VALUE
ANALYSIS II
MANUFACTURING
HOURS
Suresh T
ssuresh.t24@gmail.com
EXAMPLE PLANNED
Procurement cost:-
Nuts and grips =
Rs.50/set
Material for handle
& weight =
Rs.450/set
Assembly Hours:-
Weight lifter =
15mins/set
Machining hours:-
Handle 1st opr -
40mins/set
Handle 2nd opr –
20mins/set
Packing and transit
cost:-
= Rs.75 /set
Marketing get
the order of
500 Weight
lifting sets for
the price
Rs.2,900/set.
Then cost is
issued
Rs.2,500/Set
to costing
department.
MACHINING HOURS
EXECUTION
Capacity assessment
check
This is the process to
check
% of utilization of
machine hours
Hours Allocation
The hours to be allocated
based on the priority
quantity. Maybe
Monthly/Weekly.
Daily Plan
Daily plan need to be
updated to operators
PLANNING - Capacity assessment
check
Capacity assessment check
S.no Description Project Qty
Conv. Lathe (1st opr)
CNC Lathe (2nd opr)
C.T (Mins) Hrs.Required
C.T
(Mins) Hrs.Required
1Handle K14T 250 40 166.66 20 83.33
Total 250 167 83.5
Available Hrs per Month (Working
hours 860 Mins ie., two shifts *24
days)
344 344
Considering 15% of losses due to M/c
break down, Operator absence,
Setting, unplanned meeting etc.,
51 51
Net available Hrs 293 293
% of hours to be utilizied/ Month 57% 28%
PLANNING – Hours allocation and Daily
plan
Hours Allocation - APR'17
S.no Descrption Project Qty
Conv.Lathe CNC Machining
Plan (Hrs)
Actual
(Hrs) Plan (Hrs) Actual (Hrs)
1Handle K14T 250 167 83.5
2XXX XX 120 80 68
3YYY YY 80 48 74
4ZZZ ZZ 90 - 70
Total 295 295.5
Daily Plan 1st
Shift 01-04-2017
Machine Description Project Operation Available Mins Plan qty Achieve qty
Conv.Lathe Handle K14T 1st 430 10.75
CNC Lathe Handle K14T 2nd 430 21.5
MACHINING HOURS
MONITOR
Job Card
Operator should enter the
daily activities
Review
The same will be
reviewed by the
supervisor
Efficiency
Efficiency calculation to
be done
PRODUCTION
PLAN VS ACTUAL
JOB CARD
MACHINE SHOP JOB CARD
Machine:Conv.Lathe Date:
Shift Part Description Project Operation
Prod
Qty
RW
Qty
Rej.
Qty
Operator
Name & Sign
Supervisor
Name & Sign
1st Handle K14T 1st 8 - - Kamlakannan
2nd Handle K14T 1st 9.5 1 - Rajendran
Operations: 1st, 2nd, 3rd, 4th, Serr (Serration), BM (Blue matching) ,
SF(Semi finish)
SFF (Semi finish finished).
Remarks:
1) Front side
MACHINE SHOP JOB CARD
Shift
Time
shortcu
ts
Start
time
End
time
Total
time
Review by Shift
Time
Shortcut
s
Start
time
End
time
Total
time
Review by
1st SE 08:00 08:30 30 2nd PR 16:45 00:45 380
PR 08:30 14:00 235 TI 22:00 22:45 45
MB 14:00 15:20 80
PR 15:20 16:45 85
PR- Production time, CT- Cycle time, RW- Rework time, SE- Setting time,MB- Breakdown/ Power cut, TI-
Tool/fixture issue, NL- No load, No- No operator, OT- Others
Remarks:
EFFICIENCY CALCULATION
Shift
Machi
ne No
Operat
or
name
Part
Description
Projec
t
Oper
ation
Prd
n.Qt
y
Rw.
Qty
Avl.
Tim
e
Utili
zed
time
Loss time in
Min.
Down Time in
Min.
Machine Utilized
Efficiency
Overall Shift efficiency
Set
ting
Too
l/
Fixt
.
Oth
ers
Bre
ak
do
wn
No
ope
rat
or
No
load
Std.Cyc
le Time
Std.
Prodn
time
%
Acce
pted
Qty
Utiliz
ed
Quail
ty
OSE
in %
1
s
t
Conv
Lathe
Kamal
kanna
n
Handle K14T 1st 8
430 350
30
80
40 320
74% 8.00 0.74 1.00 74.000
0
2
n
d
Conv
Lathe
Rajend
ran
Handle K14T 1st 9.5 1
430 425
45 40 380
88% 8.50 0.88 0.81 71.240
0
PLAN vs ACTUAL
Daily Plan 01-04-2017
Shift Machine Description Project Operation
Available
Mins Plan qty
Achieve
qty
1st Conv.Lathe Handle K14T 1st 430 10.75 8
2nd Conv.Lathe Handle K14T 1st 430 10.75 8.5
Setting time Break down Tool issue
30
80
45
Loss time in mins on 1/Apr/17
Cycle time Actual Min
40
52
Actual cycle time on 1-Apr/
Component
EXAMPLE ACHIEVED
Procurement cost:-
Nuts and grips =
Rs.48.5/set
Material for handle
& weight =
Rs.452/set
Assembly Hours:-
Weight lifter =
17mins/set
Machining hours:-
Handle 1st opr -
46mins
Handle 2nd opr –
24mins
Packing and transit
cost:-
= Rs.72/sets
Planned -
Rs.2,500/Set
Achieved-
Rs.2,851/set
Monitor tool:-
EBS
MANUAL XLS
OEE
Etc..,

