Mohammad Yousef
Project Plan
4/23/14
MGMT404
Professor: Keith Earnshaw
2
Table of Contents
Page 3: Project Charter
Page 8: Scope Statement
Page 13: Work Breakdown Structure
Page 14: Network Diagram
Page 15: Risk Management Plan
Page 17: Resource Management Plan
Page 18: Communication management plan
3
Project Charter
Project
Name
Design and installation of a computer network
for Fortify Satellite Office
Project
Number
1
Project
Manager
Mohammad Yousef Prioritization 1
Owner(s)
Keith Earnshaw
Start Date: 3/09/2014
Scheduled
Completion
Date:
4/01/2014
Mission/
Purpose
What is your project going to accomplish? How does this project relate to overall
goals and objectives of the company? It is part of a program or larger project?
To design and install a computer network for the new Fortify Satellite office based on network and user
requirements.
SOW What will this project create? What is the product of the project? At a high level,
how do you plan on doing the work of the project? What are the high-level
deliverables for this project?
This project will create a new network for the new office of Fortify based on their user requirements. It
will allow the staff of Fortify to work efficiently and keep up productivity. The product of this project is a
new computer network system. I plan on first going over the requirements of the network provided by
the company (Fortify). Based on how many users and network requirements, and office/building specs,
I will decide the necessary equipment and hardware. I will then go on sight to draw blueprints of the
design of the network for the office. I plan on doing the project with my team on sight. All installation,
implementation, and configurations will be done on sight. The deliverables for this project is to have a a
proper, efficient network to allow the staff to work productively.
4
Objectives What objectives, if any, of the company is this project designed to meet?
1.) Fast connection and easily accessible network
2.) Quality VoIP to ensure best customer service by staff
3.) Design and install quality equipment and configurations to have lowest
possibilities of network failure.
4.) Complete in a timely fashion in order to allow staff members to begin
working in the new office.
Business
Need
Why should we do this project? What will be gained, changed, or modified? Is
there a financial or business reason to do this project? This area should
contain any feasibility studies, NPV, PI, PB, or PBD used to advance the
project.
The project must be done to allow new satellite office to be used. The staff can not
start working in the new office location unless they have network connectivity.
Fortify is a growing company and is constantly expanding and creating new offices
all over the world. In order to work from a satellite office, there must be an efficient
network in place to allow communication between office and HQ as well as clients.
Without a network in place, the staff will be useless and not be able to
communicate to the outside world or get any work done. A quality network is
essential for staff members in the Chicago office to succeed.
Project
Manager and
Stakeholders
Who will lead this project? Who are the major stakeholders?
I will lead the project in designing and supervising the team to install, implement,
and configure the network.
The major project stake holders are the staff of the new office and upper
management of Fortify approving the project and approving the budget.
Milestones What are the key milestone dates associated with the project?
5
 Initial consultancy - 3/15/2014
 Design and planning - 3/20/2014
 Implementation - 4/01/2014
 Troubleshooting – 4/02/2014
 Training – 4/10/2014
Budget What is the order-of-magnitude budget for this project?
$8,500 (-$2,125) (+$2,975)
User Acceptance
Criteria/Quality
What are the minimum success criteria as defined by the key
stakeholders?
A working computer network system and VoIP service
High-Level
Project
Assumptions
What are the assumptions on which the project is based?
The assumptions of this project are the network will be working properly with minimal
network failure and will be completed by the quotes time in order to move the staff
into the new office.
High-Level
Project
Constraints
What are the major limiting factors that affect the project?
There are not many constraints besides the budget. If we can meet at the agreed
budget, there should be no other constraints. The timeline has been agreed between
both parties and is easily manageable within the given time request.
Exclusions
and
Boundaries
What are the boundaries of the project? What is to be included and what is to be
excluded from the project?
6
Exclusions include
1.) Admin access to staff members
2.) Network failure due to uncontrollable circumstances (i.e. natural
disasters/weather related, service providers network failure, and building
network failures)
Major
Risks
What are the major risks affecting the project?
The major risks involved are going over budget and unforeseeable/network network
failures.
KEY STAKEHOLDERS
Project Manager
Authority Level
Legitimate
Project Core
Team
7
Mohammad Yousef – Design and Supervision
Adam Case – Implementation
Sam Hughes – Implementation
Drake Seems - Training
Subject Matter
Experts (SMEs)
(include company
and channel
designations if
applicable)
Fortify
APPROVALS
Type Name Signature Date
Project Manager Approval:
Mohammad Yousef
03/09/14
Customer/Sponsor Approval:
Robert Grady 03/09/14
8
Project Scope Statement
Project Name Design and installation of a computer
network for Fortify Satellite Office
Project
Number
1
Project Manager Mohammad Yousef Prioritization 1
Owner(s) Keith Earnshaw
Statement of
Work—
Project
Description
and
Project
Product
This project will create a new network for the new office of Fortify based on their
user requirements. It will allow the staff of Fortify to work efficiently and keep up
productivity.
We intend to do this by installing and implementing top of the line equipment and
correct configurations based on the users requirements. We plan on using only Cisco
equipment (i.e. routers, switches, etc) All of our techs are well rehearsed in network
design and have their Cisco certifications. This will all benefit the project and assure
that everything goes accordingly.
The product of this project is a new computer network system. I plan on first going
over the requirements of the network provided by the company (Fortify). Based on
how many users and network requirements, and office/building specs, I will decide
the necessary equipment and hardware. I will then go on sight to draw blueprints of
the design of the network for the office. I plan on doing the project with my team on
sight. All installation, implementation, and configurations will be done on sight. The
deliverables for this project is to have a a proper, efficient network to allow the staff
to work productively.
We believe that we will need a total of 1 Cisco Router, 2 Cisco access point, 1 Cisco
24 port switch, 300 feet of cat 6 cables, and 6 Cisco VoIP phones. Our techs will install
all the equipment first. They will then run the cables so they are not in the way. We
well then configure the network, test, and trouble shoot for any issues.
9
Project
Deliverables
1.) The network will be working properly with minimal network failure and will
be completed by the quotes time in order to move the staff into the new office.
5.) Fast connection and easily accessible network
6.) Quality VoIP to ensure best customer service by staff
7.) Design and install quality equipment and configurations to have lowest
possibilities of network failure.
8.) Complete in a timely fashion in order to allow staff members to begin working
in the new office.
Project
Objectives
1.) Fast connection and easily accessible network
2.) Quality VoIP to ensure best customer service by staff
3.) Design and install quality equipment and configurations to have lowest
possibilities of network failure.
4.) Complete in a timely fashion in order to allow staff members to begin
working in the new office.
5.) Keep the cost of the project under the estimated budget which was $8,500
(-$2,125) (+$2,975)
6.) We arrived at this number through the use of the following equation:
Budget Estimate (Variance of -10% to +25%)
Project
Assumptions
The assumptions of this project are the network will be working properly with
minimal network failure and will be completed by the quotes time in order to move
the staff into the new office.
Project
Constraints
There are not many constraints besides the budget. If we can meet at the agreed
budget, there should be no other constraints. The timeline has been agreed between
both parties and is easily manageable within the given time request.
Exclusions Exclusions include
3.) Admin access to staff members
4.) Network failure due to uncontrollable circumstances (i.e. natural
disasters/weather related, service providers network failure, and building
network failures)
Acceptance
Criteria
A working computer network system and VoIP service with minimal network failures.
The VoIP service must have good call quality and maintain a 90% up time. If updates
are required and network and VoIP services will be down, we must give a 2 week
notice before hand for quality assurance from Fortify to customers.
10
Technical
Requirements
Hardware Cisco UCS C210M2 for non NEBs Compliant Systems
Software Linux RedHat RHEL 5 Update 3 or Update 5 (64 bit).
See Linux Update Requirements for details on the required Linux updates.
CPU Type 6-core (Cisco UCS C210M2)
CPU Number 6
CPU Speed 3 GHz
Memory (RAM) 32 GB or greater
Swap Space 32 GB or greater
Storage • Cisco UCS C210M2—Expansion, Performance, and Reliability Option
– For OS: One 146 GB SAS 15K RPM Drive
– For database using RAID10: Six 146 GB SAS 15K RPM Drives
– For backups using RAID10: Four 300 GB SAS 10K RPM Drives
– Requires usage Of LSI MegaRAID Controllers
– Dual PowerSupply
• Cisco UCS C210M2—Performance Option
– For OS: One 146 GB SAS 15K RPM Drive
– For database using RAID10: Six 146 GB SAS 15K RPM Drives
– For backups: One 600 GB SAS 10K RPM Drive
– Requires Usage Of LSI MegaRAID Controllers
• Cisco UCS C210M2—Basic Option With Additional Performance
– For OS: One 146 GB SAS 15K RPM Drive
– For database using RAID0: Two 300 GB SAS 10K RPM Drives
11
– For backups: One 600 GB SAS 10K RPM Drive
– Uses LSI Mezzanine RAID Controller
• Cisco UCS C210M2—Basic Option
– For OS: One 146 GB SAS 15K RPM Drive
– For database: One 300 GB SAS 10K RPM Drives
– For backups: One 600 GB SAS 10K RPM Drive
– Uses LSI Mezzanine RAID Controller
APPROVALS
Type Name Signature Date
Project Manager Approval: Mohammad Yousef
03/23/14
Customer/Sponsor Approval: Robert Grady
03/23/14
12
Work Breakdown Structure
13
Network Diagram
14
15
Risk Management Plan
16
17
Resource Management Plan
18
Communication Management Plan

