SlideShare a Scribd company logo
INDIA
ODISHA
PLANT
SITE
CPP VAL – PLANT LOCATION
10/8/2013
AWARDS & RECOGNITION
 CPP-VAL has been Awarded 1st Prize in
“National Energy Conservation Award-
2012” by Bureau of Energy Efficiency in
Thermal Power Sector.
 CPP-VAL was Awarded 2nd Prize in
“National Energy Conservation Award-
2011” by Bureau of Energy Efficiency in
Thermal Power Sector.
 CPP- VAL along with Smelter is
Awarded by Frost & Sullivan Green
Manufacturing Award-2013.
 CPP-VAL is certified ISO-50001:2011
Energy Management System (EnMS).
 CII award for “Excellence in Energy
Management-2013”
PLANT PROFILE
Largest Captive Power Plant in India
Fastest completed CPP in India.
Water Source – Hirakud Reservoir
Coal Source- Mahanadi Coal Fields
High Concentration Slurry Disposal
Hybrid ESP with SPM level <
40mg/Nm3
An ISO 9001, 14001, 50001 & OHSAS 18001
Certified Company
10/8/2013
10/8/2013
ELECTROSTATIC PRECIPITATOR
AN INTRODUCTION
10/8/2013
ESP OVERVIEW
10/8/2013
PROCESS OF PRECIPITATION
INITIAL PARTICLE
CHARGING
CORONA DISCHARGE
PARTICLE COLLECTION & REMOVAL PARTICLE CHARGING
GAS IONIZATION
OLD ESP TO HYBRID ESP
STEP TOWARDS SUSTAINABILITY
CHALLENGE
 SPM levels of all the Units were slightly higher than
the standard norms.
 Anticipated more stringent norms of emissions
(< 50 mg/Nm3) to be enforced in near future.
STATUTORY ENVIRONMENTAL NORMS
136
105
113
125 126 119 125 127
111
99 92
81
0
40
80
120
160
200
Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12
AVERAGE SPM (2011-12) Average SPM
CHALLENGE
 CPP was designed for coal of 3300 kcal / Kg and 41 % ash.
 The average GCV and Ash content of used coal was 2500 kcal / kg
& ash of 50-55 %.
 Ash has a high resistivity.
 Characteristics of coal and ash not consistent with the design.
 Reduction in the collection efficiency of ESP’s.
COAL & ASH CHARACTERSTICS
10/8/2013
BRAINSTORMING
&
IDEA GENERATION
CAUSE & EFFECT
MATERIAL
MACHINE
METHODSMEN
High Ash
High resistivity
Distribution screen
Electrode alignment
PF Coal/Ash grain size
Ash Evacuation
Control of O2
Uniform coal
feeding
Conveying air flow/pressure
Rapping cyclesTemp monitoring
ESP Controllers
Slurry disposal/SILO level control
Maintenance
practices
Ash evacuation
cycle timing
Size of Fields
SPM around 100
mg/Nm3
High flue gas
volume
Transformer sizing
High SCC
ALTERNATIVES CONSIDERED
a) Continue to run with present ESPs with ammonia dosing:
b) Going for dual conditioning system Ammonia
c) Going for Retrofitting of current ESP with addition of extra fields
d) Retrofit the ESP and install a fabric filter plant with high temperature
bags:
10/8/2013
HYBRID ESP
AN INTRODUCTION
CONCEPT OF HYBRID ESP’s
 ESP-FF hybrid precipitator is a combination of ESP & Fabric filter.
 It has an advantage of both ESP & Fabric filter.
 Gases are separated from dispersed particles by passing it through
fabric medium.
 Particles that are not able to
penetrate will remain on the
surface of medium so called
“Filter cake”.
 90% dust collection is done by
ESP fields rest by bag filters.
FABRIC FILTERS
 Fabric filters has one or more compartment
containing cylindrical fabric bags.
 Compartment system generally contain
multiple rows of bags.
 Normally service life of fabric filter is 3 to 4
years.
 Fabric filter system is fitted with high
temperature bags - Polyphenylenesulphide
(PPS).
 Low temperature bags - Polyacrylonitrile
(PAN) may also be used.
10/8/2013
HYBRID ESP - THE PROJECT
HYBRID ESP- THE PROJECT
 VAL-CPP has undergone Bag filter modification in a phased manner.
 Last two fields of ESP were removed and bag filter was installed.
 Modification completed for all the 9 units.
 EPC contractor – SEPCO.
HYBRID ESP- THE PROJECT
 Project Zero date – Nov-2011.
 Manpower involved in each unit is around 300.
 53 m3 of concreting was done.
 454 tones of steel erection.
 Timely completion of the project as per schedule.
DISMANTLING OF OLD ESP
 Top penthouse & monorail Hoist are dismantled.
 Outer roof along with Inner roof are dismantled with insulator
compartments.
 Collecting plates along with Emitters are separated out along with
suspension frame & rapping mechanism.
 Distribution plates with hopper baffles & recti formers are dismantled.
 Total 2700 Tones of structure was dismantled from Old ESP.
DISMANTLING OF OLD ESP
 Dismantling of Flue gas duct before & after ID Fan.
 ID Fan dismantling along with bearing housing, Impeller motor & support
structure.
 Rectifier Transformers along with cables & insulators are dismantled.
ERECTION OF HYBRID ESP
 Erection of outer & inner roof with roof beam.
 Commissioning of Air tanks & guide equipment.
 Erection of gas path system, pre coating pipelines , cage & bag filters
arrangement.
 ID Fans support structure installation.
 Erection of bypass duct & dampers.
ERRECTION OF HYBRID ESP
 Installation of Flue gas duct along with motor dampers.
 Installation of ID Fans with Casing ,Impeller , Rotor, Bearing house &
Expansion Joints.
 Installation of new Compressors with driers & filters.
 Insulation of total System.
GLIMPSES OF HYBRID ESP
PROJECT SAFETY
COMMIT
TOWARDS
SAFETY
ZERO LOSS
OF TIME DUE
TO INJURY
ZERO
FATALITY
DURING THE
PROJECT
SAFETY
TRAININGS &
DRILLS
DURING
PROJECT
10/8/2013
PERFORMANCE
&
EFFICIENCY
HYBRID ESP- AFTER COMMISSIONING
 Fabric filter system is fitted with high temperature bags -
Polyphenylenesulphide (PPS) were considered taking the worst scenario.
 The performance of the plant is good with emission values consistently
below the 40mg/Nm3.
Filter Plant Type : Pulse Jet
Filtration Velocity : 1.04 m/min
Bag Material : PPS (PTFE Impregnation Treatment)
Bag Quantity : 5002
Bag Specification : Dia 130 X 8065
Injection Pressure : 0.25 -0.35 MPa
HYBRID ESP- PERFORMANCE
 Reductions in SPM < 40 mg/Nm3.
 Improvement in collection efficiency and stable operation of ESP’s.
 Reduction in energy consumption of ESP’s.
 Increase in life of bag filters due to small pressure difference across filter
bags.
 Maintenance friendly.
 OPTIPOW pulse valve adopted to guarantee high efficiency and for.
stable and reliable ash removal.
 The operation of the equipment is controlled by PLC through the
temperature, pressure differential pressure, current, voltage and the
travel feedback signal.
HYBRID ESP - PERFORMANCE
127
111
99 92
81
71 66
55
47 41 45
24 22 20 23 25 26 28 24 26
0
40
80
120
160
200
Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13
Average SPM Average SPM
Before
After
10/8/2013
HYBRID ESP
O&M PRACTICES
HYBRID ESP – BAG CLEANING SYSTEM
 Fiber filter adopts differential pressure control mode for cleaning the ash
deposited on bag.
 Differential pressure of dust collector is the criterion for ash removal
from bag filters.
 Ash removal will not stop until differential pressure of bag filter drops
below the set value.
When the differential pressure of the dust
collector surpasses a setting value, PLC
will transmit a signal to the pulse
controller, then the pulse valve will
open, the compressed air in the air tank will
instantly release and enter into the filter
bag. The dust cake accumulated on the
outside will break and get loose and then
drop into dust hopper when the filter bag
expands
HYBRID ESP – OPERATION
 Amount of moist, acid and sticky dust collected on the filter bags during
the start-up phase to be minimized.
 The FF shall not be connected to the flue gas stream until coal starts to
be fired in the boiler and the thermal power achieves 80% above the
total thermal power.
 The flue gas temperature ought to be at least 20℃ above the acid dew
point.
Main monitoring Screen
HYBRID ESP – MAINTENANCE
 Regular checking of differential pressure of dust collector.
 Monitoring of gas flow.
 Checking the compressed air of pulse cleaning dust collector.
 Checking nozzle compartments and dust hopper for dust accumulations.
 When about 10% of the bags in a compartment have been blocked, all
damaged bags shall be replaced.
BEST PRACTICES
 The most common and usual problem with pulse injection FF is the
water and oil content in compressed air which is used for ash discharge
from filter bag.
 The water and oil permeates the filter material, wetting the dust, which
chokes the filter bag.
 This increases the pressure drop and finally the bag is to be replaced.
HIGH QUALITY OF COMPRESSED AIR
BEST PRACTICES
 During commissioning pre coating of bag filters is required before taking
the system into service.
 After long shutdown of the unit or if bag purging is done in shutdown
condition Pre-coating is required.
PRE COATING OF BAG FILTERS AFTER LONG SHUTDOWNS
BEST PRACTICES
 In case of tube leakages unit shutdown should be taken
immediately, otherwise pressure drop in bags may increase.
 In case of If Oil Gun is taken into service the bag filters need to be
bypassed.
 During light up or Shutdown of the Unit bag filters will only be taken into
service after removal of Oil Guns.
IMMEDIATE SHUTDOWN OF UNIT IN CASE OF TUBE LEAKAGES
THANK YOU

