SlideShare a Scribd company logo
1 of 8
Uttaranchal Jal Vidyut Nigam Limited (UJVNL) with it's headquarter at Dehradun in the state of
Uttaranchal (India) is operating, maintaining & constructing Hydro Power Plants.

 Dehradun is the capital of the state of Uttaranchal and is approximately 300 km far in northern
direction from New Delhi closed to the Himalayan Mountains and well-connected through road,
rail & air. The main concern in this project is the rehabilitation of the following 5 power stations
below.

       Chibro with Ichari Dam
       Khodri
       Dhakrani
       Dhalipur
       Kulhal

In this project was an assessment of the current physical condition of all of the 5 plants, which
includes a survey of the project area and an inspection of all plant equipment, collection of data,
records and statistics referring to the operation of the plants related to the I&C system.
Furthermore, develop preliminary feasible options for modernization and upgrading and a state
of the art control concept for all of the 6 power stations.
TONS RIVER VALLEY POWER STATIONS

Chibro & Khodri Power Stations utilize the water of river Tons. Tons river is an important
tributary of the Yamuna River. This river joins Yamuna at Kalsi in the Northwestern part of
Dehradun valley, which is approximately 50 km. away from Dehradun. A diversion dam across
the river Tons has been constructed at Ichari with a 6.2 km long headrace tunnel from the
diversion dam to Chibro under ground power station. Ichari is approximately 100 km from
Dehradun in the hilly terrain.




   Tons river upstream from Ichari dam   Ichari dam on Tons river   Tons river downstream
CHIBRO POWER STATION




Chibro power station is an underground power station built on the left bank of river Tons nearly
25 km downstream of Ichari dam and 75 km from Dehradun and it surrounded by hills. The
power station is located at 33° 33' 23" N & 077° 47'50" E. The power station was commissioned
in 1975.

The power station consists of four generating units each having a capacity of 60 MW. The total
installed electrical capacity is 240 MW.

The main power station equipments including turbine, generator and power transformer had been
supplied by M/s Bharat Heavy Electrical Ltd. Bhopal.

The turbines are Vertical shaft Francis turbines. Each unit has its own penstock with a butterfly
valve. The power station is provided with a unit system of layout, where each generator is
directly connected to a power transformer.

For the outdoor switchyard, 220 kV oil filled cables coming from transformers situated in
powerhouse. The Switchyard is connected through two 220 kV outgoing feeders to Khodri.




         220 kV Switchyard              Central Control Room          Cavern with Control Room
KHODRI POWER STATION




The tail water collection gallery of Chibro power house supplies water to the power Tunnel of
Khodri Power House by means of a siphon across river Tons.

Khodri power station is a 4x30 MW surface power station built on right bank of river Yamuna
and is nearly 50 km from Dehradun.

The power station is located at 30° 30' 30" N & 077° 47'58" E closed to the barrage across river
Yamuna at Dakpathar. The power station was commissioned in 1984.

The headrace tunnel system consider a 7.5 m in diameter concrete lined circular tunnel with 4628
m length and three tunnels of smaller diameter in remaining length.

The total length of the tunnel system is 5.6 km. The tailrace is a short open channel connecting to
river Yamuna.

The power station consists of four generating units each having a capacity of 30 MW. The total
installed electrical capacity is 120 MW. The main power station equipments including turbine,
generator and power transformer had been supplied by M/s Bharat Heavy Electrical Ltd. Bhopal.
The turbines are Vertical shaft Francis turbines.




         220 kV Switchyard                  Turbine Hall                 Central Control Room
YAMUNA RIVER VALLEY

River Yamuna originates from the Himalayas and is joined by its major tributary the Tons at
Kalsi, approximately 50 Km from Dehradun. The Yamuna river collect the water from an
elaborate web of water channels all across North India. These tributaries of Yamuna are the main
source of water in Northern India. A barrage across river Yamuna at Dakpathar 3 Km
downstream of Kalsi has been constructed. 14 Km power channel takes of at the Dakpathar
barrage having its outfall into the river Asan, immediately upstream of the junction of Asan and
Yamuna rivers.

Dhakrani & Dhalipur are the two power stations along this power channel with a total installed
capacity of 84.75 MW. Another power channel takes of at Asan barrage having its outfall into
the river Yamuna near Paonta Sahib. Kulhal power station with a capacity of 3x10 MW is
running along this power channel.




