SlideShare a Scribd company logo
1 of 12
Download to read offline
1
Lean Thinking
Subtitle
Lean Thinking
Subtitle
Lean Thinking
Subtitle
Lean Thinking
Subtitle
Lean Thinking
Subtitle
Lean Thinking
Subtitle
Lean Thinking
Subtitle
Lean Thinking
Subtitle
Lean Thinking
Subtitle
“Hidden Waste in Your Processes” (Part 1) +
“Successfully Implementing Operational Enhancements” (Part 2)
Chris Piccin
25
Day Two
26
Day Two Topics
Continuous Flow
Theory of Constraints
Cost of Poor Quality
Continuous Improvement / Six Sigma
By the end of this session you will:
•  know how to identify and relieve production
constraints
•  understand the cost of poor quality and the DMAIC
improvement framework
•  have learned facilitation and problem solving skills
27
3. Continuous Flow
move as fast as value can be
added, no waiting.
Little’s Law
Theory of Constraints
Set-up Time Reduction
Takt Time
Kanban
Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 27
28
Measuring the Flow of Processes
with Little’s Law
Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 28
Work in Progress
Output
Work in Progress / Output = Cycle-time
120 gallons / 60 gallons per minute = 2 minutes
29
Continuous Flow
The Theory of Constraints
Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 29
CB BA
•  Constraints produce the fewest outputs per unit of time.
Often they will have a stack of work in front of them
•  Constraints govern the output for the whole process – an
hour lost at the bottleneck is lost for the whole process.
•  Efficiency gains at any other location don’t improve
productivity of the process.
Managing the Constraint
1.  Identify it
2.  Exploit it
3.  Subordinate everything else
4.  Increase output of constraint
5.  Rinse and repeat
30
Set-up Time
Reduction
https://vimeo.com/98796938
31
Set-up Time Reduction
(Single Minute Exchange of Die)
Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 31
1 Separate
Elements
Identify tasks that can be performed
during production and make them
“external” to the change over
2 Parallel
Work
Identify tasks performed
sequentially and, where possible,
complete them simultaneously
3 Convert
Elements
Review remaining internal elements
and ask what it would take to make
them external. Convert as many as
possible
4 Streamline Review all elements for
simplification to shorten both
external and change over time.
32
33
Production Systems
Takt Time Example: Willow Run
Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 33
68
Flow, Takt Time and Cellular Design
1940 – A bomber per hour at Willow Run
34,500 Employees
488,000 Discrete parts
33,000 Components
24 Assemblies
1 B-24 per hour
34
Production Systems
Kanban Overview
Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 34Source: http://logisticsglobal.blogspot.com/2011/10/kanban-system-parts-procurement-toyota.html
35
Production Systems
Kanban Board Example: Hiring Process
Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 35
1.  Define Value Stream
2.  Set Work in Process Limit
3.  Establish the Backlog
4.  Start Pulling Work
Application
Received Phone Screen
Manager
Interview
Interview
Complete Decision
G. Martin
Declined
M. Taylor
Offer
B. Miller
W. Jones
F. Brown
C. Williams
A Johnson
C. Smith
M. Jackson
3
M. Garcia
2 Rodriguez
AndersonJ. Davis
1
A. Thomas
Declined
Hernandez
Declined
T. Moore
Declined
D. Jones
No Go
R. Martinez
Offer
A. Richards
Start 15th
G. Wilson
4
36
Simulation Round 3:
Continuous Flow
•  Owner is responsible for final decisions
•  Changes must be reversible
•  No changes that involve customers
•  No elimination of staff
•  Facilitator has final approval
•  Implement changes and train if necessary
Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 36
Objective: identify and relieve constraints in the process.
37
4. Perfection
produce exactly what the
customer wants…
•  Cost of Poor Quality
•  The Case for Continuous
Improvement
•  Simple Six Sigma
37Copyright © Vox Datum LLC (2016-2017). All Rights Reserved.
38
The Cost of Poor Quality
Estimated Costs for American Companies
Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 38
Non-conformance
“The cost of getting it wrong”
Conformance
“The cost of getting it right”
Internal Failures (20% to 40%) Controls (10% to 50%)
•  Scrap materials
•  Rework – doing work twice
•  Lost production time
•  Inspecting for errors, defects
•  Delays waiting for approval
External Failures (20% to 40%) Prevention (0% to 5%)
•  Fines, Penalties
•  Warranties, Concessions
•  Lost revenue
•  Measurement and tracking
•  Root cause analysis
•  Mitigation
Source: The Quality Engineer Primer by Bill Wortman, 1997
39
40
The Limits of Inspection Controls
(and The Case for Continuous Improvement)
Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 40
“Finished files are the result of years
of scientific study combined with the
functional experience offered by
many Financial Services experts.”
41
Another Different Approach to Cost of Quality:
Continuous Improvement
Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 41
Total Costs
Control / Inspection Costs
Non-conformance Costs
Quality
Cost
Prevention Costs
(Continuous Improvement)
42
Conventional wisdom: “This is good enough.”
Six Sigma:
What is it? When is it useful?
Sigma Defects per Million % Good
6 3 99.99966%
5 233 99.977 %
4 6,210 99.4 %
3 66,807 93.3 %
2 308,537 69.2 %
Condition: 99% Good (4 sigma) 99.99966% Good (6 sigma)
High Risk 4 plane crashes per day 1 accident every 5 years
High Volume 2,800 lost packages per hour Less than 2 lost items per day
High Complexity 4,000 surgical mistakes per year Less than 2 mistakes per year
Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 42
Three conditions when “good enough” isn’t:
43
Continuous Improvement:
Will Six Sigma work for us?
Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 43
“Too Complicated”
“Bureaucratic”
“It’s a Black Box”
44
Continuous Improvement:
Six Sigma works for Dabbawallas
Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 44