More Related Content

What's hot

Rourkela steel plant internship ppt
Rourkela steel plant internship pptRourkela steel plant internship ppt
Rourkela steel plant internship ppt
YasowantNayak
 
production process of Exide
production process of Exideproduction process of Exide
production process of Exide
Mayank Gupta
 
Aluminium World Journal 2013
Aluminium World Journal 2013Aluminium World Journal 2013
Aluminium World Journal 2013
Global Media Communication Ltd.
 
Electrical furnace and Substation at Tata Steel
Electrical furnace and Substation at Tata SteelElectrical furnace and Substation at Tata Steel
Electrical furnace and Substation at Tata Steelnishantrj
 
Schneider Electric
Schneider ElectricSchneider Electric
Schneider Electricsudhakar_hr
 
Vocational Training in Steel Authority of India Limited (SAIL)-Bokaro Steel P...
Vocational Training in Steel Authority of India Limited (SAIL)-Bokaro Steel P...Vocational Training in Steel Authority of India Limited (SAIL)-Bokaro Steel P...
Vocational Training in Steel Authority of India Limited (SAIL)-Bokaro Steel P...Sumit Kumar
 
Aluminum Air Battery: How Do They Work? (Plus DIY)
Aluminum Air Battery: How Do They Work? (Plus DIY)Aluminum Air Battery: How Do They Work? (Plus DIY)
Aluminum Air Battery: How Do They Work? (Plus DIY)
Dr.Raja R
 
A project report on adani power ltd.
A project report on adani power ltd.A project report on adani power ltd.
A project report on adani power ltd.
Nipranch Shah
 
Industrial Training Report on Direct Reduced Iron Plant(DRI)
Industrial Training Report on Direct Reduced Iron Plant(DRI)Industrial Training Report on Direct Reduced Iron Plant(DRI)
Industrial Training Report on Direct Reduced Iron Plant(DRI)
Shani Kumar Singh
 
