V 2.0
Project Scope Statement
Project Name
Speakeasy Hotel Network Installation
Project Number
P05258-5
Project Manager
Timothy P Ross
Prioritization
1A
Owner(s)
Trifecta Corp. ( Owners - David Eaker, Troy Gray, and Coura Badiane )
Statement of Work—Project Description and
Project Product
The purpose of the project is to coordinate and successfully install the network infrastructure in the Speakeasy Hotel in order to ensure a smooth operational grand opening that will provide administrative and guest network services including; phone, video, internet, security, guest tracking, and POS system. Trifecta inc. is renovating a new acquisition in preparation of a scheduled grand opening. This project will help Speakeasy to better serve their client base, make their stay comfortable and enjoyable and better enable the staff to manage the day to day activities of the hotel. The scope of this network installation includes the planning, design, deployment, configuration, testing, and transition of the network system. This network will meet or exceed organizational requirements established in the project charter. The scope of this project also includes the completion of all documentation, manuals, and training aides to be used in conjunction with the various systems. Project completion will occur when the network and documentation package has been successfully executed.
We intend to execute this project by completing the following:
1. Maintain focus on the implementation of the approved LAN Vendor solution and ongoing support services, including but not limited to;
2. Project Management, serving as a local single point of contact for the Owner/Operator ( Trifecta inc. )
3. Implementing the approved LSP solution including the installation of all equipment, configuration, integration, and testing.
4. Obtain all onboarding documents from network vendors specifying network requirements for IPTV system, Security system, Phone system, Business Center, Guest Services System, and Point of Sale System.
5. Perform a site survey to determine strategic location of equipment deployment for maximum coverage and reliability.
6. Utilize the LAN Vendor as to test and ensure all vendor equipment communicates effectively on the network observing high network security standards and routing protocols.
7. Obtain a contract for 3 – 5 years for ongoing customer support utilizing Helpdesk Services, a Remote Call Center, a Remote Network Operations Center ( NOC ), and arranging onsite support as necessary to maintain network integrity.
8. Obtain all network drawings, applicable licenses & permits, equipment specifications, port mapping/ identification information, training documentation, and warranty documentation to ensure Speakeasy staff is able to effectively identify and support equipment at the hotel.
Project Deliverables
There are 4 tangible services being provided from this network installation project. Each service is being installed by a separate vendo ...
This project was a culmination of two years of study at ITT-Technical Institutes\'s Bessemer, AL campus for an Associates degree in ITCNS (Information Technology Computer Network Systems). It was a team project of 7 members with the goal of designing a network solution for a fictional medical practice consolidation of 5 doctors in a company named Radiant Medical Services.
Implementation plan for a De Novo Mortgage bank. Looks at all aspects of the setup from Human Capital, Facilities Implementation, Technology, Support Functions & Vendor Development and Sales and Marketing, Licensing and Registration, Business Documentation, Funding and Exit Strategies
This project was a culmination of two years of study at ITT-Technical Institutes\'s Bessemer, AL campus for an Associates degree in ITCNS (Information Technology Computer Network Systems). It was a team project of 7 members with the goal of designing a network solution for a fictional medical practice consolidation of 5 doctors in a company named Radiant Medical Services.
Implementation plan for a De Novo Mortgage bank. Looks at all aspects of the setup from Human Capital, Facilities Implementation, Technology, Support Functions & Vendor Development and Sales and Marketing, Licensing and Registration, Business Documentation, Funding and Exit Strategies
Authentic Assessment Project (AAP) Jan 2017Background Informat.docxrock73
Authentic Assessment Project (AAP) Jan 2017
Background Information for World-Wide Trading Company
World-Wide Trading Company (WWTC) is a large online broker firm in the Hong Kong. The trading company has a staff of 9,000 who are scattered around the globe. Due to aggressive growth in business, they want to establish a regional office in New York City. They leased the entire floor of a building on Wall Street. You were selected as a contractor (your group) to build a state of the art high availability, secure network. The President of the company asked you to set up the state of the art network by end of this year. He shared with you the organizational structure and a list of the 100 employees. The current floor of the new site is solid and gigabit network can be set up on existing network wiring. Also, the existing power supply will meet the client’s current and future demand. The President has required these business goals:
Business and Technical Goals
· Increaserevenue from 10 billion to 40 billion in three to four years
· Reduce the operating cost from 30 to 15 percent in two to three years by using an automated system for buying and selling.
· Provide secure means of customer purchase and payment over Internet.
· Build a high availability, moderate confidentiality and moderate integrity unclassified network (based on The National Institute of Standards and Technology- NIST)
· Build a classified network with high confidentiality, moderate integrity, and moderate availability (based on NIST)
· Allow employee to attach their notebook computers to the WWTC network and wireless Internet services.