More Related Content

What's hot

Charles M Cottrell - RESUME
Charles M Cottrell - RESUMECharles M Cottrell - RESUME
Charles M Cottrell - RESUME
Chuck Cottrell
 
Paul cliff-2014 combo resume
Paul cliff-2014 combo resumePaul cliff-2014 combo resume
Paul cliff-2014 combo resumePaul Cliff
 
Pieter_Christian_Le_Roux's_Resume_02
Pieter_Christian_Le_Roux's_Resume_02Pieter_Christian_Le_Roux's_Resume_02
Pieter_Christian_Le_Roux's_Resume_02Pieter Le Roux
 
(Reviewed) Resume Mayeta 2016
(Reviewed) Resume Mayeta 2016(Reviewed) Resume Mayeta 2016
(Reviewed) Resume Mayeta 2016Orlando Mayeta
 
Vineet Resume with 5.9 years of Experience in Cisco Contact Center
Vineet Resume with 5.9 years of Experience in Cisco Contact CenterVineet Resume with 5.9 years of Experience in Cisco Contact Center
Vineet Resume with 5.9 years of Experience in Cisco Contact Centervineet pandey
 
Prakash soni
Prakash soniPrakash soni
Prakash soni
prakash soni
 
Practical Routers & Switches for Electrical Engineers
Practical Routers & Switches for Electrical EngineersPractical Routers & Switches for Electrical Engineers
Practical Routers & Switches for Electrical Engineers
Living Online
 
Pm deep dive scope management
Pm deep dive   scope managementPm deep dive   scope management
Pm deep dive scope managementNiraj Agarwal
 

What's hot (17)

Robbie Greig CV
Robbie Greig CVRobbie Greig CV
Robbie Greig CV
 
Nemi_ ProjectManager 16192016
Nemi_ ProjectManager 16192016Nemi_ ProjectManager 16192016
Nemi_ ProjectManager 16192016
 
IT Engineer
IT EngineerIT Engineer
IT Engineer
 
Charles M Cottrell - RESUME
Charles M Cottrell - RESUMECharles M Cottrell - RESUME
Charles M Cottrell - RESUME
 
Nasir Zohaib CV
Nasir Zohaib CVNasir Zohaib CV
Nasir Zohaib CV
 
Stretton CV-f
Stretton CV-fStretton CV-f
Stretton CV-f
 
Paul cliff-2014 combo resume
Paul cliff-2014 combo resumePaul cliff-2014 combo resume
Paul cliff-2014 combo resume
 
Pieter_Christian_Le_Roux's_Resume_02
Pieter_Christian_Le_Roux's_Resume_02Pieter_Christian_Le_Roux's_Resume_02
Pieter_Christian_Le_Roux's_Resume_02
 
Sivan N Resume 2016
Sivan N Resume 2016Sivan N Resume 2016
Sivan N Resume 2016
 
Michael Seebeck Resume
Michael Seebeck ResumeMichael Seebeck Resume
Michael Seebeck Resume
 
Resume
ResumeResume
Resume
 
(Reviewed) Resume Mayeta 2016
(Reviewed) Resume Mayeta 2016(Reviewed) Resume Mayeta 2016
(Reviewed) Resume Mayeta 2016
 
Vineet Resume with 5.9 years of Experience in Cisco Contact Center
Vineet Resume with 5.9 years of Experience in Cisco Contact CenterVineet Resume with 5.9 years of Experience in Cisco Contact Center
Vineet Resume with 5.9 years of Experience in Cisco Contact Center
 
MyResume
MyResumeMyResume
MyResume
 
Prakash soni
Prakash soniPrakash soni
Prakash soni
 
Practical Routers & Switches for Electrical Engineers
Practical Routers & Switches for Electrical EngineersPractical Routers & Switches for Electrical Engineers
Practical Routers & Switches for Electrical Engineers
 
Pm deep dive scope management
Pm deep dive   scope managementPm deep dive   scope management
Pm deep dive scope management
 

Similar to Project Plan

Running head CIS 532 Term PaperAssignment 5 .docx
Running head CIS 532 Term PaperAssignment 5 .docxRunning head CIS 532 Term PaperAssignment 5 .docx
Running head CIS 532 Term PaperAssignment 5 .docx
todd271
 
Network Developement Capstone Project 2009 Sping Quarter
Network Developement Capstone Project 2009 Sping QuarterNetwork Developement Capstone Project 2009 Sping Quarter
Network Developement Capstone Project 2009 Sping Quarter
richlan421
 
CLASS NAMEMIS600PROFESSORS NAME STUDENTS NAME PRO.docx
CLASS NAMEMIS600PROFESSORS NAME STUDENTS NAME PRO.docxCLASS NAMEMIS600PROFESSORS NAME STUDENTS NAME PRO.docx
CLASS NAMEMIS600PROFESSORS NAME STUDENTS NAME PRO.docx
monicafrancis71118
 
Muaya cv 30.11.2015
Muaya cv 30.11.2015Muaya cv 30.11.2015
Muaya cv 30.11.2015Muayad Odeh
 
VISHAL KESWANI -May 2015
VISHAL KESWANI -May 2015VISHAL KESWANI -May 2015
VISHAL KESWANI -May 2015Vishal Keswani
 
181472589 basis project report
181472589  basis project report181472589  basis project report
181472589 basis project report
IsmailSaruar
 
Why is Network Planning and Design So Important.pptx
Why is Network Planning and Design So Important.pptxWhy is Network Planning and Design So Important.pptx
Why is Network Planning and Design So Important.pptx
Bluechip Gulf IT Services
 
Waqas Khan(Project Manager)
Waqas Khan(Project Manager)Waqas Khan(Project Manager)
Waqas Khan(Project Manager)zzaakk10
 
Adeel Technical Project management
Adeel Technical Project managementAdeel Technical Project management
Adeel Technical Project managementEngineer Adeel Ahmad
 
CIS337– Networking in Business Unit 6 Assignment Final
CIS337– Networking in Business  Unit 6 Assignment FinalCIS337– Networking in Business  Unit 6 Assignment Final
CIS337– Networking in Business Unit 6 Assignment Final
VinaOconner450
 
Fibersat network company profile
Fibersat network company profileFibersat network company profile
Fibersat network company profile
MOHDSUZALEEAMINUDDIN
 
CPIN 269 Final Documentation
CPIN 269 Final DocumentationCPIN 269 Final Documentation
CPIN 269 Final DocumentationJennifer Cordes
 
BI CV 6 June 2016 [448161]
BI CV 6 June 2016 [448161]BI CV 6 June 2016 [448161]
BI CV 6 June 2016 [448161]Bassem Kamel
 
Design Scenario Network Analysis & Design
Design Scenario Network Analysis & Design   Design Scenario Network Analysis & Design
Design Scenario Network Analysis & Design
Muhd Mu'izuddin
 
Carl Dean - CV
Carl Dean - CVCarl Dean - CV
Carl Dean - CVCarl Dean
 
Mortgage Bank Implementation Process
Mortgage Bank Implementation ProcessMortgage Bank Implementation Process
Mortgage Bank Implementation Process
Dan Nelson
 
ITP-1 – Project CharterGroup 3 - The Project Management Masters .docx
ITP-1 – Project CharterGroup 3 - The Project Management Masters .docxITP-1 – Project CharterGroup 3 - The Project Management Masters .docx
ITP-1 – Project CharterGroup 3 - The Project Management Masters .docx
priestmanmable
 