“There is a service called FedEx that is
similar to ours but they don’t deliver hot
lunches.”
Dhondu Kondaji Chowdhury
45
Continuous Improvement:
How Dabba Deliveries Work
Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 45
10C
VP
M
Collection Codes
VP Residential Location
(Vile Parle)
C Residential Railway Station
(Cooper Hospital)
Red Dabbawalla teams color
Destination Codes
10 Destination Railway Station
(Nariman Point)
9 Dabbawalla team number
M Building Identification
(Mittal Tower)
12 Floor number
“The unavoidable price of reliability is simplicity.”
C. Hoare
46
Six Sigma
DMAIC Improvement Methodology
Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 46
Process Optimization
(People Driven)
Process Characterization
(Fact Driven)
MEASURE
Record performance in a
measurement system
CONTROL
Ensure sustainability
IMPROVE
Agree and make required
changes
ANALYZE
Find the critical few
factors
DEFINE
Document issue, allocate
resources
47
Define:
Tips for Starting an Improvement Project
Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 47
Define the objective •  Articulate the compelling need for change
•  Define goals tied to business objectives
•  Get buy-in from the critical stakeholders
Build the right team •  Ensure stakeholder representation
•  Keep the team small and co-located where possible
•  Hold frequent, timely, informal communications
Freeze the target •  Set specific, measurable success metric(s)
•  Set stretch targets. When in doubt, 50% improvement
•  Make the metrics visible for all and the target hard to change
Invent offline •  Make the most of existing or proven technology
•  Use technical innovation only when it’s fully tested
Be time driven •  80% of target is a win, celebrate success and move on
•  Iterate often, plan multi-generation releases
•  Use parallel work streams where possible
48
Measure:
Record Performance with Run Charts
Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 48
49
Analyze:
Find Critical Few Factors with Pareto Charts
Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 49
50
Analyze:
Using the Five Whys to Find Root Cause
Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 50
Where the Failure Occurred - Process Gaps
1.  Understand what the customer expects
2.  Design the process to meet customer
expectations.
3.  Follow the process as designed
4.  All communications are consistent with
how the process operates
Why? A solid rocket booster exploded.
Why? Hot gasses escaped from the rocket booster.
Why? O-ring seals failed in at least one of the
booster’s joints.
Why? The shuttle launched when the air temperature
was below design specifications for the O-rings
Why? “…NASA’s structure permitted internal flight
safety problems to bypass key shuttle
managers.”
Rogers Commission Report
On January 28, 1986 the Space Shuttle Challenger disintegrated over the Atlantic Ocean 73
seconds into its flight, leading to the deaths of its seven crew members. What went wrong?
51
Improve:
Better Quality with Error Proofing
Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 51
Risk Priority Number = Severity * Occurrence * Detection
Shut down Lock out Warning
Severity Occurrence Detection
5 Harm a customer or employee
Trigger legal or regulatory action
5 Very High (greater than 10%) 5 No controls
4 Cause significant reputational or
financial risk
4 High (1% to 10%) 4 Low
QC/QA sampling
3 Result in a customer complaint 3 Moderate (1/10,000 to 1%) 3 Moderate
100% manual inspection
2 Minor effect on performance 2 Low (1/10,000 to 1/Million) 2 High
Statistical Process Control
1 Unnoticed by customer
Internal waste or rework
1 Very Low (less than 1/Million) 1 Very High
100% auto inspection
52
Control:
Standard Work for Consistency
Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 52
Elements of Standard Work
1.  Inventory – material types and
quantities required to keep the process
operating smoothly
2.  Work Sequence – order of tasks an
operator must perform within takt time
3.  Takt Time - the rate at which
components must be made to meet
customer demand
Prep. Time 15 min.
53
Control:
Monitoring Key Metric(s) Over Time
Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 53
Trend – Six consecutive data points in
either direction
Shift – Eight consecutive points on
one side of the median
54
Process Optimization
Facilitation for Results
Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 54
The problem is often about the process…
“85% of the reasons for failure to meet customer expectations
are related to deficiencies in systems and process…change
the process rather than badgering individuals to do better.”
Dr. W. Edwards Deming
…solutions are ALWAYS about people
Results = Solution * Acceptance
55
Facilitation for
Results
55Copyright © Vox Datum LLC (2016-2017). All Rights Reserved.
56
Facilitation for Results
Open: Idea Generation
Brain Writing
•  One idea per Post-it note
•  In order, each person
reads an idea and puts it
on a wall
•  Team uses what the hear
to modify or generate new
ideas
•  Keep going until ideas dry
up.
Assumption Busting
•  Identify rules or behaviors
that lead to the current
state
•  Surface assumptions
underlying rules or
behaviors (ask why 5x)
•  Challenge assumptions –
existing exceptions?
Premortem
•  Ask, “How can we ensure
the problem happens ALL
the time?”
•  Run like Brain Writing
Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 56
57
Facilitation for Results
Narrow: Affinity Grouping Adds Clarity
Group
A
Others
Group
B
Group
C
Group
D
•  Go through the ideas to see where they can be
meaningfully grouped
•  Move the ideas that belong in the same group
together
•  Look for duplicate ideas. Get permission from each
idea author to consolidate duplicates so that they
overlap
•  Work with the group to define a title post-it that
succinctly describes each group
•  Place all single ideas under the title “Others”
Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 57

