The document summarizes a project to install an advanced home theater and video conferencing system in a newly constructed auditorium at Bahria University in Islamabad, Pakistan. The project will include interior development works, electrical wiring, equipment installation for the home theater and video conferencing systems, and maintenance. The contractor will be responsible for delivering and installing all hardware and software, and training university staff on the new systems over a four month period of performance according to the requirements in the document.
V 2.0Project Scope StatementProject NameSpeakeasy Ho.docxdickonsondorris
V 2.0
Project Scope Statement
Project Name
Speakeasy Hotel Network Installation
Project Number
P05258-5
Project Manager
Timothy P Ross
Prioritization
1A
Owner(s)
Trifecta Corp. ( Owners - David Eaker, Troy Gray, and Coura Badiane )
Statement of Work—Project Description and
Project Product
The purpose of the project is to coordinate and successfully install the network infrastructure in the Speakeasy Hotel in order to ensure a smooth operational grand opening that will provide administrative and guest network services including; phone, video, internet, security, guest tracking, and POS system. Trifecta inc. is renovating a new acquisition in preparation of a scheduled grand opening. This project will help Speakeasy to better serve their client base, make their stay comfortable and enjoyable and better enable the staff to manage the day to day activities of the hotel. The scope of this network installation includes the planning, design, deployment, configuration, testing, and transition of the network system. This network will meet or exceed organizational requirements established in the project charter. The scope of this project also includes the completion of all documentation, manuals, and training aides to be used in conjunction with the various systems. Project completion will occur when the network and documentation package has been successfully executed.
We intend to execute this project by completing the following:
1. Maintain focus on the implementation of the approved LAN Vendor solution and ongoing support services, including but not limited to;
2. Project Management, serving as a local single point of contact for the Owner/Operator ( Trifecta inc. )
3. Implementing the approved LSP solution including the installation of all equipment, configuration, integration, and testing.
4. Obtain all onboarding documents from network vendors specifying network requirements for IPTV system, Security system, Phone system, Business Center, Guest Services System, and Point of Sale System.
5. Perform a site survey to determine strategic location of equipment deployment for maximum coverage and reliability.
6. Utilize the LAN Vendor as to test and ensure all vendor equipment communicates effectively on the network observing high network security standards and routing protocols.
7. Obtain a contract for 3 – 5 years for ongoing customer support utilizing Helpdesk Services, a Remote Call Center, a Remote Network Operations Center ( NOC ), and arranging onsite support as necessary to maintain network integrity.
8. Obtain all network drawings, applicable licenses & permits, equipment specifications, port mapping/ identification information, training documentation, and warranty documentation to ensure Speakeasy staff is able to effectively identify and support equipment at the hotel.
Project Deliverables
There are 4 tangible services being provided from this network installation project. Each service is being installed by a separate vendo ...
V 2.0Project Scope StatementProject NameSpeakeasy Ho.docxdickonsondorris
V 2.0
Project Scope Statement
Project Name
Speakeasy Hotel Network Installation
Project Number
P05258-5
Project Manager
Timothy P Ross
Prioritization
1A
Owner(s)
Trifecta Corp. ( Owners - David Eaker, Troy Gray, and Coura Badiane )
Statement of Work—Project Description and
Project Product
The purpose of the project is to coordinate and successfully install the network infrastructure in the Speakeasy Hotel in order to ensure a smooth operational grand opening that will provide administrative and guest network services including; phone, video, internet, security, guest tracking, and POS system. Trifecta inc. is renovating a new acquisition in preparation of a scheduled grand opening. This project will help Speakeasy to better serve their client base, make their stay comfortable and enjoyable and better enable the staff to manage the day to day activities of the hotel. The scope of this network installation includes the planning, design, deployment, configuration, testing, and transition of the network system. This network will meet or exceed organizational requirements established in the project charter. The scope of this project also includes the completion of all documentation, manuals, and training aides to be used in conjunction with the various systems. Project completion will occur when the network and documentation package has been successfully executed.