More Related Content

What's hot

Motion and time study english
Motion and time study englishMotion and time study english
Motion and time study englishNorhan Abd Elaziz
 
Cold forming of austenitic stainless steel tubes
Cold forming of austenitic stainless steel tubesCold forming of austenitic stainless steel tubes
Cold forming of austenitic stainless steel tubesBPrajapati
 
Line balancing example
Line balancing exampleLine balancing example
Line balancing examplePrakash Kale
 
9.INTRODUCTION TO CONSTRUCTION MANAGEMENT (ACE) GTU
9.INTRODUCTION TO CONSTRUCTION MANAGEMENT (ACE) GTU9.INTRODUCTION TO CONSTRUCTION MANAGEMENT (ACE) GTU
9.INTRODUCTION TO CONSTRUCTION MANAGEMENT (ACE) GTUVATSAL PATEL
 
Sequential Models - Meaning, assumptions, Types and Problems
Sequential Models - Meaning, assumptions, Types and ProblemsSequential Models - Meaning, assumptions, Types and Problems
Sequential Models - Meaning, assumptions, Types and ProblemsSundar B N
 

What's hot (9)

Motion and time study english
Motion and time study englishMotion and time study english
Motion and time study english
 
Cold forming of austenitic stainless steel tubes
Cold forming of austenitic stainless steel tubesCold forming of austenitic stainless steel tubes
Cold forming of austenitic stainless steel tubes
 
1. MIND MAP FINAL
1. MIND MAP FINAL1. MIND MAP FINAL
1. MIND MAP FINAL
 
Cutting speed and feed
Cutting speed and feedCutting speed and feed
Cutting speed and feed
 
Line balancing example
Line balancing exampleLine balancing example
Line balancing example
 
rate analysis
rate analysisrate analysis
rate analysis
 
9.INTRODUCTION TO CONSTRUCTION MANAGEMENT (ACE) GTU
9.INTRODUCTION TO CONSTRUCTION MANAGEMENT (ACE) GTU9.INTRODUCTION TO CONSTRUCTION MANAGEMENT (ACE) GTU
9.INTRODUCTION TO CONSTRUCTION MANAGEMENT (ACE) GTU
 
Sequential Models - Meaning, assumptions, Types and Problems
Sequential Models - Meaning, assumptions, Types and ProblemsSequential Models - Meaning, assumptions, Types and Problems
Sequential Models - Meaning, assumptions, Types and Problems
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
 

Similar to Value analysis 2

CIM report - final
CIM report - finalCIM report - final
CIM report - finalPraveen S R
 
ZBC in commodities.ppt
ZBC in commodities.pptZBC in commodities.ppt
ZBC in commodities.pptSoulmananIndia
 
blastinginprovementtechniques-131019092354-phpapp01 (1).pdf
blastinginprovementtechniques-131019092354-phpapp01 (1).pdfblastinginprovementtechniques-131019092354-phpapp01 (1).pdf
blastinginprovementtechniques-131019092354-phpapp01 (1).pdf20JE0369GAURAVKUMAR
 
Application Of Workstudy
Application Of WorkstudyApplication Of Workstudy
Application Of Workstudybejayrocks
 