· Provide state of the art VoIP and Data Network
· Provide Active Directory, DNS, and DCHP services
· Provide faster Network services
· Provide fast and secure wireless services in the lobby, conference rooms (100x60), and the cubical areas.
On the basis of these business goals, your group is responsible for designing, configuring, and implementing fast, reliable and secure networks (classified and unclassified).
WWTC LAN/WLAN/VoIP
· Propose a secure network design that solves the network and security challenges, to meet business needs, and the other technical goals. You are also required to provide a modular and scalable network. Provide redundancy at building core layer, building distribution layer, and access layer to avoid single point of failure. For Building Access layer provide redundant uplinks connection.
· Select appropriate Cisco switch model for each part of your enterprise campus model design from the Cisco Products Link, and use the following assumptions in your selection process:
1. Selecting the Access layers’ switches:
0. Provide one port to each device
0. Make provision for 100% growth
1. Server farm switches
a. Assume 6 NIC cards in each server and one NIC card uses one port of switch
b. Dual processors and dual power supply
· Propose an IP addressing redesign that optimizes IP addressing and IP routing (including ...
Background Information for World-Wide Trading CompanyWorld-Wide .docxikirkton
Background Information for World-Wide Trading Company
World-Wide Trading (WWTC) is a large online broker firm in the Hong Kong. The trading company has a staff of 9,000 who are scattered around the globe. Due to aggressive growth in business, they want to establish a regional office in New York City. They leased the entire floor of a building on Wall Street. You were hired as the director of the IT Department. The President of the company asked you to set up the state of the art network by December 15, 2013. He shared with you the organizational structure and a list of the staff. You hired a consultant to test the network infrastructure and power requirement at WWTC office space. The consultant reported that the network infrastructure is solid and gigabit network can be set up on existing network wiring. Also, the existing power supply will meet their current and future demand. The President has reiterated these business goals.
Business and Technical Goals
· Increaserevenue from 10 billion to 40 billion by the year 2015
· Reduce the operating cost from 30 to 15 percent by the year 2015 by using an automated system for buying and selling.
· Provide secure means of customer purchase and payment over Internet.
· Allow employee to attach their notebook computers to the WWTC network and Internet services.
· Provide state of the art VoIP and Data Network
· Provide faster Network services
· Provide fast and secure wireless services in the lobby and two large conference rooms (100x60)
On the basis of these business goals, you prepared a RFP to solicit a proposal for designing and implementing a fast, reliable and secure network.
The purpose of this Request for Proposal is to solicit from qualified vendors proposals for a
secure and fast network to ensure proper operation of the network.
To prepare a design for a state of the art network at the Wall Street location of World-Wide Trading.
Propose a Network design that solves the current security audit problems (see security sections), to meet business and technical goals.
Provide a modular, scalable and network.
Provide redundancy at building core layer and building distribution layer and access layer and at workstation level to avoid failure at one point. For Building Access layer provide redundant uplinks connection to Building Distribution layer.
Select appropriate Cisco switch model for each part of your enterprise campus model design from the Cisco Products Link, listed below and use the following assumptions in your selection process.
Selecting the Access layers switches:
0. Provide one port to each device
0. Make provision for 100% growth
Server farm switches
· Assume 6 NIC cards in each server and one NIC card uses one port of switch
· Dual processors and dual power supply
Propose an IP addressing redesign that optimizes IP addressing and IP routing (including the use of route summarization). Provide migration provision to IPv6 protocol in future.
Propose a High Level securi ...
WWTC Office Layout Diagram.htmlBackground Information for Wo.docxericbrooks84875
WWTC Office Layout Diagram.html
Background Information for World-Wide Trading Company
World-Wide Trading (WWTC) is a large online broker firm in the Hong Kong. The trading company has a staff of 9,000 who are scattered around the globe. Due to aggressive growth in business, they want to establish a regional office in New York City. They leased the entire floor of a building on Wall Street. You were hired as the director of the IT Department. The President of the company asked you to set up the state of the art network by December 15, 2013. He shared with you the organizational structure and a list of the staff. You hired a consultant to test the network infrastructure and power requirement at WWTC office space. The consultant reported that the network infrastructure is solid and gigabit network can be set up on existing network wiring. Also, the existing power supply will meet their current and future demand. The President has reiterated these business goals.
Business and Technical Goals
· Increaserevenue from 10 billion to 40 billion by the year 2015
· Reduce the operating cost from 30 to 15 percent by the year 2015 by using an automated system for buying and selling.
· Provide secure means of customer purchase and payment over Internet.
· Allow employee to attach their notebook computers to the WWTC network and Internet services.