More Related Content

What's hot

Value Stream Mapping: Beyond the Mechanics - Part 3 (Executing the Transforma...
Value Stream Mapping: Beyond the Mechanics - Part 3 (Executing the Transforma...Value Stream Mapping: Beyond the Mechanics - Part 3 (Executing the Transforma...
Value Stream Mapping: Beyond the Mechanics - Part 3 (Executing the Transforma...TKMG, Inc.
 
Black Belt Project-6Sigma-Crank_Noise.
Black Belt Project-6Sigma-Crank_Noise.Black Belt Project-6Sigma-Crank_Noise.
Black Belt Project-6Sigma-Crank_Noise.Pradip Kumar
 
Value Stream Mapping in Non-Manufacturing Environments
Value Stream Mapping in Non-Manufacturing EnvironmentsValue Stream Mapping in Non-Manufacturing Environments
Value Stream Mapping in Non-Manufacturing EnvironmentsTKMG, Inc.
 
Lean Six Sigma project Caponera
Lean Six Sigma project CaponeraLean Six Sigma project Caponera
Lean Six Sigma project CaponeraAnnalisa Caponera
 
2015 06-03 ti4 agile presented at ncs
2015 06-03 ti4 agile presented at ncs2015 06-03 ti4 agile presented at ncs
2015 06-03 ti4 agile presented at ncsRuud Teunissen
 
Value Stream Mapping in Office and Service
Value Stream Mapping in Office and ServiceValue Stream Mapping in Office and Service
Value Stream Mapping in Office and ServiceTKMG, Inc.
 
Clarity the Essence of Lean Management
Clarity the Essence of Lean ManagementClarity the Essence of Lean Management
Clarity the Essence of Lean ManagementTKMG, Inc.
 
Clarity First: What it is. Why you need it. How to get it.
Clarity First: What it is. Why you need it. How to get it.Clarity First: What it is. Why you need it. How to get it.
Clarity First: What it is. Why you need it. How to get it.TKMG, Inc.
 
Value stream mapping and kaizen in agile retrospectives
Value stream mapping and kaizen in agile retrospectivesValue stream mapping and kaizen in agile retrospectives
Value stream mapping and kaizen in agile retrospectivesAngela Dugan
 
3960 alkermes case_study8_fa7
3960 alkermes case_study8_fa73960 alkermes case_study8_fa7
3960 alkermes case_study8_fa7Yasmin AbdelAziz
 
A performance-based approach for developing upstream professionals - Salam Sa...
A performance-based approach for developing upstream professionals - Salam Sa...A performance-based approach for developing upstream professionals - Salam Sa...
A performance-based approach for developing upstream professionals - Salam Sa...Society of Petroleum Engineers
 
GE Home Depot Black Belt Project
GE Home Depot Black Belt ProjectGE Home Depot Black Belt Project
GE Home Depot Black Belt ProjectDee Daley
 
Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project ManagementShyam Kerkar
 
UTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream MappingUTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream MappingLean6Sigma4all
 
Value stream management is essential for dev ops v4
Value stream management is essential for dev ops v4Value stream management is essential for dev ops v4
Value stream management is essential for dev ops v4DevOps.com
 

What's hot (20)

Value Stream Mapping: Beyond the Mechanics - Part 3 (Executing the Transforma...
Value Stream Mapping: Beyond the Mechanics - Part 3 (Executing the Transforma...Value Stream Mapping: Beyond the Mechanics - Part 3 (Executing the Transforma...
Value Stream Mapping: Beyond the Mechanics - Part 3 (Executing the Transforma...
 