We intend to execute this project by completing the following:
1. Maintain focus on the implementation of the approved LAN Vendor solution and ongoing support services, including but not limited to;
2. Project Management, serving as a local single point of contact for the Owner/Operator ( Trifecta inc. )
3. Implementing the approved LSP solution including the installation of all equipment, configuration, integration, and testing.
4. Obtain all onboarding documents from network vendors specifying network requirements for IPTV system, Security system, Phone system, Business Center, Guest Services System, and Point of Sale System.
5. Perform a site survey to determine strategic location of equipment deployment for maximum coverage and reliability.
6. Utilize the LAN Vendor as to test and ensure all vendor equipment communicates effectively on the network observing high network security standards and routing protocols.
7. Obtain a contract for 3 – 5 years for ongoing customer support utilizing Helpdesk Services, a Remote Call Center, a Remote Network Operations Center ( NOC ), and arranging onsite support as necessary to maintain network integrity.
8. Obtain all network drawings, applicable licenses & permits, equipment specifications, port mapping/ identification information, training documentation, and warranty documentation to ensure Speakeasy staff is able to effectively identify and support equipment at the hotel.
Project Deliverables
There are 4 tangible services being provided from this network installation project. Each service is being installed by a separate vendo ...
The must-have program/project management reporting feature before applying f...Shane Emerson
Learn more about CEC-NG Government Contract Requirements in terms of the technical functional requirements which every contract should abide by concerning the CEC-NG contract.
Technical functional requirements every contractor must adhere to before appl...Shane Emerson
Learn more about CEC-NG Government Contract Requirements in terms of the technical functional requirements which every contract should abide by concerning the CEC-NG contract.
This project was a culmination of two years of study at ITT-Technical Institutes\'s Bessemer, AL campus for an Associates degree in ITCNS (Information Technology Computer Network Systems). It was a team project of 7 members with the goal of designing a network solution for a fictional medical practice consolidation of 5 doctors in a company named Radiant Medical Services.
The Must-Have Program/Project Management Reporting Feature before Applying fo...Shane Emerson
The document has provided you with enough insights about the C4ISR-TLS contract. Not only will this document help you in having a thorough knowledge about the contract requirements and stuff but also it would help you in selecting the best eCommerce solution
Jennifer Schaus and Associates hosts a complimentary webinar series on The FAR in 2024. Join the webinars on Wednesdays and Fridays at noon, eastern.
Recordings are on YouTube and the company website.
https://www.youtube.com/@jenniferschaus/videos
A process server is a authorized person for delivering legal documents, such as summons, complaints, subpoenas, and other court papers, to peoples involved in legal proceedings.
Russian anarchist and anti-war movement in the third year of full-scale warAntti Rautiainen
Anarchist group ANA Regensburg hosted my online-presentation on 16th of May 2024, in which I discussed tactics of anti-war activism in Russia, and reasons why the anti-war movement has not been able to make an impact to change the course of events yet. Cases of anarchists repressed for anti-war activities are presented, as well as strategies of support for political prisoners, and modest successes in supporting their struggles.