· Provide state of the art VoIP and Data Network
· Provide faster Network services
· Provide fast and secure wireless services in the lobby and two large conference rooms (100x60)
On the basis of these business goals, you prepared a RFP to solicit a proposal for designing and implementing a fast, reliable and secure network.
The purpose of this Request for Proposal is to solicit from qualified vendors proposals for a
secure and fast network to ensure proper operation of the network.
To prepare a design for a state of the art network at the Wall Street location of World-Wide Trading.
Propose a Network design that solves the current security audit problems (see security sections), to meet business and technical goals.
Provide a modular, scalable and network.
Provide redundancy at building core layer and building distribution layer and access layer and at workstation level to avoid failure at one point. For Building Access layer provide redundant uplinks connection to Building Distribution layer.
Select appropriate Cisco switch model for each part of your enterprise campus model design from the Cisco Products Link, listed below and use the following assumptions in your selection process.
Selecting the Access layers switches:
0. Provide one port to each device
0. Make provision for 100% growth
Server farm switches
· Assume 6 NIC cards in each server and one NIC card uses one port of switch
· Dual processors and dual power supply
Propose an IP addressing redesign that optimizes IP addressing and IP routing (including the use of route summarization). Provide migration provision to IPv6 protocol in fut.
1 CITY OF DuPONT REQUEST FOR PROPOSALS .docxkarisariddell
1
CITY OF DuPONT
REQUEST FOR PROPOSALS
INFORMATION TECHNOLOGY
SUPPORT SERVICES
Issue Date: January 5, 2006
Due Date: 3:00 P.M., January 31, 2006
2
CITY OF DuPONT
REQUEST FOR PROPOSALS
INFORMATION TECHNOLOGY SUPPORT SERVICES
I. Introduction
The City of DuPont is soliciting proposals from qualified professional vendors for Information
Technology support services. The qualified vendor will enable the City to significantly improve
information technology (IT) effectiveness, enhance its quality of services, minimize its support
cost, and maximize return on investment in IT.
II. Background Information
The City of DuPont currently runs a Windows 2000 server with workstations running Windows
2000 or Windows XP Professional. These workstations connect via basic network shares to the
server which serves as a basic file server and a Springbrook financial software server. City Hall
is connected to the Internet via a T-1 line provided by Eschelon Telecommunications. The Police
Department computers are managed by LESA (Law Enforcement Support Agency) and they
connect to the Internet via LESA’s connection. The Fire Department currently connect to the
Internet via Comcast cable, and the Public Works shop is in the process of installing an additional
T-1 line to connect via Eschelon. City E-Mail and the City website are hosted by Eschelon
Telecommunications.
The City deploys Norton Corporate Security for computers located within City Hall. Outside
City Hall (Fire and Public Works) users have stand-alone versions of Norton Antivirus which
updates via LiveUpdate. The Windows 2000 Server was originally designed for use for
Springbrook only, but has been adapted for file server use. This is an issue which needs to be
addressed so as to keep the systems separate in the future.
III. Services Required
The following details the services to be provided to the City of DuPont in the area of information
services:
1. Initial Assessment – Compile/update inventory of all information technology related
assets, assess system architecture and current processes, and make recommendations for
improved city-wide IT system performance.
2. Desktop Applications Support - Performs basic support functions including installing
PCs, laptops, PDAs, printers, peripherals, and office automation software; diagnosing and
correcting desktop application problems, configuring laptops and desktops for standard
applications and identifying and correcting end user hardware problems, and performing
advanced troubleshooting. Maintain an up-to-date inventory of ALL City computer
related hardware and make available to City personnel upon request. Assist designated
City personnel with software and hardware purchases. Assist in development of
software/hardware policies and procedures.
3
3. Server Administration Services - Managing computer systems and networks to include
complex a.
Professional Summary:
6 years of experience in Telecom industry.
Excellent communication and interpersonal skills. Highly motivated with strong commitment to quality and customer service
Specialties: Telecom Testing,,SS7/SIGTRAN,Diameter/PCRF,GSM/GPRS,CAMEL(IN),Automation(Shell & AWK), Nagios tool,Linux,
Authentic Assessment Project (AAP) Jan 2017Background Informat.docxrock73
Authentic Assessment Project (AAP) Jan 2017
Background Information for World-Wide Trading Company
World-Wide Trading Company (WWTC) is a large online broker firm in the Hong Kong. The trading company has a staff of 9,000 who are scattered around the globe. Due to aggressive growth in business, they want to establish a regional office in New York City. They leased the entire floor of a building on Wall Street. You were selected as a contractor (your group) to build a state of the art high availability, secure network. The President of the company asked you to set up the state of the art network by end of this year. He shared with you the organizational structure and a list of the 100 employees. The current floor of the new site is solid and gigabit network can be set up on existing network wiring. Also, the existing power supply will meet the client’s current and future demand. The President has required these business goals:
Business and Technical Goals
· Increaserevenue from 10 billion to 40 billion in three to four years
· Reduce the operating cost from 30 to 15 percent in two to three years by using an automated system for buying and selling.
