
(objectives, non-objectives)
Current Objectives Adjusted Objectives as of (date)
Main objectives
Additional
objectives
 Process waste and crops to produce
electricity and heating (biogas
energy)
 Constructing silo & weighing
machine
 Constructing block heat & power
plant
 Constructing fermentation & waste
facilities
Non objectives  Securing contract with local farmers
 Selling of electricity
Project Handbook
Biogas Powerplant Project
4. Description of pre- and post-project phase
description of pre- and post
project phase
1) pre project phase
What triggered the project?
 EEG law forced the states in Germany to construct Bio gas power plants as agricultural facilities in
farms
 The need to use the liquid waste for better use
 To generate the cheaper electricity
Relevant decisions, events
 Decision to do the project in a farm in the westphalian countryside
Relevant documents
 Contract with local farmers (prerequisite for starting the project)
 Project planning documentations
2) post project phase
What will happen after the project has ended?
 Control the flow of resources needed to produce the biogas
 Secure more contracts with local farmers
Use of experiences
 The team will focus long term on Biogas projects
 The team can apply their experiences in other states and countries
 The resulting action plan from the lessons learned review will be executed
Relevant documents
 Project manual
 Review documentations
Project Handbook
Biogas Powerplant Project
5. Project environment analysis
Project environment analysis
Project environment table
Environment Relationship Evaluation Activity Responsible Date
Project
Owners
(Daniel &
Anton)
Customer
(Positive)
Expect and desire
project success
Project start &
closure
(WBS 1.1.2
WBS 1.1.6)
Biogas
production
(WBS 1.6)
Reviews
(WBS 1.7)
PM (Carsten) 24.08.09-
01.09.09
30.12.09
17.11.09-
29.12.09
01.12.09-
29.12.09
Projects
managers
(Axel, Willi,
Sven, Hans,
Gerd)
Executes the
project
phases
(Positive)
Motivated to
achieve their
success with
responsibility and
accountability
Execution of
the project
(WBS 1.2-1.7)
PM (Carsten)
Projects
managers (Axel,
Willi, Sven,
Hans, Gerd)
24.08.09-
29.12.09
Biogas powerplant
project
Overall project
manager
(Carsten)
Project owners
(Daniel & Anton)
Project managers
Planner
(Marco)
Farmer & main user
(Stefan)
Bank contact
(Bernd)
Other farmers
(Josef & Armin)
Public authorities
(Markus)
+ : Positive influence
- : Negative influence
+
+
+
+
+
-
-
+
External
Internal
Project Handbook
Biogas Powerplant Project
Farmer &
main user
(Stefan)
Farm owner
(Positive)
Gain access to
renewable energy
to reduce costs
Biogas
production
(WBS 1.6.2)
Review
(WBS 1.7)
PM (Carsten) 08.12.09-
28.12.09
01.12.09-
31.12.09
Public
authorities
(Markus)
Grant
permits
(Negative)
Make sure the
requirements to
start the project
are met
Project
management
(WBS 1.1)
PM (Carsten) 24.08.09-
31.12.09
Other
farmers
(Josef &
Armin)
Supply crops
for making
biogas
(Positive)
Gain access to
renewable energy
Biogas
production
(WBS 1.6.2)
PM (Carsten) 08.12.09-
28.12.09
Bank contact
(Bernd)
Help finance
the project
(Negative)
Discussion of
possibility for
project funding
Project
management
(WBS 1.1)
PM (Carsten) 24.08.09-
31.12.09
Planner
(Marco)
Develop plan
for the
project
(Positive)
Develop strategic
plan to support
the overall
execution of the
project
Project
management
(WBS 1.1)
PM (Carsten) 24.08.09-
31.12.09
Project Handbook
Biogas Powerplant Project
6. Connection between project, other projects and the organization’s strategy
connection between the project and other projects
Project Relationship Evaluation Activity Responsible Date
connection between the project and organization’s strategy
Strategy of the
organization
Description of the relationship
Improve the usage of
renewable energy in
Germany
Reduce the usage of fossil fuel and CO2 level in Germany
Address the farmers in
Westphalia countryside
Give them the possibility to process the waste to another form of
process and gain some income from it
Project Handbook
Biogas Powerplant Project
(project support)
Project Organization
7. Project organization chart
Project Managers
(project execution)
Carsten
(Project
Manager)
Axel
(Ground
Work)
Gerd
(Weighing
Machine)
Hans
(Trafo)
Sven
(Fermenter +
Block Power +
Heat Plant)
Willi
(Silo)
Bernd
(Bank
Contact)
Josef &
Armin
(Other
Farmers)
Markus
(Public
Authorities)
Daniel &
Anton
(Project
Owners)
Marco
(Planner)
Stefan
(Farmer &
Main
User)
Project Handbook
Biogas Powerplant Project
1. Biogas
powerplant project
1.1 PM 1.2 Project setup
1.3 Silo & weighing
machine
1.4 Block heat &
power plant
1.5 Fermentation &
waste facilities
1.6 Production
1.7 Review & sign
off
1.1.1 Project started
1.1.2 Project start
activity
1.1.3 Project
coordination
1.1.4 Project controlling
1.1.5 Project marketing
1.1.6 Project closure
1.1.7 Project end
1.2.1 Hire human
resources
1.2.2 Purchase
materials
1.2.3 Setup
done
1.3.1 Concrete walls
1.3.2 Waste water
system
1.3.3 Traffic area 1
1.3.4 Asphalt
1.3.5 Weighing
machine
1.3.7 Silo finished
1.3.6 Traffic area 2
1.4.1 Trafo
1.4.2 Heating facility
1.4.3 Facilities
finished
1.5.1 Ground
movement
1.5.2 Floor
1.5.3 Walls
1.5.4 Roof + isolation
1.5.5 Equipment
1.5.7 Facilities
finished
1.5.6 Small building
1.6.3 Production
finished
1.6.1 Heating the pots 1.7.1 Unit performance
review
1.7.2 Electricity
production review
1.7.3 Technical review
1.7.4 Documentation