Six sigma-black-belt-project-sample
Six sigma-black-belt-project-sampleSix sigma-black-belt-project-sample
Six sigma-black-belt-project-sample
 
Black Belt Project-6Sigma-Crank_Noise.
Black Belt Project-6Sigma-Crank_Noise.Black Belt Project-6Sigma-Crank_Noise.
Black Belt Project-6Sigma-Crank_Noise.
 
Value Stream Mapping in Non-Manufacturing Environments
Value Stream Mapping in Non-Manufacturing EnvironmentsValue Stream Mapping in Non-Manufacturing Environments
Value Stream Mapping in Non-Manufacturing Environments
 
Lean Six Sigma project Caponera
Lean Six Sigma project CaponeraLean Six Sigma project Caponera
Lean Six Sigma project Caponera
 
Laboratory Relocation Roundtable
Laboratory Relocation RoundtableLaboratory Relocation Roundtable
Laboratory Relocation Roundtable
 
2015 06-03 ti4 agile presented at ncs
2015 06-03 ti4 agile presented at ncs2015 06-03 ti4 agile presented at ncs
2015 06-03 ti4 agile presented at ncs
 
Value Stream Mapping in Office and Service
Value Stream Mapping in Office and ServiceValue Stream Mapping in Office and Service
Value Stream Mapping in Office and Service
 
Clarity the Essence of Lean Management
Clarity the Essence of Lean ManagementClarity the Essence of Lean Management
Clarity the Essence of Lean Management
 
Clarity First: What it is. Why you need it. How to get it.
Clarity First: What it is. Why you need it. How to get it.Clarity First: What it is. Why you need it. How to get it.
Clarity First: What it is. Why you need it. How to get it.
 
Value stream mapping and kaizen in agile retrospectives
Value stream mapping and kaizen in agile retrospectivesValue stream mapping and kaizen in agile retrospectives
Value stream mapping and kaizen in agile retrospectives
 
3960 alkermes case_study8_fa7
3960 alkermes case_study8_fa73960 alkermes case_study8_fa7
3960 alkermes case_study8_fa7
 
A performance-based approach for developing upstream professionals - Salam Sa...
A performance-based approach for developing upstream professionals - Salam Sa...A performance-based approach for developing upstream professionals - Salam Sa...
A performance-based approach for developing upstream professionals - Salam Sa...
 
Tollgate Presentation
Tollgate PresentationTollgate Presentation
Tollgate Presentation
 
GE Home Depot Black Belt Project
GE Home Depot Black Belt ProjectGE Home Depot Black Belt Project
GE Home Depot Black Belt Project
 
Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project Management
 
UTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream MappingUTC Aerospace System - Value Stream Mapping
UTC Aerospace System - Value Stream Mapping
 
Presentation1
Presentation1Presentation1
Presentation1
 
Value stream management is essential for dev ops v4
Value stream management is essential for dev ops v4Value stream management is essential for dev ops v4
Value stream management is essential for dev ops v4
 
Webb Control Tollgate 15 DEC 14 Final Version
Webb Control Tollgate  15 DEC 14 Final VersionWebb Control Tollgate  15 DEC 14 Final Version
Webb Control Tollgate 15 DEC 14 Final Version
 

Similar to Lean Thinking Summary

Week 6: chris piccin lean - 042417 - day 2
Week 6: chris piccin   lean - 042417 - day 2Week 6: chris piccin   lean - 042417 - day 2
Week 6: chris piccin lean - 042417 - day 2Talou Diallo
 
Lean Six Sigma - Concept & Application
Lean Six Sigma - Concept & ApplicationLean Six Sigma - Concept & Application
Lean Six Sigma - Concept & ApplicationHusnain Shahid
 
Lean Six Sigma overview Julian Kalac
Lean  Six Sigma overview Julian KalacLean  Six Sigma overview Julian Kalac
Lean Six Sigma overview Julian KalacJulian Kalac P.Eng
 
Process Improvement - 10 Essential Ingredients
Process Improvement - 10 Essential IngredientsProcess Improvement - 10 Essential Ingredients
Process Improvement - 10 Essential IngredientsRichard Ouellette
 
Value Stream Mapping – Stories From the Trenches
Value Stream Mapping – Stories From the TrenchesValue Stream Mapping – Stories From the Trenches
Value Stream Mapping – Stories From the TrenchesDevOps.com
 
Engineering DevOps Right the First Time
Engineering DevOps Right the First TimeEngineering DevOps Right the First Time
Engineering DevOps Right the First TimeMarc Hornbeek
 
Newport News Shipbuilding Takes the Pain out of Compliance & Testing
Newport News Shipbuilding Takes the Pain out of Compliance & TestingNewport News Shipbuilding Takes the Pain out of Compliance & Testing
Newport News Shipbuilding Takes the Pain out of Compliance & TestingWorksoft
 