· Provide secure means of customer purchase and payment over Internet.
· Build a high availability, moderate confidentiality and moderate integrity unclassified network (based on The National Institute of Standards and Technology- NIST)
· Build a classified network with high confidentiality, moderate integrity, and moderate availability (based on NIST)
· Allow employee to attach their notebook computers to the WWTC network and wireless Internet services.
· Provide state of the art VoIP and Data Network
· Provide Active Directory, DNS, and DCHP services
· Provide faster Network services
· Provide fast and secure wireless services in the lobby, conference rooms (100x60), and the cubical areas.
On the basis of these business goals, your group is responsible for designing, configuring, and implementing fast, reliable and secure networks (classified and unclassified).
WWTC LAN/WLAN/VoIP
· Propose a secure network design that solves the network and security challenges, to meet business needs, and the other technical goals. You are also required to provide a modular and scalable network. Provide redundancy at building core layer, building distribution layer, and access layer to avoid single point of failure. For Building Access layer provide redundant uplinks connection.
· Select appropriate Cisco switch model for each part of your enterprise campus model design from the Cisco Products Link, and use the following assumptions in your selection process:
1. Selecting the Access layers’ switches:
0. Provide one port to each device
0. Make provision for 100% growth
1. Server farm switches
a. Assume 6 NIC cards in each server and one NIC card uses one port of switch
b. Dual processors and dual power supply
· Propose an IP addressing redesign that optimizes IP addressing and IP routing (including ...
Background Information for World-Wide Trading CompanyWorld-Wide .docxikirkton
Background Information for World-Wide Trading Company
World-Wide Trading (WWTC) is a large online broker firm in the Hong Kong. The trading company has a staff of 9,000 who are scattered around the globe. Due to aggressive growth in business, they want to establish a regional office in New York City. They leased the entire floor of a building on Wall Street. You were hired as the director of the IT Department. The President of the company asked you to set up the state of the art network by December 15, 2013. He shared with you the organizational structure and a list of the staff. You hired a consultant to test the network infrastructure and power requirement at WWTC office space. The consultant reported that the network infrastructure is solid and gigabit network can be set up on existing network wiring. Also, the existing power supply will meet their current and future demand. The President has reiterated these business goals.
Business and Technical Goals
· Increaserevenue from 10 billion to 40 billion by the year 2015
· Reduce the operating cost from 30 to 15 percent by the year 2015 by using an automated system for buying and selling.
· Provide secure means of customer purchase and payment over Internet.
· Allow employee to attach their notebook computers to the WWTC network and Internet services.
· Provide state of the art VoIP and Data Network
· Provide faster Network services
· Provide fast and secure wireless services in the lobby and two large conference rooms (100x60)
On the basis of these business goals, you prepared a RFP to solicit a proposal for designing and implementing a fast, reliable and secure network.
The purpose of this Request for Proposal is to solicit from qualified vendors proposals for a
secure and fast network to ensure proper operation of the network.
To prepare a design for a state of the art network at the Wall Street location of World-Wide Trading.
Propose a Network design that solves the current security audit problems (see security sections), to meet business and technical goals.
Provide a modular, scalable and network.
Provide redundancy at building core layer and building distribution layer and access layer and at workstation level to avoid failure at one point. For Building Access layer provide redundant uplinks connection to Building Distribution layer.
Select appropriate Cisco switch model for each part of your enterprise campus model design from the Cisco Products Link, listed below and use the following assumptions in your selection process.
Selecting the Access layers switches:
0. Provide one port to each device
0. Make provision for 100% growth
Server farm switches
· Assume 6 NIC cards in each server and one NIC card uses one port of switch
· Dual processors and dual power supply
Propose an IP addressing redesign that optimizes IP addressing and IP routing (including the use of route summarization). Provide migration provision to IPv6 protocol in future.
Propose a High Level securi ...
WWTC Office Layout Diagram.htmlBackground Information for Wo.docxericbrooks84875
WWTC Office Layout Diagram.html
Background Information for World-Wide Trading Company
World-Wide Trading (WWTC) is a large online broker firm in the Hong Kong. The trading company has a staff of 9,000 who are scattered around the globe. Due to aggressive growth in business, they want to establish a regional office in New York City. They leased the entire floor of a building on Wall Street. You were hired as the director of the IT Department. The President of the company asked you to set up the state of the art network by December 15, 2013. He shared with you the organizational structure and a list of the staff. You hired a consultant to test the network infrastructure and power requirement at WWTC office space. The consultant reported that the network infrastructure is solid and gigabit network can be set up on existing network wiring. Also, the existing power supply will meet their current and future demand. The President has reiterated these business goals.