1.7.5 Sign off
1.7.6 Review & sign off
done
1.6.2 Producing biogas
energy
8. Work breakdown structure (WBS)
Project Handbook
Biogas Powerplant Project
9. Project work-package specifications
Project work-package specifications
WBS 1.5.1,
ground movement
Content
 Digging holes for fermentation pots
 Lowering the whole fermentation facility 3m below surface
 Surrounding the whole area with a 2,5m high rampart
Non-content
Doing ground movement for areas other than the fermentation pots
Results
Ground are finished and ready to be constructed on
Progress measure
Work on fermentation pots can start
WBS 1.5.6,
Small building
Content
 Building small building
 Installation of pump and control electronics
Non-content
Building the fermentation pots
Results
Pumps and control electronics are installed
Progress measure
Pumps and control electronics functions properly with the
fermentation pots
WBS 1.6.1,
Heating the pots
Content
Heating up the pots to 38°C
Non-content
Collection of crops and wastes
Results
The pots are heated
Progress measure
Crops and wastes can be started to be fed to the pots
Project Handbook
Biogas Powerplant Project
10. Project responsibility matrix
project responsibility matrix
Roles
WBS-code & WP-title
(ProjectOwners)
DanielandAnton
(OverallProjectManager)Carsten
(Planner)Marco
(ProjectManagerGroundWork)Axel
(ProjectManagerSilo)Willi
(ProjectManagerFermenter+Block
PowerandHeatPlant)Sven
ProjectManagerTrafo)Hans
(ProjectManagerWeighingMachine)
Gerd
1.1 Project management
1.1.2 Project start activity I R I I I I I I
1.1.3 Project coordination R C
1.1.4 Project controlling R C
1.1.5 Project marketing R C
1.1.6 Project closure I R I I I I I I
1.2 Project setup
1.2.1 Hire human resources R C C C C C C
1.2.2 Purchase materials R C C C C C C
1.3 Silo & weighing machine
1.3.1 Concrete walls I R
1.3.2 Waste water system I R
1.3.3 Traffic area 1 I R
1.3.4 Asphalt I R
1.3.5 Weighing machine I I R
1.3.6 Traffic area 2 I R
1.4 Block heat & power plant
1.4.1 Trafo I I R
1.4.2 Heating facility I R
1.5 Fermentation & waste
facilities
1.5.1 Ground movement I R I
1.5.2 Floor I R
1.5.3 Walls I R
1.5.4 Roof + isolation I R
1.5.5 Equipment I R
1.5.6 Small building I R
Project Handbook
Biogas Powerplant Project
Informations:
R: Responsible
C: Contribution
I: Information
D: Decision
1.6 Production
1.6.1 Heating the pots I R I I I I I I
1.6.2 Producing biogas energy I R I I I I I I
1.7 Review & sign off
1.7.1 Unit performance review I R
1.7.2 Electricity production
review
I R
1.7.3 Technical review I R
1.7.4 Documentation I R
1.7.5 Signoff R I
Project Handbook
Biogas Powerplant Project
11. Milestone plan
Project milestone plan
WBS
code
Milestone Plan date Revised date Actual date
1.1.1 Project started 24.08.09
1.1.7 Project end 31.12.09
1.2.3 Setup done 31.08.09
1.3.7 Silo finished 29.09.09
1.4.3 Facilities finished 28.10.09
1.5.7 Facilities finished 01.12.09
1.6.3 Production finished 29.12.09
1.7.6 Review and sign off done 31.12.09
Project Handbook
Biogas Powerplant Project
12. Project bar chart
Project Handbook
Biogas Powerplant Project
13. Personnel planning
personnel planning
WBS code phase /
work
package
resource
type
base plan
person
days
revised
plan
person
days
actuals
person
days
deviation
person
days
1.1.2 Project Start
Activity
7
1.1.3 Project
Coordination
21
1.1.4 Project
Controlling
28
1.1.5 Project
Marketing
28
1.1.6 Project Closure 1
1.1 Project
management
85
1.2.1 Hire human
resources
5
Project Handbook
Biogas Powerplant Project
1.2.2 Purchase
materials
5
1.2 Project setup 10
1.3.1 Concrete walls 5
1.3.2 Waste water
system
5
1.3.3 Traffic area 1 5
1.3.4 Asphalt 5
1.3.5 Weighing
machine
5
1.3.6 Traffic area 2 5
1.3 Silo &
weighing
machine
30
1.4.1 Trafo 5
Project Handbook
Biogas Powerplant Project
1.4.2 Heating facility 8
1.4 Block heat &
power plant
13
1.5.1 Ground
movement
5
1.5.2 Floor 5
1.5.3 Walls 5
1.5.4 Roof + isolation 5
1.5.5 Equipment 5
1.5.6 Small building 7.5
1.5 Fermentation
& waste
facilities
32.5
1.6.1 Heating the
pots
5
Project Handbook
Biogas Powerplant Project
1.6.2 Producing
biogas energy
5
1.6 Production 10
1.7.1 Unit
performance
review
5
1.7.2 Electricity
production
review
1
1.7.3 Technical
review
5
1.7.4 Documentation 5.5
1.7.5 Signoff 1
1.7 Review & sign
off
17.5
Project Handbook
Biogas Powerplant Project
14. Project cost plan
project cost plan
WBS-code,
project
work
package
cost type base
plan
cost
revised
plan cost
€
actuals
cost
€
cost
deviation
€
Phase 1 personnel (150
EUR / man
day)
12,750
Material
external services
Other
Total PM 12,750
Phase 2 personnel (150
EUR / man
day)
1500
Material
Project Handbook
Biogas Powerplant Project
external services
Other
Total Project
setup
1,500
Phase 3 personnel (150
EUR / man
day)
4500
material 230,000
external services
other
Total Silo &
weighting
machine
234,500
Phase 4 personnel (150
EUR / man
day)
1,950
material 1,075,000
Project Handbook
Biogas Powerplant Project
external services
other
Total Block
heat & power
plant
1,076,950
Phase 5 personnel (150
EUR / man
day)
4,875
material 130,000
external services
other
Total Fermentation
& waste facilities
134,875
Phase 6 personnel (150
EUR / man
day)
1,500
material 160,000
Project Handbook
Biogas Powerplant Project
external services
other
Total
Production
161,500
Phase 7 personnel (150
EUR / man
day)
2,625
material
external services
other
Total Review &
sign off
2,625
Total cost 1,624,700