Similar to Project Plan (20)

Running head CIS 532 Term PaperAssignment 5 .docx
Running head CIS 532 Term PaperAssignment 5 .docxRunning head CIS 532 Term PaperAssignment 5 .docx
Running head CIS 532 Term PaperAssignment 5 .docx
 
Network Developement Capstone Project 2009 Sping Quarter
Network Developement Capstone Project 2009 Sping QuarterNetwork Developement Capstone Project 2009 Sping Quarter
Network Developement Capstone Project 2009 Sping Quarter
 
CLASS NAMEMIS600PROFESSORS NAME STUDENTS NAME PRO.docx
CLASS NAMEMIS600PROFESSORS NAME STUDENTS NAME PRO.docxCLASS NAMEMIS600PROFESSORS NAME STUDENTS NAME PRO.docx
CLASS NAMEMIS600PROFESSORS NAME STUDENTS NAME PRO.docx
 
Muaya cv 30.11.2015
Muaya cv 30.11.2015Muaya cv 30.11.2015
Muaya cv 30.11.2015
 
VISHAL KESWANI -May 2015
VISHAL KESWANI -May 2015VISHAL KESWANI -May 2015
VISHAL KESWANI -May 2015
 
181472589 basis project report
181472589  basis project report181472589  basis project report
181472589 basis project report
 
Why is Network Planning and Design So Important.pptx
Why is Network Planning and Design So Important.pptxWhy is Network Planning and Design So Important.pptx
Why is Network Planning and Design So Important.pptx
 
Waqas Khan(Project Manager)
Waqas Khan(Project Manager)Waqas Khan(Project Manager)
Waqas Khan(Project Manager)
 
LaMima Gilbert Lewis PM
LaMima Gilbert Lewis PMLaMima Gilbert Lewis PM
LaMima Gilbert Lewis PM
 
Mohsin-Hussain Resume-31122014
Mohsin-Hussain Resume-31122014Mohsin-Hussain Resume-31122014
Mohsin-Hussain Resume-31122014
 
Adeel Technical Project management
Adeel Technical Project managementAdeel Technical Project management
Adeel Technical Project management
 
CIS337– Networking in Business Unit 6 Assignment Final
CIS337– Networking in Business  Unit 6 Assignment FinalCIS337– Networking in Business  Unit 6 Assignment Final
CIS337– Networking in Business Unit 6 Assignment Final
 
Fibersat network company profile
Fibersat network company profileFibersat network company profile
Fibersat network company profile
 
CPIN 269 Final Documentation
CPIN 269 Final DocumentationCPIN 269 Final Documentation
CPIN 269 Final Documentation
 
Eyer
EyerEyer
Eyer
 
BI CV 6 June 2016 [448161]
BI CV 6 June 2016 [448161]BI CV 6 June 2016 [448161]
BI CV 6 June 2016 [448161]
 
Design Scenario Network Analysis & Design
Design Scenario Network Analysis & Design   Design Scenario Network Analysis & Design
Design Scenario Network Analysis & Design
 
Carl Dean - CV
Carl Dean - CVCarl Dean - CV
Carl Dean - CV
 
Mortgage Bank Implementation Process
Mortgage Bank Implementation ProcessMortgage Bank Implementation Process
Mortgage Bank Implementation Process
 
ITP-1 – Project CharterGroup 3 - The Project Management Masters .docx
ITP-1 – Project CharterGroup 3 - The Project Management Masters .docxITP-1 – Project CharterGroup 3 - The Project Management Masters .docx
ITP-1 – Project CharterGroup 3 - The Project Management Masters .docx
 