Business and Technical Goals
· Increaserevenue from 10 billion to 40 billion by the year 2015
· Reduce the operating cost from 30 to 15 percent by the year 2015 by using an automated system for buying and selling.
· Provide secure means of customer purchase and payment over Internet.
· Allow employee to attach their notebook computers to the WWTC network and Internet services.
· Provide state of the art VoIP and Data Network
· Provide faster Network services
· Provide fast and secure wireless services in the lobby and two large conference rooms (100x60)
On the basis of these business goals, you prepared a RFP to solicit a proposal for designing and implementing a fast, reliable and secure network.
The purpose of this Request for Proposal is to solicit from qualified vendors proposals for a
secure and fast network to ensure proper operation of the network.
To prepare a design for a state of the art network at the Wall Street location of World-Wide Trading.
Propose a Network design that solves the current security audit problems (see security sections), to meet business and technical goals.
Provide a modular, scalable and network.
Provide redundancy at building core layer and building distribution layer and access layer and at workstation level to avoid failure at one point. For Building Access layer provide redundant uplinks connection to Building Distribution layer.
Select appropriate Cisco switch model for each part of your enterprise campus model design from the Cisco Products Link, listed below and use the following assumptions in your selection process.
Selecting the Access layers switches:
0. Provide one port to each device
0. Make provision for 100% growth
Server farm switches
· Assume 6 NIC cards in each server and one NIC card uses one port of switch
· Dual processors and dual power supply
Propose an IP addressing redesign that optimizes IP addressing and IP routing (including the use of route summarization). Provide migration provision to IPv6 protocol in fut.
1 CITY OF DuPONT REQUEST FOR PROPOSALS .docxkarisariddell
1
CITY OF DuPONT
REQUEST FOR PROPOSALS
INFORMATION TECHNOLOGY
SUPPORT SERVICES
Issue Date: January 5, 2006
Due Date: 3:00 P.M., January 31, 2006
2
CITY OF DuPONT
REQUEST FOR PROPOSALS
INFORMATION TECHNOLOGY SUPPORT SERVICES
I. Introduction
The City of DuPont is soliciting proposals from qualified professional vendors for Information
Technology support services. The qualified vendor will enable the City to significantly improve
information technology (IT) effectiveness, enhance its quality of services, minimize its support
cost, and maximize return on investment in IT.
II. Background Information
The City of DuPont currently runs a Windows 2000 server with workstations running Windows
2000 or Windows XP Professional. These workstations connect via basic network shares to the
server which serves as a basic file server and a Springbrook financial software server. City Hall
is connected to the Internet via a T-1 line provided by Eschelon Telecommunications. The Police
Department computers are managed by LESA (Law Enforcement Support Agency) and they
connect to the Internet via LESA’s connection. The Fire Department currently connect to the
Internet via Comcast cable, and the Public Works shop is in the process of installing an additional
T-1 line to connect via Eschelon. City E-Mail and the City website are hosted by Eschelon
Telecommunications.
The City deploys Norton Corporate Security for computers located within City Hall. Outside
City Hall (Fire and Public Works) users have stand-alone versions of Norton Antivirus which
updates via LiveUpdate. The Windows 2000 Server was originally designed for use for
Springbrook only, but has been adapted for file server use. This is an issue which needs to be
addressed so as to keep the systems separate in the future.
III. Services Required
The following details the services to be provided to the City of DuPont in the area of information
services:
1. Initial Assessment – Compile/update inventory of all information technology related
assets, assess system architecture and current processes, and make recommendations for
improved city-wide IT system performance.
2. Desktop Applications Support - Performs basic support functions including installing
PCs, laptops, PDAs, printers, peripherals, and office automation software; diagnosing and
correcting desktop application problems, configuring laptops and desktops for standard
applications and identifying and correcting end user hardware problems, and performing
advanced troubleshooting. Maintain an up-to-date inventory of ALL City computer
related hardware and make available to City personnel upon request. Assist designated
City personnel with software and hardware purchases. Assist in development of
software/hardware policies and procedures.
3
3. Server Administration Services - Managing computer systems and networks to include
complex a.
Professional Summary:
6 years of experience in Telecom industry.
Excellent communication and interpersonal skills. Highly motivated with strong commitment to quality and customer service
Specialties: Telecom Testing,,SS7/SIGTRAN,Diameter/PCRF,GSM/GPRS,CAMEL(IN),Automation(Shell & AWK), Nagios tool,Linux,
Instructions for Submissions thorugh G- Classroom.pptxJheel Barad
This presentation provides a briefing on how to upload submissions and documents in Google Classroom. It was prepared as part of an orientation for new Sainik School in-service teacher trainees. As a training officer, my goal is to ensure that you are comfortable and proficient with this essential tool for managing assignments and fostering student engagement.