More Related Content

What's hot

What's hot (20)

Bio gas
Bio gasBio gas
Bio gas
 
Biomass briquetting
Biomass briquettingBiomass briquetting
Biomass briquetting
 
BIOGAS for Everyone : Simplified for all
BIOGAS for Everyone : Simplified for all BIOGAS for Everyone : Simplified for all
BIOGAS for Everyone : Simplified for all
 
Gasification and Gasifiers
Gasification and GasifiersGasification and Gasifiers
Gasification and Gasifiers
 
Biogas .ppt
Biogas .pptBiogas .ppt
Biogas .ppt
 
Biomass energy and biouels
Biomass energy and biouelsBiomass energy and biouels
Biomass energy and biouels
 
Report on Bio Gas Plant
Report on Bio Gas PlantReport on Bio Gas Plant
Report on Bio Gas Plant
 
Biogas
BiogasBiogas
Biogas
 
BIOGAS PRODUCTION USING SMALL SCALE BIODIGESTER
BIOGAS PRODUCTION USING SMALL SCALE BIODIGESTER BIOGAS PRODUCTION USING SMALL SCALE BIODIGESTER
BIOGAS PRODUCTION USING SMALL SCALE BIODIGESTER
 
Biogas - Presentation
Biogas - PresentationBiogas - Presentation
Biogas - Presentation
 
BIOGAS PLANT
BIOGAS PLANTBIOGAS PLANT
BIOGAS PLANT
 
Biogas - Sustainability Through Green Energy
Biogas - Sustainability Through  Green Energy Biogas - Sustainability Through  Green Energy
Biogas - Sustainability Through Green Energy
 
Bio-Gas
Bio-Gas Bio-Gas
Bio-Gas
 
Torrefaction
TorrefactionTorrefaction
Torrefaction
 
Production Process Wood Pellet From Wood Biomass
Production Process Wood Pellet From Wood BiomassProduction Process Wood Pellet From Wood Biomass
Production Process Wood Pellet From Wood Biomass
 
Biomass Pyrolysis
Biomass PyrolysisBiomass Pyrolysis
Biomass Pyrolysis
 
Biomass By Akash Kewal
Biomass By Akash KewalBiomass By Akash Kewal
Biomass By Akash Kewal
 
Biomass Energy and Scenario in India
Biomass Energy and Scenario in IndiaBiomass Energy and Scenario in India
Biomass Energy and Scenario in India
 
Pyrolysis ppt
Pyrolysis pptPyrolysis ppt
Pyrolysis ppt
 
Biogas ppt
Biogas pptBiogas ppt
Biogas ppt
 

Viewers also liked

Biogas final project proposal submitted
Biogas final project proposal  submittedBiogas final project proposal  submitted
Biogas final project proposal submittedAdane Nega
 
Biogas plant project
Biogas plant projectBiogas plant project
Biogas plant projectTulika Ghosh
 
Biogas production
Biogas productionBiogas production
Biogas productionAsad Leo
 
Business plan bio gas
Business plan bio gasBusiness plan bio gas
Business plan bio gasAwais Alii
 
Biomass energy ppt
Biomass energy pptBiomass energy ppt
Biomass energy pptSann Jana
 
In-Game Advvertising research
In-Game Advvertising researchIn-Game Advvertising research
In-Game Advvertising researchWentao Guo
 
Bio CNG FromWholesaleVegetableAndFruitMarkets:A Truly Sustanable and renewabl...
Bio CNG FromWholesaleVegetableAndFruitMarkets:A Truly Sustanable and renewabl...Bio CNG FromWholesaleVegetableAndFruitMarkets:A Truly Sustanable and renewabl...
Bio CNG FromWholesaleVegetableAndFruitMarkets:A Truly Sustanable and renewabl...Sarita Mishra
 
Biogas-energy of the future
Biogas-energy of the futureBiogas-energy of the future
Biogas-energy of the futureAbhinav Ojha
 
BIOMASS PROJECT DEVELOPMENT 140723-d2s2.indo
BIOMASS PROJECT DEVELOPMENT 140723-d2s2.indoBIOMASS PROJECT DEVELOPMENT 140723-d2s2.indo
BIOMASS PROJECT DEVELOPMENT 140723-d2s2.indoDinno Kurniawan
 

Viewers also liked (17)

Biogas final project proposal submitted
Biogas final project proposal  submittedBiogas final project proposal  submitted
Biogas final project proposal submitted
 
Biogas plant project
Biogas plant projectBiogas plant project
Biogas plant project
 
Biogas
BiogasBiogas
Biogas
 
Bio gas
Bio gasBio gas
Bio gas
 
Biogas production
Biogas productionBiogas production
Biogas production
 
Disco Road Biogas Utilization Project
Disco Road Biogas Utilization ProjectDisco Road Biogas Utilization Project
Disco Road Biogas Utilization Project
 
Biomass energy in India
Biomass energy in IndiaBiomass energy in India
Biomass energy in India
 
Biogas
BiogasBiogas
Biogas
 
Biogas in India
Biogas in IndiaBiogas in India
Biogas in India
 
Ceramic Bearing ppt
Ceramic Bearing pptCeramic Bearing ppt
Ceramic Bearing ppt
 
Business plan bio gas
Business plan bio gasBusiness plan bio gas
Business plan bio gas
 
Biomass energy ppt
Biomass energy pptBiomass energy ppt
Biomass energy ppt
 
In-Game Advvertising research
In-Game Advvertising researchIn-Game Advvertising research
In-Game Advvertising research
 
Bio CNG FromWholesaleVegetableAndFruitMarkets:A Truly Sustanable and renewabl...
Bio CNG FromWholesaleVegetableAndFruitMarkets:A Truly Sustanable and renewabl...Bio CNG FromWholesaleVegetableAndFruitMarkets:A Truly Sustanable and renewabl...
Bio CNG FromWholesaleVegetableAndFruitMarkets:A Truly Sustanable and renewabl...
 