IRJET- Design and Fabrication of Material Handling Trolley
IRJET- Design and Fabrication of Material Handling TrolleyIRJET- Design and Fabrication of Material Handling Trolley
IRJET- Design and Fabrication of Material Handling TrolleyIRJET Journal
 
SAM_METHOD 1 _Training Presentation .pptx.pdf
SAM_METHOD 1 _Training Presentation .pptx.pdfSAM_METHOD 1 _Training Presentation .pptx.pdf
SAM_METHOD 1 _Training Presentation .pptx.pdfhasansyeadbuft
 
Blasting inprovement techniques
Blasting inprovement techniquesBlasting inprovement techniques
Blasting inprovement techniquesKrishna Deo Prasad
 
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET Journal
 
Case study electronics industry
Case study   electronics industryCase study   electronics industry
Case study electronics industryGanesh TN
 
B. Manufacturing Engineering.docx
B. Manufacturing Engineering.docxB. Manufacturing Engineering.docx
B. Manufacturing Engineering.docxssusera85eeb1
 
parth presentation
parth presentationparth presentation
parth presentationParth Gandhi
 

Similar to Value analysis 2 (20)

Equipment mgmt 4.pdf
Equipment mgmt 4.pdfEquipment mgmt 4.pdf
Equipment mgmt 4.pdf
 
CIM report - final
CIM report - finalCIM report - final
CIM report - final
 
CIM report - final
CIM report - finalCIM report - final
CIM report - final
 
CIM Report
CIM ReportCIM Report
CIM Report
 
ZBC in commodities.ppt
ZBC in commodities.pptZBC in commodities.ppt
ZBC in commodities.ppt
 
blastinginprovementtechniques-131019092354-phpapp01 (1).pdf
blastinginprovementtechniques-131019092354-phpapp01 (1).pdfblastinginprovementtechniques-131019092354-phpapp01 (1).pdf
blastinginprovementtechniques-131019092354-phpapp01 (1).pdf
 
SMC CFT 2012-13-IInd Half.
SMC CFT 2012-13-IInd Half.SMC CFT 2012-13-IInd Half.
SMC CFT 2012-13-IInd Half.
 
Application Of Workstudy
Application Of WorkstudyApplication Of Workstudy
Application Of Workstudy
 
K012556370
K012556370K012556370
K012556370
 
K012556370
K012556370K012556370
K012556370
 
IRJET- Design and Fabrication of Material Handling Trolley
IRJET- Design and Fabrication of Material Handling TrolleyIRJET- Design and Fabrication of Material Handling Trolley
IRJET- Design and Fabrication of Material Handling Trolley
 
zone 3 ppt.pptx
zone 3 ppt.pptxzone 3 ppt.pptx
zone 3 ppt.pptx
 
SAM_METHOD 1 _Training Presentation .pptx.pdf
SAM_METHOD 1 _Training Presentation .pptx.pdfSAM_METHOD 1 _Training Presentation .pptx.pdf
SAM_METHOD 1 _Training Presentation .pptx.pdf
 
Blasting inprovement techniques
Blasting inprovement techniquesBlasting inprovement techniques
Blasting inprovement techniques
 
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
 
Project control
Project controlProject control
Project control
 
Case study electronics industry
Case study   electronics industryCase study   electronics industry
Case study electronics industry
 
Work measurement
Work measurementWork measurement
Work measurement
 
B. Manufacturing Engineering.docx
B. Manufacturing Engineering.docxB. Manufacturing Engineering.docx
B. Manufacturing Engineering.docx
 
parth presentation
parth presentationparth presentation
parth presentation
 

More from suresh t

INDIVIDUALITY
INDIVIDUALITYINDIVIDUALITY
INDIVIDUALITYsuresh t
 
S analysis
S analysisS analysis
S analysissuresh t
 
Negative will make you Positive
Negative will make you PositiveNegative will make you Positive
Negative will make you Positivesuresh t
 
Value analysis
Value analysisValue analysis
Value analysissuresh t
 
Vendor/Supplier rating
Vendor/Supplier ratingVendor/Supplier rating
Vendor/Supplier ratingsuresh t
 
Five Don't think
Five Don't think Five Don't think
Five Don't think suresh t
 
Inspiring leader
Inspiring leaderInspiring leader
Inspiring leadersuresh t
 
Most important tool for manufacturing industries
Most important tool for manufacturing industriesMost important tool for manufacturing industries
Most important tool for manufacturing industriessuresh t
 

More from suresh t (9)