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxEduSkills OECD
Andreas Schleicher presents at the OECD webinar ‘Digital devices in schools: detrimental distraction or secret to success?’ on 27 May 2024. The presentation was based on findings from PISA 2022 results and the webinar helped launch the PISA in Focus ‘Managing screen time: How to protect and equip students against distraction’ https://www.oecd-ilibrary.org/education/managing-screen-time_7c225af4-en and the OECD Education Policy Perspective ‘Students, digital devices and success’ can be found here - https://oe.cd/il/5yV
Operation “Blue Star” is the only event in the history of Independent India where the state went into war with its own people. Even after about 40 years it is not clear if it was culmination of states anger over people of the region, a political game of power or start of dictatorial chapter in the democratic setup.
The people of Punjab felt alienated from main stream due to denial of their just demands during a long democratic struggle since independence. As it happen all over the word, it led to militant struggle with great loss of lives of military, police and civilian personnel. Killing of Indira Gandhi and massacre of innocent Sikhs in Delhi and other India cities was also associated with this movement.
We all have good and bad thoughts from time to time and situation to situation. We are bombarded daily with spiraling thoughts(both negative and positive) creating all-consuming feel , making us difficult to manage with associated suffering. Good thoughts are like our Mob Signal (Positive thought) amidst noise(negative thought) in the atmosphere. Negative thoughts like noise outweigh positive thoughts. These thoughts often create unwanted confusion, trouble, stress and frustration in our mind as well as chaos in our physical world. Negative thoughts are also known as “distorted thinking”.
The Roman Empire A Historical Colossus.pdfkaushalkr1407
The Roman Empire, a vast and enduring power, stands as one of history's most remarkable civilizations, leaving an indelible imprint on the world. It emerged from the Roman Republic, transitioning into an imperial powerhouse under the leadership of Augustus Caesar in 27 BCE. This transformation marked the beginning of an era defined by unprecedented territorial expansion, architectural marvels, and profound cultural influence.
The empire's roots lie in the city of Rome, founded, according to legend, by Romulus in 753 BCE. Over centuries, Rome evolved from a small settlement to a formidable republic, characterized by a complex political system with elected officials and checks on power. However, internal strife, class conflicts, and military ambitions paved the way for the end of the Republic. Julius Caesar’s dictatorship and subsequent assassination in 44 BCE created a power vacuum, leading to a civil war. Octavian, later Augustus, emerged victorious, heralding the Roman Empire’s birth.
Under Augustus, the empire experienced the Pax Romana, a 200-year period of relative peace and stability. Augustus reformed the military, established efficient administrative systems, and initiated grand construction projects. The empire's borders expanded, encompassing territories from Britain to Egypt and from Spain to the Euphrates. Roman legions, renowned for their discipline and engineering prowess, secured and maintained these vast territories, building roads, fortifications, and cities that facilitated control and integration.
The Roman Empire’s society was hierarchical, with a rigid class system. At the top were the patricians, wealthy elites who held significant political power. Below them were the plebeians, free citizens with limited political influence, and the vast numbers of slaves who formed the backbone of the economy. The family unit was central, governed by the paterfamilias, the male head who held absolute authority.
Culturally, the Romans were eclectic, absorbing and adapting elements from the civilizations they encountered, particularly the Greeks. Roman art, literature, and philosophy reflected this synthesis, creating a rich cultural tapestry. Latin, the Roman language, became the lingua franca of the Western world, influencing numerous modern languages.
Roman architecture and engineering achievements were monumental. They perfected the arch, vault, and dome, constructing enduring structures like the Colosseum, Pantheon, and aqueducts. These engineering marvels not only showcased Roman ingenuity but also served practical purposes, from public entertainment to water supply.
Unit 8 - Information and Communication Technology (Paper I).pdfThiyagu K
This slides describes the basic concepts of ICT, basics of Email, Emerging Technology and Digital Initiatives in Education. This presentations aligns with the UGC Paper I syllabus.
The Art Pastor's Guide to Sabbath | Steve ThomasonSteve Thomason
What is the purpose of the Sabbath Law in the Torah. It is interesting to compare how the context of the law shifts from Exodus to Deuteronomy. Who gets to rest, and why?
Ethnobotany and Ethnopharmacology:
Ethnobotany in herbal drug evaluation,
Impact of Ethnobotany in traditional medicine,
New development in herbals,
Bio-prospecting tools for drug discovery,
Role of Ethnopharmacology in drug evaluation,
Reverse Pharmacology.