Biogas-energy of the future
Biogas-energy of the futureBiogas-energy of the future
Biogas-energy of the future
 
BIOMASS PROJECT DEVELOPMENT 140723-d2s2.indo
BIOMASS PROJECT DEVELOPMENT 140723-d2s2.indoBIOMASS PROJECT DEVELOPMENT 140723-d2s2.indo
BIOMASS PROJECT DEVELOPMENT 140723-d2s2.indo
 
Garry Porter - Mt. Everest Biogas Project
Garry Porter - Mt. Everest Biogas ProjectGarry Porter - Mt. Everest Biogas Project
Garry Porter - Mt. Everest Biogas Project
 

Similar to Biogas project report

Co-design of an implementation concept for a deep geothermal energy project a...
Co-design of an implementation concept for a deep geothermal energy project a...Co-design of an implementation concept for a deep geothermal energy project a...
Co-design of an implementation concept for a deep geothermal energy project a...Oeko-Institut
 
20181128 1 schoof platform geothermie and geothermal masterplan
20181128 1 schoof   platform geothermie and geothermal masterplan20181128 1 schoof   platform geothermie and geothermal masterplan
20181128 1 schoof platform geothermie and geothermal masterplanAlexandros Daniilidis
 
IEF programme theme #2 Just & Affordable Clean Energy_20230214.pptx
IEF programme theme #2 Just & Affordable Clean Energy_20230214.pptxIEF programme theme #2 Just & Affordable Clean Energy_20230214.pptx
IEF programme theme #2 Just & Affordable Clean Energy_20230214.pptxTEPBLEMIGAS
 
Ignalina Nuclear Power Plant Presentation to the Assembly of Contributors
Ignalina Nuclear Power Plant Presentation to the Assembly of ContributorsIgnalina Nuclear Power Plant Presentation to the Assembly of Contributors
Ignalina Nuclear Power Plant Presentation to the Assembly of ContributorsOsvaldas Ciuksys
 
Updated (version 0.6) European Union & IEA Energy Plan (REPowerEU 2022)-Ver 0...
Updated (version 0.6) European Union & IEA Energy Plan (REPowerEU 2022)-Ver 0...Updated (version 0.6) European Union & IEA Energy Plan (REPowerEU 2022)-Ver 0...
Updated (version 0.6) European Union & IEA Energy Plan (REPowerEU 2022)-Ver 0...EmadfHABIB2
 
Applied Project Management Team Assignment Eco-House Project Management Plan
Applied Project Management Team Assignment Eco-House Project Management PlanApplied Project Management Team Assignment Eco-House Project Management Plan
Applied Project Management Team Assignment Eco-House Project Management PlanNicole Heredia
 
Rice husk based cogeneration power plant for finance, subsidy & project rel...
Rice husk based cogeneration power plant   for finance, subsidy & project rel...Rice husk based cogeneration power plant   for finance, subsidy & project rel...
Rice husk based cogeneration power plant for finance, subsidy & project rel...Radha Krishna Sahoo
 
Rice husk power plant information for finance, subsidy & project related su...
Rice husk power plant information   for finance, subsidy & project related su...Rice husk power plant information   for finance, subsidy & project related su...
Rice husk power plant information for finance, subsidy & project related su...Radha Krishna Sahoo
 
Final Project: Odense Residential Building Renovation
Final Project: Odense Residential Building RenovationFinal Project: Odense Residential Building Renovation
Final Project: Odense Residential Building RenovationMonica Badia Marin
 
Ignalina NPP Presentation To A o C (June 2011)
Ignalina NPP Presentation To A o C (June 2011)Ignalina NPP Presentation To A o C (June 2011)
Ignalina NPP Presentation To A o C (June 2011)Osvaldas Ciuksys
 
Austrijas pieredze ESKO projektu īstenošanā valsts īpašumā esošās ēkās
Austrijas pieredze ESKO projektu īstenošanā valsts īpašumā esošās ēkāsAustrijas pieredze ESKO projektu īstenošanā valsts īpašumā esošās ēkās
Austrijas pieredze ESKO projektu īstenošanā valsts īpašumā esošās ēkāsEkonomikas ministrija/ Dzīvo siltāk
 
Horizon 2020 Green Deal: Information and Consortia Building Event Series, 9 O...
Horizon 2020 Green Deal: Information and Consortia Building Event Series, 9 O...Horizon 2020 Green Deal: Information and Consortia Building Event Series, 9 O...
Horizon 2020 Green Deal: Information and Consortia Building Event Series, 9 O...KTN
 
Steve- Fall 2015 Research Poster revision4
Steve- Fall 2015 Research Poster revision4Steve- Fall 2015 Research Poster revision4
Steve- Fall 2015 Research Poster revision4Jeehwan Steve Lee
 

Similar to Biogas project report (20)

Co-design of an implementation concept for a deep geothermal energy project a...
Co-design of an implementation concept for a deep geothermal energy project a...Co-design of an implementation concept for a deep geothermal energy project a...
Co-design of an implementation concept for a deep geothermal energy project a...
 
20181128 1 schoof platform geothermie and geothermal masterplan
20181128 1 schoof   platform geothermie and geothermal masterplan20181128 1 schoof   platform geothermie and geothermal masterplan
20181128 1 schoof platform geothermie and geothermal masterplan
 
IEF programme theme #2 Just & Affordable Clean Energy_20230214.pptx
IEF programme theme #2 Just & Affordable Clean Energy_20230214.pptxIEF programme theme #2 Just & Affordable Clean Energy_20230214.pptx
IEF programme theme #2 Just & Affordable Clean Energy_20230214.pptx
 
PDD for GTCC
PDD for GTCCPDD for GTCC
PDD for GTCC
 
Germany’s experience with renovation financing | Knut Höller
Germany’s experience with renovation financing | Knut HöllerGermany’s experience with renovation financing | Knut Höller
Germany’s experience with renovation financing | Knut Höller
 
Topic 1.ppt
Topic 1.pptTopic 1.ppt
Topic 1.ppt
 
Proposal snowflake ski basin case
Proposal snowflake ski basin caseProposal snowflake ski basin case
Proposal snowflake ski basin case
 
Ignalina Nuclear Power Plant Presentation to the Assembly of Contributors
Ignalina Nuclear Power Plant Presentation to the Assembly of ContributorsIgnalina Nuclear Power Plant Presentation to the Assembly of Contributors
Ignalina Nuclear Power Plant Presentation to the Assembly of Contributors
 
Updated (version 0.6) European Union & IEA Energy Plan (REPowerEU 2022)-Ver 0...
Updated (version 0.6) European Union & IEA Energy Plan (REPowerEU 2022)-Ver 0...Updated (version 0.6) European Union & IEA Energy Plan (REPowerEU 2022)-Ver 0...
Updated (version 0.6) European Union & IEA Energy Plan (REPowerEU 2022)-Ver 0...
 
Hydrogen Gas Turbine
Hydrogen Gas TurbineHydrogen Gas Turbine
Hydrogen Gas Turbine
 
Applied Project Management Team Assignment Eco-House Project Management Plan
Applied Project Management Team Assignment Eco-House Project Management PlanApplied Project Management Team Assignment Eco-House Project Management Plan
Applied Project Management Team Assignment Eco-House Project Management Plan
 
Rice husk based cogeneration power plant for finance, subsidy & project rel...
Rice husk based cogeneration power plant   for finance, subsidy & project rel...Rice husk based cogeneration power plant   for finance, subsidy & project rel...
Rice husk based cogeneration power plant for finance, subsidy & project rel...
 
Rice husk power plant information for finance, subsidy & project related su...
Rice husk power plant information   for finance, subsidy & project related su...Rice husk power plant information   for finance, subsidy & project related su...
Rice husk power plant information for finance, subsidy & project related su...
 
Final Project: Odense Residential Building Renovation
Final Project: Odense Residential Building RenovationFinal Project: Odense Residential Building Renovation
Final Project: Odense Residential Building Renovation
 
Ignalina NPP Presentation To A o C (June 2011)
Ignalina NPP Presentation To A o C (June 2011)Ignalina NPP Presentation To A o C (June 2011)
Ignalina NPP Presentation To A o C (June 2011)
 
Austrijas pieredze ESKO projektu īstenošanā valsts īpašumā esošās ēkās
Austrijas pieredze ESKO projektu īstenošanā valsts īpašumā esošās ēkāsAustrijas pieredze ESKO projektu īstenošanā valsts īpašumā esošās ēkās
Austrijas pieredze ESKO projektu īstenošanā valsts īpašumā esošās ēkās
 
Waste to energy plant
Waste to energy plantWaste to energy plant
Waste to energy plant
 
Horizon 2020 Green Deal: Information and Consortia Building Event Series, 9 O...
Horizon 2020 Green Deal: Information and Consortia Building Event Series, 9 O...Horizon 2020 Green Deal: Information and Consortia Building Event Series, 9 O...
Horizon 2020 Green Deal: Information and Consortia Building Event Series, 9 O...
 
Steve- Fall 2015 Research Poster revision4
Steve- Fall 2015 Research Poster revision4Steve- Fall 2015 Research Poster revision4
Steve- Fall 2015 Research Poster revision4
 
Eef first movers_eng_web_revised
Eef first movers_eng_web_revisedEef first movers_eng_web_revised
Eef first movers_eng_web_revised
 

More from Ujjwal Joshi

Client Service Executive - Junior Event Manager
Client Service Executive - Junior Event ManagerClient Service Executive - Junior Event Manager
Client Service Executive - Junior Event ManagerUjjwal Joshi
 
Understanding france- Brief overview of Marseille
Understanding france- Brief overview of MarseilleUnderstanding france- Brief overview of Marseille
Understanding france- Brief overview of MarseilleUjjwal Joshi
 
Npv and IRR, a link to Project Management
Npv and IRR, a link to Project ManagementNpv and IRR, a link to Project Management
Npv and IRR, a link to Project ManagementUjjwal Joshi
 
Melamchi Drinking Water Project
Melamchi Drinking Water ProjectMelamchi Drinking Water Project
Melamchi Drinking Water ProjectUjjwal Joshi
 
Namibia- Project Hope
Namibia- Project HopeNamibia- Project Hope
Namibia- Project HopeUjjwal Joshi
 
Implementation of SAP BI in Coca Cola
Implementation of SAP BI in Coca ColaImplementation of SAP BI in Coca Cola
Implementation of SAP BI in Coca ColaUjjwal Joshi
 
Micro patterns in agile software
Micro patterns in agile softwareMicro patterns in agile software
Micro patterns in agile softwareUjjwal Joshi
 
Project Types and their importance
Project Types and their importanceProject Types and their importance
Project Types and their importanceUjjwal Joshi
 
ICB Competence, Project Standards
ICB Competence, Project StandardsICB Competence, Project Standards
ICB Competence, Project StandardsUjjwal Joshi
 
PMBOK Risk Management and Safety Health and Environment
PMBOK Risk Management and Safety Health and EnvironmentPMBOK Risk Management and Safety Health and Environment
PMBOK Risk Management and Safety Health and EnvironmentUjjwal Joshi
 
Report on Kotter's Change Model
Report on Kotter's Change ModelReport on Kotter's Change Model
Report on Kotter's Change ModelUjjwal Joshi
 
Chad cameroon pipeline project
Chad cameroon pipeline projectChad cameroon pipeline project
Chad cameroon pipeline projectUjjwal Joshi
 
Kotter’s 8 step change model
Kotter’s 8 step change modelKotter’s 8 step change model
Kotter’s 8 step change modelUjjwal Joshi
 
Knowledge Management- Ernst & Young
Knowledge Management- Ernst & YoungKnowledge Management- Ernst & Young
Knowledge Management- Ernst & YoungUjjwal Joshi
 
Code of conduct_2011
Code of conduct_2011Code of conduct_2011
Code of conduct_2011Ujjwal Joshi
 
Niccolo machiavelli
Niccolo machiavelliNiccolo machiavelli
Niccolo machiavelliUjjwal Joshi
 