   Yamuna River Valley Downstream        Dakpathar Barrage          Yamuna River Valley Upstream
DHAKRANI POWER STATION




Dhakrani power station is a 3x11.25 MW surface power station located at a distance of
approximately 40 km from Dehradun. It is built on the power channel emanating from Dakpathar
Barrage & is approximately 7 Km from Dakpathar Barrage.

The power station is located at 30° 27' 25" N & 077° 44'13" E. The commissioning for 2 units
was in 1965 and the last unit was commissioned in 1970.

Dhakrani is the first of two power stations (Dhalipur is following) running in cascade and using
the same power channel down stream from Dakpathar.

The power station consists of three generating units each having a capacity of 11.25 MW. The
total installed electrical capacity is 33.75 MW.

The main power station equipments including turbine and generator had been supplied by M/s
Litostroj, Yugoslavia. The turbines are Vertical shaft Kaplan turbines.




         Water Intake Gates                Turbine Hall                Central Control Room
DHALIPUR POWER STATION




Dhalipur is a 3x17 MW surface power station built down stream of Dhakrani power station,
which is 7 km from Dhakrani and about 12 km down stream of Dakpathar barrage.

The power station is located at 30° 27' 22" N & 077° 44'1" E. This power station utilizes the
discharge of Tons and Yamuna Rivers through a 12 km long channel. The commissioning for the
three units started in 1965, 1966 and finnished in1970.

The total installed electrical capacity is 51 MW. The designed head is 30.5 meter with a
maximum discharge of 200 cubic meter. The main turbine equipment for the power station was
supplied by M/s Litostroj, Yugoslavia and main electric equipment by M/s Rade Koncar,
Yugoslavia through M/s Ingra Zegreb.

The transformers were supplied by M/s Heavy Electrical (India) Ltd. Bhopal having 20 MVA
capacity each. The turbines are Vertical shaft Francis turbines.




         Bypass Channel                  Turbine Hall                Central Control Room
KULHAL POWER STATION




Kulhal is a 3x10 MW surface power station built down stream of Dhalipur power station and is 5
km from Asan Barrage. The power station is located at 30° 25' 42" N & 77° 37'49" E.

It is situated on left bank of river Yamuna, opposite Paonta Saheb town of Himachal Pradesh and
is about 4.5 Km downstream of Asan Barrage and about 50 Km from the nearest Railhead,
Dehradun.

This surface power station utilizes the discharge of Tons, Yamuna and Asan River through a 4.5
Km long power channel. The commissioning of the units was in 1975.

The total installed electrical capacity is 30 MW with a head of 18 meters. M/s BHEL, Hardwar,
supplied the main turbine & electrical equipments of this power station.

The Power Transformers, each of 12.5 MVA capacity were supplied by M/s Transformers and
Electricals Ltd., Kerala (India). The turbines are Vertical shaft Kaplan turbines.




          Bypass Channel                  Turbine Hall                Central Control Room

More Related Content

What's hot

EE6801 - Electric Energy Generation Utilisation and Conservation
EE6801 - Electric Energy Generation Utilisation and ConservationEE6801 - Electric Energy Generation Utilisation and Conservation
EE6801 - Electric Energy Generation Utilisation and Conservationrmkceteee
 
Electricity generation, distribution and transmission
Electricity generation, distribution and transmissionElectricity generation, distribution and transmission
Electricity generation, distribution and transmissionAshar143
 
RRVUN hydro power plant
RRVUN hydro power plantRRVUN hydro power plant
RRVUN hydro power plantravi kant
 
Electric Traction
Electric Traction Electric Traction
Electric Traction ZunAib Ali
 
A Report on Industrial Visit
A Report on Industrial VisitA Report on Industrial Visit
A Report on Industrial VisitSymon Saroar
 
Modern electric trends in electric drives
Modern electric trends in electric drivesModern electric trends in electric drives
Modern electric trends in electric drivesSurinder Kumar
 
Electric traction in railways
Electric traction in railwaysElectric traction in railways
Electric traction in railwayssuresh shindhe
 
ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1
ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1
ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1Prashant kumar
 
NWR summer training ppt
NWR summer training pptNWR summer training ppt
NWR summer training pptKaushu Deshwal
 
Industrial visit Report
 Industrial visit Report Industrial visit Report
Industrial visit ReportANANDU KB
 