Thumbnail picture is by MediaZona, you may read their report on anti-war arson attacks in Russia here: https://en.zona.media/article/2022/10/13/burn-map
Links:
Autonomous Action
http://Avtonom.org
Anarchist Black Cross Moscow
http://Avtonom.org/abc
Solidarity Zone
https://t.me/solidarity_zone
Memorial
https://memopzk.org/, https://t.me/pzk_memorial
OVD-Info
https://en.ovdinfo.org/antiwar-ovd-info-guide
RosUznik
https://rosuznik.org/
Uznik Online
http://uznikonline.tilda.ws/
Russian Reader
https://therussianreader.com/
ABC Irkutsk
https://abc38.noblogs.org/
Send mail to prisoners from abroad:
http://Prisonmail.online
YouTube: https://youtu.be/c5nSOdU48O8
Spotify: https://podcasters.spotify.com/pod/show/libertarianlifecoach/episodes/Russian-anarchist-and-anti-war-movement-in-the-third-year-of-full-scale-war-e2k8ai4
Understanding the Challenges of Street ChildrenSERUDS INDIA
By raising awareness, providing support, advocating for change, and offering assistance to children in need, individuals can play a crucial role in improving the lives of street children and helping them realize their full potential
Donate Us
https://serudsindia.org/how-individuals-can-support-street-children-in-india/
#donatefororphan, #donateforhomelesschildren, #childeducation, #ngochildeducation, #donateforeducation, #donationforchildeducation, #sponsorforpoorchild, #sponsororphanage #sponsororphanchild, #donation, #education, #charity, #educationforchild, #seruds, #kurnool, #joyhome
ZGB - The Role of Generative AI in Government transformation.pdfSaeed Al Dhaheri
This keynote was presented during the the 7th edition of the UAE Hackathon 2024. It highlights the role of AI and Generative AI in addressing government transformation to achieve zero government bureaucracy
1. Project Appraisal Document (PAD)
Title: Installation of Home-Theater & Video Conferencing System in the Newly Constructed
Auditorium at Bahria University, Islamabad Campus.
The objective of the AV and HT systems installation & interior development activity is to make
available state-of-the –art facilities for Bahria University members for inter-university communication
at global level and recreational purposes at local level for the university academia, staff and students.
Bahria University Islamabad Campus intends to install a state-of-the–art Home theater (HT) system to
give a cinematic functionality to the venue and to provide the subject facility of video conferencing and
entertainment for its members. The size of the auditorium is 150’x80’. The structure includes the
audio-visual (AV) system, sitting arrangement through reclining chairs and the noise-cancelling wall
paneling as interior development activities. The University also intends to have a video conferencing
system for two-way communication with world’s leading universities. All the sub-activities will be
executed in a single contract, with multiple work packages.
The project will be funded by Government funds under the Federal PPRA Rules 2004.
The tasks include Interior Development Works for the reclining chairs, Interior Development Works for
noise-canceling wall paneling, Electrical works for the new HT system wiring, Electrical works for the
new VC system wiring, Installation of Home Theater (HT) Equipment, Installation of Video
Conferencing (VC) Equipment, Civil works for installation fixtures, Electrical works for Uninterrupted
power supply, Plumbing works/waste water flushing, Maintenance /repair of the facility, Patio Tiling
and Vehicle Parking. The Work Requirements for the this contract include the contractual service
which must be accomplished through single point of contact through contractor’s project manager who
will liaise with the University’s Project Director for precise measurements, tolerances, materials,
quality control requirements, and other Government requirements that control the processes of the
Contractor.
The Contractor shall install the hardware and software for both the systems for testing in the
Auditorium to determine digital capability of the systems with the ability to record at least five streams
of input simultaneously. The upgrade shall include a digital face camera that video records a
participant’s face, feed from an overhead camera, an audio input component, The Contractor’s
system shall have the ability to record voice notes over the combined recording after the fact, and
include some sort of logging recording along with these other five streams of data.
• The software described above shall allow real-time flagging of digital data feed so that later
coding can be done where the feed was flagged. This later coding will entail detailed behavior
coding.
• 50” LED high definition TV for VC with all cables included capable of picture-in-picture display
of screen and participant.
• Streamline the wiring feed between the control room and the center stage to eliminate wire
cluttering.
• Ensure all hardware and software communicates across systems and software.
The HT System will be installed as per technical specifications given in the Technical Specification
Section of the Standard Bidding Documents (SBDs).
2. Hardware and software shall be delivered free of defects and viruses and shall be installed and
demonstrated to work is accordance with the above requirements prior to acceptance. Program
Manager and Project Director will notify vendor in writing of acceptance.
NOTE: In this section, remote computer access refers to any number of services where the vendor is
able to view the screen of the lab computers remotely and walk the user through the trouble-shooting
process while looking at the same screen.