Knowledge Management in NASA
Knowledge Management in NASAKnowledge Management in NASA
Knowledge Management in NASAUjjwal Joshi
 

More from Ujjwal Joshi (20)

Client Service Executive - Junior Event Manager
Client Service Executive - Junior Event ManagerClient Service Executive - Junior Event Manager
Client Service Executive - Junior Event Manager
 
Understanding france- Brief overview of Marseille
Understanding france- Brief overview of MarseilleUnderstanding france- Brief overview of Marseille
Understanding france- Brief overview of Marseille
 
Npv and IRR, a link to Project Management
Npv and IRR, a link to Project ManagementNpv and IRR, a link to Project Management
Npv and IRR, a link to Project Management
 
Melamchi Drinking Water Project
Melamchi Drinking Water ProjectMelamchi Drinking Water Project
Melamchi Drinking Water Project
 
Namibia- Project Hope
Namibia- Project HopeNamibia- Project Hope
Namibia- Project Hope
 
Supply chain
Supply chainSupply chain
Supply chain
 
Implementation of SAP BI in Coca Cola
Implementation of SAP BI in Coca ColaImplementation of SAP BI in Coca Cola
Implementation of SAP BI in Coca Cola
 
Micro patterns in agile software
Micro patterns in agile softwareMicro patterns in agile software
Micro patterns in agile software
 
KANBAN
KANBANKANBAN
KANBAN
 
Project Types and their importance
Project Types and their importanceProject Types and their importance
Project Types and their importance
 
ICB Competence, Project Standards
ICB Competence, Project StandardsICB Competence, Project Standards
ICB Competence, Project Standards
 
PMBOK Risk Management and Safety Health and Environment
PMBOK Risk Management and Safety Health and EnvironmentPMBOK Risk Management and Safety Health and Environment
PMBOK Risk Management and Safety Health and Environment
 
Report on Kotter's Change Model
Report on Kotter's Change ModelReport on Kotter's Change Model
Report on Kotter's Change Model
 
Chad cameroon pipeline project
Chad cameroon pipeline projectChad cameroon pipeline project
Chad cameroon pipeline project
 
Kotter’s 8 step change model
Kotter’s 8 step change modelKotter’s 8 step change model
Kotter’s 8 step change model
 
Knowledge Management- Ernst & Young
Knowledge Management- Ernst & YoungKnowledge Management- Ernst & Young
Knowledge Management- Ernst & Young
 
Communication 1
Communication 1Communication 1
Communication 1
 
Code of conduct_2011
Code of conduct_2011Code of conduct_2011
Code of conduct_2011
 
Niccolo machiavelli
Niccolo machiavelliNiccolo machiavelli
Niccolo machiavelli
 
Knowledge Management in NASA
Knowledge Management in NASAKnowledge Management in NASA
Knowledge Management in NASA
 

Recently uploaded

“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...RKavithamani
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfchloefrazer622
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 

Recently uploaded (20)

“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
Privatization and Disinvestment - Meaning, Objectives, Advantages and Disadva...
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
Mattingly "AI & Prompt Design: Structured Data, Assistants, & RAG"
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Arihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdfArihant handbook biology for class 11 .pdf
Arihant handbook biology for class 11 .pdf
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 