Engineering DevOps to meet Business Goals
 Engineering DevOps to meet Business Goals Engineering DevOps to meet Business Goals
Engineering DevOps to meet Business GoalsMarc Hornbeek
 
2015 06-24 innovation in the large enterprise final-v2
2015 06-24 innovation in the large enterprise final-v22015 06-24 innovation in the large enterprise final-v2
2015 06-24 innovation in the large enterprise final-v2Jeffrey Einhorn
 
When Agile is a Quality Game Changer Webinar - Michael Mah, Philip Lew
When Agile is a Quality Game Changer Webinar - Michael Mah, Philip LewWhen Agile is a Quality Game Changer Webinar - Michael Mah, Philip Lew
When Agile is a Quality Game Changer Webinar - Michael Mah, Philip LewXBOSoft
 
Lci la chapter lean intro 071410 no pics
Lci la chapter lean intro 071410 no picsLci la chapter lean intro 071410 no pics
Lci la chapter lean intro 071410 no picshaganone
 
Kabir Kassam: 6 – sigma training - Midterm Review
Kabir Kassam: 6 – sigma training - Midterm Review Kabir Kassam: 6 – sigma training - Midterm Review
Kabir Kassam: 6 – sigma training - Midterm Review Kabir Kassam
 
Agile Methods: Fact or Fiction
Agile Methods: Fact or FictionAgile Methods: Fact or Fiction
Agile Methods: Fact or FictionMatt Ganis
 
Quality improvement
Quality improvementQuality improvement
Quality improvementAdel Younis
 
Value Stream Mapping
Value Stream MappingValue Stream Mapping
Value Stream MappingTKMG, Inc.
 

Similar to Lean Thinking Summary (20)

Week 6: chris piccin lean - 042417 - day 2
Week 6: chris piccin   lean - 042417 - day 2Week 6: chris piccin   lean - 042417 - day 2
Week 6: chris piccin lean - 042417 - day 2
 
Week 06_Handout day 2
Week 06_Handout day 2Week 06_Handout day 2
Week 06_Handout day 2
 
Lean Six Sigma - Concept & Application
Lean Six Sigma - Concept & ApplicationLean Six Sigma - Concept & Application
Lean Six Sigma - Concept & Application
 
Lean Six Sigma overview Julian Kalac
Lean  Six Sigma overview Julian KalacLean  Six Sigma overview Julian Kalac
Lean Six Sigma overview Julian Kalac
 
Agile method
Agile methodAgile method
Agile method
 
Process Improvement - 10 Essential Ingredients
Process Improvement - 10 Essential IngredientsProcess Improvement - 10 Essential Ingredients
Process Improvement - 10 Essential Ingredients
 
Value Stream Mapping – Stories From the Trenches
Value Stream Mapping – Stories From the TrenchesValue Stream Mapping – Stories From the Trenches
Value Stream Mapping – Stories From the Trenches
 
Engineering DevOps Right the First Time
Engineering DevOps Right the First TimeEngineering DevOps Right the First Time
Engineering DevOps Right the First Time
 
08 project quality management
08 project quality management08 project quality management
08 project quality management
 
SAFe and DevOps - better together
SAFe and DevOps - better togetherSAFe and DevOps - better together
SAFe and DevOps - better together
 
DFSS short
DFSS shortDFSS short
DFSS short
 
Newport News Shipbuilding Takes the Pain out of Compliance & Testing
Newport News Shipbuilding Takes the Pain out of Compliance & TestingNewport News Shipbuilding Takes the Pain out of Compliance & Testing
Newport News Shipbuilding Takes the Pain out of Compliance & Testing
 
Engineering DevOps to meet Business Goals
 Engineering DevOps to meet Business Goals Engineering DevOps to meet Business Goals
Engineering DevOps to meet Business Goals
 
2015 06-24 innovation in the large enterprise final-v2
2015 06-24 innovation in the large enterprise final-v22015 06-24 innovation in the large enterprise final-v2
2015 06-24 innovation in the large enterprise final-v2
 
When Agile is a Quality Game Changer Webinar - Michael Mah, Philip Lew
When Agile is a Quality Game Changer Webinar - Michael Mah, Philip LewWhen Agile is a Quality Game Changer Webinar - Michael Mah, Philip Lew
When Agile is a Quality Game Changer Webinar - Michael Mah, Philip Lew
 
Lci la chapter lean intro 071410 no pics
Lci la chapter lean intro 071410 no picsLci la chapter lean intro 071410 no pics
Lci la chapter lean intro 071410 no pics
 
Kabir Kassam: 6 – sigma training - Midterm Review
Kabir Kassam: 6 – sigma training - Midterm Review Kabir Kassam: 6 – sigma training - Midterm Review
Kabir Kassam: 6 – sigma training - Midterm Review
 
Agile Methods: Fact or Fiction
Agile Methods: Fact or FictionAgile Methods: Fact or Fiction
Agile Methods: Fact or Fiction
 