The maintenance contract is for the period of one fiscal year with one (1) option year to renew at the
end of the initial year. The contractor shall give an estimate for one year of maintenance service only.
The Contractor shall also Provide two site visits during the period of performance to 1) ensure that all
of the hardware and software in the Auditorium is functioning correctly, efficiently and in accordance
with the specifications and standards provided in each component’s manual and according to industry
standards and, 2) solve equipment or software problems as reported in writing by the program
manager. He shall maintain functional control of the two installed systems from the control room
during testing sessions as well as bi-directional audio video communication between the control room
and the connected station (s). He shall maintain functional transmission of participant video and audio
feed along with screen shot feed in real time to the observation screen. He shall respond to requests
for maintenance within 24 hours of request. He shall respond to basic questions about hardware and
software within 12 business hours of request. He shall provide trouble-shooting/remote assistance on
an unlimited basis during period of performance. The hardware required to achieve this remote control
from the control room shall include updated and streamlined hardware.
The University expects to accomplish under the contract the completion of the tasks at the same time
within the budgetary allocation for new systems installation and interior development, both within four
months under the Lump sum Fixed price contract.
Place of performance will be the North-East side of the University on Plot coordinates latitude 37’-09
and 14’-38 Longitude. The said coordinates will be indicated by the PD on the Coordinates map and
will be given to the Contractor after contract award.
A combination of hardware and software/firmware that performs a dedicated function serving a
Government requirement, including, but not limited to electronics equipment, networks, shelters,
ground support equipment, and support structures. These also include all University-furnished
property, as mentioned in the lists at the time of contract award.
Certain University office or laboratory space may be made available for performance of specific
Tasks. Contractor may be required to establish operations and support facilities and warehouses
within a University-provided facility that comply with Product or process certification and accreditation
requirements
The unique security requirements associated with contract performance:
• Special pass for identification requirements will be issued by the University management.
Project Director will sign the said passes.
• All contractor personnel will require special security clearance as the contract performance site
belongs to an Defence establishment;
• Special escort requirements arranged by the PD will be required for the Contractor’s
specialized technical staff to University’s server rooms, IT installations and electricity facilities.
Including generator room.
The signaling and ICT gadgets are required to be inspected by the University’s Security staff before
giving a green flag to the same for their entry into the premises. Such equipment whose frequency
may interfere with the frequency of the signaling equipment of the Defence establishments, will be
treated as Special materials and their transport, entry and handling will be treated differently as per
the SOPs issued by the PD in this regard. The Contractor may describe requirements for any other
special materials that are to be encountered in the performance of the service(s).
3. The Contractor must deliver its technical input on the schematic drawings of the new structure for civil,
plumbing and electrical works 7 days after the contract award.
The Contractor must deliver the work schedule in Primavera Project Planner not more than 7 days
after the submission of its technical input.
The deliverables shall include complete, functional system including hardware and software as
described above. The whole system should function to support the daily workflow of the functions,
maintenance both remotely and on-site twice per fiscal year, provision by contractor before
installation, of upgrade, detailed diagrams and descriptions of the work that will be done as well as
contact information for the person to be contacted for trouble-shooting for each component of the
system. After installation, he needs to provide detailed specs, diagrams, and manuals to document
the new equipment setup and functionality. Contractor shall give 2-3 hours training on the new
equipment and at least 4 hours training on the new integrated software system for up to 8 University
employees. He shall visit two site visits during contract performance.
In order to maintain the hassle-free traffic of vehicles and undisturbed flow of student entry into the
university premises, the Contractor’s personnel will be allowed to travel to the back gate of the
University through the passage which is otherwise exclusively reserved for the defence personnel for
reaching the Bahria and Air Force establishments. The Contractor may require to tell any other travel
requirements that are to be encountered in the performance of the service(s).
The Contractor may describe requirements for any other unique materials that are to be encountered
in the performance of the service(s) or considerations.
The period of performance is not more than four months from the date of award of contract.