Biogas project report

  • 1. Project Handbook Biogas Powerplant Project Project Handbook Biogas Powerplant Project Version 1.0 Project Manager: Carsten Group Members: Ujjwal Kumar Joshi
  • 2. Project Handbook Biogas Powerplant Project Contents 1. Short description of project 2. Project assignment 3. Plan of objectives 4. Description of pre- and post-project phase 5. Project environment analysis 6. Connection between the project, other projects and the organization’s strategy 7. Project organization chart 8. Work breakdown structure (WBS) 9. Project work-package specifications 10. Project responsibility matrix 11. Milestone plan 12. Project bar chart 13. Personnel planning 14. Project cost plan
  • 3. Project Handbook Biogas Powerplant Project 1. Short description of project The production of biogas and the conversion into electricity is subsidized in Germany via the EEG law. This allowed the construction of biogas power plants with up to 500 kW electrical powers as agricultural facilities in the farms. The biogas power plant project is planned to be implemented within a farm in the Westphalian countryside. This farm produces piglets (young pigs) which are produced by hosting around 400 sows (mother pigs). The pigs produced also 2000 cbm of waste, in which it must be stored to be used as fuel for producing heating and electricity. The biogas power plant will use the liquid waste to produce methane gas for heating of the farm. The power plant also need apart from biogas, energy from crops like corn or grass. Electricity will also be produced from the power plant, which will be sold to local energy provider for fixed price and have a guaranteed price by law for the next 20 years. The project is intended to produce electricity in 2009. The prerequisite for the permit to build the power plant is that there must be an agreed contract with local farmers to purchase energy crops over 5 years. After the prerequisite is fulfilled, the power plant construction can be started, in which it consisted of 3 main building blocks which is crop silo, block power and heat plant, fermentation and waste facilities. Biogas will be produced 3-4 weeks after starting to feed the fermentation pots. The project is planned to be finished at the end 2009 so that the goal to produce electricity can be achieved.
  • 4. Project Handbook Biogas Powerplant Project 2. Project Assignment Project Assignment project start event: Contracts with local farmers are secured project start date: 24-08-2009 project end event: Production of biogas energy project end date: 31-12-2009 project objectives:  Process waste and crops to produce electricity and heating (biogas energy)  Constructing silo & weighing machine  Constructing block heat & power plant  Constructing fermentation & waste facilities non-objectives:  Securing contract with local farmers  Selling of electricity main tasks (project phases):  Project management  Project setup  Silo & weighing machine  Block heat & power plant  Fermentation & waste facilities  Production (one time test production)  Review & sign off project resources and costs: Resource/cost type unit cost (euro)  Silo  Weighing Machine  Trafo  Block heat and power plant  Auxiliary heating facility  Fermentation facilities  Ground movement + traffic areas  Small building  Crops harvest  Materials, bio diesel, oil TOTAL 200,000 30,000 50,000 200,000 25,000 800,000 100,000 30,000 150,000 10,000 1,595,000 project owner: Daniel and Anton project manager: Carsten project team:  Marco (Planner)  Axel (Project Manager Ground Work)  Willi (Project Manager Silo)  Sven (Project Manager Fermenter + Block Power and Heat Plant)  Hans (Project Manager Trafo)  Gerd (Project Manager Weighing Machine) project coach: ……………………………………………………… ………………………………………………………….. Carsten (project manager) Daniel and Anton (project owners)
  • 5. Project Handbook Biogas Powerplant Project 3. Plan of objectives Plan of goals (objectives, non-objectives) Current Objectives Adjusted Objectives as of (date) Main objectives Additional objectives  Process waste and crops to produce electricity and heating (biogas energy)  Constructing silo & weighing machine  Constructing block heat & power plant  Constructing fermentation & waste facilities Non objectives  Securing contract with local farmers  Selling of electricity
  • 6. Project Handbook Biogas Powerplant Project 4. Description of pre- and post-project phase description of pre- and post project phase 1) pre project phase What triggered the project?  EEG law forced the states in Germany to construct Bio gas power plants as agricultural facilities in farms  The need to use the liquid waste for better use  To generate the cheaper electricity Relevant decisions, events  Decision to do the project in a farm in the westphalian countryside Relevant documents  Contract with local farmers (prerequisite for starting the project)  Project planning documentations 2) post project phase What will happen after the project has ended?  Control the flow of resources needed to produce the biogas  Secure more contracts with local farmers Use of experiences  The team will focus long term on Biogas projects  The team can apply their experiences in other states and countries  The resulting action plan from the lessons learned review will be executed Relevant documents  Project manual  Review documentations
  • 7. Project Handbook Biogas Powerplant Project 5. Project environment analysis Project environment analysis Project environment table Environment Relationship Evaluation Activity Responsible Date Project Owners (Daniel & Anton) Customer (Positive) Expect and desire project success Project start & closure (WBS 1.1.2 WBS 1.1.6) Biogas production (WBS 1.6) Reviews (WBS 1.7) PM (Carsten) 24.08.09- 01.09.09 30.12.09 17.11.09- 29.12.09 01.12.09- 29.12.09 Projects managers (Axel, Willi, Sven, Hans, Gerd) Executes the project phases (Positive) Motivated to achieve their success with responsibility and accountability Execution of the project (WBS 1.2-1.7) PM (Carsten) Projects managers (Axel, Willi, Sven, Hans, Gerd) 24.08.09- 29.12.09 Biogas powerplant project Overall project manager (Carsten) Project owners (Daniel & Anton) Project managers Planner (Marco) Farmer & main user (Stefan) Bank contact (Bernd) Other farmers (Josef & Armin) Public authorities (Markus) + : Positive influence - : Negative influence + + + + + - - + External Internal
  • 8. Project Handbook Biogas Powerplant Project Farmer & main user (Stefan) Farm owner (Positive) Gain access to renewable energy to reduce costs Biogas production (WBS 1.6.2) Review (WBS 1.7) PM (Carsten) 08.12.09- 28.12.09 01.12.09- 31.12.09 Public authorities (Markus) Grant permits (Negative) Make sure the requirements to start the project are met Project management (WBS 1.1) PM (Carsten) 24.08.09- 31.12.09 Other farmers (Josef & Armin) Supply crops for making biogas (Positive) Gain access to renewable energy Biogas production (WBS 1.6.2) PM (Carsten) 08.12.09- 28.12.09 Bank contact (Bernd) Help finance the project (Negative) Discussion of possibility for project funding Project management (WBS 1.1) PM (Carsten) 24.08.09- 31.12.09 Planner (Marco) Develop plan for the project (Positive) Develop strategic plan to support the overall execution of the project Project management (WBS 1.1) PM (Carsten) 24.08.09- 31.12.09