Full-scale converter for synchronous wind turbine generators
Full-scale converter for synchronous wind turbine generatorsFull-scale converter for synchronous wind turbine generators
Full-scale converter for synchronous wind turbine generatorsLong Thang Pham
 
Indian Railways Workshop Electrical PPT
Indian Railways Workshop Electrical PPTIndian Railways Workshop Electrical PPT
Indian Railways Workshop Electrical PPTNikunj Parashar
 
Electric Traction System
Electric  Traction  SystemElectric  Traction  System
Electric Traction Systemsahotaharman
 
Electric traction in railways
Electric traction in railwaysElectric traction in railways
Electric traction in railwayssuresh shindhe
 

What's hot (20)

Final
FinalFinal
Final
 
EE6801 - Electric Energy Generation Utilisation and Conservation
EE6801 - Electric Energy Generation Utilisation and ConservationEE6801 - Electric Energy Generation Utilisation and Conservation
EE6801 - Electric Energy Generation Utilisation and Conservation
 
Electricity generation, distribution and transmission
Electricity generation, distribution and transmissionElectricity generation, distribution and transmission
Electricity generation, distribution and transmission
 
RRVUN hydro power plant
RRVUN hydro power plantRRVUN hydro power plant
RRVUN hydro power plant
 
Electric Traction
Electric Traction Electric Traction
Electric Traction
 
TELK Industrial Visit Report
TELK Industrial Visit ReportTELK Industrial Visit Report
TELK Industrial Visit Report
 
A Report on Industrial Visit
A Report on Industrial VisitA Report on Industrial Visit
A Report on Industrial Visit
 
Modern electric trends in electric drives
Modern electric trends in electric drivesModern electric trends in electric drives
Modern electric trends in electric drives
 
Electric traction in railways
Electric traction in railwaysElectric traction in railways
Electric traction in railways
 
ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1
ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1
ABOUT NATIONAL THERMAL POWER PLANT COOPERATIO1
 
NWR summer training ppt
NWR summer training pptNWR summer training ppt
NWR summer training ppt
 
Industrial visit Report
 Industrial visit Report Industrial visit Report
Industrial visit Report
 
How is electricity_produced
How is electricity_producedHow is electricity_produced
How is electricity_produced
 
Full-scale converter for synchronous wind turbine generators
Full-scale converter for synchronous wind turbine generatorsFull-scale converter for synchronous wind turbine generators
Full-scale converter for synchronous wind turbine generators
 
Indian Railways Workshop Electrical PPT
Indian Railways Workshop Electrical PPTIndian Railways Workshop Electrical PPT
Indian Railways Workshop Electrical PPT
 
Electric Traction System
Electric  Traction  SystemElectric  Traction  System
Electric Traction System
 
My training ppt
My training pptMy training ppt
My training ppt
 
Ba4102382385
Ba4102382385Ba4102382385
Ba4102382385
 
Electric traction in railways
Electric traction in railwaysElectric traction in railways
Electric traction in railways
 
Electric locomotive
Electric locomotiveElectric locomotive
Electric locomotive
 

Similar to Uttaranchal jal vidyut nigam limited

Prospect of Small Hydro Power in Uttarakhand
Prospect of Small Hydro Power in UttarakhandProspect of Small Hydro Power in Uttarakhand
Prospect of Small Hydro Power in Uttarakhandijsrd.com
 
Electricity Generating Power Plants Of India By anuj.pptx
Electricity Generating Power Plants Of India By anuj.pptxElectricity Generating Power Plants Of India By anuj.pptx
Electricity Generating Power Plants Of India By anuj.pptxAnujThakur93
 
Power plant in bangladesh
Power plant in bangladeshPower plant in bangladesh
Power plant in bangladeshLitonMaruf
 
Bhakra dam - Geography project
Bhakra dam - Geography projectBhakra dam - Geography project
Bhakra dam - Geography projectNishanthini Kumar
 
National Hydro Power Plant collage PPT 1.pptx
National  Hydro Power Plant  collage PPT  1.pptxNational  Hydro Power Plant  collage PPT  1.pptx
National Hydro Power Plant collage PPT 1.pptxrupasharma39
 
Hydro Electric project
Hydro Electric projectHydro Electric project
Hydro Electric projectRanjeet Verma
 
Koyna Hydro-electric Project
Koyna Hydro-electric Project Koyna Hydro-electric Project
Koyna Hydro-electric Project Agrodwip Das
 
