SlideShare a Scribd company logo
Verifying
Transformer Rated Service
Installations
January 2019
Field Meter Testing Using
Phantom Load
OPPORTUNITY FOR A PROBLEM BEYOND
THE METER?
K Y Z GNDK Y Z GND
INSTRUMENT TRANSFORMERS
INSTRUMENT TRANSFORMERS
CURRENT RETURN SWITCHES
CURRENT RETURN SWITCHES
C Phase Current in open
position
CURRENT RETURN SWITCHES
C Phase Current in closed position making contact with
attachment screw for shunt buss.
This re-routes current to by pass the meter.
CURRENT RETURN SWITCHES
Form 9S Abase Adaptor
Nicked Control Cable
SYSTEM ANALYZERS
PowerMetrix
PowerMaster
Spinlab
Bird Dog Plus
testMET
Gold Miner
Radian
RD31-221
SYSTEM ANALYZER WE USE
PowerMaster
5 Series Model
Testing Options Available
On the PowerMaster
Proper PPE must be
worn and all Safety
Guidelines followed.
Install the Duckbill
Current Leads
Connect the Potential
Leads making sure
they are matched to
the proper current.
Before Beginning the Integrated Site Scan
The Following Steps Must be Performed
Why ?
Select the Vector Analysis Option
Before Starting
Vector
View the Vector to Verify your Connections …
View the Vector to Verify your Connections …
4 Wire Wye Service at Unity Power Factor
4 Wire Wye Service at 50% Power Factor
Single Phase Service
Unity 50% PF Unity
No Lag (1.00 PF) 30° Lag (0.866 PF) Waveform
Three Wire Three Phase Network Service
Three Wire Three Phase Delta Service
No Lag (1.00 PF) 30° Lag (0.866 PF)
Delta Service at Unity Power Factor
Delta Service at 50% Power Factor
VIEW THE VECTOR TO VERIFY YOUR
CONNECTIONS …
View the Vector to Verify your Connections …
View the Vector to Verify your Connections …
Correct Vector
Potentials and Currents Match.
Start the Scan
What your Looking For!
INTEGRATED SITE TEST
Capture of Sine Waves of Amps & Volts
Capture of Vector
Captures System Overall Summary
“Breakdown Of Vector”
Harmonics for Amp And Volts
Amps Volts
Harmonics
CAUSES OF HARMONICS
Harmonics are caused by devices that use an irregular current
sinewave when the normal sinewave voltage is applied
LINEAR LOADS (Few Harmonics)
• Incandescent Lights
• Heating Loads (Resistive)
• Some Motors
NON-LINEAR LOADS (Harmonics)
• DC Drives
•Power Rectifiers
•Compact Fluorescent Bulbs
HARMONIC DISTORTION
Harmonic waveforms are simply multiples of the fundamental waveform.
The graphs below show the relationship between a fundamental (60 Hz)
current waveform and a 5th harmonic (300 Hz) component with about 25%
peak deviation.
Fundamental(60Hz)
5th Harmonic(300Hz)
ResultantWaveForm
INCANDESCENT BULB
COMPACT FLUORESCENT BULB
MOTOR
POWER SUPPLY FOR LAP TOP
COMPUTER
Meter Accuracy Test
Meter Accuracy Test
Customer or Phantom Load Test
Meter Accuracy Test Setup
Meter Test Results
kWH
Phantom Load Tests Results
VERIFYING CT ACCURACY
SETUP SCREEN FOR VERIFYING CT ACCURACY
DEVICES USED TO MEASURE THE
CT’S “PRIMARY” CURRENT
(CUSTOMER LOAD)
High Voltage Fiber Optic
Probe
Used on Primary and Overhead
Secondary Services
Flex 36 for Services 600 Volts or Less
MEASURING SECONDARY CURRENT
VERIFYING CT ACCURACY ON 600 VOLTS
OR LESS
FLEX PROBE MEASURING CT’S
“PRIMARY” CURRENT IN AN U.G.
TRANSFORMER
FLEX PROBE MEASURING CT’S “PRIMARY”
CURRENT IN SWITCHGEAR
IMPORTANT NOTE
GET AHEAD OF THE CTS…
Source Side of the CTs
WHY?
Do your best to get close to the
source as possible…
But do it SAFE!
Fiber Optic Horseshoe Probe used on
Primary Services (above 600 volts)