Quality improvement
Quality improvementQuality improvement
Quality improvement
 
Value Stream Mapping
Value Stream MappingValue Stream Mapping
Value Stream Mapping
 

More from Tokunbo Anifalaje (20)

Week 12_Handout
Week 12_HandoutWeek 12_Handout
Week 12_Handout
 
Week 12_Human resources
Week 12_Human resourcesWeek 12_Human resources
Week 12_Human resources
 
Week 11_Access to capital
Week 11_Access to capitalWeek 11_Access to capital
Week 11_Access to capital
 
Week 10_Handouts
Week 10_HandoutsWeek 10_Handouts
Week 10_Handouts
 
Week 10_sustainability orientation-handout
Week 10_sustainability orientation-handoutWeek 10_sustainability orientation-handout
Week 10_sustainability orientation-handout
 
Week 10_Sustainability
Week 10_SustainabilityWeek 10_Sustainability
Week 10_Sustainability
 
Week 09_Handout benchmark data
Week 09_Handout benchmark dataWeek 09_Handout benchmark data
Week 09_Handout benchmark data
 
Week 09_Handout
Week 09_HandoutWeek 09_Handout
Week 09_Handout
 
Week 09_Financials
Week 09_FinancialsWeek 09_Financials
Week 09_Financials
 
Week 08_Handout
Week 08_HandoutWeek 08_Handout
Week 08_Handout
 
Week 08_Marketing
Week 08_MarketingWeek 08_Marketing
Week 08_Marketing
 
Week 07_Supply chain
Week 07_Supply chainWeek 07_Supply chain
Week 07_Supply chain
 
Week 06_Handout day 1
Week 06_Handout day 1Week 06_Handout day 1
Week 06_Handout day 1
 
Week 06_Operations (Part 2)
Week 06_Operations (Part 2)Week 06_Operations (Part 2)
Week 06_Operations (Part 2)
 
Week 05_Handout day 1
Week 05_Handout day 1Week 05_Handout day 1
Week 05_Handout day 1
 
Week 05_Operation (part 1)
Week 05_Operation (part 1)Week 05_Operation (part 1)
Week 05_Operation (part 1)
 
Week 04_Designed to scale handout
Week 04_Designed to scale handoutWeek 04_Designed to scale handout
Week 04_Designed to scale handout
 
Week 04_Product design
Week 04_Product designWeek 04_Product design
Week 04_Product design
 
Week 03_Handout
Week 03_HandoutWeek 03_Handout
Week 03_Handout
 
Week 03_Sales
Week 03_SalesWeek 03_Sales
Week 03_Sales
 

Recently uploaded

Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communicationskarancommunications
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...lizamodels9
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewasmakika9823
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsApsara Of India
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in managementchhavia330
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneVIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneCall girls in Ahmedabad High profile
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfpollardmorgan
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Serviceankitnayak356677
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdfOrient Homes
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 

Recently uploaded (20)

Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Pharma Works Profile of Karan Communications
Pharma Works Profile of Karan CommunicationsPharma Works Profile of Karan Communications
Pharma Works Profile of Karan Communications
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service DewasVip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
Vip Dewas Call Girls #9907093804 Contact Number Escorts Service Dewas
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call GirlsCash Payment 9602870969 Escort Service in Udaipur Call Girls
Cash Payment 9602870969 Escort Service in Udaipur Call Girls
 
GD Birla and his contribution in management
GD Birla and his contribution in managementGD Birla and his contribution in management
GD Birla and his contribution in management
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service PuneVIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
VIP Call Girls Pune Kirti 8617697112 Independent Escort Service Pune
 
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdfIntro to BCG's Carbon Emissions Benchmark_vF.pdf
Intro to BCG's Carbon Emissions Benchmark_vF.pdf
 
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts ServiceVip Female Escorts Noida 9711199171 Greater Noida Escorts Service
Vip Female Escorts Noida 9711199171 Greater Noida Escorts Service
 
Best Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting PartnershipBest Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting Partnership
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Catalogue ONG NUOC PPR DE NHAT .pdf
Catalogue ONG NUOC PPR DE NHAT      .pdfCatalogue ONG NUOC PPR DE NHAT      .pdf
Catalogue ONG NUOC PPR DE NHAT .pdf
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 