Project Plan

  • 2. 2 Table of Contents Page 3: Project Charter Page 8: Scope Statement Page 13: Work Breakdown Structure Page 14: Network Diagram Page 15: Risk Management Plan Page 17: Resource Management Plan Page 18: Communication management plan
  • 3. 3 Project Charter Project Name Design and installation of a computer network for Fortify Satellite Office Project Number 1 Project Manager Mohammad Yousef Prioritization 1 Owner(s) Keith Earnshaw Start Date: 3/09/2014 Scheduled Completion Date: 4/01/2014 Mission/ Purpose What is your project going to accomplish? How does this project relate to overall goals and objectives of the company? It is part of a program or larger project? To design and install a computer network for the new Fortify Satellite office based on network and user requirements. SOW What will this project create? What is the product of the project? At a high level, how do you plan on doing the work of the project? What are the high-level deliverables for this project? This project will create a new network for the new office of Fortify based on their user requirements. It will allow the staff of Fortify to work efficiently and keep up productivity. The product of this project is a new computer network system. I plan on first going over the requirements of the network provided by the company (Fortify). Based on how many users and network requirements, and office/building specs, I will decide the necessary equipment and hardware. I will then go on sight to draw blueprints of the design of the network for the office. I plan on doing the project with my team on sight. All installation, implementation, and configurations will be done on sight. The deliverables for this project is to have a a proper, efficient network to allow the staff to work productively.
  • 4. 4 Objectives What objectives, if any, of the company is this project designed to meet? 1.) Fast connection and easily accessible network 2.) Quality VoIP to ensure best customer service by staff 3.) Design and install quality equipment and configurations to have lowest possibilities of network failure. 4.) Complete in a timely fashion in order to allow staff members to begin working in the new office. Business Need Why should we do this project? What will be gained, changed, or modified? Is there a financial or business reason to do this project? This area should contain any feasibility studies, NPV, PI, PB, or PBD used to advance the project. The project must be done to allow new satellite office to be used. The staff can not start working in the new office location unless they have network connectivity. Fortify is a growing company and is constantly expanding and creating new offices all over the world. In order to work from a satellite office, there must be an efficient network in place to allow communication between office and HQ as well as clients. Without a network in place, the staff will be useless and not be able to communicate to the outside world or get any work done. A quality network is essential for staff members in the Chicago office to succeed. Project Manager and Stakeholders Who will lead this project? Who are the major stakeholders? I will lead the project in designing and supervising the team to install, implement, and configure the network. The major project stake holders are the staff of the new office and upper management of Fortify approving the project and approving the budget. Milestones What are the key milestone dates associated with the project?
  • 5. 5  Initial consultancy - 3/15/2014  Design and planning - 3/20/2014  Implementation - 4/01/2014  Troubleshooting – 4/02/2014  Training – 4/10/2014 Budget What is the order-of-magnitude budget for this project? $8,500 (-$2,125) (+$2,975) User Acceptance Criteria/Quality What are the minimum success criteria as defined by the key stakeholders? A working computer network system and VoIP service High-Level Project Assumptions What are the assumptions on which the project is based? The assumptions of this project are the network will be working properly with minimal network failure and will be completed by the quotes time in order to move the staff into the new office. High-Level Project Constraints What are the major limiting factors that affect the project? There are not many constraints besides the budget. If we can meet at the agreed budget, there should be no other constraints. The timeline has been agreed between both parties and is easily manageable within the given time request. Exclusions and Boundaries What are the boundaries of the project? What is to be included and what is to be excluded from the project?
  • 6. 6 Exclusions include 1.) Admin access to staff members 2.) Network failure due to uncontrollable circumstances (i.e. natural disasters/weather related, service providers network failure, and building network failures) Major Risks What are the major risks affecting the project? The major risks involved are going over budget and unforeseeable/network network failures. KEY STAKEHOLDERS Project Manager Authority Level Legitimate Project Core Team
  • 7. 7 Mohammad Yousef – Design and Supervision Adam Case – Implementation Sam Hughes – Implementation Drake Seems - Training Subject Matter Experts (SMEs) (include company and channel designations if applicable) Fortify APPROVALS Type Name Signature Date Project Manager Approval: Mohammad Yousef 03/09/14 Customer/Sponsor Approval: Robert Grady 03/09/14