Fiber Optic Horseshoe Probe used on
Primary Service (above 600 volts)
Phase A
125v 1.66a
Phase B
125v 1.60a
Phase C
125v 0.00a
Fiber Optic Horseshoe Probe used on
Primary Service (above 600 volts)
Fiber Optic Horseshoe Probe can also be
used on Over Head Secondary Service
CT Ratio Test Information Results
Possible Errors will be
in RED, this appears to
be a CT running
backwards.
If you didn’t check the
vector before starting,
this is probably your
probe installed in
reverse. Check the probe
and retest the phase in
question.
CT Ratio Test Information Results
RESULTS FOR RATIO ONLY
Results for Burden Only
Should be 2000:5
Ratioed at 1432:5
Failure Began Before .1 Ohms Of
Burden Is Applied
Bad CT
Bad CT ?
Ratio Should Be 200 : 5
No, Just A Bad Electrician
Current Flow
Current Flow
Additional run of wire installed and pulled
through Two CTs backwards
Bad CT ?
300 : 5 Primary CTs Ratio Results at 112%
Best Resolution Achieved If Secondary Amps
Are At Least 10% of CT Value
Same CT 15 Minutes Later
What Happened ?
21% of CT
Rated Load
Vectors
What Do We Look For ?
Services At Unity Power Factor
4 wire WYE 4 wire Delta3 wire Delta
Typical WYE Service
Problem ?
A Phase and B Phase Current Crossed
Problem ?
CTs Wired Backwards
Three Wire Three Phase
Delta Service
Three Wire Three Phase Delta
Bad Power Factor
15° (Lag)
Normally Leading BY 30 °
Normally Laging BY 30 °
74°
Three Wire Three Phase Delta
with Worse Power Factor
Forward Rotation Stops at 90°
as the Angle Increases Reverse Rotation Begins
93°
33°
Three Wire Three Phase Delta
with Even Worse Power Factor
It looks like A-phase current is matched with B-phase
potential, and B-phase current with A-phase potential.
Problem- Crossed Potentials?
Instrumentation data from the Metercat Diagnostic Read
agreed with data reported from the AMI meter.
As the load changed, the meter would
alternate between forward energy flow and
reverse energy flow.
Problem- Crossed Potentials?
The actual problem was found to be non-brothered service conductors
through two of the current transformers. Phase-C current transformer
on the far right was correct.
C-phase CT
Measured 9.5 amps and 49.1 amps
C-phase CT
Total current measured by C-phase CT was 58.6 amps
Vectors with the same angle simply add together
Total current measured
Voltage
Current
BA C
A-phase CT
Measured 92.3 amps on B-phase and 15.4 amps on A-phase
A-phase CT
Total current measured by A-phase CT was 85.3 amps
How does 92.3 and 15.4 add up to be 85.3 ?
B-phase CT
Measured 12.5 amps on B-phase and 56.9 amps on A-phase
B-phase CT
Total current measured by A-phase CT was 47.2 amps
How does 12.5 and 56.9 add up to be 47.2 ?
Total current measured
Voltage
Current
BA C
A complex number can be visually represented as
a pair of numbers (a, b) forming a vector on a
diagram, representing the complex plane. "Re" is
the real axis, "Im" is the imaginary axis, and i is the
imaginary unit
Illustration of on-site measurements
The customer added
the 225 amp panel
some time after the
original installation.
Opportunity to Bill for Excessive Reactive Load
Metering Problem ?
Bad Power Factor
Balanced Load
WHAT CAN A CUSTOMER OR
UTILITY DO ABOUT BAD FACTOR?
?
VARs Compensator
Vars Compensator Off
Vars Compensator On
Site With VARs Compensator Installed
SAFETY
IS THE ABSOLUTE NUMBER ONE PRIORITY
Hardhat
 Eye Protection
 FR Clothing
 Rubber gloves with “Grabbit” gloves or Leather
outer protectors


More Related Content

What's hot

What's hot (20)

Contingency analysis
Contingency analysisContingency analysis
Contingency analysis
 
Q meter ppt
Q meter pptQ meter ppt
Q meter ppt
 
DC link ripple analysis on five phase pwm voltage source inverter with unbala...
DC link ripple analysis on five phase pwm voltage source inverter with unbala...DC link ripple analysis on five phase pwm voltage source inverter with unbala...
DC link ripple analysis on five phase pwm voltage source inverter with unbala...
 
Fault location for transmission line
Fault location  for transmission lineFault location  for transmission line
Fault location for transmission line
 
Meter Forms: Wiring and Uses
Meter Forms: Wiring and UsesMeter Forms: Wiring and Uses
Meter Forms: Wiring and Uses
 
Instrumentation Lab. Experiment #4 Report: Op-Amps: Integrator, Differentiato...
Instrumentation Lab. Experiment #4 Report: Op-Amps: Integrator, Differentiato...Instrumentation Lab. Experiment #4 Report: Op-Amps: Integrator, Differentiato...
Instrumentation Lab. Experiment #4 Report: Op-Amps: Integrator, Differentiato...
 
Converting Capacitance Into Controller Counts
Converting Capacitance Into Controller CountsConverting Capacitance Into Controller Counts
Converting Capacitance Into Controller Counts
 
Burden Testing, Theory, and Practice
Burden Testing, Theory, and PracticeBurden Testing, Theory, and Practice
Burden Testing, Theory, and Practice
 
Measurement of 3 phase power by two watt-meter method
Measurement of 3 phase power by two watt-meter methodMeasurement of 3 phase power by two watt-meter method
Measurement of 3 phase power by two watt-meter method
 
Electrical Circuit Theorem
Electrical Circuit TheoremElectrical Circuit Theorem
Electrical Circuit Theorem
 
Short circuit (wic) testing and parameters.
Short circuit (wic) testing and parameters.Short circuit (wic) testing and parameters.
Short circuit (wic) testing and parameters.
 
Three Phase Power Measurement
Three Phase Power MeasurementThree Phase Power Measurement
Three Phase Power Measurement
 
Unit 09 instruments
Unit 09 instrumentsUnit 09 instruments
Unit 09 instruments
 
Capacitive Touch Sensor Charge Time
Capacitive Touch Sensor Charge TimeCapacitive Touch Sensor Charge Time
Capacitive Touch Sensor Charge Time
 
Ratio, Burden, Admittance Testing
Ratio, Burden, Admittance TestingRatio, Burden, Admittance Testing
Ratio, Burden, Admittance Testing
 
FAULT DETECTION ON OVERHEAD TRANSMISSION LINE USING ARTIFICIAL NEURAL NET...
 FAULT DETECTION ON OVERHEAD TRANSMISSION LINE  USING ARTIFICIAL NEURAL NET... FAULT DETECTION ON OVERHEAD TRANSMISSION LINE  USING ARTIFICIAL NEURAL NET...
FAULT DETECTION ON OVERHEAD TRANSMISSION LINE USING ARTIFICIAL NEURAL NET...
 
Harmonic Analysis of 6-Pulse and 12-Pulse Converter Models
Harmonic Analysis of 6-Pulse and 12-Pulse Converter ModelsHarmonic Analysis of 6-Pulse and 12-Pulse Converter Models
Harmonic Analysis of 6-Pulse and 12-Pulse Converter Models
 
Instrumentation Lab. Experiment #12 Report: Lateral Beam Vibration
Instrumentation Lab. Experiment #12 Report: Lateral Beam VibrationInstrumentation Lab. Experiment #12 Report: Lateral Beam Vibration
Instrumentation Lab. Experiment #12 Report: Lateral Beam Vibration
 
CONCEPT OF SYMMETRICAL COMPONENT AS A TECHNIQUE FOR ANALYSIS OF FAULT AND IMP...
CONCEPT OF SYMMETRICAL COMPONENT AS A TECHNIQUE FOR ANALYSIS OF FAULT AND IMP...CONCEPT OF SYMMETRICAL COMPONENT AS A TECHNIQUE FOR ANALYSIS OF FAULT AND IMP...
CONCEPT OF SYMMETRICAL COMPONENT AS A TECHNIQUE FOR ANALYSIS OF FAULT AND IMP...
 
5 ammeter and voltmeter
5 ammeter and voltmeter5 ammeter and voltmeter
5 ammeter and voltmeter
 

Similar to Verifying Transformer Rated Service Installations

Ac Power Problems And Measurement Sreevidhya@Students
Ac Power Problems And Measurement Sreevidhya@StudentsAc Power Problems And Measurement Sreevidhya@Students
Ac Power Problems And Measurement Sreevidhya@Students
B Bhargav Reddy
 

Similar to Verifying Transformer Rated Service Installations (20)

Ratio Burden Admittance Testing
Ratio Burden Admittance TestingRatio Burden Admittance Testing
Ratio Burden Admittance Testing
 
Complete Site Testing
Complete Site TestingComplete Site Testing
Complete Site Testing
 
Ratio, Burden, and Admittance Testing
Ratio, Burden, and Admittance TestingRatio, Burden, and Admittance Testing
Ratio, Burden, and Admittance Testing
 
Complete Site Testing
Complete Site TestingComplete Site Testing
Complete Site Testing
 
Power Quality Issues.ppt
Power Quality Issues.pptPower Quality Issues.ppt
Power Quality Issues.ppt
 
CT Testing - Theory and Practice.pptx
CT Testing - Theory and Practice.pptxCT Testing - Theory and Practice.pptx
CT Testing - Theory and Practice.pptx
 
Ac Power Problems And Measurement Sreevidhya@Students
Ac Power Problems And Measurement Sreevidhya@StudentsAc Power Problems And Measurement Sreevidhya@Students
Ac Power Problems And Measurement Sreevidhya@Students
 
Transformer Rated Metering Site Verification
Transformer Rated Metering Site VerificationTransformer Rated Metering Site Verification
Transformer Rated Metering Site Verification
 
Introduction to Transformer Rated Metering
Introduction to Transformer Rated MeteringIntroduction to Transformer Rated Metering
Introduction to Transformer Rated Metering
 
Power Quality Issues Detailed Analysis.PPT
Power Quality Issues Detailed Analysis.PPTPower Quality Issues Detailed Analysis.PPT
Power Quality Issues Detailed Analysis.PPT
 
Nebraska Meter Conference 2017 - CT Testing - Ratio, Burden, and Admittance
Nebraska Meter Conference 2017 - CT Testing - Ratio, Burden, and AdmittanceNebraska Meter Conference 2017 - CT Testing - Ratio, Burden, and Admittance
Nebraska Meter Conference 2017 - CT Testing - Ratio, Burden, and Admittance
 
Transformer Rated Metering 09.27.17
Transformer Rated Metering 09.27.17Transformer Rated Metering 09.27.17
Transformer Rated Metering 09.27.17
 
TESCO Tuesday: Meter Testing in the Field
TESCO Tuesday: Meter Testing in the FieldTESCO Tuesday: Meter Testing in the Field
TESCO Tuesday: Meter Testing in the Field
 
Introduction to Transformer Rated Metering
Introduction to Transformer Rated MeteringIntroduction to Transformer Rated Metering
Introduction to Transformer Rated Metering
 
Site Verification for Self-Contained Hot Socket Detection
Site Verification for Self-Contained Hot Socket DetectionSite Verification for Self-Contained Hot Socket Detection
Site Verification for Self-Contained Hot Socket Detection
 
Introduction to Transformer Rated Metering
Introduction to Transformer Rated Metering Introduction to Transformer Rated Metering
Introduction to Transformer Rated Metering
 
Transformer Rated Metering
Transformer Rated MeteringTransformer Rated Metering
Transformer Rated Metering
 
Transformer Rated Metering Site Verification
Transformer Rated Metering Site VerificationTransformer Rated Metering Site Verification
Transformer Rated Metering Site Verification
 
B10391282S18.pdf
B10391282S18.pdfB10391282S18.pdf
B10391282S18.pdf
 
06 -synchronous_machine_parameter_measurement
06  -synchronous_machine_parameter_measurement06  -synchronous_machine_parameter_measurement
06 -synchronous_machine_parameter_measurement
 

Recently uploaded

Essentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with ParametersEssentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with Parameters
Safe Software
 
Search and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical FuturesSearch and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical Futures
Bhaskar Mitra
 

Recently uploaded (20)

Behind the Scenes From the Manager's Chair: Decoding the Secrets of Successfu...
Behind the Scenes From the Manager's Chair: Decoding the Secrets of Successfu...Behind the Scenes From the Manager's Chair: Decoding the Secrets of Successfu...
Behind the Scenes From the Manager's Chair: Decoding the Secrets of Successfu...
 
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
 
Unpacking Value Delivery - Agile Oxford Meetup - May 2024.pptx
Unpacking Value Delivery - Agile Oxford Meetup - May 2024.pptxUnpacking Value Delivery - Agile Oxford Meetup - May 2024.pptx
Unpacking Value Delivery - Agile Oxford Meetup - May 2024.pptx
 
Speed Wins: From Kafka to APIs in Minutes
Speed Wins: From Kafka to APIs in MinutesSpeed Wins: From Kafka to APIs in Minutes
Speed Wins: From Kafka to APIs in Minutes
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
 
Demystifying gRPC in .Net by John Staveley
Demystifying gRPC in .Net by John StaveleyDemystifying gRPC in .Net by John Staveley
Demystifying gRPC in .Net by John Staveley
 
Exploring UiPath Orchestrator API: updates and limits in 2024 🚀
Exploring UiPath Orchestrator API: updates and limits in 2024 🚀Exploring UiPath Orchestrator API: updates and limits in 2024 🚀
Exploring UiPath Orchestrator API: updates and limits in 2024 🚀
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
 
ODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User GroupODC, Data Fabric and Architecture User Group
ODC, Data Fabric and Architecture User Group
 
10 Differences between Sales Cloud and CPQ, Blanka Doktorová
10 Differences between Sales Cloud and CPQ, Blanka Doktorová10 Differences between Sales Cloud and CPQ, Blanka Doktorová
10 Differences between Sales Cloud and CPQ, Blanka Doktorová
 
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualitySoftware Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
 
Measures in SQL (a talk at SF Distributed Systems meetup, 2024-05-22)
Measures in SQL (a talk at SF Distributed Systems meetup, 2024-05-22)Measures in SQL (a talk at SF Distributed Systems meetup, 2024-05-22)
Measures in SQL (a talk at SF Distributed Systems meetup, 2024-05-22)
 
Essentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with ParametersEssentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with Parameters
 
How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...
 
Integrating Telephony Systems with Salesforce: Insights and Considerations, B...
Integrating Telephony Systems with Salesforce: Insights and Considerations, B...Integrating Telephony Systems with Salesforce: Insights and Considerations, B...
Integrating Telephony Systems with Salesforce: Insights and Considerations, B...
 
IESVE for Early Stage Design and Planning
IESVE for Early Stage Design and PlanningIESVE for Early Stage Design and Planning
IESVE for Early Stage Design and Planning
 
In-Depth Performance Testing Guide for IT Professionals
In-Depth Performance Testing Guide for IT ProfessionalsIn-Depth Performance Testing Guide for IT Professionals
In-Depth Performance Testing Guide for IT Professionals
 
Powerful Start- the Key to Project Success, Barbara Laskowska
Powerful Start- the Key to Project Success, Barbara LaskowskaPowerful Start- the Key to Project Success, Barbara Laskowska
Powerful Start- the Key to Project Success, Barbara Laskowska
 
Search and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical FuturesSearch and Society: Reimagining Information Access for Radical Futures
Search and Society: Reimagining Information Access for Radical Futures
 
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
 

Verifying Transformer Rated Service Installations