Lean Thinking Summary

  • 1. 1 Lean Thinking Subtitle Lean Thinking Subtitle Lean Thinking Subtitle Lean Thinking Subtitle Lean Thinking Subtitle Lean Thinking Subtitle Lean Thinking Subtitle Lean Thinking Subtitle Lean Thinking Subtitle “Hidden Waste in Your Processes” (Part 1) + “Successfully Implementing Operational Enhancements” (Part 2) Chris Piccin 25 Day Two 26 Day Two Topics Continuous Flow Theory of Constraints Cost of Poor Quality Continuous Improvement / Six Sigma By the end of this session you will: •  know how to identify and relieve production constraints •  understand the cost of poor quality and the DMAIC improvement framework •  have learned facilitation and problem solving skills
  • 2. 27 3. Continuous Flow move as fast as value can be added, no waiting. Little’s Law Theory of Constraints Set-up Time Reduction Takt Time Kanban Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 27 28 Measuring the Flow of Processes with Little’s Law Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 28 Work in Progress Output Work in Progress / Output = Cycle-time 120 gallons / 60 gallons per minute = 2 minutes 29 Continuous Flow The Theory of Constraints Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 29 CB BA •  Constraints produce the fewest outputs per unit of time. Often they will have a stack of work in front of them •  Constraints govern the output for the whole process – an hour lost at the bottleneck is lost for the whole process. •  Efficiency gains at any other location don’t improve productivity of the process. Managing the Constraint 1.  Identify it 2.  Exploit it 3.  Subordinate everything else 4.  Increase output of constraint 5.  Rinse and repeat
  • 3. 30 Set-up Time Reduction https://vimeo.com/98796938 31 Set-up Time Reduction (Single Minute Exchange of Die) Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 31 1 Separate Elements Identify tasks that can be performed during production and make them “external” to the change over 2 Parallel Work Identify tasks performed sequentially and, where possible, complete them simultaneously 3 Convert Elements Review remaining internal elements and ask what it would take to make them external. Convert as many as possible 4 Streamline Review all elements for simplification to shorten both external and change over time. 32
  • 4. 33 Production Systems Takt Time Example: Willow Run Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 33 68 Flow, Takt Time and Cellular Design 1940 – A bomber per hour at Willow Run 34,500 Employees 488,000 Discrete parts 33,000 Components 24 Assemblies 1 B-24 per hour 34 Production Systems Kanban Overview Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 34Source: http://logisticsglobal.blogspot.com/2011/10/kanban-system-parts-procurement-toyota.html 35 Production Systems Kanban Board Example: Hiring Process Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 35 1.  Define Value Stream 2.  Set Work in Process Limit 3.  Establish the Backlog 4.  Start Pulling Work Application Received Phone Screen Manager Interview Interview Complete Decision G. Martin Declined M. Taylor Offer B. Miller W. Jones F. Brown C. Williams A Johnson C. Smith M. Jackson 3 M. Garcia 2 Rodriguez AndersonJ. Davis 1 A. Thomas Declined Hernandez Declined T. Moore Declined D. Jones No Go R. Martinez Offer A. Richards Start 15th G. Wilson 4
  • 5. 36 Simulation Round 3: Continuous Flow •  Owner is responsible for final decisions •  Changes must be reversible •  No changes that involve customers •  No elimination of staff •  Facilitator has final approval •  Implement changes and train if necessary Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 36 Objective: identify and relieve constraints in the process. 37 4. Perfection produce exactly what the customer wants… •  Cost of Poor Quality •  The Case for Continuous Improvement •  Simple Six Sigma 37Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 38 The Cost of Poor Quality Estimated Costs for American Companies Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 38 Non-conformance “The cost of getting it wrong” Conformance “The cost of getting it right” Internal Failures (20% to 40%) Controls (10% to 50%) •  Scrap materials •  Rework – doing work twice •  Lost production time •  Inspecting for errors, defects •  Delays waiting for approval External Failures (20% to 40%) Prevention (0% to 5%) •  Fines, Penalties •  Warranties, Concessions •  Lost revenue •  Measurement and tracking •  Root cause analysis •  Mitigation Source: The Quality Engineer Primer by Bill Wortman, 1997
  • 6. 39 40 The Limits of Inspection Controls (and The Case for Continuous Improvement) Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 40 “Finished files are the result of years of scientific study combined with the functional experience offered by many Financial Services experts.” 41 Another Different Approach to Cost of Quality: Continuous Improvement Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 41 Total Costs Control / Inspection Costs Non-conformance Costs Quality Cost Prevention Costs (Continuous Improvement)
  • 7. 42 Conventional wisdom: “This is good enough.” Six Sigma: What is it? When is it useful? Sigma Defects per Million % Good 6 3 99.99966% 5 233 99.977 % 4 6,210 99.4 % 3 66,807 93.3 % 2 308,537 69.2 % Condition: 99% Good (4 sigma) 99.99966% Good (6 sigma) High Risk 4 plane crashes per day 1 accident every 5 years High Volume 2,800 lost packages per hour Less than 2 lost items per day High Complexity 4,000 surgical mistakes per year Less than 2 mistakes per year Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 42 Three conditions when “good enough” isn’t: 43 Continuous Improvement: Will Six Sigma work for us? Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 43 “Too Complicated” “Bureaucratic” “It’s a Black Box” 44 Continuous Improvement: Six Sigma works for Dabbawallas Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 44 “There is a service called FedEx that is similar to ours but they don’t deliver hot lunches.” Dhondu Kondaji Chowdhury