Project Report on Industrial Summer Training at NTPC Simhadri
 Project Report on Industrial Summer Training at NTPC Simhadri Project Report on Industrial Summer Training at NTPC Simhadri
Project Report on Industrial Summer Training at NTPC Simhadri
Ashish Uppu
 
SUMMER TRAINING REPORT
SUMMER TRAINING REPORTSUMMER TRAINING REPORT
SUMMER TRAINING REPORTNIKHIL AGRAWAL
 
ppt on the Dcm shriram limited, kota
ppt on the Dcm shriram limited, kotappt on the Dcm shriram limited, kota
ppt on the Dcm shriram limited, kota
Yuvraj Singh
 
A Industrial Training Report On ADANI POWER LIMITED
A Industrial Training Report On  ADANI POWER LIMITEDA Industrial Training Report On  ADANI POWER LIMITED
A Industrial Training Report On ADANI POWER LIMITED
Saikat Bhandari
 
Training presentation-BHILAI STEEL PLANT
Training presentation-BHILAI STEEL PLANTTraining presentation-BHILAI STEEL PLANT
Training presentation-BHILAI STEEL PLANT
KHAGENDRA KUMAR DEWANGAN
 
Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)
Ajeet Chaurasia
 

What's hot (20)

Rourkela steel plant internship ppt
Rourkela steel plant internship pptRourkela steel plant internship ppt
Rourkela steel plant internship ppt
 
production process of Exide
production process of Exideproduction process of Exide
production process of Exide
 
Aluminium World Journal 2013
Aluminium World Journal 2013Aluminium World Journal 2013
Aluminium World Journal 2013
 
Ntpc simhadri
Ntpc simhadriNtpc simhadri
Ntpc simhadri
 
PROJECT
PROJECTPROJECT
PROJECT
 
Electrical furnace and Substation at Tata Steel
Electrical furnace and Substation at Tata SteelElectrical furnace and Substation at Tata Steel
Electrical furnace and Substation at Tata Steel
 
Schneider Electric
Schneider ElectricSchneider Electric
Schneider Electric
 
Vocational Training in Steel Authority of India Limited (SAIL)-Bokaro Steel P...
Vocational Training in Steel Authority of India Limited (SAIL)-Bokaro Steel P...Vocational Training in Steel Authority of India Limited (SAIL)-Bokaro Steel P...
Vocational Training in Steel Authority of India Limited (SAIL)-Bokaro Steel P...
 
Aluminum Air Battery: How Do They Work? (Plus DIY)
Aluminum Air Battery: How Do They Work? (Plus DIY)Aluminum Air Battery: How Do They Work? (Plus DIY)
Aluminum Air Battery: How Do They Work? (Plus DIY)
 
short Report
short Reportshort Report
short Report
 
A project report on adani power ltd.
A project report on adani power ltd.A project report on adani power ltd.
A project report on adani power ltd.
 
Industrial Training Report on Direct Reduced Iron Plant(DRI)
Industrial Training Report on Direct Reduced Iron Plant(DRI)Industrial Training Report on Direct Reduced Iron Plant(DRI)
Industrial Training Report on Direct Reduced Iron Plant(DRI)
 
Project Report on Industrial Summer Training at NTPC Simhadri
 Project Report on Industrial Summer Training at NTPC Simhadri Project Report on Industrial Summer Training at NTPC Simhadri
Project Report on Industrial Summer Training at NTPC Simhadri
 
SUMMER TRAINING REPORT
SUMMER TRAINING REPORTSUMMER TRAINING REPORT
SUMMER TRAINING REPORT
 
ppt on the Dcm shriram limited, kota
ppt on the Dcm shriram limited, kotappt on the Dcm shriram limited, kota
ppt on the Dcm shriram limited, kota
 
TATA STEEL PPT
TATA STEEL PPTTATA STEEL PPT
TATA STEEL PPT
 
A Industrial Training Report On ADANI POWER LIMITED
A Industrial Training Report On  ADANI POWER LIMITEDA Industrial Training Report On  ADANI POWER LIMITED
A Industrial Training Report On ADANI POWER LIMITED
 
Training presentation-BHILAI STEEL PLANT
Training presentation-BHILAI STEEL PLANTTraining presentation-BHILAI STEEL PLANT
Training presentation-BHILAI STEEL PLANT
 
Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)Summer Training Report Ntpc barh (ajeet)
Summer Training Report Ntpc barh (ajeet)
 
Presentation on exide
Presentation on exidePresentation on exide
Presentation on exide
 

Viewers also liked

Vedanta resources plc.
Vedanta resources plc.Vedanta resources plc.
Vedanta resources plc.
Abhay Singh
 
Vedanta
VedantaVedanta
Vedanta
Sumit Tirkey
 
Combustible Dust_Webinar version
Combustible Dust_Webinar versionCombustible Dust_Webinar version
Combustible Dust_Webinar versionScott Dame
 
Simulating pot room logistics in aluminum smelters
Simulating pot room logistics in aluminum smeltersSimulating pot room logistics in aluminum smelters
Simulating pot room logistics in aluminum smeltersjhjsmits
 
Vedantaindiaoperationssitevisit zincindiahzlpresentation-26sep2012
Vedantaindiaoperationssitevisit zincindiahzlpresentation-26sep2012Vedantaindiaoperationssitevisit zincindiahzlpresentation-26sep2012
Vedantaindiaoperationssitevisit zincindiahzlpresentation-26sep2012
Vedanta Group
 
Vedanta presentationatcreditsuisseconferenceseptember2012
Vedanta presentationatcreditsuisseconferenceseptember2012Vedanta presentationatcreditsuisseconferenceseptember2012
Vedanta presentationatcreditsuisseconferenceseptember2012
Vedanta Group
 
Vedanta Resources Plc India Operations Site Visit: Corporate Presentation
Vedanta Resources Plc India Operations Site Visit: Corporate PresentationVedanta Resources Plc India Operations Site Visit: Corporate Presentation
Vedanta Resources Plc India Operations Site Visit: Corporate PresentationVedanta Group
 
Operations Management
Operations ManagementOperations Management
Operations Management
Mayank Kashyap
 
Vedanta resources plc
Vedanta resources plcVedanta resources plc
Vedanta resources plcRS P
 
Ash problems
Ash problemsAsh problems
Ash problems
13thidiot
 
THERMAL POWER PLANT AND COAL HANDLING
THERMAL POWER PLANT AND COAL HANDLING THERMAL POWER PLANT AND COAL HANDLING
THERMAL POWER PLANT AND COAL HANDLING
AFAQAHMED JAMADAR
 
8 logistics network design
8 logistics network design8 logistics network design
8 logistics network designSurajit Goswami
 

Viewers also liked (16)

Vedanta resources plc.
Vedanta resources plc.Vedanta resources plc.
Vedanta resources plc.
 