Hydropower field visi report, pokhara (Presentation slide)
Hydropower field visi report, pokhara (Presentation slide)Hydropower field visi report, pokhara (Presentation slide)
Hydropower field visi report, pokhara (Presentation slide)lochan Shrestha
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plantsnelkoli
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plantsnelkoli
 
harduaganj thermal power station h.t.p.s.
harduaganj thermal power station h.t.p.s.harduaganj thermal power station h.t.p.s.
harduaganj thermal power station h.t.p.s.vaibyfrndz
 
Art integrated project of sikkim about physics
Art integrated project of sikkim about physics Art integrated project of sikkim about physics
Art integrated project of sikkim about physics Aryankumar852031
 
Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV Girish Gupta
 

Similar to Uttaranchal jal vidyut nigam limited (20)

Prospect of Small Hydro Power in Uttarakhand
Prospect of Small Hydro Power in UttarakhandProspect of Small Hydro Power in Uttarakhand
Prospect of Small Hydro Power in Uttarakhand
 
Electricity Generating Power Plants Of India By anuj.pptx
Electricity Generating Power Plants Of India By anuj.pptxElectricity Generating Power Plants Of India By anuj.pptx
Electricity Generating Power Plants Of India By anuj.pptx
 
RPS.pptx
RPS.pptxRPS.pptx
RPS.pptx
 
Power plant in bangladesh
Power plant in bangladeshPower plant in bangladesh
Power plant in bangladesh
 
hydro power
hydro power hydro power
hydro power
 
Bhakra dam - Geography project
Bhakra dam - Geography projectBhakra dam - Geography project
Bhakra dam - Geography project
 
National Hydro Power Plant collage PPT 1.pptx
National  Hydro Power Plant  collage PPT  1.pptxNational  Hydro Power Plant  collage PPT  1.pptx
National Hydro Power Plant collage PPT 1.pptx
 
Hydro Electric project
Hydro Electric projectHydro Electric project
Hydro Electric project
 
Koyna Hydro-electric Project
Koyna Hydro-electric Project Koyna Hydro-electric Project
Koyna Hydro-electric Project
 
waris.pptx
waris.pptxwaris.pptx
waris.pptx
 
Hydropower field visi report, pokhara (Presentation slide)
Hydropower field visi report, pokhara (Presentation slide)Hydropower field visi report, pokhara (Presentation slide)
Hydropower field visi report, pokhara (Presentation slide)
 
Hydro power
Hydro powerHydro power
Hydro power
 
EIA_ppt.pptx
EIA_ppt.pptxEIA_ppt.pptx
EIA_ppt.pptx
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
 
Construction of PCC Parapet
Construction of PCC Parapet Construction of PCC Parapet
Construction of PCC Parapet
 
harduaganj thermal power station h.t.p.s.
harduaganj thermal power station h.t.p.s.harduaganj thermal power station h.t.p.s.
harduaganj thermal power station h.t.p.s.
 
Art integrated project of sikkim about physics
Art integrated project of sikkim about physics Art integrated project of sikkim about physics
Art integrated project of sikkim about physics
 
Chichoki power plant
Chichoki power plantChichoki power plant
Chichoki power plant
 
Electrical substations: 132 KV
Electrical substations: 132 KV Electrical substations: 132 KV
Electrical substations: 132 KV
 

More from IIT Roorkee

Advanced control techniques for the brushless permanent magnet ac motor by po...
Advanced control techniques for the brushless permanent magnet ac motor by po...Advanced control techniques for the brushless permanent magnet ac motor by po...
Advanced control techniques for the brushless permanent magnet ac motor by po...IIT Roorkee
 
artificail neural network application
artificail neural network applicationartificail neural network application
artificail neural network applicationIIT Roorkee
 
Salient features
Salient featuresSalient features
Salient featuresIIT Roorkee
 
Power factor improvement of an induction motor
Power factor improvement of an induction motorPower factor improvement of an induction motor
Power factor improvement of an induction motorIIT Roorkee
 

More from IIT Roorkee (7)

Advanced control techniques for the brushless permanent magnet ac motor by po...
Advanced control techniques for the brushless permanent magnet ac motor by po...Advanced control techniques for the brushless permanent magnet ac motor by po...
Advanced control techniques for the brushless permanent magnet ac motor by po...
 