INDIVIDUALITY
INDIVIDUALITYINDIVIDUALITY
INDIVIDUALITY
 
S analysis
S analysisS analysis
S analysis
 
Negative will make you Positive
Negative will make you PositiveNegative will make you Positive
Negative will make you Positive
 
Value analysis
Value analysisValue analysis
Value analysis
 
Vendor/Supplier rating
Vendor/Supplier ratingVendor/Supplier rating
Vendor/Supplier rating
 
Five Don't think
Five Don't think Five Don't think
Five Don't think
 
Leader
LeaderLeader
Leader
 
Inspiring leader
Inspiring leaderInspiring leader
Inspiring leader
 
Most important tool for manufacturing industries
Most important tool for manufacturing industriesMost important tool for manufacturing industries
Most important tool for manufacturing industries
 

Recently uploaded

fluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answerfluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answerapareshmondalnita
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Aryaabh.arya
 
KIT-601 Lecture Notes-UNIT-3.pdf Mining Data Stream
KIT-601 Lecture Notes-UNIT-3.pdf Mining Data StreamKIT-601 Lecture Notes-UNIT-3.pdf Mining Data Stream
KIT-601 Lecture Notes-UNIT-3.pdf Mining Data StreamDr. Radhey Shyam
 
Natalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in KrakówNatalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in Krakówbim.edu.pl
 
Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfAbrahamGadissa
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationRobbie Edward Sayers
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...Amil baba
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdfKamal Acharya
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.PrashantGoswami42
 
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and ClusteringKIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and ClusteringDr. Radhey Shyam
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopEmre Günaydın
 
fundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projectionfundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projectionjeevanprasad8
 
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringC Sai Kiran
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxR&R Consult
 
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfRESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfKamal Acharya
 
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdfONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdfKamal Acharya
 
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWINGBRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWINGKOUSTAV SARKAR
 
Pharmacy management system project report..pdf
Pharmacy management system project report..pdfPharmacy management system project report..pdf
Pharmacy management system project report..pdfKamal Acharya
 
Peek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdfPeek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdfAyahmorsy
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234AafreenAbuthahir2
 

Recently uploaded (20)

fluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answerfluid mechanics gate notes . gate all pyqs answer
fluid mechanics gate notes . gate all pyqs answer
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
KIT-601 Lecture Notes-UNIT-3.pdf Mining Data Stream
KIT-601 Lecture Notes-UNIT-3.pdf Mining Data StreamKIT-601 Lecture Notes-UNIT-3.pdf Mining Data Stream
KIT-601 Lecture Notes-UNIT-3.pdf Mining Data Stream
 
Natalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in KrakówNatalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in Kraków
 
Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
NO1 Pandit Amil Baba In Bahawalpur, Sargodha, Sialkot, Sheikhupura, Rahim Yar...
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and ClusteringKIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
KIT-601 Lecture Notes-UNIT-4.pdf Frequent Itemsets and Clustering
 
İTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering WorkshopİTÜ CAD and Reverse Engineering Workshop
İTÜ CAD and Reverse Engineering Workshop
 
fundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projectionfundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projection
 
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical EngineeringIntroduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
Introduction to Machine Learning Unit-5 Notes for II-II Mechanical Engineering
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdfRESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
RESORT MANAGEMENT AND RESERVATION SYSTEM PROJECT REPORT.pdf
 
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdfONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
ONLINE VEHICLE RENTAL SYSTEM PROJECT REPORT.pdf
 
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWINGBRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
BRAKING SYSTEM IN INDIAN RAILWAY AutoCAD DRAWING
 
Pharmacy management system project report..pdf
Pharmacy management system project report..pdfPharmacy management system project report..pdf
Pharmacy management system project report..pdf
 
Peek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdfPeek implant persentation - Copy (1).pdf
Peek implant persentation - Copy (1).pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 

Value analysis 2

  • 2. EXAMPLE PLANNED Procurement cost:- Nuts and grips = Rs.50/set Material for handle & weight = Rs.450/set Assembly Hours:- Weight lifter = 15mins/set Machining hours:- Handle 1st opr - 40mins/set Handle 2nd opr – 20mins/set Packing and transit cost:- = Rs.75 /set Marketing get the order of 500 Weight lifting sets for the price Rs.2,900/set. Then cost is issued Rs.2,500/Set to costing department.
  • 3. MACHINING HOURS EXECUTION Capacity assessment check This is the process to check % of utilization of machine hours Hours Allocation The hours to be allocated based on the priority quantity. Maybe Monthly/Weekly. Daily Plan Daily plan need to be updated to operators
  • 4. PLANNING - Capacity assessment check Capacity assessment check S.no Description Project Qty Conv. Lathe (1st opr) CNC Lathe (2nd opr) C.T (Mins) Hrs.Required C.T (Mins) Hrs.Required 1Handle K14T 250 40 166.66 20 83.33 Total 250 167 83.5 Available Hrs per Month (Working hours 860 Mins ie., two shifts *24 days) 344 344 Considering 15% of losses due to M/c break down, Operator absence, Setting, unplanned meeting etc., 51 51 Net available Hrs 293 293 % of hours to be utilizied/ Month 57% 28%
  • 5. PLANNING – Hours allocation and Daily plan Hours Allocation - APR'17 S.no Descrption Project Qty Conv.Lathe CNC Machining Plan (Hrs) Actual (Hrs) Plan (Hrs) Actual (Hrs) 1Handle K14T 250 167 83.5 2XXX XX 120 80 68 3YYY YY 80 48 74 4ZZZ ZZ 90 - 70 Total 295 295.5 Daily Plan 1st Shift 01-04-2017 Machine Description Project Operation Available Mins Plan qty Achieve qty Conv.Lathe Handle K14T 1st 430 10.75 CNC Lathe Handle K14T 2nd 430 21.5
  • 6. MACHINING HOURS MONITOR Job Card Operator should enter the daily activities Review The same will be reviewed by the supervisor Efficiency Efficiency calculation to be done PRODUCTION PLAN VS ACTUAL
  • 7. JOB CARD MACHINE SHOP JOB CARD Machine:Conv.Lathe Date: Shift Part Description Project Operation Prod Qty RW Qty Rej. Qty Operator Name & Sign Supervisor Name & Sign 1st Handle K14T 1st 8 - - Kamlakannan 2nd Handle K14T 1st 9.5 1 - Rajendran Operations: 1st, 2nd, 3rd, 4th, Serr (Serration), BM (Blue matching) , SF(Semi finish) SFF (Semi finish finished). Remarks: 1) Front side MACHINE SHOP JOB CARD Shift Time shortcu ts Start time End time Total time Review by Shift Time Shortcut s Start time End time Total time Review by 1st SE 08:00 08:30 30 2nd PR 16:45 00:45 380 PR 08:30 14:00 235 TI 22:00 22:45 45 MB 14:00 15:20 80 PR 15:20 16:45 85 PR- Production time, CT- Cycle time, RW- Rework time, SE- Setting time,MB- Breakdown/ Power cut, TI- Tool/fixture issue, NL- No load, No- No operator, OT- Others Remarks:
  • 8. EFFICIENCY CALCULATION Shift Machi ne No Operat or name Part Description Projec t Oper ation Prd n.Qt y Rw. Qty Avl. Tim e Utili zed time Loss time in Min. Down Time in Min. Machine Utilized Efficiency Overall Shift efficiency Set ting Too l/ Fixt . Oth ers Bre ak do wn No ope rat or No load Std.Cyc le Time Std. Prodn time % Acce pted Qty Utiliz ed Quail ty OSE in % 1 s t Conv Lathe Kamal kanna n Handle K14T 1st 8 430 350 30 80 40 320 74% 8.00 0.74 1.00 74.000 0 2 n d Conv Lathe Rajend ran Handle K14T 1st 9.5 1 430 425 45 40 380 88% 8.50 0.88 0.81 71.240 0
  • 9. PLAN vs ACTUAL Daily Plan 01-04-2017 Shift Machine Description Project Operation Available Mins Plan qty Achieve qty 1st Conv.Lathe Handle K14T 1st 430 10.75 8 2nd Conv.Lathe Handle K14T 1st 430 10.75 8.5 Setting time Break down Tool issue 30 80 45 Loss time in mins on 1/Apr/17 Cycle time Actual Min 40 52 Actual cycle time on 1-Apr/ Component
  • 10. EXAMPLE ACHIEVED Procurement cost:- Nuts and grips = Rs.48.5/set Material for handle & weight = Rs.452/set Assembly Hours:- Weight lifter = 17mins/set Machining hours:- Handle 1st opr - 46mins Handle 2nd opr – 24mins Packing and transit cost:- = Rs.72/sets Planned - Rs.2,500/Set Achieved- Rs.2,851/set Monitor tool:- EBS MANUAL XLS OEE Etc..,