  • 8. 8 Project Scope Statement Project Name Design and installation of a computer network for Fortify Satellite Office Project Number 1 Project Manager Mohammad Yousef Prioritization 1 Owner(s) Keith Earnshaw Statement of Work— Project Description and Project Product This project will create a new network for the new office of Fortify based on their user requirements. It will allow the staff of Fortify to work efficiently and keep up productivity. We intend to do this by installing and implementing top of the line equipment and correct configurations based on the users requirements. We plan on using only Cisco equipment (i.e. routers, switches, etc) All of our techs are well rehearsed in network design and have their Cisco certifications. This will all benefit the project and assure that everything goes accordingly. The product of this project is a new computer network system. I plan on first going over the requirements of the network provided by the company (Fortify). Based on how many users and network requirements, and office/building specs, I will decide the necessary equipment and hardware. I will then go on sight to draw blueprints of the design of the network for the office. I plan on doing the project with my team on sight. All installation, implementation, and configurations will be done on sight. The deliverables for this project is to have a a proper, efficient network to allow the staff to work productively. We believe that we will need a total of 1 Cisco Router, 2 Cisco access point, 1 Cisco 24 port switch, 300 feet of cat 6 cables, and 6 Cisco VoIP phones. Our techs will install all the equipment first. They will then run the cables so they are not in the way. We well then configure the network, test, and trouble shoot for any issues.
  • 9. 9 Project Deliverables 1.) The network will be working properly with minimal network failure and will be completed by the quotes time in order to move the staff into the new office. 5.) Fast connection and easily accessible network 6.) Quality VoIP to ensure best customer service by staff 7.) Design and install quality equipment and configurations to have lowest possibilities of network failure. 8.) Complete in a timely fashion in order to allow staff members to begin working in the new office. Project Objectives 1.) Fast connection and easily accessible network 2.) Quality VoIP to ensure best customer service by staff 3.) Design and install quality equipment and configurations to have lowest possibilities of network failure. 4.) Complete in a timely fashion in order to allow staff members to begin working in the new office. 5.) Keep the cost of the project under the estimated budget which was $8,500 (-$2,125) (+$2,975) 6.) We arrived at this number through the use of the following equation: Budget Estimate (Variance of -10% to +25%) Project Assumptions The assumptions of this project are the network will be working properly with minimal network failure and will be completed by the quotes time in order to move the staff into the new office. Project Constraints There are not many constraints besides the budget. If we can meet at the agreed budget, there should be no other constraints. The timeline has been agreed between both parties and is easily manageable within the given time request. Exclusions Exclusions include 3.) Admin access to staff members 4.) Network failure due to uncontrollable circumstances (i.e. natural disasters/weather related, service providers network failure, and building network failures) Acceptance Criteria A working computer network system and VoIP service with minimal network failures. The VoIP service must have good call quality and maintain a 90% up time. If updates are required and network and VoIP services will be down, we must give a 2 week notice before hand for quality assurance from Fortify to customers.
  • 10. 10 Technical Requirements Hardware Cisco UCS C210M2 for non NEBs Compliant Systems Software Linux RedHat RHEL 5 Update 3 or Update 5 (64 bit). See Linux Update Requirements for details on the required Linux updates. CPU Type 6-core (Cisco UCS C210M2) CPU Number 6 CPU Speed 3 GHz Memory (RAM) 32 GB or greater Swap Space 32 GB or greater Storage • Cisco UCS C210M2—Expansion, Performance, and Reliability Option – For OS: One 146 GB SAS 15K RPM Drive – For database using RAID10: Six 146 GB SAS 15K RPM Drives – For backups using RAID10: Four 300 GB SAS 10K RPM Drives – Requires usage Of LSI MegaRAID Controllers – Dual PowerSupply • Cisco UCS C210M2—Performance Option – For OS: One 146 GB SAS 15K RPM Drive – For database using RAID10: Six 146 GB SAS 15K RPM Drives – For backups: One 600 GB SAS 10K RPM Drive – Requires Usage Of LSI MegaRAID Controllers • Cisco UCS C210M2—Basic Option With Additional Performance – For OS: One 146 GB SAS 15K RPM Drive – For database using RAID0: Two 300 GB SAS 10K RPM Drives
  • 11. 11 – For backups: One 600 GB SAS 10K RPM Drive – Uses LSI Mezzanine RAID Controller • Cisco UCS C210M2—Basic Option – For OS: One 146 GB SAS 15K RPM Drive – For database: One 300 GB SAS 10K RPM Drives – For backups: One 600 GB SAS 10K RPM Drive – Uses LSI Mezzanine RAID Controller APPROVALS Type Name Signature Date Project Manager Approval: Mohammad Yousef 03/23/14 Customer/Sponsor Approval: Robert Grady 03/23/14
  • 14. 14
  • 16. 16