Vedanta
VedantaVedanta
Vedanta
 
Combustible Dust_Webinar version
Combustible Dust_Webinar versionCombustible Dust_Webinar version
Combustible Dust_Webinar version
 
Simulating pot room logistics in aluminum smelters
Simulating pot room logistics in aluminum smeltersSimulating pot room logistics in aluminum smelters
Simulating pot room logistics in aluminum smelters
 
CV_DP
CV_DPCV_DP
CV_DP
 
Vedantaindiaoperationssitevisit zincindiahzlpresentation-26sep2012
Vedantaindiaoperationssitevisit zincindiahzlpresentation-26sep2012Vedantaindiaoperationssitevisit zincindiahzlpresentation-26sep2012
Vedantaindiaoperationssitevisit zincindiahzlpresentation-26sep2012
 
Vedanta presentationatcreditsuisseconferenceseptember2012
Vedanta presentationatcreditsuisseconferenceseptember2012Vedanta presentationatcreditsuisseconferenceseptember2012
Vedanta presentationatcreditsuisseconferenceseptember2012
 
Vedanta Resources Plc India Operations Site Visit: Corporate Presentation
Vedanta Resources Plc India Operations Site Visit: Corporate PresentationVedanta Resources Plc India Operations Site Visit: Corporate Presentation
Vedanta Resources Plc India Operations Site Visit: Corporate Presentation
 
VEDANTA-CAIRN DEAL
VEDANTA-CAIRN DEALVEDANTA-CAIRN DEAL
VEDANTA-CAIRN DEAL
 
Vedanta Acquired Cairn
Vedanta Acquired Cairn Vedanta Acquired Cairn
Vedanta Acquired Cairn
 
Operations Management
Operations ManagementOperations Management
Operations Management
 
vedanta cairn deal
vedanta cairn dealvedanta cairn deal
vedanta cairn deal
 
Vedanta resources plc
Vedanta resources plcVedanta resources plc
Vedanta resources plc
 
Ash problems
Ash problemsAsh problems
Ash problems
 
THERMAL POWER PLANT AND COAL HANDLING
THERMAL POWER PLANT AND COAL HANDLING THERMAL POWER PLANT AND COAL HANDLING
THERMAL POWER PLANT AND COAL HANDLING
 
8 logistics network design
8 logistics network design8 logistics network design
8 logistics network design
 

Similar to Vedanta Aluminium Ltd.

Hybrid ESP Project
Hybrid ESP ProjectHybrid ESP Project
Hybrid ESP Projectanuragpatel
 
Instrument air package
Instrument air packageInstrument air package
Instrument air package
Dipankar Maity
 
Talk on energy efficiency by ajai arora
Talk on energy efficiency  by ajai aroraTalk on energy efficiency  by ajai arora
Talk on energy efficiency by ajai arora
Ratan Kuber
 
A Guide To Fume Extraction Systems & Components
A Guide To Fume Extraction Systems & ComponentsA Guide To Fume Extraction Systems & Components
A Guide To Fume Extraction Systems & Components
Axair Fan (UK) Ltd.
 
Redesigned Filter Capsule Improves Final Filtration Assembly Design and Opera...
Redesigned Filter Capsule Improves Final Filtration Assembly Design and Opera...Redesigned Filter Capsule Improves Final Filtration Assembly Design and Opera...
Redesigned Filter Capsule Improves Final Filtration Assembly Design and Opera...
MilliporeSigma
 
Making Renewable Energy "Greener"
Making Renewable Energy "Greener"Making Renewable Energy "Greener"
Making Renewable Energy "Greener"
Justin Stover
 
J D J
J D JJ D J
J D J
jjinesh
 
Cool while saving even in humid climate areas
Cool while saving even in humid climate areasCool while saving even in humid climate areas
Cool while saving even in humid climate areas
CAREL Industries S.p.A
 
New technology for desalination
New technology for desalinationNew technology for desalination
New technology for desalinationDainik Patel
 
“STUDY AND FABRICATION OF OUTDOOR MIST/FOG COOLING SYSTEM THROUGH HIGH PRESSU...
“STUDY AND FABRICATION OF OUTDOOR MIST/FOG COOLING SYSTEM THROUGH HIGH PRESSU...“STUDY AND FABRICATION OF OUTDOOR MIST/FOG COOLING SYSTEM THROUGH HIGH PRESSU...
“STUDY AND FABRICATION OF OUTDOOR MIST/FOG COOLING SYSTEM THROUGH HIGH PRESSU...
SHAILESH SHUKLA
 
Atmospheric water generator
Atmospheric water generatorAtmospheric water generator
Atmospheric water generator
Mohammed Netarwala
 
Cleanrooms 101
Cleanrooms 101Cleanrooms 101
Cleanrooms 101
Adhitya Maulana Yusuf
 
All Energy Exhibition & Conference, Glasgow, May 2017
All Energy Exhibition & Conference, Glasgow, May 2017All Energy Exhibition & Conference, Glasgow, May 2017
All Energy Exhibition & Conference, Glasgow, May 2017
Hugo Gallagher (hugo@logis-tech.co.uk)
 
01. LIKU-TECH - PRODUCTS & SERVICES.ppt
01. LIKU-TECH - PRODUCTS & SERVICES.ppt01. LIKU-TECH - PRODUCTS & SERVICES.ppt
01. LIKU-TECH - PRODUCTS & SERVICES.ppt
AjayKrishnaM3
 

Similar to Vedanta Aluminium Ltd. (20)

Hybrid ESP Project
Hybrid ESP ProjectHybrid ESP Project
Hybrid ESP Project
 
Instrument air package
Instrument air packageInstrument air package
Instrument air package
 
Talk on energy efficiency by ajai arora
Talk on energy efficiency  by ajai aroraTalk on energy efficiency  by ajai arora
Talk on energy efficiency by ajai arora
 
A Guide To Fume Extraction Systems & Components
A Guide To Fume Extraction Systems & ComponentsA Guide To Fume Extraction Systems & Components
A Guide To Fume Extraction Systems & Components
 
Efficient Power Usage
Efficient Power UsageEfficient Power Usage
Efficient Power Usage
 
Redesigned Filter Capsule Improves Final Filtration Assembly Design and Opera...
Redesigned Filter Capsule Improves Final Filtration Assembly Design and Opera...Redesigned Filter Capsule Improves Final Filtration Assembly Design and Opera...
Redesigned Filter Capsule Improves Final Filtration Assembly Design and Opera...
 
Making Renewable Energy "Greener"
Making Renewable Energy "Greener"Making Renewable Energy "Greener"
Making Renewable Energy "Greener"
 
IWC 16-49
IWC 16-49IWC 16-49
IWC 16-49
 
DH PRESENTATION
DH PRESENTATIONDH PRESENTATION
DH PRESENTATION
 
DH PRESENTATION
DH PRESENTATIONDH PRESENTATION
DH PRESENTATION
 
J D J
J D JJ D J
J D J
 
Cool while saving even in humid climate areas
Cool while saving even in humid climate areasCool while saving even in humid climate areas
Cool while saving even in humid climate areas
 
New technology for desalination
New technology for desalinationNew technology for desalination
New technology for desalination
 
Cpg 2010
Cpg 2010Cpg 2010
Cpg 2010
 
“STUDY AND FABRICATION OF OUTDOOR MIST/FOG COOLING SYSTEM THROUGH HIGH PRESSU...
“STUDY AND FABRICATION OF OUTDOOR MIST/FOG COOLING SYSTEM THROUGH HIGH PRESSU...“STUDY AND FABRICATION OF OUTDOOR MIST/FOG COOLING SYSTEM THROUGH HIGH PRESSU...
“STUDY AND FABRICATION OF OUTDOOR MIST/FOG COOLING SYSTEM THROUGH HIGH PRESSU...
 
Atmospheric water generator
Atmospheric water generatorAtmospheric water generator
Atmospheric water generator
 
Cleanrooms 101
Cleanrooms 101Cleanrooms 101
Cleanrooms 101
 
All Energy Exhibition & Conference, Glasgow, May 2017
All Energy Exhibition & Conference, Glasgow, May 2017All Energy Exhibition & Conference, Glasgow, May 2017
All Energy Exhibition & Conference, Glasgow, May 2017
 
01. LIKU-TECH - PRODUCTS & SERVICES.ppt
01. LIKU-TECH - PRODUCTS & SERVICES.ppt01. LIKU-TECH - PRODUCTS & SERVICES.ppt
01. LIKU-TECH - PRODUCTS & SERVICES.ppt
 
Cosmodyne aspen 1000
Cosmodyne aspen 1000Cosmodyne aspen 1000
Cosmodyne aspen 1000
 

More from engineeringwatch

Eduindia UPTU Portfolio
Eduindia UPTU PortfolioEduindia UPTU Portfolio
Eduindia UPTU Portfolio
engineeringwatch
 
Engineering Watch Fellowship Portfolio
Engineering Watch Fellowship PortfolioEngineering Watch Fellowship Portfolio
Engineering Watch Fellowship Portfolio
engineeringwatch
 
Eduindia Portfolio
Eduindia PortfolioEduindia Portfolio
Eduindia Portfolio
engineeringwatch
 
Engineering Watch Fellowship Questionnaire Booklet
Engineering Watch Fellowship Questionnaire BookletEngineering Watch Fellowship Questionnaire Booklet
Engineering Watch Fellowship Questionnaire Booklet
engineeringwatch
 
Edu india presentation
Edu india presentationEdu india presentation
Edu india presentation
engineeringwatch
 
Presentation :: Curtain Raiser :: Re-Engineering India 2014
Presentation :: Curtain Raiser :: Re-Engineering India 2014 Presentation :: Curtain Raiser :: Re-Engineering India 2014
Presentation :: Curtain Raiser :: Re-Engineering India 2014
engineeringwatch
 
A novel drip irrigation system
A novel drip irrigation systemA novel drip irrigation system
A novel drip irrigation system
engineeringwatch
 
Wankhede nomination 31-08-2013
Wankhede nomination   31-08-2013Wankhede nomination   31-08-2013
Wankhede nomination 31-08-2013
engineeringwatch
 
The capital nomination 31-08-2013
The capital nomination   31-08-2013The capital nomination   31-08-2013
The capital nomination 31-08-2013
engineeringwatch
 
Globus infocom limited
Globus infocom limitedGlobus infocom limited
Globus infocom limited
engineeringwatch
 
Ongc tripura power company limited
Ongc tripura power company limitedOngc tripura power company limited
Ongc tripura power company limitedengineeringwatch
 
Bharatiya nabhikiya vidyut nigam limited (bhavini)
Bharatiya nabhikiya vidyut nigam limited (bhavini)Bharatiya nabhikiya vidyut nigam limited (bhavini)
Bharatiya nabhikiya vidyut nigam limited (bhavini)
engineeringwatch
 
Hll lifecare ltd.
Hll lifecare ltd.Hll lifecare ltd.
Hll lifecare ltd.
engineeringwatch
 
Csir cftri
Csir cftriCsir cftri
Csir cftri
engineeringwatch
 
Beml limited
Beml limitedBeml limited
Beml limited
engineeringwatch
 
Beml limited
Beml limitedBeml limited
Beml limited
engineeringwatch
 
Larsen & toubro constructions
Larsen & toubro constructionsLarsen & toubro constructions
Larsen & toubro constructionsengineeringwatch
 
Hscc (india) ltd
Hscc (india) ltdHscc (india) ltd
Hscc (india) ltd
engineeringwatch
 
Airports authority of india,kolkata
Airports authority of india,kolkataAirports authority of india,kolkata
Airports authority of india,kolkataengineeringwatch
 

More from engineeringwatch (20)

Eduindia UPTU Portfolio
Eduindia UPTU PortfolioEduindia UPTU Portfolio
Eduindia UPTU Portfolio
 
Engineering Watch Fellowship Portfolio
Engineering Watch Fellowship PortfolioEngineering Watch Fellowship Portfolio
Engineering Watch Fellowship Portfolio
 
Eduindia Portfolio
Eduindia PortfolioEduindia Portfolio
Eduindia Portfolio
 
Engineering Watch Fellowship Questionnaire Booklet
Engineering Watch Fellowship Questionnaire BookletEngineering Watch Fellowship Questionnaire Booklet
Engineering Watch Fellowship Questionnaire Booklet
 
Edu india presentation
Edu india presentationEdu india presentation
Edu india presentation
 
Presentation :: Curtain Raiser :: Re-Engineering India 2014
Presentation :: Curtain Raiser :: Re-Engineering India 2014 Presentation :: Curtain Raiser :: Re-Engineering India 2014
Presentation :: Curtain Raiser :: Re-Engineering India 2014
 
A novel drip irrigation system
A novel drip irrigation systemA novel drip irrigation system
A novel drip irrigation system
 
Wankhede nomination 31-08-2013
Wankhede nomination   31-08-2013Wankhede nomination   31-08-2013
Wankhede nomination 31-08-2013
 
The capital nomination 31-08-2013
The capital nomination   31-08-2013The capital nomination   31-08-2013
The capital nomination 31-08-2013
 
Globus infocom limited
Globus infocom limitedGlobus infocom limited
Globus infocom limited
 
Ongc tripura power company limited
Ongc tripura power company limitedOngc tripura power company limited
Ongc tripura power company limited
 
Bharatiya nabhikiya vidyut nigam limited (bhavini)
Bharatiya nabhikiya vidyut nigam limited (bhavini)Bharatiya nabhikiya vidyut nigam limited (bhavini)
Bharatiya nabhikiya vidyut nigam limited (bhavini)
 
Hll lifecare ltd.
Hll lifecare ltd.Hll lifecare ltd.
Hll lifecare ltd.
 
Csir cftri
Csir cftriCsir cftri
Csir cftri
 
Hll lifecare ltd.
Hll lifecare ltd.Hll lifecare ltd.
Hll lifecare ltd.
 
Beml limited
Beml limitedBeml limited
Beml limited
 
Beml limited
Beml limitedBeml limited
Beml limited
 
Larsen & toubro constructions
Larsen & toubro constructionsLarsen & toubro constructions
Larsen & toubro constructions
 
Hscc (india) ltd
Hscc (india) ltdHscc (india) ltd
Hscc (india) ltd
 
Airports authority of india,kolkata
Airports authority of india,kolkataAirports authority of india,kolkata
Airports authority of india,kolkata
 

Recently uploaded

GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
Neo4j
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
BookNet Canada
 
By Design, not by Accident - Agile Venture Bolzano 2024
By Design, not by Accident - Agile Venture Bolzano 2024By Design, not by Accident - Agile Venture Bolzano 2024
By Design, not by Accident - Agile Venture Bolzano 2024
Pierluigi Pugliese
 
National Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practicesNational Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practices
Quotidiano Piemontese
 
Elevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object CalisthenicsElevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object Calisthenics
Dorra BARTAGUIZ
 
The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
Laura Byrne
 
A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...
sonjaschweigert1
 
PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)
Ralf Eggert
 
UiPath Test Automation using UiPath Test Suite series, part 5
UiPath Test Automation using UiPath Test Suite series, part 5UiPath Test Automation using UiPath Test Suite series, part 5
UiPath Test Automation using UiPath Test Suite series, part 5
DianaGray10
 
Free Complete Python - A step towards Data Science
Free Complete Python - A step towards Data ScienceFree Complete Python - A step towards Data Science
Free Complete Python - A step towards Data Science
RinaMondal9
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
KatiaHIMEUR1
 
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptx
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptxSecstrike : Reverse Engineering & Pwnable tools for CTF.pptx
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptx
nkrafacyberclub
 
Elizabeth Buie - Older adults: Are we really designing for our future selves?
Elizabeth Buie - Older adults: Are we really designing for our future selves?Elizabeth Buie - Older adults: Are we really designing for our future selves?
Elizabeth Buie - Older adults: Are we really designing for our future selves?
Nexer Digital
 
Uni Systems Copilot event_05062024_C.Vlachos.pdf
Uni Systems Copilot event_05062024_C.Vlachos.pdfUni Systems Copilot event_05062024_C.Vlachos.pdf
Uni Systems Copilot event_05062024_C.Vlachos.pdf
Uni Systems S.M.S.A.
 
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdfObservability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Paige Cruz
 
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
SOFTTECHHUB
 
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
James Anderson
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
Jemma Hussein Allen
 
Epistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI supportEpistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI support
Alan Dix
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Albert Hoitingh
 

Recently uploaded (20)

GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
GraphSummit Singapore | Graphing Success: Revolutionising Organisational Stru...
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
 
By Design, not by Accident - Agile Venture Bolzano 2024
By Design, not by Accident - Agile Venture Bolzano 2024By Design, not by Accident - Agile Venture Bolzano 2024
By Design, not by Accident - Agile Venture Bolzano 2024
 
National Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practicesNational Security Agency - NSA mobile device best practices
National Security Agency - NSA mobile device best practices
 
Elevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object CalisthenicsElevating Tactical DDD Patterns Through Object Calisthenics
Elevating Tactical DDD Patterns Through Object Calisthenics
 
The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
 
A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...A tale of scale & speed: How the US Navy is enabling software delivery from l...
A tale of scale & speed: How the US Navy is enabling software delivery from l...
 
PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)
 
UiPath Test Automation using UiPath Test Suite series, part 5
UiPath Test Automation using UiPath Test Suite series, part 5UiPath Test Automation using UiPath Test Suite series, part 5
UiPath Test Automation using UiPath Test Suite series, part 5
 
Free Complete Python - A step towards Data Science
Free Complete Python - A step towards Data ScienceFree Complete Python - A step towards Data Science
Free Complete Python - A step towards Data Science
 
Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !Securing your Kubernetes cluster_ a step-by-step guide to success !
Securing your Kubernetes cluster_ a step-by-step guide to success !
 
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptx
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptxSecstrike : Reverse Engineering & Pwnable tools for CTF.pptx
Secstrike : Reverse Engineering & Pwnable tools for CTF.pptx
 
Elizabeth Buie - Older adults: Are we really designing for our future selves?
Elizabeth Buie - Older adults: Are we really designing for our future selves?Elizabeth Buie - Older adults: Are we really designing for our future selves?
Elizabeth Buie - Older adults: Are we really designing for our future selves?
 
Uni Systems Copilot event_05062024_C.Vlachos.pdf
Uni Systems Copilot event_05062024_C.Vlachos.pdfUni Systems Copilot event_05062024_C.Vlachos.pdf
Uni Systems Copilot event_05062024_C.Vlachos.pdf
 
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdfObservability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
Observability Concepts EVERY Developer Should Know -- DeveloperWeek Europe.pdf
 
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
Why You Should Replace Windows 11 with Nitrux Linux 3.5.0 for enhanced perfor...
 
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...
 
The Future of Platform Engineering
The Future of Platform EngineeringThe Future of Platform Engineering
The Future of Platform Engineering
 
Epistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI supportEpistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI support
 
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
Encryption in Microsoft 365 - ExpertsLive Netherlands 2024
 

Vedanta Aluminium Ltd.

  • 1.
  • 2. INDIA ODISHA PLANT SITE CPP VAL – PLANT LOCATION 10/8/2013
  • 3. AWARDS & RECOGNITION  CPP-VAL has been Awarded 1st Prize in “National Energy Conservation Award- 2012” by Bureau of Energy Efficiency in Thermal Power Sector.  CPP-VAL was Awarded 2nd Prize in “National Energy Conservation Award- 2011” by Bureau of Energy Efficiency in Thermal Power Sector.  CPP- VAL along with Smelter is Awarded by Frost & Sullivan Green Manufacturing Award-2013.  CPP-VAL is certified ISO-50001:2011 Energy Management System (EnMS).  CII award for “Excellence in Energy Management-2013”
  • 4. PLANT PROFILE Largest Captive Power Plant in India Fastest completed CPP in India. Water Source – Hirakud Reservoir Coal Source- Mahanadi Coal Fields High Concentration Slurry Disposal Hybrid ESP with SPM level < 40mg/Nm3 An ISO 9001, 14001, 50001 & OHSAS 18001 Certified Company 10/8/2013
  • 7. 10/8/2013 PROCESS OF PRECIPITATION INITIAL PARTICLE CHARGING CORONA DISCHARGE PARTICLE COLLECTION & REMOVAL PARTICLE CHARGING GAS IONIZATION
  • 8. OLD ESP TO HYBRID ESP STEP TOWARDS SUSTAINABILITY
  • 9. CHALLENGE  SPM levels of all the Units were slightly higher than the standard norms.  Anticipated more stringent norms of emissions (< 50 mg/Nm3) to be enforced in near future. STATUTORY ENVIRONMENTAL NORMS 136 105 113 125 126 119 125 127 111 99 92 81 0 40 80 120 160 200 Apr-11 May-11 Jun-11 Jul-11 Aug-11 Sep-11 Oct-11 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 AVERAGE SPM (2011-12) Average SPM
  • 10. CHALLENGE  CPP was designed for coal of 3300 kcal / Kg and 41 % ash.  The average GCV and Ash content of used coal was 2500 kcal / kg & ash of 50-55 %.  Ash has a high resistivity.  Characteristics of coal and ash not consistent with the design.  Reduction in the collection efficiency of ESP’s. COAL & ASH CHARACTERSTICS
  • 12. CAUSE & EFFECT MATERIAL MACHINE METHODSMEN High Ash High resistivity Distribution screen Electrode alignment PF Coal/Ash grain size Ash Evacuation Control of O2 Uniform coal feeding Conveying air flow/pressure Rapping cyclesTemp monitoring ESP Controllers Slurry disposal/SILO level control Maintenance practices Ash evacuation cycle timing Size of Fields SPM around 100 mg/Nm3 High flue gas volume Transformer sizing High SCC
  • 13. ALTERNATIVES CONSIDERED a) Continue to run with present ESPs with ammonia dosing: b) Going for dual conditioning system Ammonia c) Going for Retrofitting of current ESP with addition of extra fields d) Retrofit the ESP and install a fabric filter plant with high temperature bags:
  • 15. CONCEPT OF HYBRID ESP’s  ESP-FF hybrid precipitator is a combination of ESP & Fabric filter.  It has an advantage of both ESP & Fabric filter.  Gases are separated from dispersed particles by passing it through fabric medium.  Particles that are not able to penetrate will remain on the surface of medium so called “Filter cake”.  90% dust collection is done by ESP fields rest by bag filters.
  • 16. FABRIC FILTERS  Fabric filters has one or more compartment containing cylindrical fabric bags.  Compartment system generally contain multiple rows of bags.  Normally service life of fabric filter is 3 to 4 years.  Fabric filter system is fitted with high temperature bags - Polyphenylenesulphide (PPS).  Low temperature bags - Polyacrylonitrile (PAN) may also be used.
  • 17. 10/8/2013 HYBRID ESP - THE PROJECT
  • 18. HYBRID ESP- THE PROJECT  VAL-CPP has undergone Bag filter modification in a phased manner.  Last two fields of ESP were removed and bag filter was installed.  Modification completed for all the 9 units.  EPC contractor – SEPCO.
  • 19. HYBRID ESP- THE PROJECT  Project Zero date – Nov-2011.  Manpower involved in each unit is around 300.  53 m3 of concreting was done.  454 tones of steel erection.  Timely completion of the project as per schedule.
  • 20. DISMANTLING OF OLD ESP  Top penthouse & monorail Hoist are dismantled.  Outer roof along with Inner roof are dismantled with insulator compartments.  Collecting plates along with Emitters are separated out along with suspension frame & rapping mechanism.  Distribution plates with hopper baffles & recti formers are dismantled.  Total 2700 Tones of structure was dismantled from Old ESP.
  • 21. DISMANTLING OF OLD ESP  Dismantling of Flue gas duct before & after ID Fan.  ID Fan dismantling along with bearing housing, Impeller motor & support structure.  Rectifier Transformers along with cables & insulators are dismantled.
  • 22. ERECTION OF HYBRID ESP  Erection of outer & inner roof with roof beam.  Commissioning of Air tanks & guide equipment.  Erection of gas path system, pre coating pipelines , cage & bag filters arrangement.  ID Fans support structure installation.  Erection of bypass duct & dampers.
  • 23. ERRECTION OF HYBRID ESP  Installation of Flue gas duct along with motor dampers.  Installation of ID Fans with Casing ,Impeller , Rotor, Bearing house & Expansion Joints.  Installation of new Compressors with driers & filters.  Insulation of total System.
  • 25. PROJECT SAFETY COMMIT TOWARDS SAFETY ZERO LOSS OF TIME DUE TO INJURY ZERO FATALITY DURING THE PROJECT SAFETY TRAININGS & DRILLS DURING PROJECT
  • 27. HYBRID ESP- AFTER COMMISSIONING  Fabric filter system is fitted with high temperature bags - Polyphenylenesulphide (PPS) were considered taking the worst scenario.  The performance of the plant is good with emission values consistently below the 40mg/Nm3. Filter Plant Type : Pulse Jet Filtration Velocity : 1.04 m/min Bag Material : PPS (PTFE Impregnation Treatment) Bag Quantity : 5002 Bag Specification : Dia 130 X 8065 Injection Pressure : 0.25 -0.35 MPa
  • 28. HYBRID ESP- PERFORMANCE  Reductions in SPM < 40 mg/Nm3.  Improvement in collection efficiency and stable operation of ESP’s.  Reduction in energy consumption of ESP’s.  Increase in life of bag filters due to small pressure difference across filter bags.  Maintenance friendly.  OPTIPOW pulse valve adopted to guarantee high efficiency and for. stable and reliable ash removal.  The operation of the equipment is controlled by PLC through the temperature, pressure differential pressure, current, voltage and the travel feedback signal.
  • 29. HYBRID ESP - PERFORMANCE 127 111 99 92 81 71 66 55 47 41 45 24 22 20 23 25 26 28 24 26 0 40 80 120 160 200 Nov-11 Dec-11 Jan-12 Feb-12 Mar-12 Apr-12 May-12 Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12 Dec-12 Jan-13 Feb-13 Mar-13 Apr-13 May-13 Jun-13 Average SPM Average SPM Before After
  • 31. HYBRID ESP – BAG CLEANING SYSTEM  Fiber filter adopts differential pressure control mode for cleaning the ash deposited on bag.  Differential pressure of dust collector is the criterion for ash removal from bag filters.  Ash removal will not stop until differential pressure of bag filter drops below the set value. When the differential pressure of the dust collector surpasses a setting value, PLC will transmit a signal to the pulse controller, then the pulse valve will open, the compressed air in the air tank will instantly release and enter into the filter bag. The dust cake accumulated on the outside will break and get loose and then drop into dust hopper when the filter bag expands
  • 32. HYBRID ESP – OPERATION  Amount of moist, acid and sticky dust collected on the filter bags during the start-up phase to be minimized.  The FF shall not be connected to the flue gas stream until coal starts to be fired in the boiler and the thermal power achieves 80% above the total thermal power.  The flue gas temperature ought to be at least 20℃ above the acid dew point. Main monitoring Screen
  • 33. HYBRID ESP – MAINTENANCE  Regular checking of differential pressure of dust collector.  Monitoring of gas flow.  Checking the compressed air of pulse cleaning dust collector.  Checking nozzle compartments and dust hopper for dust accumulations.  When about 10% of the bags in a compartment have been blocked, all damaged bags shall be replaced.
  • 34. BEST PRACTICES  The most common and usual problem with pulse injection FF is the water and oil content in compressed air which is used for ash discharge from filter bag.  The water and oil permeates the filter material, wetting the dust, which chokes the filter bag.  This increases the pressure drop and finally the bag is to be replaced. HIGH QUALITY OF COMPRESSED AIR
  • 35. BEST PRACTICES  During commissioning pre coating of bag filters is required before taking the system into service.  After long shutdown of the unit or if bag purging is done in shutdown condition Pre-coating is required. PRE COATING OF BAG FILTERS AFTER LONG SHUTDOWNS
  • 36. BEST PRACTICES  In case of tube leakages unit shutdown should be taken immediately, otherwise pressure drop in bags may increase.  In case of If Oil Gun is taken into service the bag filters need to be bypassed.  During light up or Shutdown of the Unit bag filters will only be taken into service after removal of Oil Guns. IMMEDIATE SHUTDOWN OF UNIT IN CASE OF TUBE LEAKAGES