Uttaranchal map
Uttaranchal mapUttaranchal map
Uttaranchal map
 
GAte 2012
GAte 2012GAte 2012
GAte 2012
 
artificail neural network application
artificail neural network applicationartificail neural network application
artificail neural network application
 
Salient features
Salient featuresSalient features
Salient features
 
Power factor improvement of an induction motor
Power factor improvement of an induction motorPower factor improvement of an induction motor
Power factor improvement of an induction motor
 
Harshit agarwal
Harshit agarwalHarshit agarwal
Harshit agarwal
 

Recently uploaded

CELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxCELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxJiesonDelaCerna
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersSabitha Banu
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...M56BOOKSTORE PRODUCT/SERVICE
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaVirag Sontakke
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitolTechU
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfUjwalaBharambe
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxEyham Joco
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxsocialsciencegdgrohi
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceSamikshaHamane
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 

Recently uploaded (20)

CELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptxCELL CYCLE Division Science 8 quarter IV.pptx
CELL CYCLE Division Science 8 quarter IV.pptx
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginners
 
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
KSHARA STURA .pptx---KSHARA KARMA THERAPY (CAUSTIC THERAPY)————IMP.OF KSHARA ...
 
Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of India
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptx
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdfFraming an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
Framing an Appropriate Research Question 6b9b26d93da94caf993c038d9efcdedb.pdf
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptx
 
ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)ESSENTIAL of (CS/IT/IS) class 06 (database)
ESSENTIAL of (CS/IT/IS) class 06 (database)
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptxHistory Class XII Ch. 3 Kinship, Caste and Class (1).pptx
History Class XII Ch. 3 Kinship, Caste and Class (1).pptx
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in Pharmacovigilance
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 