  • 8. 45 Continuous Improvement: How Dabba Deliveries Work Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 45 10C VP M Collection Codes VP Residential Location (Vile Parle) C Residential Railway Station (Cooper Hospital) Red Dabbawalla teams color Destination Codes 10 Destination Railway Station (Nariman Point) 9 Dabbawalla team number M Building Identification (Mittal Tower) 12 Floor number “The unavoidable price of reliability is simplicity.” C. Hoare 46 Six Sigma DMAIC Improvement Methodology Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 46 Process Optimization (People Driven) Process Characterization (Fact Driven) MEASURE Record performance in a measurement system CONTROL Ensure sustainability IMPROVE Agree and make required changes ANALYZE Find the critical few factors DEFINE Document issue, allocate resources 47 Define: Tips for Starting an Improvement Project Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 47 Define the objective •  Articulate the compelling need for change •  Define goals tied to business objectives •  Get buy-in from the critical stakeholders Build the right team •  Ensure stakeholder representation •  Keep the team small and co-located where possible •  Hold frequent, timely, informal communications Freeze the target •  Set specific, measurable success metric(s) •  Set stretch targets. When in doubt, 50% improvement •  Make the metrics visible for all and the target hard to change Invent offline •  Make the most of existing or proven technology •  Use technical innovation only when it’s fully tested Be time driven •  80% of target is a win, celebrate success and move on •  Iterate often, plan multi-generation releases •  Use parallel work streams where possible
  • 9. 48 Measure: Record Performance with Run Charts Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 48 49 Analyze: Find Critical Few Factors with Pareto Charts Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 49 50 Analyze: Using the Five Whys to Find Root Cause Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 50 Where the Failure Occurred - Process Gaps 1.  Understand what the customer expects 2.  Design the process to meet customer expectations. 3.  Follow the process as designed 4.  All communications are consistent with how the process operates Why? A solid rocket booster exploded. Why? Hot gasses escaped from the rocket booster. Why? O-ring seals failed in at least one of the booster’s joints. Why? The shuttle launched when the air temperature was below design specifications for the O-rings Why? “…NASA’s structure permitted internal flight safety problems to bypass key shuttle managers.” Rogers Commission Report On January 28, 1986 the Space Shuttle Challenger disintegrated over the Atlantic Ocean 73 seconds into its flight, leading to the deaths of its seven crew members. What went wrong?
  • 10. 51 Improve: Better Quality with Error Proofing Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 51 Risk Priority Number = Severity * Occurrence * Detection Shut down Lock out Warning Severity Occurrence Detection 5 Harm a customer or employee Trigger legal or regulatory action 5 Very High (greater than 10%) 5 No controls 4 Cause significant reputational or financial risk 4 High (1% to 10%) 4 Low QC/QA sampling 3 Result in a customer complaint 3 Moderate (1/10,000 to 1%) 3 Moderate 100% manual inspection 2 Minor effect on performance 2 Low (1/10,000 to 1/Million) 2 High Statistical Process Control 1 Unnoticed by customer Internal waste or rework 1 Very Low (less than 1/Million) 1 Very High 100% auto inspection 52 Control: Standard Work for Consistency Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 52 Elements of Standard Work 1.  Inventory – material types and quantities required to keep the process operating smoothly 2.  Work Sequence – order of tasks an operator must perform within takt time 3.  Takt Time - the rate at which components must be made to meet customer demand Prep. Time 15 min. 53 Control: Monitoring Key Metric(s) Over Time Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 53 Trend – Six consecutive data points in either direction Shift – Eight consecutive points on one side of the median
  • 11. 54 Process Optimization Facilitation for Results Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 54 The problem is often about the process… “85% of the reasons for failure to meet customer expectations are related to deficiencies in systems and process…change the process rather than badgering individuals to do better.” Dr. W. Edwards Deming …solutions are ALWAYS about people Results = Solution * Acceptance 55 Facilitation for Results 55Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 56 Facilitation for Results Open: Idea Generation Brain Writing •  One idea per Post-it note •  In order, each person reads an idea and puts it on a wall •  Team uses what the hear to modify or generate new ideas •  Keep going until ideas dry up. Assumption Busting •  Identify rules or behaviors that lead to the current state •  Surface assumptions underlying rules or behaviors (ask why 5x) •  Challenge assumptions – existing exceptions? Premortem •  Ask, “How can we ensure the problem happens ALL the time?” •  Run like Brain Writing Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 56
  • 12. 57 Facilitation for Results Narrow: Affinity Grouping Adds Clarity Group A Others Group B Group C Group D •  Go through the ideas to see where they can be meaningfully grouped •  Move the ideas that belong in the same group together •  Look for duplicate ideas. Get permission from each idea author to consolidate duplicates so that they overlap •  Work with the group to define a title post-it that succinctly describes each group •  Place all single ideas under the title “Others” Copyright © Vox Datum LLC (2016-2017). All Rights Reserved. 57