V 2.0Project Scope StatementProject NameSpeakeasy Ho.docx
1. V 2.0
Project Scope Statement
Project Name
Speakeasy Hotel Network Installation
Project Number
P05258-5
Project Manager
Timothy P Ross
Prioritization
1A
Owner(s)
Trifecta Corp. ( Owners - David Eaker, Troy Gray, and Coura
Badiane )
Statement of Work—Project Description and
Project Product
The purpose of the project is to coordinate and successfully
install the network infrastructure in the Speakeasy Hotel in
order to ensure a smooth operational grand opening that will
provide administrative and guest network services including;
phone, video, internet, security, guest tracking, and POS
system. Trifecta inc. is renovating a new acquisition in
preparation of a scheduled grand opening. This project will
help Speakeasy to better serve their client base, make their stay
comfortable and enjoyable and better enable the staff to manage
the day to day activities of the hotel. The scope of this network
installation includes the planning, design, deployment,
configuration, testing, and transition of the network system.
2. This network will meet or exceed organizational requirements
established in the project charter. The scope of this project also
includes the completion of all documentation, manuals, and
training aides to be used in conjunction with the various
systems. Project completion will occur when the network and
documentation package has been successfully executed.
We intend to execute this project by completing the following:
1. Maintain focus on the implementation of the approved LAN
Vendor solution and ongoing support services, including but not
limited to;
2. Project Management, serving as a local single point of
contact for the Owner/Operator ( Trifecta inc. )
3. Implementing the approved LSP solution including the
installation of all equipment, configuration, integration, and
testing.
4. Obtain all onboarding documents from network vendors
specifying network requirements for IPTV system, Security
system, Phone system, Business Center, Guest Services System,
and Point of Sale System.
5. Perform a site survey to determine strategic location of
equipment deployment for maximum coverage and reliability.
6. Utilize the LAN Vendor as to test and ensure all vendor
equipment communicates effectively on the network observing
high network security standards and routing protocols.
7. Obtain a contract for 3 – 5 years for ongoing customer
support utilizing Helpdesk Services, a Remote Call Center, a
Remote Network Operations Center ( NOC ), and arranging
onsite support as necessary to maintain network integrity.
8. Obtain all network drawings, applicable licenses & permits,
equipment specifications, port mapping/ identification
information, training documentation, and warranty
documentation to ensure Speakeasy staff is able to effectively
identify and support equipment at the hotel.
3. Project Deliverables
There are 4 tangible services being provided from this network
installation project. Each service is being installed by a separate
vendor. Each vendor will provide a project lead or small
projects manager to coordinate their installation phase provide
daily updates to the Project Manager ( Timothy Ross ) for this
install. Upon the successful completion of this phase the
Speakeasy Hotel will have a fully functional communications,
video, and LAN network meeting the needs for the hotel
administrative staff and hotel guests including IPTV, Phones,
computers, POS, guest tracking services, security system,
billing system, printing services, and internet access.Vendor 1 -
Network LAN Vendor will provide proactive network
monitoring services ( Public IP Required ) – equipment will
include all necessary routers/switches/servers/wireless
equipment/mounting racks, televisions, set top boxes for Guest
TV system, and all applicable LAN design documentation, Bill
of Material, Wireless Site Surveys, and training documentation.
Vendor 2 - The Customer
Solution
s vendor will provide all administrative office equipment
including printers/computers/monitors/software and applicable
equipment for guest billing and tracking services including
equipment associated with food and beverage ordering as well
as equipment necessary to set up a Guest Business service
center that will be connected and monitored by Vendor 1
network Vendor – equipment will include 3 computers, printer,
and remote printing services. Vendor 3 – Will provide all
4. associated security equipment including camera’s, servers,
monitors, documentation, and applicable software and recording
equipment to maximize guest security and safety. Vendor 4 –
Will provide all equipment and software associated with
establishing communication via guest phones and administration
offices and meet all criteria associated with meeting hotel life
safety requirements – equipment will include
PBX/Servers/phones and all associated software with remote
monitoring capability ( Public IP Required )
Project Objectives
Cost
The total amount of funds budgeted for the network installation
is $500,000. This does not include the monthly expenses the
Speakeasy hotel will incur for the proactive network monitoring
service or funds required to maintain monthly internet service
with the ISP. This value is a budget estimate of the equipment
materials and labor. A contingency factor of 5% was used on
equipment and material in anticipation of potential price
increases or required network changes.
Objectives & Schedule:
1. To complete all tasks associated with the project and
Milestones are met to effectively open the Speakeasy Hotel as
scheduled as we work to expand our market presence in
preparation of the upcoming vacation season.
5. 2. Low voltage Contractor will - Test, certify, and terminate as
necessary all network cabling to maximize network integrity
and infrastructure. Contractor shall be responsible for providing
all necessary patch cables for guestrooms, conference space and
equipment rooms. Vendor will be responsible for patching the
switch ports to the patch panel.