Uttaranchal jal vidyut nigam limited

  • 1. Uttaranchal Jal Vidyut Nigam Limited (UJVNL) with it's headquarter at Dehradun in the state of Uttaranchal (India) is operating, maintaining & constructing Hydro Power Plants. Dehradun is the capital of the state of Uttaranchal and is approximately 300 km far in northern direction from New Delhi closed to the Himalayan Mountains and well-connected through road, rail & air. The main concern in this project is the rehabilitation of the following 5 power stations below. Chibro with Ichari Dam Khodri Dhakrani Dhalipur Kulhal In this project was an assessment of the current physical condition of all of the 5 plants, which includes a survey of the project area and an inspection of all plant equipment, collection of data, records and statistics referring to the operation of the plants related to the I&C system. Furthermore, develop preliminary feasible options for modernization and upgrading and a state of the art control concept for all of the 6 power stations.
  • 2. TONS RIVER VALLEY POWER STATIONS Chibro & Khodri Power Stations utilize the water of river Tons. Tons river is an important tributary of the Yamuna River. This river joins Yamuna at Kalsi in the Northwestern part of Dehradun valley, which is approximately 50 km. away from Dehradun. A diversion dam across the river Tons has been constructed at Ichari with a 6.2 km long headrace tunnel from the diversion dam to Chibro under ground power station. Ichari is approximately 100 km from Dehradun in the hilly terrain. Tons river upstream from Ichari dam Ichari dam on Tons river Tons river downstream
  • 3. CHIBRO POWER STATION Chibro power station is an underground power station built on the left bank of river Tons nearly 25 km downstream of Ichari dam and 75 km from Dehradun and it surrounded by hills. The power station is located at 33° 33' 23" N & 077° 47'50" E. The power station was commissioned in 1975. The power station consists of four generating units each having a capacity of 60 MW. The total installed electrical capacity is 240 MW. The main power station equipments including turbine, generator and power transformer had been supplied by M/s Bharat Heavy Electrical Ltd. Bhopal. The turbines are Vertical shaft Francis turbines. Each unit has its own penstock with a butterfly valve. The power station is provided with a unit system of layout, where each generator is directly connected to a power transformer. For the outdoor switchyard, 220 kV oil filled cables coming from transformers situated in powerhouse. The Switchyard is connected through two 220 kV outgoing feeders to Khodri. 220 kV Switchyard Central Control Room Cavern with Control Room
  • 4. KHODRI POWER STATION The tail water collection gallery of Chibro power house supplies water to the power Tunnel of Khodri Power House by means of a siphon across river Tons. Khodri power station is a 4x30 MW surface power station built on right bank of river Yamuna and is nearly 50 km from Dehradun. The power station is located at 30° 30' 30" N & 077° 47'58" E closed to the barrage across river Yamuna at Dakpathar. The power station was commissioned in 1984. The headrace tunnel system consider a 7.5 m in diameter concrete lined circular tunnel with 4628 m length and three tunnels of smaller diameter in remaining length. The total length of the tunnel system is 5.6 km. The tailrace is a short open channel connecting to river Yamuna. The power station consists of four generating units each having a capacity of 30 MW. The total installed electrical capacity is 120 MW. The main power station equipments including turbine, generator and power transformer had been supplied by M/s Bharat Heavy Electrical Ltd. Bhopal. The turbines are Vertical shaft Francis turbines. 220 kV Switchyard Turbine Hall Central Control Room
  • 5. YAMUNA RIVER VALLEY River Yamuna originates from the Himalayas and is joined by its major tributary the Tons at Kalsi, approximately 50 Km from Dehradun. The Yamuna river collect the water from an elaborate web of water channels all across North India. These tributaries of Yamuna are the main source of water in Northern India. A barrage across river Yamuna at Dakpathar 3 Km downstream of Kalsi has been constructed. 14 Km power channel takes of at the Dakpathar barrage having its outfall into the river Asan, immediately upstream of the junction of Asan and Yamuna rivers. Dhakrani & Dhalipur are the two power stations along this power channel with a total installed capacity of 84.75 MW. Another power channel takes of at Asan barrage having its outfall into the river Yamuna near Paonta Sahib. Kulhal power station with a capacity of 3x10 MW is running along this power channel. Yamuna River Valley Downstream Dakpathar Barrage Yamuna River Valley Upstream
  • 6. DHAKRANI POWER STATION Dhakrani power station is a 3x11.25 MW surface power station located at a distance of approximately 40 km from Dehradun. It is built on the power channel emanating from Dakpathar Barrage & is approximately 7 Km from Dakpathar Barrage. The power station is located at 30° 27' 25" N & 077° 44'13" E. The commissioning for 2 units was in 1965 and the last unit was commissioned in 1970. Dhakrani is the first of two power stations (Dhalipur is following) running in cascade and using the same power channel down stream from Dakpathar. The power station consists of three generating units each having a capacity of 11.25 MW. The total installed electrical capacity is 33.75 MW. The main power station equipments including turbine and generator had been supplied by M/s Litostroj, Yugoslavia. The turbines are Vertical shaft Kaplan turbines. Water Intake Gates Turbine Hall Central Control Room
  • 7. DHALIPUR POWER STATION Dhalipur is a 3x17 MW surface power station built down stream of Dhakrani power station, which is 7 km from Dhakrani and about 12 km down stream of Dakpathar barrage. The power station is located at 30° 27' 22" N & 077° 44'1" E. This power station utilizes the discharge of Tons and Yamuna Rivers through a 12 km long channel. The commissioning for the three units started in 1965, 1966 and finnished in1970. The total installed electrical capacity is 51 MW. The designed head is 30.5 meter with a maximum discharge of 200 cubic meter. The main turbine equipment for the power station was supplied by M/s Litostroj, Yugoslavia and main electric equipment by M/s Rade Koncar, Yugoslavia through M/s Ingra Zegreb. The transformers were supplied by M/s Heavy Electrical (India) Ltd. Bhopal having 20 MVA capacity each. The turbines are Vertical shaft Francis turbines. Bypass Channel Turbine Hall Central Control Room
  • 8. KULHAL POWER STATION Kulhal is a 3x10 MW surface power station built down stream of Dhalipur power station and is 5 km from Asan Barrage. The power station is located at 30° 25' 42" N & 77° 37'49" E. It is situated on left bank of river Yamuna, opposite Paonta Saheb town of Himachal Pradesh and is about 4.5 Km downstream of Asan Barrage and about 50 Km from the nearest Railhead, Dehradun. This surface power station utilizes the discharge of Tons, Yamuna and Asan River through a 4.5 Km long power channel. The commissioning of the units was in 1975. The total installed electrical capacity is 30 MW with a head of 18 meters. M/s BHEL, Hardwar, supplied the main turbine & electrical equipments of this power station. The Power Transformers, each of 12.5 MVA capacity were supplied by M/s Transformers and Electricals Ltd., Kerala (India). The turbines are Vertical shaft Kaplan turbines. Bypass Channel Turbine Hall Central Control Room