  • 9. Project Handbook Biogas Powerplant Project 6. Connection between project, other projects and the organization’s strategy connection between the project and other projects Project Relationship Evaluation Activity Responsible Date connection between the project and organization’s strategy Strategy of the organization Description of the relationship Improve the usage of renewable energy in Germany Reduce the usage of fossil fuel and CO2 level in Germany Address the farmers in Westphalia countryside Give them the possibility to process the waste to another form of process and gain some income from it
  • 10. Project Handbook Biogas Powerplant Project (project support) Project Organization 7. Project organization chart Project Managers (project execution) Carsten (Project Manager) Axel (Ground Work) Gerd (Weighing Machine) Hans (Trafo) Sven (Fermenter + Block Power + Heat Plant) Willi (Silo) Bernd (Bank Contact) Josef & Armin (Other Farmers) Markus (Public Authorities) Daniel & Anton (Project Owners) Marco (Planner) Stefan (Farmer & Main User)
  • 11. Project Handbook Biogas Powerplant Project 1. Biogas powerplant project 1.1 PM 1.2 Project setup 1.3 Silo & weighing machine 1.4 Block heat & power plant 1.5 Fermentation & waste facilities 1.6 Production 1.7 Review & sign off 1.1.1 Project started 1.1.2 Project start activity 1.1.3 Project coordination 1.1.4 Project controlling 1.1.5 Project marketing 1.1.6 Project closure 1.1.7 Project end 1.2.1 Hire human resources 1.2.2 Purchase materials 1.2.3 Setup done 1.3.1 Concrete walls 1.3.2 Waste water system 1.3.3 Traffic area 1 1.3.4 Asphalt 1.3.5 Weighing machine 1.3.7 Silo finished 1.3.6 Traffic area 2 1.4.1 Trafo 1.4.2 Heating facility 1.4.3 Facilities finished 1.5.1 Ground movement 1.5.2 Floor 1.5.3 Walls 1.5.4 Roof + isolation 1.5.5 Equipment 1.5.7 Facilities finished 1.5.6 Small building 1.6.3 Production finished 1.6.1 Heating the pots 1.7.1 Unit performance review 1.7.2 Electricity production review 1.7.3 Technical review 1.7.4 Documentation 1.7.5 Sign off 1.7.6 Review & sign off done 1.6.2 Producing biogas energy 8. Work breakdown structure (WBS)
  • 12. Project Handbook Biogas Powerplant Project 9. Project work-package specifications Project work-package specifications WBS 1.5.1, ground movement Content  Digging holes for fermentation pots  Lowering the whole fermentation facility 3m below surface  Surrounding the whole area with a 2,5m high rampart Non-content Doing ground movement for areas other than the fermentation pots Results Ground are finished and ready to be constructed on Progress measure Work on fermentation pots can start WBS 1.5.6, Small building Content  Building small building  Installation of pump and control electronics Non-content Building the fermentation pots Results Pumps and control electronics are installed Progress measure Pumps and control electronics functions properly with the fermentation pots WBS 1.6.1, Heating the pots Content Heating up the pots to 38°C Non-content Collection of crops and wastes Results The pots are heated Progress measure Crops and wastes can be started to be fed to the pots
  • 13. Project Handbook Biogas Powerplant Project 10. Project responsibility matrix project responsibility matrix Roles WBS-code & WP-title (ProjectOwners) DanielandAnton (OverallProjectManager)Carsten (Planner)Marco (ProjectManagerGroundWork)Axel (ProjectManagerSilo)Willi (ProjectManagerFermenter+Block PowerandHeatPlant)Sven ProjectManagerTrafo)Hans (ProjectManagerWeighingMachine) Gerd 1.1 Project management 1.1.2 Project start activity I R I I I I I I 1.1.3 Project coordination R C 1.1.4 Project controlling R C 1.1.5 Project marketing R C 1.1.6 Project closure I R I I I I I I 1.2 Project setup 1.2.1 Hire human resources R C C C C C C 1.2.2 Purchase materials R C C C C C C 1.3 Silo & weighing machine 1.3.1 Concrete walls I R 1.3.2 Waste water system I R 1.3.3 Traffic area 1 I R 1.3.4 Asphalt I R 1.3.5 Weighing machine I I R 1.3.6 Traffic area 2 I R 1.4 Block heat & power plant 1.4.1 Trafo I I R 1.4.2 Heating facility I R 1.5 Fermentation & waste facilities 1.5.1 Ground movement I R I 1.5.2 Floor I R 1.5.3 Walls I R 1.5.4 Roof + isolation I R 1.5.5 Equipment I R 1.5.6 Small building I R
  • 14. Project Handbook Biogas Powerplant Project Informations: R: Responsible C: Contribution I: Information D: Decision 1.6 Production 1.6.1 Heating the pots I R I I I I I I 1.6.2 Producing biogas energy I R I I I I I I 1.7 Review & sign off 1.7.1 Unit performance review I R 1.7.2 Electricity production review I R 1.7.3 Technical review I R 1.7.4 Documentation I R 1.7.5 Signoff R I
  • 15. Project Handbook Biogas Powerplant Project 11. Milestone plan Project milestone plan WBS code Milestone Plan date Revised date Actual date 1.1.1 Project started 24.08.09 1.1.7 Project end 31.12.09 1.2.3 Setup done 31.08.09 1.3.7 Silo finished 29.09.09 1.4.3 Facilities finished 28.10.09 1.5.7 Facilities finished 01.12.09 1.6.3 Production finished 29.12.09 1.7.6 Review and sign off done 31.12.09
  • 16. Project Handbook Biogas Powerplant Project 12. Project bar chart
  • 17. Project Handbook Biogas Powerplant Project 13. Personnel planning personnel planning WBS code phase / work package resource type base plan person days revised plan person days actuals person days deviation person days 1.1.2 Project Start Activity 7 1.1.3 Project Coordination 21 1.1.4 Project Controlling 28 1.1.5 Project Marketing 28 1.1.6 Project Closure 1 1.1 Project management 85 1.2.1 Hire human resources 5
  • 18. Project Handbook Biogas Powerplant Project 1.2.2 Purchase materials 5 1.2 Project setup 10 1.3.1 Concrete walls 5 1.3.2 Waste water system 5 1.3.3 Traffic area 1 5 1.3.4 Asphalt 5 1.3.5 Weighing machine 5 1.3.6 Traffic area 2 5 1.3 Silo & weighing machine 30 1.4.1 Trafo 5
  • 19. Project Handbook Biogas Powerplant Project 1.4.2 Heating facility 8 1.4 Block heat & power plant 13 1.5.1 Ground movement 5 1.5.2 Floor 5 1.5.3 Walls 5 1.5.4 Roof + isolation 5 1.5.5 Equipment 5 1.5.6 Small building 7.5 1.5 Fermentation & waste facilities 32.5 1.6.1 Heating the pots 5
  • 20. Project Handbook Biogas Powerplant Project 1.6.2 Producing biogas energy 5 1.6 Production 10 1.7.1 Unit performance review 5 1.7.2 Electricity production review 1 1.7.3 Technical review 5 1.7.4 Documentation 5.5 1.7.5 Signoff 1 1.7 Review & sign off 17.5
  • 21. Project Handbook Biogas Powerplant Project 14. Project cost plan project cost plan WBS-code, project work package cost type base plan cost revised plan cost € actuals cost € cost deviation € Phase 1 personnel (150 EUR / man day) 12,750 Material external services Other Total PM 12,750 Phase 2 personnel (150 EUR / man day) 1500 Material
  • 22. Project Handbook Biogas Powerplant Project external services Other Total Project setup 1,500 Phase 3 personnel (150 EUR / man day) 4500 material 230,000 external services other Total Silo & weighting machine 234,500 Phase 4 personnel (150 EUR / man day) 1,950 material 1,075,000
  • 23. Project Handbook Biogas Powerplant Project external services other Total Block heat & power plant 1,076,950 Phase 5 personnel (150 EUR / man day) 4,875 material 130,000 external services other Total Fermentation & waste facilities 134,875 Phase 6 personnel (150 EUR / man day) 1,500 material 160,000
  • 24. Project Handbook Biogas Powerplant Project external services other Total Production 161,500 Phase 7 personnel (150 EUR / man day) 2,625 material external services other Total Review & sign off 2,625 Total cost 1,624,700