3. Vendor 1 will Install all network associated equipment to
establish essential communications and services to ensure hotel
staff, hotel equipment, and vendor equipment are fully
operational to maximize the health, comfort, and safety of hotel
guests.
4. Vendor 2 - will install, configure, establish network
communications, test, train hotel staff, and aide in the Grand
opening to ensure all critical hotel operational systems are on
line and processing per operational guidelines.
5. Vendor 3 will install, configure, establish network
communications, test, train hotel security and engineering staff
on equipment deployment, basic troubleshooting, and system
operations in accordance with the security system being
deployed to help ensure safety of hotel guests and staff.
6. Vendor 4 will install, configure, establish network
communications, test, and train hotel engineering staff on basic
system operation and deployment to effectively establish phone
communications throughout the hotel.
6. 7. Vendor 1 will provide all necessary warranty documentation,
network diagrams, equipment specifications, and configurations
as well as provide 3 years of “Proactive Network Monitoring”
of network equipment.
8. Owners – Will approve the network design and network
specifications provided by Vendor 1in a timely fashion to allow
all equipment to be ordered in time to meet all milestones.
9. Owners – Will pay a 30% deposit to all vendors per the
contract guidelines in order for vendors to order required
equipment and to begin work.
10. 3rd Party onboarding docs will be provided 16 weeks prior
Grand Opening.
11. ISP WAN Router installation will be ordered and installed 4
weeks prior to grand opening.
12. VLAN and Network IP Scheme will be provided 6 weeks
prior toGrand Opening.
13. List of ALL software applications requiring ISP interface
will be provided 3 weeks prior to Grand Opening.
14. Port counts, equipment locations, and site survey will be
finalized 12 weeks prior to Grand Opening.
15. Hotel Equipment deployment will be completed 3 weeks
prior to Grand Opening.
16. Guest services including wireless network equipment be
completed 3 weeks prior to Grand Opening.
17. Go Live testing will occur 1 week prior to Grand Opening.
7. Hotel will be open for business for non-paying guests.
18. Billing and guest tracking interface and software will be
operational 1 week prior to Go Live date.
19. Wireless and network testing will begin 1 week prior to Go
Live date utilizing and documenting accordingly test results in
accordance to the established test criteria..
20. Associate operations and training will begin 1 week prior to
Go Live date.
21. System acceptance testing will begin 2 days prior to Grand
Opening.
Project Assumptions
This statement of work is based on the following key
assumptions. Any assumptions found to be invalid could have
an effect on price or schedule and will be handled in accordance
with the “Communication & Project Change Procedure”. The
budget allows for slight variances in order to meet project
deadlines. Project budget is expected to be high initially and
market projections indicate a sustained return on investment
after Grand Opening.
1. Vendors will provide services described in this Scope of
Work Statement during Vendor’s normal business hours, 9:00 to
6:00 Monday thru Friday.
2. Vendors will not be responsible for any project delays.
3. LAN Vendor will provide a Service Level Agreement
8. addressing any service interruptions caused by equipment
failure.
4. ISP will provide a Service Level Agreement addressing any
service interruptions caused by the Internet Vendor line or
service outage.
5. The implementation of this project is based on the equipment
list provided by each vendor associated with their system of
responsibility and products associated with such equipment.
Project Constraints· It may be difficult to free up the required
internal staff without 24 hour notice.· The timeline must be met
to meet “Go Live” dates for Grand Opening.· ISP services must
be ordered with sufficient time to allow ISP provisioning.· No
new temporary hires are allowed with the exception of the PM.
Exclusions
· There will not be Internet access to the new system during this
implementation project.
· RFID ( Radio Frequency Identification Device ) will not be a
part of the network installation or utilized on the network.
· No used equipment will be authorized for this installation
without prior consent and justification. If PM determines used
equipment can or should be utilized said equipment must be
refurbished and warrantied
Acceptance Criteria
Vendors will provide a property site completion list
9. documenting that all of the required installation and migration
tasks as listed in this SOW have been successfully completed,
and will also complete the Acceptance Checklist.to be
completed during the Test Phase. Vendors shall have fulfilled
their obligations under the SOW when any of the following first
occurs:
· Vendor accomplishes the Vendor tasks described under "
Vendor Responsibilities"
· The Operator/Owner notifies Vendor, in writing, that further
services are not required.
Technical Requirements
Upon completion of this project and the network installation
this hotel will be fully operational capable of supporting and
servicing hotel guests. This property consists of 527 guest
rooms, 12 meeting spaces, 1 ball room, a restaurant, a bar, pool,
and exercise area. The Speakeasy hotel is centrally located near
a variety of local attractions and a major sports venue that will
help attract clients.
APPROVALSType NameSignatureDate
Project Manager Approval: